Professional Documents
Culture Documents
net/publication/286920184
CITATIONS READS
3 1,161
3 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Eric Jackson on 15 December 2015.
ABSTRACT
Miscellaneous Surface Equipment:
Perry Slingsby Systems is upgrading the T750 Workshop and stores containers provided: both 6.1m
Trenching System originally supplied to Canyon A0 rated standard ISO offshore containers,
Offshore in 2003 to include a rock-cutting wheel. This interconnecting cables and hoses, vehicle charge cart
wheel will extend the trenching capability to cut and winch HPU.
trenches 8” wide by 24” deep through rock with a UCS
of 8MPa at 80 m/hr, and will allow the trencher to
perform rock cutting and water jet trenching PROJECT SPECIFIC REQUIREMENTS
simultaneously under a single subsea vehicle
configuration. Subsea 7 / Petro SA have a requirement to in install 3
off in-field umbilicals utilizing the vessel ‘Navica’,
This paper will describe, in some depth, the principle offshore South Africa.
features of the upgraded trencher and methods of
calculating predicted trenching performance. Subject to A new pipeline is to be laid adjacent to the umbilical
availability - the field results will be compared with the route and options for the protection of the post laid
performance predictions. umbilicals include displacement of the umbilical towards
the pipeline to afford cover for the umbilical from the
pipeline, alternatively the umbilicals are to be buried. If
INTRODUCTION the burial option is preferred, the seabed characteristics
are such that a proportion of the route can be jetted
The T750 advanced trenching system was delivered by with conventional water jet based trenching tools of the
PSS to Canyon Offshore UK Ltd., in August 2003. The type originally supplied with the T750. There are 4
complete system, as delivered, comprised; routes to be trenched, having a mixture of jet-
trenchable soils and rock. A total of approximately 50
Subsea Vehicle Assembly: km of the routes to be trenched have been identified as
ROV based system configurable for trenching being unsuitable for water jet trenching. For these
operations to a maximum of 1500msw in free-fly, pipe / sections it will therefore be necessary to deploy
cable – riding, tracked and skid modes. Water jet alternative trenching tools to achieve the desired
powered primary trenching tooling system - mounted trench.
mid-vehicle and including three pairs of interchangeable
cable and flow line burial tools of lengths 1m, 2m and There are three umbilicals to be trenched:
3m mounted on a deployment mechanism to achieve
burial depths and accommodate trench widths over a Main Umbilical, OD = 143.8mm
nominal range of 120mm to 750mm. Aft mounted Infield Umbilical, OD = 137.6mm
tooling – comprising water jet powered eductor tools Buoy Umbilical, OD = 116.5mm
interchangeable with water jet powered backfill tools.
The design minimum bend radius for the umbilicals for
Surface Control & Power Systems: trenching purposes has been identified as being 3000
Pilot, Co- Pilot, Tooling and Auxiliary control consoles, to 5000mm, the desired trench depth is specified as
transformers and power distribution panels mounted 500mm.
within a 6.1m standard A0 rated ISO container. Primary
power system including variable speed drive system Water depth is specified as 300m maximum for the
mounted within a 9.1m A0 rated ISO container. umbilicals installation project.
Umbilical & Winch: The current / projected work schedule for the T750 is
1800m of 58mm diameter, power and fiber armored lift full utilization offshore until end of September 2006,
umbilical provided for operations to a maximum depth with the exception of a period on the beach in Houston
of 1500m, supplied with 20m coverage of Linksyn during March / April 2006 for essential maintenance /
umbilical flotation. Also provided – hydraulically flotation refit. Any upgrade work required on the system
powered umbilical winch for storage, deployment and to make ready for rock trenching would need to be
recovery of 1800m of armored umbilical to a maximum conducted during November / December 2006, the
diameter of 62mm at line speeds between 22m/min and location for the upgrade work being Aberdeen,
30m/min. Scotland.
PSS presented their preliminary thoughts and concepts It is understood that the preferred configuration for the
based around proposed modifications to the existing vehicle during either jet or rock trenching shall be track
subsea vehicle system through the addition of a mode. Careful consideration is to be given to the
mechanical cutting tool mounted aft to supplement the loading and trim effects of the additional upgrade
existing water jet trenching tools plus product guide equipment on the vehicle structure and the ability of the
pathway passing over the top of the vehicle and a track systems to accommodate any increased weight.
product loading / unloading manipulator. This is especially pertinent if an optimised solution
between jet and rock cutting in a single configuration is
DISCUSSION OF SUITABLE UPGRADE CONCEPTS to be achieved.
In addition to the project specific charac teristics Loading and unloading of the product into the T750,
identified above, PSS identified the following resultant prior to and at the completion of a trenching run is
design requirements and critical interfaces which must another critical interface / process which requires
be taken into consideration when determining the careful consideration. PSS have previous experience of
suitability of upgrade options: providing product loading and unloading equipment for
similar applications and have found that the use of a
Umbilical / Cable Path marinised industrial off-the-shelf knuckle boom crane
offers a very efficient, effective and economical
Given the diameter and MBR of the products to be solution. Previous trenching equipment supply projects
handled and buried by the trencher, an essential design on which PSS have successfully applied this approach
constraint is to ensure that at no point through the include the GATOR I & II and HDCP1500 heavy duty
guiding or burial of the product is the MBR plow. The latter vehicle used a marinised Palfinger
compromised. To ensure this, the product path through PK10000MA knuckle-boom crane mounted on the
the trencher must include a positive guiding and vehicle structure and operated remotely from the
support mechanism sufficiently robust to capture, surface via the vehicle’s control system, to successfully
deflect and retain the product along the desired path load and unload interfield umbilicals during a number of
from seabed to the bottom of the newly cut trench, trenching campaigns offshore Norway and UK, 2001.
without damaging the product in anyway. Therefore at
no point anywhere in the product guide / trencher The crane can be mounted on the vehicle structure in
interface must the product be deflected against a such a position that every point on the product path
guiding surface with a radius of less than the through the vehicle can be accessed to ensure that the
constraining MBR. product is properly loaded or unloaded. A typical end
effector used on the crane to handle the product
Burial Depth / Trench Characteristics comprises an off-the-shelf log handling claw set
modified to include specially profiled UHDP guide
The specified burial depth for the product is specified as shoes fitted to the jaws to prevent damage to the outer
a nominal 500mm (20”) to bottom of trench. A parallel sheath of the product during handling.
walled trench profile, i.e. vertical trench walls with no
slope is acceptable. In order to account for undulations,
etc., in the seabed during trenching a nominal ‘safety
margin’ of 250mm has been added to the target trench
depth by PSS. Therefore the rock cutting tool
deployment mechanism fitted to the T750 shall have
the capability of deploying the cutting tool to a
maximum trench depth of 750mm (24”). The trench
width is to be suitable to accommodate the diameter of
the product plus a nominal clearance, the maximum
product diameter being 143.8 mm (5”) the trench width
is to be 203mm (8”).
FWD AFT
Vehicle Configuration
By routing the product above the vehicle, the product is The outline sequence of operations for loading /
kept clear of the cutting zone and remains completely unloading and handling the product subsea, using the
visible during loading / unloading and the entire upgraded T750 system would be as follows:
trenching process, Any chance of interference between
the rock wheel and the product is thus eliminated. a). The T750 is deployed from the surface vessel via
the lift umbilical, through the water column in the
conventional manner.
b). The T750 is landed-out on the seabed such that the
product to be trenched lays at a nominal distance clear
from the STBD side of the T750.
e). The pilot is then able to rotate the crane about its
base to the MID and AFT positions of the vehicle and
repeat the product lifting, positioning and release
sequences, ensuring that the product is fully loaded
through the entire product guide trough.
Crane
Advance pentrtn
Rate f(X/Y) Rock
Figure 2: Rock Wheel Drive System Relationships
Electric
Motor pick
rpm flow rpm rpm speed
cc/rev cc/rev ratio radius
Flushing System
We performed an analysis to see if the spinning action
of the wheel was adequate to flush the cuttings out of
the trench. The wheel pulls water around its perimeter,
acting as a pump. The pump is loaded due to the drag
of the fluid and the acceleration and lifting of the
cuttings out of the trench.
The analysis focused mainly on the region of the rock
wheel in which the picks are in full contact with the rock,
as shown in Figure 3. This region is shaped as a
section of torus with a rectangular cross section,
Figure 2: Cut Volume Profile bounded on three sides by the solid rock trench walls
and floor, and on the upper side by the rim of the rock
6
0.03 upgraded system was originally specified as:
PROGRESS