You are on page 1of 5

中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.

96)工程比价评审会签单
ECRL Section 6 - Price Comparison Review and Countersign for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage
318+192.94 to Chainage 322+079.96

中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程报价单


询价内容 Quotation Analysis for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96,
Inquiry Work Scope Section 6

评审地点 六分部现场办公室 评审日期 20/9/2019


Evaluation Location Regional Site Office Review Date

报价 (RM)
Quotation (RM)
序号 工作内容 单位 工程量
No. Description Unit Qty. (A) (B) (C) (D)
HEBEI JIANKAN (MALAYSIA) JACK WORLD GEOTECHNICS SDN
中济建设私人有限公司 中祥建设有限公司 SDN BHD BHD
First Quotation
1 #REF! L/S 1.00 624,500.00 723,500.00 1,040,000.00 1,310,000.00

2 #REF! L/S 1.00 10,882,785.50 10,152,778.90 11,477,148.50 11,607,857.50

In Total RM 11,507,285.50 RM 10,876,278.90 RM 12,517,148.50 RM 12,917,857.50

Revised Quotation
(A) (B) (C) (D)
PEMBINAAN LINTAS PACIFIC HSL GROUND ENGINEERING HEBEI JIANKAN (MALAYSIA) 中祥建设有限公司 (ZHONGXIANG
SDN BHD SDN BHD SDN BHD CONSTRUCTION SDN.BHD)
1 #REF! L/S 1.00 727,235.00 500,000.00 455,000.00 841,900.00

2 #REF! L/S 1.00 8,557,348.00 11,241,151.00 11,435,120.00 12,919,901.00

In Total RM 9,284,583.00 RM 11,741,151.00 RM 11,890,120.00 RM 13,761,801.00

评审意见
Comment

Page 1 of 5
中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程比价评审会签单
ECRL Section 6 - Price Comparison Review and Countersign for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage
318+192.94 to Chainage 322+079.96

中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程报价单


询价内容 Quotation Analysis for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96,
Inquiry Work Scope Section 6

评审地点 六分部现场办公室 评审日期 20/9/2019


Evaluation Location Regional Site Office Review Date

报价 (RM)
Quotation (RM)
序号 工作内容 单位 工程量
No. Description Unit Qty. (A) (B) (C) (D)
HEBEI JIANKAN (MALAYSIA) JACK WORLD GEOTECHNICS SDN
中济建设私人有限公司 中祥建设有限公司 SDN BHD BHD
□综合部Administration Dept. □物资设备部Material & Equipment Dept. □工程管理部Engineering Dept. □技术质量部QA/QC Dept. □HSE部HSE Dept.
□商务合约部Contracts & Commercial Dept. □外联部LA&PR Dept. □财务部Finance Dept. □试验室Lab □工点Work Zone

部门会签
Dept. Opinion

商务合约部分管领导及国别合
规官会签
HOD of Contract & Commercial
Dept. and Compliance Officer‘s
Opinion

执行主管部门分管领导意见
HOD of Executive Dept.

Page 2 of 5
中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程比价评审会签单
ECRL Section 6 - Price Comparison Review and Countersign for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage
318+192.94 to Chainage 322+079.96

中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程报价单


询价内容 Quotation Analysis for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96,
Inquiry Work Scope Section 6

评审地点 六分部现场办公室 评审日期 20/9/2019


Evaluation Location Regional Site Office Review Date

报价 (RM)
Quotation (RM)
序号 工作内容 单位 工程量
No. Description Unit Qty. (A) (B) (C) (D)
HEBEI JIANKAN (MALAYSIA) JACK WORLD GEOTECHNICS SDN
中济建设私人有限公司 中祥建设有限公司 SDN BHD BHD
□刘涛 □张文锋 □刘勇 □刘林北 □赵小波
(请合同订立主管部门选定会签领导,并在□内打“√”)

其他部门分管领导意见
HOD of Other Dept.

分部项目经理/常务副总经理意

Section’s Project Manager
Opinion

Page 3 of 5
中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程价格分析表(第二版)
Revised Quotation Analysis for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96, Section 6

工作范围
Work Scope 东海岸铁路第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程报价分析单 (第二版)

Revised Quotation for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96 of ECRL Site Office Section 6 (First Revision)
A B C D E F G H I J A B C D E F G H I J
工程量 单位 最低价 中祥建设有限公司 中铁 (岩土) 工程有 中祥建设有限公司 中铁 (岩土) 工程有
Qty. Unit Lowest Rate JACK WORLD PECK CHEW HEBEI JIANKAN PEMBINAAN HSL GROUND ETONE 限公司 (CREC JACK WORLD PECK CHEW HEBEI JIANKAN PEMBINAAN HSL GROUND ETONE
GEOTECHNICAL (ZHONGXIANG (ZHONGXIANG
编号 工作内容 BIAXIS (M) SDN JF FOUNDATION BIAXIS (M) SDN JF FOUNDATION (M) 限公司 (CREC
GEOTECHNICS PILING (M) SDN (MALAYSIA) SDN LINTAS PACIFIC ENGINEERING SDN Geotechnical GEOTECHNICS SDN PILING (M) SDN (MALAYSIA) SDN LINTAS PACIFIC ENGINEERING SDN GEOTECHNICAL 备注
No. Description BHD (M) SDN BHD CONSTRUCTION BHD SDN BHD CONSTRUCTION Geotechnical
SDN BHD BHD BHD SDN BHD BHD (M) SDN BHD Engineering Sdn BHD BHD BHD SDN BHD BHD (M) SDN BHD Remarks
SDN.BHD) SDN.BHD) Engineering Sdn Bhd)
Bhd)
单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 总价 (RM) 总价 (RM)
Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Amount (RM) Amount (RM)

1.0 PRELIMINARIES
1.1 Allow for moving piling frame, plants, equipment and tools. 1.00 225,000.00 225,000.00 310,000.00 500,000.00 225,000.00 310,000.00 500,000.00
1.2 Statutory requirement fees 1.00 15,000.00 Inclu. 15,000.00 200,000.00 21,900.00 Inclu. 15,000.00 200,000.00 21,900.00
1.3 Provide all working and efficient Plant and Equipment Insurances 1.00 15,000.00 90,000.00 15,000.00 30,000.00 90,000.00 15,000.00 30,000.00
1.4 Insurance 1.00 198,000.00 198,000.00 198,000.00 -
1.5 Temporary power, water, corrective making good to Works, mechanical
1.00 40,000.00 Inclu. 70,000.00 100,000.00 40,000.00 Inclu. 70,000.00 100,000.00 40,000.00
repairs,and consumables
1.6 As Built Drawings, piling record , drilling and bored cast in place piles 1.00 30,000.00 50,000.00 30,000.00 500,000.00 30,000.00 50,000.00 30,000.00 500,000.00 30,000.00
installation signed records
Provide competent full time management, supervision and construction
1.7 1.00 50,000.00 225,000.00 240,000.00 800,000.00 50,000.00 225,000.00 240,000.00 800,000.00 50,000.00
management
1.8 Filling of Bentonite during boring 1.00 200,000.00 Inclu. Inclu. 200,000.00 Inclu. Inclu. 200,000.00
1.9 Mobilisation and Demobilisation. As a requirement provide sufficient Rigs to
compliance with Contract Program, all within this Subcontract value 1.00 Item 210,580.00 750,000.00 810,000.00 210,580.00 500,000.00 5,300,000.00 1,030,000.00 600,000.00 900,000.00 750,000.00 810,000.00 210,580.00 500,000.00 5,300,000.00 1,030,000.00 600,000.00 900,000.00
1.9.1 Mobilisation and Demobilisation.Price based on per Rigs basis 1.00 Rig 250,000.00 250,000.00 250,000.00
1.9.2 Mobilisation and Demobilisation. As a requirement provide sufficient Rigs to
compliance with Contract Program, all within this Subcontract value 2.00 台 150,000.00 150,000.00 300,000.00

Included, Only For Included, Only For


1.10 Allow for temporary Site Office and Off site Accommodation. 1.00 Item 10,000.00 10,000.00 180,000.00 24,500.00 100,000.00 244,860.00
Our Scope
50,000.00 10,000.00 50,000.00 100,000.00 10,000.00 180,000.00 24,500.00 100,000.00 244,860.00
Our Scope
50,000.00 10,000.00 50,000.00 100,000.00

1.11 Provide bench marks for the setting out of the works including the pile point
& provision of site survey
1.00 Item 5,000.00 50,000.00 72,000.00 73,500.00 5,000.00 52,890.00 Inclu. 120,000.00 55,000.00 30,000.00 80,000.00 50,000.00 72,000.00 73,500.00 5,000.00 52,890.00 Inclu. 120,000.00 55,000.00 30,000.00 80,000.00
1.12 Cost for incurred by complying with all safety, Health and Welfare regulations
1.00 Item 15,000.00 50,000.00 198,000.00 15,000.00 20,000.00 183,645.00 Inclu. 100,000.00 50,000.00 20,000.00 200,000.00 50,000.00 198,000.00 15,000.00 20,000.00 183,645.00 Inclu. 100,000.00 50,000.00 20,000.00 200,000.00
1.13 To privide the Performance Bond to the Main Contractor on thier Works 1.00 Item 30,000.00 55,000.00 N/A 30,000.00 35,260.00 Inclu. 40,000.00 inclu. 55,000.00 N/A 30,000.00 35,260.00 Inclu. 40,000.00 Inclu.
Any other items deem necessary for Works not specified above Included, Only For Included, Only For
1.14 1.00 Item 100,000.00 100,000.00 Our Scope 100,000.00 100,000.00 Our Scope 100,000.00

1.14.1 a) Plant & machinery Standy Cost 1.00 Rig/Day 7,500.00 7,500.00 Rate Only

2.0 PILING WORKS (1200MM DIAMETER BORED PILE)


2.1 Maintain the existing access that provided by Main Contractor
a) The pay length for boring of foundation bored pile shall be measured from
2.2 the proposed earthwork platform level to the toe of irrespective depth
b) The pay length for concrete of foundation bored pile shall be measured
2.3 the length between the toe and the cut off level
c) The measurement for boring through rock are measured nett and not as
2.4 extra over boring through soil or other type of material.
2.5 d) Compressive core strength > 30mpa defined as rock
2.6 Forming 1200mm diameter in soil and sand boring with piling equipment 7,036.00 m 250.00 250.00 360.00 280.00 250.00 349.00 280.00 435.00 350.00 256.00 280.00 1,759,000.00 2,532,960.00 1,970,080.00 1,759,000.00 2,455,564.00 1,970,080.00 3,060,660.00 2,462,600.00 1,801,216.00 1,970,080.00
2.7 Forming 1200mm diameter in rock boring with piling equipment 5,565.00 m 836.00 1,750.00 2,520.00 3,500.00 1,500.00 836.00 1,355.00 4,350.00 1,955.00 1,792.00 1,960.00 9,738,750.00 14,023,800.00 19,477,500.00 8,347,500.00 4,652,340.00 7,540,575.00 24,207,750.00 10,879,575.00 9,972,480.00 10,907,400.00
Installation of 1400mm permanent steel casing without removal upon
2.8 Unit Rate m 150.00 1,000.00 200.00 220.00 600.00 272.00 150.00 5,800.00 1,500.00 173.00 BY MC
completion
2.9 Supply and Install Sector tube to serve as access for Rock drilling. Unit Rate m 15.00 15.00 15.00 25.00 20.00 49.00 30.00 250.00 15.00 45.00 BY MC
Lifting steel cage at main contractor yard and deliver to site and placing to 841.00 ton 400.00 500.00 850.00 350.00 781.00 300.00 1,200.00 300.00 350.00 336,400.00 420,500.00 714,850.00 294,350.00 656,821.00 252,300.00 1,009,200.00 252,300.00 294,350.00
2.10 300.00
bored holes for the reinforcement cage in 1200mm diameter piles
*supply machinery and labour to unloading and placing, transportation by 841.00 ton 1,100.00 925,100.00
2.10.1 1,100.00
main contractor
2.11 Concrete cast insitu for 1200mm diameter bore piles (367 nos) 14,251.00 m3 43.00 77.50 99.00 95.00 70.00 43.00 96.00 138.00 55.00 90.00 1,104,452.50 1,410,849.00 1,353,845.00 997,570.00 612,793.00 1,368,096.00 - 1,966,638.00 783,805.00 1,282,590.00
2.11.1 * Supply machinery and labour to casting only 14,251.00 m3 150.00 150.00 2,137,650.00
2.12 Drilling waste shall dispose not execeeding (≤5Km) from the site Unit Rate Item 26.00 40.00 26.00 278,550.00 40.00 27.00 650,000.00 TBA 1,603,237.50 285,020.00 BY MC
2.13 Drilling waste shall dispose execeeding (>5Km) from the bridge site Unit Rate Item 27.00 55.00 27.00 413,846.00 50.00 40.00 700,000.00 TBA 2,137,650.00 427,530.00 BY MC
To provide and carry out 1200mm Sonic logging piles test including placing
2.14 Unit Rate m 10.00 10.00 3,600.00 25.00 20.00 37.00 50.00 15,000.00 16.00 5,000.00 150.00
the sonic tubes
2.15 To provide and carry out 1200mm pile Integrity test 367.00 No. 100.00 100.00 270.00 525.00 100.00 490.00 300.00 300.00 110.00 300.00 400.00 36,700.00 99,090.00 192,675.00 36,700.00 179,830.00 110,100.00 110,100.00 40,370.00 110,100.00 146,800.00

3.0 PILING WORKS (1000MM & 1500MM DIAMETER BORED PILE)


3.1 Maintain the existing access that provided by Main Contractor
a) The pay length for boring of foundation bored pile shall be measured from
3.2 the proposed earthwork platform level to the toe of irrespective depth
b) The pay length for concrete of foundation bored pile shall be measured
3.3 the length between the toe and the cut off level
c) The measurement for boring through rock are measured nett and not as
3.4 extra over boring through soil or other type of material.
3.5 d) Compressive core strength > 30mpa defined as rock
3.7 Forming 1000mm diameter in soil and sand boring with piling equipment Unit Rate m 210.00 220.00 270.00 250.00 210.00 307.00 275.00 365.00 280.00 220.00 250.00
3.8 Forming 1500mm diameter in soil and sand boring; ditto Unit Rate m 350.00 380.00 450.00 350.00 400.00 545.00 499.00 600.00 490.00 355.00 450.00
3.9 Forming 1000mm diameter in rock boring with piling equipment Unit Rate m 762.00 1,430.00 1,530.00 3,125.00 1,260.00 762.00 1,320.00 3,650.00 1,600.00 1,540.00 1,750.00
3.10 Forming 1500mm diameter in rock boring; ditto Unit Rate m 1,355.00 2,660.00 2,880.00 4,375.00 2,400.00 1,355.00 2,495.00 6,000.00 2,950.00 2,485.00 3,150.00
Installation of 1200mm permanent steel casing without removal upon
3.12 Unit Rate m 148.00 800.00 150.00 220.00 550.00 231.00 150.00 5,000.00 1,350.00 148.00 BY MC
completion
3.13 Installation of1700mm permanent steel casing; ditto Unit Rate m 150.00 1,300.00 400.00 300.00 1,000.00 339.00 150.00 7,800.00 1,650.00 210.00 BY MC
3.14 Supply and Install Dector tube to serve as acess for Rock drilling. Unit Rate m 15.00 15.00 15.00 25.00 20.00 49.00 30.00 250.00 15.00 45.00 BY MC
Lifting steel cage at main contractor yard and deliver to site and placing to
3.15 Unit Rate ton 300.00 400.00 500.00 850.00 350.00 781.00 300.00 1,200.00 300.00 350.00
bored holes for the reinforcement cage in 1000mm diameter piles
*supply machinery and labour for unloading and placing, transportation by
3.15.1 Unit Rate ton 1,100.00 1,100.00
main contractor
Lifting steel cage at main contractor yard and deliver to site and placing to
3.16 Unit Rate ton 300.00 400.00 500.00 850.00 350.00 781.00 300.00 1,200.00 300.00 350.00
bored holes for the reinforcement cage in 1500mm diameter piles
3.16.1 * supply machinery and labour for unloading and placing Unit Rate ton 1,100.00 1,100.00
3.17 Concrete cast insitu for 1000 mm diameter bore piles Unit Rate m3 43.00 77.50 99.00 95.00 70.00 43.00 96.00 150.00 138.00 55.00 90.00
3.18 Concrete cast insitu for 1500 mm diameter bore piles Unit Rate m3 43.00 77.50 99.00 95.00 70.00 43.00 96.00 150.00 138.00 55.00 90.00
3.19 Drilling waste shall dispose not execeeding (≤5Km) from the site Unit Rate Item 26.00 40.00 26.00 35.00 40.00 27.00 650,000.00 TBA 285,020.00 BY MC
3.20 Drilling waste shall dispose execeeding (>5Km) from the bridge site Unit Rate Item 27.00 55.00 27.00 52.00 50.00 40.00 700,000.00 TBA 427,530.00 BY MC
3.21 To provide and carry out 1200mm Sonic logging piles test including placing
Unit Rate No. 10.00 10.00 3,600.00 5,750.00 20.00 42.00 1,500.00 15,000.00 16.00 5,000.00 150.00
the sonic tubes
3.22 To provide and carry out 1500mm; ditto Unit Rate No. 10.00 10.00 3,600.00 8,625.00 100.00 42.00 2,000.00 20,000.00 16.00 6,500.00 150.00
3.23 To provide and carry out 1000mm pile Integrity test Unit Rate No. 10.00 10.00 270.00 518.00 20.00 490.00 300.00 300.00 110.00 300.00 400.00
3.24 To provide and carry out 1500mm; ditto Unit Rate No. 10.00 10.00 270.00 518.00 100.00 490.00 300.00 300.00 110.00 300.00 400.00

4.0 DAYWORK SCHEDULE


4.1 General labourer Unit Rate day 65.00 80.00 65.00 100.00 95.00 80.00 100.00 108.00 80.00 120.00
4.2 Semi skilled labourer Unit Rate day 85.00 85.00 120.00 110.00 120.00 90.00 135.00
4.3 Skilled labourer Unit Rate day 100.00 100.00 120.00 150.00 120.00 210.00 100.00 150.00
4.4 Concretor Unit Rate day 85.00 85.00 100.00 120.00 120.00 120.00 150.00
4.5 Barbender Unit Rate day 85.00 85.00 120.00 160.00 120.00 150.00
4.6 Drainlayer Unit Rate day 120.00 120.00 120.00 145.00 120.00
4.7 Carpenter Unit Rate day 85.00 85.00 120.00 170.00 150.00
4.8 Steelworker Unit Rate day 85.00 85.00 120.00 150.00 120.00 150.00
4.9 Welder Unit Rate day 115.00 120.00 150.00 120.00 115.00 200.00 200.00 150.00 165.00
4.10 Plasterer Unit Rate day 120.00 120.00 120.00 120.00 150.00
4.11 Tiler Unit Rate day 120.00 120.00 120.00 150.00
4.12 Glazier Unit Rate day 120.00 120.00 120.00 150.00
4.13 Plumber Unit Rate day 120.00 120.00 120.00 150.00
4.14 Roofer Unit Rate day 120.00 120.00 120.00 150.00
4.15 Painter Unit Rate day 120.00 120.00 120.00 150.00
4.16 Truck driver Unit Rate day 120.00 120.00 140.00 230.00 170.00
4.17 Crane driver Unit Rate day 150.00 150.00 250.00 150.00 500.00 290.00 200.00 250.00
中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程价格分析表(第二版)
Revised Quotation Analysis for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96, Section 6

工作范围
Work Scope 东海岸铁路第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程报价分析单 (第二版)

Revised Quotation for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96 of ECRL Site Office Section 6 (First Revision)
A B C D E F G H I J A B C D E F G H I J
工程量 单位 最低价 中祥建设有限公司 中铁 (岩土) 工程有 中祥建设有限公司 中铁 (岩土) 工程有
Qty. Unit Lowest Rate JACK WORLD PECK CHEW HEBEI JIANKAN PEMBINAAN HSL GROUND ETONE 限公司 (CREC JACK WORLD PECK CHEW HEBEI JIANKAN PEMBINAAN HSL GROUND ETONE
GEOTECHNICAL (ZHONGXIANG (ZHONGXIANG
编号 工作内容 BIAXIS (M) SDN JF FOUNDATION BIAXIS (M) SDN JF FOUNDATION (M) 限公司 (CREC
GEOTECHNICS PILING (M) SDN (MALAYSIA) SDN LINTAS PACIFIC ENGINEERING SDN Geotechnical GEOTECHNICS SDN PILING (M) SDN (MALAYSIA) SDN LINTAS PACIFIC ENGINEERING SDN GEOTECHNICAL 备注
No. Description BHD (M) SDN BHD CONSTRUCTION BHD SDN BHD CONSTRUCTION Geotechnical
SDN BHD BHD BHD SDN BHD BHD (M) SDN BHD Engineering Sdn BHD BHD BHD SDN BHD BHD (M) SDN BHD Remarks
SDN.BHD) SDN.BHD) Engineering Sdn Bhd)
Bhd)
单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 总价 (RM) 总价 (RM)
Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Amount (RM) Amount (RM)
4.18 Piling equipment operator Unit Rate day 150.00 200.00 350.00 150.00 287.00 500.00 420.00 250.00 500.00
4.19 Pneumatic tool operator Unit Rate day 120.00 120.00 140.00 200.00
4.20 Compressor - Portable (including tools and hose) Unit Rate day 100.00 180.00 150.00 100.00 500.00 200.00
4.21 Mobile crane - 25 tons Unit Rate day 750.00 750.00 1,000.00 1,500.00 880.00 1,200.00 1,500.00
4.22 Generator - 300 KVA Unit Rate day 120.00 120.00 550.00 450.00 250.00
4.23 Excavator - 200 Unit Rate day 400.00 485.00 580.00 800.00 800.00 400.00 1,000.00 580.00 1,000.00 400.00
4.24 Excavator - 300 Unit Rate day 500.00 680.00 1,200.00 2,000.00 1,500.00 500.00
4.25 Roller - 6 tons Unit Rate day 500.00 800.00 500.00 600.00 850.00
4.26 Roller - 10 tons Unit Rate day 700.00 1,500.00 700.00 800.00 1,000.00
4.27 Lorries - 6 wheels (licence) Unit Rate day 450.00 650.00 800.00 450.00
4.28 Lorries - 10 wheels (licence) Unit Rate day 650.00 850.00 1,000.00 650.00 1,200.00
4.29 Lorries - 10 wheels (non licence) Unit Rate day 650.00 650.00 900.00 850.00
4.30 Concrete mixer Unit Rate day 60.00 60.00 200.00 250.00
4.31 Backhoe Unit Rate day 500.00 520.00 1,000.00 1,000.00 500.00 800.00
4.32 Back pusher Unit Rate day 450.00 450.00 1,000.00 500.00
4.33 Flat compactor - 90kg Unit Rate day 80.00 80.00 500.00 300.00
4.34 Water pump - 75hp Unit Rate day 50.00 80.00 50.00 500.00
4.35 Welding and cutting set - 375 amp Unit Rate day 50.00 70.00 50.00 500.00
4.36 Vibrator poke - 25mm Unit Rate day 30.00 30.00 50.00 450.00
4.37 Air Breaker Unit Rate day 50.00 80.00 50.00 300.00
4.38 Hydraulic Breaker - 300hp Unit Rate day 80.00 80.00 80.00 2,000.00

合计 Total RM 972,257.50 RM 2,125,303.00 RM 1,784,819.00 RM 317,030.00 RM 749,451.00 RM 3,213,354.00 RM 8,035,950.00 RM 5,006,217.50 RM 2,308,774.00 RM 1,299,430.00 RM 13,935,302.50 RM 20,590,199.00 RM 24,751,950.00 RM 11,890,120.00 RM 9,284,583.00 RM 11,741,151.00 RM 38,381,260.00 RM 17,603,383.00 RM 13,761,801.00 RM 15,881,220.00