ID Task Task Name Duration Start Finish Predecessors

Resource % 29 Feb '16 07 Mar '16 14 Mar '16 21 Mar '16 28 Mar '16 04 Apr '16 11 Apr '16
Mode Names Complete T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 Fabrication Phase 26 days Fri 11/03/16 Fri 15/04/16 31%
2 Fabrication Starts 1 day Fri 11/03/16 Fri 11/03/16 0%
3 Maufacture 1 day Thu Thu J,L,C 100% Maufacture Aerofoil Jig
Aerofoil Jig 17/03/16 17/03/16
4 Cut all Chassis 3 days Tue Thu S,M,R,E 75% S,M,R,E
Components to 22/03/16 24/03/16
Length
5 Manufacture 3 days Tue Thu 3 J,L,C 90% J,L,C
Aerofoil Ribs 22/03/16 24/03/16
6 Form all Chassis 3 days Fri 18/03/16 Tue 4 S,M,R,E 30% S,M,R,E
Components 29/03/16
7 Construct Each Sail 4 days Thu Wed 5 J,L,C 23% Construct Each Sail Half
Half 24/03/16 30/03/16
8 Front Fork and 3 days Tue Fri 01/04/16 6 S,M,R,E 0% Front Fork and Steering Fabrication
Steering 29/03/16
Fabrication
9 Additional Sail 3 days Wed Mon 7 J,L,C 0% Additional Sail Fabrication
Fabrication 30/03/16 04/04/16
10 Additional Chassis 1 day Fri 01/04/16 Mon 8 S,M,R,E 0% Additional Chassis Fabrication
Fabrication 04/04/16

11 Assembly 2 days Mon 04/04/16Wed 06/04/169,10 J,L,C,S,M,R,E 0% Assembly


12 Display, Test, Race 1 day Fri 15/04/16 Fri 15/04/16 11 J,L,C,S,M,R,E 0% Display, Te

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: Fabrication Plan (Roug
Milestone Inactive Summary Start-only Critical
Date: Thu 24/03/16
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Late