Professional Documents
Culture Documents
Strategies to successfully
manage your major project
Whitepaper 1
kpmg.com/nz
Major construction projects are large in fundamental legal and accountability Effective management of major projects
every sense – including major size, major obligations. As a result, the KDC relies on three key concepts: early planning
cost, major complexity, and major risk. effectively lost control of a major and organising, stakeholder communication
When things go awry, it can also mean infrastructure project.1 and project controls integration, and
major cost and reputational damage. continuous improvement.
According to the Office of the Auditor-
For example, the Kaipara District Council
General’s Report November 2013, the In this first instalment of a three-part series,
(“KDC”) managed the Mangawhai
principal causes of the project’s failures KPMG’s Major Projects Advisory practice
community wastewater scheme between
were: poor governance, lack of effective offers eight best practices for early planning
1996 and 2012, at an estimated cost of
and efficient management and records, and organising of your major project.
$63.3 million. Yet the actual cost of the
and ineffective management oversight.
project is unknown, due to poor records
The lesson from this report is that project
and systematic information on the amount
management on major projects must be
spent. The project failed to attend to its
equal to the task.1
Project Advisory / Leadership Series 10 / Whitepaper 1 /02
Project teams need to be both cautious and allowances where design details for factors such as new or unproven technology,
realistic when developing project estimates. specific project elements are insufficient difficult or challenging geographic conditions,
Because company executives are naturally for preparing feasibility stage estimates. resource constraints, or fluid materials price
enthusiastic about a project’s anticipated escalations will make it very difficult to
After the conclusion of the feasibility stage
benefits, they also can be overly optimistic achieve this desired level of accuracy. It may
and just before project authorisation, the
about cost and time constraints. Have your require additional analysis and studies unless
project estimate (sometimes referred to as
core team validate initial concept estimates the organisation is willing to accept a lower
the ‘budget at completion’ or ‘performance
and identify significant estimating errors and level of accuracy and a larger contingency.
measurement baseline’) should have a
omissions. During the design development
predictive accuracy of plus 20 percent Your project team will also develop
stage, rely on parametric cost estimates
to minus 15 percent. If the estimate estimates of the time needed for
and benchmark data that are recognised
is prepared correctly, the project team completing the project. The duration and
industry-wide, rather than on your own
effectively represents that: completion dates of interim milestones –
internal estimates. Develop pricing models
such as detailed engineering, long-lead
based on a range of possible outcomes. i) the estimate is realistic and achievable;
equipment procurement, site work,
As the project moves into the feasibility ii) that quantities and pricing have been foundations, structure, mechanical
stage, conduct preliminary studies that checked and validated by both internal completion, and testing and commissioning
produce a “design-basis” estimate. This and external engineering resources; and – will be discussed and agreed upon. Once
should include all engineering quantities, again, it is important that experienced
iii) that the project team is committed
craft and supporting labour hours, Critical Path Method (CPM) schedulers
to managing cost within the relative
commodity pricing, equipment pricing, and estimators are involved in the
percentage band surrounding the
project management costs, and internal development and vetting of the project’s
budget estimate.
company costs (e.g. shared services, initial schedules. Scheduling errors leading
management time, financing costs, interest That’s a tall order for a multiyear, to unrealistic project durations have a ripple
expenses) utilising appropriate engineering multimillion dollar major project – but effect upon contractors, subcontractors,
and procurement resources. Depending corporate executives and audit committees suppliers, internal resources, operational
on the length of the project, factor in the expect no less. They rely on the project readiness teams, and other stakeholders.
impact of price escalation on commodities, team’s budget representations when the Obviously there can be consequent impacts
labour, and equipment. Also provide project is approved for execution. Key to the project’s financial expectations.
Project Advisory / Leadership Series 10 / Whitepaper 1 /04
Risk management is about identifying risks, within the direct control and influence of point estimates of activity durations are
both internal and external, to the successful the project team, while others are wholly used in the simulation instead of cost
completion and implementation of the outside the project team’s control. Good estimates. Even when experienced
project. Project risks, and their attendant stakeholder communication and risk schedulers and estimators are used in the
questions, can be characterised as follows: management practices can mitigate many preparation of the baseline determinative
project risks, whether internal or external schedule, it is often surprising to see the
»» Technical risk – How mature is the
to the project. results of a probabilistic schedule simulation.
proposed technology? What happens
On a multiyear major project, many months
if the technology fails? Project risks are typically captured in a
of schedule risk contingency may be needed
‘risk register’ that summarises both risks
»» Scope risk – Is the project scope defined to reach a 70 to 90 percent confidence
as well as opportunities for the project. The
adequately in sufficient detail? level. The project team must allow for this
risk register is a dynamic document that is
»» Schedule risk – Are activity durations possibility and carry additional schedule risk
updated throughout the project, as new risks
reasonable? What is our risk of extending contingency amounts in the project budget.
are identified and other risks are closed out.
the project? The register captures basic risk information Risks must be managed throughout the
»» Cost risk – Are cost estimates based needed to prioritise project risks. It is project life cycle. Many major projects get
on current market pricing? Have we also useful for assigning those individuals bogged down by delays and poorly planned
included allowances for undefined responsible for developing discrete risk design and engineering processes. The
project components, design development, response plans, monitoring them, and result is that the project team attempts to
escalation, and other contingencies? reporting on the risk status. accelerate the procurement and construction
phases, which is not always possible,
»» Human resources risk – Will we have The project team should determine the
especially where project milestones are
sufficient skilled resources when we cost impact of significant risks and
already very tight. Additionally, any attempt
need them? How do we retain them opportunities through quantitative cost
to accelerate the schedule beyond its
for the duration of the project? risk analysis. Probabilistic techniques such
optimal activity durations will result in
»» Regulatory risk – Have all regulatory as Monte Carlo Simulation2 are used to
additional labour, equipment, material, and
risks been defined? Are any permits or calculate the amount of reasonable risk
contractor costs. Delayed receipt of long-lead
approvals on the project’s critical path? contingency that should be carried in the
equipment is also common, requiring special
project budget. Knowledgeable project team
»» Safety and security risk – Is craft labour attention to procurement risk items
members develop three-point cost estimates
trained in construction safety procedures? in the risk register. Of course, delays and
to describe the best case, worst case, and
Is the project in a locale where there is cost impacts are the norm and not an
most likely case for individual risk items on
a significant security risk to personnel exception during the construction phase.
the risk register. When these cost estimates
and property? Construction risks such as adverse weather,
are run thousands of times in simulation
poor contractor/subcontractor performance,
»» Political risk – Is the project subject to software, the output is an estimate of
safety and environmental risks, resource
periodic funding approvals? Does the the cost risk contingency required for the
availability, and coordination among various
project have strong political approval project. Typically, construction owners elect
program components need to be carefully
and backing? to reserve contingency based on a 70 to 90
monitored and controlled.
percent confidence level.
Early risk planning and identification of
Without proper risk planning, identification,
risks during the prefeasibility and feasibility Similarly, quantitative schedule risk analysis
analysis, and monitoring, your major project
stages of the project are essential to develop may be used to determine a realistic project
is likely to experience significant issues.
a complete and accurate estimate of the completion date. In this case, a summarised
project’s time and cost. Some risks are version of the project CPM is used and three-
Project Advisory / Leadership Series 10 / Whitepaper 1 /05
5. Obtain buy-in from operations. Regional and divisional managers authority limits). The project sponsor
senior management also play a role, particularly when the project is a key position for successfully managing
will be built outside of the company’s your major project, and serves as the direct
Every corporate major project must have
usual area of operations. The investment liaison between the project team and
strong senior management buy-in to be
committee receives a complete budget executive management. The role of the
successful. Before the project is approved,
approval package to review in advance of project sponsor is to report on the progress
a complete project charter, project execution
the project team’s oral presentation of the of the project, discuss project risks and
plan, baseline budget, and baseline schedule
project for approval. The timing, format, challenges, and update senior management
must be prepared and vetted by the project
content, and procedure of investment regarding the project’s financial and other
team. Engineering designs to approximately
committee meetings are usually formalised. resource requirements. The project sponsor
35 percent completion, cash flow models,
is expected to alert senior management
financial analysis, and funding methods all Depending on the outcome of the
as soon as the project team forecasts a
must be evaluated and developed to the investment committee meeting, either
significant over- or under-run against the
point that the project can be visualised the project will receive full funding
approved project budget.
and built “on paper.” Most importantly, the approval – or the project team will have to
project must be strategically aligned with revise, plan, and provide the investment
the company’s and stakeholders’ current committee with supplemental information 6. Develop project specific policies
goals and objectives. The project must be at a subsequent meeting. Regardless of and procedures
relevant, considered to be the best use of the timing, the approval is meant to cover As any experienced project manager knows,
capital funds by senior management, and all of the project’s costs from concept to the success of a major project depends
designed to deliver tangible results. start-up. There should be no incremental of successful collaboration within the
or additional funding requests or ‘surprise’ extended project team. The extended project
Typically, the project is reviewed by a
scope change requests. team includes: the constructions owner’s
capital projects committee or investment
committee made up of executives from Once the project is approved by the team; joint venture partners; lenders;
various company functional units: including investment committee and the board of insurers; outside counsel; the engineering,
the CEO, CFO, strategic planning, finance, directors, a project sponsor is appointed procurement and construction (EPC)
legal, marketing, internal audit, sales, and (if required by the company’s delegation of contractor; subcontractors; suppliers and
others. Collaboration requires a robust set
of policies and procedures, clear roles and
responsibilities, and frequent communication
through approved channels.
Project management and »» Environment, health, safety, and Informed) chart; and a Division of
control categories security (EHSS); Responsibility (DOR) chart that includes
narrative job descriptions.
Project-specific policies and procedures »» Project management self-
should address the following project assessments; and All of the tools described above should be
management and control categories: »» Lessons learned. widely distributed and continuously updated
to reflect changes in the organisation or
Strategy, organisation, and administration
Schedule management project team.
»» Roles and responsibilities;
»» Schedule planning and development;
»» Communication planning; 8. Have frequent team meetings
»» Schedule updating;
»» Project infrastructure and systems; and Scheduling team meetings at an appropriate
»» Schedule change management; and
»» Document control and frequency will enhance collaboration and
»» Schedule integration.
records management. help maximise the benefits of having a
combined project team. Develop agenda
Cost and financial management 7. Assign project specific roles templates for all meetings based on subject
and responsibilities matter, and always identify specific team
»» Budgeting;
Your project team will function most members with action items that result from
»» Payment processing and administration;
effectively if each member understands a meeting. A standard set of weekly and
»» Project cost reporting; his or her specific roles and responsibilities. monthly meetings should be on the calendar.
»» Estimating/forecasting; In construction, as in other industries, what
For specific interest groups (such as
appears to be self-explanatory is actually
»» Contingency management; engineering, procurement, construction;
more complex when pen goes to paper.
»» Cash flow reporting; and project controls; project accounting) and
Develop the organisational chart so that all
reporting, limit the attendance to team
»» Value engineering. the key players and third-party resources
members within the specific functional areas.
are clearly and fully identified, and include
This will focus the participants’ attention
Procurement management clear indication of hierarchical reporting
on activities within their own sphere of
»» Procurement planning; relationships. Names, positions, and
responsibility. Conversely, have your project
telephone/e-mail contact information
»» Solicitation and source selection; director schedule regular monthly meetings
should also appear in the organisational
»» Contracting; with his or her senior project managers to
chart. In addition, develop narrative job
discuss project coordination, cross-functional
»» Contract administration; descriptions and a responsibilities listing
issues, and risks as a group.
for every resource appearing on the
»» Materials management; and
organisational chart. A “short form” of the Remember to schedule regular meetings
»» Contract closeout. narrative job description should be published with contractors, subcontractors, suppliers,
and distributed to all project team members. and other third parties to share information
Project controls and risk management
about progress, safety and security, and
Terminology used in the job descriptions
»» Change order management; coordination of work. Every contractor
should be consistent, and roles and
»» Risk management; should have the ability to contact his or her
responsibilities should match those
contract administrator any time to clarify
»» Design standards and specifications; identified in the project-specific policies and
work scope, change orders, pricing,
procedures. For clarity and completeness,
»» Regulatory compliance; schedule, etc.
we recommend you have both a RACI
»» Quality control and inspection; (Responsible, Accountable, Consulted,
CONCLUSION
You cannot successfully manage a major procedures, assigning roles, and conducting
project simply by drawing on industry experience, effective meetings.
following project management principles, and
In Part 2 of this series, we will discuss a second
applying technology. A critical aspect of success
key concept – how to effectively communicate
is an effective planning and organising effort.
and practice time-tested controls over cost,
That is the first key concept which has schedule, scope and quality. No single project
been outlined in Part 1 of this Whitepaper. director or manager can deliver a successful
It encompasses team assignment, delivery major project on his or her own. It is a team
strategy, estimating, risk management, effort; along with the input, advice, and consent
buy-in from leadership, policies and of appropriate stakeholders.
Project Advisory / Leadership Series 10 / Whitepaper 1 /07
KPMG’s Project Advisory services are KPMG applies leading concepts Project Advisory Services can assist
objective, professional approaches to and practices, supported by: organisations to generate significant
managing the many risks associated › Experienced practitioners cost savings by minimising poor
with major change: risks that involve selection decisions, costly overruns,
› Recognised best practices
complexity, technology, governance, misalignment with business needs,
selection and management of vendors › Effective tools and templates poor quality deliverables and
and partners, implementation of › International standards failed projects.
solutions and acceptance of change › Built-in knowledge transfer
throughout the organisation.
Contact us
kpmg.com/nz
© 2014 KPMG, a New Zealand partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative (“KPMG International”), a Swiss
entity. All rights reserved. Printed in New Zealand. The KPMG name, logo and “cutting through complexity” are registered trademarks or trademarks of KPMG International.
The information contained herein is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavour to provide accurate and timely
information, there can be no guarantee that such information is accurate as of the date it is received or that it will continue to be accurate in the future. No one should act on such information without
appropriate professional advice after a thorough examination of the particular situation. 00403