You are on page 1of 13

OTC 18923

Design and Operation of an Extractable Caisson Foundation for Offshore Structures


M. Hesar, Subsea 7 (London UK)

Copyright 2007, Offshore Technology Conference


During installation the platforms will be placed on four
This paper was prepared for presentation at the 2007 Offshore Technology Conference held in pin-piles, pre-installed one under each corner leg. These pin-
Houston, Texas, U.S.A., 30 April–3 May 2007.
piles replace the conventional mudmats that were used to
This paper was selected for presentation by an OTC Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
support the Phase 1 and 2 platforms in the project for on
presented, have not been reviewed by the Offshore Technology Conference and are subject to bottom stability. The reason for this change in Phase 3 was a
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Offshore Technology Conference, its officers, or members. Papers presented at combination of factors including, soft soil conditions and
OTC are subject to publication review by Sponsor Society Committees of the Offshore
Technology Conference. Electronic reproduction, distribution, or storage of any part of this
excessive wind resistance on the large sized mudmats during
paper for commercial purposes without the written consent of the Offshore Technology towing on barge to site.
Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not
more than 300 words; illustrations may not be copied. The abstract must contain conspicuous The eight pin piles were installed by deploying two pieces
acknowledgment of where and by whom the paper was presented. Write Librarian, OTC, P.O.
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
of temporary structures, the Pin pile Installation Frame (PPIF)
and Locator Arm (LA), see Fig. 2. Both these structures were
Abstract supported on circular caisson foundations (referred to as
This Paper describes the development and first successful mudmats for simplicity in the remainder of this paper). At
application of a caisson foundation providing a reliable and DUQ platform location the PPIF was docked onto the pre-
easily extractable foundation solution for offshore structures. drilling template and placed on the seabed first. The LA,
The specific structure described is a two piece template called which incorporates the pin pile driving sleeve, was then
Pin Pile Installation Frames (PPIF, 400te) and Locator Arm connected to each of the four faces of the PPIF structure to
(LA, 275te). Pin piles are typically used as alternatives to locate the position of the corner pin piles in turn, see Fig. 1.
mudmats for temporary support of jacket structures in deep This paper presents the results and supporting geotechnical
water soft clay sites, where the required mudmat area would calculations for the mudmat foundations of PPIF and LA
be prohibitively large. The PPIF and LA were successfully structures. The nominal water depth at the site is 175m.
used in May 2006 to install eight 96” diameter, 100m The submerged weights of PPIF and LA are 200.6 tonnes
penetration pin piles for two jackets in BP’s Gunashli field in and 141.8 tonnes, respectively. Penetration of the skirted
175m water depth in the Caspian Sea. The piles were installed mudmats into seabed will take place under the self weight of
well within the ±150mm lateral and vertical positional each structure. Extraction of the mudmat foundations from
accuracy and 0.1° inclination tolerance. seabed were to utilize a passive suction (PS) system with an
The Paper illustrates how a diffuser system utilising a active water injection system (AWIS) forming a backup
geotextile product routinely used in onshore construction system. In the PS system the mudmats will be subjected to an
practice, in conjunction with a passive suction system was uplifting force (crane lift) and water will be sucked into the
developed and used to provide a simple yet effective means of cylindrical cavity through suction ports as a result of negative
avoiding the soil adhesion problem. 1:20 scale 1g physical pressures developing there in response to the applied load. In
model tests and laboratory interface friction tests on the the AWIS system water is injected into the cylindrical cavity
special paint system for skirts are discussed. The philosophy below the mudmat base to piston the mudmat out of the
developed for sizing the capacity of passive suction system seabed. Both systems comprise valved penetrations on
and the back-up active injection system is explained. Also individual mudmats. To avoid the well known adhesion
described are the nonlinear geotechnical FE analyses, which problem between the mudmat base and seabed clay and to
made it possible to justify minimizing the size of caisson ease the breakout of mudmats during lifting off from the
foundations beyond Code factor of safety to ensure extraction seabed all mudmats are provided with a special layer of
within 5 minutes, whilst maintaining the required system Terram geotextile underneath the base plate.
reliability.
Review of Previous Applications of Suction
Introduction Foundations
Azerbaijan International Operating Company (AIOC) is The effectiveness of caisson foundations for permanent
developing the ACG field in the Azerbaijan sectopr of the support of offshore structures has been well established. In
Caspian Sea. Phase 3 of the project involves installation of recent years caissons have been used to provide foundation
two platforms in the Deep Water Gunashli (DWG) field, the support to a variety of offshore structures, ranging from
Drilling/Utilities/Quarters (DUQ) platform and the concrete gravity bases1 and steel jackets2,3 to subsea facilities4
Production/Compression/Water Injection/Utilities platform and pipelines; in both clay and sand seabed conditions.
(PCWU), see Fig. 1. However, in order to avoid the notoriously protracted
2 OTC 18923

“breakout” phenomenon during extraction5, it is desirable to Soil Conditions


have a foundation system that can be extracted from the The surface layer of gravely shelly sand was encountered in
seabed swiftly at the end of normal service life of the facility all of the core locations and the majority of CPT locations. It
or end of operation6. Examples include all types of fixed comprised a very thin, 1 to 10cm, locally up to 20cm thick
structures supported on shallow foundations, mobile offshore layer of shelly fine to medium sand and fine to medium
production units used for exploitation of marginal fields, gravel.
jackup rigs, or heavy structures deployed repetitively on the Beneath the sand layer a relatively uniform calcareous clay
seabed for some subsea operation. layer was encountered down to at least 10m. The clay has a
shear strength of 8kPa at the surface, increasing uniformly to
Present Design 35kPa at 10m. Laminations of organic matter and pockets of
The foundation design comprises four skirted and one un- silty fine sand occur throughout the deposit investigated.
skirted mudmats for the PPIF and 2 skirted and one un-skirted
mudmats for the LA, Fig. 2. All mudmats are 6.2m in diameter Design Soil Parameters
and depth of skirts is 0.75m. The un-skirted mudmat of the Fig. 3 shows the combined plots of undrained shear strength
PPIF is termed the “5th” mudmat (towards centre of PPIF, not profiles. The results of laboratory tests are also shown
shown in Fig. 2) and that of the LA is termed the “Apex” superimposed on these plots. The characteristic strength
mudmat. The skirts were painted with a special friction profile revealed from these plots is as follows:
reducing paint system to minimise adhesion between the skirts
Su = 8 + 2.7 z (Su units in kPa)
The underbase of all mudmats was lined with a geotextile
product (Terram) which acts as a diffuser to distribute and The presence or otherwise, nature, depth, and degree of
equalise the water pressures. Both active injection and passive variability of the top gravely sand layer are of special
suction systems for extracting the mudmats were designed. importance for the present mudmats. All the core samples
Separate suction ports were provided for the active and were split and photographed prior to logging. A typical
passive systems. A programme of 1:20 scaled model tests photograph of the cores is shown in Fig. 4. Permeability
together with a set of interface friction tests was carried out by values of the surficial granular layer are in the range 2.25x10-
Fugro Limited in the UK. These tests revealed that the Terram 8 and 4.0x10-4m/s. If it could be guaranteed that this surficial
diffuser is very effective in eliminating the underbase layer would be present at the time of pin-piling operations,
adhesion during the removal operations, both with the active then there would be no need for the geotextile diffuser layer
water injection and passive suction schemes. The skirt lining the underbase of the mudmats. However, prior to pin
adhesion -value obtained from the interface tests between pile installation operations at least one well was to be drilled at
clay and painted skirt surfaces is around 0.37. DWG and it was likely that significant drill cuttings would be
Skirted mudmats have 4 number 160mm diameter passive present on the seabed spread over the site. For these reasons
suction holes, except for the two Row-1 mudmats of the PPIF, the high permeability benefit from the insitu granular layer
which have 2 additional 14” holes. These served to improve could not be relied upon and hence design of mudmats
the breakout time from seabed in the final lifting of the PPIF assumed cohesive seabed conditions.
at the end of pin-piling operations. The removal systems were The clay sensitivity with depth obtained from a number of
designed to release the skirted mudmats from seabed in less different tests and instruments is variable, with an average
than 30 minutes. With the contingency margins adopted the value of 3.0 over the deopth of interest. Atterberg Limits
actual breakout times turned out to be between 5 to 10 within the depth of interest is reasonably uniform and
minutes. indicates an average plasticity Index of around 27 in the upper
3.5m.
Site and Soil Conditions
DUQ and PCWU Jackets are located at the Deep Water Combined Bearing-Sliding Capacity
Gunashli site. The seabed is gently sloping, with a level The combined bearing-sliding-moment capacity of shallow
difference across diagonal legs of each jacket of about 1m. foundations typically falls on the surface of an egg-shaped 3D
Apart from a deep borehole site investigation campaign by envfelope7. In the absence of moment loading, the envelopes
Fugro in 2004, aimed at the design of platform main pile degenerate to a 2D cross-section of the 3D version. Both
foundation, a shallow site investigation was performed by conventional bearing capacity envelope methods8 and
Andrew Survey, also in 2004. This survey comprised nonlinear finite element analysis techniques were used in the
piezocone penetration testing (PCPT) to 10m, piston/gravity design of mudmats. A load and resistance factor design
cores capable of penetrating up to 6m depth and box cores. methodology was adopted in accordance with API LRFD9.
The aim of this SI was to provide a better definition of the Factored loads generated from structural analysis of the PPIF
shallow soil conditions both in terms of strength parameters and LA structures were used. In the FE analyses the
and lateral variability. During this site investigation a characteristic soil strength was derated by the appropriate
relatively large volume of soil was recovered from the site by material resistance factor. One of the most important aspects
utilising piston core tubes to be used in a medium sized model of the design of these mudmats is the consideration of the
soil bed for scaled model tests discussed later. A programme “breakout” phenomenon. The mudmats need to be kept to a
of laboratory soil testing was conducted following the field small size in order to reduce weight and facilitate easy release
work on the piston samples recovered. from the seabed, while at the same time be able to carry the
design loads without failure or excessive settlement.
OTC 18923 3

Foundation Loads The undrained internal friction angle, u was set equal to zero
The maximum load on the 5th mudmat occurs when the PPIF and a perfectly plastic post-yield behaviour was selected.
was being installed over the DUQ drilling template. At this Therefore, the yield and failure surfaces were coincident
stage the weight of the PPIF was supported on the tops of the implying an associated flow rule. The Poisson’s ratio was set
two template support piles, together with the 5th mudmat equal to 0.49 to simulate no volume change conditions for
forming a three-point support. The factored load on the 5th undrained clay.
mudmat for this condition was 1472kN. Similarly each time The steel structure of the mudmat was modelled with shell
the LA was being set-up its weight was carried on a three- elements. Fig. 7 shows the steel structure of a typical skirted
point support, the two claws at the PPIF end and the Apex mudmat. Photographs taken at the site during fabrication are
mudmat at the pile sleeve end. The load on the Apex mudmat presented in Fig. 8a and 8b. Distribution of contact soil
for this load condition was 1100kN. pressures against skirts as well as bending moments and shear
forces were obtained from this model. For the un-skirted
Reaction loads on skirted mudmat supports were produced
mudmats the skirt elements were simply removed from the
from the SESAM structural model. The worst scenario loading
model, leaving a flat base.
on the skirted mudmats occured on one of the aft mudmats of
Combined vertical and horizontal loads were applied to the
the LA when the pile was being stabbed into the sleeve cone
centre node of mudmat at the top level of web stiffeners and
(and inadvertently landed on the edge of the cone). For this
ramped up proportionally to twice the maximum design values
load case 25% of the pile weight was applied statically onto
in order to define the full load-displacement response of the
the pile cone top rim in the structural analysis. The horizontal
mudmat.
and vertical mudmat reaction components for this scenario
The mudmat skirts were coated with friction reducing
were 123kN and 1874kN, respectively.
paint to make the extraction of mudmats easier, and the
laboratory interface tests (discussed later) showed that the
Conventional V-H Stability Envelope Results
Bearing capacity analyses were performed in accordance with prevailing -factor with the specified paint system was of the
DnV8 recommendations for linearly increasing soil shear order 0.37. In order to account for contact and desired -factor
strength with depth. Ultimate and allowable bearing capacity along skirt interface, a 3D FE model was developed which
envelopes (V-H diagrams) were produced for skirted and un- allowed for large-sliding frictional contact between the outer
skirted mudmats. V-H diagrams for both skirted and un- face of skirts and soil. A finer mesh grading in the vicinity of
skirted mudmats assumed a ‘rough’ base condition. the mudmat foundation was used together with a lining of
Fig. 5 shows the envelopes for un-skirted PPIF 5th and LA special infinite elements outside of this core mesh. In this way
Apex mudmats together with the maximum load conditions. It a relatively fine mesh of well proportioned and shaped
can be seen that for the mudmat diameter of 6.2m the elements captured the elasto-plastic behaviour of the soil and
conventional analysis methods predict a vertical bearing contacting surfaces with good accuracy, while not
capacity with an available factor of safety (FOS) in the order compromising the contribution of the rest of the soil domain.
1.21, less than the API LRFD required value of 1.5. A typical output showing contours of vertical displacement
Similar envelopes for the skirted mudmats showed that for the at the end of the analysis run with the latter model is shown in
latter case even the ultimate capacity of the mudmats would be Fig. 9. The classical “displacement bulb” shapes can be seen,
exceeded. and they are continuous across the boundaries between the
The above results suggest that in the conventional sense finite and infinite element meshes.
the mudmat area is not sufficient. The conventional bearing A set of three load-displacement curves obtained from the
capacity formulae make a number of simplifying assumptions, above model are shown in Fig. x10. The top curve shows the
chiefly among them is the assumption of a uniformly loaded results with an upper bound estimate of undrained Young’s
area, i.e. a flexible foundation with uniform pressure with no modulus profile varying between 200*Su at seabed to 500*Su
soil containment of skirts. This shortcoming, together with the at 16m below mudline. The -factor used on skirt interface
restrictions imposed by seabed lifting requirements was 0.5. For comparison the analysis was repeated with the
(desirability of smaller mudmats to make breakout from the lower bound estimate of Young’s modulus profile varying
seabed easier) motivated the use of non-linear FE analysis. between 100*Su at seabed to 400*Su at 16m below mudline.
The results obtained from FE analyses are discussed below. The results shown in Fig. x10 suggest that a minimum
vertical capacity of at least 2000kN is obtained. At
Finite Element Model and Results approximately 2000kN load the curves begin to flatten and
A number of finite element models were used to analyse the this load level was treated as ultimate load. Load levels
bearing capacity, settlement and stiffness of the mudmat beyond 2000kN conservatively ignored, since element
foundations. Fig. 6 shows a typical deformed shape contour distortions may mean the results are unreliable beyond this
plots of the early 3D FE model used to derive foundation point. Therefore according to the Load and Resistance Factor
lateral, vertical and combined capacities and stiffness for Design philosophy an additional margin of safety of at least
skirted and non-skirted mudmats. Due to symmetry, in the 6% exists.
subsequent analyses only one half of the full domain was
analysed. In the absence of any soil test results which might Foundation Settlement
have provided parameters for an advanced soil constitutive During setting up of the PPIF a substantial proportion of the
model, the soil was represented with the Mohr-Coulomb structure weight is carried by the 5th mudmat for a short
constitutive model, calibrated for undrained clay response. period until the skirted mudmats were jacked down. Once the
skirted mudmats was embedded the 5th mudmat was extracted
4 OTC 18923

and the PPIF structure will be levelled. Similarly for the LA DAYS AFTER INSTALLATION 2 4 7 14 30 60
the Apex mudmat supported the sleeve end until the aft
mudmats were lower to the seabed and jacked in to take up Consolidation Settlement (mm)
their share of the load. For these conditions the immediate
elastic settlement of the un-skirted mudmats was of
importance. (Upper Bound) Consolidation
During operation the skirted mudmats were expected to Settlement
10 15 20 23 25 30
undergo some degree of consolidation settlement.
Consolidation is a very slow process in clays due to their soft (Lowe Bound) Consolidation
skeleton and very low permeability. These time-related Settlement
consolidation settlements were calculated using an FE model 0.5 1 1.2 3 4 8
described below.

Immediate Settlements From Elastic Theory Foundation Stiffness


Elastic settlements of the 5th and Apex mudmats during setting Foundation stiffness was calculated from both the 3D finite
down on the seabed were estimated using the conventional element model and conventional methods provided in
elastic theory hand calculation10. For the high estimate Reference 8. In Fig. x13 the results of horizontal load against
stiffness estimate Ir values selected were 100 at mudline and horizontal displacement are compared for a mudmat with and
500 at 12.8m depth. Fig. x11 shows the profiles of predicted without skirts. The effect of skirts is to double the horizontal
elastic settlement of the PPIF 5th mudmat with depth below sliding capacity as well as increasing the lateral stiffness by
mudline for the low estimate and best estimate rigidity index about 40%.
values under the loads expected. In general the initial stiffnesses from FE analysis are
higher than DnV results. The results from both sets of analyses
Consolidationn Settlements using Coupled FE are summarized below in Table-2:
Analysis
Simulation of time dependent consolidation effects are best Table-2 Mudmat foundation stiffness values
performed using the FE methods, since closed form solutions
are only available for specific conditions such as 1-D cases ABAQUS ABAQUS DNV
and cannot model arbitrary shaped foundations and boundary (INITIAL) ( AT 50%ULTIMATE (REF. 8)
conditions. An axisymmetric FE model was used for these LOAD)
coupled stress-pore pressure analyses. In this model the
(kN/m)
mudmat was represented with axisymmetric shell elements.
Free drainage was allowed to take place from beneath the Horizontal 39,000 29,000 34,000
mudmat base plate as well. This simulates the presence of the Vertical 70,000 60,000 51,000
diffuser with the passive suction valves being left open.
Consolidation was simulated for a hypothetically long time of
33 years in order to obtain the theoretical final settlement as a
Jack-to-Mudmat Connection Design
reference value. Upper and lower bound estimates of soil
When the LA mudmats approach the sloping seabed with an
stiffness and permeability coefficients were used to obtain a
attitude relative to the seabed, the skirt penetration is
range of predicted consolidation settlement. Elastic parameters
essentially axially symmetric. However once the base plate
were the same as those used for elastic settlement calculations.
starts to contact the seabed the eccentric loading causes a
Permeability coefficients were obtained from the results of a
bending moment about the jack connection point.
few oedometer tests that were performed on specimens from
the top layers as part of the deep borehole SI.
Skirt Frictional Resistance
Typical consolidation settlement-time curves for the PPIF
The penetration and extraction resistance of mudmat skirts
5th mudmat with the high and low soil stiffness estimates are
were assessed following the well established NGI
shown in Fig. x12. The results of consolidation settlement
methodology11. In this method the unit skirt friction, f, is
prediction for the PPIF skirted mudmats under still water loads
calculated as:
after a selection of time periods relevant to the installation
activities are listed in Table-1 below. The static load for this
case is 1232kN. Consolidation settlement values have been f = Aw . DSS . SuDSS
rounded up to the nearest 5mm for the upper bound case. The
lower bound settlement estimates are negligible. Where:

Aw = Skirt Wall Surface Area in contact with soil


DSS = -factor for skirt-soil interface
SuDSS = Undrained shear strength in Direct Simple Shear
Table-1 Consolidation settlements after a selection (DSS) test
of time periods following installation
In the absence of any DSS test data, a typical correlation
factor between triaxial compression and DSS strengths of 0.8
OTC 18923 5

was used. The -factors for extraction were selected using the where, GMF is the Gross Mudmat uplift Force. It is the
relation: EMF that causes a differential suction head to develop across
the Terram layer and hence suck the water into the mudmat
 = Ct (1/ St) chamber allowing it to be released. In Fig. x16 curves have
been plotted for different size of total passive openings in the
Where: mudmat. All mudmats have four passive holes of 160mm
Ct = Clay thixotropy factor diameter each (equivalent to one 12” diameter opening),
St = Clay sensitivity except the Row-1 mudmats of PPIF which have an additional
two 12” holes (i.e. total of 3x12” opening size, the brown
A thixotropy factor of 1.2 was selected following the curve).
recommendations in Ref. 15 for estimated time lapses between As an example, to extract the Row-1 mudmats in a time of
setting up and lifting off of the PPIF of the order one month 1.1 minutes, an EMF of 500kN would be required. Therefore
(exaggerated to account for a breakdown scenario). The - for total skirt frictional resistance of 10te (at the start of
factors calculated were 0.33 for penetration and 0.4 for extraction) and mudmat self-weight of 10te, the gross upward
extraction. force required to extract the Row-1 mudmats would be

Sizing Passive Suction System Capacity 500kN = GMF -100kN – 100kN,


Basic data from the standard Terram data sheet was used in
developing the Passive Suction system. A spreadsheet giving a Gross Mudmat uplift Force of 700kN. The Green
program was used to perform the calculations. The essential (uppermost curve) in Fig. x15 depicts the force-time
steps in the calculation process are summarized below: relationship for all the other skirted mudmats. For these
mudmats if the same constant force of 670kN was to be
applied, they would be completely extracted in 3.3 minutes
Base area A
Sizing Active Injection System Capacity
The criterion for designing the size of active injection system
was to limit the required time to less than the practical time of
d 30 minutes. The design pump capacity was quoted at
120m3/hr. The total chamber volume of mudmat to fill is 22.5
m3. Hence it was expected that the pumps should be capable
of extracting the mudmats out in 11 minutes. In practice
1. Uplift Force is F (assumed constant)
piping would occur in the soil shortly before the skirts were
2. Suction Pressure, P = F/A
completely out, especially when the skirt tips rose to the level
3. Suction Head, h = P/9.81
of granular layer on the seabed. If this was to happen water
4. Suction-Flux, q = qTerram . h/hTerram
injection would be continued, while the structure was lifted
(Units: m3/s per m2 of Terram)
out by the crane.
5. Volume Increment, V = A ( dn+1 –dn)
The final design of the lifting system proved tom be
6. Upward Displacement Increment, d governed by the response characteristics of the derrick barge
7. Time to Lift by d (and fill volume V), in the design sea state. This entailed incorporation of a
t = V/(q x A valves) Cranemaster damper element into the lifting line in order to
8. Extraction Time, T = t . V/V damp out the “shock” forces. In the actual field operations the
9. Extraction Speed, S = d/T passive system performed perfectly adequate and the active
system was not needed. The active injection system was only
used as an additional aid under the unskirted mudmats during
Passive + Active Injection Case, t = V/[(q . Avalve) + Qactive]
lifting off of each structure clear of the seabed to give a
precautionary protection to the Cranemaster damper element.
The latter Passive + Active Injection Case was for the final
lift off of the PPIF from seabed at the end of operations, when
Model Tests on Extraction Resistance
only the two Row-1 mudmats were embedded. Water was to
Due to the novel nature of the concept used to overcome the
be actively injected while the passive suction holes were open
mudmat sticktion problem a series of 1:20 laboratory scaled
to allow the mudmats to be released from seabed easier.
model tests were carried out by Fugro Ltd in the UK. In
For typical skirted mudmats extracted by retracting the
addition, a series of interface friction tests were also
jacks Fig. 15 shows the relationship between Effective
performed by Fugro Ltd to assess the range of likely values of
Mudmat Forces (EMF) and time required to completely
remove the skirts from soil. The EMF is the net uplift force -factor that might develop between the painted surfaces of
which is required to cause the passive flow into the expanding skirts and clay. These interaface tests are described and
chamber under the mudmat as it moves upwards: discussed later.
The prime objective of these tests was to verify that the
EMF = GMF – (mudmat self-weight) – (skirt friction) Terram-lined base plate separated from the seabed as the
design intended. Both Passive Suction and Active Water
Injection Systems were tested. The following means of
6 OTC 18923

mudmat release mechanism from seabed were simulated in the loading motor and after an extraction of 6-7mm the rate
model tests: reduced. The maximum underbase suction recorded in test 12
 Base Plate fitted with Terram lining and provided was 14kPa, compared to 5.5kPa in the other passive tests. This
with active or passive holes observed dependence of pulling force on uplift displacement is
reproduced by the analytical predictions presented later in the
 Base Plate with no lining and provided with passive paper.
holes
Three possible states of seabed condition were considered Discussion of Active Tests
in the test programme: In two of the tests the active injection system with the most
onerous conditions of structure self weight (20kg and 55 kg
1. Insitu conditions, where the seabed is covered by a surcharge) sitting on the mudmat with bare clay seabed was
nominal layer of granular material, simulated by a simulated. Even in these tests the diffuser element (Terram)
3mm thick layer of sand allowed the injected water to be distributed under the base
2. Seabed being covered by an impermeable layer of plate and the mudmat was lifted off the seabed. In all the
drill cuttings, simulated by a 2mm thick layer of active injection tests piping occurred generally prior to
bentonite slurry. complete extraction of the skirts. However, in these tests
3. Bare clay, corresponding to the condition of a seabed piping occurred earlier than active tests without surcharge.
being jetted to remove drill cutting materials and in The piping was severest in test with 55kg of surcharge.
the process removing the granular layer as well.
Soil Skirt Interface Model Tests
In all, four separate models were milled from single pieces The skirt surfaces on both inside and outside of the mudmats
of Aluminium alloy (dural) all to 1:20 geometric scale. The were painted with friction reducing paint. A two-coat paint
model skirts were 38mm deep and 0.75mm thickens. In order system was used to give a low friction finished surface
to keep the correct scaling, painting was avoided. Instead, the condition. A number of interface tests were performed by
model skirts were polished to a smooth surface, except for one Fugro Ltd. on three different surface conditions:
case where rough skirts were simulated. The smoothing was
intended to simulate the friction reducing effect of paint on 1. The smooth Aluminium with three different
skirts. Three pore pressure transducers were used to monitor consolidation times: 23, 89 & 963 minutes.
the underbase cavity water pressure. A selection of 2. Paint system 1- only first coat applied on a steel
photographs taken during the model testing programme is specimen
shown in Fig. 16. 3. Paint system 2– both coats applied on a steel specimen
The tests proved that the presence of Terram ensures a
clear and easy separation of the mudmat from soil in both the Surface condition of the smooth Aluminium alloy (Dural)
active and passive cases and in all three seabed soil conditions was as used in the 1:20 scaled model tests discussed above.
tested. In all, five tests were performed (3 on smooth aluminium
and 2 on painted steel specimens. The tests were performed in
Discussion of Passive Tests a manner to simulate the conditions that would prevail in the
In nine of the passive tests the models were pulled at a rate of field and also in the model tests, in terms of set-up time,
8.33 mm/sec corresponding to the design prototype extraction shearing rate (8mm) and soil specimen interface orientation.
time of 30 minutes. In all of these tests the mudmat was The soil specimens used were all clay from depths ranging
recovered successfully. 0.75m -1.65m depth.
After the design of testing apparatus and start of the The following conclusion was reported: The peak average
programme it was decided to do an additional test. This was interface friction ratio ( -factor) for Aluminium alloy as used
to simulate snatch loading of the crane-hook lifting the PPIF in the mudmat model tests is 0.37. The peak average interface
structure off the seabed on completion of the pin-pile friction ratio for both Paint systems 1 and 2 is 0.35.
installation operations. In this case the weight would be These -values agree well with the calculations based on
supported on the two Row-1 mudmats of PPIF, fully DSS strength, described above; between 0.33 for penetration
embedded in the seabed together with the un-skirted 5th and 0.4 for extraction.
mudmat. seven attempts were made on this test to pull the
mudmat model off the soil bed at the faster rate of 25mm/sec
corresponding to prototype extraction time of 10 minutes. The Conclusions
outcome of this test is quite significant, even though the Scaled model tests and FE analyses have shown that the
apparatus was not designed for it and equipment failures were Terram diffuser is very effective in eliminating the underbase
caused. adhesion during the removal of mudmats, both with the active
The results showed a strong dependence of the mudmat water injection and passive suction schemes. However, one
resistance on uplift speed. Higher under-base suctions test simulating an extraction time of 10 minutes (prototype),
recorded in this test resulted in loads that were up to three i.e. three times faster than the design value, showed that the
times higher than the other passive tests. Indeed the attempted force required is almost three times the value for extraction
model scale pulling speed of 25mm/sec was based on time of 30 minutes (prototype). Therefore, any “snatch”
limitations of the testing equipment (loading motor and frame, loading should be avoided during the field operations.
etc.). Even this pulling rate could not be sustained by the
OTC 18923 7

Laboratory interface tests show that the selected paint 5. “On the Extrication of large objects from the ocean bottom (the
system reduces skirt friction effectively. The skirt adhesion - breakout phenomenon)” Foda, M.A., J. Fluid Mech., Vol. 117,
value obtained from the interface tests was around 0.37. p. 211-2331.
Maximum in place loading occurs during pile stabbing into 6. Hesar, M. “Optimal Inclined Bearing Capacity of Shallow
the sleeve cone. The size of mudmats has been kept to a Foundations”, Proc. 16th ISOPE Conf., Paper JSC-416, San
minimum in order to minimise problems during removal. Francisco, 2006.
Although the bearing capacity of mudmats has been verified to 7. Bransby, M.F. & Martin, C.M. (1999). “Elasto-plastic
be adequate using non-linear FE models, care should be taken modelling of bucket foundations” Proc. 7th Int. Symp. on
during pile stabbing operations to avoid this load scenario and Numerical Models in Geomechanics, Graz, pp 425-430.
potentially disturbing the levelling of the LA.
8. Det Norsk Veritas, Classification Notes No. 30.4
Maximum consolidation settlement of the longest loaded “FOUNDATIONS”, February, 1992
PPIF mudmats is predicted to be of the order 30mm over a
period of 1 month. The maximum immediate elastic settlement 9. API RP2A-LRFD, 'Recommended Practice for Planning,
of the PPIF 5th mudmat is estimated to be of the order 100mm. Designing and Constructing Fixed Offshore Platforms - Load
It is recommended that the settlement of mudmats be and Resistance Factor Design', American Petroleum Institute,
First Edition, July 1, 1993
monitored during field operations to assist in any necessary re-
levelling of the PPIF structure. 10. Janbu, N., Bjerrum, L. and Kjaernsli, B. (1956): Norwegian
Geotechnical Institute Publication No. 16
11. Norwegian Geotechnical Institute, Joint Industry Project
Acknowledgement “Skirted Foundations and Anchors in Clay: Set-up Effects
The author is grateful to BP Exploration UK for permission to outside Skirt Wall”, Report No. 524071-2, 11 May 1999
publish this work.

References
1. Tjelta, T.I., Aas, P.M., Hermstad, S. and Andenaes, E. “The
skirt piled Gullfaks C installation”, OTC 6473, Houston 1990.
2. Tjelta, T.I., “Geotechnical aspects of Bucket Foundations
replacing piles for the Europipe 16/11-E jacket”, OTC 7379,
Houston 1994.
3. Kolk, H.J. and Kay, S. “North Nemba Flare Bucket
Foundations”, OTC 13057, Houston 2001
4. Fisher, R. “Gravity Base Design for Subsea Structures”, Proc.
Int. Conf. Offshore Site Investigation and Geotechnics –
Diversity and Sustainability, London, November 2002.
8 OTC 18923

Figure 1 Bathymetric plot with PPIF and LA positions on DWG


sites

Figure 2 Conceptual Schematics of PPIF and LA


OTC 18923 9

Fig. 3 Undrained shear strength profile Fig. 4 Photograph of a typical Core sample from seabed
10 OTC 18923

2000

1800

1600

1400

1200
Vertical Load (kN)

1000

800

600

400

200
Fig. 7 Mudmat structure modeled with shell elements

0
0 50 100 150 200 250 300
Horizontal Load (kN)

Ultimate Rough Surf ace Factored Rough Surf ace Factored Design Loads

Fig. 5 Stability envelopes for un-skirted PPIF 5th and LA Apex


Mudmats

Fig. 8 (a) PPIF structure under construction

Fig. 6 Typical Deformed Shape plot showing Contours of Vertical


Displacement (Combined Lateral-Vertical Loading)

Fig. 8 (b) Skirted mudmat during fabrication in Baku


OTC 18923 11

ACG Phase 3 DWG - Pin Pile Installation System Mudmat


Immediate Elastic Settlement of 5th PPIF Mudmat

M udmat Elastic Settlement (mm)


0 20 40 60 80 100 120
0

10

Depth Below Mudline (m)


15

Fig. 9 Fig. 4.9 Contours of Vertical Displacement, Combined


Lateral-Vertical Loading ABAQUS model with 3D Infinite
Elements, magnification factor = 10.
20

25

30

Lower Bound Settlement Upper Bound Settlement

Fig. 11 Immediate seabed settlement profiles under 5th mudmat


from Elastic Theory

ACG Phase 3 DWG - Pin Pile Installation System Mudmats


Consolidation Settlement of Typical PPIF Mudmat

0.00 0.00 0.10 10.00 1000.00 100000.00


-60

-70

-80
Settlement (mm)

Fig. 10 Vertical Load versus Vertical Displacement response from -90


model shown in Fig. 4.9

-100

-110

-120
Time (Days)

Low Estimate High Estimate

Fig. 12 Consolidation settlement time history of skirted mudmats


12 OTC 18923

AIOC PROJECT - PHASE 3


DWG Pin-Pile Instalation Frame Mudmats
Horizontal Load-Displacement Response

700

600

500
Lateral Load (kN)

400

300

200
Fig. 16 (a) Laboratory scale model for the active injection system
testing

100

0
0.000 0.010 0.020 0.030 0.040 0.050
Lateral Displacem ent (m)

LA-6m LA-6m-sk75

Fig 13 Lateral load-displacement response with and without skirts

AIOC - ACG PHASE III - Deep Water Gunashli


PPIF Row-1 Skirted mudmat extraction Constant Force
Extraction Times extrapolated from vol. increments)

900

800 6x12inch valves

"5x12inch valves"

700 4x12inch valves


Effective Mudmat Uplift Force (kN)

"3x12inch valves"
600
"2x12inch valves"

4x6inch valves
500
Fig. 16 (b) Laboratory scale model for the passive suction system
testing
400

300

200

100

0
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0
Extraction Time (Minutes)

Fig. 15 Effective mudmat uplift force v. Extraction time for


different passive suction hole opening sizes
OTC 18923 13

Fig. 16 (c) Scale model in the test tank

You might also like