Professional Documents
Culture Documents
GT2008
June 9-13, 2008, Berlin, Germany
GT2008-50159
Secondly, the validation of the LM2500+G4 gas generator - Inlet Air mass flow measurement
coupled with the HSPT in GE Oil&Gas Massa facilities. - Inlet and exhaust pressure drop measurement
A wide range of operating situations were set up for this - Possibility to run the GT at baseload conditions for the
campaign to cover conditions for both mechanical drive and whole HSPT speed operating range (50% - 105% HSPT
generator drive applications. The test matrix included a step-by- speed)
step approach from pre-start phase to mechanical off-design
tests, to minimize machine impact risks and satisfy validation An existing “production” test bed, normally used to test at
- Aeromechanics
- Thermo-mechanical assessment
- GT Performances (base load and off design)
- Operability and control
- Noise and Emissions characterization
- Auxiliary systems (gas skid, lube oil system)
30.000
v/f=const
Gen max output with gear #2 and
To fully understand HSPT behavior, the FETT was
v/f=const
Maximum power turbine output
instrumented with:
25.000
Gen max output with gear #1 and
− Total Static Channels: 880
20.000 v/f=opt
Gen max output with gear #2 and
− Total Dynamic Channels: 57
v/f=opt
15.000
40.0 50.0 60.0 70.0 80.0
Power turbine speed %
90.0 100.0 110.0
In order to evaluate the engine performance, the shaft
power output and the gas fuel flow, which are critical for the
Figure 5. Two-gear set Configuration performance validation of the engine, were measured carefully,
to reach the highest possible accuracy.
2) The possibility to install a new single gear-set torque- The shaft power output was provided by:
overrated to cover the whole operating range with no speed − A torque-meter, for a direct reading
mapping interruption due to torque limitation, together with − A wattmeter for the electric generator power output which,
providing additional air cooling to the generator to allow its taking into account gear and generator losses, gives an
operation at low operating speeds. indirect double check (engine heat balance).
This last arrangement was finally selected, with the Two calibrated orifices were installed in series on the fuel
installation of a modified generator cooler and two additional 4” feed line in order to measure fuel gas flow.
fans and the connection of the generator to load resistors.
Performance
PGT25+G4 Expected Quoting
The test bed flexible configuration (electric generator PGT25+G4 FETT Results
-10 0 10 20 30 40
Ambient Temperature, °C
1 2 3 4 5
Figure 10 shows the shaft output power measured on the Figure 12. Power Turbine efficiency at different expansion
prototype at FSFL, compared to the PGT25+G4 expected ratios and 100% of corrected speed
quoting performance and to the PGT25+ present quoting
performance. Fig. 12 is a sample of the results for this effort, showing
The output power values have been corrected to sea level the isentropic efficiency of the power turbine versus the
ambient pressure (101.3 kPa) and to zero inlet and exhaust expansion ratio at 100% of corrected speed. The scattered
pressure losses, for homogeneity of comparison. The FETT points represent the measured data, while the solid line is the
demonstrated to meet the minimum target power with adequate expected efficiency curve. As it can be observed, at high loads
margins, providing about 35 MW at ISO ambient temperature (high expansion ratio) the expected and the actual efficiencies
(15°C). are very close, while at part load conditions the map is less
Similarly, Figure 11 represents the measured engine heat accurate. Using such information it has been possible to obtain
rate: also in this case the target performance is met with a power turbine map matching the data, which has been
adequate margins. implemented in the aero-thermal cycle model for reliable
predictions of the gas turbine performance at off design
conditions.
Overfrequency,%
sudden load steps and full load rejections needed to be 18 6.75
Load MW
investigated comprehensively. 16 6
PT Speed %
Power %
24 6
106% 60%
22 5.5
104% 40%
Unde rfre quenc y,%
20 5
18 4.5
Loa d MW
102% 20%
16 4
14 3.5 100% 0%
12 3
98% -20%
10 2.5 0 10 20 30 40 50
8 2
Time (sec)
6 1.5
4 1
2 0.5 Figure 15. Dynamic response of the PT speed after full load
0
0 2 4 6 8 10 12 14 16 18 20 22 24
0
26 rejection
Tes t Run #
Thermo-mechanical Assessment – Casings
Figure 13. Load acceptance Runs
In order to optimize HSPT casings cooling flows and
Figures 13 and 14 summarize the results of these tests. improve overall engine efficiency without affecting parts
These figures contain a lot of information that need a detailed oxidation and durability, a Design of Experiments (DOE) was
description for a better understanding: conducted (Fig. 16) by using different orifices on cooling pipes
- The yellow bars represent the start and the end power to define a correlation (transfer function) among cooling flows,
in MW (obviously the starting power is the lowest in cavities air temperature, casings metal temperature and ambient
the acceptance step, and vice versa in the other case); conditions. After the test, collected data were used to tune both
- The blue points represent the total power variation in secondary flows and FEM models by matching all temperatures
MW during each step (which is the absolute difference and pressures; in this way models predictability was maximized
between the initial power and the landing power); and parts life requirements in terms of creep, fatigue and
- The red points represent the corresponding maximum oxidation successfully verified.
frequency variation expressed in % (which can be read
on the right axes of the plot).
Figure 15 shows the dynamic response of the PT speed
after the full load rejection. The peak speed (111%) is well
within the maximum over-speed limit of the power turbine,
which is 115%; after about 11 seconds the frequency is again
below 105% of the nominal value.
Aeromechanics 7,000
5 min
7500 RPM GG idle
5 min
6,000
2,000 2 min
On the basis of the MCA results, airfoils to be 1,000
motoring
@2400
instrumented and exact strain gages’ locations on each airfoil 0
0
blade variability were conducted. Figure 19. Power Generation Endurance Cycle
During FETT test, the whole operating speed range has
been investigated for mechanical drive and generator drive
applications. FETT TEARDOWN
More than 100 PT speed sweeps were executed at various
loads covering all operating and off-design conditions. The FETT teardown included the borescope inspection of
the gas turbine and the visual inspection of all the HSPT
-10 0 10 20 30 40
Am bient Tem perature, °C
PGT25+ Quoting
Alliance Unit
REFERENCES
CONCLUSIONS