Item Description Unit Quantity As Remarks
No. Rate Amount Quantity Amount Quantity Amount Quantity Amount % completion
per Contract
GENERAL
MOBILIZATION AND DEMOBILIZATION
L.S. 1.00 500,000.00 500,000.00 1.00 500,000.00 1.00 500,000.00 - - 100.00%
1 Mobilization of the construction by constructing temporaty
acomodation
SITE OFFICE forESTABLISHMENT
labours and site staff with required suitable Per
facilities 14.00 25,000.00 350,000.00 14.00 350,000.00 14.00 350,000.00 - - 100.00%
2 Providingand andkeeping
Maintainingthe sameSite inOffice
good of hygenic condition
two Rooms for
having Month
entire project
total Area 20 completion
sq.m for the time.useDemolition
of Client ofand the Consultant
same and
PROJECT INFORMATION BOARD
3 cleaning
includingthe site after completion
office of thefile
construction activities nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 - - 100.00%
Providing and chair,
FixingTable, Lockable
of Project cabinet,board
Information Stationery
with
all complete.
Items (Ink,Text
Paper,[Note:
Pen, 50% payment
Pencils etc.), shall be made
1 Computer after
approved
SAFETY SIGN inBOARD
appropriate location includingand all 1required
Printer
completion
with all of mobilization
necessary set up. all and remaining
complete as per 50% after
instruction of nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 - - 100.00%
fixing accessories
Providing and as perofdrawing
Fixing all complete.
4 completion
engineer. The as perSafety
of Specification
works contract]Sign Board with approved
of computer shall not be less than
Text and Sinage including
BARRICADING WORKS required fixing accessories as per
(19.5" led monitor with Core i5, 7th Generation, 500 gb Hdd, R.m 45.00 2,000.00 90,000.00 45.00 90,000.00 45.00 90,000.00 - - 100.00%
drawing all complete.
Barricading between
5 8gb ddr 4 ram), Printer theshould School
function Academic
at least ofarea and
Printing,
Construction
SAFETY
Scanning and area
MATERIALS with 1.8&
Photocopy mSITE
of high
A4 CGI size Sheet
SAFETY fixed toProviding
documents. Bamboo
support frame L.S. 1.00 100,000.00 100,000.00 1.00 100,000.00 1.00 100,000.00 - - 100.00%
6 Providing andall
and Maintaining complete
all aboveasitems
Maintaining per instruction
Construction
on Rental ofBasis
Safety Engineer.
Measures
for entirein
Construction
project completion
RELOCATING SiteOF with
time. proper Safety
EXISTING TLCmeasures to person and
work area (Helmet, Shoes, First AidLearning
Kit, Clothing, Glove, sq.m 19.21 3,000.00 57,630.00 18.00 54,000.00 18.00 54,000.00 - - 93.70%
7 Relocating of Existing Temporary Centre (TLC),
Guardconstruction
from Rail for edge siteprotection,
to Safety
other place by Net, Safety rope,
Demolition Fall
and using
LAB TEST(WATER TEST)
8 Protection
existing and etc.)
materials as required
obtained by
fromthe Contract
demolition Clause
of TLC GCC 24
to the job 1.00 7,500.00 7,500.00 - - - - - 0.00%
Testing Providing Lab Test Report for Quality of Water in
and Specification
place decided division 1 "GENERAL REQUIREMENT
Water
TEMPORARY Streamby (Up SMC.and Down streem) located near by
TOILET
CLAUSE 8(C)". The number of Safety Materials Personal nos. 2.00 150,000.00 300,000.00 2.00 300,000.00 2.00 300,000.00 - - 100.00%
9 Construction of
Construction sitetemporary
before Starting
toilet and CGI
with after Sheet
completion
fixed of
to
Protecting Equipments (PPE) shall be minimum but not
construction
Bamboo work. Thisand
support Testallhas to be done toincluding
mark the Septic
affect
ROAD
limited to 35 sets.frame
REPAIR AND
Payment necesary
MAINTENANCE
shall be made items
in Prorata Basis for
of
pit,construction
Pipeline, work in water stream. Km. 56.00 50,000.00 2,800,000.00 56.00 2,800,000.00 56.00 2,800,000.00 - - 100.00%
10 Providing
entire andToilet
duration Pan etc. for
Maintaining
of project. the entire
roadsproject completion
as necessary time
to avoid
all complete
blockage as per Instruction
by Landslides of Engineer.
and Rockfall Rate shall
for regular include
transport of
all Material
construction cost
materials with fixing, construction
and site inspection during overallcharges and
CIVIL WORKS-
demolition & BUILDING
cleaning of the same after completion of the
construction period. Rate shall include all Material cost with
SITE CLEARANCE
construction activities & complete.
all MOBILIZATION:
demolition charges, cleaning, fixing & construction charges of
Clearing and grubbing the site for construction by removing sq.m 352.54 100.00 35,254.00 343.75 34,375.00 376.75 37,675.00 (33.00) (3,300.00) 97.51%
the same after completion of the construction activities all
150mm
1.1 complete. thick top soil including bushes, small trees, leveling of
undulated
EARTHWORK ground,INshorting
EXCAVATION and stacking/storing
: selected top
soil for reuse in landscaping cu.m 195.91 400.00 78,364.00 188.67 75,467.12 188.67 75,468.82 (0.00) (1.70) 96.30%
1.2 Excavation in foundations in all works,
type of disposing unsuitable
soils for foundation,
materials footing,
trenches, from site, pits etc.,
etc. all
to thecomplete
requiredas depth
per drawings,
including
specificationsbyandmanual
dewatering instructions of the Engineer.
or mechanical means etc. as per
specifications with all contractor’s own machinery and
equipment's, providing crossing of track, shoring, strutting,
timbering and buttressing with appropriate materials and all
Preparedsuch measures necessary to retain in position the sides of the
by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
foundation pit and including refilling the excavated material
with watering, ramming, leveling the site and disposing off the
surplus/unusable earth to outside the construction premises,
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
Item Description Unit Quantity As Remarks
No. Rate Amount Quantity Amount Quantity Amount Quantity Amount % completion
per Contract
Pay
Item Description Unit Quantity As Remarks
No. Rate Amount Quantity Amount Quantity Amount Quantity Amount % completion
per Contract
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
Item Description Unit Quantity As Remarks
No. Rate Amount Quantity Amount Quantity Amount Quantity Amount % completion
per Contract
D Sanitary Works
1 WATER SUPPLY INSTALLATION
a CPVC pipes SDR-11
40 mm r.m 92.00 1,600.00 147,200.00 88.00 140,800.00 88.00 140,800.00 - - 95.65%
25mm r.m 6.00 1,000.00 6,000.00 6.00 6,000.00 6.00 6,000.00 - - 100.00%
c CPVC Ball Valve - - -
40 mm nos. 3.00 2,000.00 6,000.00 3.00 6,000.00 3.00 6,000.00 - - 100.00%
25 mm nos. 2.00 900.00 1,800.00 2.00 1,800.00 2.00 1,800.00 - - 100.00%
d Electrical Centrifugal Water Pump nos. 1.00 12,500.00 12,500.00 1.00 12,500.00 1.00 12,500.00 - - 100.00%
e 2000 litres Capacity Water Storage Tank nos. 1.00 34,000.00 34,000.00 1.00 34,000.00 1.00 34,000.00 - - 100.00%
2 Sewer, Rain and Waste Water Installation - - -
110 mm r.m 23.00 1,400.00 32,200.00 22.00 30,800.00 22.00 30,800.00 - - 95.65%
75mm r.m 20.00 1,200.00 24,000.00 19.00 22,800.00 19.00 22,800.00 - - 95.00%
50mm r.m 6.00 350.00 2,100.00 5.00 1,750.00 5.00 1,750.00 - - 83.33%
B School Blocks - - -
1 Sanitary Installation - - -
a Water Closet Set set 1.00 30,000.00 30,000.00 1.00 30,000.00 1.00 30,000.00 - - 100.00%
b Orissa Pan set 4.00 3,100.00 12,400.00 4.00 12,400.00 4.00 12,400.00 - - 100.00%
c Hand Wash Basin set 5.00 8,000.00 40,000.00 5.00 40,000.00 5.00 40,000.00 - - 100.00%
d Ladies Urinal set 2.00 11,000.00 22,000.00 2.00 22,000.00 2.00 22,000.00 - - 100.00%
e Self Closing Bib Cock nos. 4.00 4,000.00 16,000.00 4.00 16,000.00 4.00 16,000.00 - - 100.00%
f CP Spreader in Urinal set 4.00 2,500.00 10,000.00 4.00 10,000.00 4.00 10,000.00 - - 100.00%
g Toilet Paper Holder nos. 1.00 2,600.00 2,600.00 1.00 2,600.00 1.00 2,600.00 - - 100.00%
h Commode Spray nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 - - 100.00%
i PVC Multi Floor Trap nos. 3.00 600.00 1,800.00 3.00 1,800.00 3.00 1,800.00 - - 100.00%
j Waste Coupling and PVC Bottle Trap nos. 1.00 1,500.00 1,500.00 1.00 1,500.00 1.00 1,500.00 - - 100.00%
k 40mm SS Grab Bar-Side nos. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 - - 100.00%
l 40mm SS Grab Bar-Rear nos. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 - - 100.00%
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
Item Description Unit Quantity As Remarks
No. Rate Amount Quantity Amount Quantity Amount Quantity Amount % completion
per Contract
m CP Foldable Hinge nos. 1.00 5,500.00 5,500.00 1.00 5,500.00 1.00 5,500.00 - - 100.00%
- -
E CIVIL WORKS : SITE DEVELOPMENT - -
1 EARTHWORKS - -
1 SITE CLEARANCE AND MOBILIZATION Sq.m 186.30 100.00 18,630.00 181.61 18,161.12 136.50 13,650.00 45.11 4,511.12 97.48%
2 EARTHWORK IN EXCAVATION Cu.m 151.05 400.00 60,420.00 80.15 32,059.05 26.58 10,631.40 53.57 21,427.65 53.06%
3 EARTHBACK FILLING Cu.m 6.26 300.00 1,878.00 5.09 1,525.73 - 5.09 1,525.73 81.24%
4 BOULDER SOLING Cu.m 19.80 6,000.00 118,800.00 21.18 127,083.75 21.18 127,083.75 - - 106.97%
5 P.C.C (1:3:6) Cu.m 0.54 14,000.00 7,560.00 0.54 7,602.00 0.54 7,602.00 - - 100.56%
6 P.C.C (1:2:4) Cu.m 10.64 16,000.00 170,240.00 10.24 163,800.00 10.24 163,800.00 - - 96.22%
7 P.C.C FOR R.C.C WORK cu.m 0.99 20,000.00 19,800.00 0.99 19,766.20 0.99 19,766.20 - - 99.83%
8 SILICA CEMENT ADMIXTURE Kg 9.90 300.00 2,970.00 9.88 2,964.93 9.88 2,964.93 - - 99.83%
9 STEEL REINFORCEMENT Mt. 0.10 130,000.00 13,000.00 0.10 12,902.51 0.10 12,902.51 - - 99.25%
10 FORM WORKS Sq.m 9.12 800.00 7,296.00 11.33 9,064.00 9.12 7,292.80 2.21 1,771.20 124.23%
13 BRICKS MASONRY WORKS (1:4 c/s) Cu.m 0.22 18,000.00 3,960.00 0.72 13,032.72 0.72 13,032.72 - - 329.11%
14 NEAT CEMENT SKIRTING r.m 4.72 100.00 472.00 4.40 440.00 4.40 440.00 - - 93.22%
15 METAL WORKS FOR FENCE k.g 1477.83 220.00 325,122.60 1,035.50 227,810.00 1,035.50 227,810.00 - - 70.07%
16 METAL WORKS FOR GATE k.g 130.78 600.00 78,468.00 123.31 73,986.00 118.89 71,333.04 4.42 2,652.96 94.29%
17 PLASTER ON OUTER WALL Sq.m 7.92 600.00 4,752.00 7.80 4,679.04 7.80 4,679.04 - - 98.46%
18 EXTERIOR WEATHER COAT PAINT Sq.m 8.87 350.00 3,104.50 8.27 2,895.20 8.27 2,895.20 - - 93.26%
19 CHAIN LINK FENCE Sq.m 150.14 1,000.00 150,140.00 159.60 159,600.00 159.60 159,600.00 - - 106.30%
20 FLAG POLE nos. 2.00 25,000.00 50,000.00 2.00 50,000.00 2.00 50,000.00 - - 100.00%
- - -
CIVIL WORKS-RESERVIOR TANK - - -
1.1 SITE CLEARANCE & MOBILIZATION:
sq.m 22.31 50.00 1,115.50 22.31 1,115.50 22.31 1,115.50 - - 100.00%
1.1 Clearing and grubbing the site for construction by removing
150mm
1.2 thick top soil IN
EARTHWORK including
EXCAVATION bushes, small : trees, leveling of
undulated ground, shortinginand cu.m 24.58 400.00 9,832.00 24.57 9,828.72 24.57 9,828.00 0.00 0.72 99.97%
1.2 Excavation in foundations all stacking/storing
type of soils forselected foundation, top
soil for reuse
trenches, footing, in landscaping works, disposing unsuitable
1.3 EARTH BACKpits etc. to the
FILLING : required depth including
1.3 materials
dewatering from site, etc., all complete as per drawings, cu.m 4.02 300.00 1,206.00 4.01 1,202.85 4.01 1,203.00 (0.00) (0.15) 99.74%
Back fillingbyin manual foundation or mechanical
and sides of means etc. as with
foundation per
specifications
specifications andwith instructions
allfrom of the Engineer.
contractor’s own machinery and
approved
1.4 BOULDER soil obtained
SOLING : the excavation at site and stacked
equipment's,
at site or brought providing crossing
from uncoursed
outside in layer of track, shoring, strutting, cu.m 2.08 6,000.00 12,480.00 2.08 12,462.00 2.08 12,480.00 (0.00) (18.00) 99.86%
1.4 Providing and laying hand not packedexceeding 15 cm
Dry Rubble
timbering
thick (compactedand buttressing
thickness) with appropriate
including materials of andsoil,
all
Stone soling in foundation,
2. CONCRETE WORKSto retain under floortransportation
plinth with out any
such measures
spreading in necessary
required line and inlevel,
position the sides water,
sprinkling of the cu.m 0.78 14,000.00 10,920.00 0.78 10,904.25 0.78 10,920.00 (0.00) (15.75) 99.86%
special
2.1.1 2.1 P.C.C dressing of stone including filling interstices with
foundationcompacting
ramming, pit and including with refilling the
mechanical excavated
rammers, material
testing, etc.,
suitable
2.1.1 quarry
P.C.C waste or
(1:3:6) stone chips or quarry sand, watering,
2.2
all P.C.C.
withcomplete
watering, FOR perR.C.C.
asramming, drawing, WORKS
leveling the: site and
specification and disposing
instructions off the
of
compacting
Providing and using
laying appropriate
machine mechanical
mixed Plain compaction
Cement means
Concrete cu.m 7.42 20,000.00 148,400.00 7.41 148,295.00 7.41 148,200.00 0.00 95.00 99.93%
Providing
surplus/unusable
2.2 with
the Engineer. and layingearth in position
to outside machine
the mixed
construction and machine
premises,
of all contractors
nominal mix 1:3:6 (1materials,
cement 3handling,
:1:1.5:3
sand(1 placing
: 6specifications
coarse etc. all)
aggregate
vibrated
etc. all
2.3 SILICA cement
complete
CEMENTconcrete as of
per mix
ADMIXTURE drawings, cement:1.5 sand:and 3
2.3 complete
for leveling
coarse
as course
aggregate)
instructions
per drawings,
of themixingM20
Engineer.
specifications
in foundations
grade and
forCement
and floor
under
reinforced
instruction
cement
of the
of building,
concrete kg 74.20 300.00 22,260.00 74.15 22,244.25 74.15 22,245.00 (0.00) (0.75) 99.93%
Providing
Engineer. Theand complete itemSilica
including Admixture
all lead &sizelift. notofmore in
etc. in all level
work usingconcrete with
approved broken stone aggregate of
structural
2.4 STEEL REINFORCEMENTat cement
the rate with of 2.50%20 mmbygraded weightmachineof the
than
crushed25 mm stone of approved
aggregatequality including formwork
of approved quality inwherever various Mt. 1.46 130,000.00 189,800.00 1.47 191,574.92 1.58 205,400.00 (0.11) (13,825.08) 100.94%
cement
2.4 Providing for
and promoting
fixing inbatching, workability,
position Fe improving
500 steel reinforcementstrength, of
necessary,and
locations dewatering,
heights including mixing, transporting,
transportation of placing,
concrete to
achievingdiameter
various waterproofing confirming properties,
to all bleeding
relevant prevention,
ISandcode etc.
2.5
site FORM
compacting,
of placing,WORKS
curing,
compaction,including finished tolead
required lift,in
line and
R.C.C.
etc. all
level,
Silica Cement
works including Admixture
straightening, shall cutting,
be the productbending, ofbinding
Silica Japan
with sq.m 54.93 800.00 43,944.00 54.67 43,738.00 56.46 45,168.00 (1.79) (1,430.00) 99.53%
Supplying
complete asand
2.5 or
protection andperlaying
drawings,centering, shuttering
etc.specifications
completeand of various
asasthe pattern
instructions
20 superior
SWG and curing,
annealed shallwiremeet theallrequirements
forthick
tying the proof
reinforcement
per drawings,
mentioned bars in
at
formworks
of the
INTERNAL Engineer.
specifications with 19/12
CEMENT
and themm PLASTER
instructions water (1:4) theplyEngineer,
of WITH wood
PUNNING & steel
specification
each junctions of(binding
materials wire and Workmanship,
shall not be measured Division –but
separately) 4: sq.m 33.66 700.00 23,562.00 33.66 23,565.25 33.65 23,555.00 0.01 10.25 100.01%
adjustable
excludingWorks,
3.1.1 Concrete props for
the costArticle all kinds
of centering, of RCC works for
shuttering, and reinforcement, foundations,
including all waste and beams, 2.4cut pieces,
columns,
all complete shear
as perwalls,
drawings, specifications slab, provision
staircase, forlintel,
and instructions
adequate
sill,
of
4 WATER
numbers PROOF
of spacers, COATING
chairs, propping
providing scaffolding,
and placing staging, cement sq.m 33.66 550.00 18,513.00 33.66 18,515.55 33.65 18,507.50 0.01 8.05 100.01%
pergola,
the Engineer. including nails,
mortar (1:1) cover blocks to keep the
supporting and bracing in proper lines and level, sealing the bars in intended position - - -
F at all levels
Furniture
joints with Works all complete
heavy duty brown as perself drawings,
adhesivespecifications
tape, aligningand to lot 1.00 3,000,000.00 3,000,000.00 1.00 3,000,000.00 1.00 3,000,000.00 - - 100.00%
instructions
line and levels of the including
Engineer. Total (Authorized
Ties, PVClapSpacer, length and for the
Providing 41,958,840.10 42,241,224.74 38,853,405.83 3,387,818.91
bar length cutouts/
openings/ exceeding 10 meter
pockets, in length
applying shall be measured
De-shuttering chemical, for
the payment, except
De-shuttering as approvedto column).by the Engineer etc., complete at all
levels as per drawing, specifications and instructions of the
Engineer.
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-9C(XS)-B
School Name : Shree Devi Jal Kumari Lower Secondary School
Location : Aaruarbang, Gorkha
Abstract of Cost - Civil Works
Pay Type Design
Quantity in Total
Item Description of Works Unit Rate (NRs.) Amount Remarks
BOQ 3-9C(XS)-B Site Development Water Tank Quantity
No.
GENERAL
1 MOBILIZATION AND DEMOBILIZATION L.S. 1.00 500,000.00 1.00 500,000.00
2 SITE OFFICE ESTABLISHMENT Per Month 14.00 25,000.00 14.00 350,000.00
3 PROJECT INFORMATION BOARD nos. 1.00 10,000.00 1.00 10,000.00
4 SAFETY SIGN BOARD nos. 1.00 10,000.00 1.00 10,000.00
5 BARRICADING WORKS R.m 45.00 2,000.00 45.00 90,000.00
6 SAFETY MATERIALS & SITE SAFETY L.S. 1.00 100,000.00 1.00 100,000.00
7 RELOCATING OF EXISTING TLC sq.m 19.21 3,000.00 18.00 54,000.00
9 TEMPORARY TOILET nos. 2.00 150,000.00 2.00 300,000.00
10 ROAD REPAIR AND MAINTENANCE Km. 56.00 50,000.00 56.00 2,800,000.00
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG Providing and sq.m 326.92 550.00 - -
8.1.1 POINTING WORK IN BRICK MASONRY sq.m 287.39 400.00 - -
BOQ Total of items 3.1., 7.2.3 & 8.1.1:
Replaced items 3.1, 7.2.3 and 8.1.1 with following items for 3-
9C(XS)-B
Brick Masonry Works (1:4 c/s) cu.m 18,000.00 - -
Cement Plaster Works on Outer Wall (1:6) sq.m 600.00 - -
Exterior Weather Coat Paint sq.m 350.00 - -
3.2 BRICK MASONRY WORKS ( 1 : 4 c/s ) cu.m 42.44 18,000.00 114.98 114.98 2,069,586.63
5.2 NEAT CEMENT SKIRTING r.m 284.29 100.00 344.62 344.62 34,462.10
5.3 TERRAZZO CAST-IN SITU DADO sq.m 56.78 1,500.00 56.36 56.36 84,535.20
7.1.1 7. PLASTERING/ WALL FINISHING WORKS
7.1 CEMENT PLASTER WORKS sq.m 859.19 600.00 750.32 750.32 450,189.53
7.1.2 7.1.1
7.1.2 ON
ON INNER WALL
CEILING (1:4) (1:6) sq.m 540.15 500.00 569.32 569.32 284,660.98
7.1.3.1 7.1.3 ON OUTER WALL (1:6):
7.1.3.1 EXTERNAL PLASTER sq.m 604.57 600.00 1,059.72 1,059.72 635,832.32
7.2..2 EXTERIOR WEATHER COAT PAINT sq.m 617.15 350.00 1,059.73 1,059.73 370,905.50
7.2.4 ENAMEL PAINT sq.m 287.39 400.00 365.69 365.69 146,276.00
8 MISCELLANEOUS - -
8.3 RAILING kg 1,610.53 6,500.00 1,738.63 1,738.63 11,301,106.08
8.4 PUMP SHED nos. 1.00 80,000.00 1.00 1.00 80,000.00
8.5 SEWER, RAIN AND WASTE WATER INSTALLATION R.m 44.26 1,500.00 39.10 39.10 58,650.00
C ELECTRICAL WORKS
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure nos. 1.00 12,000.00 1.00 1.00 12,000.00
2 CABLES & WIRES
2.1 2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper conductor r.m 60.00 800.00 56.00 56.00 44,800.00
B wires
School Blocks - -
1 DISTRIBUTION BOARDS - -
1.1 Ground Floor DB (DB-1) nos. 1.00 32,000.00 1.00 1.00 32,000.00
1.2 First Floor DB (DB-2) nos. 1.00 32,000.00 1.00 1.00 32,000.00
1.3 Second Floor DB (DB-3) nos. 1.00 32,000.00 1.00 1.00 32,000.00
D Sanitary Works
1 WATER SUPPLY INSTALLATION
a CPVC pipes SDR-11
40 mm r.m 92.00 1,600.00 88.00 88.00 140,800.00
25mm r.m 6.00 1,000.00 6.00 6.00 6,000.00
5 Barricading Works 1 45 45 Rm
Ramp
For Slope 1 1.30 0.52 Area 0.67
Wall Along Grid B 1 0.50 0.45 0.45 0.10
Wall Parallel to Ramp 1 6.80 0.45 0.41 1.25
Outside Steps 1 18.93 0.68 0.15 1.92
1 2.50 0.68 0.15 0.25
Total 188.67 Cu.m
Building Floors
Classroom 3 5.70 4.70 0.20 16.07
Corridor 1 21.30 2.20 0.20 9.37
Staircase 1 4.70 4.20 0.20 3.95
Ramp
Slopped Portion 1 1.30 1.36 Area 1.77
Wall Along Grid B 1 0.50 0.45 0.10 0.02
Wall Parallel to Ramp 1 6.80 0.45 0.10 0.31
At Slope 1 22.93 0.99 0.10 2.26
Pebbles Compacted Earth 1 22.93 0.63 0.10 1.43
Outside Steps 1 18.93 0.68 0.10 1.28
1 2.50 0.68 0.10 0.17
2 CONCRETE WORKS
2.1 P.C.C. Works
2.1.1 P.C.C.(1:3:6) Works
For Footing
Footing (F1) 3 1.80 1.80 0.10 0.97
Combine Footing (CF1) 3 7.20 2.20 0.10 4.75
Combine Footing (CF2) 2 7.20 1.80 0.10 2.59
Combine Footing (CF3) 1 6.50 1.80 0.10 1.17
Ramp
Wall Along Grid B 1 0.50 0.45 0.05 0.01
Wall Parallel to Ramp 1 6.80 0.45 0.05 0.15
Septic Tank
1 0.83 1.45 0.08 0.09
Sewer Manhole (Rectangular)
Bottom 2 1.00 1.00 0.10 0.20
Total 10.70 Cu.m
Beam
Foundation Tie Beam(250x300)
Along grid 1,2,3 3 20.80 0.30 0.30 5.62
Along grid A,B,C,D,E 5 6.45 0.30 0.30 2.90
Plinth Beam(300x300)
Along grid 1,2,3 3 20.80 0.30 0.30 5.62
Along grid A,B,C,D,E 5 6.45 0.30 0.53 5.08
Secondary beam(250x425)
Along A1,B1,D1 9 6.90 0.25 0.43 6.60
Slab deduction
Beam at first,second and Third floor level
Main Beam(300x500)
Along grid 1,2,3 -9 20.80 0.30 0.13 -7.30
Along grid A,B,C,D,E -15 6.45 0.30 0.13 -3.77
Secondary beam(250x425)
Along A1,B1,D1 -9 6.90 0.25 0.13 -2.02
Slab
First Floor Level Slab 1 22.80 7.80 0.13 23.12
Projection at Grid 1 1 11.58 0.58 0.13 0.87
1 5.58 0.58 0.13 0.42
Projection at Grid 3 12.13 1.01 0.13 1.60
Projection on staircase Landing on 1st Floor 1 4.08 0.60 0.13 0.32
Deduction
Staircase Void -1 4.70 4.20 0.13 -2.57
Staircase
Ground Floor to First Floor
Steps 19 0.023 Area 2.00 0.86
Waist Slab 1 3.38 2.00 0.20 1.35
1 3.35 2.00 0.20 1.34
Landing 1 4.17 1.65 0.21 1.41
1 4.05 0.90 0.30 1.09
Landing Beam 1 4.08 0.25 0.43 0.43
Lintel Band
Ground Floor
Along grid 1 1 6.03 0.23 0.08 0.10
Along grid 2 1 6.83 0.23 0.08 0.12
Along grid A,B,C,D,E 5 4.48 0.23 0.08 0.39
Wall Partition Between Male and Female Toilet 1 2.73 0.23 0.08 0.05
1 3.75 0.23 0.08 0.06
Partition Wall at Toilet
Boys Toilet 1 2.28 0.13 0.08 0.02
1 1.18 0.13 0.08 0.01
Girls Toilet 1 2.28 0.13 0.08 0.02
1 1.18 0.13 0.08 0.01
Disabled Toilet 1 1.82 0.13 1.08 0.24
1 2.35 0.13 2.08 0.61
First Floor
Along grid 1 1 6.03 0.23 0.08 0.10
Along grid 2 1 6.83 0.23 0.08 0.12
Along grid A,B,C,D,E 5 4.48 0.23 0.08 0.39
Second Floor
Along grid 1 1 6.03 0.23 0.08 0.10
Along grid 2 1 6.83 0.23 0.08 0.12
Along grid A,B,C,D,E 5 4.48 0.23 0.08 0.39
Sill band
Ground Floor
Along grid 1 1 20.80 0.23 0.08 0.36
Along grid 2 1 16.73 0.23 0.08 0.29
Along grid A,B,C,D,E 5 4.48 0.23 0.08 0.39
At store Below Landing 1 1.92 0.23 0.08 0.03
Wall Partition Between Male and Female Toilet 1 2.73 0.23 0.08 0.05
1 3.75 0.23 0.08 0.06
Partition Wall at Toilet
Boys Toilet 1 2.28 0.13 0.08 0.02
1 1.18 0.13 0.08 0.01
Girls Toilet 1 2.28 0.13 0.08 0.02
1 1.18 0.13 0.08 0.01
Disabled Toilet 1 1.82 0.13 1.08 0.24
1 2.35 0.13 2.08 0.61
First Floor
Along grid 1 1 16.73 0.23 0.08 0.29
Along grid 2 1 16.73 0.23 0.08 0.29
Along grid A,B,C,D,E 5 4.48 0.23 0.08 0.39
Second Floor
Along grid 1 1 16.73 0.23 0.08 0.29
Along grid 2 1 16.73 0.23 0.08 0.29
Along grid A,B,C,D,E 5 4.48 0.23 0.08 0.39
Band at Parapet
Band at Top Floor Wall (Below door) 2 6.45 0.23 0.20 0.59
Third Floor Level 1 65.78 0.35 0.10 2.30
Vertical Band 44 0.80 0.23 0.23 1.86
Roof Top 1 29.20 0.35 0.10 1.02
Vertical Band 19 0.90 0.23 0.23 0.93
Pedestal
Base Block 11 0.50 0.25 0.25 0.34
Septic Tank
At Bottom 1 4.33 2.15 0.12 1.13
1 1.98 2.15 0.15 0.64
Band 1 1.40 0.23 0.15 0.05
2 1.13 0.23 0.12 0.06
1 0.95 0.23 0.12 0.03
1 0.95 0.13 0.12 0.01
1 4.78 2.15 0.12 1.23
Deduction of cover -1 0.60 0.60 0.12 -0.04
Soak Pit
RCC slab 1 2.27 Area 0.13 0.28
Manhole/Waste Chamber
Sewer Manhole (Rectangular)
Top Cover 2 1.00 1.00 0.10 0.20
Deduction Cap -2 0.28 Area 0.10 -0.06
Total 276.07 cu.m
2.5 Formworks
Foundation
F1 3 7.20 0.20 4.32
CF1 3 18.80 0.65 36.66
Beam
Foundation Tie Beam(250x300)
Along grid 1,2 2 20.80 0.60 24.95
Along grid 3 1 20.00 0.60 12.00
Along grid A,B,C,D,E 5 6.45 0.60 19.35
Plinth Beam(300x300)
Along grid 1,2 2 20.80 0.60 24.96
Along grid 3 1 20.00 0.60 12.00
Along grid A,B,C,D,E 5 6.45 0.60 19.35
Secondary Beam(250x425)
Along A1,B1,D1 9 6.90 1.10 68.31
Secondary Beam(250x425)
Along A1,B1,D1 -9 6.90 0.26 -16.15
Column
Foundation to Plinth 15 1.90 1.00 28.50
Ground Floor 15 1.90 3.00 85.50
First Floor 15 1.90 3.00 85.50
Second Floor 15 1.90 3.00 85.50
Slab
First Floor Level Slab 1 23.06 8.06 185.86
Projection at Grid 1 1 11.58 0.58 6.66
1 5.58 0.58 3.21
Projection at Grid 3 12.13 1.01 12.28
Projection on staircase Landing on 1st Floor 1 4.21 0.86 3.62
Deduction
Staircase Void -1 4.70 4.20 -19.74
Secondary Beam(250x425)
Along A1,B1,D1 -9 6.90 0.25 -15.53
Staircase
Upto first floor level
Steps 38 0.021 Area 0.80
Waist slab 1 3.38 2 6.75
1 3.38 2 6.75
Side formwork for waist slab 2 3.38 0.2 1.35
2 3.38 0.2 1.35
Landing 1 4.20 1.67 7.01
Side formwork for landing 1 3.34 0.21 0.68
Tread 19 2.00 0.15 5.70
Landing Beam 1 4.08 1.07 4.34
Lintel Band
Ground Floor
Along grid 1 1 6.03 0.15 0.90
Along grid 2 1 6.83 0.15 1.02
Along grid A,B,C,D,E 5 4.48 0.15 3.36
Wall Partition Between Male and Female Toilet 1 2.73 0.15 0.41
1 3.75 0.15 0.56
Partition Wall at Toilet
Boys Toilet 1 2.28 0.15 0.34
1 1.18 0.15 0.18
Girls Toilet 1 2.28 0.15 0.34
1 1.18 0.15 0.18
Disabled Toilet 1 1.82 0.15 0.27
1 2.35 0.15 0.35
Second Floor
Along grid 1 1 6.03 0.15 0.90
Along grid 2 1 6.83 0.15 1.02
Along grid A,B,C,D,E 5 4.48 0.15 3.36
Sill band
Ground Floor
Along grid 1 1 20.80 0.15 3.12
Along grid 2 1 16.73 0.15 2.51
Along grid A,B,C,D,E 5 4.48 0.15 3.36
At store Below Landing 1 1.92 0.15 0.29
Wall Partition Between Male and Female Toilet 1 2.73 0.15 0.41
1 3.75 0.15 0.56
Partition Wall at Toilet
Boys Toilet 1 2.28 0.15 0.34
1 1.18 0.15 0.18
Girls Toilet 1 2.28 0.15 0.34
1 1.18 0.15 0.18
Disabled Toilet 1 1.82 0.15 0.27
1 2.35 0.15 0.35
First Floor
Along grid 1 1 16.73 0.15 2.51
Along grid 2 1 16.73 0.15 2.51
Along grid A,B,C,D,E 5 4.48 0.15 3.36
Band at Parapet
Band at Top Floor Wall (Below door) 2 6.45 0.40 5.16
1 47.71 0.30 14.31
1 13.80 0.30 4.14
1 28.19 0.30 8.46
Total 1,625.25 sq.m
3 Brickworks
3.2 Full Brick (230 mm) Works (1:4c/s)
Below Plinth level
Along Grid 1,2,3 3 20.78 0.23 0.40 5.73
Along Grid A,B,C,D,E 5 6.45 0.23 0.40 2.97
Ground Floor
Along grid 1 1 16.73 0.23 2.35 9.04
1 4.08 0.23 2.00 1.87
Along grid 2 1 16.73 0.23 2.35 9.04
Along Grid A,B,C,D,E 5 4.48 0.23 2.35 12.09
Wall Partition Between Male and Female Toilet 1 2.73 0.23 2.42 1.52
1 3.50 0.23 2.72 2.19
Deduction
D1 -4 1.10 0.23 2.35 -2.38
D4 -1 1.00 0.23 2.35 -0.54
D5 -1 0.90 0.23 2.35 -0.49
W1 -8 1.10 0.23 1.13 -2.28
W3 -1 1.50 0.23 0.33 -0.11
V1 -8 1.10 0.23 0.55 -1.11
V2 -1 2.63 0.23 0.55 -0.33
V3 -1 2.70 0.23 0.55 -0.34
Toilet Opening -1 1.16 0.23 2.35 -0.63
First Floor
Along grid 1 1 16.73 0.23 2.35 9.04
1 4.08 0.23 2.08 1.94
Along grid 2 1 16.73 0.23 2.35 9.04
Along Grid A,B,C,D,E 5 4.48 0.23 2.35 12.09
Partition Wall at Computer Lab 1 3.38 0.23 1.20 0.93
Second Floor
Along grid 1 1 16.73 0.23 2.35 9.04
1 4.08 0.23 2.08 1.94
Along grid 2 1 16.73 0.23 2.35 9.04
Along Grid A,B,C,D,E 5 4.48 0.23 2.35 12.09
Partition Wall at Principal/Administration 1 1.48 0.23 2.72 0.92
Deduction
D1 -6 1.10 0.23 2.35 -3.57
W1 -12 1.10 0.23 1.13 -3.42
W2 -1 1.50 0.23 1.08 -0.37
V1 -12 1.10 0.23 0.55 -1.67
Top Floor
Along Grid 1,3 2 4.08 0.23 2.03 3.80
Along Grid C,D 2 6.45 0.23 1.83 5.41
Deduction
D2 -2 1.00 0.23 2.10 -0.97
W2 -1 1.50 0.23 1.08 -0.37
Parapet Wall
1 47.71 0.23 0.80 8.78
1 13.80 0.23 1.40 4.44
1 28.19 0.23 0.90 5.84
Outside
Steps 1 19.27 0.30 0.10 0.58
1 18.61 0.30 0.25 1.40
1 0.60 0.50 0.30 0.09
1 0.54 0.50 0.30 0.08
1 0.60 0.50 0.30 0.09
Ramp
Wall Along -B 1 1.33 0.25 Area 0.33
1 6.91 0.17 Area 1.19
Total 114.98 cu.m
5 FLOORING WORKS
Cement Concrete Flooring (40mm) With Neat
5.1 Cement Punning
Ground floor
Rooms 3 5.75 4.75 81.94
Below staircase 1 4.2 4.75 19.95
Corridor 1 22.8 2.525 57.57
Staircase
Landing 1 4.2 2 8.40
Tread 18 1.95 0.3 10.53
Riser 19 1.95 0.15 5.56
First floor
Rooms 3 5.75 4.75 81.94
Corridor 1 22.8 2.525 57.57
Staircase
Landing 1 4.2 2 8.40
Tread 18 1.95 0.3 10.53
Riser 19 1.95 0.15 5.56
Second floor
Rooms 3 5.75 4.75 81.94
Corridor 1 22.8 2.525 57.57
Staircase
Landing 1 4.2 2 8.40
Tread 18 1.95 0.3 10.53
Riser 19 1.95 0.15 5.56
Outside
Outer steps 1 18.91 0.90 17.02
Ramp 1 8.39 Area 8.39
7 PLASTER/PAINTING WORKS
7.1 Internal Plaster
7.1.1 Internal Plaster on Wall (1:6)
Ground floor
Classroom-1 1 21 2.905 61.01
Classroom-2 1 21 2.905 61.01
Classroom-3 1 21 2.905 61.01
Staircase 1 13.43 2.82 37.82
Wall Partition Between Male and Female Toilet 2 2.73 1.15 6.27
2 3.75 1.52 11.40
Partition Wall at Toilet
Boys Toilet 2 2.28 2.10 9.56
2 1.18 2.10 4.94
1 1.33 1.20 1.59
Girls Toilet 1 2.28 2.10 4.78
1 1.18 2.10 2.47
1 1.33 1.20 1.59
Disabled Toilet 1 1.82 2.88 5.22
1 2.35 2.88 6.76
Deduction
D1 -4 1.10 2.50 -5.50
D4 -1 1.00 2.50 -1.25
D5 -1 0.90 2.50 -1.13
W1 -8 1.10 1.13 -4.95
W3 -1 1.50 0.33 -0.24
V1 -8 1.10 0.55 -2.42
V2 -1 2.63 0.55 -0.72
V3 -1 2.70 0.55 -0.74
First floor
Classroom-3 1 21 2.905 61.01
Classroom-4 1 21 2.905 61.01
Classroom-5 1 21 2.905 61.01
Partition Wall at Computer Lab 2 3.38 1.20 8.10
2 0.25 1.20 0.60
Staircase 1 13.43 2.82 37.82
Deduction
D1 -6 1.10 2.50 -8.25
W1 -12 1.10 1.13 -7.43
W2 -1 1.50 1.08 -0.81
V1 -12 1.10 0.55 -3.63
Second floor
Classroom-6 1 21 2.905 61.01
Classroom-7 1 21 2.905 61.01
Classroom-8 1 21 2.905 61.01
Partition Wall at Principal/Administration 1 5.88 2.72 15.98
1 5.75 2.72 15.64
Staircase 1 13.43 2.82 37.82
Deduction
D1 -6 1.10 2.50 -8.25
D2 -1 1.00 2.10 -1.05
W1 -12 1.10 1.13 -7.43
W2 -1 1.50 1.08 -0.81
V1 -12 1.10 0.55 -3.63
Top Floor
1 23.15 2.40 55.51
Deduction
W2 -1 1.50 1.08 -0.81
D3 -2 1.10 1.90 -2.09
Total 750.32 sq.m
At Staircase Cover
Slab 1.00 8.30 5.30 43.99
Total 569.32 sq.m
Outer Beam
First floor level beam
Along grid 1 1 20.80 0.55 11.44
Along grid A and E 2 4.48 0.55 4.92
Landing beam 1 4.05 0.60 2.41
First Floor
Class Room Corner 4 1.18 3.00 14.10
Intermediate Corner 6 0.70 3.00 12.60
Corridor Column 5 1.90 3.00 28.50
Deduction
D1 -6 1.10 2.50 -16.50
W1 -12 1.10 1.13 -14.85
W3 -1 1.50 0.33 -0.49
V1 -12 1.10 0.55 -7.26
First Floor
Along grid 1 1 16.73 2.50 41.81
1 4.08 2.08 8.46
Along grid 2 1 16.73 2.50 41.81
Along grid A,E/(1-2) 2 4.48 2.50 22.38
Deduction
D1 -6 1.10 2.50 -16.50
W1 -12 1.10 1.13 -14.85
W2 -1 1.50 1.08 -1.61
V1 -12 1.10 0.55 -7.26
Second Floor
Along grid 1 1 16.73 2.50 41.81
1 4.08 2.08 8.46
Along grid 2 1 16.73 2.50 41.81
Along grid A,E/(1-2) 2 4.48 2.50 22.38
Deduction
D1 -6 1.10 2.50 -16.50
W1 -12 1.10 1.13 -14.85
W2 -1 1.50 1.08 -1.61
V1 -12 1.10 0.55 -7.26
Top Floor
Along Grid 1,3 2 4.08 2.10 17.12
Along Grid C,D 2 6.45 1.90 24.51
Deduction
D2 -2 1.00 2.10 -4.20
W2 -1 1.50 1.08 -1.62
8 MISCELLANEOUS
Total
8.3 Railling Length kg/m
Length
Staircase Railing
Ground Floor Lvl to First Floor Level
ISNB 40M(Horizontal Handrail) 1 6.28 6.28 3.56 22.36
25mm Square Pipe(Horizontal Bars) 4 6.19 24.74 0.85 21.03
Vertical 38mm Square Pipe 8 0.9 7.20 2.82 20.30
For Terrace
ISNB 40M(Horizontal Bars) 1 81.63 81.63 3.56 290.59
ISNB 32M(Horizontal Bars) 1 52.75 52.75 3.10 163.53
ISNB 32M(Vertical Bars) 36 0.36 12.89 3.10 39.95
25mm Square Pipe(Vertical Bars) 350 0.26 90.30 0.85 76.76
B Column
1 All Grid 15 20mm ɸ 16mm ɸ
Main Bar 20 2 7.11 213.30 2.47 526.85
20 2 4.04 121.20 2.47 299.36
16 4 3.56 213.60 1.59 339.62
16 4 6.55 393.00 1.59 624.87 6.29 5.97
0.125 0.125
0.7 0.46
0.345
0.158 0.1
Stirrups 0.25
Grid 1,2,3 3 10 209 1.20 752.40 0.62 466.49 0.1
Grid A,B,C,D,E 5 10 65 1.20 390.00 0.62 241.80 0.25
E GF Column
1 All Grid 15
Main Bar 20 2 7.20 216.00 2.47 533.52 20mmɸ 16mmɸ
16 4 6.96 417.60 1.59 663.98 6 6
1.2 0.96
0.345
0.158 0.1
F Staircase
1 First Flight
Top Main Bar 16 16 6.50 104.00 1.59 165.36 3 1.95
Bottom Main Bar 16 16 2.10 33.60 1.59 53.42 0.9 0.35
Top Distribution Bar 10 14 1.96 27.44 0.62 17.01 0.2
Bottom Distribution Bar 10 30 1.96 58.80 0.62 36.46 1
Extra Bar 16 15 2.00 30.00 1.59 47.70 0.2 0.9
2 Landing
Bottom bar in first flight 16 12 3.10 37.16 1.59 59.09 1
Top Distribution Bar 16 7 1.96 13.72 1.59 21.81 1
Bottom Distribution Bar 10 14 4.16 58.24 0.62 36.11
Top Distribution Bar 10 14 4.16 58.24 0.62 36.11 4.16
Extra Bar 16 15 2.00 30.00 1.59 47.70 1.88
3 Second Flight 1 0.21
Top Main Bar 16 12 6.50 78.00 1.59 124.02
Bottom main Bar 16 12 3.45 41.40 1.59 65.83 0.75 3
Bottom Distribution Bar 10 23 1.96 44.43 0.62 27.54 0.4
Top Distribution Bar 10 14 1.96 27.44 0.62 17.01 2.1 0.35
Extra Bar 16 30 2.00 60.00 1.59 95.40 1
4 Nosing Bar 10 20 1.96 39.20 0.62 24.30 2.1 0.35
4 Grid A 1 7.89
Top bar 20 2 9.78 19.56 2.47 48.31 0.945 0.945
16 1 9.22 9.22 1.59 14.66
Bottom bar 16 3 9.22 138.30 1.59 219.90 0.665 7.89 0.665
Stirupps 10 57 1.60 91.60 0.62 56.79
5 Grid B 1 7.89
Top bar 20 2 9.78 19.56 2.47 48.31 0.945 0.945
16 1 9.22 9.22 1.59 14.66
Bottom bar 16 3 9.22 138.30 1.59 219.90 0.665 7.89 0.665
Stirupps 10 57 1.60 91.60 0.62 56.79
6 Grid C 1 7.89
Top bar 20 2 9.78 19.56 2.47 48.31 0.945 0.945
16 1 9.22 9.22 1.59 14.66
Bottom bar 16 3 9.22 138.30 1.59 219.90 0.665 7.89 0.665
Stirupps 10 57 1.60 91.60 0.62 56.79
7 Grid D 1 7.89
Top bar 20 3 9.78 29.34 2.47 72.47 0.945 0.945
Bottom bar 16 3 9.22 138.30 1.59 219.90
Stirupps 10 57 1.60 91.60 0.62 56.79 0.665 7.89 0.665
8 Grid E 1 7.89
Top bar 20 3 9.78 29.34 2.47 72.47 0.945 0.945
Bottom bar 16 3 9.22 138.30 1.59 219.90
Stirupps 10 57 1.60 91.60 0.62 56.79 0.665 7.89 0.665
Secondary beam
1 Grid A1,B1,D1 3 7.89
Top bar 16 3 9.22 138.30 1.59 659.69 0.665 0.665
Bottom bar 16 3 9.22 138.30 1.59 659.69
Stirupps 10 56 1.35 75.94 0.62 141.24 0.665 7.89 0.665
Extra bar
Long span
0.96 0.96
H Bent up bar in primary and 16 30 3.01 90.3 1.59 143.58
secondary beam junction 0.42
0.25
I Landing Beam 4.85
Top bar 16 3 5 15 1.59 23.85 0.075 0.075
Bottom bar 16 3 5 15 1.59 23.85 0.2
Stirrups 1 10 42 1.35 56.7 0.62 35.154 0.1
0.375
0.375 0.55
Long Span 0.085 0.33
A-C 1
Main Bar Type A 8 19 13.92 264.48 0.4 105.79 0.45 Type A 0.45
Main bar Type B 8 19 14.12 268.24 0.4 107.30 0.085 0.085
6.2
D-E 1
Main Bar Type A 8 19 7.27 138.13 0.4 55.25
Main bar Type B 8 19 7.34 139.38 0.4 55.75
Distribution Bar 12
Along Grid 1 1 8 2 18 36.00 0.4 14.40
Along Grid 2 1 8 13 22.98 298.74 0.4 119.50 8.5
Along Grid 3 1 8 2 22.98 45.96 0.4 18.38
Along Grid A 1 8 2 8.5 17.00 0.4 6.80
Along Grid A1,B,B1 & D1 4 8 12 8.5 408.00 0.4 163.20
Along Grid C, D and E 3 8 5 8.5 127.50 0.4 51.00
3.75
Negative bar
Along Grid A1,B1 & D1 4 8 14 2.16 120.96 0.4 48.38 0.055 2.05 0.055
Along Grid 2( A-D and D-E) 2 8 11 2.06 45.32 0.4 18.13 0.055 1.95 0.055
Along Grid 2 (C-D) 1 8 4 2.17 8.69 0.4 3.48
0.055 2.06 0.055
1 FF Column
1.1 Grid A,B and E 9
Main Bar 20 2 6.48 116.64 2.47 288.10 20mmɸ 16mmɸ
16 4 6.24 224.64 1.59 357.18 6.48 6.24
0.345
0.158 0.1
2 Staircase
2.1 First Flight
Top Main Bar 16 16 7.08 113.28 1.59 180.12 3 1.95
Bottom Main Bar 16 16 2.10 33.60 1.59 53.42 0.9 0.35
Top Distribution Bar 10 14 1.96 27.44 0.62 17.01 0.2
Bottom Distribution Bar 10 30 1.96 58.80 0.62 36.46 1
Extra Bar 16 15 2.00 30.00 1.59 47.70 0.2 0.9
Landing
Bottom bar in first flight 16 12 3.10 37.16 1.59 59.09 1
Top Distribution Bar 16 7 1.96 13.72 1.59 21.81 1
Bottom Distribution Bar 10 14 4.16 58.24 0.62 36.11
Top Distribution Bar 10 14 4.16 58.24 0.62 36.11 4.16
Extra Bar 16 15 2.00 30.00 1.59 47.70
Projected Portion
Top Bar 16 1.96 5.00 9.80 1.59 15.58
Bottom Bar 16 1.96 5.00 9.80 1.59 15.58
1.88
2.2 Second Flight 1 0.21
Top Main Bar 16 12 7.08 84.96 1.59 135.09
Bottom main Bar 16 12 3.45 41.40 1.59 65.83 0.75 3
Bottom Distribution Bar 10 23 1.96 44.43 0.62 27.54 0.4
Top Distribution Bar 10 14 1.96 27.44 0.62 17.01 2.1 0.35
Extra Bar 16 30 2.00 60.00 1.59 95.40 1
Long Span
A-C 1
Main Bar Type A 8 19 13.92 264.48 0.4 105.79 0.45 Type A 0.45
Main bar Type B 8 19 14.12 268.24 0.4 107.30 0.085 0.085
6.2
D-E 1
Main Bar Type A 8 19 7.27 138.13 0.4 55.25
Main bar Type B 8 19 7.34 139.38 0.4 55.75
Projected Portion
Along Long Span 2
Grid A-C 8 8 12.00 192.00 0.4 76.80
Grid D-E 8 8 6.00 96.00 0.4 38.40
Distribution Bar 12
Along Grid 1 1 8 4 18 72.00 0.4 28.80
Along Grid 2 1 8 13 22.98 298.74 0.4 119.50 8.5
Along Grid 3 1 8 4 22.98 91.92 0.4 36.77
Along Grid A 1 8 4 8.5 34.00 0.4 13.60
Along Grid A1,B,B1 & D1 3 8 12 8.5 306.00 0.4 122.40
Along Grid B,C, D and E 4 8 5 8.5 170.00 0.4 68.00
3.75
Negative bar
Along Grid A1,B1 & D1 3 8 14 2.16 90.72 0.4 36.29 0.055 2.05 0.055
Along Grid 2( A-C and D-E) 3 8 11 2.06 67.98 0.4 27.19 0.055 1.95 0.055
Along Grid 2 (C-D) 1 8 4 2.17 8.69 0.4 3.48
0.055 2.06 0.055
Grid C and D 6
Main Bar 20 2 6.48 77.76 2.47 192.07
16 4 6.24 149.76 1.59 238.12
0.345
0.158 0.1
7 Staircase
7.1 First Flight
Top Main Bar 16 16 6.50 104.00 1.59 165.36 3 1.95
Bottom Main Bar 16 16 2.10 33.60 1.59 53.42 0.9 0.35
Top Distribution Bar 10 14 1.96 27.44 0.62 17.01 0.2
Bottom Distribution Bar 10 30 1.96 58.80 0.62 36.46 1
Extra Bar 16 15 2.00 30.00 1.59 47.70 0.2 0.9
Landing
Bottom bar in first flight 16 12 3.10 37.16 1.59 59.09 1
Top Distribution Bar 16 7 1.96 13.72 1.59 21.81 1
Bottom Distribution Bar 10 14 4.16 58.24 0.62 36.11
Top Distribution Bar 10 14 4.16 58.24 0.62 36.11 4.16
Extra Bar 16 15 2.00 30.00 1.59 47.70
0.25
Bent up bar in primary and
16 18 3.01 54.18 1.59 86.15 4.47
secondary beam junction
0.765 0.765
0.2
9 Landing Beam 0.1
Top bar 16 3 6 18 1.59 28.62 0.375
Bottom bar 16 3 6 18 1.59 28.62
Stirrups 1 10 42 1.35 56.7 0.62 35.154
Long Span
A-C 1
Main Bar Type A 8 19 14.16 269.04 0.4 107.62 0.45 Type A 0.45
Main bar Type B 8 19 14.86 282.34 0.4 112.94 0.085 0.085
6.2
D-E 1
Main Bar Type A 8 19 8.16 155.04 0.4 62.02 Type B
Main bar Type B 8 19 8.86 168.34 0.4 67.34
2.4 1.88 2.05
A-E Grid (2-3) 1
Main bar
Main Bar Type A 8 13 25.76 334.88 0.4 133.95
Main bar Type B 8 13 27.16 353.08 0.4 141.23
Projected Poetion 8
Along Long Span
Along Grid 1 1
Grid A-C 8 16 14.00 224.00 0.4 89.60
Grid D-E 8 16 8.00 128.00 0.4 51.20
Along Grid 3 1 12
Grid A-C 8 22 14.00 308.00 0.4 123.20
Grid D-E 8 22 8.00 176.00 0.4 70.40
0.345
Grid C-D 1
Long Span Type A
A-C 1
Main Bar Type A 8 20 9.3 186.00 0.4 74.40 6.2
Main bar Type B 8 20 9.70 194.00 0.4 77.60
Type B
Distribution Bar
Along Grid C, D 2 8 5 8.5 85.00 0.4 34.00
3.75
Negative bar
Along Grid 2 (C-D) 1 8 4 2.17 8.69 0.4 3.48
0.055 2.06 0.055
14 Lintel Bands
Ground floor level
Main Bar
Along grid A,B,C,D,E 10 10 2 4.93 98.60 0.62 61.13
Along grid 1 3 10 2 6.03 36.18 0.62 22.43
Along grid 2 3 10 2 6.03 36.18 0.62 22.43 0.075 0.075
At store 2 10 2 6.03 24.12 0.62 14.95 6.03
Tie Bar 0.075 0.075
Along grid A,B,C,D,E 10 8 38 0.40 152.00 0.40 60.80 0.25
Along grid 1 3 8 38 0.40 45.60 0.40 18.24
Along grid 2 3 8 38 0.40 45.60 0.40 18.24
At store 2 8 38 0.40 30.40 0.40 12.16
15 Sill Bands
Ground floor level
Main Bar
Along grid A,B,C,D,E 10 10 2 4.93 98.60 0.62 61.13
Along grid 1 3 10 2 6.03 36.18 0.62 22.43
Along grid 2 3 10 2 6.03 36.18 0.62 22.43 0.075 0.075
At store 2 10 2 6.03 24.12 0.62 14.95 5.88
Tie Bar 0.075 0.075
Along grid A,B,C,D,E 10 8 38 0.40 152.00 0.40 60.80 0.25
Along grid 1 3 8 38 0.40 45.60 0.40 18.24
Along grid 2 3 8 38 0.40 45.60 0.40 18.24
At store 2 8 38 0.40 30.40 0.40 12.16
16 Band at Parapet
Band at Top Floor Wall 2 10 2 6.45 25.80 0.40 10.32
1 10 2 48.00 96.00 0.40 38.40
1 10 2 13.00 26.00 0.40 10.40
1 10 2 30.00 60.00 0.40 24.00
Tie Bar 1 8 640 0.40 256.00 0.40 102.40
17 Vertical Bands
Ground Floor 12
Main Bar 10 2 2.95 70.80 0.62 43.90
Tie Bar 8 17 0.40 81.60 0.40 32.64
First Floor 12
Main Bar 10 2 2.95 70.80 0.62 43.90
Tie Bar 8 17 0.40 81.60 0.40 32.64
Second Floor 12
Main Bar 10 2 2.95 70.80 0.62 43.90
Tie Bar 8 17 0.40 81.60 0.40 32.64
Total 41014.65 kgs
41.01 MT.
6950
200
short span
4400
4400
200
slab
Along Y axis
1915
110 8 1 34 9.03 306.85 0.40 121.21 Main Bar
7000
distribution bar 8 2 10 7.00 140.00 0.40 55.30
Corner bars 10 12 3 0.60 21.60 0.62 13.33
Concealed beam
main bars 10 2 4 6.60 52.80 0.62 32.58
Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)
1 Site Clearance
Infront of Bldg 1 16.50 2.50 41.25
1 6.00 1.50 9.00
Side of Bldg 1 6.00 2.50 15.00
From Gate to Bldg 1 23.50 2.50 58.75
At Gate 1 5.00 2.50 12.50
Septic Tank 1 8.75 3.95 34.56
Soak Pit 1 8.55 Area 8.55
For Sewer Manhole (Rectangular) 2 1.00 1.00 2.00
Total 181.61 sq.m
2 Earth Work Excavation
Infront of Bldg 1 16.50 2.50 0.15 6.19
1 6.00 1.50 0.15 1.35
Side of Bldg 1 6.00 2.50 0.15 2.25
From Gate to Bldg 1 23.50 2.50 0.15 8.81
At Gate 1 5.00 2.50 0.15 1.88
4 Boulder Soling
Infront of Bldg 1 16.50 2.50 0.15 6.19
1 6.00 1.50 0.15 1.35
Side of Bldg 1 6.00 2.50 0.15 2.25
From Gate to Bldg 1 23.50 2.50 0.15 8.81
At Gate 1 5.00 2.50 0.15 1.88
Chain Link Fence 55 0.15 0.15 0.15 0.19
Soling For Gate Column
Column 2 0.90 0.90 0.20 0.32
Stone Soling for Flag Pole 1 0.70 0.80 0.35 0.20
Total 21.18 cu.m
5 P.C.C.(1:3:6) Works
PCC For Gate Column
B Column
Gate Column 2 0.30 0.30 2.95 0.53
Top RCC Coping 2 0.59 0.59 0.05 0.03
2 0.175 0.05 0.02
Total 0.99 cu.m
17 External Plaster
Column Inside face 4 0.54 1.64 3.54
Column Outside face 2 1.2 0.20 0.48
4 0.54 1.70 3.67
Deduct -2 0.3 1.40 -0.84
Top Coping 2 2.36 0.05 0.24
4 0.59 0.30 0.71
Total 7.80 sq.m
19 Flag Pole
75 Dia GI Pipe 2.00 1 2.00
Total 2.00 nos
2 Concrete Works
2.1 PCC
2.1.1 PCC Work (1:3:6)
Below Water Tank 1 3.35 3.1 0.075 0.78
Total 0.78 Cu.m.
1.915 1.915
3.02
1.915 1.915
3.29
1.884 1.884
0.05
0.49 0.49
1.884 1.884
0.05
0.49 0.49
0.592
0.592 0.6 0.6
D. Horizontal Bars(outer 4
0.3 0.3
1 Shorter Span 10 20 3.62 289.6 0.62 179.552
3.02 3.02
0.3 0.3
3.27 3.27
0.3 0.3
E. Base Slab bar 4
1 Shorter Span 10 32 3.14 401.92 0.62 249.19 3.045
0.05 0.05