Professional Documents
Culture Documents
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including Conditions of Contract and
Division 1 Specification Sections, apply to this Section.
0.2 SUMMARY
0.3 SUBMITTALS
A. Product Data: Include refrigerant; rated capacities; shipping, installed, and operating
weights; noise criteria; furnished specialties; and accessories for each model indicated. Data
shall also include performance data showing the energy input versus cooling load output
from 100% to 20% of full load with constant entering condenser water temperature.
B. Material, Equipment, and Fixture Lists shall be submitted for centrifugal chiller systems in
accordance with paragraph entitled, "General Requirements," of this section.
C. Product Data: Equipment Foundation Data shall be submitted for the following items in
accordance with paragraph entitled, "General Requirements," of this section.
1. Evaporator.
2. Compressor.
3. Condenser.
4. Purge System.
5. Motors.
6. Control Panel.
7. Equipment and Performance Data shall be submitted for centrifugal water chillers in
accordance with paragraph entitled, "General Requirements," of this section.
1. Evaporator.
2. Compressor.
3. Condenser.
4. Cooler.
5. Purge System.
6. Motors.
7. Control and Control Panels.
8. Insulation.
9. Vibration Isolation.
10. Accessories.
11. Special Tools.
12. Spare Parts.
E. Samples: Manufacturer's Standard Color Chart shall be submitted in accordance with Article
entitled, "General Requirements," of this section.
G. Shop Drawings: Signed and sealed by a qualified professional engineer. Drawings shall
indicate the physical layout of all controls, and internal tubing and wiring details
H. Connection diagrams shall be submitted indicating the relations and connections of the
following items.
1. Evaporator.
2. Compressor.
3. Condenser.
4. Cooler.
5. Purge System.
6. Motors.
7. Control and Control Panels.
8. Control Diagrams shall be submitted for centrifugal chiller units in accordance with
paragraph entitled, "General Requirements," of this section.
9. Installation drawings shall be submitted for centrifugal chiller systems in accordance
with the paragraph entitled, "Installation," of this section. Drawings shall indicate
overall physical features, dimensions, ratings, service requirements, and equipment
weights.
10. Wiring Diagrams: Detail wiring for power, signal, and control systems and
differentiate between manufacturer-installed and field-installed wiring.
11. Alarm Systems.
I. Design Calculations: Calculate requirements for selecting vibration isolators and seismic
restraints and for designing vibration isolation bases. Design Analysis and Calculations
shall be submitted in accordance with paragraph entitled, "General Requirements," of this
section.
J. Vibration Isolation Base Details: Detail fabrication, including anchorages and attachments
to structure and to supported equipment. Include auxiliary motor slides and rails, and base
weights.
K. Coordination Drawings: Floor plans drawn to scale and coordinating the following:
1. Structural supports.
2. Piping roughing-in requirements.
CENTRIFUGAL WATER CHILLERS 15625 - Page 2/18
STD-SPC-DCA(A3)-ME-DCA REV A
<Project Title>
L. As-Built Drawings shall be submitted for centrifugal chiller units in accordance with Article
entitled, "General Requirements," of this section.
M. Product Certificates: Certification of performance according to ARI 550 and that chillers
have been started and function properly.
N. Certificates: Listing of Product Installation shall be submitted for centrifugal chiller units in
accordance with Article entitled, "Installation," of this section. Certificates shall be
submitted for following items showing conformance with the referenced standards
contained in this section:
1. Evaporator.
2. Compressor.
3. Condenser.
4. Cooler.
5. Purge System.
6. Motors.
7. Control and Control Panels.
8. Insulation.
9. Vibration Isolation.
10. Special Tools.
11. Spare Parts.
P. Operation and Maintenance Data: Operation and Maintenance Manuals shall be submitted
in accordance with paragraph entitled, "Manufacturer's Representative," of this section.
A. Control Diagrams shall be submitted for centrifugal chiller units showing the physical and
functional relationship of equipment. Electrical diagrams shall show the size, type, and
capacity of the system.
B. Material, Equipment, and Fixture Lists shall be submitted for centrifugal chiller systems
including manufacturer's style or catalog numbers, specification and drawing reference
numbers, warranty information, and fabrication site information.
C. Equipment Foundation Data shall be submitted including equipment weight and operating
loads, location and projection of anchor bolts, and horizontal and vertical clearances for
installation, operation, and maintenance. Data shall also include dimensions of foundations
and relative elevations, and installation requirements such as noise abatement, vibration
isolation, and utility services.
D. Manufacturer's Standard Color Chart shall indicate the manufacturer's standard color
selections and finishes for chiller units.
CENTRIFUGAL WATER CHILLERS 15625 - Page 3/18
STD-SPC-DCA(A3)-ME-DCA REV A
<Project Title>
E. Design Analysis and Calculations shall be submitted for centrifugal chillers indicating the
manufacturer's recommended power ratings, rotational speeds, and piston speeds.
F. Test Reports: Factory Tests: Reports shall certify the compliance with performance
requirements and follow the format of the required testing standard for both the Chiller
Performance Tests and the Chiller Sound Tests. Test report shall include certified
calibration report of all test instrumentation. Calibration report shall include certification
that all test instrumentation has been calibrated within 6 months prior to the test date,
identification of all instrumentation, and certification that all instrumentation complies with
requirements of the test standard Test report shall be submitted one week after completion
of the factory test.
G. System Performance Factory Tests: The report shall document compliance with the
specified performance criteria upon completion and testing of the system. The report shall
indicate the number of days covered by the tests and any conclusions as to the adequacy of
the system. The report shall also include the following information and shall be taken at
least three different times at outside dry-bulb temperatures that are at least 3 deg. C apart:
H. Certificates: Where the system, components, or equipment are specified to comply with
requirements of AGA, NFPA, ARI, ASHRAE, ASME, or UL, copy of proof of such
compliance shall be provided. The label or listing of the specified agency shall be
acceptable evidence. In lieu of the label or listing, a written certificate from an approved,
internationally recognized testing organization equipped to perform such services, stating
that the items have been tested and conform to the requirements and testing methods of the
specified agency may be submitted.
1. Operation Manuals shall list step-by-step procedures required for system startup,
operation, abnormal shutdown, emergency shutdown, and normal shutdown at least 4
weeks prior to the first training course. The manuals shall include the manufacturer's
name, model number, service manual, and a brief description of all equipment and
their basic operating features.
2. Maintenance Manuals shall list routine maintenance procedures, possible breakdowns
and repairs, and a troubleshooting guide. The manuals shall include piping and
equipment layouts and simplified wiring and control diagrams of the system as
installed.
B. ASHRAE Compliance: Comply with ASHRAE 15 for chiller design, construction, leak
testing, and installation.
C. ASME Compliance: Comply with ASME Boiler and Pressure Vessel Code: Section VIII,
"Pressure Vessels," for constructing and testing evaporator and condenser pressure vessels.
Stamp with ASME label.
A. Deliver centrifugal water chillers, factory charged with refrigerant and oil, and with
protective crating and covering.
B. Store chillers to prevent damage and protect from weather, dirt, fumes, water, and
construction debris in clean dry space.
C. Handle chillers according to manufacturer's written rigging and installation instructions for
unloading, transporting, and setting in final location.
0.7 COORDINATION
A. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases.
Concrete, reinforcement, and formwork requirements are specified in Division 3 Section
"Cast-in-Place Concrete."
0.8 WARRANTY
1. Warranty Period: [2] <Insert number> years from date of Substantial Completion.
2. Warranty Period on Compressor Motor: [5] <Insert number> years from date of
Substantial Completion.
3. Warranty Period on Compressor Bearings: [5] <Insert number> years from date of
Substantial Completion. To include any related damage, and annual tear down and
bearing inspection.
A. Maintenance: Submit four copies of manufacturer's "Agreement for Continued Service and
Maintenance," before Substantial Completion, for the Employer's acceptance. Offer terms
and conditions for furnishing consumables and providing continued testing, maintenance
and servicing to include replacing materials and components. Include one-year term of
agreement, commencing at date of Substantial Completion, with option for one-year
renewal.
PART 2 - PRODUCTS
B. Unit and spare parts shall conform to the applicable requirements of ARI 550, ARI 480, and
specified requirements. Energy efficiency rating shall exceed ASHRAE 90A requirements.
A. General: the following sub-section list the maximum permissible noise levels by octave
bands, for day and night operation. Limits will be the same for either the standard octave
bands or for the preferred centre frequency bands. All reports required to be submitted by
the Contractor are to indicate which standard is used. These figures are to be guaranteed
while operating at the design conditions at any location 1.0 m from chillers.
B. Acoustics Report: The Contractor is to submit a report listing the sound power level of the
chillers in dB re 10-12 W for the different octave band frequencies. These levels are to be
in the limits listed below when measured at 1.0 m from chillers.
dB re 10-12 95 95 92 92 88 85 83 83 85
C. If the level in any one octave band exceeds those in the two adjacent bands by more than
5dB, the indicated permissible noise level for that band is to be reduced by 5dB. The above
listed maximum values are to apply to multiple units with all fans/compressors running, as
well as single fans/compressor. Contractor has to provide the necessary treatment like
enclosure or others in order to achieve the specified resulting noise level.
D. Noise Level Outside Chillers Hall: Noise level from chillers with all chillers operating shall
not exceed 70 dB when measured with a standard sound meter on the 'A' scale at ground
level at one meter from chillers hall external wall.
0.4 COMPRESSORS
B. Compressor shall be single or multistage, centrifugal type with [gear-drive, open] [direct-
drive hermetically sealed], compressor-motor assembly.
D. Rotor assembly shall be statically and dynamically balanced to ISO 1940/1-1986, [G6.3]
[G2.5] [G1.0].
F. Lubrication system shall be of the forced-feed type with oil sump, hermetically sealed
motor-driven positive displacement pump, oil filter, and strainer. Oil temperature shall be
thermostatically controlled. A mechanically operated oil supply shall be provided to the
bearings during spin down in event of power interruption. A differential oil-pressure cutout
shall be interlocked with starting equipment and shall allow the compressor to operate only
when the required oil pressure is available at the bearings.
0.5 EVAPORATOR
A. Description: Shell-and-tube design with refrigerant totally enclosed in shell and water in
tubes.
C. Tubes: Seamless, externally finned, individually replaceable tubes; expanded into tube
sheets.
1. Material: Copper.
D. Water Boxes: Marine type, removable, carbon steel, with vent and drain connection.
E. Refrigerant Working Pressure: 2070 kPa or, if higher, the saturation pressure of refrigerant
used at 29 deg. C (85 deg. F).
G. Insulation: Factory applied and painted, to evaporator, suction lines, water boxes and other
surfaces where condensation might occur, with flexible elastomeric insulation of the
following thickness:
1. Thickness: 25 mm.
I. Cooler capacity shall be based on refrigerant suction temperature in excess of 0 deg.C (32
deg. F) and a fouling factor of 0.0005.
J. A frangible-carbon rupture disc safety relief device shall be provided. Device to be piped to
building exterior.
0.6 CONDENSER
A. Construction: Shell-and-tube design with water enclosed in tubes and refrigerant enclosed
in shell.
1. Material: Copper.
2. Size: 19 mm OD; 0.711 mm wall thickness.
3. Internal Finish: Enhanced. Ceramic coating shall be factory applied for all internal
surfaces of end cape and face of condenser.
4. Intermediate tube supports shall be provided so that distance between supports does
not exceed approximately 3 feet (900 millimeter). Supports shall be fitted to the
tubes in a manner that will preclude corrosion, vibration, and abrasion.
5. External Finish: Enhanced.
D. Water Boxes: Marine type, removable, carbon steel, with vent and drain connection.
F. Condenser performance shall be based on a maximum water velocity of 10 feet per second
(fps) (3 meter per second) and a fouling factor of 0.001. Design and construction provisions
shall preclude tube failure due to erosion.
0.7 INSULATION
A. Cooler shell and suction piping between evaporator and first stage of each compressor unit
shall be insulated and vapor-sealed.
B. Water boxes shall be insulated to provide for ease of access to heads for inspection and
repair.
C. Where motors are the gas-cooled type, insulation and vapor seal shall be provided on the
cold-gas inlet connection to the motor.
E. Any coating that cracks when unicellular material is compressed shall be removed and
replaced with specified coating at no additional expense to the Client.
A. When HCFC-123 refrigerant is used, a high efficiency purge system shall be provided and
connected to the main refrigeration system. When in operation, the purge system shall
function to automatically remove air, water vapor, and noncondensable gases from the
refrigeration system and to condense, separate, and return to the system any refrigerant
present therein.
B. Purge system shall be manually or automatically started and stopped and shall be assembled
as a compact unit. Purge system shall be complete with operating and safety devices and
with an oil separator if recommended by the manufacturer.
C. When a positive-pressure refrigerant is used by the manufacturer in the basic liquid chiller
unit, a purge system will not be required. Units shall purge no more than 0.1 pounds (0.045
kg) of non-condensables.
D. Manually Reset Safety Controls: The following conditions shall shut down chiller and
require manual reset:
E. Interface Panel: Factory supplied interface panel to communicate and transmit data between
the chillers and BMS. All required data as from chillers as specified to be transmitted to
BMS. Interface panel to be capable for communication with the specified BMS system.
F. Remote Alarm: During the initiation of a safety shutdown, a chiller's control system shall be
capable of activating a remote alarm bell. In coordination with the chiller manufacture, the
Contractor shall provide an alarm circuit (including transformer if applicable) and a
minimum 100 mm (4 inch) diameter alarm bell. Alarm circuit shall activate bell in the
event of machine shutdown due to the chiller's monitoring of safety controls. The alarm bell
shall not sound for a chiller that uses low-pressure cutout as an operating control.
a. Initiate the chiller start up routine when it receives a request to start from the
chiller system controller.
b. Open the isolation valves on the condenser water and chilled water lines.
c. Start and stop the condenser water and chilled water pumps.
d. Once chilled water and condenser water flow is proven the chiller shall be
started if all safeties (minimum off time, flow switches, etc) permit.
e. The chiller unit controller shall undertake the chilled water supply temperature
control.
3. When a request to stop is received from the chiller system controller the chiller unit
controller shall:
a. Stop the chiller, if the minimum run time has been exceeded.
b. Stop the chilled water pump and close the chilled water isolation valve.
c. Stop the condenser water pump after a predetermined period of time.
d. Close the condenser water isolation valve when the condenser water pump has
stopped.
4. The chiller system controller shall have a data port to enable the exchange of data
from the chiller unit controllers with the BMS.
5. The chiller system controller shall communicate the following information to the
BMS via the gateway for each chiller:
0.10 MOTORS
A. Hermetically sealed motors shall conform to NEMA MG 1, ARI 520 or IP20 to IEC 60529
and to requirements for motors as specified herein.
C. If water-chilled unit or any component could be damaged by reverse motor operation, and
when proposed water-chiller unit contains a mechanically driven lubricating-oil pump, the
manufacturer's responsibility shall include providing reverse-phase rotation protection.
A. Electrical equipment, motors, motor efficiencies, and wiring shall be in accordance with
Dsivision 16.
B. Electrical motor driven equipment specified shall be provided complete with motors, motor
starters, and controls. Electrical characteristics shall be as shown, and unless otherwise
indicated, all motors of 0.746 kW ( 1 horsepower) and above with open, dripproof, totally
enclosed, or explosion proof fan cooled enclosures, shall be high efficiency type.
C. Field wiring shall be in accordance with manufacturer's instructions. Each motor shall
conform to NEMA MG 1 and NEMA MG 2 or IEE wiring regulation 16th edition and be of
sufficient size to drive the equipment at the specified capacity without exceeding the
nameplate rating of the motor.
D. Motors shall be continuous duty with the enclosure specified. Motor duty requirements
shall allow for maximum frequency start-stop operation and minimum encountered interval
between start and stop.
E. Motors shall be sized for the applicable loads. Motor torque shall be capable of accelerating
the connected load within 20 seconds with 80 percent of the rated voltage maintained at
motor terminals during one starting period. Motor bearings shall be fitted with grease
supply fittings and grease relief to outside of enclosure. Automated forced lube is preferred.
F. Manual or automatic control and protective or signal devices required for the operation
specified and any control wiring required for controls and devices specified, but not shown,
shall be provided.
A. Vibration Control: Chiller shall be supplied complete with vibration isolators pads
specifically designed for unit and application, shipped loose for field installation:
B. Equipment Support and Seismic Restraint: Minimum 200 mm thick, reinforced concrete
base extending 100 mm beyond chiller dimensions in each direction.
1. Two radial probes per journal bearing one in X-axis and one in Y-axis.
2. One for thrust bearing Z-axis on active face.
3. One keyphaser for slipping control.
B. Detector design and construction shall be compatible with the temperature, humidity,
barometric pressure and voltage fluctuations of the operating area. Detector shall have an
adjustable sensitivity such that it can detect refrigerant at or above 3 parts per million (ppm).
D. Detector shall be provided with a failure relay output that energizes when the monitor
detects a fault in its operation. Detector shall be compatible with the Building Management
System (BMS) and shall be capable to interface with the chiller plant manager system as
well as the BMS. The BMS shall be capable of generating an electronic log of the
refrigerant level in the operating area, monitoring for detector malfunctions, and monitoring
for any refrigerant alarm conditions.
A. The Contractor and proposed chiller manufacturer shall be responsible for performing the
chiller factory test to validate the specified full load capacity, full load EER, and [IPLV]
[NPLV] in accordance with ARI 550/590 except as indicated.
B. The chiller factory test shall be carried out at design ambient temperatures of 46C DB and
29C WB, as well as 52C DB with reduced capacity without mechanical failure.
C. The chiller factory test shall be performed in the presence of the Client’s and Engineer’s
representatives team. The team will comprise maximum four representatives. All expenses
to be borne by the Contractor.
D. The Contractor and chiller manufacturer shall provide to the Engineer a certified chiller
factory test report in accordance with ARI 550/590 to confirm that the chiller performs as
specified. Tests shall be conducted in an ARI certified test facility in conformance with
ARI 550/590 procedures and tolerances.
G. Test Instrumentation: The factory test instrumentation shall be per ARI 550/590 and the
calibration shall be traceable to the National Institute of Standards and Technology. All
Instrumentation shall have been calibrated within 6 month of the test date.
H. Test Report: A certified test report of all data shall be forwarded to the Engineer for
approval prior to project acceptance. Calibration curves and information sheets for all
instrumentation shall be provided.
I. Equipment Adjustments: If the equipment fails to perform within allowable tolerances, the
manufacturer shall be allowed to make necessary revisions to his equipment and retest as
required. The manufacturer shall assume all expenses incurred by the Client/Engineer to
witness the retest.
J. Chillers shall be sound tested at the factory prior to shipment to confirm the sound pressure
level specified herein. Tests and data shall be conducted and measured in strict accordance
with ARI 575 at the full load system operating conditions. The chiller sound pressure level,
in decibels (dB), with a reference pressure of 20 micropascals, shall not exceed the specified
noise level. Ratings shall be in accordance with ARI 575. No reduction of entering
condenser water temperature or raising of leaving chilled water temperature shall be
allowed. A minimum of 75 percent of the sound data points shall be taken along the length
of the machine, and established as the minimum percentage of total possible points used to
determine sound levels. In the event that the chiller does not meet the dBA sound pressure
level, the manufacturer shall, at his expense, provide sufficient attenuation to the machine to
meet the specified value. This attenuation shall be applied in such a manner that it does not
hinder the operation or routine maintenance procedures of the chiller. The attenuation
CENTRIFUGAL WATER CHILLERS 15625 - Page 14/18
STD-SPC-DCA(A3)-ME-DCA REV A
<Project Title>
material, adhesives, coatings, and other accessories shall have surface burning
characteristics as determined by ASTM E 84.
PART 3 - EXECUTION
0.1 EXAMINATION
A. Examine areas to receive chillers for compliance with maintenance clearance and tube pull
requirements, installation tolerances and other conditions affecting chiller performance.
Examine proposed route of moving chillers into place and verify that it is free of
interferences. Proceed with installation only after unsatisfactory conditions have been
corrected.
B. Final chiller locations indicated on Drawings are approximate. Determine exact locations
before roughing-in piping and electrical connections.
0.2 INSTALLATION
A. Refrigeration equipment and the installation thereof shall conform to ASHRAE 15.
Necessary supports shall be provided for all equipment, appurtenances, and pipe as required,
including frames or supports for compressors, pumps, cooling towers, condensers, liquid
coolers, and similar items. Compressors shall be isolated from the building structure.
B. Equipment shall be properly leveled, aligned, and secured in place in accordance with
manufacturer's instructions.
C. Install chillers level and plumb, and maintain manufacturer's recommended clearances for
service and maintenance.
D. Equipment Support and Seismic Restraint: Anchor concrete base and chiller for seismic
restraint by means and methods acceptable to the Engineer. Dowel concrete base to the
floor on 450 mm centers around perimeter. Anchor chiller to concrete base with at least
four 13 mm anchors that penetrate base and extend into the sub-floor at least 100 mm.
E. Electrical Wiring: Install electrical components, devices, and accessories furnished loose by
manufacturer, including remote flow switches.
A. Initial Charge: Upon completion of all the refrigerant pipe tests, the vacuum on the system
shall be broken by adding the required charge of dry refrigerant for which the system is
designed, in accordance with the manufacturer's recommendations. The Contractor shall
provide the complete charge of refrigerant in accordance with manufacturer's
recommendations. Upon satisfactory completion of the system performance tests, any
refrigerant that has been lost from the system shall be replaced. After the system is fully
operational, service valve seal caps and blanks over gauge points shall be installed and
tightened.
B. Refrigerant Leakage: If a refrigerant leak is discovered after the system has been charged,
the leaking portion of the system shall immediately be isolated from the remainder of the
system and the refrigerant shall be pumped into the system receiver or other suitable
container. The refrigerant shall not be discharged into the atmosphere.
C. Contractor's Responsibility: The Contractor shall, at all times during the installation and
testing of the refrigeration system, take steps to prevent the release of refrigerants into the
atmosphere. The steps shall include, but not be limited to, procedures that will minimize the
release of refrigerants to the atmosphere and the use of refrigerant recovery devices to
remove refrigerant from the system and store the refrigerant for reuse or reclaim. At no
time shall more than 85 g of refrigerant be released to the atmosphere in any one
occurrence. Any system leaks within the first year shall be repaired in accordance with the
specified requirements including material, labor, and refrigerant if the leak is the result of
defective equipment, material, or installation.
0.4 CONNECTIONS
C. Ground equipment.
1. Test and adjust controls and safeties. Replace damaged or defective and
malfunctioning components, controls and equipment.
2. Correct deficiencies identified by observations and tests; retest until specified
requirements and satisfactory results are obtained.
0.6 CLEANING
A. After completing installation, including outlet fittings and devices, inspect unit components.
Remove paint splatters and other spots, dirt, and debris. Repair damaged finish to match
original finish.
0.7 COMMISSIONING
C. Start-up:
a. Leak testing.
b. Refrigerant pressure testing.
c. Evacuation.
d. Dehydration.
e. Charging the chiller with refrigerant.
f. Check and record performance of chiller protection devices.
g. Check and record performance of chilled- and condenser-water flow and low-
temperature interlocks.
h. Operate chiller for run-in period as recommended by the manufacturer.
i. Check static deflection of vibration isolators, including deflection during
chiller startup and shutdown.
j. Check refrigerant charge.
k. Check oil level.
2. After the above services have been performed, the same factory-trained representative
shall be available for fifteen days to instruct the owner's personnel in the proper
operation and maintenance of the chiller.
3. The Contractor shall supply the owner with the following literature as furnished by
the manufacturer prior to start-up:
D. Guarantee the main electric motor starters shall be furnished and guaranteed by the
centrifugal chiller manufacturer who will be responsible for the refrigeration system
performance and its control.
A. Manufacturer shall be responsible for supervising the installation of the ship loose
components of the chiller on-site.
B. Manufacturer is responsible for the reconnection of all control wiring from the chiller to the
chiller control panel and starter.
D. Manufacturer shall reconfirm the proper operation of the chillers control system in all
modes of operation, including all shutdowns.
0.9 DEMONSTRATION
A. During the Defects Liability Period, when instructed by the Engineer, engage a factory-
authorized service representative to conduct a seasonal performance test according to
requirements of the Engineer. Report results in writing.