96)工程比价评审会签单
ECRL Section 6 - Price Comparison Review and Countersign for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage
318+192.94 to Chainage 322+079.96
报价 (RM)
Quotation (RM)
序号 工作内容 单位 工程量
No. Description Unit Qty. (A) (B) (C) (D)
HEBEI JIANKAN (MALAYSIA) JACK WORLD GEOTECHNICS SDN
中济建设私人有限公司 中祥建设有限公司 SDN BHD BHD
First Quotation
1 #REF! L/S 1.00 624,500.00 723,500.00 1,040,000.00 1,310,000.00
Revised Quotation
(A) (B) (C) (D)
PEMBINAAN LINTAS PACIFIC HSL GROUND ENGINEERING HEBEI JIANKAN (MALAYSIA) 中祥建设有限公司 (ZHONGXIANG
SDN BHD SDN BHD SDN BHD CONSTRUCTION SDN.BHD)
1 #REF! L/S 1.00 727,235.00 500,000.00 455,000.00 841,900.00
评审意见
Comment
Page 1 of 5
中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程比价评审会签单
ECRL Section 6 - Price Comparison Review and Countersign for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage
318+192.94 to Chainage 322+079.96
报价 (RM)
Quotation (RM)
序号 工作内容 单位 工程量
No. Description Unit Qty. (A) (B) (C) (D)
HEBEI JIANKAN (MALAYSIA) JACK WORLD GEOTECHNICS SDN
中济建设私人有限公司 中祥建设有限公司 SDN BHD BHD
□综合部Administration Dept. □物资设备部Material & Equipment Dept. □工程管理部Engineering Dept. □技术质量部QA/QC Dept. □HSE部HSE Dept.
□商务合约部Contracts & Commercial Dept. □外联部LA&PR Dept. □财务部Finance Dept. □试验室Lab □工点Work Zone
部门会签
Dept. Opinion
商务合约部分管领导及国别合
规官会签
HOD of Contract & Commercial
Dept. and Compliance Officer‘s
Opinion
执行主管部门分管领导意见
HOD of Executive Dept.
Page 2 of 5
中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程比价评审会签单
ECRL Section 6 - Price Comparison Review and Countersign for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage
318+192.94 to Chainage 322+079.96
报价 (RM)
Quotation (RM)
序号 工作内容 单位 工程量
No. Description Unit Qty. (A) (B) (C) (D)
HEBEI JIANKAN (MALAYSIA) JACK WORLD GEOTECHNICS SDN
中济建设私人有限公司 中祥建设有限公司 SDN BHD BHD
□刘涛 □张文锋 □刘勇 □刘林北 □赵小波
(请合同订立主管部门选定会签领导,并在□内打“√”)
其他部门分管领导意见
HOD of Other Dept.
分部项目经理/常务副总经理意
见
Section’s Project Manager
Opinion
Page 3 of 5
中交马来西亚东海岸铁路项目总经理部第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程价格分析表(第二版)
Revised Quotation Analysis for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96, Section 6
工作范围
Work Scope 东海岸铁路第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程报价分析单 (第二版)
Revised Quotation for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96 of ECRL Site Office Section 6 (First Revision)
A B C D E F G H I J A B C D E F G H I J
工程量 单位 最低价 中祥建设有限公司 中铁 (岩土) 工程有 中祥建设有限公司 中铁 (岩土) 工程有
Qty. Unit Lowest Rate JACK WORLD PECK CHEW HEBEI JIANKAN PEMBINAAN HSL GROUND ETONE 限公司 (CREC JACK WORLD PECK CHEW HEBEI JIANKAN PEMBINAAN HSL GROUND ETONE
GEOTECHNICAL (ZHONGXIANG (ZHONGXIANG
编号 工作内容 BIAXIS (M) SDN JF FOUNDATION BIAXIS (M) SDN JF FOUNDATION (M) 限公司 (CREC
GEOTECHNICS PILING (M) SDN (MALAYSIA) SDN LINTAS PACIFIC ENGINEERING SDN Geotechnical GEOTECHNICS SDN PILING (M) SDN (MALAYSIA) SDN LINTAS PACIFIC ENGINEERING SDN GEOTECHNICAL 备注
No. Description BHD (M) SDN BHD CONSTRUCTION BHD SDN BHD CONSTRUCTION Geotechnical
SDN BHD BHD BHD SDN BHD BHD (M) SDN BHD Engineering Sdn BHD BHD BHD SDN BHD BHD (M) SDN BHD Remarks
SDN.BHD) SDN.BHD) Engineering Sdn Bhd)
Bhd)
单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 总价 (RM) 总价 (RM)
Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Amount (RM) Amount (RM)
1.0 PRELIMINARIES
1.1 Allow for moving piling frame, plants, equipment and tools. 1.00 225,000.00 225,000.00 310,000.00 500,000.00 225,000.00 310,000.00 500,000.00
1.2 Statutory requirement fees 1.00 15,000.00 Inclu. 15,000.00 200,000.00 21,900.00 Inclu. 15,000.00 200,000.00 21,900.00
1.3 Provide all working and efficient Plant and Equipment Insurances 1.00 15,000.00 90,000.00 15,000.00 30,000.00 90,000.00 15,000.00 30,000.00
1.4 Insurance 1.00 198,000.00 198,000.00 198,000.00 -
1.5 Temporary power, water, corrective making good to Works, mechanical
1.00 40,000.00 Inclu. 70,000.00 100,000.00 40,000.00 Inclu. 70,000.00 100,000.00 40,000.00
repairs,and consumables
1.6 As Built Drawings, piling record , drilling and bored cast in place piles 1.00 30,000.00 50,000.00 30,000.00 500,000.00 30,000.00 50,000.00 30,000.00 500,000.00 30,000.00
installation signed records
Provide competent full time management, supervision and construction
1.7 1.00 50,000.00 225,000.00 240,000.00 800,000.00 50,000.00 225,000.00 240,000.00 800,000.00 50,000.00
management
1.8 Filling of Bentonite during boring 1.00 200,000.00 Inclu. Inclu. 200,000.00 Inclu. Inclu. 200,000.00
1.9 Mobilisation and Demobilisation. As a requirement provide sufficient Rigs to
compliance with Contract Program, all within this Subcontract value 1.00 Item 210,580.00 750,000.00 810,000.00 210,580.00 500,000.00 5,300,000.00 1,030,000.00 600,000.00 900,000.00 750,000.00 810,000.00 210,580.00 500,000.00 5,300,000.00 1,030,000.00 600,000.00 900,000.00
1.9.1 Mobilisation and Demobilisation.Price based on per Rigs basis 1.00 Rig 250,000.00 250,000.00 250,000.00
1.9.2 Mobilisation and Demobilisation. As a requirement provide sufficient Rigs to
compliance with Contract Program, all within this Subcontract value 2.00 台 150,000.00 150,000.00 300,000.00
1.11 Provide bench marks for the setting out of the works including the pile point
& provision of site survey
1.00 Item 5,000.00 50,000.00 72,000.00 73,500.00 5,000.00 52,890.00 Inclu. 120,000.00 55,000.00 30,000.00 80,000.00 50,000.00 72,000.00 73,500.00 5,000.00 52,890.00 Inclu. 120,000.00 55,000.00 30,000.00 80,000.00
1.12 Cost for incurred by complying with all safety, Health and Welfare regulations
1.00 Item 15,000.00 50,000.00 198,000.00 15,000.00 20,000.00 183,645.00 Inclu. 100,000.00 50,000.00 20,000.00 200,000.00 50,000.00 198,000.00 15,000.00 20,000.00 183,645.00 Inclu. 100,000.00 50,000.00 20,000.00 200,000.00
1.13 To privide the Performance Bond to the Main Contractor on thier Works 1.00 Item 30,000.00 55,000.00 N/A 30,000.00 35,260.00 Inclu. 40,000.00 inclu. 55,000.00 N/A 30,000.00 35,260.00 Inclu. 40,000.00 Inclu.
Any other items deem necessary for Works not specified above Included, Only For Included, Only For
1.14 1.00 Item 100,000.00 100,000.00 Our Scope 100,000.00 100,000.00 Our Scope 100,000.00
1.14.1 a) Plant & machinery Standy Cost 1.00 Rig/Day 7,500.00 7,500.00 Rate Only
工作范围
Work Scope 东海岸铁路第六分部关丹河特大桥桩基招标(CH 318+192.94至CH 322+079.96)工程报价分析单 (第二版)
Revised Quotation for Construction and Completion of Bored Piling Works to Sg. Kuantan Super Major Bridge from Chainage 318+192.94 to Chainage 322+079.96 of ECRL Site Office Section 6 (First Revision)
A B C D E F G H I J A B C D E F G H I J
工程量 单位 最低价 中祥建设有限公司 中铁 (岩土) 工程有 中祥建设有限公司 中铁 (岩土) 工程有
Qty. Unit Lowest Rate JACK WORLD PECK CHEW HEBEI JIANKAN PEMBINAAN HSL GROUND ETONE 限公司 (CREC JACK WORLD PECK CHEW HEBEI JIANKAN PEMBINAAN HSL GROUND ETONE
GEOTECHNICAL (ZHONGXIANG (ZHONGXIANG
编号 工作内容 BIAXIS (M) SDN JF FOUNDATION BIAXIS (M) SDN JF FOUNDATION (M) 限公司 (CREC
GEOTECHNICS PILING (M) SDN (MALAYSIA) SDN LINTAS PACIFIC ENGINEERING SDN Geotechnical GEOTECHNICS SDN PILING (M) SDN (MALAYSIA) SDN LINTAS PACIFIC ENGINEERING SDN GEOTECHNICAL 备注
No. Description BHD (M) SDN BHD CONSTRUCTION BHD SDN BHD CONSTRUCTION Geotechnical
SDN BHD BHD BHD SDN BHD BHD (M) SDN BHD Engineering Sdn BHD BHD BHD SDN BHD BHD (M) SDN BHD Remarks
SDN.BHD) SDN.BHD) Engineering Sdn Bhd)
Bhd)
单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 单价 (RM) 总价 (RM) 总价 (RM)
Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Rate (RM) Amount (RM) Amount (RM)
4.18 Piling equipment operator Unit Rate day 150.00 200.00 350.00 150.00 287.00 500.00 420.00 250.00 500.00
4.19 Pneumatic tool operator Unit Rate day 120.00 120.00 140.00 200.00
4.20 Compressor - Portable (including tools and hose) Unit Rate day 100.00 180.00 150.00 100.00 500.00 200.00
4.21 Mobile crane - 25 tons Unit Rate day 750.00 750.00 1,000.00 1,500.00 880.00 1,200.00 1,500.00
4.22 Generator - 300 KVA Unit Rate day 120.00 120.00 550.00 450.00 250.00
4.23 Excavator - 200 Unit Rate day 400.00 485.00 580.00 800.00 800.00 400.00 1,000.00 580.00 1,000.00 400.00
4.24 Excavator - 300 Unit Rate day 500.00 680.00 1,200.00 2,000.00 1,500.00 500.00
4.25 Roller - 6 tons Unit Rate day 500.00 800.00 500.00 600.00 850.00
4.26 Roller - 10 tons Unit Rate day 700.00 1,500.00 700.00 800.00 1,000.00
4.27 Lorries - 6 wheels (licence) Unit Rate day 450.00 650.00 800.00 450.00
4.28 Lorries - 10 wheels (licence) Unit Rate day 650.00 850.00 1,000.00 650.00 1,200.00
4.29 Lorries - 10 wheels (non licence) Unit Rate day 650.00 650.00 900.00 850.00
4.30 Concrete mixer Unit Rate day 60.00 60.00 200.00 250.00
4.31 Backhoe Unit Rate day 500.00 520.00 1,000.00 1,000.00 500.00 800.00
4.32 Back pusher Unit Rate day 450.00 450.00 1,000.00 500.00
4.33 Flat compactor - 90kg Unit Rate day 80.00 80.00 500.00 300.00
4.34 Water pump - 75hp Unit Rate day 50.00 80.00 50.00 500.00
4.35 Welding and cutting set - 375 amp Unit Rate day 50.00 70.00 50.00 500.00
4.36 Vibrator poke - 25mm Unit Rate day 30.00 30.00 50.00 450.00
4.37 Air Breaker Unit Rate day 50.00 80.00 50.00 300.00
4.38 Hydraulic Breaker - 300hp Unit Rate day 80.00 80.00 80.00 2,000.00
合计 Total RM 972,257.50 RM 2,125,303.00 RM 1,784,819.00 RM 317,030.00 RM 749,451.00 RM 3,213,354.00 RM 8,035,950.00 RM 5,006,217.50 RM 2,308,774.00 RM 1,299,430.00 RM 13,935,302.50 RM 20,590,199.00 RM 24,751,950.00 RM 11,890,120.00 RM 9,284,583.00 RM 11,741,151.00 RM 38,381,260.00 RM 17,603,383.00 RM 13,761,801.00 RM 15,881,220.00
Prepared by: