Professional Documents
Culture Documents
Contents
Executive summary 04
Introduction 07
Appendix 24
Sources 27
Contacts 28
2
Program management in aerospace and defense Still late and over budget
3
Program management in aerospace and defense Still late and over budget
Executive summary
In our 2009 study “Can we afford our own future? Why A&D
programs are late and over budget—and what can be done to
fix the problem,” we predicted that if significant changes were
not made to address the root causes of program management,
cost overruns and schedule delays would continue to
accentuate. In line with our prediction, total cost of the US
Department of Defense’s (DoD) 2015 Major Defense Acquisition
Program (MDAP) portfolio grew at 48.3 percent with an average
schedule delay of 29.5 months1 over original baseline estimates.
The combined cost overrun for the MDAP portfolio in 2015 was
US$468 billion, up from US$295 billion in 2008.2 Similarly, in
the commercial aerospace market, aircraft manufacturers have
continued to experience significant schedule delays and cost
overruns in their new aircraft developments.
4
Program management in aerospace and defense Still late and over budget
Looking ahead, our research indicates that although cost overruns and schedule delays
are expected to continue through 2020, the magnitude of increase is likely to be gradual.
In addition, this study has observed:
04 09
keeps cost down and offers a more
realistic estimate of how long a project
takes to complete.
Number of programs in the current Programs with the largest cost growth
DoD portfolio and their total cost is have resulted from quantity increases, •• Having realistic and feasible project cost
at the lowest level since 2004, and process inefficiencies, design and estimates at the beginning of a program to
reached its peak in 2009.6 technical modifications, and major help prevent them from rising steeply over
restructuring such as combining the course of the program lifecycle.
programs and changing the mix of
•• Using the knowledge-based approach
items purchased.
recommended by the US Government
Accountability Office (GAO) more
extensively than what current adoption
05 10 indicates.
Since 2008, only 14 major programs Some programs experienced cost •• Providing proper incentives and
have entered the DoD program reductions as a result of decreased empowering program managers, while
portfolio, which stands at 79 in 2015, quantities or program restructuring, also holding them accountable to solve
compared to 95 in 2007 and 102 in which mainly combined or eliminated problems and reduce risks by effectively
2009, respectively.7 portions of the program. addressing issues early.
5
Program management in aerospace and defense Still late and over budget
6
Program management in aerospace and defense Still late and over budget
Introduction
It has been seven years since we published in development or production and also published numerous studies with
our study on cost overruns and schedule requirements changes, cost and schedule recommendations for changes. However,
delays in the aerospace and defense (A&D) growth remain significant. Specifically, schedule and cost slippages as well as
sector. There was at that time, and there companies competing for defense shortfalls in technical performance,
continues to be, significant activity to try contracts face challenges of extensive especially on defense acquisition programs,
and address the systemic cost and schedule and ever-changing regulations, increased continue to persist.
overruns that erode the buying power of costs, and instability of funding caused by
To gain a deeper understanding of the
A&D companies. These efforts included sequestration, continuing resolutions, and
issues associated with cost and schedule
changes to the product development lapses in appropriations. More importantly,
overruns for the A&D programs, we
lifecycles, changes to the acquisition with the advent of the Budget Control Act
conducted interviews of multiple senior
processes of MDAPs, and use of ever more and the resultant effects of sequestration,
program managers from both government
sophisticated program development tools. there are even less acquisition dollars
and commercial A&D organizations,
available and we now have the smallest
As we approach this year’s election and performed extensive research from publicly
number of MDAPs in the defense portfolio
the installation of a new administration, it available information of commercial A&D
since 2003.
is timely to look at the progress over the programs, and also analyzed MDAPs using
past seven years. And, as appropriate, In the commercial aerospace market, the cost and schedule data published in
again make recommendations on what increased aircraft demand due to increasing the Department of Defense’s “Selected
can be done to abate this long term passenger miles drives the need to hold and Acquisition Reports."
problem as it has become an ever more shorten the development schedules of new
This study looks at the progress that has
critical issue. While the focus of this study models. However, recent evidence indicates
been made since our 2009 assessment,
is the DoD and defense side of the A&D the opposite. Publicly available data on
explores the root causes seen today
sector, manufacturers of commercial commercial aircraft development indicates
with respect to the key challenges
aircraft are also grappling with the same large budget overruns and schedule delays
associated with the continued trends of
issues and therefore, our conclusions and are common.9
cost and schedule growth, and provides
recommendations are applicable for the
Multiple major studies were commissioned recommendations for sustainable and long-
commercial aerospace sub-sector as well.
by US presidents, secretaries of defense, term improvement.
Although a number of programs improved Congress, government agencies, and
their buying power by finding efficiencies universities on this topic. The GAO has
7
Program management in aerospace and defense Still late and over budget
8
Program management in aerospace and defense Still late and over budget
9
Program management in aerospace and defense Still late and over budget
2011
2012
2013
Note: For 2014, GAO did not calculate a 5-year comparison as there was no data published for December 2008
60%
50%
51%
47%
40%
Percentage change
30%
29%
27%
20%
10% 5%
10%
5%
0%
2003-2005 2005-2008 2008-2012 2012-2015
10
Program management in aerospace and defense Still late and over budget
Figure 4. Number of major programs that entered and exited DoD portfolio (2000-2015)
18
16
14 14
Number of programs
12 11
10
2 1
0
0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
Year
Number of major programs entered Number of major programs exited / completed
Moreover, the DoD’s program portfolio stands at 79 at the end of 2015 as compared to 102 in 2009 and 95 in 2007.15
102
95 96 98 96
91 89
81 84
77 80 78 79
74
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
11
Program management in aerospace and defense Still late and over budget
12
Program management in aerospace and defense Still late and over budget
13
Program management in aerospace and defense Still late and over budget
Initial capability
requirements
A lack of understanding, early in the The Global 7000/8000 program’s wing
program, of what it is going to take to design to provide both short-field and long- “Sometimes people do know
deliver the platform has resulted in the range performance led to the delivery delay that it’s going to cost a lot
“appearance” of cost and schedule increases as meeting the dual requirements required
more than they’re actually
in both the commercial aircraft and defense redesign.23
markets. We believe this is most likely the fessing up to. Facing up
It is important to make sure the initial
result of optimistic planning.
capability requirements are not over-
to the truth in what we’re
Some of the examples of issues due to the estimated and are reviewed continually in seeking to develop, how
initial capability requirements include: order to avoid any changes at a later stage. much it’s going to cost, what
•• Use of composite materials requiring more If we heard one factor more frequently the risk is involved and the
testing to demonstrate performance and than any other, it was around requirement price tag of the risk, allows
reliability stability. Defining the requirements fully
for an honest analysis
early in the program and then managing the
•• Innovative and adaptive wing designs
changes with a strict program management of project pricing and
requiring more flight certification testing outcome.”20
discipline is important.
•• Integrating dissimilar materials This phase primarily focuses on program
•• Ineffective cost estimates and baseline affordability, availability of resources, and - Tina Jonas
schedule assessments estimating the prospect of success of the Former Comptroller for the DoD
program.
None of these actually failed, however, it
required additional time and money to
prove as compared to their traditional “18 percent of cost growth
counterparts. during product development
For instance, C919 faced program delays is due to initial errors in cost
of four years due to its inexperience and
estimation. A continuous
its vigilant approach to ensure no safety
issues cropped up. Also, the company had
cycle of reform, review
planned 20 percent of composite usage and revision is required
which was later cut to 10 percent to avoid in the defense acquisition
complexity and likely delays.21 Similarly, the
process.”19
MC-21 program experienced delays due to
the company’s attempt to use a new weight-
saving composite technology.22 - Todd Harrison
Director of Defense Budget
Analysis, Center for Strategic and
International Studies (CSIS)
14
Program management in aerospace and defense Still late and over budget
Technology and
risk evaluation
A few programs that faced issues during
this phase resulting in cost and schedule “Setting achievable and
overruns include: testable requirements
•• The DDG 51 Arleigh Burke class guided is probably the most
missile destroyers required substantial important part of the
design modification, to incorporate the
acquisition process, because
new Air and Missile Defense Radar (AMDR).
With those changes and associated if you get the requirements
increases in the ships’ displacement, the wrong at the beginning, it
average cost per ship over the entire will eventually derail a whole
production run increased to US$1.9
program.”25
billion in 2015 dollars, or approximately 15
percent more than the Navy’s estimate of
US$1.7 billion.24 - Todd Harrison
Director of Defense Budget
•• Also, the Standard Missile 6 program
Analysis, Center for Strategic and
experienced cost overruns as it was
International Studies (CSIS)
decided at a later stage to modify it into an
anti-ship missile, rather than just a ballistic
missile defense weapon.
Technical complexity and the desire
for technological innovations to be
incorporated into today’s sophisticated
programs are contributing to the cost
and schedule overruns we are seeing in
large development programs. While A&D
programs, weapon systems in particular,
are more complex and sophisticated now,
acquisition systems are not nimble enough
for these programs that rely heavily on
rapidly changing technologies. Increasing
complexity of systems (for example, in
F-35 combat aircraft) is one of the principal
reasons that development times have
increased significantly in the past
few decades.
15
Program management in aerospace and defense Still late and over budget
Development
We see the effects of this during the •• In the 787 Dreamliner program, the key
development phase of the program composite structured elements failed
when we begin to try and integrate the during testing, which resulted in significant
myriad of elements and begin to test their redesign and reviews causing US$26
performance: billion in cost growth.26
16
Program management in aerospace and defense Still late and over budget
Statistical
process control
(SPC) processes and
techniques are not used
prior to transitioning from
Late
limited production
program
to full-scale
requirements
production
and changes require
retooling and/or different
manufacturing
Many of the current Existing program and assembly
production methods management tools technologies
do not support the usage including material resource
of advanced/specialty planning and management
materials, such as systems are dated and as such,
composites are ineffective to manage and
address today’s complexity Global supply
programs changes complicate
and impact the overall
lead time and costs when
faced with supplier
Production
bottlenecks and
breakdowns
The production phase includes commencement of production and operational deployment. There has to be effective
coordination between the DoD and contractors during this phase in order to ensure a smooth flow of production without
facing any hurdles. Lengthy purchase cycles lead to technology becoming obsolete during the phase of the acquisition
process, weapon system and the technology being acquired becomes obsolete due to the prolonged purchase cycle. In
various instances, this has resulted in modifications and subsequent costs as well as schedule delays. Such issues are more
prevalent in new technologies and emerging threats such as cyber.
17
Program management in aerospace and defense Still late and over budget
Cross-cutting
contributing issues
Issues of cost and schedule overruns are based communications tool for suppliers customer demand and implementing
cutting across all or some of these program to input information. In another instance, new technologies while achieving
phases: A380 Jumbo Jet program experienced a productivity targets. The issue is growing
two-year schedule delay, where one of and is exacerbated by a number of factors
•• Engagement between OEMs and
the reasons for the delay was the design including baby boomer retirements, loss of
suppliers/contractors. There have been
inconsistencies due to different Computer embedded knowledge due to movement
various instances where contractors have
Aided Design (CAD) software used by the of experienced workers, a negative image
failed to understand OEMs’ requirements
OEM. of the manufacturing industry among
to develop and deliver the best possible
younger generations, and lack of STEM
product in a timely fashion. Over the •• Culture. Program managers have been
(science, technology, engineering and
past many years, contractors have put in working in an operating environment
mathematics) skills among workers.
enormous efforts and spent huge time to where the culture does not encourage
convince the OEMs to buy the equipment prioritizing programs, making hard
manufactured by them in order to avoid decisions, conducting tough analysis, and
losses. increasing focus on costs. Also, they have
Ash Carter suggested that
lesser authority and lack the ability to say reducing number of people
•• Lengthy lifecycle. Length of the program
lifecycle of today’s programs cause further
no, i.e., they are not empowered to focus involved in acquisition
on building critical military capabilities process, which will include
issues such as changing technology,
while working to reduce non-core
obsolescence, and frequent requirement
workforce and associated costs.
evaluating, “and where
changes. appropriate reducing”
•• The widening skills gap. US
•• Discipline. It’s often seen that proper
manufacturers, including those in the
members of the Defense
discipline is not followed across the phases Acquisition Board, which
A&D sector, continue to report a sizeable
of a program, such as lack of scoping in the
initial capability requirements. Time and
gap between the science and engineering currently is composed of
talent they need to keep growing their 35 principals and advisers.
again, special processes and procedures
businesses and the talent they can
are based on only a few problems faced in
actually find. According to Deloitte and
“Reducing these layers will
the past, which are not likely to recur. both free up staff time
the Manufacturing Institute's The Skills
•• Communication. There are excessive Gap in US Manufacturing study, six out and focus decision-making
lines of communication and layers within of 10 manufacturing positions currently energy on overcoming
the DoD acquisition domain. These involve remain unfilled due to the talent shortage.
program managers, deputy executive Additionally, it takes an average of 94 days
real obstacles to program
officers, executive officers, and then to recruit employees in the engineering success rather than
the higher ranks of the DoD acquisition, field and an average of 70 days to recruit bureaucratic hurdles,” Carter
technology, and logistics office. skilled production workers. The effects said.27
of the talent shortage are being felt in
•• Program management tools. There was
functions throughout the A&D companies.
a schedule delay for four years with huge - Ash Carter
Specifically, the greatest impact of the
cost overruns for the 787 Dreamliner United States Secretary of Defense
skills shortage has been in maintaining or
program. One of the causes for the delay
increasing production levels in line with
included the failure of Exostar, a web-
18
Program management in aerospace and defense Still late and over budget
19
Program management in aerospace and defense Still late and over budget
Recommendations: How
can the A&D sector address
program management issues?
01. Have realistic cost and schedule 02. Empower program managers and 04. Follow engineering change
estimates. make them accountable. discipline.
To address cost estimation and Give program managers more A discipline in terms of engineering
other technical issues, contractors responsibility and make them changes should be followed strictly in
and program managers should be accountable throughout the project order to restrict program management
realistic about their expectations of lifecycle. No-go decisions should be challenges. Implications of any changes
their programs' accomplishments taken by program managers in cases once the critical design review is
concerning timelines and budgets. Since where there are substantial changes that complete should be communicated
implementing change and assessing the may result in the project being unviable clearly as such changes lead to both
effects of major policy changes is a time or delayed unreasonably. cost and schedule delays. Project
consuming process, program managers requirements should be identified at
03. Leverage an advanced risk-based
and DoD leaders should be educated an early stage and adding additional
approach to managing acquisition
and encouraged to have patience. requirements later in the process
programs.
Anxiety by program managers to have should be avoided. Maintaining the
The issue of a complex operating
and see on-ground improvements requirements from the initial phase of
environment can be overcome by
quickly could result in further new the project can ensure low costs and can
developing an advanced risk-based
changes being made even before the also provide a more accurate estimate of
approach to managing acquisition
reforms lead to a positive effect. the project duration.
programs. This can be done by
Follow a knowledge-based considering the exclusive features of
acquisition approach. the weapon systems being acquired
A&D sector will likely gain from and the circumstances (funding,
leveraging a knowledge-based geopolitical climate, etc.) in which these
acquisition approach, where product procurements are being executed.
developers ensure significant knowledge Program managers should analyze past
is attained during key development data to identify and increase focus on
stages. As suggested by GAO in its those programs or phases of programs,
“Assessments of Selected Weapon which are likely to experience challenges
Programs” report published in March in the future, based on empirical data.
2016,28 key action areas include
ensuring:
–– technology, schedule, cost, and other
resources are in line with customer’s
expectations
–– design stability that meets
performance expectations
–– production is in line with cost,
schedule, and quality objectives
20
Program management in aerospace and defense Still late and over budget
05. Ensure smooth cross-functional 06. Engage with innovative niche 07. Work towards creating a supply of
communication. players. workers with strong skills.
Program managers should ensure Large companies could benefit from Skilled engineers and production
there is an effective and smooth improving engagement with small, workers will be critical to the future
cross-functional communication innovative companies to harness their competitiveness of A&D companies and
between teams. For instance, different expertise to develop products and the sector as a whole. A&D companies
engineering departments should systems that are needed in a cost- therefore, should take the lead in
clearly communicate with each other effective and timely manner. Increased managing the talent crisis by designing
before committing any timelines to efforts should be made to engage with strategies that not only optimize talent
management. Lack of communication niche and innovative players, specifically acquisition, and deployment, but also
may lead to delays or budget overruns startups from the technology hubs contribute to developing manufacturing
as inputs from some teams may be across the country, offering advanced and engineering skills in their
missing at the time of decision making. solutions at a cheaper cost and faster communities. Fresh approaches in areas
pace. For example, Thales announced such as employer branding can generate
Align R&D efforts with DoD’s future
their xPlor innovation platform as they big results when pursued in tandem
needs.
are seeking to engage a wider set of with more traditional approaches.
Defense contractors’ Internal Research
start-ups and an academic ecosystem to Similarly, many manufacturers are using
and Development’s (IRAD) spending
share ideas. a number of the same tactics to talent
decisions should be made keeping in
development that were being employed
mind the DoD’s future needs as well
a decade ago. New performance tools
as to avoid significant spending on
and formal processes should be playing
developing weapons and equipment
a larger role in any A&D manufacturer's
that the military does not actually need.
talent management plan.
For instance, to ensure Boeing’s UCLASS
drone fighter is equipped for long-range
strike, intelligence, surveillance and
reconnaissance missions, Pentagon
decided to pause the program, which
was a significant IRAD investment for the
OEM.29 So, it is highly recommended for
the industry to align their internal R&D
spending with what the DoD requires.
21
Program management in aerospace and defense Still late and over budget
22
Program management in aerospace and defense Still late and over budget
Summary: Holding
the line and staying
on target
The A&D sector has been struggling with programs are introduced, cost and schedule
program management for decades. Major challenges experienced previously could
A&D programs, both commercial aerospace reappear without significant reforms and
and defense systems are increasingly additional investments in acquisition and
becoming more complex and sophisticated, program management initiatives.
leading to a significant increase in
Significant and long-lasting improvements
schedule delays and development costs.
to program management in the A&D sector
However, there have been improvements
is possible by addressing the problem at the
implemented, programs restructured,
grass roots level. Key focus areas, among
and decline in cost and schedule growth
others, should include having realistic
at the DoD during the past five years. This
cost and schedule estimates, empowering
progress more likely is due to maturing
program managers and making them
programs and a significant decline in new
accountable, and following a knowledge-
program starts, although serious efforts
based acquisition approach to programs.
by the acquisition community appear
to be taking hold. However, as new DoD
23
Program management in aerospace and defense Still late and over budget
Appendix
Figure 8: Key defense programs that witnessed significant cost variation
Amounts in US$ millions
Handheld, Issues faced in the testing phases, where the Manpack did
Manpack, and not meet reliability requirements twice, leading to schedule
$9,130 $5,211 $3,919 75.2%
Small Form Fit delays and cost overruns. However, redesigning efforts have
Radios been able to resolve these problems.
24
Program management in aerospace and defense Still late and over budget
LHA 6
America class Witnessed increase in costs due to design changes and
$9,971 $6,958 $3,013 43.3%
amphibious technological advancements.
assault ship
EA-18G Growler
$15,305 $12,628 $2,677 21.2% Increase in costs primarily attributed to increase in quantity.
aircraft
AH-64E Apache
$13,992 $11,516 $2,476 21.5% Cost increase due to upgradation efforts.
Remanufacture
Patriot
Advanced Cost decrease primarily due to decrease in quantities
Capability-3 $6,354 $8,361 ($2,007) -24.0% from 1,528 units to 1,093 units and also due to due to the
Missile Segment acceleration of the procurement buy profile.
Enhancement
RQ-4A/B
Global Hawk
$10,039 $14,785 ($4,746) -32.1% Mainly led by decrease in quantity.
unmanned
aircraft system
25
Program management in aerospace and defense Still late and over budget
Figure 8: Key defense programs that witnessed significant cost variation (contd.)
Amounts in US$ millions
Figure 9: Commercial aircraft programs that witnessed cost and schedule overruns
Witnessed a schedule delay of 4 years with massive cost overruns, primarily due to complexity in the global supply
787 Dreamliner
chain, use of structural elements made of composites, and lack of supply chain and risk management experts
The program witnessed a two-year delay in the 747-8 led by limited availability of engineering resources within the
747-8
company, changes in design, and factory worker’s strike.
Witnessed a two-year delay in schedule and a US$6.1 billion in cost overruns due to technical complexity of the aircraft
A380 - the aircraft’s composite fuselage, high efficiency, and adaptive wings required extensive testing to prove consistency
prior to entering into service.
Witnessed delay and cost overruns as a certifying technology for the composite fuselage frames for the aircraft
A350-900 structure was absent initially. Also, A350-900 used advanced production techniques with over 1,000 lightweight
3D-printed resin parts in the initial production aircraft leading to delays.
Cost and schedule delays were led by issues from suppliers, longer than expected system integration processes,
C Series
difficulties with certification flight testing, engine failure in one of the four test aircrafts, as well as order cancellations.
Global The Global 7000/8000 program’s wing design to provide both short-field and long-range performance led to the
7000/8000 delivery delay as meeting the dual requirements required redesign.
C919 faced program delays of 4 years due to its inexperience and its vigilant approach to ensure no safety issues crop
C919 up. Also, the company had planned 20 percent of composite usage initially, which was later cut to 10 percent to avoid
complexity and likely delays.
Mitsubishi MRJ program was delayed by 4 years as there were delays in the procurement of engines and other components,
Regional Jet which delayed flight testing. The program also had aircraft weight issues.
26
Program management in aerospace and defense Still late and over budget
Sources
1 “Defense Acquisitions: Assessments of Selected Weapon Programs,” GAO Report to Congressional Committees, Mar 2016
2 Deloitte analysis based on GAO’s “Assessments of Selected Weapon Programs” and “Selected Acquisition Reports”
3 Ibid
4 Ibid
5 Ibid
6 “Defense Acquisitions: Assessments of Selected Weapon Programs,” GAO Report to Congressional Committees, Mar 2016
7 Ibid
8 Deloitte analysis based on GAO’s “Assessments of Selected Weapon Programs” and “Selected Acquisition Reports”
9 “Boeing’s Tanker Cost Overruns Exceed $1 Billion,” Aviation Week, Jul 2015 aviationweek.com/defense/boeing-s-tanker-cost-overruns-exceed-1-
billion; “Bombardier’s biggest gamble: How everything went so wrong with the C Series dream,” Financial Post, Dec 2015 business.financialpost.com/
news/transportation/bombardiers-biggest-gamble-how-everything-went-so-wrong-with-the-cseries-dream; “The eye of the storm,” The Economist,
May 2016 www.economist.com/news/business/21698706-building-new-plane-take-airbus-would-be-huge-risk-boeing-eye-storm; Deloitte analysis
10 “Defense Acquisitions: Assessments of Selected Weapon Programs,” GAO Report to Congressional Committees, Mar 2016
11 Deloitte analysis based on GAO’s “Assessments of Selected Weapon Programs” and “Selected Acquisition Reports”
12 “Q&A with Ashton B. Carter,” Belfer Center for Science and International Affairs, 2012 belfercenter.ksg.harvard.edu/publication/21563/qa_with_
ashton_b_carter.html
13 “Defense Acquisitions: Assessments of Selected Weapon Programs,” GAO Report to Congressional Committees, Mar 2016
14 Deloitte analysis based on GAO’s “Assessments of Selected Weapon Programs” and “Selected Acquisition Reports”
15 Ibid
16 Deloitte analysis
17 “Qatar Looks To Boeing After Canceling Airbus Order; 737 To Stretch,” Investor’s Business Daily, Jul 2016 www.investors.com/news/boeing-nabs-two-
4-billion-deals-as-farnborough-airshow-begins
18 “Airbus Launches Initiatives Addressing A350 Delays, Supplier Issues,” Aviation Week, May 2016 aviationweek.com/commercial-aviation/airbus-
launches-initiatives-addressing-a350-delays-supplier-issues
19 “3 takeaways from Lexington Institute's forum on defense acquisition reform,” American City Business Journals, Jun 2015 www.bizjournals.com/
washington/blog/fedbiz_daily/2015/06/3-takeaways-from-lexington-institutes-forum-on.html
20 Ibid
21 “Comac reduces C919 composite use to speed up progress,” FlightGlobal, May 2013 www.flightglobal.com/news/articles/comac-reduces-c919-
composite-use-to-speed-up-progress-386300
22 “Irkut president sets out MC-21 ambitions,” FlightGlobal, June 2015 www.flightglobal.com/news/articles/paris-irkut-president-sets-out-mc-21-
ambitions-413204
23 “Bombardier announces two-year Global 7000 delay,” FlightGlobal, July 2015 www.flightglobal.com/news/articles/bombardier-announces-two-year-
global-7000-delay-415200
24 “Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress,” Congressional Research Service, May 2016 www.fas.org/
sgp/crs/weapons/RL32109.pdf
25 “3 takeaways from Lexington Institute's forum on defense acquisition reform,” American City Business Journals, Jun 2015 www.bizjournals.com/
washington/blog/fedbiz_daily/2015/06/3-takeaways-from-lexington-institutes-forum-on.html
26 Deloitte analysis
27 “Remarks on Goldwater-Nichols at 30: An Agenda for Updating (Center for Strategic and International Studies),” US DoD, Apr 2016 www.defense.gov/
News/Speeches/Speech-View/Article/713736/remarks-on-goldwater-nichols-at-30-an-agenda-for-updating-center-for-strategic
28 “Defense Acquisitions: Assessments of Selected Weapon Programs,” GAO Report to Congressional Committees, Mar 2016
29 “CEOs Question DoD’s New IRAD Rule,” Breaking Defense, Jun 2015 breakingdefense.com/2015/06/ceos-question-dods-new-irad-rule
27
Contacts
Author:
Robin S. Lineberger
Principal, Aerospace & Defense
Deloitte Consulting LLP
+1 571 882 7100
rlineberger@deloitte.com
Co-Author:
Aijaz Hussain
Associate Vice President, Aerospace & Defense
Deloitte Center for Industry Insights
Deloitte Services LP
aihussain@deloitte.com
Acknowledgements:
Thank you to Siddhant Mehra from Deloitte Services LP for his contributions to this study.
About Deloitte
Deloitte refers to one or more of Deloitte Touche Tohmatsu Limited, a UK private company limited by guarantee (“DTTL”), its
network of member firms, and their related entities. DTTL and each of its member firms are legally separate and independent
entities. DTTL (also referred to as “Deloitte Global”) does not provide services to clients. Please see www.deloitte.com/about for
a detailed description of DTTL and its member firms. Please see www.deloitte.com/us/about for a detailed description of the
legal structure of Deloitte LLP and its subsidiaries. Certain services may not be available to attest clients under the rules and
regulations of public accounting.
This publication contains general information only and Deloitte is not, by means of this publication, rendering accounting,
business, financial, investment, legal, tax, or other professional advice or services. This publication is not a substitute for such
professional advice or services, nor should it be used as a basis for any decision or action that may affect your business. Before
making any decision or taking any action that may affect your business, you should consult a qualified professional advisor.
Deloitte shall not be responsible for any loss sustained by any person who relies on this publication.