Professional Documents
Culture Documents
Shree Sarbodhaya LSS, Chhoprak
Shree Sarbodhaya LSS, Chhoprak
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
7.1.1 ON INNER WALL sq.m 923.13 600.00 553,878.00 947.85 568,709.19 923.13 553,878.00 24.72 14,831.19 102.68%
7.1.2 ON CEILING (1:4) sq.m 360.86 500.00 180,430.00 495.87 247,936.89 360.86 180,429.96 135.01 67,506.93 137.41%
7.1.3 ON OUTER WALL (1:6)
7.1.3.1 EXTERNAL PLASTER sq.m 430.90 600.00 258,540.00 775.79 465,474.24 697.26 418,358.85 78.53 47,115.39 180.04%
7.1.4 EXTERNAL PLASTER WITH CEMENT PUNNING sq.m 35.21 700.00 24,647.00 35.66 24,962.00 35.66 24,962.00 0.00 - 101.28%
7 PAINTING WORKS
7.2.1 DISTEMPER PAINT sq.m 1599.82 200.00 319,964.00 1,817.29 363,457.50 1659.67 331,934.00 157.62 31,523.50 113.59%
7.2.2 EXTERIOR WEATHER COAT PAINT sq.m 461.26 350.00 161,441.00 775.79 271,527.81 411.73 144,105.50 364.06 127,422.31 168.19%
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG sq.m 369.72 550.00 203,346.00 - - 0.00 - 0.00 - 0.00%
7.2.4 ENAMEL PAINT sq.m 392.72 400.00 157,088.00 409.43 163,771.80 347.79 139,116.00 61.64 24,655.80 104.25%
8 MISCELLANEOUS
8.2 CEMENT BOARD WALL sq.m 32.61 6,500.00 211,965.00 34.16 222,040.00 32.61 211,965.00 1.55 10,075.00 104.75%
8.3 RAILING kg 1496.50 220.00 329,230.00 1,527.10 335,962.96 1287.60 283,272.00 239.50 52,690.96 102.05%
8.4 PUMP SHED nos. 1.00 80,000.00 80,000.00 1.00 80,000.00 0.00 - 1.00 80,000.00 100.00%
3 ELECTRICAL WORKS
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure no. 2.00 12,000.00 24,000.00 2.00 24,000.00 2.00 24,000.00 0.00 - 100.00%
1.2 Stand Alone 6 A DP MCB with Enclosure no. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2.1 2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper rm 100.00 800.00 80,000.00 97.00 77,600.00 100.00 80,000.00 -3.00 (2,400.00) 97.00%
2.2 conductor wires mutistranded copper conductor wires + 1
2 Nos 2.5 Sq.mm rm 50.00 250.00 12,500.00 51.00 12,750.00 0.00 - 51.00 12,750.00 102.00%
B Nos. 1.5sq
School mm multistranded Cu wire
Blocks
1 DISTRIBUTION BOARDS nos.
1.1 Ground Floor nos. 2.00 30,000.00 60,000.00 2.00 60,000.00 2.00 60,000.00 0.00 - 100.00%
1.2 First Floor nos. 2.00 22,000.00 44,000.00 2.00 44,000.00 2.00 44,000.00 0.00 - 100.00%
1.3 Second Floor nos. 1.00 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 0.00 - 100.00%
1.4 Stand Alone 6 A DP MCB with Enclosure nos. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm
2.1 Multistranded Cu wire rm 15.00 600.00 9,000.00 15.00 9,000.00 15.00 9,000.00 0.00 - 100.00%
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm
2.2 Multistranded Cu wire rm 15.00 500.00 7,500.00 10.00 5,000.00 15.00 7,500.00 -5.00 (2,500.00) 66.67%
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.2 rm 30.00 250.00 7,500.00 16.00 4,000.00 30.00 7,500.00 -14.00 (3,500.00) 53.33%
Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point pts. 74.00 700.00 51,800.00 75.00 52,500.00 74.00 51,800.00 1.00 700.00 101.35%
3.2 Two Way Light Point pts. 3.00 900.00 2,700.00 3.00 2,700.00 3.00 2,700.00 0.00 - 100.00%
3.3 Ceiling Fan Point pts. 8.00 900.00 7,200.00 8.00 7,200.00 6.00 5,400.00 2.00 1,800.00 100.00%
4 16 A Universal Pin Light Power Socket Wiring pts. 1.00 900.00 900.00 1.00 900.00 1.00 900.00 0.00 - 100.00%
5 6A Universal Pin Light Power Supplying, wiring, testing and
Socket Wiring pts. 43.00 700.00 30,100.00 43.00 30,100.00 43.00 30,100.00 0.00 - 100.00%
commissioning and putting into operation for 6 A light power
6 Switch
point Socket
using 2 x Outlets
4 sq mm + 1 x 2.5 Sq mm multi stranded
6.1 copper
16 conductor,
A Universal Pin 1100
Lightvolts grade,
Power PVC insulated
Socket Wiring wires nos. 1.00 1,500.00 1,500.00 1.00 1,500.00 1.00 1,500.00 0.00 -
drawn through pre
6A Universal Powerinstalled
Switch25Socket
mm dia 2 mm
Supplying, thick HDP
wiring, pipe,
testing
6.2 nos. 43.00 900.00 38,700.00 44.00 39,600.00 43.00 38,700.00 1.00 900.00 102.33%
cablecommissioning
and sleeve/support but andincluding specified
putting into dia pipes
operation for 6 A light
7 Sweep
power Ceiling/Exhaust
concealed in wall
point usingand Fans/
2 xfloor Wall
4 sqincluding
mm + 1 xall Fan
2.5fixing
Sq mm andmulti
connecting
7.1 materials.
stranded The rateCeiling
1200 mm copper
Sweep for point
conductor,Fanwiring
1100 shall
volts include
grade, PVCthe circuit no. 2.00 4,500.00 9,000.00 2.00 9,000.00 4.00 18,000.00 -2.00 (9,000.00) 100.00%
wiring from
insulated deginated
wires drawnDistribution
through pre Board (DB)25
installed upmmto the
diafirst
2
7.2 400 mm Sweep Wall Fan no. 6.00 3,500.00 21,000.00 6.00 21,000.00 12.00 42,000.00 -6.00 (21,000.00) 100.00%
power
mm pointHDP
thick thenpipe,
the looping between sockets.
cable sleeve/support butThe cost shall
including
7.3 225mm
be dia
excluding
specified diaM/D Exhaust
modular
pipes Fan inswitch
formation
concealed wall and sockets
floorand their all
including nos. 2.00 6,000.00 12,000.00 2.00 12,000.00 2.00 12,000.00 0.00 - 100.00%
8 flushing
fixing andGIconnecting
box but including
Light Fixtures/Luminaires &GIAccessories
materials. fish
Thewire,
ratecutting
for pointandwiring
filling
chasesinclude
shall for recessed pipes wiring
the circuit as deemedfrom as deginated
per drawing and lay out
Distribution
plan all(DB)
Board complete.
up to the first power point then the looping
between sockets. The cost shall be excluding modular
formation switch sockets and their flushing GI box but
Prepared by contractor
including GI fish wire, cutting Checked andby Consultant,
filling chases for DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
recessed pipes as deemed as per drawing and lay out plan
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
8.1 24 W LED Recessed Mounted Square type nos. 4.00 4,500.00 18,000.00 4.00 18,000.00 4.00 18,000.00 0.00 - 100.00%
8.2 18 W LED Surface Mounted Square type CRCA Powder nos. 22.00 2,700.00 59,400.00 22.00 59,400.00 22.00 59,400.00 0.00 - 100.00%
8.3 Coated
18 withRecessed
W LED PMMA Diffuser
Mountedhaving
Square6000
typeKCRCA
ColorPowder nos. 12.00 2,700.00 32,400.00 12.00 32,400.00 12.00 32,400.00 0.00 - 100.00%
Temperature,
Coated IP20 rated.
withSurface
PMMA Diffuser Cylindrical
having 6000type
K Color
8.4 12 W LED Mounted CRCA Powder nos. 15.00 2,400.00 36,000.00 15.00 36,000.00 13.00 31,200.00 2.00 4,800.00 100.00%
Temperature,
Coated IP20 rated.
withRecessed
PMMA Diffuser
8.5 12 W LED Mountedhaving 6000
Crrcular K CRCA
type Color Powder nos. 10.00 2,400.00 24,000.00 10.00 24,000.00 10.00 24,000.00 0.00 - 100.00%
Temperature,
Coated IP20 rated.
withLight
PMMA Diffuser
8.6 LED Wall made of highhaving 6000 K aluminium
grade die-cast Color nos. 3.00 1,800.00 5,400.00 3.00 5,400.00 3.00 5,400.00 0.00 - 100.00%
Temperature,
Powder IP20 rated.
8.7 9W LEDCoated
Surface with PMMACylindrical
Mounted Diffuser having 6000 K
type CRCA Color
Powder nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
Temperature,
Coated with IP65 rated
PMMA with 7having
Diffuser W LED Lamp.
8.8 6W LED Recessed Mounted Circular6000
type K Color nos. 3.00 1,800.00 5,400.00 3.00 5,400.00 3.00 5,400.00 0.00 - 100.00%
Temperature, IP20 rated.
8.9 7W LED T5 Slim Mirror Light nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
9 Pull Box nos. 6.00 700.00 4,200.00 6.00 4,200.00 6.00 4,200.00 0.00 - 100.00%
10 External Post Top Light Pole nos. 6.00 7,500.00 45,000.00 6.00 45,000.00 6.00 45,000.00 0.00 - 100.00%
11 Post Top External Light Fixtures nos. 6.00 9,800.00 58,800.00 6.00 58,800.00 6.00 58,800.00 0.00 - 100.00%
12 Earthing & Lighting Protection
12.1 Chemical Earthing nos. 6.00 45,000.00 270,000.00 6.00 270,000.00 6.00 270,000.00 0.00 - 100.00%
12.2 Earthing Bar nos. 6.00 2,200.00 13,200.00 6.00 13,200.00 6.00 13,200.00 0.00 - 100.00%
13 Earthing Strip/Wires
13.1 25 x 3 mm GI strip mtr. 130.00 300.00 39,000.00 132.00 39,600.00 130.00 39,000.00 2.00 600.00 101.54%
13.2 12 SWG Cu wire mtr. 30.00 200.00 6,000.00 31.00 6,200.00 30.00 6,000.00 1.00 200.00 103.33%
14 Earth Test link nos. 2.00 1,500.00 3,000.00 2.00 3,000.00 2.00 3,000.00 0.00 - 100.00%
C Solar PV System
1 Solar PV Panel nos. 4.00 26,000.00 104,000.00 4.00 104,000.00 4.00 104,000.00 0.00 - 100.00%
2 Tubular Deep Cycle Battery nos. 2.00 30,000.00 60,000.00 2.00 60,000.00 2.00 60,000.00 0.00 - 100.00%
3 Hybrid Inverter 1.00 100,000.00 100,000.00 1.00 100,000.00 1.00 100,000.00 0.00 - 100.00%
D FIRE EXTINGUISHER
a Supplying Fire extinguisher ABC stored Pressure 5.0kg size nos. 2.00 8,000.00 16,000.00 2.00 16,000.00 0.00 - 2.00 16,000.00 100.00%
b ABC stored pressure
Dry Powder type Fire conforming
Fire Extinguisher extinguisher.to BS 5423:1987 or nos. 1.00 8,000.00 8,000.00 1.00 8,000.00 0.00 - 1.00 8,000.00 100.00%
as given in BOQ. The Dry Powder agents shall be mono-
ammonium phosphate and ammonium sulphate base as per
BILL No. below.all
specidfied 4. SANITARY WORKS
complete
A PIPING WORKS
1 WATER SUPPLY INSTALLATION
a) CPVC pipes
- 40 mm Rm 60 1,600.00 96,000.00 55.00 88,000.00 10.00 16,000.00 45.00 72,000.00 91.67%
- 25 mm Rm 70 1,000.00 70,000.00 18.00 18,000.00 15.00 15,000.00 3.00 3,000.00 25.71%
- 20 mm Rm 11 700.00 7,700.00 10.00 7,000.00 5.00 3,500.00 5.00 3,500.00 90.91%
- 15 mm Rm 4 500.00 2,000.00 2.50 1,250.00 15.00 7,500.00 -12.50 (6,250.00) 62.50%
c) CPVC Ball Valve
- 40 mm No. 4 2,000.00 8,000.00 2.00 4,000.00 2.00 4,000.00 0.00 - 50.00%
- 25 mm No. 4 900.00 3,600.00 3.00 2,700.00 2.00 1,800.00 1.00 900.00 75.00%
20mm No. 2 400.00 800.00 2.00 800.00 2.00 800.00 0.00 - 100.00%
40 mm dia Gun Metal Check valve No. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 0.00 - 100.00%
d) Electric Centrifugal Water Pump Set 1 12,500.00 12,500.00 1.00 12,500.00 - 1.00 12,500.00 100.00%
e) 1000 litres capacity Plastic cyllindrical vertical water storage No. 1 34,000.00 34,000.00 1.00 34,000.00 1.00 34,000.00 0.00 - 100.00%
tank
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
2 SEWER, RAIN AND WASTE WATER INSTALLATION
PVC SWR
110 mm Rm 33 1,400.00 46,200.00 32.00 44,800.00 15.00 21,000.00 17.00 23,800.00 96.97%
B SCHOOL BLOCKS
1 SANITARY INSTALLATION
a Stainless Steel Kitchen Sink Set 1 35,000.00
b CP self closing bib cock No 1 4,000.00 4,000.00 1.00 4,000.00 - 1.00 4,000.00 100.00%
c PVC Multi-floor trap with cover No. 1 600.00 600.00 1.00 600.00 - 1.00 600.00 100.00%
CP Waste Coupling and PVC bottle trap for water trough
d No. 1 1,500.00 1,500.00 1.00 1,500.00 - 1.00 1,500.00 100.00%
2 SANITARY INSTALLATION
a Water Closet set Set 1 34,000.00 34,000.00 1.00 34,000.00 - 1.00 34,000.00 100.00%
b 580x480mm Orissa Pan Set 2 3,100.00 6,200.00 2.00 6,200.00 - 2.00 6,200.00 100.00%
c Hand wash basin Set 1 8,000.00 8,000.00 1.00 8,000.00 - 1.00 8,000.00 100.00%
d Urinal Set 2 110,000.00 220,000.00 2.00 220,000.00 - 2.00 220,000.00 100.00%
e CP self closing bib cock No 6 4,000.00 24,000.00 6.00 24,000.00 - 6.00 24,000.00 100.00%
f CP spreader for Urinal Set 2 2,500.00 5,000.00 2.00 5,000.00 - 2.00 5,000.00 100.00%
g CP Toilet Paper Holder heavy No. 1 2,600.00 2,600.00 1.00 2,600.00 1.00 2,600.00 0.00 - 100.00%
h 15mm CP Commode Spray with plastic head No. 1 2,000.00 2,000.00 1.00 2,000.00 - 1.00 2,000.00 100.00%
i PVC Multi-floor trap with cover No. 5 600.00 3,000.00 5.00 3,000.00 - 5.00 3,000.00 100.00%
j CP Waste Coupling and PVC bottle trap for water trough No. 2 1,500.00 3,000.00 2.00 3,000.00 - 2.00 3,000.00 100.00%
k 40 mm SS Grab bar of 600mm Length - Side Set 1 4,500.00 4,500.00 1.00 4,500.00 - 1.00 4,500.00 100.00%
l 40 mm SS Grab bar of 600mm Length - Rear Set 1 4,500.00 4,500.00 1.00 4,500.00 - 1.00 4,500.00 100.00%
m CP Foldable Hinge Set 2 5,500.00 11,000.00 2.00 11,000.00 1.00 5,500.00 1.00 5,500.00 100.00%
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
20 FLAG POLE nos. 2.00 25,000.00 50,000.00 2.00 50,000.00 2.00 50,000.00 0.00 - 100.00%
-
CIVIL WORKS-RESERVOIR TANK -
1 EARTH WORK -
1.1 SITE CLEARANCE AND MOBILIZATION sq.m 22.31 100.00 2,231.00 22.31 2,231.00 22.31 2,231.00 0.00 - 100.00%
1.2 EARTHWORK IN EXCAVATION cu.m 24.58 400.00 9,832.00 24.57 9,828.72 24.57 9,828.72 0.00 - 99.97%
1.3 EARTH BACK FILLING cu.m 4.02 300.00 1,206.00 4.01 1,202.85 4.01 1,202.85 0.00 - 99.74%
1.4 BOULDER SOLING cu.m 2.08 6,000.00 12,480.00 2.08 12,462.00 2.08 12,462.00 0.00 - 99.86%
2 CONCRETE WORKS
2.1 P.C.C (1:3:6) cu.m 0.78 14,000.00 10,920.00 0.78 10,904.25 0.78 10,904.25 0.00 - 99.86%
2.2 P.C.C FOR R.C.C WORKS cu.m 7.42 20,000.00 148,400.00 7.41 148,295.00 7.41 148,295.00 0.00 - 99.93%
2.3 SILICA CEMENT ADMIXTURE kg 74.20 300.00 22,260.00 74.15 22,244.25 74.15 22,244.25 0.00 - 99.93%
2.4 STEEL REINFORCEMENT Mt 1.46 130,000.00 189,800.00 1.58 204,902.61 1.57 203,977.54 0.01 925.07 107.96%
2.5 FORMWORKS sq.m 54.93 800.00 43,944.00 56.46 45,170.80 56.46 45,170.80 0.00 - 102.79%
3 PLASTERING/WALL FINISHING WORKS
INTERNAL PLASTER ON WALL (1:4) WITH CEMENT
3.1.1 sq.m 33.66 700.00 23,562.00 35.46 24,824.45 27.57 19,301.45 7.89 5,523.00 105.36%
PUNNING
4 WATERPROOFING WORKS sq.m 33.66 550.00 18,513.00 35.46 19,504.93 27.57 15,165.43 7.89 4,339.50 105.36%
- - - 0.00 - 0.00 -
FURNITURE WORKS lot 1 4,000,000.00 4,000,000.00 1.00 4,000,000.00 1.00 4,000,000.00 0.00 - 100.00%
Total 35,254,804.90 35,280,032.74 32,354,943.32 2,925,089.43
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Government of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (Education)
District Level Project Implementation Unit (Education),Gorkha
Emergency School Reconstruction Project (ESRP), JICA Loan No. : NE-P11
Contract Bills
FINAL INTERIM PAYMENT CERTIFICATE
Period: 15th November 2018 to 14th January 2020
Name of School: Shree Sarbodhaya L. S. School Payment Voucher no:
Name of Contractor:Sharma-A.M Joint Venture Date of payment:
Contract Number:ESRP/MOE/CLPIU/074/075-GORKHA-15 Page no of measurement book:
Serial no. of payment bills: 7
Voucher no.of previous payment bills:
Date of order for commencement of work: 15th November, 2018
Date of work to be completed: 14th January, 2020
Date of completion of work:
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
BILL NO.1 PRELIMINARIES/TEMPORARY WORKS
MOBILIZATION AND DEMOBILIZATION
1 L.S. 1.00 500,000.00 500,000.00 1.00 500,000.00 0.50 250,000.00 0.50 250,000.00 100.00%
Mobilization of the construction by constructing temporaty
acomodation
SITE OFFICE forESTABLISHMENT
labours and site staff with required suitable Per
2 facilities and 15.00 25,000.00 375,000.00 15.00 375,000.00 16.00 400,000.00 -1.00 (25,000.00) 100.00%
Providing andkeeping
Maintaining the same Site inOffice
good of hygenic
two Roomsconditionhavingfor Month
entire project completion
total Area INFORMATION
20 sq.m for the BOARD time. Demolition of
use of Client and Consultantthe same and
PROJECT
3 cleaning
includingthe site after completion
office of thefileconstruction activities nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 0.00 - 100.00%
Providing and chair,
FixingTable, Lockable
of Project cabinet,board
Information Stationery
with
all complete.
Items (Ink,Text Paper,[Note:
Pen, 50% payment
Pencils etc.), shall be and
1 Computer made after
1required
Printer
approved
SAFETY SIGN in appropriate
BOARD location including all
4 completion
with all of
necessary mobilization
set up. all and
complete remaining
as per 50%
instruction after
of nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 0.00 - 100.00%
fixing accessories
Providing and Fixing as per drawingSign
of per
Safety all complete.
Board with approved Text
completionThe
engineer. of works
Specificationas contract]
of computer shall not be less than
and Sinage
BARRICADING including required fixing accessories as per
5 (19.5" led monitorWORKS with Core i5, 7th Generation, 500 gb Hdd, R.m 90.00 2,000.00 180,000.00 90.00 180,000.00 90.00 180,000.00 0.00 - 100.00%
drawing
Barricading all complete.
between
8gb ddr 4 ram), Printer the should School
function Academic
at least ofarea and
Printing,
Construction
DISMANTLING area
Scanning and Photocopy with OF 1.8ofmCOMPLETELY
A4highsizeCGI Sheet fixed
documents. to Bamboo
DAMAGED
Providing and
6 support frame all complete as per instruction of Engineer. sq.m 186.60 5,000.00 933,000.00 179.00 895,000.00 179.00 895,000.00 0.00 - 95.93%
BUILDING
Maintaining all above items on Rental Basis for entire project
Demolition of existing damaged
completionMATERIALS
SAFETY time. & SITEbuilding SAFETY safely and handover
7 of the reusable L.S. 1.00 100,000.00 100,000.00 1.00 100,000.00 0.94 94,000.00 0.06 6,000.00 100.00%
Providing and materials
Maintaining to the school authority,
Construction Safety storing
Measures them in
to the location
Construction Siteshownwith by theSafety schoolmeasures
and disposing debris
CONSTRUCTION OFproper
NEW TLC to person and
8 including
work area transportation
(Helmet, of debris ,cleaning site etc. Glove,
as per sq.m 104.82 3,000.00 314,460.00 104.82 314,460.00 104.82 314,460.00 0.00 - 100.00%
Construction of new Shoes, Temporary FirstLearning
Aid Kit,Centre(TLC),
Clothing, with
specification
Guard Rail andedge
for instruction
protection,of Engineer.Net, Safety rope, Fall
Locally
LAB Available
TEST(WATER materials
TEST) (CGISafetySheet and Bamboo etc.), rate
9 Protection
shall include etc.) as required
all Materials by the Contract Clause GCC 24 and job 1.00 7,500.00 7,500.00 - - 0.00 - 0.00 - 0.00%
Testing and Providing LabwithTestfixing
Report charge.
for Quality of Water in
Specification division 1 "GENERAL REQUIREMENT
Water
TEMPORARY Stream (Up and Down streem) located near by
10 CLAUSE 8(C)".TOILETThe number of Safety Materials Personal nos. 2 150,000.00 300,000.00 2.00 300,000.00 2.00 300,000.00 0.00 - 100.00%
Construction of
Construction sitetemporary
before Starting and CGI after completion of
Protecting Equipments (PPE) toilet
shall be withminimumSheet but notfixed
limited to
construction
Bamboo work.
support Thisand
frame Testallhas to be done
necesary itemstoincluding
mark the affect
ROAD REPAIR
to 35 sets. Payment AND shallMAINTENANCE
be made in Prorata Basis for Septic
entire
11 of construction
pit, Pipeline, workPan
Toilet in water
etc. forstream. project completion time Km 4.00 50,000.00 200,000.00 4.00 200,000.00 4.00 200,000.00 0.00 - 100.00%
Providing
duration of and Maintaining
project. the entire
roads as necessary to avoid
all complete
blockage as per Instruction
by Landslides of Engineer.
and Rockfall Rate shall
for regular include
transport of
all Material materials
construction cost withand fixing,
site construction
inspection during charges and
overall
BILL NO. 2 CIVIL WORKS- BUILDING
demolition &period.
construction cleaning Rate ofshall
the sameinclude after
all completion
Material cost ofwith
the
SITE CLEARANCE
construction activities & MOBILIZATION:
all complete.
1.1 demolition charges, cleaning, fixing & construction charges of sq.m 701.87 100.00 70,187.00 642.41 64,241.35 696.52 69,652.00 -54.11 (5,410.65) 91.53%
Clearing and grubbing the site for construction by removing
the same after
150mm thick top IN completion
soilEXCAVATION
including of bushes,
the construction activities all
EARTHWORK
complete. : small trees, leveling of
1.2 undulated ground, shortinginand top cu.m 315.17 400.00 126,068.00 317.72 127,088.50 289.67 115,866.89 28.05 11,221.61 100.81%
Excavation in foundations all stacking/storing
type of soils forselected foundation,
soil for reuse
trenches, footing, in pitslandscaping
etc. to works, disposing unsuitable
EARTH BACK FILLING : the required depth including
1.3 materials
dewatering from site, etc., or all complete means as peretc.drawings, per cu.m 204.21 300.00 61,263.00 236.58 70,972.99 191.14 57,342.00 45.44 13,630.99 115.85%
Back fillingbyin manualfoundation mechanical
and sides of foundationas with
specifications
specifications and
with instructions
allfrom of the Engineer.
contractor’s ownat machinery and
approved soil
BOULDER SOLING : obtained the excavation site and stacked
1.4 equipment's,
at site or broughtprovidingfrom crossinginoflayer
outside track,not shoring,
exceeding strutting,
cm cu.m 98.81 6,000.00 592,860.00 98.87 593,222.73 78.96 473,730.45 19.92 119,492.28 100.06%
Providing and laying uncoursed hand packed Dry Rubble15 Stone
timbering and buttressing
thick (compacted thickness) with appropriate
including materials andsoil, all
soling
SAND in foundation,
FILLING : under floor plinthtransportation
with out any of special
1.5 such measures
spreading of necessary
in required to retain
line and level, in position
sprinkling the
water,sides of
ramming, the cu.m 4.98 6,000.00 29,880.00 4.65 27,900.00 0.00 - 4.65 27,900.00 93.37%
dressing
Providing and stone
filling including filling
sand inrefilling
soak pit. interstices with suitable
foundation
compacting pitwith
and including
mechanical rammers, theallexcavated
completematerial
testing,
as per
etc., all
quarry
drawings, waste or stone
specifications and chips or quarry
instruction ofand sand, watering,
the Engineer.
with watering,
complete perramming,
as using drawing, leveling
specificationthe site disposing off
and compaction
instructions of the
the
compacting appropriate mechanical means
surplus/unusable earth to outside the construction premises, etc.
Engineer.
with all contractors materials, handling, placing etc. all
all complete as per drawings, specifications and instructions of
complete as per drawings, specifications and instruction of the
the Engineer.
Prepared by contractor Checked
Engineer. The complete item including all leadby Consultant, DSC
& lift. Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
CONCRETE WORKS
2.1.1 cu.m 13.20 14,000.00 184,800.00 14.09 197,314.25 13.78 192,920.00 0.31 4,394.25 106.77%
P.C.C (1:3:6)
Providing
P.C.C and WORKS
(1:2:4) laying machine mixed Plain Cement Concrete of
2.1.2 nominal mix cu.m 27.19 16,000.00 435,040.00 24.18 386,819.16 19.73 315,680.00 4.45 71,139.16 88.92%
Providing and1:3:6laying (1 machine
cement : mixed 3 sandPlain : 6 coarse
Cement aggregate
Concrete ) for
of
leveling course
nominal mix 1:2:4 in foundations
cement : and
(1 WORKS 2: sandunder floor ofaggregate
: 4 coarse building,)etc.
for
P.C.C. FOR R.C.C.
2.2 in all level
leveling withinbroken
course foundationsstone aggregate under of
andmachine floorsizeofnot more than
building, etc. cu.m 240.98 20,000.00 4,819,600.00 240.41 4,808,165.34 224.25 4,485,024.02 16.16 323,141.31 99.76%
Providing and laying in position mixed and machine
25 mm
in all levelof with
approved
brokenqualitystone including offormwork
aggregate size not more wherever
than3
vibrated
SILICA cementCEMENT concrete of mix
ADMIXTURE 1:1.5:3 (1 cement:1.5 sand:
2.3 necessary,
25 mmaggregate) dewatering,
of approved batching,
quality mixing,
including transporting,
formwork placing,
wherever kg 2,409.80 300.00 722,940.00 2,404.08 721,224.80 2242.51 672,753.60 161.57 48,471.20 99.76%
coarse
Providing andcuring, mixing M20 grade
Silica Cementfor reinforced cement concrete
compacting,
necessary, dewatering, including
batching, leadAdmixture
all mixing, of all
andtransporting,
lift, etc. in structural
complete
placing,
work
concrete usingat theapproved
rate ofcement
2.50% with byand 20 mm
weight of graded
the cement machine
for
STEEL
compacting, REINFORCEMENT
as per drawings, curing, specifications
including all lead the lift,
and instructions
etc. all of the
complete
2.4 crushed stone
promoting aggregate of approved strength,quality inachievingvarious Mt. 38.57 130,000.00 5,014,100.00 40.74 5,295,781.23 39.53 5,139,125.75 1.21 156,655.48 105.62%
Providing
Engineer.
as per andworkability,
drawings, fixing in position
specifications
improving
Feand 500thesteel reinforcement
instructions of
of the
locations and heights
waterproofing properties, includingbleeding transportation
prevention, of concrete
etc. to
Silica
various
FORM
Engineer. diameter confirming to relevant IS code in R.C.C.
WORKS
2.5 site of placing,
Cement Admixture compaction,
shall be finished
the to required
product of line and
Silica level,
Japan or sq.m 1,734.43 800.00 1,387,544.00 1,719.80 1,375,838.08 1627.28 1,301,822.44 92.52 74,015.64 99.16%
works including
Supplying and straightening,
laying centering, cutting,
shuttering bending,
of binding
various with
pattern
protection
superior and
and shallwirecuring,
meet etc. all complete as per drawings,
20 SWG annealed
formworks withand 19/12 for the
tying requirements
thick the reinforcement as mentioned
bars & in
at each
BRICK
specifications
specification MASONRY
of materialsthemminstructions
WORKSBRICK water
and Workmanship,
proof
of theplyEngineer,
wood
MASONRY
Division
steel
– but
4:
junctions
adjustable (binding
props forofwire
all shall
kinds ofnotRCC be works
measured separately)
forreinforcement,
foundations,
3.1 WORKS
excluding
Concrete Works, (
the 1 : 4
cost c/s )
Article ONE
centering,SIDE FAIRFACE
shuttering, and
2.4cut pieces, provision for adequate cu.m 84.41 20,000.00 1,688,200.00 - - 0.00 - 0.00 -
including
columns, all waste
shear walls, and
beams, slab, staircase, lintel, sill, pergola,
Providing
all complete andaslaying first class
per drawings, selected
specifications factory pressed
and instructions wire
of
numbers of
including nails,spacers,
propping chairs, providing
scaffolding, and supporting
staging, placing cement and
cut Fair Face
the Engineer. brick (machine made brick) one or more brick
7.2.3 mortar
bracing
CLEAR (1:1)
in coverlines
proper
SILICON blocks and tolevel,
WATER-REPELENT keep sealing
the barsCOATING
in joints
the intended withposition
heavy sq.m
thick wall in cement mortar 1:4 (1 cement : 4coarse sand) in
at
dutyall brown
levelsWORK all
self complete astape,
per drawings, specifications and
8.1.1 POINTING
,superstructure andadhesive
IN
otherBRICKspecified aligning
MASONARY places to in line and levels
all heights and sq.m
instructions Ties,
including of the PVC Engineer. Spacer,(Authorized lapopenings/
length andcutouts/
for the
level
BOQ
bar
including
Totalexceeding
length
the cost
of items 3.1.,
10
of7.2.3
meter
single &Providing
in
or multi stage
8.1.1:
length shall be
self standing
measured for
pockets, applying
scaffolding, soaking De-shuttering
bricks, curing, chemical,
raking De-shuttering
joints, provision as
for
Replaced
the payment, items 3.1, to 7.2.3 and 8.1.1 with following items for
approved
recesses, by except
the Engineer
openings,
column).
toothing etc.,
etc., complete
all complete at all as levels
per as per
drawing,
3-6C(S)-E, 2-4C(S) and Ts(F)
drawing, specifications
specifications and instructionsand instructions
of the Engineer. of the Engineer.
Brick Masonry Works (1:4 c/s) cu.m 18,000.00 - - - 0.00 - 0.00 -
Cement Plaster Works on Outer Wall (1:6) sq.m 600.00 - - - 0.00 - 0.00 -
Exterior Weather Coat Paint sq.m 350.00 - - - 0.00 - 0.00 -
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
7.1.1 ON INNER WALL sq.m 923.13 600.00 553,878.00 947.85 568,709.19 923.13 553,878.00 24.72 14,831.19 102.68%
7.1.2 ON CEILING (1:4) sq.m 360.86 500.00 180,430.00 495.87 247,936.89 360.86 180,429.96 135.01 67,506.93 137.41%
7.1.3 ON OUTER WALL (1:6)
7.1.3.1 EXTERNAL PLASTER sq.m 430.90 600.00 258,540.00 775.79 465,474.24 697.26 418,358.85 78.53 47,115.39 180.04%
7.1.4 EXTERNAL PLASTER WITH CEMENT PUNNING sq.m 35.21 700.00 24,647.00 35.66 24,962.00 35.66 24,962.00 0.00 - 101.28%
7 PAINTING WORKS
7.2.1 DISTEMPER PAINT sq.m 1599.82 200.00 319,964.00 1,817.29 363,457.50 1659.67 331,934.00 157.62 31,523.50 113.59%
7.2.2 EXTERIOR WEATHER COAT PAINT sq.m 461.26 350.00 161,441.00 775.79 271,527.81 411.73 144,105.50 364.06 127,422.31 168.19%
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG sq.m 369.72 550.00 203,346.00 - - 0.00 - 0.00 - 0.00%
7.2.4 ENAMEL PAINT sq.m 392.72 400.00 157,088.00 409.43 163,771.80 347.79 139,116.00 61.64 24,655.80 104.25%
8 MISCELLANEOUS
8.2 CEMENT BOARD WALL sq.m 32.61 6,500.00 211,965.00 34.16 222,040.00 32.61 211,965.00 1.55 10,075.00 104.75%
8.3 RAILING kg 1496.50 220.00 329,230.00 1,527.10 335,962.96 1287.60 283,272.00 239.50 52,690.96 102.05%
8.4 PUMP SHED nos. 1.00 80,000.00 80,000.00 1.00 80,000.00 0.00 - 1.00 80,000.00 100.00%
3 ELECTRICAL WORKS
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure no. 2.00 12,000.00 24,000.00 2.00 24,000.00 2.00 24,000.00 0.00 - 100.00%
1.2 Stand Alone 6 A DP MCB with Enclosure no. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2.1 2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper rm 100.00 800.00 80,000.00 97.00 77,600.00 100.00 80,000.00 -3.00 (2,400.00) 97.00%
2.2 conductor wires mutistranded copper conductor wires + 1
2 Nos 2.5 Sq.mm rm 50.00 250.00 12,500.00 51.00 12,750.00 0.00 - 51.00 12,750.00 102.00%
B Nos. 1.5sq
School mm multistranded Cu wire
Blocks
1 DISTRIBUTION BOARDS nos.
1.1 Ground Floor nos. 2.00 30,000.00 60,000.00 2.00 60,000.00 2.00 60,000.00 0.00 - 100.00%
1.2 First Floor nos. 2.00 22,000.00 44,000.00 2.00 44,000.00 2.00 44,000.00 0.00 - 100.00%
1.3 Second Floor nos. 1.00 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 0.00 - 100.00%
1.4 Stand Alone 6 A DP MCB with Enclosure nos. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm
2.1 Multistranded Cu wire rm 15.00 600.00 9,000.00 15.00 9,000.00 15.00 9,000.00 0.00 - 100.00%
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm
2.2 Multistranded Cu wire rm 15.00 500.00 7,500.00 10.00 5,000.00 15.00 7,500.00 -5.00 (2,500.00) 66.67%
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.2 rm 30.00 250.00 7,500.00 16.00 4,000.00 30.00 7,500.00 -14.00 (3,500.00) 53.33%
Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point pts. 74.00 700.00 51,800.00 75.00 52,500.00 74.00 51,800.00 1.00 700.00 101.35%
3.2 Two Way Light Point pts. 3.00 900.00 2,700.00 3.00 2,700.00 3.00 2,700.00 0.00 - 100.00%
3.3 Ceiling Fan Point pts. 8.00 900.00 7,200.00 8.00 7,200.00 6.00 5,400.00 2.00 1,800.00 100.00%
4 16 A Universal Pin Light Power Socket Wiring pts. 1.00 900.00 900.00 1.00 900.00 1.00 900.00 0.00 - 100.00%
5 6A Universal Pin Light Power Supplying, wiring, testing and
Socket Wiring pts. 43.00 700.00 30,100.00 43.00 30,100.00 43.00 30,100.00 0.00 - 100.00%
commissioning and putting into operation for 6 A light power
6 Switch
point Socket
using 2 x Outlets
4 sq mm + 1 x 2.5 Sq mm multi stranded
6.1 copper
16 conductor,
A Universal Pin 1100
Lightvolts grade,
Power PVC insulated
Socket Wiring wires nos. 1.00 1,500.00 1,500.00 1.00 1,500.00 1.00 1,500.00 0.00 -
drawn through pre
6A Universal Powerinstalled
Switch25Socket
mm dia 2 mmwiring,
Supplying, thick HDP pipe,
testing
6.2 nos. 43.00 900.00 38,700.00 44.00 39,600.00 43.00 38,700.00 1.00 900.00 102.33%
cablecommissioning
and sleeve/support but andincluding specified
putting into dia pipes
operation for 6 A light
7 Sweep
power Ceiling/Exhaust
concealed in wall
point usingand 4 Fans/
2 xfloor mmWall+ 1 xFan
sqincluding all
2.5fixing
Sq mm andmulti
connecting
7.1 materials.
stranded The rateCeiling
1200 mm copper
Sweep for point
conductor,Fanwiring
1100 shall
volts include the circuit
grade, PVC no. 2.00 4,500.00 9,000.00 2.00 9,000.00 4.00 18,000.00 -2.00 (9,000.00) 100.00%
wiring from
insulated deginated
wires drawnDistribution
through pre Board (DB)25
installed upmmto the
diafirst
2
7.2 400 mm Sweep Wall Fan no. 6.00 3,500.00 21,000.00 6.00 21,000.00 12.00 42,000.00 -6.00 (21,000.00) 100.00%
power
mm pointHDP
thick thenpipe,
the looping between sockets.
cable sleeve/support butThe cost shall
including
7.3 225mm
be dia
diaM/D
excluding
specified Exhaust
modular
pipes Fan inswitch
formation
concealed wall andsockets
floorand their all
including nos. 2.00 6,000.00 12,000.00 2.00 12,000.00 2.00 12,000.00 0.00 - 100.00%
8 flushing
fixing andGIconnecting
box but including
Light Fixtures/Luminaires &GIAccessories
materials. fish
Thewire,
ratecutting
for pointandwiring
filling
chasesinclude
shall for recessed pipes wiring
the circuit as deemedfrom as deginated
per drawing and lay out
Distribution
plan all(DB)
Board complete.
up to the first power point then the looping
between sockets. The cost shall be excluding modular
formation switch sockets and their flushing GI box but
Prepared by contractor
including GI fish wire, cutting andChecked by Consultant,
filling chases for DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
recessed pipes as deemed as per drawing and lay out plan
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
8.1 24 W LED Recessed Mounted Square type nos. 4.00 4,500.00 18,000.00 4.00 18,000.00 4.00 18,000.00 0.00 - 100.00%
8.2 18 W LED Surface Mounted Square type CRCA Powder nos. 22.00 2,700.00 59,400.00 22.00 59,400.00 22.00 59,400.00 0.00 - 100.00%
8.3 Coated
18 withRecessed
W LED PMMA Diffuser
Mountedhaving
Square6000
typeKCRCA
ColorPowder nos. 12.00 2,700.00 32,400.00 12.00 32,400.00 12.00 32,400.00 0.00 - 100.00%
Temperature,
Coated IP20 rated.
withSurface
PMMA Diffuser Cylindrical
having 6000type
K Color
8.4 12 W LED Mounted CRCA Powder nos. 15.00 2,400.00 36,000.00 15.00 36,000.00 13.00 31,200.00 2.00 4,800.00 100.00%
Temperature,
Coated IP20 rated.
withRecessed
PMMA Diffuser
8.5 12 W LED Mountedhaving 6000
Crrcular K CRCA
type Color Powder nos. 10.00 2,400.00 24,000.00 10.00 24,000.00 10.00 24,000.00 0.00 - 100.00%
Temperature,
Coated IP20 rated.
withLight
PMMA Diffuser
8.6 LED Wall made of highhaving 6000 K aluminium
grade die-cast Color nos. 3.00 1,800.00 5,400.00 3.00 5,400.00 3.00 5,400.00 0.00 - 100.00%
Temperature,
Powder IP20 rated.
8.7 9W LEDCoated
Surface with PMMACylindrical
Mounted Diffuser having 6000 KPowder
type CRCA Color nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
Temperature,
Coated with IP65 rated
PMMA with having
Diffuser 7 W LED Lamp.
8.8 6W LED Recessed Mounted Circular6000
type K Color nos. 3.00 1,800.00 5,400.00 3.00 5,400.00 3.00 5,400.00 0.00 - 100.00%
Temperature, IP20 rated.
8.9 7W LED T5 Slim Mirror Light nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
9 Pull Box nos. 6.00 700.00 4,200.00 6.00 4,200.00 6.00 4,200.00 0.00 - 100.00%
10 External Post Top Light Pole nos. 6.00 7,500.00 45,000.00 6.00 45,000.00 6.00 45,000.00 0.00 - 100.00%
11 Post Top External Light Fixtures nos. 6.00 9,800.00 58,800.00 6.00 58,800.00 6.00 58,800.00 0.00 - 100.00%
12 Earthing & Lighting Protection
12.1 Chemical Earthing nos. 6.00 45,000.00 270,000.00 6.00 270,000.00 6.00 270,000.00 0.00 - 100.00%
12.2 Earthing Bar nos. 6.00 2,200.00 13,200.00 6.00 13,200.00 6.00 13,200.00 0.00 - 100.00%
13 Earthing Strip/Wires
13.1 25 x 3 mm GI strip mtr. 130.00 300.00 39,000.00 132.00 39,600.00 130.00 39,000.00 2.00 600.00 101.54%
13.2 12 SWG Cu wire mtr. 30.00 200.00 6,000.00 31.00 6,200.00 30.00 6,000.00 1.00 200.00 103.33%
14 Earth Test link nos. 2.00 1,500.00 3,000.00 2.00 3,000.00 2.00 3,000.00 0.00 - 100.00%
C Solar PV System
1 Solar PV Panel nos. 4.00 26,000.00 104,000.00 4.00 104,000.00 4.00 104,000.00 0.00 - 100.00%
2 Tubular Deep Cycle Battery nos. 2.00 30,000.00 60,000.00 2.00 60,000.00 2.00 60,000.00 0.00 - 100.00%
3 Hybrid Inverter 1.00 100,000.00 100,000.00 1.00 100,000.00 1.00 100,000.00 0.00 - 100.00%
D FIRE EXTINGUISHER
a Supplying Fire extinguisher ABC stored Pressure 5.0kg size nos. 2.00 8,000.00 16,000.00 2.00 16,000.00 0.00 - 2.00 16,000.00 100.00%
b ABC stored pressure
Dry Powder type Fire conforming
Fire Extinguisher extinguisher.to BS 5423:1987 or nos. 1.00 8,000.00 8,000.00 1.00 8,000.00 0.00 - 1.00 8,000.00 100.00%
as given in BOQ. The Dry Powder agents shall be mono-
ammonium phosphate and ammonium sulphate base as per
BILL No. below.all
specidfied 4. SANITARY WORKS
complete
A PIPING WORKS
1 WATER SUPPLY INSTALLATION
a) CPVC pipes
- 40 mm Rm 60 1,600.00 96,000.00 55.00 88,000.00 10.00 16,000.00 45.00 72,000.00 91.67%
- 25 mm Rm 70 1,000.00 70,000.00 18.00 18,000.00 15.00 15,000.00 3.00 3,000.00 25.71%
- 20 mm Rm 11 700.00 7,700.00 10.00 7,000.00 5.00 3,500.00 5.00 3,500.00 90.91%
- 15 mm Rm 4 500.00 2,000.00 2.50 1,250.00 15.00 7,500.00 -12.50 (6,250.00) 62.50%
c) CPVC Ball Valve
- 40 mm No. 4 2,000.00 8,000.00 2.00 4,000.00 2.00 4,000.00 0.00 - 50.00%
- 25 mm No. 4 900.00 3,600.00 3.00 2,700.00 2.00 1,800.00 1.00 900.00 75.00%
20mm No. 2 400.00 800.00 2.00 800.00 2.00 800.00 0.00 - 100.00%
40 mm dia Gun Metal Check valve No. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 0.00 - 100.00%
d) Electric Centrifugal Water Pump Set 1 12,500.00 12,500.00 1.00 12,500.00 - 1.00 12,500.00 100.00%
e) 1000 litres capacity Plastic cyllindrical vertical water storage No. 1 34,000.00 34,000.00 1.00 34,000.00 1.00 34,000.00 0.00 - 100.00%
tank
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
2 SEWER, RAIN AND WASTE WATER INSTALLATION
PVC SWR
110 mm Rm 33 1,400.00 46,200.00 32.00 44,800.00 15.00 21,000.00 17.00 23,800.00 96.97%
B SCHOOL BLOCKS
1 SANITARY INSTALLATION
a Stainless Steel Kitchen Sink Set 1 35,000.00
b CP self closing bib cock No 1 4,000.00 4,000.00 1.00 4,000.00 - 1.00 4,000.00 100.00%
c PVC Multi-floor trap with cover No. 1 600.00 600.00 1.00 600.00 - 1.00 600.00 100.00%
CP Waste Coupling and PVC bottle trap for water trough
d No. 1 1,500.00 1,500.00 1.00 1,500.00 - 1.00 1,500.00 100.00%
2 SANITARY INSTALLATION
a Water Closet set Set 1 34,000.00 34,000.00 1.00 34,000.00 - 1.00 34,000.00 100.00%
b 580x480mm Orissa Pan Set 2 3,100.00 6,200.00 2.00 6,200.00 - 2.00 6,200.00 100.00%
c Hand wash basin Set 1 8,000.00 8,000.00 1.00 8,000.00 - 1.00 8,000.00 100.00%
d Urinal Set 2 110,000.00 220,000.00 2.00 220,000.00 - 2.00 220,000.00 100.00%
e CP self closing bib cock No 6 4,000.00 24,000.00 6.00 24,000.00 - 6.00 24,000.00 100.00%
f CP spreader for Urinal Set 2 2,500.00 5,000.00 2.00 5,000.00 - 2.00 5,000.00 100.00%
g CP Toilet Paper Holder heavy No. 1 2,600.00 2,600.00 1.00 2,600.00 1.00 2,600.00 0.00 - 100.00%
h 15mm CP Commode Spray with plastic head No. 1 2,000.00 2,000.00 1.00 2,000.00 - 1.00 2,000.00 100.00%
i PVC Multi-floor trap with cover No. 5 600.00 3,000.00 5.00 3,000.00 - 5.00 3,000.00 100.00%
j CP Waste Coupling and PVC bottle trap for water trough No. 2 1,500.00 3,000.00 2.00 3,000.00 - 2.00 3,000.00 100.00%
k 40 mm SS Grab bar of 600mm Length - Side Set 1 4,500.00 4,500.00 1.00 4,500.00 - 1.00 4,500.00 100.00%
l 40 mm SS Grab bar of 600mm Length - Rear Set 1 4,500.00 4,500.00 1.00 4,500.00 - 1.00 4,500.00 100.00%
m CP Foldable Hinge Set 2 5,500.00 11,000.00 2.00 11,000.00 1.00 5,500.00 1.00 5,500.00 100.00%
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
20 FLAG POLE nos. 2.00 25,000.00 50,000.00 2.00 50,000.00 2.00 50,000.00 0.00 - 100.00%
-
CIVIL WORKS-RESERVOIR TANK -
1 EARTH WORK -
1.1 SITE CLEARANCE AND MOBILIZATION sq.m 22.31 100.00 2,231.00 22.31 2,231.00 22.31 2,231.00 0.00 - 100.00%
1.2 EARTHWORK IN EXCAVATION cu.m 24.58 400.00 9,832.00 24.57 9,828.72 24.57 9,828.72 0.00 - 99.97%
1.3 EARTH BACK FILLING cu.m 4.02 300.00 1,206.00 4.01 1,202.85 4.01 1,202.85 0.00 - 99.74%
1.4 BOULDER SOLING cu.m 2.08 6,000.00 12,480.00 2.08 12,462.00 2.08 12,462.00 0.00 - 99.86%
2 CONCRETE WORKS
2.1 P.C.C (1:3:6) cu.m 0.78 14,000.00 10,920.00 0.78 10,904.25 0.78 10,904.25 0.00 - 99.86%
2.2 P.C.C FOR R.C.C WORKS cu.m 7.42 20,000.00 148,400.00 7.41 148,295.00 7.41 148,295.00 0.00 - 99.93%
2.3 SILICA CEMENT ADMIXTURE kg 74.20 300.00 22,260.00 74.15 22,244.25 74.15 22,244.25 0.00 - 99.93%
2.4 STEEL REINFORCEMENT Mt 1.46 130,000.00 189,800.00 1.58 204,902.61 1.57 203,977.54 0.01 925.07 107.96%
2.5 FORMWORKS sq.m 54.93 800.00 43,944.00 56.46 45,170.80 56.46 45,170.80 0.00 - 102.79%
3 PLASTERING/WALL FINISHING WORKS
INTERNAL PLASTER ON WALL (1:4) WITH CEMENT
3.1.1 sq.m 33.66 700.00 23,562.00 35.46 24,824.45 27.57 19,301.45 7.89 5,523.00 105.36%
PUNNING
4 WATERPROOFING WORKS sq.m 33.66 550.00 18,513.00 35.46 19,504.93 27.57 15,165.43 7.89 4,339.50 105.36%
- - - 0.00 - 0.00 -
FURNITURE WORKS lot 1 4,000,000.00 4,000,000.00 1.00 4,000,000.00 1.00 4,000,000.00 0.00 - 100.00%
Total 35,254,804.90 35,280,032.74 32,354,943.32 2,925,089.43
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Project Name : Emergency School Reconstruction Project (ESRP)
School Name : Shree Sarbodaya Lower Secondary School
Buildings: 3-6CS, 2-4C(S)-H, T(S)-F
Location : Choprak,Gorkha
Abstract of Cost
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank
3.2 BRICK MASONRY WORKS ( 1 : 4 c/s ) cu.m 76.21 18,000.00 72.19 48.26 24.88 145.33 2,615,986.35
3.3 HALF BRICK WORKS ( 1 : 4 c/s ) sq.m 64.50 1,500.00 11.04 6.75 10.61 28.40 42,599.10
3.4 HONEY COMB BRICK WORKS (1:3 c/s) cu.m 0.48 9,000.00 0.24 0.24 0.48 4,279.50
4 DOORS & WINDOWS WORKS
4.1 METAL FRAME
4.1.1 Door Frame r.m 151.04 1,100.00 89.94 61.10 151.04 166,144.00
Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank
4.1.2 Window Frame r.m 383.66 1,100.00 223.80 139.26 363.06 399,360.50
4.2 METAL SHUTTER
4.2.1 WINDOW SHUTTER sq.m 78.99 7,500.00 39.21 25.07 64.28 482,071.31
4.3 WOODEN SHUTTER
4.3.1 FLUSH DOOR SHUTTER (32MM) sq.m 58.33 8,000.00 31.03 21.61 52.64 421,083.60
4.4 UPVC DOOR
4.4.1 Shutter/Frame sq.m 7.14 9,000.00 6.97 6.97 62,730.00
4.5 WINDOW GRILL sq.m 50.07 2,500.00 39.77 25.07 6.23 71.07 177,665.44
4.6 COLLAPSIBLE GATE sq.m 14.98 10,000.00 7.55 7.43 14.98 149,767.50
5 FLOORING WORKS
5.1 HARDENED CEMENT CONCRETE FLOOR sq.m 782.82 900.00 433.94 305.97 41.53 781.44 703,293.98
5.2 NEAT CEMENT SKIRTING r.m 420.91 100.00 228.46 193.98 11.50 433.94 43,394.10
5.3 TERRAZZO CAST-IN SITU DADO sq.m 36.63 1,500.00 2.40 1.20 32.88 36.48 54,720.00
6 ROOFING/TERRACING WORK
6.1 METAL WORKS (TRUSS) kg 6660.99 220.00 3,545.29 3,545.29 597.05 7,687.63 1,691,279.68
6.2 CGI SHEET ROOFING sq.m 439.95 2,000.00 205.50 205.50 33.54 444.54 889,080.00
6.3 CGI SHEET ROOFING RIDGE r.m 42.6 1,200.00 17.90 17.90 6.95 42.75 51,300.00
6.4 GI FACIA (EAVES) kg 387.62 250.00 143.91 143.91 8.06 295.89 73,972.50
6.5 CEMENT BOARD FALSE CEILING sq.m 344.15 1,500.00 174.90 174.90 23.75 373.56 560,337.00
7 PLASTERING/WALL FINISHING WORK
7.1 CEMENT PLASTER WORK
7.1.1 ON INNER WALL sq.m 923.13 600.00 534.33 361.00 52.52 947.85 568,709.19
7.1.2 ON CEILING (1:4) sq.m 360.86 500.00 288.40 183.87 23.60 495.87 247,936.89
7.1.3 ON OUTER WALL (1:6)
7.1.3.1 EXTERNAL PLASTER sq.m 430.90 600.00 372.47 334.39 68.93 775.79 465,474.24
7.1.4 EXTERNAL PLASTER WITH CEMENT PUNNING sq.m 35.21 700.00 35.66 35.66 24,962.00
7 PAINTING WORKS
7.2.1 DISTEMPER PAINT sq.m 1599.82 200.00 997.64 719.78 99.87 1,817.29 363,457.50
7.2.2 EXTERIOR WEATHER COAT PAINT sq.m 461.26 350.00 372.47 334.39 68.93 775.79 271,527.81
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG sq.m 369.72 550.00
7.2.4 ENAMEL PAINT sq.m 392.72 400.00 218.67 184.53 6.23 409.43 163,771.80
8 MISCELLANEOUS
8.2 CEMENT BOARD WALL sq.m 32.61 6,500.00 15.39 15.39 3.38 34.16 222,040.00
8.3 RAILING kg 1496.50 220.00 992.98 534.12 1,527.10 335,962.96
8.4 PUMP SHED nos. 1.00 80,000.00 1.00 1.00 80,000.00
3 ELECTRICAL WORKS
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure no. 2.00 12,000.00 1.00 1.00 2.00 24,000.00
1.2 Stand Alone 6 A DP MCB with Enclosure no. 1.00 8,500.00 1.00 1.00 8,500.00
2 CABLES & WIRES
2.1 2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper conductor wires rm 100.00 800.00 55.00 42.00 97.00 77,600.00
2 Nos 2.5 Sq.mm mutistranded copper conductor wires + 1 Nos. 1.5sq mm
2.2 multistranded Cu wire rm 50.00 250.00 51.00 51.00 12,750.00
B School Blocks
1 DISTRIBUTION BOARDS
1.1 Ground Floor nos. 2.00 30,000.00 1.00 1.00 2.00 60,000.00
1.2 First Floor nos. 2.00 22,000.00 1.00 1.00 2.00 44,000.00
1.3 Second Floor nos. 1.00 22,000.00 1.00 1.00 22,000.00
1.4 Stand Alone 6 A DP MCB with Enclosure nos. 1.00 8,500.00 1.00 1.00 8,500.00
Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank
2 CABLES & WIRES
2.1 2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm Multistranded Cu wire rm 15.00 600.00 10.00 5.00 15.00 9,000.00
2.2 2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm Multistranded Cu wire rm 15.00 500.00 10.00 10.00 5,000.00
2.2 2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm Multistranded Cu wire rm 30.00 250.00 16.00 16.00 4,000.00
3 General Service Light Point Wiring
3.1 One Way Light Point pts. 74.00 700.00 41.00 29.00 5.00 75.00 52,500.00
3.2 Two Way Light Point pts. 3.00 900.00 2.00 1.00 3.00 2,700.00
3.3 Ceiling Fan Point pts. 8.00 900.00 4.00 4.00 8.00 7,200.00
4 16 A Universal Pin Light Power Socket Wiring pts. 1.00 900.00 1.00 1.00 900.00
5 6A Universal Pin Light Power Socket Wiring pts. 43.00 700.00 28.00 15.00 43.00 30,100.00
6 Switch Socket Outlets
6.1 16 A Universal Pin Light Power Socket Wiring nos. 1.00 1,500.00 1.00 1.00 1,500.00
6.2 6A Universal Power Switch Socket nos. 43.00 900.00 28.00 16.00 44.00 39,600.00
7 Sweep Ceiling/Exhaust Fans/ Wall Fan
7.1 1200 mm Sweep Ceiling Fan no. 2.00 4,500.00 2.00 2.00 9,000.00
7.2 400 mm Sweep Wall Fan no. 6.00 3,500.00 6.00 6.00 21,000.00
7.3 225mm dia M/D Exhaust Fan nos. 2.00 6,000.00 2.00 2.00 12,000.00
8 Light Fixtures/Luminaires & Accessories
8.1 24 W LED Recessed Mounted Square type nos. 4.00 4,500.00 4.00 4.00 18,000.00
8.2 18 W LED Surface Mounted Square type nos. 22.00 2,700.00 16.00 6.00 22.00 59,400.00
8.3 18 W LED Recessed Mounted Square type nos. 12.00 2,700.00 8.00 4.00 12.00 32,400.00
8.4 12 W LED Surface Mounted Cylindrical type nos. 15.00 2,400.00 9.00 6.00 15.00 36,000.00
8.5 12 W LED Recessed Mounted Crrcular type nos. 10.00 2,400.00 5.00 5.00 10.00 24,000.00
8.6 LED Wall Light nos. 3.00 1,800.00 1.00 1.00 1.00 3.00 5,400.00
8.7 9W LED Surface Mounted Cylindrical type nos. 1.00 2,000.00 1.00 1.00 2,000.00
8.8 6W LED Recessed Mounted Circular type nos. 3.00 1,800.00 3.00 3.00 5,400.00
8.9 7W LED T5 Slim Mirror Light nos. 1.00 2,000.00 1.00 1.00 2,000.00
9 Pull Box nos. 6.00 700.00 3.00 3.00 6.00 4,200.00
10 External Post Top Light Pole nos. 6.00 7,500.00 3.00 3.00 6.00 45,000.00
11 Post Top External Light Fixtures nos. 6.00 9,800.00 3.00 3.00 6.00 58,800.00
12 Earthing & Lighting Protection
12.1 Chemical Earthing nos. 6.00 45,000.00 3.00 3.00 6.00 270,000.00
12.2 Earthing Bar nos. 6.00 2,200.00 3.00 3.00 6.00 13,200.00
13 Earthing Strip/Wires
13.1 25 x 3 mm GI strip mtr. 130.00 300.00 67.00 65.00 132.00 39,600.00
13.2 12 SWG Cu wire mtr. 30.00 200.00 16.00 15.00 31.00 6,200.00
14 Earth Test link nos. 2.00 1,500.00 1.00 1.00 2.00 3,000.00
C Solar PV System
1 Solar PV Panel nos. 4.00 26,000.00 4.00 4.00 104,000.00
2 Tubular Deep Cycle Battery nos. 2.00 30,000.00 2.00 2.00 60,000.00
3 Hybrid Inverter 1.00 100,000.00 1.00 1.00 100,000.00
D FIRE EXTINGUISHER
a ABC stored Pressure 5.0kg size ABC stored pressure type Fire extinguisher. nos. 2.00 8,000.00 2.00 2.00 16,000.00
b Dry Powder Fire Extinguisher nos. 1.00 8,000.00 1.00 1.00 8,000.00
Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank
a) CPVC pipes
Rm 60 1,600.00 55.00 55.00 88,000.00
- 40 mm
- 25 mm Rm 70 1,000.00 18.00 18.00 18,000.00
- 20 mm Rm 11 700.00 10.00 10.00 7,000.00
- 15 mm Rm 4 500.00 2.50 2.50 1,250.00
c) CPVC Ball Valve No. 4 2,000.00
- 40 mm 2.00 2.00 4,000.00
- 25 mm No. 4 900.00 3.00 3.00 2,700.00
20 mm No. 2 400.00 2.00 2.00 800.00
40 mm dia Gun Metal Check valve No. 1.00 4,500.00 1.00 1.00 4,500.00
d) Electric Centrifugal Water Pump Set 1 12,500.00 1.00 1.00 12,500.00
e) 1000 litres capacity Plastic cyllindrical vertical water storage tank No. 2 34,000.00 1.00 1.00 34,000.00
B SCHOOL BLOCKS
1 SANITARY INSTALLATION
a Stainless Steel Kitchen Sink Set 1 35,000.00 1.00 1.00 35,000.00
b CP self closing bib cock No 1 4,000.00 1.00 1.00 4,000.00
c PVC Multi-floor trap with cover No. 1 600.00 1.00 1.00 600.00
d CP Waste Coupling and PVC bottle trap for water trough No. 1 1,500.00 1.00 1.00 1,500.00
2 SANITARY INSTALLATION
a Water Closet set Set 1 34,000.00 1.00 1.00 34,000.00
b 580x480mm Orissa Pan Set 2 3,100.00 2.00 2.00 6,200.00
c Hand wash basin Set 1 8,000.00 1.00 1.00 8,000.00
d Ladies Urinal Set 2 110,000.00 2.00 2.00 220,000.00
e CP self closing bib cock No 6 4,000.00 6.00 6.00 24,000.00
f CP spreader for Urinal Set 2 2,500.00 2.00 2.00 5,000.00
g CP Toilet Paper Holder heavy No. 1 2,600.00 1.00 1.00 2,600.00
h 15mm CP Commode Spray with plastic head No. 1 2,000.00 1.00 1.00 2,000.00
i PVC Multi-floor trap with cover No. 5 600.00 5.00 5.00 3,000.00
j CP Waste Coupling and PVC bottle trap for water trough No. 2 1,500.00 2.00 2.00 3,000.00
k 40 mm SS Grab bar of 600mm Length - Side Set 1 4,500.00 1.00 1.00 4,500.00
l 40 mm SS Grab bar of 600mm Length - Rear Set 1 4,500.00 1.00 1.00 4,500.00
m CP Foldable Hinge Set 2 5,500.00 2.00 2.00 11,000.00
Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank
8 SILICA CEMENT ADMIXTURE Kg 9.90 300.00 9.90 9.90 2,970.00
9 STEEL REINFORCEMENT Mt. 0.10 130,000.00 0.11 0.11 13,897.00
10 FORM WORKS Sq.m 9.12 800.00 11.33 11.33 9,064.00
11 STONE MASONARY WORKS (1:4 c/s) Cu.m 4.81 10,000.00 4.35 4.35 43,500.00
13 BRICKS MASONRY WORKS (1:4 c/s) Cu.m 0.22 18,000.00 7.91 7.91 142,469.82
14 NEAT CEMENT SKIRTING r.m 4.72 100.00 4.72 4.72 472.00
15 METAL WORKS FOR FENCE k.g 790.75 220.00 744.98 744.98 163,895.60
16 METAL WORKS FOR GATE k.g 130.78 220.00 123.31 123.31 27,128.09
17 PLASTER ON OUTER WALL Sq.m 7.92 600.00 49.26 49.26 29,556.00
18 EXTERIOR WEATHER COAT PAINT Sq.m 8.87 350.00 8.28 8.28 2,898.00
19 CHAIN LINK FENCE Sq.m 82.94 1,000.00 102.00 102.00 102,000.00
20 FLAG POLE nos. 2.00 25,000.00 2.00 2.00 50,000.00
Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Project Name : Emergency School Reconstruction Project (ESRP)
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha
5 Barricading Works 1 37 37 Rm
Breadth Height
S.No Description No. Length (m) Qty. Unit Remarks
(m) (m)
1 Earthworks
1.1 Site Clearance and Mobilization 1 21.95 13.95 306.20
Total 306.20 Sq.m
Building Floors
Classroom
Class Room 2 5.75 5.75 0.20 13.23
Corridor 2 5.75 2.25 0.20 5.18
1 3.25 2.25 0.20 1.46
Below Staircase 1 3.25 5.75 0.20 3.74
Below ramp
For Slope 1 6.82 1.18 0.20 1.61
For Front wall 3-AB 1 6.50 0.45 0.10 0.29
For Side wall -3B 1 1.33 0.45 0.10 0.06
Total 45.99 Cu.m
Column
From lower to plinth tie beam 12.00 0.45 0.45 1.20 2.92
Plinth tie beam
Grid 1,2,3 3.00 14.15 0.30 0.53 6.69
Grid A,B,C,D 4.00 7.60 0.30 0.53 4.79
Ground Floor
For column 12 0.45 0.45 3.00 7.29
G.F Staircase
Landing beam 1 3.05 0.25 0.38 0.29
Landing 1 1 3.20 1.50 0.15 0.72
Landing 2 1 3.20 1.85 0.15 0.89
First flight
Waist Slab 1 3.35 1.50 0.15 0.75
Riser 9 Area 0.02 1.50 0.30
Second Flight
Waist Slab 1 3.40 1.50 0.15 0.77
Riser 10 Area 0.02 1.50 0.34
Staircase gap
Waist Slab 1 1.30 0.20 0.15 0.04
Riser 3 Area 0.02 0.45 0.03
First floor beam
Primary Beam
Grid 1-2-3 3 14.15 0.30 0.53 6.69
Grid A-B-C_D 4 7.60 0.30 0.53 4.79
Secondary Beam
Grid A1-C1 2 7.90 0.25 0.43 1.68
Grid 1a 2 5.45 0.25 0.43 1.16
Grid 1b 1 3.20 0.25 0.43 0.34
F.F. Slab
Class room 8 2.73 2.73 0.13 7.43
First Floor
For column 12 0.45 0.45 3.00 7.29
F.F Staircase
Landing beam 1 3.05 0.25 0.38 0.29
Landing 2 1 3.2 1.85 0.15 0.89
First flight
Waist Slab 1 3.35 1.5 0.15 0.75
Riser 9 Area 0.02 1.50 0.30
Second Flight
Waist Slab 1 3.40 1.50 0.15 0.77
Riser 10 Area 0.02 1.50 0.34
Second Floor Beam
Primary Beam
Grid 1-2-3 3 14.15 0.30 0.53 6.69
Grid A-B-C_D 4 7.60 0.30 0.53 4.79
Secondary Beam
Grid A1-C1 2 7.90 0.25 0.43 1.68
Grid 1a 2 5.45 0.25 0.43 1.16
Grid 1b 1 3.20 0.25 0.43 0.34
S.F. Slab
Class room 8 2.73 2.73 0.13 7.43
Corridoor 4 2.73 2.20 0.13 3.00
1 3.20 2.20 0.13 0.88
Slab between beam 1b & 2B-2C 1 0.49 3.20 0.13 0.20
Staircase top slab 1 0.39 3.20 0.15 0.18
Lintel Bands, First floor level
Along grid A,B,C,D 4 5.55 0.23 0.13 0.64
Along grid 1 1 11.10 0.23 0.13 0.32
Along grid 2 1 11.10 0.23 0.13 0.32
Sill Bands, First floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Second Floor
For column 12 0.45 0.45 2.60 6.32
Second Floor Truss Beam
Primary Beam
Grid 1-2-3 3 14.15 0.30 0.40 5.09
Grid A-B-C-D 4 7.60 0.30 0.40 3.65
Lintel Bands, Second floor level
Along grid A,B,C,D 4 5.55 0.23 0.13 0.64
Along grid 1 1 11.10 0.23 0.13 0.32
Along grid 2 1 14.15 0.23 0.13 0.41
Sill Bands, Second floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 11.10 0.23 0.08 0.19
Along grid 2 1 11.10 0.23 0.08 0.19
Vetical Band 4.00 2.48 0.25 0.08 0.19
3 Brick works
3.2 Brick Masonary Works (1:4 c/s)
Foundation upto plinth
Grid 1,2,3 3 14.15 0.23 0.38 3.66
Ground floor
Along grid A,B,C,D/(1-2) 4 5.55 0.23 2.33 11.87
Along grid 1 1 11.10 0.23 2.33 5.94
1 3.05 0.23 2.02 1.42
Along grid 2 1 10.80 0.23 2.33 5.78
5 FLOORING WORKS
5.1 Hardened Cement Concrete Flooring (40mm) With Neat Cement Punning
Ground floor plan
Class Room 2 5.78 5.75 66.41
Corridor 1 15.80 2.50 39.50
1 3.20 1.50 4.80
Below Staircase 1 4.50 3.20 14.40
Staircase Tread 18 0.3 1.50 8.10
Riser 20 0.15 1.50 4.50
Staircase landing 1 1.80 3.20 5.76
7 PLASTER/PAINTING WORKS
7.1 Internal Plaster
7.1.1 Internal Plaster on Wall (1:6)
Ground Floor
Classroom 2.00 23.15 2.91 134.73
Staircase 1.00 14.67 2.91 42.69
Store Below Landing 1.00 2.50 1.25 3.11
2.00 0.31 1.25 0.78
2.00 0.69 1.44 1.98
2.00 1.44 1.63 4.69
Pedestal 4.00 1.25 0.25 1.25
4.00 0.50 0.25 0.50
Column
Grid 2A,2D 2.00 0.35 0.68 0.47
Grid 2B,2C 2.00 0.98 0.68 1.32
First Floor
Classroom 2.00 23.15 2.91 134.73
Deductions
W1 -8 1.10 1.13 -4.95
V1 -8 1.10 0.53 -2.31
W2 -1 1.50 1.00 -0.75
D1 -4 1.10 2.48 -5.45
Second Floor
Classroom 2.00 23.15 3.00 138.90
Staircase 1.00 14.67 3.00 44.01
Column
Grid 2A,2D 2.00 0.45 3.00 2.70
Grid 2B,2C 2.00 1.08 3.00 6.45
Deductions
W1 -8 1.10 1.13 -4.95
W2 -1 1.50 1.00 -0.75
V2 -8 1.10 0.65 -2.86
D2 -4 1.10 2.60 -5.72
Total 534.33 sq.m
Below staircase
Waist slab 1 3.35 1.50 5.03
Landing 1 1.94 1.50 2.90
1 1.47 1.70 2.49
Second floor
Truss Beam
Classroom 4 4 5.55 0.40 8.88
Classroom 5 4 5.55 0.40 8.88
Corridor; Along grid 2 , ( A-B) and (C-D) 2 5.55 0.40 4.44
Corridor; Along grid 2 , ( B-C) 1 3.05 1.10 3.36
Corridor; Along grid 3 , ( A-B), (B-C) and (C-
D) 1 14.15 0.70 9.91
Corridor; Along grid A, B, C and D; (2-3) 4 2.20 1.10 9.68
Total 288.40 sq.m
Truss Level
Main Beam(300 x 400)
Along grid 1 1.00 14.15 0.40 5.66
Along grid 3 1.00 14.15 0.40 5.66
Column Plaster
Upto Plinth Level
Along grid 1
Grid 1A,1D 2.00 1.10 0.45 0.99
Grid 1B,1C 2.00 0.65 0.45 0.59
Along grid 2
Grid 2A,2D 2.00 0.55 0.45 0.50
Along grid 3
Along grid 3A 1.00 0.08 0.38 0.03
1.00 0.45 0.40 0.18
Grid 3B 1.00 0.08 0.15 0.01
Grid 3C 1.00 0.60 0.15 0.09
Grid 3D 1.00 1.05 0.15 0.16
Upto Sill Level
Along grid 1
Grid 1A,1D 2.00 0.90 0.68 1.22
Grid 1B,1C 2.00 0.45 0.68 0.61
Along grid 2
Grid 2A,2D 2.00 0.55 0.68 0.74
Ground Floor
Along grid 1
Grid 1A,1D 2.00 1.10 2.33 5.12
Grid 1B,1C 2.00 0.65 2.33 3.02
Along grid 2
Grid 2A,2D 2.00 0.65 2.33 3.02
Along grid 3
Grid 3A,3D 2.00 1.05 3.00 6.30
2.00 0.75 2.88 4.31
Grid 3B,3C 2.00 1.20 2.88 6.90
2.00 0.60 3.00 3.60
First Floor
Along grid 1
Grid 1A,1D 2.00 1.10 2.33 5.12
Grid 1B,1C 2.00 0.65 2.33 3.02
Along grid 2
Grid 2A,2D 2.00 0.65 2.33 3.02
Along grid 3
Grid 3A,3D 2.00 1.05 3.00 6.30
2.00 0.75 2.88 4.31
Grid 3B,3C 2.00 1.20 2.88 6.90
2.00 0.60 3.00 3.60
Second Floor
Along grid 1
Grid 1A,1D 2.00 1.10 2.33 5.12
Outer Steps
Grid 2A,2D 2.00 1.03 0.45 0.92
8 MISCELLANOUS
8.2 Cement Board
8.3 Railing
Total
Staircase Railing Kg/m Total
No. Length (m) Length
Horizontal ISNB 40 M 1 18.40 18.40 3.61 66.42
Vertical 38 mm Square Pipe 14 0.86 12.04 3.14 37.81
Horizontal 25mm Square Pipe 4 17.35 69.40 0.85 58.99
Balcony Railing
Horizontal ISNB 40 M 2 18.25 36.50 3.61 131.77
Horizontal ISNB 32 M 4 16.40 65.60 3.14 205.98
Vertical ISNB 40 M 34 1.08 36.72 3.61 132.56
Vertical 25mm Square Pipe 236 0.82 193.52 0.85 164.49
Pedestal
ISNB 40M 8 1.70 13.60 3.61 49.10
ISNB 40M 8 2.05 16.40 3.61 59.20
Base plate 69 0.00009375 0.01 7850 50.78
12 mm dia. Anchor Bolt, Nut 276 0.13 35.88
Total 992.98 k.gs
B Column
1 Grid 1 (A & D) 2 20mm ɸ 20mm ɸ
Main Bar 20 6 4.22 50.63 2.47 125.04
20 6 7.26 87.08 2.47 8.00
3.40 6.44
0.125 0.125
0.699 0.699
2 Grid 1(B & C) 2 25mm ɸ 25mm ɸ
Main Bar 25 6 4.82 57.83 3.86 223.20
25 6 7.82 93.83 3.86 362.16
3.70 6.70
0.125 0.125
0.999 0.999
0.125 0.125
0.125 0.125
0.999 0.699
5 Grid 3 (A,B,C & D) 4
Main Bar 20 6 4.22 101.25 2.47 250.09 20mm ɸ 20mm ɸ
20 6 7.26 174.15 2.47 430.15
3.40 6.44
0.125 0.125
0.699 0.699
6 Stiruups 0.37
For 12 column 12 8 18 1.64 344.40 0.40 137.76 0.08 0.37
8 18 1.18 247.80 0.40 99.12 0.37 0.14 0.08
8 18 1.18 247.80 0.40 99.12
0.25
0.37
9 Ground floor column 0.08 0.37
Grid 1,(A &D) 2 20 6 7.20 86.40 2.47 213.41 0.37 0.14 0.08
Grid 1 (B &C) 2 25 6 7.50 90.00 3.86 347.40
Grid 2 (A,B,C,D) 4 20 2 7.20 57.60 2.47 142.27
25 4 7.50 120.00 3.86 463.20
Grid 3 (A) 1 20 6 7.20 43.20 3.86 166.75
Grid 3 (B,C,D) 3 20 6 5.72 103.01 2.47 254.42
Stiruups
For 12 column 12 8 30 1.64 590.40 0.40 236.16 20mmɸ 25mmɸ
8 30 1.18 424.80 0.40 169.92
8 30 1.18 424.80 0.40 169.92
7.2 7.5
10 Stair Case GF
10.1 First Flight 3.35 1.46
Top Main Bar 12 12 7.26 87.11 0.89 77.53 1.67 0.31
Bottom Main Bar 12 12 2.74 32.89 0.89 29.27 0.45
Top Distribution Bar 10 16 1.46 23.36 0.62 14.48 1.2
Bottom Distribution Bar 10 42 1.46 61.32 0.62 38.02 0.3 1.24
Extra Bar 12 12 2.00 24.00 0.89 21.36
10.2 Landing 1
Bottom bar in first flight 12 12 2.90 34.80 0.89 30.97 1
Top Distribution Bar 10 8 1.46 11.68 0.62 7.24
Bottom Distribution Bar 10 12 3.16 37.92 0.62 23.51 3.16
Top Distribution Bar 10 12 3.16 37.92 0.62 23.51 1.69
Extra Bar 12 12 2.00 24.00 0.89 21.36 1 0.21
10.3 Second Flight
Top Main Bar 12 12 7.31 87.74 0.89 78.09 0.82 3.402
Bottom main Bar 12 12 3.30 39.60 0.89 35.24 0.45
Bottom Distribution Bar 10 23 1.46 33.09 0.62 20.52 2.32 0.31
Top Distribution Bar 10 13 1.46 19.47 0.62 12.07 1.2
Top main bar in forst floor level 12 12 2.38 28.55 0.89 25.41 1.89 0.21
Extra Bar 12 22 2.00 44.00 0.89 39.16
1.46
10.4 Nosing Bar 10 20 1.46 29.20 0.62 18.10
10.5 Nosing ties 0.26
18 8 5 0.67 60.66 0.40 24.26 0.22
0.15
16.67
11.2 Grid A,B,C,D ( Main Beam) 4 0.25
Top bar 16 3 10.29 123.48 1.59 196.33 0.1
1 1
8.87
8.87
11.3 Grid 1a (Secondary Beam) 2
Top bar 16 3 7.94 0.00 1.59 0.00 0.2
Bottom bar 16 3 7.94 0.00 1.59 0.00 0.8
Stirupps 8 49 1.31 0.00 0.40 0.00 0.375
0.96 0.96
0.25
12 Landing Beam 3.87
Top bar 16 3 4.02 12.06 1.59 19.18 0.075 0.075
Bottom bar 16 3 4.02 12.06 1.59 19.18 0.2
Stirrups 1 8 31 1.22 37.82 0.40 15.13 0.8
0.33
0.475 0.55
0.085 0.33 0.085
Long Span(upto 1b) 2
Type A 8 19 7.47 0.00 0.40 0.00 0.55 Type A 0.55
Type B 8 19 7.54 0.00 0.40 0.00 0.085 0.085
6.2
Grid 1b-3 1 Type B
Main bar 0.55 1.35 0.55
Type A 8 12 17.45 209.40 0.40 83.76 0.085 0.33
Type B 8 12 17.71 212.57 0.40 85.03
0.55 Type A 0.55
Grid B-C 1 0.085 0.48
Main bar 0.55 Type B
Type A 8 11 4.30 47.25 0.40 18.90 0.085 0.33
Type B 8 11 4.63 50.88 0.40 20.35
Distribution Bar 6
Along Grid 1 2 8 2 6.00 24.00 0.40 9.60
Along Grid 1a 2 8 13 6.00 156.00 0.40 62.40 15.98
Along Grid 2 2 8 12 15.98 383.52 0.40 153.41
Along Grid 3 1 8 2 15.98 31.96 0.40 12.78
Along Grid A1- C1 2 8 13 8.50 221.00 0.40 88.40
Along Grid B and C 2 8 5 8.50 85.00 0.40 34.00 8.5
Along Grid between B and C 2 8 7 3.75 52.50 0.40 21.00
3.75
Negative bar
Along Grid A1-C1 2 8 14 2.16 60.48 0.40 24.19 0.055 2.05 0.055
Along Grid 1a( A-B and C-D) 2 8 11 2.16 47.52 0.40 19.01
Along Grid 2( A-B and C-D) 2 8 11 2.06 45.32 0.40 18.13 0.055 1.95 0.055
along Grid 2 (B-C) 1 8 4 2.17 8.69 0.40 3.48
0.055 2.06 0.055
2 Stair Case FF
2.1 First Flight 3.35 1.46
Top Main Bar 12 12 7.26 87.108 0.89 77.53 1.67 0.31
Bottom Main Bar 12 12 2.74 32.892 0.89 29.27 0.45
Top Distribution Bar 10 16 1.46 23.36 0.62 14.48 1.2
Bottom Distribution Bar 10 42 1.46 61.32 0.62 38.02 0.3 1.24
Extra Bar 12 12 2 24 0.89 21.36
2.2 Landing 1
Bottom bar in first flight 12 12 2.90 34.8 0.89 30.97 1
Top Distribution Bar 10 8 1.46 11.68 0.62 7.24
Bottom Distribution Bar 10 12 3.16 37.92 0.62 23.51 3.16
Top Distribution Bar 10 12 3.16 37.92 0.62 23.51 1.69
Extra Bar 12 12 2 24 0.89 21.36 1 0.21
2.3 Second Flight
Top Main Bar 12 12 7.31 87.744 0.89 78.09 0.82 3.402
Bottom main Bar 12 12 3.3 39.6 0.89 35.24 0.45
16.67
3.2 Grid A,B,C,D (Main Beam) 4 0.25
Top bar 16 3 10.29 123.48 1.59 196.33 0.1
Bottom bar 20 2 10.87 86.96 2.47 214.79 0.475
16 2 10.29 82.32 1.59 130.89
Stirrups
Grid A,B,C & D 4 10 76 1.65 501.60 0.62 310.99
Torsion bar 4 16 2 8.87 70.96 1.59 112.83
0.71 0.71
8.87
1 1
8.87
8.87
3.3 Grid 1a (Secondary Beam) 2
Top bar 16 3 7.94 47.64 1.59 75.75 0.2
Bottom bar 16 3 7.94 47.64 1.59 75.75 0.8
Stirupps 8 49 1.31 128.38 0.4 51.35 0.375
0.96 0.96
Bent up bar in primary and 16 24 3.01 72.24 1.59 114.86
3.7 secondary beam junction 0.42
0.25
4 Landing Beam 3.87
Top bar 16 3 4.02 12.06 1.59 19.18 0.075 0.075
Bottom bar 16 3 4.02 12.06 1.59 19.18 0.2
Stirrups 1 8 31 1.22 37.82 0.4 15.13 0.8
0.33
0.475 0.55
0.085 0.33 0.085
Long Span(upto 1b) 2
Type A 8 19 7.47 283.86 0.4 113.54 0.55 Type A 0.55
Type B 8 19 7.54 286.37 0.4 114.55 0.085 0.085
6.2
5.2 Grid 1b-3 1 Type B
Main bar 0.55 1.35 0.55
Type A 8 12 17.45 209.40 0.4 83.76 0.085 0.33
Type B 8 12 17.71 212.57 0.4 85.03
0.55 Type A 0.55
5.3 Grid B-C 1 0.085 0.48
Main bar 0.55 Type B
Type A 8 11 4.295 47.25 0.4 18.90 0.085 0.33
Type B 8 11 4.625 50.88 0.4 20.35
Distribution Bar 6
Along Grid 1 2 8 2 6 24.00 0.4 9.60
Along Grid 1a 2 8 13 6 156.00 0.4 62.40 15.98
Along Grid 2 2 8 12 15.98 383.52 0.4 153.41
Along Grid 3 1 8 2 15.98 31.96 0.4 12.78
Along Grid A1- C1 2 8 13 8.5 221.00 0.4 88.40
Along Grid B and C 2 8 5 8.5 85.00 0.4 34.00 8.5
Along Grid between B and C 2 8 7 3.75 52.50 0.4 21.00
3.75
Negative bar
Along Grid A1-C1 2 8 14 2.16 60.48 0.4 24.19 0.055 2.05 0.055
Along Grid 1a( A-B and C-D) 2 8 11 2.16 47.52 0.4 19.01
9 Sill Bands
9.1 Ground floor level
Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51 0.075 0.075
At store 2 10 2 5.85 23.40 0.62 14.51 5.7
Tie Bar 0.075 0.075
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64 0.25
Along grid 1 2 8 38 0.40 30.40 0.40 12.16
Along grid 2 2 8 38 0.40 30.40 0.40 12.16
At store 2 8 38 0.40 30.40 0.40 12.16
10 Vertical Bands
10.1 Ground Floor 4
Main Bar 10 2 2.50 20.00 0.62 12.40
Tie Bar 8 17 0.40 27.20 0.40 10.88
Total 24821.53
24.82 Mt.
Site
S. No. Description G.F F.F S.F Quantity Unit Remarks
Development
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure 1.00 1.00 nos.
2 CABLES & WIRES
2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded
2.1 55.00 r.m
copper conductor wires
Breadth Height
S.No Description No. Length (m) Qty. Unit Remarks
(m) (m)
1 EARTH WORKS
1.1 Site Clearance 1 19.50 12.50 243.75
Soak Pit 1 8.55 Area 8.55
Total 252.30 sq.m
2 CONCRETE WORKS
2.1 P.C.C. Works
2.1.1 P.C.C.(1:3:6) Works
Footing
For Isolated Foundation, F1 4 1.40 1.40 0.10 0.78
For Isolated Foundation, F2 3 1.50 1.50 0.10 0.68
For Isolated Foundation, F3 3 1.90 1.90 0.10 1.08
For Isolated Foundation, F4 2 2.00 2.00 0.10 0.80
For Lower Tie Beam
Along Grid A 1 4.65 0.40 0.05 0.09
Along Grid B 1 4.45 0.40 0.05 0.09
Along Grid C 1 4.30 0.40 0.05 0.09
Along Grid D 1 4.65 0.40 0.05 0.09
Inclined Part
For Isolated Foundation, F1 4 1.34 Area 0.25 1.34
B Beam
Footing beam(250x300)
Along grid 1,2,3 3 14.15 0.25 0.30 3.18
Along grid A,B,C,D 4 7.60 0.25 0.30 2.28
Secondary beam(250x425)
Along 1a 2 5.70 0.25 0.43 1.21
Along Grid 1b 1 3.20 0.25 0.43 0.34
Between A1 and C1 2 7.65 0.25 0.43 1.63
Slab deduction
Main beam(300x525)
Along grid 1,2,3 -3 14.15 0.30 0.125 -1.59
Along grid A,B,C,D -4 7.60 0.30 0.125 -1.14
Secondary beam(250x425)
Along 1a -2 5.70 0.25 0.125 -0.36
Along Grid 1b -1 3.20 0.25 0.125 -0.10
Between A1 and C1 -2 7.65 0.25 0.125 -0.48
C Column
Ground floor plan
Total columns(450x450) 12 0.45 0.45 3.00 7.29
E Staircase
Landing A 1 3.20 1.50 0.15 0.72
Landing B 1 3.20 1.90 0.15 0.91
Waist Slab 2 3.35 1.50 0.15 1.51
Steps 20 0.0225 Area 1.50 0.68
F Lintel Bands
Ground floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 11.10 0.23 0.08 0.19
Along grid 2 1 4.50 0.23 0.08 0.08
First floor level
G Sill Bands
Ground floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 14.15 0.23 0.08 0.24
Along grid 2 1 4.50 0.23 0.08 0.08
First floor level
Along grid A, D 2 5.55 0.23 0.08 0.19
Along grid B,C 2 5.55 0.23 0.08 0.19
Along grid 1 1 14.15 0.23 0.08 0.24
Along grid 2 1 4.50 0.23 0.08 0.08
L Soak Pit
RCC slab 1 2.27 Area 0.13 0.28
Total 86.91 cu.m
Secondary beam(250x425)
Between A,B and C,D 2 7.90 1.10 17.38
Along Grid 1b 1 3.20 1.10 3.52
Between 1 and 2 1 11.50 1.10 12.65
Slab deduction
Main beam(300x525)
Secondary beam(250x425)
Between A,B and C,D -2 7.60 0.250 -3.80
Along Grid 1b -1 3.20 0.250 -0.80
Between 1 and 2 -1 11.50 0.250 -2.88
Deduction
Staircase void -1 Area 14.80 -14.80
E Staircase
Landing A 1 3.20 1.50 4.80
Landing B 1 3.20 1.90 6.08
Waist Slab 2 3.35 1.50 10.06
Steps 20 0.0225 Area 0.45
Side formwork for waist slab 2 6.0690 0.15 1.82
F Lintel Bands
Ground floor level
Along grid A,B,C,D 4 5.55 0.15 3.33
Along grid 1 1 11.10 0.15 1.67
Along grid 2 1 4.50 0.15 0.68
First floor level
Along grid A, D 2 5.55 0.15 1.67
Along grid B,C 2 5.55 0.15 1.67
Along grid 1 1 14.15 0.15 2.12
Along grid 2 1 4.50 0.15 0.68
G Sill Bands
Ground floor level
Along grid A,B,C,D 4 5.55 0.15 3.33
Along grid 1 1 14.15 0.15 2.12
Along grid 2 1 4.50 0.15 0.68
First floor level
Along grid A, D 2 5.55 0.15 1.67
Along grid B,C 2 5.55 0.15 1.67
Along grid 1 1 11.10 0.15 1.67
Along grid 2 1 4.50 0.15 0.68
Ground floor
Along grid A,B,C,D 4 5.55 0.23 2.33 11.87
Along Grid 1 1 14.15 0.23 2.33 7.57
Along grid 2 1 11.10 0.23 2.33 5.94
4.2 Shutter
4.2.1 Metal Window Shutter
Ground floor
W1 7 0.97 1.04 6.99
V1 7 1.01 0.44 3.08
First floor plan
W1 8 0.97 1.04 7.99
V2 8 1.01 0.56 4.52
W2 2 1.37 0.91 2.48
Total 25.07 sq.m
5 FLOORING WORKS
5.1 Hardened Cement Concrete Flooring (40mm) With Neat Cement Punning
Ground floor plan
Kitchen 1 5.75 2.78 15.96
Store 1 5.75 2.75 15.81
ECD Room 2 5.75 5.75 66.13 66.13
Below Staircase 1 3.2 5.75 18.40
Ramp 1 6.82 1.25 8.53
Corridor 1 15.80 2.43 38.32
Staircase
Landing 1 3.2 1.5 4.80
Rise 20 1.5 0.15 4.50
Tread 19 1.5 0.3 8.55
Exterior Steps 2 1.55 0.45 1.40
1 12.25 0.45 5.51
7 PLASTER/FINISHING WORKS
7.1 Cement Plaster Works
7.1.1 Internal Plaster on Wall (1:6)
Ground floor plan
Kitchen 1 17.05 Perimeter 2.91 49.62
Store 1 17.00 Perimeter 2.91 49.47
Secondary beam(300x425)
Between A,B and C,D 2.00 11.15 0.43 9.48
Between A and B 2.00 2.20 0.43 1.87
Secondary Beam for Staircase (250 x 425) 2.00 3.20 0.43 2.72
Slab deduction
Main beam(300x525)
Along grid 1,2, -2.00 14.15 0.125 -3.55
Along grid A,B,C,D -6.00 5.55 0.125 -4.16
Secondary beam(300x425)
Between A,B and C,D -2.00 11.15 0.125 -2.79
Between 1 and 2 -2.00 5.55 0.125 -1.39
Secondary Beam for Staircase (300 x 425) -2.00 3.20 0.125 -0.80
Column Plaster
Along grid 1 2.00 3.30 3.00 19.80
Along grid 2 2.00 3.20 3.00 19.18
Along grid 3 8.00 1.80 3.00 43.20
For Grill
W1 15 1.10 1.13 2.00 37.13
V1 7 1.10 0.53 2.00 8.09
V2 8 1.10 0.65 2.00 11.44
W2 1 1.50 1.00 2.00 3.00
W3 1 1.50 0.37 2.00 1.11
Collapsible Gate 1 3.05 2.44 2.00 14.85
Total 184.53 sq.m
8 MISCELLANOUS
8.2 Cement Board
8.2.1 Partition
Above Side Walls 1.00 9.73 1.58 15.38
Total 15.39 sq.m
8.3 Railing
Total
Staircase Railing Nos length Kg/m Total
Length
Horizontal ISNB 40 M 1 6.563 6.56 3.56 23.36
Vertical ISNB 32 M 8 0.929 7.43 3.10 23.04
Horizontal 25mm Square Pipe 4 6.563 26.25 0.85 22.31
Balcony Railing
Horizontal ISNB 40 M 1 18.25 18.25 3.56 64.97
Horizontal ISNB 32 M 2 18.25 36.50 3.10 113.15
Vertical ISNB 32 M 15 1.08 16.20 3.10 50.22
Vertical 25mm Square Pipe 132 0.82 108.24 0.85 92.00
ISNB 40M 6 1.625 9.75 3.56 34.71
ISNB 40M 6 2.05 12.30 3.56 43.79
Base plate 53 0.00009375 0.00 7850 39.00
12 mm dia. Anchor Bolt, Nut 212 0.13 27.56
Total 534.12 k.g
Piece
Dia. Spacing Wt./m Weight Total Wt.
SN Description Bar Shape Nos. Length Remarks
(mm) (mm) (Kg) (Kg) (Kg)
(m)
1.30
Bars (Y - direction) 12 150 0.888 10 1.5 13.32 53.28
0.10
1.40
F2 Footing (3 Nos):
12 150 0.888 10 1.6 14.21 28.42
1500*1500mm, Bars 0.10
1.40
12 150 0.888 10 1.6 14.21 28.42
0.10
1.70
F3 Footing (3 Nos):
12 150 0.888 12 1.9 20.25 80.99
1800*1800mm, Bars 0.10
1.70
12 150 0.888 12 1.9 20.25 80.99
0.10
1.90
F4 Footing (2 Nos):
12 150 0.888 14 2.1 26.11 52.21
2000*2000mm, Bars 0.10
1.90
12 150 0.888 14 2.1 26.11 52.21
0.10
COLUMNS, (450*450mm)
Grid 1,2,3 Columns (12 Nos.):
=3.39
Main Bars 20 2.467 4 4.22 41.64 499.72 1 Lap in GF
0.08+0.75 0.37+0.75+0.45+(0.62+1.2)
1.03
=5.36
20 2.467 4 6.39 63.06 756.68
(6-0.62-0.025)
=3.15
16 1.58 2 3.74 11.82 141.82 1 Lap in GF
0.08+0.51 0.37+0.75+0.45+0.62+0.96
0.74
=5.36
16 1.58 2 6.10 19.28 231.31
(6-0.62-0.025)
=6.18
16 1.58 6 6.77 64.18 770.16 1 Lap in FF
0.08+0.51 0.37+0.75+0.45+3+1.61
0.74
=2.33
16 1.58 6 3.07 29.10 349.24
0.37 0.10
100 &
Stirrups (for Lap Portion) 10 0.617 22 1.68 22.39 268.68
150
0.37
0.10
0.13 100 &
10 0.617 44 1.20 32.58 390.93 Double
150
0.37
0.37 0.08
100 &
Stirrups (other) 8 0.395 29 1.64 18.96 227.51
150
0.37
0.08
0.20 100 &
Stirrups (for 250*300) 8 0.395 123 0.86 41.84 125.52
150
0.15
0.20 0.08
100 &
Stirrups (for 250*300) 8 0.395 67 0.86 22.70 90.81
150
0.15
Main Bars (Long side beams); Along Grid 1-1, 2-2, 3-3 3 Beams
0.74 Incl. 2
Top (T/O) 15.5+0.45-2(0.07) 16 1.58 5 18.25 144.18 432.53 Torsion
Rebars (3+2)
15.5+0.45-2(0.07)
Bottom (T/O) 0.74 16 1.58 4 18.25 115.34 346.02
0.74
Extra Bars (at 2 Ends) 0.38+1.50 16 1.58 4 2.62 16.56 16.56
0.47 0.12
Stirrups (for 300*525) 12 100 0.888 145 1.68 215.57 646.71
0.25
0.74 Incl. 2
Top (T/O) 8.5+0.45-2(0.07) 16 1.58 5 10.29 81.29 325.16 Torsion
Rebars (3+2)
8.5+0.45-2(0.07)
Bottom (T/O) 0.74 16 1.58 4 10.29 65.03 260.13
0.74 0.38+1.7
Extra Bars (at 2 ends) 0.38+2.5+1.7 16 1.58 2 8.14 25.72 102.89
0.47 0.12
Stirrups (for 300*525) 12 100 0.888 78 1.68 116.36 465.45
0.25
7804.47 OK
15.5+0.45-2(0.07)
Bottom Bars (T/O) 0.76 20 2.467 2 18.47 91.13 182.26
0.53
Top Bars (T/O) 15.5+0.45-2(0.07) 16 1.58 3 17.78 84.28 168.55
0.76
Extra Bars (above A) 0.38+1.50 20 2.467 2 2.64 13.03 26.05
1.05
Extra Bars (above D) 0.38+1.70 25 3.855 2 3.13 24.13 48.26
0.91 2 Nos. at
Bent-up Bars 0.34 16 1.58 4 2.75 17.38 34.76
a point
0.475 0.10
100 &
Stirrups 10 0.617 124 1.64 125.81 251.62
150
0.25
15.5+0.45-2(0.07)
Bottom Bars (T/O) 0.76 20 2.467 2 18.47 91.13 91.13
15.5+0.45-2(0.07)
0.53 16 1.58 2 17.78 56.18 56.18
0.53
Top Bars (T/O) 15.5+0.45-2(0.07) 16 1.58 3 17.78 84.28 84.28
0.53
Extra Bars (above A) 0.38+1.50 16 1.58 2 2.41 7.62 7.62
0.53
Extra Bars (above D) 0.38+1.5 16 1.58 2 2.41 7.62 7.62
0.91 2 Nos. at
Bent-up Bars 0.34 16 1.58 4 2.75 17.38 17.38
a point
0.475 0.10
100 &
Stirrups 10 0.617 124 1.64 125.81 125.81
150
0.25
8.5+0.45-2(0.07)
Bottom Bars (T/O) 0.76 20 2.467 4 11.47 113.19 452.74
0.53
Top Bars (T/O) 8.5+0.45-2(0.07) 16 1.58 3 9.87 46.78 187.14
1.05
Extra Bars (above 1) 0.38+1.70 25 3.855 2 3.13 24.13 96.53
1.05
Above 2, 3 0.38+2.5+1.7 25 3.855 2 5.63 43.41 173.63
0.91 2 Nos. at
Bent-up Bars 0.34 16 1.58 2 2.75 8.69 34.76
a point
Secondary Beams:
0.65
Top & Bottom bars (T/O) 8.5+0.30-2(0.035) 16 1.58 6 10.03 95.08 190.17
0.37 0.08
100 &
Stirrups (250*425 mm) 8 0.395 71 1.30 36.63 73.26
150
0.20
0.65
Top & Bottom bars (T/O) 6.0+0.30-2(0.035) 16 1.58 6 7.53 71.38 142.77
0.37 0.08
100 &
Stirrups (250*425 mm) 8 0.395 48 1.30 24.82 49.64
150
0.20
Along Grid (1b),
0.65
Top & Bottom bars (T/O) 3.5+0.30-2(0.035) 16 1.58 6 5.03 47.68 47.68
0.37 0.08
100 &
Stirrups (250*425 mm) 8 0.395 28 1.30 14.46 14.46
150
0.20
15.5+0.45-2(0.07)
Bottom Bars (T/O) 0.53 16 1.58 2 17.78 56.18 168.55
15.5+0.45-2(0.07)
0.30 12 0.888 2 17.09 30.35 91.06
0.53
Top Bars (T/O) 15.5+0.45-2(0.07) 16 1.58 3 17.78 84.28 252.83
0.35 0.08
100 &
Stirrups (300*400 mm) 8 0.395 124 1.36 66.79 200.38
150
0.25
Short side Beams: 300*400 Along Grid A,B,C,D
0.53 8.5+0.45-2(0.07)
Bottom Bars (T/O) 16 1.58 2 9.87 31.19 124.76
8.5+0.45-2(0.07)
0.30 12 0.888 2 9.41 16.71 66.85
0.53
Top Bars (T/O) 8.5+0.45-2(0.07) 16 1.58 3 9.87 46.78 187.14
0.35 0.08
100 &
Stirrups (300*400 mm) 8 0.395 70 1.36 37.34 149.34
150
0.25
6 Staircase:
1.0 1.0
Bottom extra bar 12 125 0.888 13 2.00 22.52
3.35
1.67 1.46
12 125 0.888 13 7.00 78.82
0.3
0.22
1.46
Top distribution 10 150 0.617 24 1.46 21.56
Upper Flight:
1.20 1.89
Main bars 12 125 0.888 13 3.31 37.27
0.22
3.35
2.32
0.82 12 125 0.888 13 6.81 76.68
0.32
0.33 1.0
Top extra bar 0.26 12 125 0.888 13 1.59 17.90
0.27
12 125 0.888 13 1.51 17.00
0.42 0.82
0.26
0.15
Nosing Tie 0.12 8 300 0.395 117 0.68 31.52
0.15
0.33 0.08
100 &
Stirrups 8 0.395 27 1.22 13.09
150
0.20
588.84 588.84
7 SLAB:
0.51 0.58
1 Lap (in mid
Along Short Span: Main Bars 0.085 8.8-0.04 8 300 0.395 19 10.79 163.32
cranked)
0.51 0.58
0.085 8.8-0.04 8 300 0.395 19 10.01 151.57
0.51
0.085 3.88 8 300 0.395 12 4.56 20.99
0.51
0.085 3.88 8 300 0.395 12 4.47 20.60
0.58
Along Long Span: Main Bars 6.26 8 300 0.395 16 7.70 98.75
0.07
0.58
6.26 8 300 0.395 16 7.56 96.95
0.07
0.58
15.76 8 300 0.395 11 18.08 80.21
0.07
0.58
15.76 8 300 0.395 11 17.52 77.72
0.07
15.76
Distribution Bar 8 200 0.395 12 16.22 73.66
6.26
8 200 0.395 13 6.26 64.78
Site
S. No. Description G.F F.F Quantity Unit Remarks
Development
A. Common Installation
1 Stand Alone 40 A DP MCB with Enclosure 1.00 1.00 nos.
2 CABLES & WIRES
2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded
2.1 42.00 r.m
copper conductor wires
B School Blocks
1 DISTRIBUTION BOARDS 1.00 1.00 2.00 nos.
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4
2.1 5.00 r.m
Sq mm Multistranded Cu wire
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5
2.2 10.00 r.m
Sq mm Multistranded Cu wire
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No
2.3 16.00 r.m
1.5 Sq mm Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point 3.00 13.00 13.00 29.00 pts.
3.2 Two Way Light Point 1.00 1.00 pts.
3.3 Ceiling Fan Point 4.00 4.00 pts.
4 16A Universal Pin Light Power Socket Wiring 1.00 1.00 pts.
5 6A Universal Pin Light Power Socket Wiring 8.00 7.00 15.00 pts.
6 Switch Socket Outlets
6.1 16A Universal Power Switch Socket 1.00 1.00 no.
6.2 6A Universal Power Switch Socket 9.00 7.00 16.00 no.
7 Sweep Ceiling/Exhaust Fans/ Wall Fan
7.1 1200mm Sweep Ceiling Fan 2.00 2.00 no.
7.2 400mm Sweep Wall Fan 4.00 6.00 no.
7.3 225mm dia M/D Exhaust Fan 2.00 2.00 no.
8 Light Fixtures/Luminaires & Accessories
8.1 24 W LED Recessed Mounted Square type 4.00 4.00 no.
8.2 18 W LED Surface Mounted Square type 6.00 6.00 no.
8.3 18 W LED Recessed Mounted Square type 4.00 4.00 no.
8.4 12 W LED Surface Mounted Cylindrical type 6.00 6.00 no.
8.5 12 W LED Recessed Mounted Circular type 5.00 5.00 no.
8.6 7W LED Wall Light 1.00 1.00 no.
9 Pull Box 3.00 3.00 no.
10 External Post Top Light Pole 3.00 3.00 no.
11 Post Top External Light Fixtures 3.00 3.00 no.
12 Earthing & Lighting Protection
12.1 Chemical Earthing 3.00 3.00 no.
12.2 Earthing Bar 3.00 3.00 no.
12.3 Earthing Strip/Wires
12.3.1 25 x 3 mm GI strip 65.00 65.00 r.m
12.3.2 12 SWG Cu wire 15.00 15.00 r.m
13 Earth Test link 1.00 1.00 no.
D Fire Extinguisher
5.0kg Size ABC Stored Pressure Type Fire
1 1.00 1.00 2.00 nos.
Extinguisher
Library
7 Library Table T-02 4 nos.
8 Library Shelf F-04 3 nos.
9 Student Bench (3 Seater) B-02C 8 nos.
Office
10 Cabinet F-06 3 nos.
11 Office Table T-07 12 nos.
12 Office Chair C-03 12 nos.
13 Dinning Chair C-05 12 nos.
14 Dinning Table T-09 2 nos.
Miscellaneous
15 Cusions F-16 18 nos.
16 Carpet 33.2 sq.m
17 Equipment Cabinet F-09 2 nos.
Total 89 nos.
2 Concrete Works
2.1 PCC
2.1.1 P.C.C.(1:3:6) Works
For Footing 1
P.C.C. for isolated footing(F1) 6 1.00 1.00 0.10 0.60
Septic Tank
1 5.50 2.25 0.08 0.99
Sewer Manhole
Bottom 1 1.00 Area 0.10 0.10
Waste water Chamber 0.00
Bottom 2 1.00 1.00 0.10 0.20
Total 2.49 Cu.m
Beam
Foundation Beam
Along grid 1 1 4.70 0.25 0.30 0.35
Along grid 2 1 4.70 0.25 0.30 0.35
Along grid 3 1 4.70 0.25 0.30 0.35
Along grid A 1 5.40 0.25 0.30 0.41
Along grid B/(1,2) 1 3.20 0.25 0.30 0.24
Tie Beam
Along grid 1 1 4.70 0.25 0.30 0.35
Along grid 2 1 4.70 0.25 0.30 0.35
Along grid 3 1 4.70 0.25 0.30 0.35
Along grid A 1 5.40 0.25 0.30 0.41
Along grid B(1,2) 1 3.20 0.25 0.30 0.24
Along grid B/(2,3) 1 2.20 0.25 0.59 0.32
Column
Column up to plinth level 6 0.30 0.30 1.00 0.54
Column from plinth to top 6 0.30 0.30 3.00 1.62
Slab
Slab of first floor 1 4.75 2.25 0.15 1.60
Lintel Bands
For first floor
Along grid 1 1 4.70 0.125 0.25 0.15
Along grid 2 1 4.70 0.125 0.25 0.15
Along grid 3 1 4.70 0.125 0.25 0.15
Along grid A 1 5.40 0.125 0.25 0.17
Along grid B 1 3.20 0.125 0.25 0.10
Along the partition wall 1 3.25 0.125 0.25 0.10
For the partition wall 1 2.77 0.125 0.13 0.04
Soak Pit
RCC slab 1 1.13 Area 0.12 0.14
Sewer Manhole
Top Cover 1 1.00 1.00 0.10 0.10
Waste Water Chamber
Top Cover 2 1.00 1.00 0.10 0.20
Total 16.46 Cu.m
2.5 Formworks
Foundation
Isolated footing (F1) 6 4.00 0.20 4.80
Beam
Foundation Beam
Along grid 1 1 4.70 0.50 2.35
Along grid 2 1 4.70 0.50 2.35
Along grid 3 1 4.70 0.50 2.35
Along grid A 1 5.40 0.50 2.70
Along grid B/(1,2) 1 3.20 0.50 1.60
Tie Beam
Along grid 1 1 4.70 0.60 2.82
Along grid 2 1 4.70 0.60 2.82
Along grid 3 1 4.70 0.60 2.82
Along grid A 1 5.40 0.60 3.24
Along grid B/(2,3) 1 2.20 1.18 2.60
Column
Slab
Along corridor 1 4.75 2.25 10.69
Lintel Bands
Along grid 1 2 4.70 0.125 1.18
Along grid 2 2 4.70 0.125 1.18
Along grid 3 2 4.70 0.125 1.18
Along grid A 2 5.40 0.125 1.35
Along grid B 2 3.20 0.125 0.80
Along partition walls 1 2.77 0.125 0.35
Sewer Manhole
Top Cover 1 0.60 Area 0.60
3 Brick Works
3.2 Full Brick (230 mm) Works (1:4c/s)
Brick Works under Plinth beam
Along grid 1 1 4.70 0.23 0.45 0.49
5 FLOORING WORKS
5.1 Cement Concrete Flooring (40mm) With Neat Cement Punning
Toilets ( Female) 1
At corridor 1 5.30 1.20 6.36
At Ramp 1 5.60 1.20 6.72
Along the terrace 1 4.75 2.25 10.69
step 1 0.30 1.20 0.36
Inside the room 1 3.23 2.00 6.45
1 3.23 2.50 8.06
At Doors 1 1.90 0.25 0.48
Along the water trough 1 3.45 0.7 2.42
Total 41.53 sq.m
7 PLASTER/PAINTING WORKS
7.1 Internal Plaster
7.1.1 Internal Plaster on Wall (1:6)
Toilets ( Female) 1
Along grid A & B 2 3.20 1.80 11.52
Along A 1 2.20 3.00 6.60
Along grid 1 1 4.70 1.80 8.46
Along grid 2 1 2.55 1.80 4.59
On partition wall 2 3.25 1.80 11.70
Long wall 1 1.63 1.80 2.93
1 1.88 1.80 3.38
Short wall 2 0.43 1.80 1.53
Deduction
V1 -1 3.48 0.38 -0.65
V2 -1 3.48 0.33 -0.56
V3 -1 1.98 0.38 -0.37
V4 -1 1.98 0.33 -0.32
D1 -1 1.00 0.90 -0.45
D2 -1 0.90 0.90 -0.41
Along grid 3 1 4.70 1.95 4.57
Total 52.52 sq.m
8 MISCELLANOUS
8.2 Cement Board
For Partition
2.00 1.69 Area 3.37
Total 3.38 sq.m
900
a. Along Y-axis 100 12 150 6 7 1100 46.2 0.889 41.07
100
900
b. Along X-axis 100 12 150 6 7 1100 46.2 0.889 41.07
100
B. Column-MAIN BAR
465
4251
a. Longitudinal bar upto full height 12 - 6 8 5160 247.68 0.889 220.16
100 344
STIRRUPS FOR COLUMN SIZE 300 x 300 upto Plinth Height-
220
80
1
160 6
80 0
c Stirrups 8 100 6 11 800 52.8 0.395 20.86
1
6 160
0
C Column (300*300)
220
80
a Stirrups for Column upto floor Height 220 8 125 6 25 1040 156 0.395 61.63
1
160 6
80 0
b " 8 125 6 25 800 120 0.395 47.41
1
6 160
0
D BEAM
1 Foundation Beam (250*250)
5000
a Along Grid-1,2 & 3- Top Bar 720 720 12 3 3 6440 57.96 0.889 51.52
b Along Grid--1,2 & 3-Bottom Bar 720 12 3 3 6440 57.96 0.889 51.52
5000 720
6000
c Along Grid-A & B-Top Bar 720 12 3 3 7440 66.96 0.889 59.52
720
200
80
e Stirrups Along Grid 1, 2 & 3 8 150 3 34 960 97.92 0.395 38.69
200
200
80
f Stirrups Along A & B 8 150 2 40 960 76.8 0.395 30.35
200
5000
a. Along Grid-1 -Top Bar 960 16 1 2 6920 13.84 1.580 21.88
960
5000
b 720 12 1 1 6440 6.44 0.889 5.73
720
5000
c Along Grid-1 -Bottom Bar 960 16 1 2 6920 13.84 1.580 21.88
960
5000
d 720 12 1 1 6440 6.44 0.889 5.73
720
e Along Grid-2 & 3-Top Bar 960 16 2 2 6920 27.68 1.580 43.75
5000 960
g Along Grid-2 & 3-Bottom Bar 960 16 2 2 6920 27.68 1.580 43.75
5000 960
6000
i Along Grid-A & B-Top Bar 12 2 3 7440 44.64 0.889 39.68
720 720
j Along Grid-A & B-Bottom Bar 720 12 2 4 7440 59.52 0.889 52.91
6000 720
200
80
200
80
3 FLOOR BEAM
LONGITUDINAL BARS
Along Grid 1,2&3
5200
a Top Bars 870 16 3 2 6940 41.64 1.580 65.81
870
5200
b Top Bars 12 3 1 6380 19.14 0.889 17.02
590 590
6200
e Top Bars 12 2 3 7380 44.28 0.889 39.36
590 590
STIRRUPS
200
8
0
g Stirrups for Beam Size 250*400 350 8 125 1 93 1260 117.18 0.395 46.30
200
80
h Stirrups for Beam Size 250*450 400 8 125 1 124 1360 168.64 0.395 66.63
E SLAB
850 850
a Main Bars Short Span 100 10 150 1 33 4600 151.8 0.617 93.71
100 2700
1475 1475
b Main Bars Long Span 100 10 150 1 16 8350 133.6 0.617 82.47
5200 100
220
80
1
160 6
80 0
b Stirrups 8 125 6 21 800 100.8 0.395 39.83
1
6 160
0
G SOAKPIT
d=1850+Ld
d=1450+Ld
c Main Bar Along both Direction 8 200 1 2 1650 3.3 0.395 1.31
1650
h Top Bar Along Radial Direction 8 200 1 8 425 3.4 0.395 1.35
425
H SEPTIC TANK
200
6
a Stirrups for Concealed Beam 5 8 150 1 13 670 8.71 0.395 3.45
70
1850
b 10Ø Longitudional Bar for CB-Top Bar 10 1 2 1970 3.94 0.617 2.44
60
60
c 10Ø Longitudional Bar for CB-Bottom Bar 10 1 2 1970 3.94 0.617 2.44
60 1850
60
Bed RCC Bars
d Bottom Mesh Bar-Along Length Wise 8 200 1 12 5550 66.6 0.395 26.32
50 5450
50
e Bottom Mesh Bar-Along WIdth Wise 8 200 1 28 2300 64.4 0.395 25.45
50 2200 50
f Septic Tank Slab Cover
1215 1475
j 8Ø Bottom bar along Length wise 8 1 9 7650 68.85 0.395 27.20
60 4840 60
1215
k 8 1 4 3780 15.12 0.395 5.98
60 2445 60
1
n Top Bars-Along Width Wise 0 8 1 8 620 4.96 0.395 1.96
0 520
I SILL BAND
Longitudinal Bars
3400 75
800
800
a Grid 1/A-B ,Grid 3/A-B 10
75 2 2 6350 25.4 0.617 15.68
75 600 600
1175 75
1700
b Grid 2/A-B 10 1 2 2950 5.9 0.617 3.65
75
2650 75
425
425
c Grid A/1-2, B/1-2 10 2 2 4950 19.8 0.617 12.23
75
75 600 600
2150 75
175
175
d Grid A/2-3 10 1 2 3850 7.7 0.617 4.76
75
75 600 600
e Partition Wall between Grid A & Grid B 10 1 2 3600 7.2 0.617 4.45
3600
Ties
65 65
i Grid 1/A-B ,Grid 3/A-B 8 150 2 33 320 21.12 0.395 8.35
190
65 65
j Grid 2/A-B 8 150 1 20 320 6.4 0.395 2.53
190
65 65
k Grid A/1-2, B/1-2 8 150 2 23 320 14.72 0.395 5.82
190
65 65
l Grid A/2-3 8 150 1 16 320 5.12 0.395 2.03
190
65 65
m Partition Wall between Grid A & Grid B 8 150 1 23 320 7.36 0.395 2.91
190
50 50
n Partition Wall between Incinerator Holes 8 150 1 9 170 1.53 0.395 0.61
70
50 50
o Partition Wall between along D3 8 150 1 7 170 1.19 0.395 0.48
70
50 50
p Partion Wall for Urinal 8 150 1 5 170 0.85 0.395 0.34
70
J Lintel Band
Longitudinal Bars
3400 75
800
800
3400 75
800
800
b Grid 2/A-B 10
75 1 2 6350 12.7 0.617 7.84
75 600 600
2650 75
425
425
2150 75
175
175
d Grid A/2-3 10
75 1 2 3850 7.7 0.617 4.76
75 600 600
e Partition Wall between Grid A & Grid B 10 1 2 3700 7.4 0.617 4.57
3600
65 65
i Grid 1/A-B ,Grid 3/A-B 8 150 2 33 320 21.12 0.395 8.35
190
65 65
j Grid 2/A-B 8 150 1 33 320 10.56 0.395 4.18
190
65 65
k Grid A/1-2, B/1-2 8 150 2 23 320 14.72 0.395 5.82
190
65 65
l Grid A/2-3 8 150 1 16 320 5.12 0.395 2.03
190
65 65
m Partition Wall between Grid A & Grid B 8 150 1 23 320 7.36 0.395 2.91
190
50 50
n Partition Wall between Incinerator Holes 8 150 1 10 170 1.7 0.395 0.68
70
50 50
o Partition Wall between along D3 8 150 1 21 170 3.57 0.395 1.42
70
50 50
p Partion Wall for Urinal 8 150 1 5 170 0.85 0.395 0.34
70
M INCINERATOR
a 630*505 Grill Mesh
Toilet
S. No. Description Quantity Unit Remarks
Block
A. Common Installation
1.2 Stand Alone 6 A DP MCB with Enclosure 1 1.00 nos.
B School Blocks
1 DISTRIBUTION BOARDS nos.
1.4 Stand Alone 6 A DP MCB with Enclosure 1.00 1.00 nos.
3.1 One Way Light Point 5.00 5.00 pts.
6 Sweep Ceiling/Exhaust Fans/ Wall Fan
6.1 225mm dia M/D Exhaust Fan 2 2.00 no.
7 Light Fixtures/Luminaires & Accessories
7.5 7W LED Wall Light 1.00 1.00 no.
7.6 9W LED Surface Mounted Cylindrical type 1.00 1.00 no.
7.7 6W LED Recessed Mounted Circular type 3.00 3.00 no.
7.8 7W LED T5 Slim Mirror Light 1.00 1.00 no.
Sanitary Installation
a Water Closet Set 1 1.00 set
b Orissa Pan 2 2.00 set
c Hand Wash Basin 1 1.00 set
d Ladies Urinal 2 2.00 set
e Self Closing Bib Cock 6 6.00 nos.
f CP Spreader in Urinal 2 2.00 set
g Toilet Paper Holder 1 1.00 nos.
h Commode Spray 1 1.00 nos.
i PVC Multi Floor Trap 5 5.00 nos.
j Waste Coupling and PVC Bottle Trap 2 2.00 nos.
k 40mm SS Grab Bar-Side 1 1.00 nos.
l 40mm SS Grab Bar-Rear 1 1.00 nos.
m CP Foldable Hinge 2 2.00 nos.
4 Boulder Soling
Infront of Bldg
3-6C(S) 1 6.52 1.50 0.15 1.47
1 10.05 2.50 0.15 3.77
Side of 3-6C(S) 1 5.45 1.50 0.15 1.23
17 External Plaster
Column Inside face 4 0.54 1.64 3.54
Column Outside face 2 1.2 0.20 0.48
4 0.54 1.70 3.67
Deduct -2 0.3 1.40 -0.84
Top Coping 2 2.36 0.05 0.24
4 0.59 0.30 0.71
Between two Bldgs 1 7.35 1.58 11.61
Curve portion 2 2.45 1.58 7.74
In side of Ramp 2 4.7 0.83 7.80
Infront of 2-4C(S) 1 17.2 0.68 11.70
1 1.65 1.58 2.61
20 Flag Pole
75 Dia GI Pipe 2.00 1 2.00
Total 2.00 nos
Size Spacing c/c Structure Rebar Length/pc. Total Weight Per Total Weight
SN Description Shape Remarks
(mm) (mm) Nos Nos (mm) Length (m) Meter (Kg) (Kg)
1 Entrance Gate-Column
75 75
a 900*900 Foundation Mesh 850 10 150 2 12 1000 24 0.62 14.82
220
8 mm dia at 150 c/c for column
c 7
220 8 150 2 26 1030 53.56 0.40 21.16
stirrups-Outer 5
1
7
7 3
8 mm dia at 150 c/c for column 5
d 8 150 2 26 842 43.784 0.40 17.3
stirrups-Outer
2 Earthwork in excavation
For Water Tank 1 3.65 3.40 1.98 24.57
Total 24.57 Cu.m.
3 Earthback Filling
Total Earthwork Excavated 24.57
Water Tank Volume -1 3.35 3.1 1.98 -20.56
Total 4.01 Cu.m.
4 Boulder soling
Below Water Tank 1 3.35 3.1 0.2 2.077
Total 2.08 Cu.m.
1.915 1.915
3.02
1.915 1.915
3.29
1.884
0.05
0.49 0.49
1.884
0.05
0.49 0.49
D. Horizontal Bars(outer 4
0.3 0.3
1 Shorter Span 10 21 3.62 304.08 0.62 188.53
3.02 3.02
0.3 0.3
3.27 3.27
0.3 0.3
E. Base Slab bar 4
1 Shorter Span 10 35 3.14 439.6 0.62 272.55 3.045
0.05 0.05
1.915 1.915
3.02
1.915 1.915
3.29
1.884 1.884
0.05
0.49 0.49
1.884 1.884
0.05
0.49 0.49
0.592
0.592 0.6 0.6
D. Horizontal Bars(outer 4
0.3 0.3
1 Shorter Span 10 21 3.62 304.08 0.62 188.53
3.02 3.02
0.3 0.3
3.27 3.27
0.3 0.3
E. Base Slab bar 4
1 Shorter Span 10 35 3.14 439.6 0.62 272.55 3.045
0.05 0.05