You are on page 1of 108

Government of Nepal

National Reconstruction Authority


Central Level Project Implementation Unit (Education)
District Level Project Implementation Unit (Education),Gorkha
Emergency School Reconstruction Project (ESRP), JICA Loan No. : NE-P11
Contract Bills
FINAL INTERIM PAYMENT CERTIFICATE
Period: 15th November 2018 to 14th January 2020
Name of School: Shree Sarbodhaya L. S. School Payment Voucher no:
Name of Contractor:Sharma-A.M Joint Venture Date of payment:
Contract Number:ESRP/MOE/CLPIU/074/075-GORKHA-15 Page no of measurement book:
Serial no. of payment bills: 7
Voucher no.of previous payment bills:
Date of order for commencement of work: 15th November, 2018
Date of work to be completed: 14th January, 2020
Date of completion of work:
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
BILL NO.1 PRELIMINARIES/TEMPORARY WORKS
MOBILIZATION AND DEMOBILIZATION
1 L.S. 1.00 500,000.00 500,000.00 1.00 500,000.00 0.50 250,000.00 0.50 250,000.00 100.00%
Mobilization of the construction by constructing temporaty
acomodation
SITE OFFICE forESTABLISHMENT
labours and site staff with required suitable Per
2 facilities and 15.00 25,000.00 375,000.00 15.00 375,000.00 16.00 400,000.00 -1.00 (25,000.00) 100.00%
Providing andkeeping
Maintaining the same Site inOffice
good of hygenic
two Roomsconditionhavingfor Month
entire project completion
total Area INFORMATION
20 sq.m for the BOARD time. Demolition of
use of Client and Consultantthe same and
PROJECT
3 cleaning
includingthe site after completion
office of thefile construction activities nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 0.00 - 100.00%
Providing and chair,
FixingTable, Lockable
of Project cabinet,board
Information Stationery
with
all complete.
Items (Ink,Text Paper,[Note:
Pen, 50% payment
Pencils etc.), shall be and
1 Computer made after
1required
Printer
approved
SAFETY SIGN in appropriate
BOARD location including all
4 completion
with all of
necessary mobilization
set up. all and
complete remaining
as per 50%
instruction after
of nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 0.00 - 100.00%
fixing accessories
Providing and Fixingas per drawingSign
of per
Safety all complete.
Board with approved Text
completionThe
engineer. of works as
Specification contract]
of computer shall not be less than
and Sinage
BARRICADING including required fixing accessories as per
5 (19.5" led monitorWORKS with Core i5, 7th Generation, 500 gb Hdd, R.m 90.00 2,000.00 180,000.00 90.00 180,000.00 90.00 180,000.00 0.00 - 100.00%
drawing
Barricading all complete.
between
8gb ddr 4 ram), Printer the should School
function Academic
at least ofarea and
Printing,
Construction
DISMANTLING area
Scanning and Photocopy with OF 1.8ofmCOMPLETELY
A4highsize CGI Sheet fixed
documents. to Bamboo
DAMAGED
Providing and
6 support frame all complete as per instruction of Engineer. sq.m 186.60 5,000.00 933,000.00 179.00 895,000.00 179.00 895,000.00 0.00 - 95.93%
BUILDING
Maintaining all above items on Rental Basis for entire project
Demolition of existing damaged
completionMATERIALS
SAFETY time. & SITEbuilding SAFETY safely and handover
7 of the reusable L.S. 1.00 100,000.00 100,000.00 1.00 100,000.00 0.94 94,000.00 0.06 6,000.00 100.00%
Providing and materials
Maintaining to the school authority,
Construction Safety storing
Measures them in
to the location
Construction Siteshown
with by theSafety schoolmeasuresand disposing debris
CONSTRUCTION OFproperNEW TLC to person and
8 including
work area transportation
(Helmet, of debris ,cleaning site etc. Glove,
as per sq.m 104.82 3,000.00 314,460.00 104.82 314,460.00 104.82 314,460.00 0.00 - 100.00%
Construction of new Shoes, Temporary FirstLearning
Aid Kit,Centre(TLC),
Clothing, with
specification
Guard Rail andedge
for instruction
protection, of Engineer.Net, Safety rope, Fall
Locally
LAB Available
TEST(WATER materials
TEST) (CGISafetySheet and Bamboo etc.), rate
9 Protection
shall include etc.) as required
all Materials by the Contract Clause GCC 24 and job 1.00 7,500.00 7,500.00 - - 0.00 - 0.00 - 0.00%
Testing and Providing Labwith Testfixing
Report charge.
for Quality of Water in
Specification division 1 "GENERAL REQUIREMENT
Water
TEMPORARY Stream (Up and Down streem) located near by
10 CLAUSE 8(C)".TOILET
The number of Safety Materials Personal nos. 2 150,000.00 300,000.00 2.00 300,000.00 2.00 300,000.00 0.00 - 100.00%
Construction of
Construction sitetemporary
before Starting and CGI after completion of
Protecting Equipments (PPE) toilet
shall be withminimumSheet but notfixed
limitedto
construction
Bamboo work.
support Thisand
frame Testallhas to be done
necesary itemstoincluding
mark the affect
ROAD REPAIR
to 35 sets. Payment AND shallMAINTENANCE
be made in Prorata Basis for Septic
entire
11 of construction
pit, Pipeline, workPan
Toilet in water
etc. for stream. project completion time Km 4.00 50,000.00 200,000.00 4.00 200,000.00 4.00 200,000.00 0.00 - 100.00%
Providing
duration of and Maintaining
project. the entire
roads as necessary to avoid
all complete
blockage as per Instruction
by Landslides and Rockfallof Engineer. Rate shall
for regular include
transport of
all Material materials
construction cost withand fixing,
site construction
inspection during charges and
overall
BILL NO. 2 CIVIL WORKS- BUILDING
demolition &period.
construction cleaning Rate ofshall
the sameinclude after
all completion
Material cost ofwith
the
SITE CLEARANCE
construction activities & MOBILIZATION:
all complete.
1.1 demolition charges, cleaning, fixing & construction charges of sq.m 701.87 100.00 70,187.00 642.41 64,241.35 696.52 69,652.00 -54.11 (5,410.65) 91.53%
Clearing and grubbing the site for construction by removing
the same after
150mm thick top IN completion
soilEXCAVATION
including of bushes,
the construction activities all
EARTHWORK
complete. : small trees, leveling of
1.2 undulated ground, shortinginand top cu.m 315.17 400.00 126,068.00 317.72 127,088.50 289.67 115,866.89 28.05 11,221.61 100.81%
Excavation in foundations all stacking/storing
type of soils forselected foundation,
soil for reuse
trenches, footing, in pits
landscaping
etc. to works, disposing unsuitable
EARTH BACK FILLING : the required depth including
1.3 materials
dewatering from site, etc., or all complete means as peretc.drawings, per cu.m 204.21 300.00 61,263.00 236.58 70,972.99 191.14 57,342.00 45.44 13,630.99 115.85%
Back fillingbyin manual
foundation mechanical
and sides of foundationas with
specifications
specifications and
withinstructions
allfrom of the Engineer.
contractor’s ownat machinery and
approved soil
BOULDER SOLING : obtained the excavation site and stacked
1.4 equipment's,
at site or broughtproviding
from crossinginoflayer
outside track,not shoring,
exceeding strutting,
cm cu.m 98.81 6,000.00 592,860.00 98.87 593,222.73 78.96 473,730.45 19.92 119,492.28 100.06%
Providing and laying uncoursed hand packed Dry Rubble15 Stone
timbering and buttressing
thick (compacted thickness) with appropriate
including materials andsoil, all
soling
SAND in foundation,
FILLING : under floor plinthtransportation
with out any of special
1.5 such measures
spreadingof necessary
in required to retain
line and level, in position
sprinkling the
water,sides of
ramming, the cu.m 4.98 6,000.00 29,880.00 4.65 27,900.00 0.00 - 4.65 27,900.00 93.37%
dressing
Providing and stone including
filling filling
sand inrefilling
soak pit. interstices with suitable
foundation
compacting pitwith
and including
mechanical rammers, theallexcavated
completematerial
testing,
as per
etc., all
quarry
drawings, waste or stone
specifications and chips or quarry
instruction ofand sand, watering,
the Engineer.
with watering,
complete as perramming,
drawing, leveling
specificationthe site and disposing off
instructions of the
the
compacting using appropriate mechanical compaction means
surplus/unusable earth to outside the construction premises, etc.
Engineer.
with all contractors materials, handling, placing etc. all
all complete as per drawings, specifications and instructions of
complete as per drawings, specifications and instruction of the
the Engineer.
Prepared by contractor Checked by Consultant,
Engineer. The complete item including all lead & lift.DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
CONCRETE WORKS
2.1.1 cu.m 13.20 14,000.00 184,800.00 14.09 197,314.25 13.78 192,920.00 0.31 4,394.25 106.77%
P.C.C (1:3:6)
Providing
P.C.C and WORKS
(1:2:4) laying machine mixed Plain Cement Concrete of
2.1.2 nominal mix cu.m 27.19 16,000.00 435,040.00 24.18 386,819.16 19.73 315,680.00 4.45 71,139.16 88.92%
Providing and1:3:6laying (1 machine
cement : mixed3 sandPlain: 6 coarse
Cement aggregate
Concrete ) for
of
leveling course
nominal mix 1:2:4 in foundations
cement : and
(1 WORKS 2: sandunder floor ofaggregate
: 4 coarse building,)etc.
for
P.C.C. FOR R.C.C.
2.2 in all level
leveling withinbroken
course foundationsstone aggregate under of
andmachine sizeofnot
floor more than
building, etc. cu.m 240.98 20,000.00 4,819,600.00 240.41 4,808,165.34 224.25 4,485,024.02 16.16 323,141.31 99.76%
Providing and laying in position mixed and machine
25 mm
in all level of with
approved
brokenqualitystone including offormwork
aggregate size not more wherever
than3
vibrated
SILICA cement
CEMENT concrete of mix
ADMIXTURE 1:1.5:3 (1 cement:1.5 sand:
2.3 necessary,
25 mmaggregate)dewatering,
of approved batching,
quality mixing,
including transporting,
formwork placing,
wherever kg 2,409.80 300.00 722,940.00 2,404.08 721,224.80 2242.51 672,753.60 161.57 48,471.20 99.76%
coarse
Providing andcuring, mixing M20 grade
Silica for
Cement reinforced cement concrete
compacting,
necessary, dewatering, including
batching, leadAdmixture
all mixing, of all
andtransporting,
lift, etc. in structural
complete
placing,
work
concreteusingat theapproved
rate ofcement
2.50% with byand 20 mm
weight of graded
the cement machine
for
STEEL
compacting, REINFORCEMENT
as per drawings, curing, specifications
including all lead the lift,
and instructions
etc. all of the
complete
2.4 crushed stone
promoting aggregate of approved strength,
quality inachievingvarious Mt. 38.57 130,000.00 5,014,100.00 40.74 5,295,781.23 39.53 5,139,125.75 1.21 156,655.48 105.62%
Providing
Engineer.
as per andworkability,
drawings, fixing in position
specifications
improving
Feand 500thesteel reinforcement
instructions of
of the
locations and heights
waterproofing properties, includingbleedingtransportation
prevention, of concrete
etc. to
Silica
various
FORM
Engineer. diameter confirming to relevant IS code in R.C.C.
WORKS
2.5 site of placing,
Cement Admixture compaction,
shall be finished
the to required
product of line and
Silica level,
Japan or sq.m 1,734.43 800.00 1,387,544.00 1,719.80 1,375,838.08 1627.28 1,301,822.44 92.52 74,015.64 99.16%
works including
Supplying and straightening,
laying centering, cutting,
shutteringbending,
of binding
various with
pattern
protection
superior and
and shallwirecuring,
meet etc. all complete as per drawings,
20 SWG annealed
formworks withand 19/12 for the
tying requirements
thick the reinforcementas mentioned
bars & in
at steel
each
BRICK
specifications
specification MASONRY
of materialsthemminstructions
WORKSBRICK
and not
water proof
of
Workmanship, theplyEngineer,
wood
MASONRY
Division – but
4:
junctions
adjustable (binding
props forofwire
all shall
kinds be works
ofshuttering,
RCC measured separately)
forreinforcement,
foundations,
3.1 WORKS
excluding
Concrete Works,(
the 1 : 4
cost c/s )
Article ONE
centering,
2.4 SIDE FAIRFACE and cu.m 84.41 20,000.00 1,688,200.00 - - 0.00 - 0.00 -
including
columns, all waste
shear walls, and
beams,cutslab,pieces, provision
staircase, lintel, for
sill,adequate
pergola,
Providing
all complete andaslaying first class
per drawings, selected
specifications factory
and pressed
instructions wire
of
numbers of
including nails,spacers,
propping chairs, providing
scaffolding, and supporting
staging, placing cement and
cut Fair Face
the Engineer. brick (machine made brick) one or more brick
7.2.3 mortar
bracing
CLEAR (1:1)
in coverlines
proper
SILICON blocks and tolevel,
WATER-REPELENT keep sealing
the barsCOATING
in joints
the intended withposition
heavy sq.m
thick wall in cement mortar 1:4 (1 cement : 4coarse sand) in
at all brown
duty levels WORKall complete
selfand adhesive astape,
per drawings,
aligning specifications and
8.1.1 POINTING
,superstructure IN
otherBRICK MASONARY
specified places to in line and levels
all heights and sq.m
instructions Ties,
including of the PVCEngineer. Spacer,(Authorized lapopenings/
length andcutouts/
for the
level
BOQ
bar
including
Totalexceeding
length
the cost
of items 3.1.,
10
of7.2.3
meter
single &Providing
in
or multi stage
8.1.1:
length shall be
self standing
measured for
pockets, applying
scaffolding, soaking De-shuttering
bricks, curing, chemical,
raking De-shuttering
joints, provision as
for
Replaced
the payment, items 3.1, to 7.2.3 and 8.1.1 with following items for
approved
recesses, by except
the Engineer
openings,
column).
toothing etc.,
etc., complete
all completeat all as levels
per as per
drawing,
3-6C(S)-E, 2-4C(S) and Ts(F)
drawing, specifications
specifications and instructionsand instructions of the Engineer.
of the Engineer.
Brick Masonry Works (1:4 c/s) cu.m 18,000.00 - - - 0.00 - 0.00 -
Cement Plaster Works on Outer Wall (1:6) sq.m 600.00 - - - 0.00 - 0.00 -
Exterior Weather Coat Paint sq.m 350.00 - - - 0.00 - 0.00 -

BRICK MASONRY WORKS ( 1 : 4 c/s )


3.2 cu.m 76.21 18,000.00 1,371,780.00 145.33 2,615,986.35 137.83 2,480,932.16 7.50 135,054.20 190.70%
Providing and laying first class chimney fired brick one or
3.3 more
HALFbrick thick WORKS
BRICK wall in cement
( 1 : 4mortar
c/s ) 1:4 (1 cement : 4 coarse sq.m 64.50 1,500.00 96,750.00 28.40 42,599.10 21.95 32,921.25 6.45 9,677.85 44.03%
3.4 sand)
HONEY in COMB
foundation
BRICK up WORKS
to plinth,(1:3
superstructure
c/s) and other cu.m 0.48 9,000.00 4,320.00 0.48 4,279.50 0.24 2,160.00 0.24 2,119.50 99.06%
specified places in all heights and level including the cost of
4 DOORS & WINDOWS WORKS
single or multi stage scaffolding, soaking bricks, curing, raking
4.1 METAL
joints, FRAME for recesses, openings, toothing etc., all
provision
4.1.1 complete
Door Frame as per drawing, specifications and instructions of the r.m 151.04 1,100.00 166,144.00 151.04 166,144.00 152.00 167,200.00 -0.96 (1,056.00) 100.00%
Engineer.
4.1.2 Window Frame r.m 383.66 1,100.00 422,026.00 363.06 399,360.50 363.06 399,366.00 0.00 (5.50) 94.63%
4.2 METAL SHUTTER
4.2.1 WINDOW SHUTTER sq.m 78.99 7,500.00 592,425.00 64.28 482,071.31 78.99 592,425.00 -14.71 (110,353.69) 81.37%
4.3 WOODEN SHUTTER
4.3.1 FLUSH DOOR SHUTTER (32MM) sq.m 58.33 8,000.00 466,640.00 52.64 421,083.60 58.33 466,640.00 -5.69 (45,556.40) 90.24%
4.4 UPVC DOOR
4.4.1 Shutter/Frame sq.m 7.14 9,000.00 64,260.00 6.97 62,730.00 7.14 64,260.00 -0.17 (1,530.00) 97.62%
4.5 WINDOW GRILL sq.m 50.07 2,500.00 125,175.00 71.07 177,665.44 46.95 117,375.00 24.12 60,290.44 141.93%
4.6 COLLAPSIBLE GATE sq.m 14.98 10,000.00 149,800.00 14.98 149,767.50 0.00 - 14.98 149,767.50 99.98%
5 FLOORING WORKS
5.1 HARDENED CEMENT CONCRETE FLOOR sq.m 782.82 900.00 704,538.00 781.44 703,293.98 731.10 657,990.00 50.34 45,303.98 99.82%
5.2 NEAT CEMENT SKIRTING r.m 420.91 100.00 42,091.00 433.94 43,394.10 421.98 42,198.00 11.96 1,196.10 103.10%
5.3 TERRAZZO CAST-IN SITU DADO sq.m 36.63 1,500.00 54,945.00 36.48 54,720.00 32.88 49,320.00 3.60 5,400.00 99.59%
6 ROOFING/TERRACING WORK
6.1 METAL WORKS (TRUSS) kg 6660.99 220.00 1,465,417.80 7,687.63 1,691,279.68 6660.99 1,465,417.80 1026.64 225,861.88 115.41%
6.2 CGI SHEET ROOFING sq.m 439.95 2,000.00 879,900.00 444.54 889,080.00 439.95 879,900.00 4.59 9,180.00 101.04%
6.3 CGI SHEET ROOFING RIDGE r.m 42.6 1,200.00 51,120.00 42.75 51,300.00 42.60 51,120.00 0.15 180.00 100.35%
6.4 GI FACIA (EAVES) kg 387.62 250.00 96,905.00 295.89 73,972.50 381.29 95,322.50 -85.40 (21,350.00) 76.34%
6.5 CEMENT BOARD FALSE CEILING sq.m 344.15 1,500.00 516,225.00 373.56 560,337.00 344.14 516,210.00 29.42 44,127.00 108.55%
7 PLASTERING/WALL FINISHING WORK
7.1 CEMENT PLASTER WORK

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
7.1.1 ON INNER WALL sq.m 923.13 600.00 553,878.00 947.85 568,709.19 923.13 553,878.00 24.72 14,831.19 102.68%
7.1.2 ON CEILING (1:4) sq.m 360.86 500.00 180,430.00 495.87 247,936.89 360.86 180,429.96 135.01 67,506.93 137.41%
7.1.3 ON OUTER WALL (1:6)
7.1.3.1 EXTERNAL PLASTER sq.m 430.90 600.00 258,540.00 775.79 465,474.24 697.26 418,358.85 78.53 47,115.39 180.04%
7.1.4 EXTERNAL PLASTER WITH CEMENT PUNNING sq.m 35.21 700.00 24,647.00 35.66 24,962.00 35.66 24,962.00 0.00 - 101.28%
7 PAINTING WORKS
7.2.1 DISTEMPER PAINT sq.m 1599.82 200.00 319,964.00 1,817.29 363,457.50 1659.67 331,934.00 157.62 31,523.50 113.59%
7.2.2 EXTERIOR WEATHER COAT PAINT sq.m 461.26 350.00 161,441.00 775.79 271,527.81 411.73 144,105.50 364.06 127,422.31 168.19%
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG sq.m 369.72 550.00 203,346.00 - - 0.00 - 0.00 - 0.00%
7.2.4 ENAMEL PAINT sq.m 392.72 400.00 157,088.00 409.43 163,771.80 347.79 139,116.00 61.64 24,655.80 104.25%
8 MISCELLANEOUS
8.2 CEMENT BOARD WALL sq.m 32.61 6,500.00 211,965.00 34.16 222,040.00 32.61 211,965.00 1.55 10,075.00 104.75%
8.3 RAILING kg 1496.50 220.00 329,230.00 1,527.10 335,962.96 1287.60 283,272.00 239.50 52,690.96 102.05%
8.4 PUMP SHED nos. 1.00 80,000.00 80,000.00 1.00 80,000.00 0.00 - 1.00 80,000.00 100.00%

3 ELECTRICAL WORKS
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure no. 2.00 12,000.00 24,000.00 2.00 24,000.00 2.00 24,000.00 0.00 - 100.00%
1.2 Stand Alone 6 A DP MCB with Enclosure no. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2.1 2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper rm 100.00 800.00 80,000.00 97.00 77,600.00 100.00 80,000.00 -3.00 (2,400.00) 97.00%
2.2 conductor wires mutistranded copper conductor wires + 1
2 Nos 2.5 Sq.mm rm 50.00 250.00 12,500.00 51.00 12,750.00 0.00 - 51.00 12,750.00 102.00%
B Nos. 1.5sq
School mm multistranded Cu wire
Blocks
1 DISTRIBUTION BOARDS nos.
1.1 Ground Floor nos. 2.00 30,000.00 60,000.00 2.00 60,000.00 2.00 60,000.00 0.00 - 100.00%
1.2 First Floor nos. 2.00 22,000.00 44,000.00 2.00 44,000.00 2.00 44,000.00 0.00 - 100.00%
1.3 Second Floor nos. 1.00 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 0.00 - 100.00%
1.4 Stand Alone 6 A DP MCB with Enclosure nos. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm
2.1 Multistranded Cu wire rm 15.00 600.00 9,000.00 15.00 9,000.00 15.00 9,000.00 0.00 - 100.00%
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm
2.2 Multistranded Cu wire rm 15.00 500.00 7,500.00 10.00 5,000.00 15.00 7,500.00 -5.00 (2,500.00) 66.67%
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.2 rm 30.00 250.00 7,500.00 16.00 4,000.00 30.00 7,500.00 -14.00 (3,500.00) 53.33%
Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point pts. 74.00 700.00 51,800.00 75.00 52,500.00 74.00 51,800.00 1.00 700.00 101.35%
3.2 Two Way Light Point pts. 3.00 900.00 2,700.00 3.00 2,700.00 3.00 2,700.00 0.00 - 100.00%
3.3 Ceiling Fan Point pts. 8.00 900.00 7,200.00 8.00 7,200.00 6.00 5,400.00 2.00 1,800.00 100.00%
4 16 A Universal Pin Light Power Socket Wiring pts. 1.00 900.00 900.00 1.00 900.00 1.00 900.00 0.00 - 100.00%
5 6A Universal Pin Light Power Supplying, wiring, testing and
Socket Wiring pts. 43.00 700.00 30,100.00 43.00 30,100.00 43.00 30,100.00 0.00 - 100.00%
commissioning and putting into operation for 6 A light power
6 Switch
point Socket
using 2 x Outlets
4 sq mm + 1 x 2.5 Sq mm multi stranded
6.1 copper
16 conductor,
A Universal Pin 1100
Lightvolts grade,
Power PVC insulated
Socket Wiring wires nos. 1.00 1,500.00 1,500.00 1.00 1,500.00 1.00 1,500.00 0.00 -
drawn through pre
6A Universal Powerinstalled
Switch25Socket
mm dia 2 mm
Supplying, thick HDP
wiring, pipe,
testing
6.2 nos. 43.00 900.00 38,700.00 44.00 39,600.00 43.00 38,700.00 1.00 900.00 102.33%
cablecommissioning
and sleeve/support but andincluding specified
putting into dia pipes
operation for 6 A light
7 Sweep
power Ceiling/Exhaust
concealed in wall
point usingand Fans/
2 xfloor Wall
4 sqincluding
mm + 1 xall Fan
2.5fixing
Sq mm andmulti
connecting
7.1 materials.
stranded The rateCeiling
1200 mm copper
Sweep for point
conductor,Fanwiring
1100 shall
volts include
grade, PVCthe circuit no. 2.00 4,500.00 9,000.00 2.00 9,000.00 4.00 18,000.00 -2.00 (9,000.00) 100.00%
wiring from
insulated deginated
wires drawnDistribution
through pre Board (DB)25
installed upmmto the
diafirst
2
7.2 400 mm Sweep Wall Fan no. 6.00 3,500.00 21,000.00 6.00 21,000.00 12.00 42,000.00 -6.00 (21,000.00) 100.00%
power
mm pointHDP
thick thenpipe,
the looping between sockets.
cable sleeve/support butThe cost shall
including
7.3 225mm
be dia
excluding
specified diaM/D Exhaust
modular
pipes Fan inswitch
formation
concealed wall and sockets
floorand their all
including nos. 2.00 6,000.00 12,000.00 2.00 12,000.00 2.00 12,000.00 0.00 - 100.00%
8 flushing
fixing andGIconnecting
box but including
Light Fixtures/Luminaires &GIAccessories
materials. fish
Thewire,
ratecutting
for pointandwiring
filling
chasesinclude
shall for recessed pipes wiring
the circuit as deemedfrom as deginated
per drawing and lay out
Distribution
plan all(DB)
Board complete.
up to the first power point then the looping
between sockets. The cost shall be excluding modular
formation switch sockets and their flushing GI box but
Prepared by contractor
including GI fish wire, cutting Checked andby Consultant,
filling chases for DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
recessed pipes as deemed as per drawing and lay out plan
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
8.1 24 W LED Recessed Mounted Square type nos. 4.00 4,500.00 18,000.00 4.00 18,000.00 4.00 18,000.00 0.00 - 100.00%
8.2 18 W LED Surface Mounted Square type CRCA Powder nos. 22.00 2,700.00 59,400.00 22.00 59,400.00 22.00 59,400.00 0.00 - 100.00%
8.3 Coated
18 withRecessed
W LED PMMA Diffuser
Mountedhaving
Square6000
typeKCRCA
ColorPowder nos. 12.00 2,700.00 32,400.00 12.00 32,400.00 12.00 32,400.00 0.00 - 100.00%
Temperature,
Coated IP20 rated.
withSurface
PMMA Diffuser Cylindrical
having 6000type
K Color
8.4 12 W LED Mounted CRCA Powder nos. 15.00 2,400.00 36,000.00 15.00 36,000.00 13.00 31,200.00 2.00 4,800.00 100.00%
Temperature,
Coated IP20 rated.
withRecessed
PMMA Diffuser
8.5 12 W LED Mountedhaving 6000
Crrcular K CRCA
type Color Powder nos. 10.00 2,400.00 24,000.00 10.00 24,000.00 10.00 24,000.00 0.00 - 100.00%
Temperature,
Coated IP20 rated.
withLight
PMMA Diffuser
8.6 LED Wall made of highhaving 6000 K aluminium
grade die-cast Color nos. 3.00 1,800.00 5,400.00 3.00 5,400.00 3.00 5,400.00 0.00 - 100.00%
Temperature,
Powder IP20 rated.
8.7 9W LEDCoated
Surface with PMMACylindrical
Mounted Diffuser having 6000 K
type CRCA Color
Powder nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
Temperature,
Coated with IP65 rated
PMMA with 7having
Diffuser W LED Lamp.
8.8 6W LED Recessed Mounted Circular6000
type K Color nos. 3.00 1,800.00 5,400.00 3.00 5,400.00 3.00 5,400.00 0.00 - 100.00%
Temperature, IP20 rated.
8.9 7W LED T5 Slim Mirror Light nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
9 Pull Box nos. 6.00 700.00 4,200.00 6.00 4,200.00 6.00 4,200.00 0.00 - 100.00%
10 External Post Top Light Pole nos. 6.00 7,500.00 45,000.00 6.00 45,000.00 6.00 45,000.00 0.00 - 100.00%
11 Post Top External Light Fixtures nos. 6.00 9,800.00 58,800.00 6.00 58,800.00 6.00 58,800.00 0.00 - 100.00%
12 Earthing & Lighting Protection
12.1 Chemical Earthing nos. 6.00 45,000.00 270,000.00 6.00 270,000.00 6.00 270,000.00 0.00 - 100.00%
12.2 Earthing Bar nos. 6.00 2,200.00 13,200.00 6.00 13,200.00 6.00 13,200.00 0.00 - 100.00%
13 Earthing Strip/Wires
13.1 25 x 3 mm GI strip mtr. 130.00 300.00 39,000.00 132.00 39,600.00 130.00 39,000.00 2.00 600.00 101.54%
13.2 12 SWG Cu wire mtr. 30.00 200.00 6,000.00 31.00 6,200.00 30.00 6,000.00 1.00 200.00 103.33%
14 Earth Test link nos. 2.00 1,500.00 3,000.00 2.00 3,000.00 2.00 3,000.00 0.00 - 100.00%
C Solar PV System
1 Solar PV Panel nos. 4.00 26,000.00 104,000.00 4.00 104,000.00 4.00 104,000.00 0.00 - 100.00%
2 Tubular Deep Cycle Battery nos. 2.00 30,000.00 60,000.00 2.00 60,000.00 2.00 60,000.00 0.00 - 100.00%
3 Hybrid Inverter 1.00 100,000.00 100,000.00 1.00 100,000.00 1.00 100,000.00 0.00 - 100.00%
D FIRE EXTINGUISHER
a Supplying Fire extinguisher ABC stored Pressure 5.0kg size nos. 2.00 8,000.00 16,000.00 2.00 16,000.00 0.00 - 2.00 16,000.00 100.00%
b ABC stored pressure
Dry Powder type Fire conforming
Fire Extinguisher extinguisher.to BS 5423:1987 or nos. 1.00 8,000.00 8,000.00 1.00 8,000.00 0.00 - 1.00 8,000.00 100.00%
as given in BOQ. The Dry Powder agents shall be mono-
ammonium phosphate and ammonium sulphate base as per
BILL No. below.all
specidfied 4. SANITARY WORKS
complete
A PIPING WORKS
1 WATER SUPPLY INSTALLATION
a) CPVC pipes
- 40 mm Rm 60 1,600.00 96,000.00 55.00 88,000.00 10.00 16,000.00 45.00 72,000.00 91.67%
- 25 mm Rm 70 1,000.00 70,000.00 18.00 18,000.00 15.00 15,000.00 3.00 3,000.00 25.71%
- 20 mm Rm 11 700.00 7,700.00 10.00 7,000.00 5.00 3,500.00 5.00 3,500.00 90.91%
- 15 mm Rm 4 500.00 2,000.00 2.50 1,250.00 15.00 7,500.00 -12.50 (6,250.00) 62.50%
c) CPVC Ball Valve
- 40 mm No. 4 2,000.00 8,000.00 2.00 4,000.00 2.00 4,000.00 0.00 - 50.00%
- 25 mm No. 4 900.00 3,600.00 3.00 2,700.00 2.00 1,800.00 1.00 900.00 75.00%
20mm No. 2 400.00 800.00 2.00 800.00 2.00 800.00 0.00 - 100.00%
40 mm dia Gun Metal Check valve No. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 0.00 - 100.00%
d) Electric Centrifugal Water Pump Set 1 12,500.00 12,500.00 1.00 12,500.00 - 1.00 12,500.00 100.00%
e) 1000 litres capacity Plastic cyllindrical vertical water storage No. 1 34,000.00 34,000.00 1.00 34,000.00 1.00 34,000.00 0.00 - 100.00%
tank

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
2 SEWER, RAIN AND WASTE WATER INSTALLATION
PVC SWR
110 mm Rm 33 1,400.00 46,200.00 32.00 44,800.00 15.00 21,000.00 17.00 23,800.00 96.97%

75 mm Rm 33 1,200.00 39,600.00 25.00 30,000.00 12.00 14,400.00 13.00 15,600.00 75.76%


50 mm Rm 4 350.00 1,400.00 2.00 700.00 - 2.00 700.00 50.00%

B SCHOOL BLOCKS
1 SANITARY INSTALLATION
a Stainless Steel Kitchen Sink Set 1 35,000.00
b CP self closing bib cock No 1 4,000.00 4,000.00 1.00 4,000.00 - 1.00 4,000.00 100.00%
c PVC Multi-floor trap with cover No. 1 600.00 600.00 1.00 600.00 - 1.00 600.00 100.00%
CP Waste Coupling and PVC bottle trap for water trough
d No. 1 1,500.00 1,500.00 1.00 1,500.00 - 1.00 1,500.00 100.00%

2 SANITARY INSTALLATION
a Water Closet set Set 1 34,000.00 34,000.00 1.00 34,000.00 - 1.00 34,000.00 100.00%
b 580x480mm Orissa Pan Set 2 3,100.00 6,200.00 2.00 6,200.00 - 2.00 6,200.00 100.00%
c Hand wash basin Set 1 8,000.00 8,000.00 1.00 8,000.00 - 1.00 8,000.00 100.00%
d Urinal Set 2 110,000.00 220,000.00 2.00 220,000.00 - 2.00 220,000.00 100.00%
e CP self closing bib cock No 6 4,000.00 24,000.00 6.00 24,000.00 - 6.00 24,000.00 100.00%
f CP spreader for Urinal Set 2 2,500.00 5,000.00 2.00 5,000.00 - 2.00 5,000.00 100.00%
g CP Toilet Paper Holder heavy No. 1 2,600.00 2,600.00 1.00 2,600.00 1.00 2,600.00 0.00 - 100.00%
h 15mm CP Commode Spray with plastic head No. 1 2,000.00 2,000.00 1.00 2,000.00 - 1.00 2,000.00 100.00%
i PVC Multi-floor trap with cover No. 5 600.00 3,000.00 5.00 3,000.00 - 5.00 3,000.00 100.00%
j CP Waste Coupling and PVC bottle trap for water trough No. 2 1,500.00 3,000.00 2.00 3,000.00 - 2.00 3,000.00 100.00%
k 40 mm SS Grab bar of 600mm Length - Side Set 1 4,500.00 4,500.00 1.00 4,500.00 - 1.00 4,500.00 100.00%
l 40 mm SS Grab bar of 600mm Length - Rear Set 1 4,500.00 4,500.00 1.00 4,500.00 - 1.00 4,500.00 100.00%
m CP Foldable Hinge Set 2 5,500.00 11,000.00 2.00 11,000.00 1.00 5,500.00 1.00 5,500.00 100.00%

B CIVIL WORKS : SITE DEVELOPMENT


1 EARTHWORKS
1 SITE CLEARANCE AND MOBILIZATION Sq.m 256.72 100.00 25,672.00 152.63 15,263.00 152.63 15,263.00 0.00 - 59.45%
2 EARTHWORK IN EXCAVATION Cu.m 171.79 400.00 68,716.00 21.84 8,736.00 19.82 7,928.00 2.02 808.00 12.71%
3 EARTHBACK FILLING Cu.m 37.75 300.00 11,325.00 19.19 5,757.00 19.19 5,757.00 50.83%
4 BOULDER SOLING Cu.m 26.16 6,000.00 156,960.00 23.72 142,320.00 8.81 52,860.00 14.91 89,460.00 90.67%
5 P.C.C (1:3:6) Cu.m 1.31 14,000.00 18,340.00 1.14 15,960.00 0.54 7,560.00 0.60 8,400.00 87.02%
6 P.C.C (1:2:4) Cu.m 12.98 16,000.00 207,680.00 9.39 150,240.00 9.40 150,330.18 -0.01 (90.18) 72.34%
7 P.C.C FOR R.C.C WORK Cu.m 0.99 20,000.00 19,800.00 0.99 19,800.00 0.99 19,800.00 0.00 - 100.00%
8 SILICA CEMENT ADMIXTURE Kg 9.90 300.00 2,970.00 9.90 2,970.00 9.90 2,970.00 0.00 - 100.00%
9 STEEL REINFORCEMENT Mt. 0.10 130,000.00 13,000.00 0.11 13,897.00 0.10 12,952.47 0.01 944.53 106.90%
10 FORM WORKS Sq.m 9.12 800.00 7,296.00 11.33 9,064.00 9.12 7,296.00 2.21 1,768.00 124.23%
11 STONE MASONARY WORKS (1:4 c/s) Cu.m 4.81 10,000.00 48,100.00 4.35 43,500.00 - 4.35 43,500.00 90.44%
13 BRICKS MASONRY WORKS (1:4 c/s) Cu.m 0.22 18,000.00 3,960.00 7.91 142,469.82 0.20 3,600.00 7.71 138,869.82 3597.72%
14 NEAT CEMENT SKIRTING r.m 4.72 100.00 472.00 4.72 472.00 4.72 472.00 0.00 - 100.00%
15 METAL WORKS FOR FENCE k.g 790.75 220.00 173,965.00 744.98 163,895.60 353.18 77,699.60 391.80 86,196.00 94.21%
16 METAL WORKS FOR GATE k.g 130.78 220.00 28,771.60 123.31 27,128.09 159.63 35,118.60 -36.32 (7,990.51) 94.29%
17 PLASTER ON OUTER WALL Sq.m 7.92 600.00 4,752.00 49.26 29,556.00 49.26 29,556.00 0.00 - 621.97%
18 EXTERIOR WEATHER COAT PAINT Sq.m 8.87 350.00 3,104.50 8.28 2,898.00 8.28 2,898.00 0.00 - 93.35%
19 CHAIN LINK FENCE Sq.m 82.94 1,000.00 82,940.00 102.00 102,000.00 54.00 54,000.00 48.00 48,000.00 122.98%

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
20 FLAG POLE nos. 2.00 25,000.00 50,000.00 2.00 50,000.00 2.00 50,000.00 0.00 - 100.00%
-
CIVIL WORKS-RESERVOIR TANK -
1 EARTH WORK -
1.1 SITE CLEARANCE AND MOBILIZATION sq.m 22.31 100.00 2,231.00 22.31 2,231.00 22.31 2,231.00 0.00 - 100.00%
1.2 EARTHWORK IN EXCAVATION cu.m 24.58 400.00 9,832.00 24.57 9,828.72 24.57 9,828.72 0.00 - 99.97%
1.3 EARTH BACK FILLING cu.m 4.02 300.00 1,206.00 4.01 1,202.85 4.01 1,202.85 0.00 - 99.74%
1.4 BOULDER SOLING cu.m 2.08 6,000.00 12,480.00 2.08 12,462.00 2.08 12,462.00 0.00 - 99.86%
2 CONCRETE WORKS
2.1 P.C.C (1:3:6) cu.m 0.78 14,000.00 10,920.00 0.78 10,904.25 0.78 10,904.25 0.00 - 99.86%
2.2 P.C.C FOR R.C.C WORKS cu.m 7.42 20,000.00 148,400.00 7.41 148,295.00 7.41 148,295.00 0.00 - 99.93%
2.3 SILICA CEMENT ADMIXTURE kg 74.20 300.00 22,260.00 74.15 22,244.25 74.15 22,244.25 0.00 - 99.93%
2.4 STEEL REINFORCEMENT Mt 1.46 130,000.00 189,800.00 1.58 204,902.61 1.57 203,977.54 0.01 925.07 107.96%
2.5 FORMWORKS sq.m 54.93 800.00 43,944.00 56.46 45,170.80 56.46 45,170.80 0.00 - 102.79%
3 PLASTERING/WALL FINISHING WORKS
INTERNAL PLASTER ON WALL (1:4) WITH CEMENT
3.1.1 sq.m 33.66 700.00 23,562.00 35.46 24,824.45 27.57 19,301.45 7.89 5,523.00 105.36%
PUNNING
4 WATERPROOFING WORKS sq.m 33.66 550.00 18,513.00 35.46 19,504.93 27.57 15,165.43 7.89 4,339.50 105.36%
- - - 0.00 - 0.00 -
FURNITURE WORKS lot 1 4,000,000.00 4,000,000.00 1.00 4,000,000.00 1.00 4,000,000.00 0.00 - 100.00%
Total 35,254,804.90 35,280,032.74 32,354,943.32 2,925,089.43

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Government of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (Education)
District Level Project Implementation Unit (Education),Gorkha
Emergency School Reconstruction Project (ESRP), JICA Loan No. : NE-P11
Contract Bills
FINAL INTERIM PAYMENT CERTIFICATE
Period: 15th November 2018 to 14th January 2020
Name of School: Shree Sarbodhaya L. S. School Payment Voucher no:
Name of Contractor:Sharma-A.M Joint Venture Date of payment:
Contract Number:ESRP/MOE/CLPIU/074/075-GORKHA-15 Page no of measurement book:
Serial no. of payment bills: 7
Voucher no.of previous payment bills:
Date of order for commencement of work: 15th November, 2018
Date of work to be completed: 14th January, 2020
Date of completion of work:
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
BILL NO.1 PRELIMINARIES/TEMPORARY WORKS
MOBILIZATION AND DEMOBILIZATION
1 L.S. 1.00 500,000.00 500,000.00 1.00 500,000.00 0.50 250,000.00 0.50 250,000.00 100.00%
Mobilization of the construction by constructing temporaty
acomodation
SITE OFFICE forESTABLISHMENT
labours and site staff with required suitable Per
2 facilities and 15.00 25,000.00 375,000.00 15.00 375,000.00 16.00 400,000.00 -1.00 (25,000.00) 100.00%
Providing andkeeping
Maintaining the same Site inOffice
good of hygenic
two Roomsconditionhavingfor Month
entire project completion
total Area INFORMATION
20 sq.m for the BOARD time. Demolition of
use of Client and Consultantthe same and
PROJECT
3 cleaning
includingthe site after completion
office of thefileconstruction activities nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 0.00 - 100.00%
Providing and chair,
FixingTable, Lockable
of Project cabinet,board
Information Stationery
with
all complete.
Items (Ink,Text Paper,[Note:
Pen, 50% payment
Pencils etc.), shall be and
1 Computer made after
1required
Printer
approved
SAFETY SIGN in appropriate
BOARD location including all
4 completion
with all of
necessary mobilization
set up. all and
complete remaining
as per 50%
instruction after
of nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 0.00 - 100.00%
fixing accessories
Providing and Fixing as per drawingSign
of per
Safety all complete.
Board with approved Text
completionThe
engineer. of works
Specificationas contract]
of computer shall not be less than
and Sinage
BARRICADING including required fixing accessories as per
5 (19.5" led monitorWORKS with Core i5, 7th Generation, 500 gb Hdd, R.m 90.00 2,000.00 180,000.00 90.00 180,000.00 90.00 180,000.00 0.00 - 100.00%
drawing
Barricading all complete.
between
8gb ddr 4 ram), Printer the should School
function Academic
at least ofarea and
Printing,
Construction
DISMANTLING area
Scanning and Photocopy with OF 1.8ofmCOMPLETELY
A4highsizeCGI Sheet fixed
documents. to Bamboo
DAMAGED
Providing and
6 support frame all complete as per instruction of Engineer. sq.m 186.60 5,000.00 933,000.00 179.00 895,000.00 179.00 895,000.00 0.00 - 95.93%
BUILDING
Maintaining all above items on Rental Basis for entire project
Demolition of existing damaged
completionMATERIALS
SAFETY time. & SITEbuilding SAFETY safely and handover
7 of the reusable L.S. 1.00 100,000.00 100,000.00 1.00 100,000.00 0.94 94,000.00 0.06 6,000.00 100.00%
Providing and materials
Maintaining to the school authority,
Construction Safety storing
Measures them in
to the location
Construction Siteshownwith by theSafety schoolmeasures
and disposing debris
CONSTRUCTION OFproper
NEW TLC to person and
8 including
work area transportation
(Helmet, of debris ,cleaning site etc. Glove,
as per sq.m 104.82 3,000.00 314,460.00 104.82 314,460.00 104.82 314,460.00 0.00 - 100.00%
Construction of new Shoes, Temporary FirstLearning
Aid Kit,Centre(TLC),
Clothing, with
specification
Guard Rail andedge
for instruction
protection,of Engineer.Net, Safety rope, Fall
Locally
LAB Available
TEST(WATER materials
TEST) (CGISafetySheet and Bamboo etc.), rate
9 Protection
shall include etc.) as required
all Materials by the Contract Clause GCC 24 and job 1.00 7,500.00 7,500.00 - - 0.00 - 0.00 - 0.00%
Testing and Providing LabwithTestfixing
Report charge.
for Quality of Water in
Specification division 1 "GENERAL REQUIREMENT
Water
TEMPORARY Stream (Up and Down streem) located near by
10 CLAUSE 8(C)".TOILETThe number of Safety Materials Personal nos. 2 150,000.00 300,000.00 2.00 300,000.00 2.00 300,000.00 0.00 - 100.00%
Construction of
Construction sitetemporary
before Starting and CGI after completion of
Protecting Equipments (PPE) toilet
shall be withminimumSheet but notfixed
limited to
construction
Bamboo work.
support Thisand
frame Testallhas to be done
necesary itemstoincluding
mark the affect
ROAD REPAIR
to 35 sets. Payment AND shallMAINTENANCE
be made in Prorata Basis for Septic
entire
11 of construction
pit, Pipeline, workPan
Toilet in water
etc. forstream. project completion time Km 4.00 50,000.00 200,000.00 4.00 200,000.00 4.00 200,000.00 0.00 - 100.00%
Providing
duration of and Maintaining
project. the entire
roads as necessary to avoid
all complete
blockage as per Instruction
by Landslides of Engineer.
and Rockfall Rate shall
for regular include
transport of
all Material materials
construction cost withand fixing,
site construction
inspection during charges and
overall
BILL NO. 2 CIVIL WORKS- BUILDING
demolition &period.
construction cleaning Rate ofshall
the sameinclude after
all completion
Material cost ofwith
the
SITE CLEARANCE
construction activities & MOBILIZATION:
all complete.
1.1 demolition charges, cleaning, fixing & construction charges of sq.m 701.87 100.00 70,187.00 642.41 64,241.35 696.52 69,652.00 -54.11 (5,410.65) 91.53%
Clearing and grubbing the site for construction by removing
the same after
150mm thick top IN completion
soilEXCAVATION
including of bushes,
the construction activities all
EARTHWORK
complete. : small trees, leveling of
1.2 undulated ground, shortinginand top cu.m 315.17 400.00 126,068.00 317.72 127,088.50 289.67 115,866.89 28.05 11,221.61 100.81%
Excavation in foundations all stacking/storing
type of soils forselected foundation,
soil for reuse
trenches, footing, in pitslandscaping
etc. to works, disposing unsuitable
EARTH BACK FILLING : the required depth including
1.3 materials
dewatering from site, etc., or all complete means as peretc.drawings, per cu.m 204.21 300.00 61,263.00 236.58 70,972.99 191.14 57,342.00 45.44 13,630.99 115.85%
Back fillingbyin manualfoundation mechanical
and sides of foundationas with
specifications
specifications and
with instructions
allfrom of the Engineer.
contractor’s ownat machinery and
approved soil
BOULDER SOLING : obtained the excavation site and stacked
1.4 equipment's,
at site or broughtprovidingfrom crossinginoflayer
outside track,not shoring,
exceeding strutting,
cm cu.m 98.81 6,000.00 592,860.00 98.87 593,222.73 78.96 473,730.45 19.92 119,492.28 100.06%
Providing and laying uncoursed hand packed Dry Rubble15 Stone
timbering and buttressing
thick (compacted thickness) with appropriate
including materials andsoil, all
soling
SAND in foundation,
FILLING : under floor plinthtransportation
with out any of special
1.5 such measures
spreading of necessary
in required to retain
line and level, in position
sprinkling the
water,sides of
ramming, the cu.m 4.98 6,000.00 29,880.00 4.65 27,900.00 0.00 - 4.65 27,900.00 93.37%
dressing
Providing and stone
filling including filling
sand inrefilling
soak pit. interstices with suitable
foundation
compacting pitwith
and including
mechanical rammers, theallexcavated
completematerial
testing,
as per
etc., all
quarry
drawings, waste or stone
specifications and chips or quarry
instruction ofand sand, watering,
the Engineer.
with watering,
complete perramming,
as using drawing, leveling
specificationthe site disposing off
and compaction
instructions of the
the
compacting appropriate mechanical means
surplus/unusable earth to outside the construction premises, etc.
Engineer.
with all contractors materials, handling, placing etc. all
all complete as per drawings, specifications and instructions of
complete as per drawings, specifications and instruction of the
the Engineer.
Prepared by contractor Checked
Engineer. The complete item including all leadby Consultant, DSC
& lift. Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
CONCRETE WORKS
2.1.1 cu.m 13.20 14,000.00 184,800.00 14.09 197,314.25 13.78 192,920.00 0.31 4,394.25 106.77%
P.C.C (1:3:6)
Providing
P.C.C and WORKS
(1:2:4) laying machine mixed Plain Cement Concrete of
2.1.2 nominal mix cu.m 27.19 16,000.00 435,040.00 24.18 386,819.16 19.73 315,680.00 4.45 71,139.16 88.92%
Providing and1:3:6laying (1 machine
cement : mixed 3 sandPlain : 6 coarse
Cement aggregate
Concrete ) for
of
leveling course
nominal mix 1:2:4 in foundations
cement : and
(1 WORKS 2: sandunder floor ofaggregate
: 4 coarse building,)etc.
for
P.C.C. FOR R.C.C.
2.2 in all level
leveling withinbroken
course foundationsstone aggregate under of
andmachine floorsizeofnot more than
building, etc. cu.m 240.98 20,000.00 4,819,600.00 240.41 4,808,165.34 224.25 4,485,024.02 16.16 323,141.31 99.76%
Providing and laying in position mixed and machine
25 mm
in all levelof with
approved
brokenqualitystone including offormwork
aggregate size not more wherever
than3
vibrated
SILICA cementCEMENT concrete of mix
ADMIXTURE 1:1.5:3 (1 cement:1.5 sand:
2.3 necessary,
25 mmaggregate) dewatering,
of approved batching,
quality mixing,
including transporting,
formwork placing,
wherever kg 2,409.80 300.00 722,940.00 2,404.08 721,224.80 2242.51 672,753.60 161.57 48,471.20 99.76%
coarse
Providing andcuring, mixing M20 grade
Silica Cementfor reinforced cement concrete
compacting,
necessary, dewatering, including
batching, leadAdmixture
all mixing, of all
andtransporting,
lift, etc. in structural
complete
placing,
work
concrete usingat theapproved
rate ofcement
2.50% with byand 20 mm
weight of graded
the cement machine
for
STEEL
compacting, REINFORCEMENT
as per drawings, curing, specifications
including all lead the lift,
and instructions
etc. all of the
complete
2.4 crushed stone
promoting aggregate of approved strength,quality inachievingvarious Mt. 38.57 130,000.00 5,014,100.00 40.74 5,295,781.23 39.53 5,139,125.75 1.21 156,655.48 105.62%
Providing
Engineer.
as per andworkability,
drawings, fixing in position
specifications
improving
Feand 500thesteel reinforcement
instructions of
of the
locations and heights
waterproofing properties, includingbleeding transportation
prevention, of concrete
etc. to
Silica
various
FORM
Engineer. diameter confirming to relevant IS code in R.C.C.
WORKS
2.5 site of placing,
Cement Admixture compaction,
shall be finished
the to required
product of line and
Silica level,
Japan or sq.m 1,734.43 800.00 1,387,544.00 1,719.80 1,375,838.08 1627.28 1,301,822.44 92.52 74,015.64 99.16%
works including
Supplying and straightening,
laying centering, cutting,
shuttering bending,
of binding
various with
pattern
protection
superior and
and shallwirecuring,
meet etc. all complete as per drawings,
20 SWG annealed
formworks withand 19/12 for the
tying requirements
thick the reinforcement as mentioned
bars & in
at each
BRICK
specifications
specification MASONRY
of materialsthemminstructions
WORKSBRICK water
and Workmanship,
proof
of theplyEngineer,
wood
MASONRY
Division
steel
– but
4:
junctions
adjustable (binding
props forofwire
all shall
kinds ofnotRCC be works
measured separately)
forreinforcement,
foundations,
3.1 WORKS
excluding
Concrete Works, (
the 1 : 4
cost c/s )
Article ONE
centering,SIDE FAIRFACE
shuttering, and
2.4cut pieces, provision for adequate cu.m 84.41 20,000.00 1,688,200.00 - - 0.00 - 0.00 -
including
columns, all waste
shear walls, and
beams, slab, staircase, lintel, sill, pergola,
Providing
all complete andaslaying first class
per drawings, selected
specifications factory pressed
and instructions wire
of
numbers of
including nails,spacers,
propping chairs, providing
scaffolding, and supporting
staging, placing cement and
cut Fair Face
the Engineer. brick (machine made brick) one or more brick
7.2.3 mortar
bracing
CLEAR (1:1)
in coverlines
proper
SILICON blocks and tolevel,
WATER-REPELENT keep sealing
the barsCOATING
in joints
the intended withposition
heavy sq.m
thick wall in cement mortar 1:4 (1 cement : 4coarse sand) in
at
dutyall brown
levelsWORK all
self complete astape,
per drawings, specifications and
8.1.1 POINTING
,superstructure andadhesive
IN
otherBRICKspecified aligning
MASONARY places to in line and levels
all heights and sq.m
instructions Ties,
including of the PVC Engineer. Spacer,(Authorized lapopenings/
length andcutouts/
for the
level
BOQ
bar
including
Totalexceeding
length
the cost
of items 3.1.,
10
of7.2.3
meter
single &Providing
in
or multi stage
8.1.1:
length shall be
self standing
measured for
pockets, applying
scaffolding, soaking De-shuttering
bricks, curing, chemical,
raking De-shuttering
joints, provision as
for
Replaced
the payment, items 3.1, to 7.2.3 and 8.1.1 with following items for
approved
recesses, by except
the Engineer
openings,
column).
toothing etc.,
etc., complete
all complete at all as levels
per as per
drawing,
3-6C(S)-E, 2-4C(S) and Ts(F)
drawing, specifications
specifications and instructionsand instructions
of the Engineer. of the Engineer.
Brick Masonry Works (1:4 c/s) cu.m 18,000.00 - - - 0.00 - 0.00 -
Cement Plaster Works on Outer Wall (1:6) sq.m 600.00 - - - 0.00 - 0.00 -
Exterior Weather Coat Paint sq.m 350.00 - - - 0.00 - 0.00 -

BRICK MASONRY WORKS ( 1 : 4 c/s )


3.2 cu.m 76.21 18,000.00 1,371,780.00 145.33 2,615,986.35 137.83 2,480,932.16 7.50 135,054.20 190.70%
Providing and laying first class chimney fired brick one or
3.3 more
HALFbrick thick WORKS
BRICK wall in cement
( 1 : 4mortar
c/s ) 1:4 (1 cement : 4 coarse sq.m 64.50 1,500.00 96,750.00 28.40 42,599.10 21.95 32,921.25 6.45 9,677.85 44.03%
3.4 sand)
HONEY in COMB
foundation
BRICK up WORKS
to plinth,(1:3
superstructure
c/s) and other cu.m 0.48 9,000.00 4,320.00 0.48 4,279.50 0.24 2,160.00 0.24 2,119.50 99.06%
specified places in all heights and level including the cost of
4 DOORS & WINDOWS WORKS
single or multi stage scaffolding, soaking bricks, curing, raking
4.1 METAL
joints, FRAME for recesses, openings, toothing etc., all
provision
4.1.1 complete
Door Frame as per drawing, specifications and instructions of the r.m 151.04 1,100.00 166,144.00 151.04 166,144.00 152.00 167,200.00 -0.96 (1,056.00) 100.00%
Engineer.
4.1.2 Window Frame r.m 383.66 1,100.00 422,026.00 363.06 399,360.50 363.06 399,366.00 0.00 (5.50) 94.63%
4.2 METAL SHUTTER
4.2.1 WINDOW SHUTTER sq.m 78.99 7,500.00 592,425.00 64.28 482,071.31 78.99 592,425.00 -14.71 (110,353.69) 81.37%
4.3 WOODEN SHUTTER
4.3.1 FLUSH DOOR SHUTTER (32MM) sq.m 58.33 8,000.00 466,640.00 52.64 421,083.60 58.33 466,640.00 -5.69 (45,556.40) 90.24%
4.4 UPVC DOOR
4.4.1 Shutter/Frame sq.m 7.14 9,000.00 64,260.00 6.97 62,730.00 7.14 64,260.00 -0.17 (1,530.00) 97.62%
4.5 WINDOW GRILL sq.m 50.07 2,500.00 125,175.00 71.07 177,665.44 46.95 117,375.00 24.12 60,290.44 141.93%
4.6 COLLAPSIBLE GATE sq.m 14.98 10,000.00 149,800.00 14.98 149,767.50 0.00 - 14.98 149,767.50 99.98%
5 FLOORING WORKS
5.1 HARDENED CEMENT CONCRETE FLOOR sq.m 782.82 900.00 704,538.00 781.44 703,293.98 731.10 657,990.00 50.34 45,303.98 99.82%
5.2 NEAT CEMENT SKIRTING r.m 420.91 100.00 42,091.00 433.94 43,394.10 421.98 42,198.00 11.96 1,196.10 103.10%
5.3 TERRAZZO CAST-IN SITU DADO sq.m 36.63 1,500.00 54,945.00 36.48 54,720.00 32.88 49,320.00 3.60 5,400.00 99.59%
6 ROOFING/TERRACING WORK
6.1 METAL WORKS (TRUSS) kg 6660.99 220.00 1,465,417.80 7,687.63 1,691,279.68 6660.99 1,465,417.80 1026.64 225,861.88 115.41%
6.2 CGI SHEET ROOFING sq.m 439.95 2,000.00 879,900.00 444.54 889,080.00 439.95 879,900.00 4.59 9,180.00 101.04%
6.3 CGI SHEET ROOFING RIDGE r.m 42.6 1,200.00 51,120.00 42.75 51,300.00 42.60 51,120.00 0.15 180.00 100.35%
6.4 GI FACIA (EAVES) kg 387.62 250.00 96,905.00 295.89 73,972.50 381.29 95,322.50 -85.40 (21,350.00) 76.34%
6.5 CEMENT BOARD FALSE CEILING sq.m 344.15 1,500.00 516,225.00 373.56 560,337.00 344.14 516,210.00 29.42 44,127.00 108.55%
7 PLASTERING/WALL FINISHING WORK
7.1 CEMENT PLASTER WORK

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
7.1.1 ON INNER WALL sq.m 923.13 600.00 553,878.00 947.85 568,709.19 923.13 553,878.00 24.72 14,831.19 102.68%
7.1.2 ON CEILING (1:4) sq.m 360.86 500.00 180,430.00 495.87 247,936.89 360.86 180,429.96 135.01 67,506.93 137.41%
7.1.3 ON OUTER WALL (1:6)
7.1.3.1 EXTERNAL PLASTER sq.m 430.90 600.00 258,540.00 775.79 465,474.24 697.26 418,358.85 78.53 47,115.39 180.04%
7.1.4 EXTERNAL PLASTER WITH CEMENT PUNNING sq.m 35.21 700.00 24,647.00 35.66 24,962.00 35.66 24,962.00 0.00 - 101.28%
7 PAINTING WORKS
7.2.1 DISTEMPER PAINT sq.m 1599.82 200.00 319,964.00 1,817.29 363,457.50 1659.67 331,934.00 157.62 31,523.50 113.59%
7.2.2 EXTERIOR WEATHER COAT PAINT sq.m 461.26 350.00 161,441.00 775.79 271,527.81 411.73 144,105.50 364.06 127,422.31 168.19%
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG sq.m 369.72 550.00 203,346.00 - - 0.00 - 0.00 - 0.00%
7.2.4 ENAMEL PAINT sq.m 392.72 400.00 157,088.00 409.43 163,771.80 347.79 139,116.00 61.64 24,655.80 104.25%
8 MISCELLANEOUS
8.2 CEMENT BOARD WALL sq.m 32.61 6,500.00 211,965.00 34.16 222,040.00 32.61 211,965.00 1.55 10,075.00 104.75%
8.3 RAILING kg 1496.50 220.00 329,230.00 1,527.10 335,962.96 1287.60 283,272.00 239.50 52,690.96 102.05%
8.4 PUMP SHED nos. 1.00 80,000.00 80,000.00 1.00 80,000.00 0.00 - 1.00 80,000.00 100.00%

3 ELECTRICAL WORKS
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure no. 2.00 12,000.00 24,000.00 2.00 24,000.00 2.00 24,000.00 0.00 - 100.00%
1.2 Stand Alone 6 A DP MCB with Enclosure no. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2.1 2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper rm 100.00 800.00 80,000.00 97.00 77,600.00 100.00 80,000.00 -3.00 (2,400.00) 97.00%
2.2 conductor wires mutistranded copper conductor wires + 1
2 Nos 2.5 Sq.mm rm 50.00 250.00 12,500.00 51.00 12,750.00 0.00 - 51.00 12,750.00 102.00%
B Nos. 1.5sq
School mm multistranded Cu wire
Blocks
1 DISTRIBUTION BOARDS nos.
1.1 Ground Floor nos. 2.00 30,000.00 60,000.00 2.00 60,000.00 2.00 60,000.00 0.00 - 100.00%
1.2 First Floor nos. 2.00 22,000.00 44,000.00 2.00 44,000.00 2.00 44,000.00 0.00 - 100.00%
1.3 Second Floor nos. 1.00 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 0.00 - 100.00%
1.4 Stand Alone 6 A DP MCB with Enclosure nos. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm
2.1 Multistranded Cu wire rm 15.00 600.00 9,000.00 15.00 9,000.00 15.00 9,000.00 0.00 - 100.00%
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm
2.2 Multistranded Cu wire rm 15.00 500.00 7,500.00 10.00 5,000.00 15.00 7,500.00 -5.00 (2,500.00) 66.67%
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.2 rm 30.00 250.00 7,500.00 16.00 4,000.00 30.00 7,500.00 -14.00 (3,500.00) 53.33%
Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point pts. 74.00 700.00 51,800.00 75.00 52,500.00 74.00 51,800.00 1.00 700.00 101.35%
3.2 Two Way Light Point pts. 3.00 900.00 2,700.00 3.00 2,700.00 3.00 2,700.00 0.00 - 100.00%
3.3 Ceiling Fan Point pts. 8.00 900.00 7,200.00 8.00 7,200.00 6.00 5,400.00 2.00 1,800.00 100.00%
4 16 A Universal Pin Light Power Socket Wiring pts. 1.00 900.00 900.00 1.00 900.00 1.00 900.00 0.00 - 100.00%
5 6A Universal Pin Light Power Supplying, wiring, testing and
Socket Wiring pts. 43.00 700.00 30,100.00 43.00 30,100.00 43.00 30,100.00 0.00 - 100.00%
commissioning and putting into operation for 6 A light power
6 Switch
point Socket
using 2 x Outlets
4 sq mm + 1 x 2.5 Sq mm multi stranded
6.1 copper
16 conductor,
A Universal Pin 1100
Lightvolts grade,
Power PVC insulated
Socket Wiring wires nos. 1.00 1,500.00 1,500.00 1.00 1,500.00 1.00 1,500.00 0.00 -
drawn through pre
6A Universal Powerinstalled
Switch25Socket
mm dia 2 mmwiring,
Supplying, thick HDP pipe,
testing
6.2 nos. 43.00 900.00 38,700.00 44.00 39,600.00 43.00 38,700.00 1.00 900.00 102.33%
cablecommissioning
and sleeve/support but andincluding specified
putting into dia pipes
operation for 6 A light
7 Sweep
power Ceiling/Exhaust
concealed in wall
point usingand 4 Fans/
2 xfloor mmWall+ 1 xFan
sqincluding all
2.5fixing
Sq mm andmulti
connecting
7.1 materials.
stranded The rateCeiling
1200 mm copper
Sweep for point
conductor,Fanwiring
1100 shall
volts include the circuit
grade, PVC no. 2.00 4,500.00 9,000.00 2.00 9,000.00 4.00 18,000.00 -2.00 (9,000.00) 100.00%
wiring from
insulated deginated
wires drawnDistribution
through pre Board (DB)25
installed upmmto the
diafirst
2
7.2 400 mm Sweep Wall Fan no. 6.00 3,500.00 21,000.00 6.00 21,000.00 12.00 42,000.00 -6.00 (21,000.00) 100.00%
power
mm pointHDP
thick thenpipe,
the looping between sockets.
cable sleeve/support butThe cost shall
including
7.3 225mm
be dia
diaM/D
excluding
specified Exhaust
modular
pipes Fan inswitch
formation
concealed wall andsockets
floorand their all
including nos. 2.00 6,000.00 12,000.00 2.00 12,000.00 2.00 12,000.00 0.00 - 100.00%
8 flushing
fixing andGIconnecting
box but including
Light Fixtures/Luminaires &GIAccessories
materials. fish
Thewire,
ratecutting
for pointandwiring
filling
chasesinclude
shall for recessed pipes wiring
the circuit as deemedfrom as deginated
per drawing and lay out
Distribution
plan all(DB)
Board complete.
up to the first power point then the looping
between sockets. The cost shall be excluding modular
formation switch sockets and their flushing GI box but
Prepared by contractor
including GI fish wire, cutting andChecked by Consultant,
filling chases for DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
recessed pipes as deemed as per drawing and lay out plan
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
8.1 24 W LED Recessed Mounted Square type nos. 4.00 4,500.00 18,000.00 4.00 18,000.00 4.00 18,000.00 0.00 - 100.00%
8.2 18 W LED Surface Mounted Square type CRCA Powder nos. 22.00 2,700.00 59,400.00 22.00 59,400.00 22.00 59,400.00 0.00 - 100.00%
8.3 Coated
18 withRecessed
W LED PMMA Diffuser
Mountedhaving
Square6000
typeKCRCA
ColorPowder nos. 12.00 2,700.00 32,400.00 12.00 32,400.00 12.00 32,400.00 0.00 - 100.00%
Temperature,
Coated IP20 rated.
withSurface
PMMA Diffuser Cylindrical
having 6000type
K Color
8.4 12 W LED Mounted CRCA Powder nos. 15.00 2,400.00 36,000.00 15.00 36,000.00 13.00 31,200.00 2.00 4,800.00 100.00%
Temperature,
Coated IP20 rated.
withRecessed
PMMA Diffuser
8.5 12 W LED Mountedhaving 6000
Crrcular K CRCA
type Color Powder nos. 10.00 2,400.00 24,000.00 10.00 24,000.00 10.00 24,000.00 0.00 - 100.00%
Temperature,
Coated IP20 rated.
withLight
PMMA Diffuser
8.6 LED Wall made of highhaving 6000 K aluminium
grade die-cast Color nos. 3.00 1,800.00 5,400.00 3.00 5,400.00 3.00 5,400.00 0.00 - 100.00%
Temperature,
Powder IP20 rated.
8.7 9W LEDCoated
Surface with PMMACylindrical
Mounted Diffuser having 6000 KPowder
type CRCA Color nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
Temperature,
Coated with IP65 rated
PMMA with having
Diffuser 7 W LED Lamp.
8.8 6W LED Recessed Mounted Circular6000
type K Color nos. 3.00 1,800.00 5,400.00 3.00 5,400.00 3.00 5,400.00 0.00 - 100.00%
Temperature, IP20 rated.
8.9 7W LED T5 Slim Mirror Light nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
9 Pull Box nos. 6.00 700.00 4,200.00 6.00 4,200.00 6.00 4,200.00 0.00 - 100.00%
10 External Post Top Light Pole nos. 6.00 7,500.00 45,000.00 6.00 45,000.00 6.00 45,000.00 0.00 - 100.00%
11 Post Top External Light Fixtures nos. 6.00 9,800.00 58,800.00 6.00 58,800.00 6.00 58,800.00 0.00 - 100.00%
12 Earthing & Lighting Protection
12.1 Chemical Earthing nos. 6.00 45,000.00 270,000.00 6.00 270,000.00 6.00 270,000.00 0.00 - 100.00%
12.2 Earthing Bar nos. 6.00 2,200.00 13,200.00 6.00 13,200.00 6.00 13,200.00 0.00 - 100.00%
13 Earthing Strip/Wires
13.1 25 x 3 mm GI strip mtr. 130.00 300.00 39,000.00 132.00 39,600.00 130.00 39,000.00 2.00 600.00 101.54%
13.2 12 SWG Cu wire mtr. 30.00 200.00 6,000.00 31.00 6,200.00 30.00 6,000.00 1.00 200.00 103.33%
14 Earth Test link nos. 2.00 1,500.00 3,000.00 2.00 3,000.00 2.00 3,000.00 0.00 - 100.00%
C Solar PV System
1 Solar PV Panel nos. 4.00 26,000.00 104,000.00 4.00 104,000.00 4.00 104,000.00 0.00 - 100.00%
2 Tubular Deep Cycle Battery nos. 2.00 30,000.00 60,000.00 2.00 60,000.00 2.00 60,000.00 0.00 - 100.00%
3 Hybrid Inverter 1.00 100,000.00 100,000.00 1.00 100,000.00 1.00 100,000.00 0.00 - 100.00%
D FIRE EXTINGUISHER
a Supplying Fire extinguisher ABC stored Pressure 5.0kg size nos. 2.00 8,000.00 16,000.00 2.00 16,000.00 0.00 - 2.00 16,000.00 100.00%
b ABC stored pressure
Dry Powder type Fire conforming
Fire Extinguisher extinguisher.to BS 5423:1987 or nos. 1.00 8,000.00 8,000.00 1.00 8,000.00 0.00 - 1.00 8,000.00 100.00%
as given in BOQ. The Dry Powder agents shall be mono-
ammonium phosphate and ammonium sulphate base as per
BILL No. below.all
specidfied 4. SANITARY WORKS
complete
A PIPING WORKS
1 WATER SUPPLY INSTALLATION
a) CPVC pipes
- 40 mm Rm 60 1,600.00 96,000.00 55.00 88,000.00 10.00 16,000.00 45.00 72,000.00 91.67%
- 25 mm Rm 70 1,000.00 70,000.00 18.00 18,000.00 15.00 15,000.00 3.00 3,000.00 25.71%
- 20 mm Rm 11 700.00 7,700.00 10.00 7,000.00 5.00 3,500.00 5.00 3,500.00 90.91%
- 15 mm Rm 4 500.00 2,000.00 2.50 1,250.00 15.00 7,500.00 -12.50 (6,250.00) 62.50%
c) CPVC Ball Valve
- 40 mm No. 4 2,000.00 8,000.00 2.00 4,000.00 2.00 4,000.00 0.00 - 50.00%
- 25 mm No. 4 900.00 3,600.00 3.00 2,700.00 2.00 1,800.00 1.00 900.00 75.00%
20mm No. 2 400.00 800.00 2.00 800.00 2.00 800.00 0.00 - 100.00%
40 mm dia Gun Metal Check valve No. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 0.00 - 100.00%
d) Electric Centrifugal Water Pump Set 1 12,500.00 12,500.00 1.00 12,500.00 - 1.00 12,500.00 100.00%
e) 1000 litres capacity Plastic cyllindrical vertical water storage No. 1 34,000.00 34,000.00 1.00 34,000.00 1.00 34,000.00 0.00 - 100.00%
tank

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
2 SEWER, RAIN AND WASTE WATER INSTALLATION
PVC SWR
110 mm Rm 33 1,400.00 46,200.00 32.00 44,800.00 15.00 21,000.00 17.00 23,800.00 96.97%

75 mm Rm 33 1,200.00 39,600.00 25.00 30,000.00 12.00 14,400.00 13.00 15,600.00 75.76%


50 mm Rm 4 350.00 1,400.00 2.00 700.00 - 2.00 700.00 50.00%

B SCHOOL BLOCKS
1 SANITARY INSTALLATION
a Stainless Steel Kitchen Sink Set 1 35,000.00
b CP self closing bib cock No 1 4,000.00 4,000.00 1.00 4,000.00 - 1.00 4,000.00 100.00%
c PVC Multi-floor trap with cover No. 1 600.00 600.00 1.00 600.00 - 1.00 600.00 100.00%
CP Waste Coupling and PVC bottle trap for water trough
d No. 1 1,500.00 1,500.00 1.00 1,500.00 - 1.00 1,500.00 100.00%

2 SANITARY INSTALLATION
a Water Closet set Set 1 34,000.00 34,000.00 1.00 34,000.00 - 1.00 34,000.00 100.00%
b 580x480mm Orissa Pan Set 2 3,100.00 6,200.00 2.00 6,200.00 - 2.00 6,200.00 100.00%
c Hand wash basin Set 1 8,000.00 8,000.00 1.00 8,000.00 - 1.00 8,000.00 100.00%
d Urinal Set 2 110,000.00 220,000.00 2.00 220,000.00 - 2.00 220,000.00 100.00%
e CP self closing bib cock No 6 4,000.00 24,000.00 6.00 24,000.00 - 6.00 24,000.00 100.00%
f CP spreader for Urinal Set 2 2,500.00 5,000.00 2.00 5,000.00 - 2.00 5,000.00 100.00%
g CP Toilet Paper Holder heavy No. 1 2,600.00 2,600.00 1.00 2,600.00 1.00 2,600.00 0.00 - 100.00%
h 15mm CP Commode Spray with plastic head No. 1 2,000.00 2,000.00 1.00 2,000.00 - 1.00 2,000.00 100.00%
i PVC Multi-floor trap with cover No. 5 600.00 3,000.00 5.00 3,000.00 - 5.00 3,000.00 100.00%
j CP Waste Coupling and PVC bottle trap for water trough No. 2 1,500.00 3,000.00 2.00 3,000.00 - 2.00 3,000.00 100.00%
k 40 mm SS Grab bar of 600mm Length - Side Set 1 4,500.00 4,500.00 1.00 4,500.00 - 1.00 4,500.00 100.00%
l 40 mm SS Grab bar of 600mm Length - Rear Set 1 4,500.00 4,500.00 1.00 4,500.00 - 1.00 4,500.00 100.00%
m CP Foldable Hinge Set 2 5,500.00 11,000.00 2.00 11,000.00 1.00 5,500.00 1.00 5,500.00 100.00%

B CIVIL WORKS : SITE DEVELOPMENT


1 EARTHWORKS
1 SITE CLEARANCE AND MOBILIZATION Sq.m 256.72 100.00 25,672.00 152.63 15,263.00 152.63 15,263.00 0.00 - 59.45%
2 EARTHWORK IN EXCAVATION Cu.m 171.79 400.00 68,716.00 21.84 8,736.00 19.82 7,928.00 2.02 808.00 12.71%
3 EARTHBACK FILLING Cu.m 37.75 300.00 11,325.00 19.19 5,757.00 19.19 5,757.00 50.83%
4 BOULDER SOLING Cu.m 26.16 6,000.00 156,960.00 23.72 142,320.00 8.81 52,860.00 14.91 89,460.00 90.67%
5 P.C.C (1:3:6) Cu.m 1.31 14,000.00 18,340.00 1.14 15,960.00 0.54 7,560.00 0.60 8,400.00 87.02%
6 P.C.C (1:2:4) Cu.m 12.98 16,000.00 207,680.00 9.39 150,240.00 9.40 150,330.18 -0.01 (90.18) 72.34%
7 P.C.C FOR R.C.C WORK Cu.m 0.99 20,000.00 19,800.00 0.99 19,800.00 0.99 19,800.00 0.00 - 100.00%
8 SILICA CEMENT ADMIXTURE Kg 9.90 300.00 2,970.00 9.90 2,970.00 9.90 2,970.00 0.00 - 100.00%
9 STEEL REINFORCEMENT Mt. 0.10 130,000.00 13,000.00 0.11 13,897.00 0.10 12,952.47 0.01 944.53 106.90%
10 FORM WORKS Sq.m 9.12 800.00 7,296.00 11.33 9,064.00 9.12 7,296.00 2.21 1,768.00 124.23%
11 STONE MASONARY WORKS (1:4 c/s) Cu.m 4.81 10,000.00 48,100.00 4.35 43,500.00 - 4.35 43,500.00 90.44%
13 BRICKS MASONRY WORKS (1:4 c/s) Cu.m 0.22 18,000.00 3,960.00 7.91 142,469.82 0.20 3,600.00 7.71 138,869.82 3597.72%
14 NEAT CEMENT SKIRTING r.m 4.72 100.00 472.00 4.72 472.00 4.72 472.00 0.00 - 100.00%
15 METAL WORKS FOR FENCE k.g 790.75 220.00 173,965.00 744.98 163,895.60 353.18 77,699.60 391.80 86,196.00 94.21%
16 METAL WORKS FOR GATE k.g 130.78 220.00 28,771.60 123.31 27,128.09 159.63 35,118.60 -36.32 (7,990.51) 94.29%
17 PLASTER ON OUTER WALL Sq.m 7.92 600.00 4,752.00 49.26 29,556.00 49.26 29,556.00 0.00 - 621.97%
18 EXTERIOR WEATHER COAT PAINT Sq.m 8.87 350.00 3,104.50 8.28 2,898.00 8.28 2,898.00 0.00 - 93.35%
19 CHAIN LINK FENCE Sq.m 82.94 1,000.00 82,940.00 102.00 102,000.00 54.00 54,000.00 48.00 48,000.00 122.98%

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Pay Item Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Description Unit % completion Remarks
No. Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
20 FLAG POLE nos. 2.00 25,000.00 50,000.00 2.00 50,000.00 2.00 50,000.00 0.00 - 100.00%
-
CIVIL WORKS-RESERVOIR TANK -
1 EARTH WORK -
1.1 SITE CLEARANCE AND MOBILIZATION sq.m 22.31 100.00 2,231.00 22.31 2,231.00 22.31 2,231.00 0.00 - 100.00%
1.2 EARTHWORK IN EXCAVATION cu.m 24.58 400.00 9,832.00 24.57 9,828.72 24.57 9,828.72 0.00 - 99.97%
1.3 EARTH BACK FILLING cu.m 4.02 300.00 1,206.00 4.01 1,202.85 4.01 1,202.85 0.00 - 99.74%
1.4 BOULDER SOLING cu.m 2.08 6,000.00 12,480.00 2.08 12,462.00 2.08 12,462.00 0.00 - 99.86%
2 CONCRETE WORKS
2.1 P.C.C (1:3:6) cu.m 0.78 14,000.00 10,920.00 0.78 10,904.25 0.78 10,904.25 0.00 - 99.86%
2.2 P.C.C FOR R.C.C WORKS cu.m 7.42 20,000.00 148,400.00 7.41 148,295.00 7.41 148,295.00 0.00 - 99.93%
2.3 SILICA CEMENT ADMIXTURE kg 74.20 300.00 22,260.00 74.15 22,244.25 74.15 22,244.25 0.00 - 99.93%
2.4 STEEL REINFORCEMENT Mt 1.46 130,000.00 189,800.00 1.58 204,902.61 1.57 203,977.54 0.01 925.07 107.96%
2.5 FORMWORKS sq.m 54.93 800.00 43,944.00 56.46 45,170.80 56.46 45,170.80 0.00 - 102.79%
3 PLASTERING/WALL FINISHING WORKS
INTERNAL PLASTER ON WALL (1:4) WITH CEMENT
3.1.1 sq.m 33.66 700.00 23,562.00 35.46 24,824.45 27.57 19,301.45 7.89 5,523.00 105.36%
PUNNING
4 WATERPROOFING WORKS sq.m 33.66 550.00 18,513.00 35.46 19,504.93 27.57 15,165.43 7.89 4,339.50 105.36%
- - - 0.00 - 0.00 -
FURNITURE WORKS lot 1 4,000,000.00 4,000,000.00 1.00 4,000,000.00 1.00 4,000,000.00 0.00 - 100.00%
Total 35,254,804.90 35,280,032.74 32,354,943.32 2,925,089.43

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Project Name : Emergency School Reconstruction Project (ESRP)
School Name : Shree Sarbodaya Lower Secondary School
Buildings: 3-6CS, 2-4C(S)-H, T(S)-F
Location : Choprak,Gorkha
Abstract of Cost
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank

BILL NO.1 PRELIMINARIES/TEMPORARY WORKS


1 MOBILIZATION AND DEMOBILIZATION L.S. 1.00 500,000.00 1.00 500,000.00
2 SITE OFFICE ESTABLISHMENT Per Month 15.00 25,000.00 15.00 375,000.00
3 PROJECT INFORMATION BOARD nos. 1.00 10,000.00 1.00 10,000.00
4 SAFETY SIGN BOARD nos. 1.00 10,000.00 1 10,000.00
5 BARRICADING WORKS R.m 90.00 2,000.00 90 180,000.00
6 DISMANTLING OF COMPLETELY DAMAGED BUILDING sq.m 186.60 5,000.00 179.00 895,000.00
7 SAFETY MATERIALS & SITE SAFETY L.S. 1.00 100,000.00 1.00 100,000.00
8 CONSTRUCTION OF NEW TLC sq.m 104.82 3,000.00 104.82 314,460.00
9 LAB TEST(WATER TEST) job 1.00 7,500.00 0.00 -
10 TEMPORARY TOILET nos. 2 150,000.00 2.00 300,000.00
11 ROAD REPAIR AND MAINTENANCE Km 4.00 50,000.00 4.00 200,000.00

BILL NO. 2 CIVIL WORKS- BUILDING


1.1 SITE CLEARANCE & MOBILIZATION: sq.m 701.87 100.00 306.20 252.30 83.91 642.41 64,241.35
1.2 EARTHWORK IN EXCAVATION : cu.m 315.17 400.00 146.33 100.20 71.19 317.72 127,088.50
1.3 EARTH BACK FILLING : cu.m 204.21 300.00 109.75 63.62 63.21 236.58 70,972.99
1.4 BOULDER SOLING : cu.m 98.81 6,000.00 45.99 38.41 14.48 98.87 593,222.73
1.5 SAND FILLING : cu.m 4.98 6,000.00 2.49 2.16 4.65 27,900.00
CONCRETE WORKS
2.1.1 P.C.C (1:3:6) cu.m 13.20 14,000.00 7.32 4.28 2.49 14.09 197,314.25
2.1.2 P.C.C (1:2:4) WORKS cu.m 27.19 16,000.00 13.08 10.54 0.56 24.18 386,819.16
2.2 P.C.C. FOR R.C.C. WORKS : cu.m 240.98 20,000.00 137.04 86.91 16.46 240.41 4,808,165.34
2.3 SILICA CEMENT ADMIXTURE kg 2,409.80 300.00 1,370.37 869.09 164.63 2,404.08 721,224.80
2.4 STEEL REINFORCEMENT Mt. 38.57 130,000.00 24.82 13.79 2.13 40.74 5,295,781.23
2.5 FORM WORKS sq.m 1,734.43 800.00 947.85 643.82 128.13 1,719.80 1,375,838.08
BRICK MASONRY WORKSBRICK MASONRY WORKS ( 1 : 4 c/s ) ONE
3.1 SIDE FAIRFACE cu.m 84.41 20,000.00
7.2.3 CLEAR SILICON WATER-REPELENT COATING sq.m
8.1.1 POINTING WORK IN BRICK MASONARY sq.m
BOQ Total of items 3.1., 7.2.3 & 8.1.1:
Replaced items 3.1, 7.2.3 and 8.1.1 with following items for 3-6C(S)-E, 2-4C(S)
and Ts(F)
Brick Masonry Works (1:4 c/s) cu.m 18,000.00
Cement Plaster Works on Outer Wall (1:6) sq.m 600.00
Exterior Weather Coat Paint sq.m 350.00

3.2 BRICK MASONRY WORKS ( 1 : 4 c/s ) cu.m 76.21 18,000.00 72.19 48.26 24.88 145.33 2,615,986.35
3.3 HALF BRICK WORKS ( 1 : 4 c/s ) sq.m 64.50 1,500.00 11.04 6.75 10.61 28.40 42,599.10
3.4 HONEY COMB BRICK WORKS (1:3 c/s) cu.m 0.48 9,000.00 0.24 0.24 0.48 4,279.50
4 DOORS & WINDOWS WORKS
4.1 METAL FRAME
4.1.1 Door Frame r.m 151.04 1,100.00 89.94 61.10 151.04 166,144.00

Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank
4.1.2 Window Frame r.m 383.66 1,100.00 223.80 139.26 363.06 399,360.50
4.2 METAL SHUTTER
4.2.1 WINDOW SHUTTER sq.m 78.99 7,500.00 39.21 25.07 64.28 482,071.31
4.3 WOODEN SHUTTER
4.3.1 FLUSH DOOR SHUTTER (32MM) sq.m 58.33 8,000.00 31.03 21.61 52.64 421,083.60
4.4 UPVC DOOR
4.4.1 Shutter/Frame sq.m 7.14 9,000.00 6.97 6.97 62,730.00
4.5 WINDOW GRILL sq.m 50.07 2,500.00 39.77 25.07 6.23 71.07 177,665.44
4.6 COLLAPSIBLE GATE sq.m 14.98 10,000.00 7.55 7.43 14.98 149,767.50
5 FLOORING WORKS
5.1 HARDENED CEMENT CONCRETE FLOOR sq.m 782.82 900.00 433.94 305.97 41.53 781.44 703,293.98
5.2 NEAT CEMENT SKIRTING r.m 420.91 100.00 228.46 193.98 11.50 433.94 43,394.10
5.3 TERRAZZO CAST-IN SITU DADO sq.m 36.63 1,500.00 2.40 1.20 32.88 36.48 54,720.00
6 ROOFING/TERRACING WORK
6.1 METAL WORKS (TRUSS) kg 6660.99 220.00 3,545.29 3,545.29 597.05 7,687.63 1,691,279.68
6.2 CGI SHEET ROOFING sq.m 439.95 2,000.00 205.50 205.50 33.54 444.54 889,080.00
6.3 CGI SHEET ROOFING RIDGE r.m 42.6 1,200.00 17.90 17.90 6.95 42.75 51,300.00
6.4 GI FACIA (EAVES) kg 387.62 250.00 143.91 143.91 8.06 295.89 73,972.50
6.5 CEMENT BOARD FALSE CEILING sq.m 344.15 1,500.00 174.90 174.90 23.75 373.56 560,337.00
7 PLASTERING/WALL FINISHING WORK
7.1 CEMENT PLASTER WORK
7.1.1 ON INNER WALL sq.m 923.13 600.00 534.33 361.00 52.52 947.85 568,709.19
7.1.2 ON CEILING (1:4) sq.m 360.86 500.00 288.40 183.87 23.60 495.87 247,936.89
7.1.3 ON OUTER WALL (1:6)
7.1.3.1 EXTERNAL PLASTER sq.m 430.90 600.00 372.47 334.39 68.93 775.79 465,474.24
7.1.4 EXTERNAL PLASTER WITH CEMENT PUNNING sq.m 35.21 700.00 35.66 35.66 24,962.00
7 PAINTING WORKS
7.2.1 DISTEMPER PAINT sq.m 1599.82 200.00 997.64 719.78 99.87 1,817.29 363,457.50
7.2.2 EXTERIOR WEATHER COAT PAINT sq.m 461.26 350.00 372.47 334.39 68.93 775.79 271,527.81
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG sq.m 369.72 550.00
7.2.4 ENAMEL PAINT sq.m 392.72 400.00 218.67 184.53 6.23 409.43 163,771.80
8 MISCELLANEOUS
8.2 CEMENT BOARD WALL sq.m 32.61 6,500.00 15.39 15.39 3.38 34.16 222,040.00
8.3 RAILING kg 1496.50 220.00 992.98 534.12 1,527.10 335,962.96
8.4 PUMP SHED nos. 1.00 80,000.00 1.00 1.00 80,000.00

3 ELECTRICAL WORKS
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure no. 2.00 12,000.00 1.00 1.00 2.00 24,000.00
1.2 Stand Alone 6 A DP MCB with Enclosure no. 1.00 8,500.00 1.00 1.00 8,500.00
2 CABLES & WIRES
2.1 2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper conductor wires rm 100.00 800.00 55.00 42.00 97.00 77,600.00
2 Nos 2.5 Sq.mm mutistranded copper conductor wires + 1 Nos. 1.5sq mm
2.2 multistranded Cu wire rm 50.00 250.00 51.00 51.00 12,750.00
B School Blocks
1 DISTRIBUTION BOARDS
1.1 Ground Floor nos. 2.00 30,000.00 1.00 1.00 2.00 60,000.00
1.2 First Floor nos. 2.00 22,000.00 1.00 1.00 2.00 44,000.00
1.3 Second Floor nos. 1.00 22,000.00 1.00 1.00 22,000.00
1.4 Stand Alone 6 A DP MCB with Enclosure nos. 1.00 8,500.00 1.00 1.00 8,500.00

Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank
2 CABLES & WIRES
2.1 2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm Multistranded Cu wire rm 15.00 600.00 10.00 5.00 15.00 9,000.00
2.2 2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm Multistranded Cu wire rm 15.00 500.00 10.00 10.00 5,000.00
2.2 2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm Multistranded Cu wire rm 30.00 250.00 16.00 16.00 4,000.00
3 General Service Light Point Wiring
3.1 One Way Light Point pts. 74.00 700.00 41.00 29.00 5.00 75.00 52,500.00
3.2 Two Way Light Point pts. 3.00 900.00 2.00 1.00 3.00 2,700.00
3.3 Ceiling Fan Point pts. 8.00 900.00 4.00 4.00 8.00 7,200.00
4 16 A Universal Pin Light Power Socket Wiring pts. 1.00 900.00 1.00 1.00 900.00
5 6A Universal Pin Light Power Socket Wiring pts. 43.00 700.00 28.00 15.00 43.00 30,100.00
6 Switch Socket Outlets
6.1 16 A Universal Pin Light Power Socket Wiring nos. 1.00 1,500.00 1.00 1.00 1,500.00
6.2 6A Universal Power Switch Socket nos. 43.00 900.00 28.00 16.00 44.00 39,600.00
7 Sweep Ceiling/Exhaust Fans/ Wall Fan
7.1 1200 mm Sweep Ceiling Fan no. 2.00 4,500.00 2.00 2.00 9,000.00
7.2 400 mm Sweep Wall Fan no. 6.00 3,500.00 6.00 6.00 21,000.00
7.3 225mm dia M/D Exhaust Fan nos. 2.00 6,000.00 2.00 2.00 12,000.00
8 Light Fixtures/Luminaires & Accessories
8.1 24 W LED Recessed Mounted Square type nos. 4.00 4,500.00 4.00 4.00 18,000.00
8.2 18 W LED Surface Mounted Square type nos. 22.00 2,700.00 16.00 6.00 22.00 59,400.00
8.3 18 W LED Recessed Mounted Square type nos. 12.00 2,700.00 8.00 4.00 12.00 32,400.00
8.4 12 W LED Surface Mounted Cylindrical type nos. 15.00 2,400.00 9.00 6.00 15.00 36,000.00
8.5 12 W LED Recessed Mounted Crrcular type nos. 10.00 2,400.00 5.00 5.00 10.00 24,000.00
8.6 LED Wall Light nos. 3.00 1,800.00 1.00 1.00 1.00 3.00 5,400.00
8.7 9W LED Surface Mounted Cylindrical type nos. 1.00 2,000.00 1.00 1.00 2,000.00
8.8 6W LED Recessed Mounted Circular type nos. 3.00 1,800.00 3.00 3.00 5,400.00
8.9 7W LED T5 Slim Mirror Light nos. 1.00 2,000.00 1.00 1.00 2,000.00
9 Pull Box nos. 6.00 700.00 3.00 3.00 6.00 4,200.00
10 External Post Top Light Pole nos. 6.00 7,500.00 3.00 3.00 6.00 45,000.00
11 Post Top External Light Fixtures nos. 6.00 9,800.00 3.00 3.00 6.00 58,800.00
12 Earthing & Lighting Protection
12.1 Chemical Earthing nos. 6.00 45,000.00 3.00 3.00 6.00 270,000.00
12.2 Earthing Bar nos. 6.00 2,200.00 3.00 3.00 6.00 13,200.00
13 Earthing Strip/Wires
13.1 25 x 3 mm GI strip mtr. 130.00 300.00 67.00 65.00 132.00 39,600.00
13.2 12 SWG Cu wire mtr. 30.00 200.00 16.00 15.00 31.00 6,200.00
14 Earth Test link nos. 2.00 1,500.00 1.00 1.00 2.00 3,000.00
C Solar PV System
1 Solar PV Panel nos. 4.00 26,000.00 4.00 4.00 104,000.00
2 Tubular Deep Cycle Battery nos. 2.00 30,000.00 2.00 2.00 60,000.00
3 Hybrid Inverter 1.00 100,000.00 1.00 1.00 100,000.00
D FIRE EXTINGUISHER
a ABC stored Pressure 5.0kg size ABC stored pressure type Fire extinguisher. nos. 2.00 8,000.00 2.00 2.00 16,000.00
b Dry Powder Fire Extinguisher nos. 1.00 8,000.00 1.00 1.00 8,000.00

BILL No. 4. SANITARY WORKS


A PIPING WORKS
1 WATER SUPPLY INSTALLATION

Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank

a) CPVC pipes
Rm 60 1,600.00 55.00 55.00 88,000.00
- 40 mm
- 25 mm Rm 70 1,000.00 18.00 18.00 18,000.00
- 20 mm Rm 11 700.00 10.00 10.00 7,000.00
- 15 mm Rm 4 500.00 2.50 2.50 1,250.00
c) CPVC Ball Valve No. 4 2,000.00
- 40 mm 2.00 2.00 4,000.00
- 25 mm No. 4 900.00 3.00 3.00 2,700.00
20 mm No. 2 400.00 2.00 2.00 800.00
40 mm dia Gun Metal Check valve No. 1.00 4,500.00 1.00 1.00 4,500.00
d) Electric Centrifugal Water Pump Set 1 12,500.00 1.00 1.00 12,500.00
e) 1000 litres capacity Plastic cyllindrical vertical water storage tank No. 2 34,000.00 1.00 1.00 34,000.00

2 SEWER, RAIN AND WASTE WATER INSTALLATION


PVC SWR
110 mm Rm 33 1,400.00 32.00 32.00 44,800.00
75 mm Rm 33 1,200.00 25.00 25.00 30,000.00
50 mm Rm 4 350.00 2.00 2.00 700.00

B SCHOOL BLOCKS
1 SANITARY INSTALLATION
a Stainless Steel Kitchen Sink Set 1 35,000.00 1.00 1.00 35,000.00
b CP self closing bib cock No 1 4,000.00 1.00 1.00 4,000.00
c PVC Multi-floor trap with cover No. 1 600.00 1.00 1.00 600.00
d CP Waste Coupling and PVC bottle trap for water trough No. 1 1,500.00 1.00 1.00 1,500.00

2 SANITARY INSTALLATION
a Water Closet set Set 1 34,000.00 1.00 1.00 34,000.00
b 580x480mm Orissa Pan Set 2 3,100.00 2.00 2.00 6,200.00
c Hand wash basin Set 1 8,000.00 1.00 1.00 8,000.00
d Ladies Urinal Set 2 110,000.00 2.00 2.00 220,000.00
e CP self closing bib cock No 6 4,000.00 6.00 6.00 24,000.00
f CP spreader for Urinal Set 2 2,500.00 2.00 2.00 5,000.00
g CP Toilet Paper Holder heavy No. 1 2,600.00 1.00 1.00 2,600.00
h 15mm CP Commode Spray with plastic head No. 1 2,000.00 1.00 1.00 2,000.00
i PVC Multi-floor trap with cover No. 5 600.00 5.00 5.00 3,000.00
j CP Waste Coupling and PVC bottle trap for water trough No. 2 1,500.00 2.00 2.00 3,000.00
k 40 mm SS Grab bar of 600mm Length - Side Set 1 4,500.00 1.00 1.00 4,500.00
l 40 mm SS Grab bar of 600mm Length - Rear Set 1 4,500.00 1.00 1.00 4,500.00
m CP Foldable Hinge Set 2 5,500.00 2.00 2.00 11,000.00

B CIVIL WORKS : SITE DEVELOPMENT


1 EARTHWORKS
1 SITE CLEARANCE AND MOBILIZATION Sq.m 256.72 100.00 152.63 152.63 15,263.00
2 EARTHWORK IN EXCAVATION Cu.m 171.79 400.00 21.84 21.84 8,736.00
3 EARTHBACK FILLING Cu.m 37.75 300.00 19.19 19.19 5,757.00
4 BOULDER SOLING Cu.m 26.16 6,000.00 23.72 23.72 142,320.00
5 P.C.C (1:3:6) Cu.m 1.31 14,000.00 1.14 1.14 15,960.00
6 P.C.C (1:2:4) Cu.m 12.98 16,000.00 9.39 9.39 150,240.00
7 P.C.C FOR R.C.C WORK Cu.m 0.99 20,000.00 0.99 0.99 19,800.00

Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Type Design
Pay Total This
Quantity
Item Description of Works Unit Rate (NRs.) Bill Amount (NRs) Remarks
in BOQ Site Water
No. 3-6C(S)-E 2-4C(S)-H Ts(F) Quantity
Development Tank
8 SILICA CEMENT ADMIXTURE Kg 9.90 300.00 9.90 9.90 2,970.00
9 STEEL REINFORCEMENT Mt. 0.10 130,000.00 0.11 0.11 13,897.00
10 FORM WORKS Sq.m 9.12 800.00 11.33 11.33 9,064.00
11 STONE MASONARY WORKS (1:4 c/s) Cu.m 4.81 10,000.00 4.35 4.35 43,500.00
13 BRICKS MASONRY WORKS (1:4 c/s) Cu.m 0.22 18,000.00 7.91 7.91 142,469.82
14 NEAT CEMENT SKIRTING r.m 4.72 100.00 4.72 4.72 472.00
15 METAL WORKS FOR FENCE k.g 790.75 220.00 744.98 744.98 163,895.60
16 METAL WORKS FOR GATE k.g 130.78 220.00 123.31 123.31 27,128.09
17 PLASTER ON OUTER WALL Sq.m 7.92 600.00 49.26 49.26 29,556.00
18 EXTERIOR WEATHER COAT PAINT Sq.m 8.87 350.00 8.28 8.28 2,898.00
19 CHAIN LINK FENCE Sq.m 82.94 1,000.00 102.00 102.00 102,000.00
20 FLAG POLE nos. 2.00 25,000.00 2.00 2.00 50,000.00

CIVIL WORKS-RESERVOIR TANK


1 EARTH WORK
1.1 SITE CLEARANCE AND MOBILIZATION sq.m 22.31 100.00 22.31 22.31 2,231.00
1.2 EARTHWORK IN EXCAVATION cu.m 24.58 400.00 24.57 24.57 9,828.72
1.3 EARTH BACK FILLING cu.m 4.02 300.00 4.01 4.01 1,202.85
1.4 BOULDER SOLING cu.m 2.08 6,000.00 2.08 2.08 12,462.00
2 CONCRETE WORKS
2.1 P.C.C (1:3:6) cu.m 0.78 14,000.00 0.78 0.78 10,904.25
2.2 P.C.C FOR R.C.C WORKS cu.m 7.42 20,000.00 7.41 7.41 148,295.00
2.3 SILICA CEMENT ADMIXTURE kg 74.20 300.00 74.15 74.15 22,244.25
2.4 STEEL REINFORCEMENT Mt 1.46 130,000.00 1.58 1.58 204,902.61
2.5 FORMWORKS sq.m 54.93 800.00 56.46 56.46 45,170.80
3 PLASTERING/WALL FINISHING WORKS
3.1.1 INTERNAL PLASTER ON WALL (1:4) WITH CEMENT PUNNING sq.m 33.66 700.00 35.46 35.46 24,824.45
4 WATERPROOFING WORKS sq.m 33.66 550.00 35.46 35.46 19,504.93

FURNITURE WORKS lot 1 4,000,000.00 0.5 0.5 1.00 4,000,000.00


Total 35,315,032.74

Checked By:
Prepared By: Bimal Bahadur Thapa Approved By:
Sharma AM JV DME, DSC DLPIU
Project Name : Emergency School Reconstruction Project (ESRP)
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Length Breadth Height


S.No Description No. Qty. Unit Remarks
(m) (m) (m)
1 Mobilization and Demobilization 1 1 L.S

2 Site Office Establishment 15 15 Per month

3 Project Information Board 1 1 No.

4 Safety Sign Board 1 1 No.

5 Barricading Works 1 37 37 Rm

Dismantling of completely damaged


6
building
Building 1 1 15.00 8.00 120.00 sq.m

7 Safety materials and site safety L.S

8 Construction of new TLC


Building 1 ( 5 Class room) 1 18.5 3.95 73.075 sq.m

10 Construction of Temporary Toilet 2 2 Nos.

11 Road Repair and maintenance 4 4 km

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-6C(S)-B
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Breadth Height
S.No Description No. Length (m) Qty. Unit Remarks
(m) (m)
1 Earthworks
1.1 Site Clearance and Mobilization 1 21.95 13.95 306.20
Total 306.20 Sq.m

1.2 Earthwork in excavation


For Footing
Grid 1
Footing (F2) 2 2.50 2.50 1.50 18.75
Footing (F3) 2 2.80 2.80 1.50 23.52
Grid 2
Footing (F3) 2 2.80 2.80 1.50 23.52
Footing (F4) 2 3.10 3.10 1.50 28.83
Grid 3
Footing (F1) 4 1.80 1.80 1.50 19.44
Excavation for lower tie beam
Grid 1 1 7.40 0.60 0.90 4.00
Grid 2 1 6.50 0.50 0.90 2.93
Grid 3 1 10.10 0.60 0.90 5.45
Grid A & Grid D 2 3.55 0.60 0.90 3.83
Grid B 1 3.10 0.60 0.90 1.67
Grid C 1 3.10 0.50 0.90 1.40
Front Steps/Drain 1 10.03 1.50 0.15 2.26
1 10.03 0.60 0.05 0.30
Back Drain 1 15.95 0.98 0.15 2.33
1 15.95 0.60 0.05 0.48
Side Drain 2 6.45 0.98 0.15 1.89
2 6.45 0.60 0.05 0.39
Side Steps 1 2.43 0.75 0.15 0.27
1 2.50 0.75 1.15 2.16
Ramp
For Slope 1 3.50 1.03 0.28 0.99
For Front wall 3-AB 1 6.50 0.55 0.45 1.61
For Side wall -3B 1 1.33 0.55 0.45 0.33
Total 146.33 Cu.m

1.3 Earth Back filling


Excavated earthwork 146.33
Boulder soling -14.65
PCC -7.32

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
RCC -28.76
Brick masonry work below plinth tie beam -6.28
Class room 2 5.70 5.70 0.18 11.37
Staircase 1 3.20 5.70 0.18 3.19
Corridoor 1 14.60 2.20 0.18 5.62
Below Ramp 1 1.40 1.30 0.14 0.25
Total 109.75 Cu.m

1.4 Boulder Soling


For Footing
Grid 1
Footing (F2) 2 2.20 2.20 0.20 1.94
Footing (F3) 2 2.50 2.50 0.20 2.50
Grid 2
Footing (F3) 2 2.50 2.50 0.20 2.50
Footing (F4) 2 2.80 2.80 0.20 3.14
Grid 3
Footing (F1) 4 1.50 1.50 0.20 1.80

For Lower Tie Beam


Grid 1,3 2 12.95 0.45 0.10 1.17
Grid 2 1 12.95 0.35 0.10 0.45
Grid A,B,D 3 6.80 0.45 0.10 0.92
Grid C 1 6.80 0.35 0.10 0.24

Building Floors
Classroom
Class Room 2 5.75 5.75 0.20 13.23
Corridor 2 5.75 2.25 0.20 5.18
1 3.25 2.25 0.20 1.46
Below Staircase 1 3.25 5.75 0.20 3.74

Front Steps/Drain 1 10.03 1.50 0.10 1.50


1 10.03 0.60 0.05 0.30
Back Drain 1 15.95 0.98 0.10 1.56
1 15.95 0.60 0.05 0.48
Side Drain 2 6.45 0.98 0.10 1.26
2 6.45 0.60 0.05 0.39
Side Steps 1 2.43 0.60 0.10 0.15
1 2.50 0.60 0.10 0.15

Below ramp
For Slope 1 6.82 1.18 0.20 1.61
For Front wall 3-AB 1 6.50 0.45 0.10 0.29
For Side wall -3B 1 1.33 0.45 0.10 0.06
Total 45.99 Cu.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
2 Concrete Works
2.1 PCC
2.1.1 PCC work (1:3:6)
For Footing
Grid 1
Footing (F2) 2 2.20 2.20 0.10 0.97
Footing (F3) 2 2.50 2.50 0.10 1.25
Grid 2
Footing (F3) 2 2.50 2.50 0.10 1.25
Footing (F4) 2 2.80 2.80 0.10 1.57
Grid 3
Footing (F1) 4 1.50 1.50 0.10 0.90

For Lower Tie Beam


Grid 1,3 2 12.95 0.45 0.05 0.58
Grid 2 1 12.95 0.35 0.05 0.23
Grid A,B,D 3 6.80 0.45 0.05 0.46
Grid C 1 6.80 0.35 0.05 0.12
Total 7.32 Cu.m

2.1.2 P.C.C.(1:2:4) Works


Floor Area
Room 2 5.7 5.7 0.075 4.88
Staircase Portion 1 3.2 5.7 0.075 1.37
Verandah 1 14.6 2.2 0.075 2.41
Side Drain
Around Building-Foundation PCC 1 33 0.575 0.075 1.43
Around Building-Top PCC 1 33.4 0.125 0.05 0.21
Apron
Around Building 1 30.4 0.95 0.05 1.45
Steps
Front 1 10.025 0.6 0.05 0.31
Sides 2 1.925 0.6 0.05 0.12
Ramp
Wall- Foundation
1 6.75 0.45 0.05 0.16
1 1.4 0.45 0.05 0.04
Wall-Top
1 6.75 0.125 0.05 0.05
1 1.4 0.25 0.05 0.02
Ramp-Floor 1 6.525 1.275 0.075 0.63
Total 13.08 Cu.m

2.2 PCC for RCC Work 1:1.5:3


For Footing

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Footing F1 4.00
Square portion 1.50 1.50 0.20 1.80
Trapezoid portion Area 1.49 0.25 1.49
Footing F2 2.00
Square portion 2.20 2.20 0.20 1.94
Trapezoid portion Area 2.78 0.25 1.39
Footing F3 4.00
Square portion 2.50 2.50 0.20 5.00
Trapezoid portion Area 3.49 0.25 3.49
Footing F4 2.00
Square portion 2.80 2.80 0.20 3.14
Trapezoid portion Area 4.28 0.25 2.14
Lower Tie Beam
Grid 1,2,3 3.00 14.15 0.25 0.30 3.18
Grid A,B,C,D 4.00 7.60 0.25 0.30 2.28

Column
From lower to plinth tie beam 12.00 0.45 0.45 1.20 2.92
Plinth tie beam
Grid 1,2,3 3.00 14.15 0.30 0.53 6.69
Grid A,B,C,D 4.00 7.60 0.30 0.53 4.79
Ground Floor
For column 12 0.45 0.45 3.00 7.29
G.F Staircase
Landing beam 1 3.05 0.25 0.38 0.29
Landing 1 1 3.20 1.50 0.15 0.72
Landing 2 1 3.20 1.85 0.15 0.89
First flight
Waist Slab 1 3.35 1.50 0.15 0.75
Riser 9 Area 0.02 1.50 0.30
Second Flight
Waist Slab 1 3.40 1.50 0.15 0.77
Riser 10 Area 0.02 1.50 0.34
Staircase gap
Waist Slab 1 1.30 0.20 0.15 0.04
Riser 3 Area 0.02 0.45 0.03
First floor beam
Primary Beam
Grid 1-2-3 3 14.15 0.30 0.53 6.69
Grid A-B-C_D 4 7.60 0.30 0.53 4.79
Secondary Beam
Grid A1-C1 2 7.90 0.25 0.43 1.68
Grid 1a 2 5.45 0.25 0.43 1.16
Grid 1b 1 3.20 0.25 0.43 0.34
F.F. Slab
Class room 8 2.73 2.73 0.13 7.43

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Corridoor 4 2.73 2.20 0.13 3.00
1 3.20 2.20 0.13 0.88
Slab between beam 1b & 2B-2C 1 0.49 3.20 0.13 0.20
Staircase top slab 1 0.39 3.20 0.15 0.18
Lintel Bands, Ground floor level
Along grid A,B,C,D 4 5.55 0.23 0.13 0.64
Along grid 1 1 11.10 0.23 0.13 0.32
Along grid 2 1 11.10 0.23 0.13 0.32
Sill Bands, Ground floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 11.10 0.23 0.08 0.19
Along grid 2 1 11.10 0.23 0.08 0.19
At store 1 1.30 0.12 0.08 0.01
Vetical Band 4.00 2.48 0.25 0.08 0.19

First Floor
For column 12 0.45 0.45 3.00 7.29
F.F Staircase
Landing beam 1 3.05 0.25 0.38 0.29
Landing 2 1 3.2 1.85 0.15 0.89
First flight
Waist Slab 1 3.35 1.5 0.15 0.75
Riser 9 Area 0.02 1.50 0.30
Second Flight
Waist Slab 1 3.40 1.50 0.15 0.77
Riser 10 Area 0.02 1.50 0.34
Second Floor Beam
Primary Beam
Grid 1-2-3 3 14.15 0.30 0.53 6.69
Grid A-B-C_D 4 7.60 0.30 0.53 4.79
Secondary Beam
Grid A1-C1 2 7.90 0.25 0.43 1.68
Grid 1a 2 5.45 0.25 0.43 1.16
Grid 1b 1 3.20 0.25 0.43 0.34
S.F. Slab
Class room 8 2.73 2.73 0.13 7.43
Corridoor 4 2.73 2.20 0.13 3.00
1 3.20 2.20 0.13 0.88
Slab between beam 1b & 2B-2C 1 0.49 3.20 0.13 0.20
Staircase top slab 1 0.39 3.20 0.15 0.18
Lintel Bands, First floor level
Along grid A,B,C,D 4 5.55 0.23 0.13 0.64
Along grid 1 1 11.10 0.23 0.13 0.32
Along grid 2 1 11.10 0.23 0.13 0.32
Sill Bands, First floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along grid 1 1 11.10 0.23 0.08 0.19
Along grid 2 1 11.10 0.23 0.08 0.19
Vetical Band 4.00 2.48 0.25 0.08 0.19

Second Floor
For column 12 0.45 0.45 2.60 6.32
Second Floor Truss Beam
Primary Beam
Grid 1-2-3 3 14.15 0.30 0.40 5.09
Grid A-B-C-D 4 7.60 0.30 0.40 3.65
Lintel Bands, Second floor level
Along grid A,B,C,D 4 5.55 0.23 0.13 0.64
Along grid 1 1 11.10 0.23 0.13 0.32
Along grid 2 1 14.15 0.23 0.13 0.41
Sill Bands, Second floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 11.10 0.23 0.08 0.19
Along grid 2 1 11.10 0.23 0.08 0.19
Vetical Band 4.00 2.48 0.25 0.08 0.19

Deduction of Doors For Sill


Ground floor level
D1 -4 1.10 0.230 0.08 -0.08
First floor level
D1 -4 1.10 0.230 0.08 -0.08
Second floor level
D1 -4 1.10 0.230 0.08 -0.08

Pedestal in corridor 8 0.50 0.25 0.25 0.25


Bench Slab 2 2.50 0.60 0.08 0.23
Total 137.04 Cu.m

2.3 Silica Admixture


10 Kg per cu.m. of R.C.C. M20 10 137.04 1,370.37
Total 1370.37 kg
2.5 Form Works
For Footing
Footing F1 4 6.00 0.20 4.80
Footing F2 2 8.80 0.20 3.52
Footing F3 4 10.00 0.20 8.00
Footing F4 2 11.20 0.20 4.48
Lower tie beam
Grid 1,2,3 3 14.15 0.60 25.47
Grid A,B,C,D 4 7.60 0.60 18.24
For Column
From lower to plinth tie beam 12 1.80 1.20 25.92

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Deduction1 at beam and column junction at -34 0.25 0.30 -2.55
LTB
Deduction1 at beam and column junction at -34 0.30 0.53 -5.36
UTB
For Plinth Tie Beam
Grid 1,2 & 3 3 14.15 1.05 44.57
Grid A,B,C &D 4 7.60 1.05 31.92
Landing Beam 1 3.20 1.01 3.23
Ground floor
For column 12 1.80 3.00 64.80
Deduction for Beam opening part -34 0.30 0.53 -5.36
Staircase Area
First flight
Waist slab 1 3.35 1.50 5.03
Landing 1 1.94 1.50 2.90
1 1.47 1.70 2.49
Riser 10 1.50 0.15 2.25
Side 2 3.35 0.30 2.01
1 4.00 0.15 0.60
Second flight
Waist slab 1 3.40 1.50 5.10
Riser 10 1.50 0.15 2.25
Side 2 3.40 0.30 2.04
First floor beam
Main beam
Grid 1 (A-B & C-D) 2 5.55 1.23 13.60
Grid 1 (B-C) 1 3.05 1.35 4.12
Grid 2 1 14.15 1.10 15.57
Grid 3 1 14.15 1.23 17.33
Grid A & D 2 7.60 1.23 18.62
Grid B & C (1-2) 2 5.55 1.23 13.60
Grid B & C (2-3) 2 2.05 1.10 4.51
Secondary beam
Grid A1-C1 2 7.65 0.85 13.01
Grid 1a 2 5.70 0.85 9.69
Grid 1b 1 3.20 0.85 2.72
Deduction on main beam and secondary beam
-14 0.30 0.25 -1.05
junction
Slab
Class room 8 2.73 2.73 59.41
Corridoor 4 2.73 2.20 23.98
1 3.20 2.19 7.01
Stair case area 1 3.20 0.49 1.57
1 3.20 0.39 1.23
First Floor
For column 12 1.80 3.00 64.80
Deduction on beam and column junction -34 0.30 0.53 -5.36

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
F.F.Staircase Area
First flight
Waist slab 1 3.35 1.50 5.03
Landing 1 1.94 1.50 2.90
1 1.47 1.70 2.49
Riser 10 1.50 0.15 2.25
Side 2 3.35 0.30 2.01
1 1.47 0.15 0.22
1 1.94 0.15 0.29
1 1.25 0.15 0.19
Second flight
Waist slab 1 3.40 1.50 5.10
Riser 10 1.50 0.15 2.25
Side 2 3.40 0.30 2.04

Second Floor Beam


Main beam
Grid 1 (A-B & C-D) 2 5.55 1.23 13.60
Grid 1 (B-C) 1 3.05 1.35 4.12
Grid 2 1 14.15 1.10 15.57
Grid 3 1 14.15 1.23 17.33
Grid A & D 2 7.60 1.23 18.62
Grid B & C (1-2) 2 5.55 1.23 13.60
Grid B & C (2-3) 2 2.05 1.10 4.51
Secondary beam
Grid A1-C1 2 7.65 0.85 13.01
Grid 1a 2 5.70 0.85 9.69
Grid 1b 1 3.20 0.85 2.72
Deduction on main beam and secondary beam
-14 0.30 0.25 -1.05
junction
Slab
Class room 8 2.73 2.73 59.41
Corridoor 4 2.73 2.20 23.98
1 3.20 2.19 7.01
Stair case area 1 3.20 0.49 1.57
1 3.20 0.39 1.23
Second Floor
For column 12 1.80 3.00 64.80
Deduction on beam and column junction -34 0.30 0.53 -5.36
Second Floor Beam
Truss beam
Grid 1-2-3 3 14.15 1.10 46.70
Grid A-B-C-D 4 7.60 1.10 33.44
Lintel Bands
Ground floor level
Along grid A,B,C,D 8 5.55 0.13 5.55

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along grid 1 2 11.10 0.13 2.78
Along grid 2 2 11.10 0.13 2.78
First floor level
Along grid A,B,C,D 8 5.55 0.13 5.55
Along grid 1 2 11.10 0.13 2.78
Along grid 2 2 11.10 0.13 2.78
Second floor level
Along grid A,B,C,D 8 5.55 0.13 5.55
Along grid 1 2 11.10 0.13 2.78
Along grid 2 2 11.10 0.13 2.78
Sill Bands
Ground floor level
Along grid A,B,C,D 8 5.55 0.08 3.33
Along grid 1 2 11.10 0.08 1.67
Along grid 2 2 11.10 0.08 1.67
At store 2 1.30 0.08 0.20
First floor level
Along grid A,B,C,D 8 5.55 0.08 3.33
Along grid 1 2 11.10 0.08 1.67
Along grid 2 2 11.10 0.08 1.67
Second floor level
Along grid A,B,C,D 8 5.55 0.08 3.33
Along grid 1 2 11.10 0.08 1.67
Along grid 2 2 11.10 0.08 1.67
Vetical Band
Ground Floor 4.00 2.48 0.38 3.76
First Floor 4.00 2.48 0.38 3.76
First Floor 4.00 2.60 0.38 3.95

Deduction of Doors For Sill


Ground floor level
D1 -8 1.10 0.08 -0.66
First floor level
D1 -8 1.10 0.08 -0.66
Second floor level
D1 -8 1.10 0.08 -0.66
Pedestal in corridor 8 1.25 0.25 2.50
Bench
Bench Top Slab 2 5.80 0.125 1.45
Bottom 2 1.90 0.25 0.95
Total 947.85 sq.m

3 Brick works
3.2 Brick Masonary Works (1:4 c/s)
Foundation upto plinth
Grid 1,2,3 3 14.15 0.23 0.38 3.66

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Grid A,B,C,D,E 4 7.60 0.23 0.38 2.62

Ground floor
Along grid A,B,C,D/(1-2) 4 5.55 0.23 2.33 11.87
Along grid 1 1 11.10 0.23 2.33 5.94
1 3.05 0.23 2.02 1.42
Along grid 2 1 10.80 0.23 2.33 5.78

Deduction for doors and windows


Ground floor plan
W1 -8 1.10 0.23 1.13 -2.28
V1 -8 1.10 0.23 0.53 -1.06
W3 -1 1.50 0.23 0.37 -0.13
D1 -4 1.10 0.23 2.33 -2.35

First floor level


Along grid A,B,C,D 4 5.55 0.23 2.33 11.87
Along grid 1 1 11.10 0.23 2.33 5.94
1 3.05 0.23 2.05 1.43
Along grid 2 1 10.80 0.23 2.33 5.78

Deduction for doors and windows


First floor plan
W1 -8 1.10 0.23 1.13 -2.28
V1 -8 1.10 0.23 0.53 -1.06
W2 -1 1.50 0.23 1.00 -0.35
D1 -4 1.10 0.23 2.33 -2.35

Second floor level


Along grid A,B,C,D 4 5.55 0.23 2.45 12.51
Along grid 1 1 11.10 0.23 2.45 6.25
1 3.05 0.23 2.53 1.77
Along grid 2 1 10.80 0.23 2.45 6.09

Deduction for doors and windows


Second floor plan
W1 -8 1.10 0.23 1.13 -2.28
V2 -8 1.10 0.23 0.65 -1.32
W2 -1 1.50 0.23 1.00 -0.35
D2 -4 1.10 0.23 2.45 -2.48

Drain 1 33.40 0.23 0.15 1.15


Below ramp
For Front wall 3-AB 1 6.50 0.35 0.30 0.68
For Side wall -3B 1 1.33 0.35 0.30 0.14

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Above ramp
For Front wall 3-AB 1 1.40 0.23 0.38 0.12
1 4.25 0.23 0.19 0.18
For Side wall -3B 1 1.33 0.23 0.59 0.18

External Steps 1 13.50 0.48 0.10 1.35


1 13.50 0.18 0.15 2.03
1 13.50 0.08 0.10 1.35
Grid 2A 1 0.60 0.50 0.45 0.14
Grid 3A 1 0.53 0.40 0.45 0.09
Grid 2D 1 0.60 0.50 0.45 0.14
Total 72.19 Cu.m

3.3 Half brick work (1:4 c/s)


Storeroom below staircase 1 3.00 1.35 2.03
1 0.20 1.35 0.27
1 0.90 1.50 1.35
1 1.50 1.65 2.48
Deductions D3 -1 1.00 1.55 -1.55
Ramp
Grid 3AB
1 1.40 0.22 0.31
1 5.12 0.22 1.13
Bench
4 2.15 0.53 4.52
4 0.25 0.53 0.53
Total 11.04 Sq.m

4 Doors and Windows


4.1 Metal Frame
4.1.1 Door Frame
D1 8 7.07 56.56
D2 4 7.32 29.28
D3 1 4.10 4.10
Total 89.94 R.m

4.1.2 Window Frame


W1 24 5.58 133.80
W2 2 5.00 10.00
V1 16 3.25 52.00
V2 8 3.50 28.00
Total 223.80 R.m

4.2 Metal Shutter


4.2.1 Window Shutter
W1 24 1.01 1.04 25.09

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
W2 2 1.41 0.91 2.57
V1 16 1.01 0.44 7.03
V2 8 1.01 0.56 4.52
Total 39.21 Sq.m

4.3 Flush Door Shutter


D1 8 1.01 2.46 19.84
D2 4 1.01 2.56 10.32
D3 1 0.91 0.96 0.87
Total 31.03 Sq.m

4.5 Window Grill


W1 24 1.01 1.04 25.09
W2 2 1.41 0.91 2.57
W3 1 1.50 0.37 0.56
V1 16 1.01 0.44 7.03
V2 8 1.01 0.56 4.52
Total 39.77 Sq.m

4.6 Collapsible Gate


1 3.05 2.475 7.55
Total 7.55 sq.m

5 FLOORING WORKS
5.1 Hardened Cement Concrete Flooring (40mm) With Neat Cement Punning
Ground floor plan
Class Room 2 5.78 5.75 66.41
Corridor 1 15.80 2.50 39.50
1 3.20 1.50 4.80
Below Staircase 1 4.50 3.20 14.40
Staircase Tread 18 0.3 1.50 8.10
Riser 20 0.15 1.50 4.50
Staircase landing 1 1.80 3.20 5.76

First floor plan


Class Room 2 5.78 5.75 66.41
Corridor 1 15.80 2.50 39.50
1 3.20 1.50 4.80
Staircase Tread 18 0.3 1.50 8.10
Riser 20 0.15 1.50 4.50
Staircase landing 1 1.80 3.20 5.76

Second floor plan


Class Room 2 5.78 5.75 66.41
Corridor 1 15.80 2.50 39.50
1 3.20 1.50 4.80

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Ramp 1 6.52 1.30 8.48
Exterior Steps (Front) 1 13.50 0.90 12.15
Drain
Back of Building 1 15.95 0.95 15.15
Side of bulding 1 6.45 0.95 6.13
Side Steps 1 10.03 0.875 8.77
Total 433.94 sq.m

5.2 Neat Cement Skirting works


Ground floor plan
Room 2 21.35 42.70
Staircase Lobby 1 15.75 15.75
Waist Slab 2 3.00 6.00
Store Below Landing 1 4.85 4.85
Staircase/Landing 1 12.94 12.94
Column 4 2.25 9.00
Corridor 2 3.85 7.70

First floor plan


Room 2 21.35 42.70
Staircase Lobby 2 1.77 3.54
Waist Slab 2 3.00 6.00
Staircase/Landing 1 12.94 12.94
Corridor 2 4.53 9.05

Second Floor Plan 0.00


Room 2 21.35 42.70
Staircase Lobby 2 1.77 3.54
Corridor 2 4.53 9.05
Total 228.46 rm

5.3 25mm Terrazo Finishing


For In-built Furniture
Bench 2 2.40 0.50 2.40
Total 2.40 sq.m

6 Roofing/ Terracing Works


6.1 Metal Works
Truss 1 3,545.29
Total of Truss Total 3,545.29 k.g

6.2 CGI Sheet Roofing


Total Area 2 17.90 5.74 205.49
Total 205.50 sq.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
6.3 CGI Ridge
Top 1 17.90 17.90
Total 17.90 r.m

6.4 GI Facia(Eaves) Length (WxT) Density


Grid 1,3/AC 2 17.90 0.00031 7850 87.68
Grid A,D/1-3 4 5.74 0.00031 7850 56.23
Total 143.91 kgs.

6.5 Cement Board For False Ceiling


Backward and front slope of roof 2.00 15.95 1.18 37.64
Side Slope of Roof 4.00 5.65 0.97 21.92
Classroom 2.00 5.70 5.70 64.98
Staircase 1.00 5.70 3.20 18.24
Corridor 2.00 5.70 2.20 25.08
1.00 3.20 2.20 7.04
Total 174.90 Sq.m

7 PLASTER/PAINTING WORKS
7.1 Internal Plaster
7.1.1 Internal Plaster on Wall (1:6)
Ground Floor
Classroom 2.00 23.15 2.91 134.73
Staircase 1.00 14.67 2.91 42.69
Store Below Landing 1.00 2.50 1.25 3.11
2.00 0.31 1.25 0.78
2.00 0.69 1.44 1.98
2.00 1.44 1.63 4.69
Pedestal 4.00 1.25 0.25 1.25
4.00 0.50 0.25 0.50
Column
Grid 2A,2D 2.00 0.35 0.68 0.47
Grid 2B,2C 2.00 0.98 0.68 1.32

Grid 2A,2D 2.00 0.45 2.20 1.98


Grid 2B,2C 2.00 1.08 2.20 4.73
Deductions
W1 -8 1.10 1.13 -4.95
V1 -8 1.10 0.53 -2.31
W3 -1 1.50 0.37 -0.28
D1 -4 1.10 2.48 -5.45
D3 -2 1.00 1.55 -1.55

First Floor
Classroom 2.00 23.15 2.91 134.73

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Staircase 1.00 14.67 2.91 42.69
Column
Grid 2A,2D 2.00 0.45 2.91 2.62
Grid 2B,2C 2.00 1.08 2.91 6.26

Deductions
W1 -8 1.10 1.13 -4.95
V1 -8 1.10 0.53 -2.31
W2 -1 1.50 1.00 -0.75
D1 -4 1.10 2.48 -5.45

Second Floor
Classroom 2.00 23.15 3.00 138.90
Staircase 1.00 14.67 3.00 44.01
Column
Grid 2A,2D 2.00 0.45 3.00 2.70
Grid 2B,2C 2.00 1.08 3.00 6.45
Deductions
W1 -8 1.10 1.13 -4.95
W2 -1 1.50 1.00 -0.75
V2 -8 1.10 0.65 -2.86
D2 -4 1.10 2.60 -5.72
Total 534.33 sq.m

7.1.2 Internal Plaster on Ceiling (1:4)


Ground floor
Classroom 1 4 2.73 2.73 29.70
Classroom 2 4 2.73 2.73 29.70
Corridor 4 2.73 2.20 23.98
1 3.20 2.20 7.04
Staircase Area 1 3.20 0.88 2.80
Secondary Beam
Along Grid A1-C1 2 7.65 0.60 9.18
Along Grid 1a 2 5.77 0.60 6.92
Along Grid 1b 1 3.20 0.60 1.92
Below staircase
Waist slab 1 3.35 1.50 5.03
Landing 1 1.94 1.50 2.90
1 1.47 1.70 2.49
First floor
Classroom 3 4 2.73 2.73 29.70
Classroom 4 4 2.73 2.73 29.70
Corridor 4 2.73 2.20 23.98
1 3.20 2.20 7.04
Staircase Area 1 3.20 0.88 2.80

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Secondary Beam
Along Grid A1-C1 2 7.65 0.60 9.18
Along Grid 1a 2 5.70 0.60 6.84
Along Grid 1b 1 3.20 0.60 1.92

Below staircase
Waist slab 1 3.35 1.50 5.03
Landing 1 1.94 1.50 2.90
1 1.47 1.70 2.49
Second floor
Truss Beam
Classroom 4 4 5.55 0.40 8.88
Classroom 5 4 5.55 0.40 8.88
Corridor; Along grid 2 , ( A-B) and (C-D) 2 5.55 0.40 4.44
Corridor; Along grid 2 , ( B-C) 1 3.05 1.10 3.36
Corridor; Along grid 3 , ( A-B), (B-C) and (C-
D) 1 14.15 0.70 9.91
Corridor; Along grid A, B, C and D; (2-3) 4 2.20 1.10 9.68
Total 288.40 sq.m

7.1.3 External Plaster


Outer Plaster
Beam Plaster
Plinth Beam
Along grid 1 1 14.15 0.45 6.37
Along grid A & D 1 5.55 0.45 2.50

First Floor Level


Main Beam(300 x 525)
Along grid 1 1.00 11.10 0.53 5.83
Grid 1-BC 1.00 3.05 0.65 1.97
Landing Beam 1.00 3.05 0.56 1.71
Along grid 3 1.00 14.15 0.83 11.67
Along grid A and D 2.00 7.60 0.53 7.98

Second Floor Level


Main Beam(300 x 525)
Along grid 1 1.00 14.15 0.53 7.43
Landing Beam 1.00 3.05 0.38 1.16
Along grid 3 1.00 14.15 0.83 11.67
Along grid A and D 2.00 7.60 0.53 7.98

Truss Level
Main Beam(300 x 400)
Along grid 1 1.00 14.15 0.40 5.66
Along grid 3 1.00 14.15 0.40 5.66

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along grid A and D 2.00 7.60 0.40 6.08

Column Plaster
Upto Plinth Level
Along grid 1
Grid 1A,1D 2.00 1.10 0.45 0.99
Grid 1B,1C 2.00 0.65 0.45 0.59
Along grid 2
Grid 2A,2D 2.00 0.55 0.45 0.50
Along grid 3
Along grid 3A 1.00 0.08 0.38 0.03
1.00 0.45 0.40 0.18
Grid 3B 1.00 0.08 0.15 0.01
Grid 3C 1.00 0.60 0.15 0.09
Grid 3D 1.00 1.05 0.15 0.16
Upto Sill Level
Along grid 1
Grid 1A,1D 2.00 0.90 0.68 1.22
Grid 1B,1C 2.00 0.45 0.68 0.61
Along grid 2
Grid 2A,2D 2.00 0.55 0.68 0.74
Ground Floor
Along grid 1
Grid 1A,1D 2.00 1.10 2.33 5.12
Grid 1B,1C 2.00 0.65 2.33 3.02
Along grid 2
Grid 2A,2D 2.00 0.65 2.33 3.02
Along grid 3
Grid 3A,3D 2.00 1.05 3.00 6.30
2.00 0.75 2.88 4.31
Grid 3B,3C 2.00 1.20 2.88 6.90
2.00 0.60 3.00 3.60
First Floor
Along grid 1
Grid 1A,1D 2.00 1.10 2.33 5.12
Grid 1B,1C 2.00 0.65 2.33 3.02
Along grid 2
Grid 2A,2D 2.00 0.65 2.33 3.02
Along grid 3
Grid 3A,3D 2.00 1.05 3.00 6.30
2.00 0.75 2.88 4.31
Grid 3B,3C 2.00 1.20 2.88 6.90
2.00 0.60 3.00 3.60
Second Floor
Along grid 1
Grid 1A,1D 2.00 1.10 2.33 5.12

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Grid 1B,1C 2.00 0.65 2.33 3.02
Along grid 2
Grid 2A,2D 2.00 0.65 2.33 3.02
Along grid 3
Grid 3A,3D 2.00 1.05 3.00 6.30
2.00 0.75 2.88 4.31
Grid 3B,3C 2.00 1.20 2.88 6.90
2.00 0.60 3.00 3.60

Plaster in Outer Wall


Ground floor
Along grid A,D/(1-2) 2 5.55 2.33 25.81
Along grid 1 1 11.10 2.33 25.81
1 3.05 2.02 6.16
Along grid 2 1 10.80 2.33 25.11

First floor level


Along grid A,D 2 5.55 2.33 25.81
Along grid 1 1 11.10 2.33 25.81
1 3.05 2.05 6.24
Along grid 2 1 10.80 2.33 25.11

Second floor level


Along grid A,D 2 5.55 2.45 27.20
Along grid 1 1 11.10 2.45 27.20
1 3.05 2.53 7.70
Along grid 2 1 10.80 2.45 26.46
Deduction for doors and windows
Ground floor plan
W1 -8 1.10 1.13 -9.90
V1 -8 1.10 0.53 -4.62
W3 -1 1.50 0.37 -0.56
D1 -4 1.10 2.33 -10.23
First floor plan
W1 -8 1.10 1.13 -9.90
V1 -8 1.10 0.53 -4.62
W2 -1 1.50 1.00 -1.50
D1 -4 1.10 2.33 -10.23
Second floor plan
W1 -8 1.10 1.13 -9.90
V2 -8 1.10 0.65 -5.72
W2 -1 1.50 1.00 -1.50
D2 -4 1.10 2.45 -10.78

Outer Steps
Grid 2A,2D 2.00 1.03 0.45 0.92

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Grid 3A 1.00 0.93 0.45 0.42
Steps Edge 3.00 0.60 0.45 0.81
For Ramp
Top-3B 1.00 1.33 0.25 0.33
Top 3AB 1.00 6.47 0.13 0.81
Front 3-AB 1.00 1.60 0.60 0.96
1.00 5.10 0.38 1.91
Inner 1.00 7.52 0.15 1.13
Side-3B 1.00 1.33 0.60 0.80
For Bench
Top 2.00 2.40 0.50 2.40
Edge 2.00 5.80 0.13 1.45
Total 372.47 sqm

7.2 Painting Works


7.2.1 Distemper Painting Works
As per Internal plaster on wall 1.00 534.33 Area 534.33
As per internal plaster on ceiling 1.00 288.40 Area 288.40
False Ceiling 1.00 174.90 Area 174.90
Total 997.64 sq.m

7.2.2 Exterior Weather Coat Paint


Beam,Column and Walls Paint 1.00 372.47 Area 372.47
Total 372.47 sq.m

7.2.4 Enamel Painting


Doors Factor
D1 8 1.10 2.44 2.00 42.86
D2 4 1.10 2.56 2.00 22.53
D3 1 1.00 1.55 2.00 3.10
Collapsible Gate 1 3.05 2.48 2.00 15.10
Window 2.00
W1 24 1.10 1.13 2.00 59.40
W2 2 1.50 1.00 2.00 6.00
V1 16 1.10 0.53 2.00 18.48
V2 8 1.10 0.65 2.00 11.44
Window Grill
W1 24 1.01 1.04 25.09
W2 2 1.41 0.91 2.57
W3 1 1.50 0.37 0.56
V1 16 1.01 0.44 7.03
V2 8 1.01 0.56 4.52
Total 218.67 sq.m

8 MISCELLANOUS
8.2 Cement Board

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Partition
Above Side Walls 1.00 9.73 1.58 15.38
Total 15.39 sq.m

8.3 Railing
Total
Staircase Railing Kg/m Total
No. Length (m) Length
Horizontal ISNB 40 M 1 18.40 18.40 3.61 66.42
Vertical 38 mm Square Pipe 14 0.86 12.04 3.14 37.81
Horizontal 25mm Square Pipe 4 17.35 69.40 0.85 58.99
Balcony Railing
Horizontal ISNB 40 M 2 18.25 36.50 3.61 131.77
Horizontal ISNB 32 M 4 16.40 65.60 3.14 205.98
Vertical ISNB 40 M 34 1.08 36.72 3.61 132.56
Vertical 25mm Square Pipe 236 0.82 193.52 0.85 164.49
Pedestal
ISNB 40M 8 1.70 13.60 3.61 49.10
ISNB 40M 8 2.05 16.40 3.61 59.20
Base plate 69 0.00009375 0.01 7850 50.78
12 mm dia. Anchor Bolt, Nut 276 0.13 35.88
Total 992.98 k.gs

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-6C(S)-B
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Weight Length Total


S.N. Particulars Size Thickness Qty Total wt. Remarks
Per Metre (m) Length
1 TOP CHORD PIPE 50MM MID 5.03 5.641 12 67.69 340.49
2 BOTTOM CHORD PIPE 40MM MID 3.56 4.378 12 52.54 187.03
3 VERTICAL BRACING.1 40MM MID 3.56 1.351 12 16.21 57.71
4 VERTICAL BRACING.2 40MM MID 3.56 1.088 12 13.05 46.47
5 VERTICAL BRACING.3 40MM MID 3.56 0.825 12 9.90 35.24
6 VERTICAL BRACING.4 40MM MID 3.56 0.419 12 5.03 17.90
7 DIGONAL BRACING.1 32 MM MID 3.1 1.328 12 15.94 49.40
8 DIGONAL BRACING.2 32MM MID 3.1 1.123 12 13.48 41.78
9 DIGONAL BRACING.3 32MM MID 3.1 1.272 12 15.26 47.32
10 PURLIN 1 65MM MID 6.42 3.000 48 144.00 924.48
11 PURLIN 2 65MM MID 6.42 3.500 12 42.00 269.64
12 RUNNER 1 40MM MID 3.56 3.000 24 72.00 256.32
13 RUNNER2 40MM MID 3.56 3.500 8 28.00 99.68
15 END PURLIN 65MM MID 6.42 1.125 24 27.00 173.34
16 CROSS BRACING 40MM MID 3.56 1.380 32 44.16 157.21
17 BASE PLATE 250X250 10MM 4.9 18 88.20
18 BASE PLATE STIFFNER(L) 127X250 10MM 2.49 24 59.76
19 BASE PLATE STIFFNER(S) 50X75 10MM 0.29 24 6.96
20 PURLIN CLITE 200X90 10MM 1.41 144 203.04
21 TRUSS CLITE 200X90 10MM 1.41 72 101.52
22 RUNNER CLITE 175X70 10MM 0.96 40 38.40
23 R.CONNECTION BOX PLATE 175X160 10MM 2.19 12 26.28
24 TRUSS JOINT CLITE(C) 175X175 10MM 2.4 16 38.40
25 TRUSS JOINT CLITE(O) 175X175 10MM 2.4 8 19.20
26 STIPNER1. 100X63 10MM 0.49 16 7.84
27 STIPNER2. 63X63 10MM 0.31 64 19.84
28 WIND TIE PLATE 380X80 6MM 1.43 16 22.88
29 BRACING TIE STEPER 100X100 6MM 0.47 16 7.52
30 CROSS BRACING PIPE CLITE 165X80 6MM 0.62 64 39.68
31 TEMP PLATE 250X250 10MM 4.9 18 88.20
32 ANCHOR BOLT 16MM 1.58 0.45 72 32.40 51.19
33 NUT BOLT(16X60) 16MM 1.58 0.06 148 14.03
34 NUT BOLT(16X50) 16MM 1.58 0.05 48 3.79
35 NUT BOLT(16X40) 16MM 1.58 0.04 72 4.55
Total 3545.29 Kgs.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-6C(S)-B
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Cut Total
Dia. of No. of
S. No. Description No. Length Length Wt/m (Kg) Weight (Kg) Bar Shape
Bar (mm) Bars
(m) (m)
A Foundation for footing
1.1 Footing (F1,1500 X1500) 4
X- direction 12 10 1.56 62.40 0.89 55.54 0.08 0.08
Y- direction 12 10 1.56 62.40 0.89 55.54 1.4
1.2 Footing (F2,2200 X 2200) 2
X- direction 12 15 2.26 67.80 0.89 60.34 0.08 0.08
Y- direction 12 15 2.26 67.80 0.89 60.34 2.1
1.3 Footing (F3, 2500 X 2500) 4
X- direction 12 17 2.56 174.08 0.89 154.93 0.08 0.08
Y- direction 12 17 2.56 174.08 0.89 154.93 2.4
1.4 Footing (F4, 2800 X 2800) 4
X- direction 12 19 2.86 217.36 0.89 193.45 0.08 0.08
Y- direction 12 19 2.86 217.36 0.89 193.45 2.7

B Column
1 Grid 1 (A & D) 2 20mm ɸ 20mm ɸ
Main Bar 20 6 4.22 50.63 2.47 125.04
20 6 7.26 87.08 2.47 8.00
3.40 6.44

0.125 0.125
0.699 0.699
2 Grid 1(B & C) 2 25mm ɸ 25mm ɸ
Main Bar 25 6 4.82 57.83 3.86 223.20
25 6 7.82 93.83 3.86 362.16
3.70 6.70

0.125 0.125
0.999 0.999

3 Grid 2 (A) 1 20mm ɸ 20mm ɸ


Main Bar 20 6 4.22 25.31 2.47 62.52
20 6 7.26 43.54 2.47 107.54
3.40 6.44

0.125 0.125

4 Grid 2(B,C & D) 3


Main Bar 25 4 7.82 93.83 3.86 362.16 25mm ɸ 20mm ɸ
20 2 7.22 43.31 2.47 106.98
20 6 4.22 75.94 2.47 187.57
6.70 6.4

0.125 0.125
0.999 0.699
5 Grid 3 (A,B,C & D) 4
Main Bar 20 6 4.22 101.25 2.47 250.09 20mm ɸ 20mm ɸ
20 6 7.26 174.15 2.47 430.15

3.40 6.44

0.125 0.125
0.699 0.699
6 Stiruups 0.37
For 12 column 12 8 18 1.64 344.40 0.40 137.76 0.08 0.37
8 18 1.18 247.80 0.40 99.12 0.37 0.14 0.08
8 18 1.18 247.80 0.40 99.12

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
7 For Lower Tie Beam 8.13
7.1 Grid 1,2 & 3 3 0.44 8.42 0.44
Top Bar 12 2 8.86 53.16 0.89 47.31
12 2 8.57 51.42 0.89 45.76
12 1 11.35 34.05 0.89 30.30 2.97 2.97
12 2 3.41 20.46 0.89 18.21
Bottom Bar 12 3 12.00 108.00 0.89 96.12 0.44 11.35 0.44
12 3 5.45 49.05 0.89 43.65
Stirrups
Grid 1,2 & 3 3 8 125 1.06 397.39 0.40 158.96 0.44 11.56 5.01 0.44
0.72
7.2 Grid A,B,C & D 4
Top Bar 12 3 9.73 116.76 0.89 103.92
Bottom Bar 12 3 9.73 116.76 0.89 103.92
Stirrups 0.44 8.85 0.44
Grid A,B,C & D 4 8 71 1.06 300.33 0.40 120.13
0.44 8.85 0.44
0.2
0.08

0.25

8 Plinth tie beam


8.1 Grid 1,2 & 3 3 3.64 3.64
Top Bar 16 1 10.51 31.53 1.59 50.13
16 2 4.36 26.16 1.59 41.59 0.72 10.51 0.72
16 2 9.15 54.91 1.59 87.31
16 2 9.12 54.72 1.59 87.00
Bottom Bar 16 2 8.89 53.34 1.59 84.81 8.43 8.4
16 4 5.17 62.04 1.59 98.64 0.72 0.72
20 2 12.00 72.00 2.47 177.84
20 2 4.15 24.90 2.47 61.50
20 2 4.15 24.90 2.47 61.50 0.72 4.45 8.89 4.45 0.72

Stirrups 3 12 143 1.69 722.48 0.89 643.00


Torsion bar 16 2 16.67 100.02 1.59 159.03 3.15 3.15
1 1
8.2 Grid A,B,C,D 4 12
Top bar 16 3 10.31 123.72 1.59 196.71 0.72 8.87 0.72
Bottom bar 20 4 10.87 173.92 2.47 429.58 8.87
Stirrups 4 12 77 1.69 520.52 0.89 463.26 1 0.25 1
Torsion bar 16 2 8.71 69.68 1.59 110.79 0.12
0.475

8.3 Extra Bar


Grid 1 & Grid 2 2 1.9
Grid A 1 20 2 2.98 11.90 2.47 29.39 1 0.075

Grid B,C 2 20 2 7.10 56.80 2.47 140.30 6.95


0.075 0.075
Grid D 1 25 2 3.55 14.20 3.86 54.81
2.1
1.35 0.1
Grid 3 1
Grid A 1 16 2 2.70 5.39 1.59 8.57 1.9
0.72 0.075
Grid B,C 2 16 2 3.20 12.80 1.59 20.35
3.05
0.075 0.075
Gird D 1 16 2 2.70 5.39 1.59 8.57
1.9
0.72 0.075
Grid A,B,C,D, 4
Grid 1 1 25 2 3.55 28.40 3.86 109.62 2.1

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1.35 0.1
Grid 2,3 2 25 2 6.05 96.80 3.86 373.65
4.6
1.35 0.1

0.37
9 Ground floor column 0.08 0.37
Grid 1,(A &D) 2 20 6 7.20 86.40 2.47 213.41 0.37 0.14 0.08
Grid 1 (B &C) 2 25 6 7.50 90.00 3.86 347.40
Grid 2 (A,B,C,D) 4 20 2 7.20 57.60 2.47 142.27
25 4 7.50 120.00 3.86 463.20
Grid 3 (A) 1 20 6 7.20 43.20 3.86 166.75
Grid 3 (B,C,D) 3 20 6 5.72 103.01 2.47 254.42

Stiruups
For 12 column 12 8 30 1.64 590.40 0.40 236.16 20mmɸ 25mmɸ
8 30 1.18 424.80 0.40 169.92
8 30 1.18 424.80 0.40 169.92

7.2 7.5
10 Stair Case GF
10.1 First Flight 3.35 1.46
Top Main Bar 12 12 7.26 87.11 0.89 77.53 1.67 0.31
Bottom Main Bar 12 12 2.74 32.89 0.89 29.27 0.45
Top Distribution Bar 10 16 1.46 23.36 0.62 14.48 1.2
Bottom Distribution Bar 10 42 1.46 61.32 0.62 38.02 0.3 1.24
Extra Bar 12 12 2.00 24.00 0.89 21.36
10.2 Landing 1
Bottom bar in first flight 12 12 2.90 34.80 0.89 30.97 1
Top Distribution Bar 10 8 1.46 11.68 0.62 7.24
Bottom Distribution Bar 10 12 3.16 37.92 0.62 23.51 3.16
Top Distribution Bar 10 12 3.16 37.92 0.62 23.51 1.69
Extra Bar 12 12 2.00 24.00 0.89 21.36 1 0.21
10.3 Second Flight
Top Main Bar 12 12 7.31 87.74 0.89 78.09 0.82 3.402
Bottom main Bar 12 12 3.30 39.60 0.89 35.24 0.45
Bottom Distribution Bar 10 23 1.46 33.09 0.62 20.52 2.32 0.31
Top Distribution Bar 10 13 1.46 19.47 0.62 12.07 1.2
Top main bar in forst floor level 12 12 2.38 28.55 0.89 25.41 1.89 0.21
Extra Bar 12 22 2.00 44.00 0.89 39.16
1.46
10.4 Nosing Bar 10 20 1.46 29.20 0.62 18.10
10.5 Nosing ties 0.26
18 8 5 0.67 60.66 0.40 24.26 0.22
0.15

11 Ground floor beam


11.1 Grid 1,2 & 3 ( Main Beam) 3 3.64 3.64
Top Bar 16 1 10.51 0.00 1.59 0.00
16 4 4.36 0.00 1.59 0.00 0.72 10.51 0.72
16 2 9.15 0.00 1.59 0.00
16 2 9.12 0.00 1.59 0.00
Bottom Bar 16 2 12.00 0.00 1.59 0.00 0.72 8.43 8.4 0.72
16 4 3.61 0.00 1.59 0.00
20 2 10.87 0.00 2.47 0.00
20 4 4.20 0.00 2.47 0.00
0.72 2.89 2.89 0.72
Stirrups 12
Grid 1,2 & 3 3 10 142 1.65 700.43 0.62 434.26
Torsion bar 3 16 2 16.67 100.02 1.59 159.03 1 3.2 10.87 3.2 1

16.67
11.2 Grid A,B,C,D ( Main Beam) 4 0.25
Top bar 16 3 10.29 123.48 1.59 196.33 0.1

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Bottom bar 20 4 10.87 173.92 2.47 429.58 0.475
Stirrups
Grid A,B,C & D 4 10 76 1.65 501.60 0.62 310.99
Torsion bar 4 16 2 8.87 70.96 1.59 112.83
0.71 0.71
8.87

1 1
8.87

8.87
11.3 Grid 1a (Secondary Beam) 2
Top bar 16 3 7.94 0.00 1.59 0.00 0.2
Bottom bar 16 3 7.94 0.00 1.59 0.00 0.8
Stirupps 8 49 1.31 0.00 0.40 0.00 0.375

0.87 6.2 0.87


11.4 Grid 1A &1C (Secondary Beam) 2
Top bar 16 3 10.44 0.00 1.59 0.00
Bottom bar 16 3 10.44 0.00 1.59 0.00 0.87 8.7 0.87
Stirupps 8 70 1.31 0.00 0.40 0.00

11.5 Grid 1b (Secondary Beam) 1 0.6 3.53 0.6


Top bar 12 3 4.73 0.00 0.89 0.00
Bottom bar 12 4 4.73 0.00 0.89 0.00
Stirupps 8 27 1.31 0.00 0.40 0.00
11.6 Extra Bar
11.6.1 Grid 1 & Grid 2 2 1.9
Grid A 1 20 2 2.98 11.90 2.47 29.39 1 0.075

Grid B,C 2 20 2 7.10 56.80 2.47 140.30 6.95


0.075 0.075
Grid D 1 25 2 3.55 14.20 3.86 54.81
2.1
1.35 0.1
11.6.2 Grid 3 1
Grid A 1 16 2 2.70 5.39 1.59 8.57 1.9
0.72 0.075
Grid B,C 2 16 2 3.20 12.80 1.59 20.35
3.05
0.075 0.075
Gird D 1 16 2 2.70 5.39 1.59 8.57
1.9
0.72 0.075
11.6.3 Grid A,B,C,D, 4
Grid 1 1 25 2 3.55 28.40 3.86 109.62 2.1
1.35 0.1
Grid2,3 2 25 2 6.05 96.80 3.86 373.65
4.6
1.35 0.1

0.96 0.96

11.7 Bent up bar in primary and


secondary beam junction 16 24 3.01 72.24 1.59 114.86 0.42

0.25
12 Landing Beam 3.87
Top bar 16 3 4.02 12.06 1.59 19.18 0.075 0.075
Bottom bar 16 3 4.02 12.06 1.59 19.18 0.2
Stirrups 1 8 31 1.22 37.82 0.40 15.13 0.8
0.33

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
13 GF Slab Rebar 0.475 Type A 0.55
Grid A-B and C-D 2 0.085 0.085
Short Span 8.7
Type A 8 20 9.90 395.80 0.40 158.32
Type B 8 20 10.03 401.08 0.40 160.43 Type B

0.475 0.55
0.085 0.33 0.085
Long Span(upto 1b) 2
Type A 8 19 7.47 0.00 0.40 0.00 0.55 Type A 0.55
Type B 8 19 7.54 0.00 0.40 0.00 0.085 0.085
6.2
Grid 1b-3 1 Type B
Main bar 0.55 1.35 0.55
Type A 8 12 17.45 209.40 0.40 83.76 0.085 0.33
Type B 8 12 17.71 212.57 0.40 85.03
0.55 Type A 0.55
Grid B-C 1 0.085 0.48
Main bar 0.55 Type B
Type A 8 11 4.30 47.25 0.40 18.90 0.085 0.33
Type B 8 11 4.63 50.88 0.40 20.35

Distribution Bar 6
Along Grid 1 2 8 2 6.00 24.00 0.40 9.60
Along Grid 1a 2 8 13 6.00 156.00 0.40 62.40 15.98
Along Grid 2 2 8 12 15.98 383.52 0.40 153.41
Along Grid 3 1 8 2 15.98 31.96 0.40 12.78
Along Grid A1- C1 2 8 13 8.50 221.00 0.40 88.40
Along Grid B and C 2 8 5 8.50 85.00 0.40 34.00 8.5
Along Grid between B and C 2 8 7 3.75 52.50 0.40 21.00
3.75
Negative bar
Along Grid A1-C1 2 8 14 2.16 60.48 0.40 24.19 0.055 2.05 0.055
Along Grid 1a( A-B and C-D) 2 8 11 2.16 47.52 0.40 19.01
Along Grid 2( A-B and C-D) 2 8 11 2.06 45.32 0.40 18.13 0.055 1.95 0.055
along Grid 2 (B-C) 1 8 4 2.17 8.69 0.40 3.48
0.055 2.06 0.055

1 First Floor Column


Grid 1,(A &D) 2 16 6 6.50 78.015 2.47 192.70
Grid 1 (B &C) 2 20 6 6.78 81.375 2.47 201.00
Grid 2 (A,B,C,D) 4 20 6 6.78 162.75 2.47 401.99
Grid 3 (A) 1 20 6 6.78 40.68 2.47 100.48
Grid 3 (B,C,D) 3 16 6 6.50 117.0225 2.47 289.05 16mmɸ 20mmɸ
Stiruups
For 12 column 12 8 30 1.64 590.4 0.4 236.16
8 30 1.18 424.8 0.4 169.92
8 30 1.18 424.8 0.4 169.92 6.5 6.78

2 Stair Case FF
2.1 First Flight 3.35 1.46
Top Main Bar 12 12 7.26 87.108 0.89 77.53 1.67 0.31
Bottom Main Bar 12 12 2.74 32.892 0.89 29.27 0.45
Top Distribution Bar 10 16 1.46 23.36 0.62 14.48 1.2
Bottom Distribution Bar 10 42 1.46 61.32 0.62 38.02 0.3 1.24
Extra Bar 12 12 2 24 0.89 21.36
2.2 Landing 1
Bottom bar in first flight 12 12 2.90 34.8 0.89 30.97 1
Top Distribution Bar 10 8 1.46 11.68 0.62 7.24
Bottom Distribution Bar 10 12 3.16 37.92 0.62 23.51 3.16
Top Distribution Bar 10 12 3.16 37.92 0.62 23.51 1.69
Extra Bar 12 12 2 24 0.89 21.36 1 0.21
2.3 Second Flight
Top Main Bar 12 12 7.31 87.744 0.89 78.09 0.82 3.402
Bottom main Bar 12 12 3.3 39.6 0.89 35.24 0.45

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Bottom Distribution Bar 10 23 1.46 33 0.62 20.52 2.32 0.31
Top Distribution Bar 10 13 1.46 19.47 0.62 12.07 1.2
Top main bar in forst floor level 12 12 2.38 28.548 0.89 25.41 1.89 0.21
Extra Bar 12 22 2 44 0.89 39.16
1.46
2.4 Nosing Bar 10 20 1.46 29.2 0.62 18.10
2.5 Nosing ties 0.26
18 8 5 0.674 60.66 0.4 24.26 0.22
0.15

3 Second Floor beam


3.1 Grid 1,2 & 3 ( Main Beam) 3 3.64 3.64
Top Bar 16 1 10.51 31.53 1.59 50.13
16 4 4.36 52.32 1.59 83.19 0.72 10.51 0.72
16 2 9.15 54.9 1.59 87.29
16 2 9.12 54.72 1.59 87.00
Bottom Bar 16 2 12 72 1.59 114.48 0.72 8.43 8.4 0.72
16 4 3.61 43.26 1.59 68.78
20 2 10.87 65.22 2.47 161.09
20 4 4.2 50.4 2.47 124.49
0.72 2.89 2.89 0.72
Stirrups 12
Grid 1,2 & 3 3 10 142 1.65 700.43 0.62 434.26
Torsion bar 3 16 2 16.67 100.02 1.59 159.03 1 3.2 10.87 3.2 1

16.67
3.2 Grid A,B,C,D (Main Beam) 4 0.25
Top bar 16 3 10.29 123.48 1.59 196.33 0.1
Bottom bar 20 2 10.87 86.96 2.47 214.79 0.475
16 2 10.29 82.32 1.59 130.89
Stirrups
Grid A,B,C & D 4 10 76 1.65 501.60 0.62 310.99
Torsion bar 4 16 2 8.87 70.96 1.59 112.83
0.71 0.71
8.87

1 1
8.87

8.87
3.3 Grid 1a (Secondary Beam) 2
Top bar 16 3 7.94 47.64 1.59 75.75 0.2
Bottom bar 16 3 7.94 47.64 1.59 75.75 0.8
Stirupps 8 49 1.31 128.38 0.4 51.35 0.375

0.87 6.2 0.87


3.4 Grid 1A &1C (Secondary Beam 2
Top bar 16 3 10.44 62.64 1.59 99.60
Bottom bar 16 3 10.44 62.64 1.59 99.60 0.87 8.7 0.87
Stirupps 8 70 1.31 182.09 0.4 72.84

3.5 Grid 1b (Secondary Beam) 1 0.6 3.53 0.6


Top bar 12 3 4.73 14.19 0.89 12.63
Bottom bar 12 4 4.73 18.92 0.89 16.84
Stirupps 8 27 1.31 35.59 0.4 14.24

3.6 Extra Bar


Grid 1 & Grid 2 2 1.9
Grid A & D 2 20 2 2.98 23.8 2.47 58.79 1 0.075

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Grid B,C 2 20 2 7.10 56.8 2.47 140.30 6.95
0.075 0.075
Grid 3 1
Grid A 1 16 2 2.70 5.39 1.59 8.57 1.9
0.72 0.075
Grid B,C 2 16 2 3.20 12.8 1.59 20.35
3.05
0.075 0.075
Grid D 1 16 2 2.70 5.39 1.59 8.57
1.9
0.72 0.075
Grid A,B,C,D, 4

Grid 1 1 20 2 3.00 24 2.47 59.28 1.9


1 0.1
Grid2,3 2 16 2 5.22 83.52 1.59 132.80
4.4
0.72 0.1

0.96 0.96
Bent up bar in primary and 16 24 3.01 72.24 1.59 114.86
3.7 secondary beam junction 0.42

0.25
4 Landing Beam 3.87
Top bar 16 3 4.02 12.06 1.59 19.18 0.075 0.075
Bottom bar 16 3 4.02 12.06 1.59 19.18 0.2
Stirrups 1 8 31 1.22 37.82 0.4 15.13 0.8
0.33

5 FF Slab Rebar 0.475 Type A 0.55


5.1 Grid A-B and C-D 2 0.085 0.085
Short Span 8.7
Type A 8 20 9.90 395.80 0.4 158.32
Type B 8 20 10.03 401.08 0.4 160.43 Type B

0.475 0.55
0.085 0.33 0.085
Long Span(upto 1b) 2
Type A 8 19 7.47 283.86 0.4 113.54 0.55 Type A 0.55
Type B 8 19 7.54 286.37 0.4 114.55 0.085 0.085
6.2
5.2 Grid 1b-3 1 Type B
Main bar 0.55 1.35 0.55
Type A 8 12 17.45 209.40 0.4 83.76 0.085 0.33
Type B 8 12 17.71 212.57 0.4 85.03
0.55 Type A 0.55
5.3 Grid B-C 1 0.085 0.48
Main bar 0.55 Type B
Type A 8 11 4.295 47.25 0.4 18.90 0.085 0.33
Type B 8 11 4.625 50.88 0.4 20.35

Distribution Bar 6
Along Grid 1 2 8 2 6 24.00 0.4 9.60
Along Grid 1a 2 8 13 6 156.00 0.4 62.40 15.98
Along Grid 2 2 8 12 15.98 383.52 0.4 153.41
Along Grid 3 1 8 2 15.98 31.96 0.4 12.78
Along Grid A1- C1 2 8 13 8.5 221.00 0.4 88.40
Along Grid B and C 2 8 5 8.5 85.00 0.4 34.00 8.5
Along Grid between B and C 2 8 7 3.75 52.50 0.4 21.00
3.75
Negative bar
Along Grid A1-C1 2 8 14 2.16 60.48 0.4 24.19 0.055 2.05 0.055
Along Grid 1a( A-B and C-D) 2 8 11 2.16 47.52 0.4 19.01

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along Grid 2( A-B and C-D) 2 8 11 2.06 45.32 0.4 18.13 0.055 1.95 0.055
Along Grid 2 (B-C) 1 8 4 2.17 8.69 0.4 3.48
0.055 2.06 0.055
6 Second Floor Column
Grid 1,(A &D) 2 16 6 3.47 41.64 2.47 102.85
Grid 1 (B &C) 2 20 6 3.75 45 2.47 111.15
Grid 2 (A) 1 16 6 3.47 20.82 2.47 51.43
Grid 2 (A,B,C,D) 3 20 6 3.75 67.5 2.47 166.73
Grid 3 (A) 1 16 6 3.47 20.82 2.47 51.43 16mmɸ 20mmɸ
Grid 3 (B,C,D) 3 20 6 3.75 67.5 2.47 166.73
Stiruups
For 12 column 12 8 31 1.64 610.08 0.4 244.03
8 31 1.18 438.96 0.4 175.58 6.5 6.78
8 31 1.18 438.96 0.4 175.58

7 Second Floor Truss beam


7.1 Grid 1,2 & 3 ( Main Beam) 3 3.64 3.64
Top Bar 16 1 10.51 31.53 1.59 50.13
16 2 4.36 26.16 1.59 41.59 0.72 10.51 0.72
16 2 9.15 54.9 1.59 87.29
16 2 9.12 54.72 1.59 87.00
Bottom Bar 16 2 12 72 1.59 114.48 0.72 8.43 8.4 0.72
16 4 3.61 43.26 1.59 68.78
12 2 9.73 58.38 0.89 51.96
12 4 4.2 50.4 0.89 44.86
0.72 2.89 2.89 0.72
Stirrups 12
Grid 1,2 & 3 3 8 143 1.36 581.40 0.40 232.56 0.25
0.1
7.2 Grid A,B,C,D ( Main Beam) 4 0.475
Top bar 16 3 10.29 123.48 1.59 196.33
Bottom bar 12 2 9.73 77.84 0.89 69.28
16 2 10.29 82.32 1.59 130.89 0.71 0.71
Stirrups 8.87
Grid A,B,C & D 4 8 77 1.36 418.88 0.40 167.55 1 1
8.87
8 Lintel Bands
8.1 Ground floor level
Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51 0.075 0.075
At store 2 10 2 5.85 23.40 0.62 14.51 5.7
Tie Bar 0.075 0.075
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64 0.25
Along grid 1 2 8 38 0.40 30.40 0.40 12.16
Along grid 2 2 8 38 0.40 30.40 0.40 12.16
At store 2 8 38 0.40 30.40 0.40 12.16

8.2 First floor level


Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51
Tie Bar
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64
Along grid 1 2 8 38 0.40 30.40 0.40 12.16
Along grid 2 2 8 38 0.40 30.40 0.40 12.16

8.3 Second floor level


Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51
Tie Bar

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64
Along grid 1 2 8 38 0.40 30.40 0.40 12.16 0.075 0.075
Along grid 2 2 8 38 0.40 30.40 0.40 12.16 5.7

9 Sill Bands
9.1 Ground floor level
Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51 0.075 0.075
At store 2 10 2 5.85 23.40 0.62 14.51 5.7
Tie Bar 0.075 0.075
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64 0.25
Along grid 1 2 8 38 0.40 30.40 0.40 12.16
Along grid 2 2 8 38 0.40 30.40 0.40 12.16
At store 2 8 38 0.40 30.40 0.40 12.16

9.2 First floor level


Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51
Tie Bar
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64
Along grid 1 2 8 38 0.40 30.40 0.40 12.16
Along grid 2 2 8 38 0.40 30.40 0.40 12.16

9.3 Second floor level


Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51
Tie Bar
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64
Along grid 1 2 8 38 0.40 30.40 0.40 12.16 0.075 0.075
Along grid 2 2 8 38 0.40 30.40 0.40 12.16 5.7

10 Vertical Bands
10.1 Ground Floor 4
Main Bar 10 2 2.50 20.00 0.62 12.40
Tie Bar 8 17 0.40 27.20 0.40 10.88

10.2 First Floor 4


Main Bar 10 2 2.50 20.00 0.62 12.40
Tie Bar 8 17 0.40 27.20 0.40 10.88

10.3 Second Floor 4


Main Bar 10 2 2.50 20.00 0.62 12.40
Tie Bar 8 17 8.00 544.00 0.40 217.60

Total 24821.53
24.82 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Block : 3-6CS
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Site
S. No. Description G.F F.F S.F Quantity Unit Remarks
Development
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure 1.00 1.00 nos.
2 CABLES & WIRES
2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded
2.1 55.00 r.m
copper conductor wires

2.2 2 Nos 2.5 Sq.mm mutistranded copper conductor 51.00 r.m


wires + 1 Nos. 1.5sq mm multistranded Cu wire
B School Blocks
1 DISTRIBUTION BOARDS 1.00 1.00 1.00 3.00 nos.
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4
2.1 10.00 r.m
Sq mm Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point 3.00 13.00 12.00 13.00 41.00 pts.
3.2 Two Way Light Point 1.00 1.00 2.00 pts.
3.3 Ceiling Fan Point 4.00 4.00 pts.
4 6A Universal Pin Light Power Socket Wiring 12.00 12.00 4.00 28.00 pts.
5 Switch Socket Outlets
5.1 6A Universal Power Switch Socket 12.00 12.00 4.00 28.00 no.
7 Light Fixtures/Luminaires & Accessories
7.1 18 W LED Surface Mounted Square type 8.00 8.00 16.00 no.
7.2 18 W LED Recessed Mounted Square type 8.00 8.00 no.
7.3 12 W LED Surface Mounted Cylindrical type 4.00 5.00 9.00 no.
7.4 12 W LED Recessed Mounted Circular type 5.00 5.00 no.
7.5 7W LED Wall Light 1.00 1.00 no.
8 Pull Box 3.00 3.00 no.
9 External Post Top Light Pole 3.00 3.00 no.
10 Post Top External Light Fixtures 3.00 3.00 no.
11 Earthing & Lighting Protection
11.1 Chemical Earthing 3.00 3.00 no.
11.2 Earthing Bar 3.00 3.00 no.
12 Earthing Strip/Wires
12.1 25 x 3 mm GI strip 65.00 67.00 r.m
12.2 12 SWG Cu wire 15.00 16.00 r.m
13 Earth Test link 1.00 1.00 no.
C Solar PV System
1 Solar PV Panel 4.00 4.00 nos.
2 Tubular Deep Cycle Battery 2.00 2.00 nos.
3 Hybrid Inverter 1.00 1.00 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,2-4C(S)
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Breadth Height
S.No Description No. Length (m) Qty. Unit Remarks
(m) (m)
1 EARTH WORKS
1.1 Site Clearance 1 19.50 12.50 243.75
Soak Pit 1 8.55 Area 8.55
Total 252.30 sq.m

1.2 Earth Work Excavation


For Isolated Foundation
F1 4 1.70 1.70 1.50 17.34
F2 3 1.80 1.80 1.50 14.58
F3 3 2.10 2.10 1.50 19.85
F4 2 2.30 2.30 1.50 15.87

For Lower Tie Beam


Along Grid A 1 4.65 0.55 0.75 1.92
Along Grid B 1 4.45 0.55 0.75 1.84
Along Grid C 1 4.30 0.55 0.75 1.77
Along Grid D 1 4.65 0.55 0.75 1.92

Along Grid 1 1 9.80 0.55 0.75 4.04


Along Grid 2 1 8.80 0.55 0.75 3.63
Along Grid 3 1 10.40 0.55 0.75 4.29

For Drain 1 15.95 0.60 0.05 0.48


1 10.03 0.60 0.05 0.30
For side Slope 1 15.95 0.98 0.15 2.33

Outer Steps 1 12.45 0.70 0.15 1.31


1 2.50 0.70 0.15 0.26
Below Ramp slab 1 0.51 Area 1.30 0.66
Side support 1 6.75 0.45 0.45 1.37
Soak Pit small 1 4.15 Area 1.55 6.44
Total 100.20 cu.m

1.3 Earth Back Filling


Excavated earthwork 100.20
Boulder soling -14.65
PCC -7.32
RCC -28.76
Brick masonry work below plinth tie beam -6.28
Class room 2 5.70 5.70 0.18 11.37
Staircase 1 3.20 5.70 0.18 3.19
Corridoor 1 14.60 2.20 0.18 5.62
Below Ramp 1 1.40 1.30 0.14 0.25
Total 63.62 Cu.m

1.4 Boulder Soling


For Isolated Foundation
F1 4 1.40 1.40 0.20 1.57
F2 3 1.50 1.50 0.20 1.35
F3 3 1.90 1.90 0.20 2.17
F4 2 2.00 2.00 0.20 1.60
For Lower Tie Beam
Along Grid A 1 4.65 0.40 0.10 0.19
Along Grid B 1 4.45 0.40 0.10 0.18
Along Grid C 1 4.30 0.40 0.10 0.17
Along Grid D 1 4.65 0.40 0.10 0.19

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along Grid 1 1 9.80 0.40 0.10 0.39
Along Grid 2 1 8.80 0.40 0.10 0.35
Along Grid 3 1 10.40 0.40 0.10 0.42

Class Room 1 and 2 2 5.75 5.75 0.20 13.23


Corridor in front of class 1 and 2 2 5.75 2.25 0.20 5.18
Staircase 1 5.75 3.25 0.20 3.74
Corridor in front of Staircase 1 3.25 2.25 0.20 1.46
Below Ramp 1 6.75 1.33 0.20 1.79
1 1.33 0.45 0.10 0.06
1 6.75 0.45 0.10 0.30
Exterior Steps 1 12.45 0.70 0.10 0.88
1 2.50 0.70 0.10 0.18

For Drain 1 15.95 0.60 0.05 0.48


1 10.03 0.60 0.05 0.30
Inside of soak Pit 1 1.13 Area 2.00 2.26
Total 38.41 cu.m

1.5 Sand Filling


Periphery ot Soak pit 1 1.88 Area 1.32 2.49
Total 2.49 cu.m

2 CONCRETE WORKS
2.1 P.C.C. Works
2.1.1 P.C.C.(1:3:6) Works
Footing
For Isolated Foundation, F1 4 1.40 1.40 0.10 0.78
For Isolated Foundation, F2 3 1.50 1.50 0.10 0.68
For Isolated Foundation, F3 3 1.90 1.90 0.10 1.08
For Isolated Foundation, F4 2 2.00 2.00 0.10 0.80
For Lower Tie Beam
Along Grid A 1 4.65 0.40 0.05 0.09
Along Grid B 1 4.45 0.40 0.05 0.09
Along Grid C 1 4.30 0.40 0.05 0.09
Along Grid D 1 4.65 0.40 0.05 0.09

Along Grid 1 1 9.80 0.40 0.05 0.20


Along Grid 2 1 8.80 0.40 0.05 0.18
Along Grid 3 1 10.40 0.40 0.05 0.21
Total 4.28 cu.m

2.1.2 P.C.C.(1:2:4) Works


Class Room 1 and 2 2 5.75 5.75 0.08 4.96
Corridor in front of class 1 and 2 2 5.75 2.25 0.08 1.94
Staircase 1 5.75 3.25 0.08 1.40
Corridor in front of Staircase 1 3.25 2.25 0.08 0.55
Ramp 1 6.52 1.30 0.08 0.64

Exterior Steps 1 12.45 0.70 0.10 0.88


1 2.50 0.70 0.10 0.18
Total 10.54 cu.m

2.2 P.C.C For R.C.C. Works


A Foundation
Isolated footing
Rectangular Base
For Isolated Foundation, F1 4 1.40 1.40 0.20 1.57
For Isolated Foundation, F2 3 1.50 1.50 0.20 1.35
For Isolated Foundation, F3 3 1.90 1.90 0.20 2.17
For Isolated Foundation, F4 2 2.00 2.00 0.20 1.60

Inclined Part
For Isolated Foundation, F1 4 1.34 Area 0.25 1.34

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
For Isolated Foundation, F2 3 1.49 Area 0.25 1.11
For Isolated Foundation, F3 3 2.17 Area 0.25 1.62
For Isolated Foundation, F4 2 2.36 Area 0.25 1.18

B Beam
Footing beam(250x300)
Along grid 1,2,3 3 14.15 0.25 0.30 3.18
Along grid A,B,C,D 4 7.60 0.25 0.30 2.28

Tie beam(300 x 525)


Along grid 1,2,3 3 14.15 0.30 0.53 6.69
Along grid A,B,C,D 4 7.60 0.30 0.53 4.79

First floor level


Main beam(300x525)
Along grid 1,2,3 3 14.15 0.30 0.53 6.69
Along grid A,B,C,D 4 7.60 0.30 0.53 4.79

Secondary beam(250x425)
Along 1a 2 5.70 0.25 0.43 1.21
Along Grid 1b 1 3.20 0.25 0.43 0.34
Between A1 and C1 2 7.65 0.25 0.43 1.63

Landing Beam 250 x 380 1 3.05 0.25 0.38 0.29

Slab deduction
Main beam(300x525)
Along grid 1,2,3 -3 14.15 0.30 0.125 -1.59
Along grid A,B,C,D -4 7.60 0.30 0.125 -1.14

Secondary beam(250x425)
Along 1a -2 5.70 0.25 0.125 -0.36
Along Grid 1b -1 3.20 0.25 0.125 -0.10
Between A1 and C1 -2 7.65 0.25 0.125 -0.48

Second floor level


Main beam(300x400)
Along grid 1,2,3 3 14.15 0.30 0.40 5.09
Along grid A,B,C,D 4 7.60 0.30 0.40 3.65

C Column
Ground floor plan
Total columns(450x450) 12 0.45 0.45 3.00 7.29

First floor plan


Total columns(450x450) 12 0.45 0.45 3.00 7.29

Column below ground level


Total columns(450x450) 12 0.45 0.45 0.12 0.29
D Slab
First floor level 1 Area 139.49 0.13 17.44
Void deduction -1 Area 14.60 0.13 -1.90

E Staircase
Landing A 1 3.20 1.50 0.15 0.72
Landing B 1 3.20 1.90 0.15 0.91
Waist Slab 2 3.35 1.50 0.15 1.51
Steps 20 0.0225 Area 1.50 0.68
F Lintel Bands
Ground floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 11.10 0.23 0.08 0.19
Along grid 2 1 4.50 0.23 0.08 0.08
First floor level

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along grid A, D 2 5.55 0.23 0.08 0.19
Along grid B,C 2 5.55 0.23 0.08 0.19
Along grid 1 1 14.15 0.23 0.08 0.24
Along grid 2 1 4.50 0.23 0.08 0.08

G Sill Bands
Ground floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 14.15 0.23 0.08 0.24
Along grid 2 1 4.50 0.23 0.08 0.08
First floor level
Along grid A, D 2 5.55 0.23 0.08 0.19
Along grid B,C 2 5.55 0.23 0.08 0.19
Along grid 1 1 14.15 0.23 0.08 0.24
Along grid 2 1 4.50 0.23 0.08 0.08

H Vertical Band 8 2.48 0.08 0.23 0.34

I Kitchen Slab 1 2.40 0.650 0.100 0.16


Deduction -1 0.92 0.500 0.100 -0.05

J Pedestal 6 0.50 0.250 0.250 0.19

K Bench Slab 1 2.50 0.500 0.075 0.09

L Soak Pit
RCC slab 1 2.27 Area 0.13 0.28
Total 86.91 cu.m

2.3 Silica Cement Admixture


10Kg per cu.m of Rcc M20 10 86.91 869.09
Total 869.09 Kg

2.4 Steel Reinforcement 1 13788.06 13,788.06


Total 13,788.06 Kg
13.79 Mt
2.5 Formworks
A Foundation
Isolated footing
For Isolated Foundation, F1 4 5.60 0.20 4.48
For Isolated Foundation, F2 3 6.00 0.20 3.60
For Isolated Foundation, F3 3 7.60 0.20 4.56
For Isolated Foundation, F4 2 8.00 0.20 3.20
B Beam
Foundation beam(250x300)
Along grid 1,2,3 3 14.15 0.60 25.47
Along grid A,B,C,D 4 7.60 0.60 18.24

Plinth beam(300 x 525)


Along grid 1,2,3 3 14.15 1.05 44.57
Along grid A,B,C,D 4 7.60 1.05 31.92

First floor level


Main beam(300x525)
Along grid 1,2,3 3 14.15 1.35 57.31
Along grid A,B,C,D 4 7.60 1.35 41.04
Landing Beam 250 x 380 2 3.05 1.01 6.16

Secondary beam(250x425)
Between A,B and C,D 2 7.90 1.10 17.38
Along Grid 1b 1 3.20 1.10 3.52
Between 1 and 2 1 11.50 1.10 12.65
Slab deduction
Main beam(300x525)

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along grid 1,2,3 -3 14.15 0.250 -10.61
Along grid A,B,C,D -4 7.60 0.250 -7.60

Secondary beam(250x425)
Between A,B and C,D -2 7.60 0.250 -3.80
Along Grid 1b -1 3.20 0.250 -0.80
Between 1 and 2 -1 11.50 0.250 -2.88

Second floor level


Main beam(300x400)
Along grid 1,2,3 3 14.15 1.10 46.70
Along grid A,B,C,D 4 7.60 1.10 33.44
C Column
Ground floor plan
Total columns(450x450) 12 1.80 3.00 64.80

First floor plan


Total columns(450x450) 12 1.80 3.00 64.80

Column below ground level


12 1.80 0.12 2.59
D Slab
First floor level
Base area 1 139.49 Area 139.49

Deduction
Staircase void -1 Area 14.80 -14.80
E Staircase
Landing A 1 3.20 1.50 4.80
Landing B 1 3.20 1.90 6.08
Waist Slab 2 3.35 1.50 10.06
Steps 20 0.0225 Area 0.45
Side formwork for waist slab 2 6.0690 0.15 1.82

F Lintel Bands
Ground floor level
Along grid A,B,C,D 4 5.55 0.15 3.33
Along grid 1 1 11.10 0.15 1.67
Along grid 2 1 4.50 0.15 0.68
First floor level
Along grid A, D 2 5.55 0.15 1.67
Along grid B,C 2 5.55 0.15 1.67
Along grid 1 1 14.15 0.15 2.12
Along grid 2 1 4.50 0.15 0.68

G Sill Bands
Ground floor level
Along grid A,B,C,D 4 5.55 0.15 3.33
Along grid 1 1 14.15 0.15 2.12
Along grid 2 1 4.50 0.15 0.68
First floor level
Along grid A, D 2 5.55 0.15 1.67
Along grid B,C 2 5.55 0.15 1.67
Along grid 1 1 11.10 0.15 1.67
Along grid 2 1 4.50 0.15 0.68

H Vertical Band 8 2.48 0.15 2.97

I Kitchen slab 1 2.40 0.65 1.56


Along Sink Void 1 2.83 0.100 0.28
side formwork 1 6.10 0.100 0.61
Deduction -1 0.92 0.50 -0.46

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
J Pedestal 6 1.50 0.250 2.25

K Bench Slab 1 2.50 0.50 1.25


1 6.00 0.075 0.45
L Soak Pit
RCC slab
Base Area 1 1.13 1.13
Along Sides 1 5.34 0.15 0.80
side formwork for void and Removable
2 2.44 0.15 0.73
Cover
Total 643.82 sq.m

3 BRICK / STONE WORKS


3.2 Bricks Masonry Works (1:6c/s)
Bricks Masonry Work below Tie Beam
Along grid A, B,C, D 4 7.60 0.23 0.20 1.40
Along grid 1,2,3 3 14.15 0.23 0.20 1.95

Ground floor
Along grid A,B,C,D 4 5.55 0.23 2.33 11.87
Along Grid 1 1 14.15 0.23 2.33 7.57
Along grid 2 1 11.10 0.23 2.33 5.94

Partition Wall along Kitchen 1 5.75 0.23 2.58 3.41


Wall Below Kitchen Slab 2 0.50 0.23 0.65 0.15
Ramp 1 6.75 0.23 0.30 0.47
1 1.33 0.23 0.30 0.09
First floor level
Along grid A,B,C,D 4 5.55 0.23 2.45 12.51
Along grid 1 1 14.15 0.23 2.45 7.97
Along grid 2 1 11.10 0.23 2.45 6.25

Soak Pit Brick work 1 0.20 Area 0.50 0.10

Deduction for doors and windows


Ground floor plan
V1 -7 1.10 0.23 0.53 -0.93
W1 -7 1.10 0.23 1.13 -1.99
D1 -4 1.10 0.23 1.93 -1.95
W3 -1 1.50 0.23 0.37 -0.13
First floor plan
V2 -8 1.10 0.23 0.65 -1.32
W1 -8 1.10 0.23 1.13 -2.28
W2 -1 1.50 0.23 1.00 -0.35
D2 -4 1.10 0.23 2.45 -2.48
Total 48.26 cu.m

3.3 Half Brick Wall (125mm) Work (1:4c/s)


Ground Floor
Wall for Store Room Below Landing 1 3.90 1.65 6.44
Bench 2 2.00 0.47 1.86
Deduction For Door
D3 -1 1.00 1.55 -1.55
Total 6.75 sq.m

3.4 Honey Comb Brick (350 mm) Works (1:3c/s)


Soak Pit Brick work 1 0.20 1.20 0.24
Total 0.24 cu.m

4 DOORS & WINDOWS


4.1 Metal Frame
4.1.1 Metal Door Frame
Ground floor

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
D1 4 7.00 28.00
D3 1 4.10 4.10
First floor plan
D2 4 7.25 29.00
Total 61.10 r.m
4.1.2 Metal Windows Frame
Ground floor
V1 7 3.25 22.75
W1 7 5.51 38.54
First floor plan
V2 8 3.50 28.00
W1 8 5.51 44.04
W2 1 5.93 5.93
Total 139.26 R.m

4.2 Shutter
4.2.1 Metal Window Shutter
Ground floor
W1 7 0.97 1.04 6.99
V1 7 1.01 0.44 3.08
First floor plan
W1 8 0.97 1.04 7.99
V2 8 1.01 0.56 4.52
W2 2 1.37 0.91 2.48
Total 25.07 sq.m

4.3 Wooden Shutter


4.3.1 Door Shutter
Ground floor
D1 4 1.01 2.43 9.82
D3 1 0.91 2.06 1.87
First floor plan
D2 4 1.01 2.46 9.92
Total 21.61 sq.m

4.4 Window grill


Ground floor
W1 7 0.97 1.04 6.99
V1 7 1.01 0.44 3.08
First floor plan
W1 8 0.97 1.04 7.99
V2 8 1.01 0.56 4.52
W2 2 1.37 0.91 2.48
Total 25.07 sq.m
4.5 Collapsible Gate
1 3.05 2.44 7.43
Total 7.43 sq.m

5 FLOORING WORKS
5.1 Hardened Cement Concrete Flooring (40mm) With Neat Cement Punning
Ground floor plan
Kitchen 1 5.75 2.78 15.96
Store 1 5.75 2.75 15.81
ECD Room 2 5.75 5.75 66.13 66.13
Below Staircase 1 3.2 5.75 18.40
Ramp 1 6.82 1.25 8.53
Corridor 1 15.80 2.43 38.32

Staircase
Landing 1 3.2 1.5 4.80
Rise 20 1.5 0.15 4.50
Tread 19 1.5 0.3 8.55
Exterior Steps 2 1.55 0.45 1.40
1 12.25 0.45 5.51

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Drain 1 15.95 0.85 13.56
First floor plan
Library & Teachers Room 2 5.75 5.75 66.13
Corridor 1 15.80 2.43 38.39
Total 305.97 sq.m

5.2 Cement Finishing Skirting works


Ground floor plan
Kitchen 1 15.95 15.95
Store 1 15.90 15.90
Store Below Landing 1 14.55 14.55
Corridor 1 8.53 8.53
Column 4 1.80 7.20
In Stone Masonry outside 1 28.85 28.85
Staircase
Waist slab 2 3.35 6.70
Landing 1 1.5 1.50
Landing 1 1.8 1.80
Rise 20 1.5 30.00
Tread 19 0.3 5.70

First floor plan


Library & Teachers Room 2 20.80 41.60
Corridor 1 8.50 8.50
Column 4 1.80 7.20
Total 193.98 r.m

5.3 25mm Terrazo Finishing


Bench 1 2.40 0.50 1.20
Total 1.20 sq.m

6 Roofing/ Terracing Works


6.1 Metal Works
Truss 1 3,545.29
Total of Truss Total 3,545.29 k.g

6.2 CGI Sheet Roofing


Total Area 2 17.90 5.74 205.49
Total 205.50 sq.m

6.3 CGI Ridge


Top 1 17.90 17.90
Total 17.90 r.m

6.4 GI Facia(Eaves) Length (WxT) Density


Grid 1,3/AC 2 17.90 0.00031 7850 87.68
Grid A,D/1-3 4 5.74 0.00031 7850 56.23
Total 143.91 kgs.

6.5 Cement Board For False Ceiling


Backward and front slope of roof 2.00 15.95 1.18 37.64
Side Slope of Roof 4.00 5.65 0.97 21.92
Classroom 2.00 5.70 5.70 64.98
Staircase 1.00 5.70 3.20 18.24
Corridor 2.00 5.70 2.20 25.08
1.00 3.20 2.20 7.04
Total 174.90 Sq.m

7 PLASTER/FINISHING WORKS
7.1 Cement Plaster Works
7.1.1 Internal Plaster on Wall (1:6)
Ground floor plan
Kitchen 1 17.05 Perimeter 2.91 49.62
Store 1 17.00 Perimeter 2.91 49.47

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
ECD 1 23.05 Perimeter 2.91 67.08
Along grid B, C 2 5.75 2.91 33.47
Along grid 1 1 3.05 2.91 8.88
Store Below Landing 2 3.05 2.91 17.75
First floor plan
Library & Teachers Room 2 23.10 Perimeter 2.91 134.44
Along grid B, C 2 5.55 2.91 32.30
Along grid 1 1 3.05 2.91 8.88
Partition Wall 1 4.53 2.33 10.52

Deduction for Doors and Windows


Ground floor plan
V1 -7 1.10 0.53 -4.04
W1 -7 1.10 1.13 -8.66
D1 -4 1.10 2.33 -10.23
W3 -1 1.50 0.37 -0.56
First floor plan
V2 -8 1.10 0.65 -5.72
W1 -8 1.10 1.13 -9.90
W2 -1 1.50 1.00 -1.50
D2 -4 1.10 2.45 -10.78
Total 361.00 sq.m
7.1.2 Internal Plaster on Ceiling (1:4)
First floor level
Ground floor
ECD 1 5.78 5.75 33.21
Kitchen 1 5.75 2.78 15.96
Store 1 5.75 2.75 15.81
Corridor 1 15.80 2.53 39.90
Landing 1 1.17 3.25 3.79
Waist Slab 2 3.35 1.45 9.73
Side Plaster in Waist slab 2 3.35 0.15 1.01
Side in steps 20 Area 0.02 0.46
Beam plaster
First floor level
Main beam(300x525)
Along grid 1,2, 2.00 14.15 0.53 14.86
Along grid A,B,C,D 6.00 5.55 0.53 17.48

Secondary beam(300x425)
Between A,B and C,D 2.00 11.15 0.43 9.48
Between A and B 2.00 2.20 0.43 1.87
Secondary Beam for Staircase (250 x 425) 2.00 3.20 0.43 2.72
Slab deduction
Main beam(300x525)
Along grid 1,2, -2.00 14.15 0.125 -3.55
Along grid A,B,C,D -6.00 5.55 0.125 -4.16

Secondary beam(300x425)
Between A,B and C,D -2.00 11.15 0.125 -2.79
Between 1 and 2 -2.00 5.55 0.125 -1.39
Secondary Beam for Staircase (300 x 425) -2.00 3.20 0.125 -0.80

Second floor level


Main beam(300x400)
Along grid 1,2,3 3.00 14.15 0.40 16.98
Along grid A,B,C,D 6.00 5.55 0.40 13.32
Total 183.87 sq.m

7.1.3 External Plaster


7.1.3.1 Outer Plaster
Ground Floor
For Drain 1.00 33.65 0.88 29.44
For Ramp 1.00 1.33 1.09 1.44

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1.00 6.75 0.75 5.06
Bench 1.00 2.50 2.16 5.40
Beam Plaster
Ground floor Level
Main Beam(300 x 525)
Along grid 1 1.00 14.15 0.53 7.43
Along grid 2 1.00 14.15 0.53 7.43
Along grid 3 2.00 14.15 0.83 23.35
Along grid A 1.00 9.65 0.53 5.07
Along grid B 2.00 2.05 0.53 2.15
Along grid C 2.00 2.05 0.53 2.15
Along grid D 1.00 9.65 0.53 5.07
Secondary Beam(250 x 425)
Between 1 and 2 2.00 2.05 0.43 1.74
Slab deduction
Main Beam(300 x 525)
Along grid 1 -1.00 14.15 0.125 -1.77
Along grid 2 -1.00 14.15 0.125 -1.77
Along grid 3 -2.00 14.15 0.125 -3.54
Along grid A -1.00 9.65 0.125 -1.21
Along grid B -2.00 2.05 0.125 -0.51
Along grid C -2.00 2.05 0.125 -0.51
Along grid D -1.00 9.65 0.125 -1.21
Secondary Beam(250 x 425)
Between 1 and 2 -2.00 2.05 0.125 -0.51

First floor Level


Main Beam(300 x 400)
Along grid 1 1.00 14.15 0.70 9.91
Along grid 2 1.00 14.15 0.70 9.91
Along grid 3 2.00 14.15 0.40 11.32
Along grid A 1.00 9.65 0.40 3.86
Along grid B 1.00 2.05 1.40 2.87
Along grid C 2.00 2.05 1.40 5.74
Along grid D 1.00 9.65 0.40 3.86

Column Plaster
Along grid 1 2.00 3.30 3.00 19.80
Along grid 2 2.00 3.20 3.00 19.18
Along grid 3 8.00 1.80 3.00 43.20

Plaster in Outer Wall


Ground floor
Along grid A,D/(1-2) 2 5.55 2.33 25.81
Along grid 1 1 11.10 2.33 25.81
1 3.05 2.02 6.16
Along grid 2 1 10.80 2.33 25.11

First floor level


Along grid A,D 2 5.55 2.45 27.20
Along grid 1 1 11.10 2.45 27.20
1 3.05 2.53 7.70
Along grid 2 1 10.80 2.45 26.46

Deduction for Doors and Windows


Ground floor plan
V1 -7 1.10 0.53 -4.04
W1 -7 1.10 1.13 -8.66
D1 -4 1.10 2.33 -10.23
W3 -1 1.50 0.37 -0.56
First floor plan
V2 -8 1.10 0.65 -5.72
W1 -8 1.10 1.13 -9.90
W2 -1 1.50 1.00 -1.50

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
D2 -4 1.10 2.45 -10.78
Total 334.39 sq.m

7.2 Painting Works


7.2.1 Distemper Painting Works
Total of Interior Wall Plaster 1 361.00 Area 361.00
Total of Ceiling Plaster 1 183.87 Area 183.87
False Ceiling 1 174.90 Area 174.90
Total 719.78 sq.m

7.2.2 Exterior Weather Coat Paint


Total of External Wall Plain Plaster 1 334.39 Area 334.39
Total 334.39 sq.m

7.2.4 Enamel Painting


For Doors Factor
D1 4 1.10 2.44 2.00 21.43
D2 4 1.10 2.56 2.00 22.53
D3 1 1.00 2.10 2.00 4.20
For Window
W1 15 1.10 1.13 2.00 37.13
W2 1 1.50 1.00 2.00 3.00
W3 1 1.50 0.37 2.00 1.11
V1 7 1.10 0.53 2.00 8.09
V2 8 1.10 0.65 2.00 11.44

For Grill
W1 15 1.10 1.13 2.00 37.13
V1 7 1.10 0.53 2.00 8.09
V2 8 1.10 0.65 2.00 11.44
W2 1 1.50 1.00 2.00 3.00
W3 1 1.50 0.37 2.00 1.11
Collapsible Gate 1 3.05 2.44 2.00 14.85
Total 184.53 sq.m

8 MISCELLANOUS
8.2 Cement Board
8.2.1 Partition
Above Side Walls 1.00 9.73 1.58 15.38
Total 15.39 sq.m

8.3 Railing
Total
Staircase Railing Nos length Kg/m Total
Length
Horizontal ISNB 40 M 1 6.563 6.56 3.56 23.36
Vertical ISNB 32 M 8 0.929 7.43 3.10 23.04
Horizontal 25mm Square Pipe 4 6.563 26.25 0.85 22.31
Balcony Railing
Horizontal ISNB 40 M 1 18.25 18.25 3.56 64.97
Horizontal ISNB 32 M 2 18.25 36.50 3.10 113.15
Vertical ISNB 32 M 15 1.08 16.20 3.10 50.22
Vertical 25mm Square Pipe 132 0.82 108.24 0.85 92.00
ISNB 40M 6 1.625 9.75 3.56 34.71
ISNB 40M 6 2.05 12.30 3.56 43.79
Base plate 53 0.00009375 0.00 7850 39.00
12 mm dia. Anchor Bolt, Nut 212 0.13 27.56
Total 534.12 k.g

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,2-4C(S)
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Weight Length Total


S.N. Particulars Size Thickness Qty Total wt. Remarks
Per Metre (m) Length
1 TOP CHORD PIPE 50MM MID 5.03 5.641 12 67.69 340.49
2 BOTTOM CHORD PIPE 40MM MID 3.56 4.378 12 52.54 187.03
3 VERTICAL BRACING.1 40MM MID 3.56 1.351 12 16.21 57.71
4 VERTICAL BRACING.2 40MM MID 3.56 1.088 12 13.05 46.47
5 VERTICAL BRACING.3 40MM MID 3.56 0.825 12 9.90 35.24
6 VERTICAL BRACING.4 40MM MID 3.56 0.419 12 5.03 17.90
7 DIGONAL BRACING.1 32 MM MID 3.1 1.328 12 15.94 49.40
8 DIGONAL BRACING.2 32MM MID 3.1 1.123 12 13.48 41.78
9 DIGONAL BRACING.3 32MM MID 3.1 1.272 12 15.26 47.32
10 PURLIN 1 65MM MID 6.42 3.000 48 144.00 924.48
11 PURLIN 2 65MM MID 6.42 3.500 12 42.00 269.64
12 RUNNER 1 40MM MID 3.56 3.000 24 72.00 256.32
13 RUNNER2 40MM MID 3.56 3.500 8 28.00 99.68
15 END PURLIN 65MM MID 6.42 1.125 24 27.00 173.34
16 CROSS BRACING 40MM MID 3.56 1.380 32 44.16 157.21
17 BASE PLATE 250X250 10MM 4.9 18 88.20
18 BASE PLATE STIFFNER(L) 127X250 10MM 2.49 24 59.76
19 BASE PLATE STIFFNER(S) 50X75 10MM 0.29 24 6.96
20 PURLIN CLITE 200X90 10MM 1.41 144 203.04
21 TRUSS CLITE 200X90 10MM 1.41 72 101.52
22 RUNNER CLITE 175X70 10MM 0.96 40 38.40
23 R.CONNECTION BOX PLATE 175X160 10MM 2.19 12 26.28
24 TRUSS JOINT CLITE(C) 175X175 10MM 2.4 16 38.40
25 TRUSS JOINT CLITE(O) 175X175 10MM 2.4 8 19.20
26 STIPNER1. 100X63 10MM 0.49 16 7.84
27 STIPNER2. 63X63 10MM 0.31 64 19.84
28 WIND TIE PLATE 380X80 6MM 1.43 16 22.88
29 BRACING TIE STEPER 100X100 6MM 0.47 16 7.52
30 CROSS BRACING PIPE CLITE 165X80 6MM 0.62 64 39.68
31 TEMP PLATE 250X250 10MM 4.9 18 88.20
32 ANCHOR BOLT 16MM 1.58 0.45 72 32.40 51.19
33 NUT BOLT(16X60) 16MM 1.58 0.06 148 14.03
34 NUT BOLT(16X50) 16MM 1.58 0.05 48 3.79
35 NUT BOLT(16X40) 16MM 1.58 0.04 72 4.55
Total 3545.29 Kgs.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,2-4C(S)
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Bar Bending Schedule

Piece
Dia. Spacing Wt./m Weight Total Wt.
SN Description Bar Shape Nos. Length Remarks
(mm) (mm) (Kg) (Kg) (Kg)
(m)

F1 Footing (4 Nos): 1.30


1 1400*1400mm, Bars (X 12 150 0.888 10 1.5 13.32 53.28
0.10
direction)

1.30
Bars (Y - direction) 12 150 0.888 10 1.5 13.32 53.28
0.10

1.40
F2 Footing (3 Nos):
12 150 0.888 10 1.6 14.21 28.42
1500*1500mm, Bars 0.10

1.40
12 150 0.888 10 1.6 14.21 28.42
0.10

1.70
F3 Footing (3 Nos):
12 150 0.888 12 1.9 20.25 80.99
1800*1800mm, Bars 0.10

1.70
12 150 0.888 12 1.9 20.25 80.99
0.10

1.90
F4 Footing (2 Nos):
12 150 0.888 14 2.1 26.11 52.21
2000*2000mm, Bars 0.10

1.90
12 150 0.888 14 2.1 26.11 52.21
0.10

COLUMNS, (450*450mm)
Grid 1,2,3 Columns (12 Nos.):

=3.39
Main Bars 20 2.467 4 4.22 41.64 499.72 1 Lap in GF
0.08+0.75 0.37+0.75+0.45+(0.62+1.2)

1.03
=5.36
20 2.467 4 6.39 63.06 756.68
(6-0.62-0.025)

=3.15
16 1.58 2 3.74 11.82 141.82 1 Lap in GF
0.08+0.51 0.37+0.75+0.45+0.62+0.96

0.74
=5.36
16 1.58 2 6.10 19.28 231.31
(6-0.62-0.025)

=6.18
16 1.58 6 6.77 64.18 770.16 1 Lap in FF
0.08+0.51 0.37+0.75+0.45+3+1.61

0.74
=2.33
16 1.58 6 3.07 29.10 349.24

0.37 0.10
100 &
Stirrups (for Lap Portion) 10 0.617 22 1.68 22.39 268.68
150
0.37
0.10
0.13 100 &
10 0.617 44 1.20 32.58 390.93 Double
150
0.37

0.37 0.08
100 &
Stirrups (other) 8 0.395 29 1.64 18.96 227.51
150
0.37

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
0.08
0.13 100 &
8 0.395 58 1.16 26.58 318.91 Double
150
0.37
0.08 3 Nos. in
U-shaped Stirrups 8 each 0.395 12 1.80 8.53 102.38
0.37
member

4 Foundation Beams, 250*300mm

Main Bars (Long side beams); 15.5+0.45-2(0.07)


0.46 12 0.888 6 17.45 92.97 278.92 3 Beams
Along Grid 1-1, 2-2, 3-3

0.08
0.20 100 &
Stirrups (for 250*300) 8 0.395 123 0.86 41.84 125.52
150
0.15

Main Bars (Short side beams);


0.46 8.5+0.45-2(0.07) 12 0.888 6 9.73 51.84 207.37 4 Beams
Along Grid A,B,C,D

0.20 0.08
100 &
Stirrups (for 250*300) 8 0.395 67 0.86 22.70 90.81
150
0.15

5 Tie Beams, 300*525mm

Main Bars (Long side beams); Along Grid 1-1, 2-2, 3-3 3 Beams

0.74 Incl. 2
Top (T/O) 15.5+0.45-2(0.07) 16 1.58 5 18.25 144.18 432.53 Torsion
Rebars (3+2)

15.5+0.45-2(0.07)
Bottom (T/O) 0.74 16 1.58 4 18.25 115.34 346.02

0.74
Extra Bars (at 2 Ends) 0.38+1.50 16 1.58 4 2.62 16.56 16.56

Extra Bars (above B, C) 0.45+1.1+1.5 16 1.58 4 3.05 19.28 19.28

0.47 0.12
Stirrups (for 300*525) 12 100 0.888 145 1.68 215.57 646.71
0.25

Main Bars (Short side beams); Along Grid A,B,C,D 4 Beams

0.74 Incl. 2
Top (T/O) 8.5+0.45-2(0.07) 16 1.58 5 10.29 81.29 325.16 Torsion
Rebars (3+2)

8.5+0.45-2(0.07)
Bottom (T/O) 0.74 16 1.58 4 10.29 65.03 260.13

0.74 0.38+1.7
Extra Bars (at 2 ends) 0.38+2.5+1.7 16 1.58 2 8.14 25.72 102.89

0.47 0.12
Stirrups (for 300*525) 12 100 0.888 78 1.68 116.36 465.45
0.25

7804.47 OK

6 1st floor Main Beams:


Long side Beams: 300*525 Along Grid 1-1, 2-2 2 Beams

15.5+0.45-2(0.07)
Bottom Bars (T/O) 0.76 20 2.467 2 18.47 91.13 182.26

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
15.5+0.45-2(0.07)
0.53 16 1.58 2 17.78 56.18 112.37

0.53
Top Bars (T/O) 15.5+0.45-2(0.07) 16 1.58 3 17.78 84.28 168.55

0.76
Extra Bars (above A) 0.38+1.50 20 2.467 2 2.64 13.03 26.05

Extra Bars (Mid) 0.45+3.5+1.5*2 20 2.467 2 6.95 34.29 68.58

1.05
Extra Bars (above D) 0.38+1.70 25 3.855 2 3.13 24.13 48.26

0.91 2 Nos. at
Bent-up Bars 0.34 16 1.58 4 2.75 17.38 34.76
a point

0.475 0.10
100 &
Stirrups 10 0.617 124 1.64 125.81 251.62
150
0.25

Along Grid 3-3,

15.5+0.45-2(0.07)
Bottom Bars (T/O) 0.76 20 2.467 2 18.47 91.13 91.13

15.5+0.45-2(0.07)
0.53 16 1.58 2 17.78 56.18 56.18

0.53
Top Bars (T/O) 15.5+0.45-2(0.07) 16 1.58 3 17.78 84.28 84.28

0.53
Extra Bars (above A) 0.38+1.50 16 1.58 2 2.41 7.62 7.62

Extra Bars (Above B, C) (1.1+1.5+0.45) 16 1.58 4 3.05 19.28 19.28

0.53
Extra Bars (above D) 0.38+1.5 16 1.58 2 2.41 7.62 7.62

0.91 2 Nos. at
Bent-up Bars 0.34 16 1.58 4 2.75 17.38 17.38
a point

0.475 0.10
100 &
Stirrups 10 0.617 124 1.64 125.81 125.81
150
0.25

Short side beams: Along Grid A,B,C,D 4 Beams

8.5+0.45-2(0.07)
Bottom Bars (T/O) 0.76 20 2.467 4 11.47 113.19 452.74

0.53
Top Bars (T/O) 8.5+0.45-2(0.07) 16 1.58 3 9.87 46.78 187.14

1.05
Extra Bars (above 1) 0.38+1.70 25 3.855 2 3.13 24.13 96.53

1.05
Above 2, 3 0.38+2.5+1.7 25 3.855 2 5.63 43.41 173.63

0.91 2 Nos. at
Bent-up Bars 0.34 16 1.58 2 2.75 8.69 34.76
a point

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
0.475 0.10
100 &
Stirrups 10 0.617 71 1.64 71.67 286.70
150
0.25

Secondary Beams:

Along Grid A1,C1 2 beams

0.65
Top & Bottom bars (T/O) 8.5+0.30-2(0.035) 16 1.58 6 10.03 95.08 190.17

0.37 0.08
100 &
Stirrups (250*425 mm) 8 0.395 71 1.30 36.63 73.26
150
0.20

Along Grid (1a), 2 beams

0.65
Top & Bottom bars (T/O) 6.0+0.30-2(0.035) 16 1.58 6 7.53 71.38 142.77

0.37 0.08
100 &
Stirrups (250*425 mm) 8 0.395 48 1.30 24.82 49.64
150
0.20
Along Grid (1b),

0.65
Top & Bottom bars (T/O) 3.5+0.30-2(0.035) 16 1.58 6 5.03 47.68 47.68

0.37 0.08
100 &
Stirrups (250*425 mm) 8 0.395 28 1.30 14.46 14.46
150
0.20

2nd floor (Truss Level) Main Beams only:

Long side Beams: 300*400 Along Grid 1-1, 2-2, 3-3

15.5+0.45-2(0.07)
Bottom Bars (T/O) 0.53 16 1.58 2 17.78 56.18 168.55

15.5+0.45-2(0.07)
0.30 12 0.888 2 17.09 30.35 91.06

0.53
Top Bars (T/O) 15.5+0.45-2(0.07) 16 1.58 3 17.78 84.28 252.83

0.35 0.08
100 &
Stirrups (300*400 mm) 8 0.395 124 1.36 66.79 200.38
150
0.25
Short side Beams: 300*400 Along Grid A,B,C,D

0.53 8.5+0.45-2(0.07)
Bottom Bars (T/O) 16 1.58 2 9.87 31.19 124.76

8.5+0.45-2(0.07)
0.30 12 0.888 2 9.41 16.71 66.85

0.53
Top Bars (T/O) 8.5+0.45-2(0.07) 16 1.58 3 9.87 46.78 187.14

0.35 0.08
100 &
Stirrups (300*400 mm) 8 0.395 70 1.36 37.34 149.34
150
0.25
6 Staircase:

GF to FF; Lower Flight:

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1.24
Main bars 1.20 12 125 0.888 13 2.56 28.83
0.12

1.0 1.0
Bottom extra bar 12 125 0.888 13 2.00 22.52

3.35
1.67 1.46
12 125 0.888 13 7.00 78.82
0.3
0.22

Top extra bar 1.0 12 125 0.888 13 2.00 22.52


1.0

0.78 12 125 0.888 13 2.87 32.32


1.88
0.21

Bottom distribution (upto 1.46


10 150 0.617 32 1.46 28.77
Landing)

1.46
Top distribution 10 150 0.617 24 1.46 21.56

Bottom & Top distribution (in 3.16


10 150 0.617 20 3.16 38.21
Landing)

Upper Flight:

1.20 1.89
Main bars 12 125 0.888 13 3.31 37.27
0.22

Bottom extra bar 1.0


1.0 12 125 0.888 13 2.00 22.52

3.35
2.32
0.82 12 125 0.888 13 6.81 76.68
0.32

0.33 1.0
Top extra bar 0.26 12 125 0.888 13 1.59 17.90

0.27
12 125 0.888 13 1.51 17.00
0.42 0.82

Bottom distribution (upto 1.46 10 150 0.617 24 1.46 21.32


Landing)

Top distribution 1.46 10 150 0.617 15 1.46 13.81

Nosing Bar (both Flight) 1.46 10 0.617 20 1.46 18.02

0.26
0.15
Nosing Tie 0.12 8 300 0.395 117 0.68 31.52
0.15

Landing Beam (250*380):

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
0.53 3.5+0.45-2(0.07)
Main Bars (Top & bottom) 16 1.58 6 4.87 46.17

0.33 0.08
100 &
Stirrups 8 0.395 27 1.22 13.09
150
0.20
588.84 588.84

7 SLAB:

0.51 0.58
1 Lap (in mid
Along Short Span: Main Bars 0.085 8.8-0.04 8 300 0.395 19 10.79 163.32
cranked)

0.51 0.58
0.085 8.8-0.04 8 300 0.395 19 10.01 151.57

0.51
0.085 3.88 8 300 0.395 12 4.56 20.99

0.51
0.085 3.88 8 300 0.395 12 4.47 20.60

Negative Bars (0.9*2)+0.25 8 300 0.395 19 2.05 31.04

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
(0.9+0.75+0.3) 8 300 0.395 19 1.95 29.53

(0.9+0.75+0.3) 8 300 0.395 12 1.95 8.99

Distribution 8.76 8 200 0.395 15 8.76 105.19

3.88 8 200 0.395 6 3.88 19.16

0.58
Along Long Span: Main Bars 6.26 8 300 0.395 16 7.70 98.75
0.07

0.58
6.26 8 300 0.395 16 7.56 96.95
0.07

0.58
15.76 8 300 0.395 11 18.08 80.21
0.07

0.58
15.76 8 300 0.395 11 17.52 77.72
0.07

Negative Bars (0.9*2)+0.25 8 300 0.395 29 2.05 46.16

0.75+0.87+0.30 8 300 0.395 9 1.92 14.01

15.76
Distribution Bar 8 200 0.395 12 16.22 73.66

6.26
8 200 0.395 13 6.26 64.78

Slab Rebar (one floor), Subtotal = 1102.61 1102.61


Grand Total (Kg) = 13788.06
13.79 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,2-4C(S)
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Site
S. No. Description G.F F.F Quantity Unit Remarks
Development
A. Common Installation
1 Stand Alone 40 A DP MCB with Enclosure 1.00 1.00 nos.
2 CABLES & WIRES
2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded
2.1 42.00 r.m
copper conductor wires
B School Blocks
1 DISTRIBUTION BOARDS 1.00 1.00 2.00 nos.
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4
2.1 5.00 r.m
Sq mm Multistranded Cu wire
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5
2.2 10.00 r.m
Sq mm Multistranded Cu wire
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No
2.3 16.00 r.m
1.5 Sq mm Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point 3.00 13.00 13.00 29.00 pts.
3.2 Two Way Light Point 1.00 1.00 pts.
3.3 Ceiling Fan Point 4.00 4.00 pts.
4 16A Universal Pin Light Power Socket Wiring 1.00 1.00 pts.
5 6A Universal Pin Light Power Socket Wiring 8.00 7.00 15.00 pts.
6 Switch Socket Outlets
6.1 16A Universal Power Switch Socket 1.00 1.00 no.
6.2 6A Universal Power Switch Socket 9.00 7.00 16.00 no.
7 Sweep Ceiling/Exhaust Fans/ Wall Fan
7.1 1200mm Sweep Ceiling Fan 2.00 2.00 no.
7.2 400mm Sweep Wall Fan 4.00 6.00 no.
7.3 225mm dia M/D Exhaust Fan 2.00 2.00 no.
8 Light Fixtures/Luminaires & Accessories
8.1 24 W LED Recessed Mounted Square type 4.00 4.00 no.
8.2 18 W LED Surface Mounted Square type 6.00 6.00 no.
8.3 18 W LED Recessed Mounted Square type 4.00 4.00 no.
8.4 12 W LED Surface Mounted Cylindrical type 6.00 6.00 no.
8.5 12 W LED Recessed Mounted Circular type 5.00 5.00 no.
8.6 7W LED Wall Light 1.00 1.00 no.
9 Pull Box 3.00 3.00 no.
10 External Post Top Light Pole 3.00 3.00 no.
11 Post Top External Light Fixtures 3.00 3.00 no.
12 Earthing & Lighting Protection
12.1 Chemical Earthing 3.00 3.00 no.
12.2 Earthing Bar 3.00 3.00 no.
12.3 Earthing Strip/Wires
12.3.1 25 x 3 mm GI strip 65.00 65.00 r.m
12.3.2 12 SWG Cu wire 15.00 15.00 r.m
13 Earth Test link 1.00 1.00 no.
D Fire Extinguisher
5.0kg Size ABC Stored Pressure Type Fire
1 1.00 1.00 2.00 nos.
Extinguisher

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Site
S. No. Description G.F F.F Quantity Unit Remarks
Development
2 Dry Powder Fire Extinguisher 1.00 1.00 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Building: Academic Block,3-6C(S)


S.N Furniture Description Symbol Qty Unit Remarks
1 Student Desk G3-5 (2 Seater) D-01B 45 nos.
2 Student Desk G6-12 (2 Seater) D-01C 45 nos.
3 Student Bench G3-5 (2 Seater) B-01B 45 nos.
4 Student Bench G6-12 (3 Seater) B-01C 45 nos.
5 Teacher's Table T-01 6 nos.
6 Teacher's Chair C-01 6 nos.
7 White Board F-03 6 nos.
8 Notice Board F-14 1 nos.
Total 199 nos.

Building: Academic Block,2-4C(S)


S.N Furniture Description Symbol Qty Unit Remarks
Classroom
1 ECD Student Desk (6 Seater) D-03 3 nos.
2 Teacher's Table T-01 2 nos.
3 Teacher's Chair C-01 2 nos.
4 Soft Board F-01 1 nos.
5 Book Shelf F-02 3 nos.
6 White Board F-03 2 nos.

Library
7 Library Table T-02 4 nos.
8 Library Shelf F-04 3 nos.
9 Student Bench (3 Seater) B-02C 8 nos.

Office
10 Cabinet F-06 3 nos.
11 Office Table T-07 12 nos.
12 Office Chair C-03 12 nos.
13 Dinning Chair C-05 12 nos.
14 Dinning Table T-09 2 nos.

Miscellaneous
15 Cusions F-16 18 nos.
16 Carpet 33.2 sq.m
17 Equipment Cabinet F-09 2 nos.
Total 89 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
me : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,T(S)F
Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Length Breadth Height


S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
1 Earthworks
1.1 Site Clearance
Toilets ( Female)
Toilet block 1 8.34 6.35 52.91
Septic tank 1 5.00 3.95 19.75
Soak Pit 1 1.50 1.50 2.25
Sewer Manhole 1 1.00 1.00 1.00
Waste water Chamber 2 2.00 2.00 8.00
Total 83.91 Sq.m

1.2 Earth Work Excavation


For Footing
Footing F1 6 1.30 1.30 1.20 12.17

For Lower Tie Beam


Along grid 1 1 3.70 0.60 0.70 1.55
Along grid 2 1 3.70 0.50 0.70 1.30
Along grid 3 1 3.70 0.60 0.70 1.55
Along grid A 1 3.40 0.60 0.70 1.43
Along grid B/1-2 1 2.20 0.60 0.70 0.92
Along grid B/2-3 1 1.20 0.50 0.70 0.42
Between Grid AB & 2-3 1 4.50 0.60 0.45 1.20

Along the incinerator 1 1.90 1.15 0.15 0.33


For ramp 1 0.50 Area 1.03 0.51
From exterior wall to drain 1 3.00 1.30 0.05 0.20
1 2.80 0.60 0.05 0.08
Drain 1 6.50 0.60 0.05 0.20
External Steps 1 1.20 0.60 0.15 0.11
For Septic Tank 1 5.80 2.55 2.60 38.45
1 1.10 1.85 1.20 2.44
Soak Pit 1 4.15 Area 1.50 6.23
For Sewer Manhole 1 1.00 Area 0.70 0.70
Waste Water Chamber 2 1.00 1.00 0.70 1.40
Total 71.19 Cu.m

1.3 Earth Back filling


Excavated earthwork 71.19
Boulder soling -2.40
PCC -1.20
RCC -5.49
Brick masonry work below plinth tie beam -3.62

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Room 1 5.00 3.20 0.18 2.80
Corridoor 1 5.00 2.20 0.18 1.93
Total 63.21 Cu.m

1.4 Boulder Soling


For Footing
Along the isolated foundation 6 1.00 1.00 0.20 1.20

Along the plinth beam


Along grid 1 1 4.50 0.45 0.10 0.20
Along grid 2 1 4.50 0.35 0.10 0.16
Along grid 3 1 4.50 0.45 0.10 0.20
Along grid A 1 5.00 0.45 0.10 0.23
Along grid B/1-2 1 3.00 0.45 0.10 0.14
Along grid B/2-3 1 2.00 0.35 0.10 0.07
Between Grid AB & 2-3 1 4.50 0.45 0.10 0.20

Below the ground floor.


1 2.00 3.23 0.20 1.29
1 2.50 3.25 0.20 1.63
Below the corridor. 1 5.00 2.25 0.20 2.25

Along the incinerator 1 1.90 1.15 0.90 1.97


For the ramp 1 6.00 1.00 0.20 1.20
From exterior wall to drain 1 3.00 1.33 0.05 0.00
1 2.70 0.60 0.05 0.00

Septic Tank 1 5.50 2.25 0.06 0.68


1 0.80 1.55 0.06 0.07
Inside of soak Pit 1 1.20 2.00 2.40
Sewer Manhole 1 1.00 1.00 0.20 0.20
Waste Water Chamber 2 1.00 1.00 0.20 0.40
Total 14.48 Cu.m

1.5 Sand Filling


Periphery ot Soak pit 1 1.80 Area 1.20 2.16
Total 2.16 cu.m

2 Concrete Works
2.1 PCC
2.1.1 P.C.C.(1:3:6) Works
For Footing 1
P.C.C. for isolated footing(F1) 6 1.00 1.00 0.10 0.60

For Tie Beam


Along grid 1 1 4.50 0.45 0.05 0.10
Along grid 2 1 4.50 0.35 0.05 0.08

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Along grid 3 1 4.50 0.45 0.05 0.10
Along grid A 1 5.00 0.45 0.05 0.11
Along grid B/1-2 1 3.00 0.45 0.05 0.07
Along grid B/2-3 1 2.00 0.35 0.05 0.04
Between Grid AB & 2-3 1 4.50 0.45 0.05 0.10

Septic Tank
1 5.50 2.25 0.08 0.99
Sewer Manhole
Bottom 1 1.00 Area 0.10 0.10
Waste water Chamber 0.00
Bottom 2 1.00 1.00 0.10 0.20
Total 2.49 Cu.m

2.1.2 P.C.C.(1:2:4) Works


Toilets ( Female) 1
For the ramp 1 6.00 1.00 0.08 0.45
Bellow the ground floor.
1 2.00 3.23 0.08 0.00
1 2.50 3.25 0.08 0.00
Bellow the corridor. 1 5.00 2.25 0.08 0.00
Along the incinerator 1 1.90 1.15 0.05 0.11
From exterior wall to drain 1 3.00 1.20 0.05 0.00
1 2.70 0.60 0.05 0.00
Total 0.56 cu.m

2.2 P.C.C For R.C.C. Works (1:1.5:3)


Foundation
Inclined Part 6 Area 0.63 0.15 0.56
Rectangular Base 6 1.00 1.00 0.20 1.20

Beam
Foundation Beam
Along grid 1 1 4.70 0.25 0.30 0.35
Along grid 2 1 4.70 0.25 0.30 0.35
Along grid 3 1 4.70 0.25 0.30 0.35
Along grid A 1 5.40 0.25 0.30 0.41
Along grid B/(1,2) 1 3.20 0.25 0.30 0.24

Tie Beam
Along grid 1 1 4.70 0.25 0.30 0.35
Along grid 2 1 4.70 0.25 0.30 0.35
Along grid 3 1 4.70 0.25 0.30 0.35
Along grid A 1 5.40 0.25 0.30 0.41
Along grid B(1,2) 1 3.20 0.25 0.30 0.24
Along grid B/(2,3) 1 2.20 0.25 0.59 0.32

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
For first floor Beam
Main beam
Along grid 1 1 4.70 0.25 0.40 0.47
Along grid 2 1 4.70 0.25 0.45 0.53
Along grid 3 1 4.70 0.25 0.45 0.53
Along grid A/1-2 1 3.20 0.25 0.40 0.32
Along grid A/2-3 1 2.20 0.25 0.45 0.25
Along grid B/1-2 1 3.20 0.25 0.40 0.32
Along grid B/2-3 1 2.20 0.25 0.45 0.25

Column
Column up to plinth level 6 0.30 0.30 1.00 0.54
Column from plinth to top 6 0.30 0.30 3.00 1.62

Slab
Slab of first floor 1 4.75 2.25 0.15 1.60

Lintel Bands
For first floor
Along grid 1 1 4.70 0.125 0.25 0.15
Along grid 2 1 4.70 0.125 0.25 0.15
Along grid 3 1 4.70 0.125 0.25 0.15
Along grid A 1 5.40 0.125 0.25 0.17
Along grid B 1 3.20 0.125 0.25 0.10
Along the partition wall 1 3.25 0.125 0.25 0.10
For the partition wall 1 2.77 0.125 0.13 0.04

Sill Bands 0.00


For first floor 0.00
Along grid 1 1 4.70 0.075 0.43 0.15
Along grid 2 1 4.70 0.075 0.43 0.15
Along grid 3 1 4.70 0.075 0.43 0.15
Along grid A 1 5.40 0.075 0.43 0.17
Along grid B 1 3.20 0.075 0.43 0.10
Along the partition wall 1 3.25 0.075 0.25 0.06
For the partition wall 1 2.77 0.075 0.13 0.03
Deduction 0.00
D1 -1 1.00 0.075 0.43 -0.03
D2 -1 0.90 0.075 0.43 -0.03

Along the Slab of incinirator 1 0.80 1.000 0.08 0.06


Along the water trough
1 1.80 0.500 0.100 0.00
1 1.80 0.500 0.100 0.00
3 0.58 0.300 0.100 0.00
Septic Tank
At Bottom 1 5.20 1.95 0.12 1.22

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Conceal Beam 1 1.20 0.25 0.15 0.05
Top Cover 1 5.20 1.95 0.12 1.22
Deduction Cap -2 0.30 0.30 0.12 -0.02
-1 0.30 0.30 0.12 -0.01

Soak Pit
RCC slab 1 1.13 Area 0.12 0.14
Sewer Manhole
Top Cover 1 1.00 1.00 0.10 0.10
Waste Water Chamber
Top Cover 2 1.00 1.00 0.10 0.20
Total 16.46 Cu.m

2.3 Silica Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10 16.46 164.63
Total 164.63 Kg.

2.5 Formworks
Foundation
Isolated footing (F1) 6 4.00 0.20 4.80

Beam
Foundation Beam
Along grid 1 1 4.70 0.50 2.35
Along grid 2 1 4.70 0.50 2.35
Along grid 3 1 4.70 0.50 2.35
Along grid A 1 5.40 0.50 2.70
Along grid B/(1,2) 1 3.20 0.50 1.60

Tie Beam
Along grid 1 1 4.70 0.60 2.82
Along grid 2 1 4.70 0.60 2.82
Along grid 3 1 4.70 0.60 2.82
Along grid A 1 5.40 0.60 3.24
Along grid B/(2,3) 1 2.20 1.18 2.60

Truss level Beam


Main beam
Along grid 1 1 4.70 1.05 4.94
Along grid 2 1 4.70 1.15 5.41
Along grid 3 1 4.70 1.15 5.41
Along grid A/1-2 1 3.20 1.05 3.36
Along grid A/2-3 1 2.20 1.15 2.53
Along grid B/1-2 1 3.20 1.05 3.36
Along grid B/2-3 1 2.20 1.15 2.53

Column

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Column up to plinth level 6 1.00 1.20 7.20
Column from plinth to top 6 3.00 1.20 21.60

Slab
Along corridor 1 4.75 2.25 10.69

Lintel Bands
Along grid 1 2 4.70 0.125 1.18
Along grid 2 2 4.70 0.125 1.18
Along grid 3 2 4.70 0.125 1.18
Along grid A 2 5.40 0.125 1.35
Along grid B 2 3.20 0.125 0.80
Along partition walls 1 2.77 0.125 0.35

Sill Bands 0.00


Along grid 1 1 4.70 0.150 0.71
Along grid 2 1 4.70 0.150 0.71
Along grid 3 1 4.70 0.150 0.71
Along grid A 1 5.40 0.150 0.81
Along grid B 1 3.20 0.150 0.48

For the partition wall 1 2.77 0.150 0.42


subtraction 0.00
D1 -1 1.00 0.150 -0.15
D2 -1 0.90 0.150 -0.14

Along the water trough 2 3.75 0.875 6.56


6 0.50 0.300 0.90
For Septic Tank
For cover Slab 1 5.20 1.95 10.14
Conceal Beam 1 0.55 Perimeter 1.20 0.66

For Soak Pit


RCC slab
Base Area 1 1.13 1.13

Sewer Manhole
Top Cover 1 0.60 Area 0.60

Waste Water Chamber


Top Cover 2 0.75 0.75 1.13
Total 128.13 Sq.m

3 Brick Works
3.2 Full Brick (230 mm) Works (1:4c/s)
Brick Works under Plinth beam
Along grid 1 1 4.70 0.23 0.45 0.49

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Along grid 2 1 4.70 0.23 0.45 0.49
Between Grid 2 and 3 1 4.50 0.23 0.68 0.70
Along grid 3 1 4.70 0.23 0.45 0.49
Along grid A 1 5.40 0.23 0.45 0.56
Along grid B 1 3.20 0.23 0.45 0.33

Internal Partition Walls


Along grid 1 1 4.70 0.23 2.03 2.19
1 0.25 0.23 0.38 0.02
Along grid 2 1 4.70 0.23 2.03 2.19
1 0.25 0.23 0.38 0.02
Deduction -1 1.00 0.23 2.03 -0.47
-1 0.90 0.23 2.03 -0.42
Along grid 3 1 4.70 0.23 1.00 1.08
Along grid B 1 3.20 0.23 1.78 1.31
Along grid A 1 3.20 0.23 2.40 1.77
1 2.20 0.23 2.40 1.21
Middle Wall 1 3.25 2.80 0.25 2.28

Below Water Trough 1 0.58 0.23 0.30 0.04


1 0.58 0.23 0.45 0.06
At outside Drain 1 0.93 area 1.20 1.11
For Septic Tank
Inlet wall (250 mm ) 1 1.20 0.23 0.60 0.17
1 1.20 0.23 0.20 0.06
Outer Wall (375 mm) 2 4.20 0.38 2.25 7.09
2 1.20 0.38 2.25 2.03

Soak Pit Brick work 1 0.20 0.50 0.10


Total 24.88 cu.m

3.3 Half Brick (125 mm) Works (1:4c/s)


Long wall 1 1.72 2.80 4.82
Short wall 1 0.43 2.80 1.19

Sewer Man Hole


Outer Wall 1 3.20 0.45 1.44
Waste Water Chamber
Outer Wall 2 3.50 0.45 3.15
Total 10.61 sq.m

3.4 Honey Comb Brick (350 mm) Works (1:3c/s)


Soak Pit Brick work 1 0.20 1.20 0.24
Total 0.24 cu.m

4 DOORS & WINDOWS

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
4.4 UPVC Door
4.4.1 UPVC Door Shutter
Toilets (Female) 1
D1 1 1.00 2.05 2.05
D2 1 0.90 2.05 1.85
D3 2 0.75 2.05 3.08
Total 6.97 sq.m

4.4 Window Grill


Toilets ( Female) 1
Ventilation FrameV1 1 2.48 0.38 1.86
V2 1 2.48 0.33 1.61
V3 1 1.98 0.38 1.48
V4 1 1.98 0.33 1.28
6.23 sq.m

5 FLOORING WORKS
5.1 Cement Concrete Flooring (40mm) With Neat Cement Punning
Toilets ( Female) 1
At corridor 1 5.30 1.20 6.36
At Ramp 1 5.60 1.20 6.72
Along the terrace 1 4.75 2.25 10.69
step 1 0.30 1.20 0.36
Inside the room 1 3.23 2.00 6.45
1 3.23 2.50 8.06
At Doors 1 1.90 0.25 0.48
Along the water trough 1 3.45 0.7 2.42
Total 41.53 sq.m

5.2 Neat cement Skirting


1 11.5 11.50
Total 11.50 r.m

5.3 Terrazo Cast In-Situ Dado


Toilets (Male & Female) 1
Along grid A & B 2 3.20 1.20 7.68
Along grid 1 1 4.50 1.20 5.40
Along grid 2 1 2.60 1.20 3.12
Along the water trough 1 3.45 0.80 2.76
Along the partition wall 1 5.10 1.20 6.12
2 3.25 1.20 7.80
Total 32.88 sq.m

6 Roofing/ Terracing Works


6.1 Metal Works
Truss 597.05

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Total 597.05 kg

6.2 CGI Sheet Roofing


Toilets (Female) 1
1.00 6.95 2.71 area 18.82
1.00 6.95 2.12 area 14.71
Total 33.54 sq.m

6.3 CGI Ridge


Toilets (Female) 1
1.00 6.95 6.95
Total 6.95 r.m
6.4 Eves Board
Toilets (Female) 1
23.32 0.288 1.20 7.85 8.06
Total 8.06 k.g

6.5 Cement Board For False Ceiling


Inside the room 1 1.00 2.00 3.25 6.50
Inside the room 2 1.00 2.50 3.25 8.13
Slopped Roof 1.00 6.95 0.64 4.42
1.00 4.82 0.98 4.70
Total 23.75 sq.m

7 PLASTER/PAINTING WORKS
7.1 Internal Plaster
7.1.1 Internal Plaster on Wall (1:6)
Toilets ( Female) 1
Along grid A & B 2 3.20 1.80 11.52
Along A 1 2.20 3.00 6.60
Along grid 1 1 4.70 1.80 8.46
Along grid 2 1 2.55 1.80 4.59
On partition wall 2 3.25 1.80 11.70
Long wall 1 1.63 1.80 2.93
1 1.88 1.80 3.38
Short wall 2 0.43 1.80 1.53
Deduction
V1 -1 3.48 0.38 -0.65
V2 -1 3.48 0.33 -0.56
V3 -1 1.98 0.38 -0.37
V4 -1 1.98 0.33 -0.32
D1 -1 1.00 0.90 -0.45
D2 -1 0.90 0.90 -0.41
Along grid 3 1 4.70 1.95 4.57
Total 52.52 sq.m

7.1.2 Internal Plaster on Ceiling (1:4)

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Toilets ( Female) 1
slab
Along corridor 1 2.24 2.24
Beam Along 1 1 4.45 0.40 1.78
Beam Along 2 1 4.45 0.90 4.01
Beam Along A 1 3.2 0.40 1.28
1 2.2 0.45 0.99
Beam Along B 1 3.2 0.40 1.28
1 2.2 0.45 0.99
Along Corridor 1 5.03 2.20 11.04
Total 23.60 sq.m

7.1.3 External Plaster


External Plaster on Beam/Column
Toilets (Female) 1
Along grid 1 1 4.70 0.40 1.88
Along grid 3 1 4.70 0.45 2.12
Along grid A 1 3.20 0.40 1.28
2.20 0.45 0.99
Along grid B 1 3.20 0.40 1.28
1 2.20 0.45 0.99
slab
Along side edge of the slab 2 2.25 0.15 0.68
Along the column 6 3.00 0.60 10.80
0.00
External Plaster on Walls
Along Grid 1 1 4.70 2.23 10.46
Along Grid 2 1 4.70 2.23 10.46
Along Grid 3 1 4.70 1.20 5.64
Along Grid A 1 5.40 2.60 14.04
Along Grid B 1 3.20 2.60 8.32
Total 68.93 sq.m

7.1.4 Internal Plaster on Wall (1:4) with Cement Punning


Inside Septic Tank Wall
Long Wall 2.00 5.20 2.25 23.40
Short Wall 2.00 1.95 2.25 8.78
Baffle wall 2.00 1.20 1.45 3.48
35.66 Sq.m

7.2 Painting works


7.2.1 Distemper painting Works
As Per Internal Plaster on Ceilings 1 23.60 23.60
As per internal plaster on wall 1 52.52 52.52
False Ceiling Works 1 23.75 23.75
99.87 sq.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
7.2.2 Exterior Weather Coat Paint
AS per External Plaster 1 68.93 68.93
68.93 sq.m

7.2.4 Enamel Paint


Window grill
Ventilation FrameV1 1 2.48 0.38 2.00 1.86
V2 1 2.48 0.33 2.00 1.61
V3 1 1.98 0.38 2.00 1.48
V4 1 1.98 0.33 2.00 1.28
6.23 sq.m

8 MISCELLANOUS
8.2 Cement Board
For Partition
2.00 1.69 Area 3.37
Total 3.38 sq.m

8.4 Pump Shed


1 1 1.00
Total 1.00 Nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,T(S)F
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)
A. Foundation Mesh
Footing F1

900
a. Along Y-axis 100 12 150 6 7 1100 46.2 0.889 41.07
100

900
b. Along X-axis 100 12 150 6 7 1100 46.2 0.889 41.07
100

B. Column-MAIN BAR
465

4251
a. Longitudinal bar upto full height 12 - 6 8 5160 247.68 0.889 220.16

100 344
STIRRUPS FOR COLUMN SIZE 300 x 300 upto Plinth Height-

220
80

b Stirrups 220 8 100 6 9 1040 56.16 0.395 22.19

1
160 6
80 0
c Stirrups 8 100 6 11 800 52.8 0.395 20.86
1
6 160
0

C Column (300*300)

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

220
80
a Stirrups for Column upto floor Height 220 8 125 6 25 1040 156 0.395 61.63

1
160 6
80 0
b " 8 125 6 25 800 120 0.395 47.41
1
6 160
0

D BEAM
1 Foundation Beam (250*250)

5000
a Along Grid-1,2 & 3- Top Bar 720 720 12 3 3 6440 57.96 0.889 51.52

b Along Grid--1,2 & 3-Bottom Bar 720 12 3 3 6440 57.96 0.889 51.52
5000 720

6000
c Along Grid-A & B-Top Bar 720 12 3 3 7440 66.96 0.889 59.52
720

d Along Grid-Bottom Bar 720 12 3 3 7440 66.96 0.889 59.52


6000 720

200
80
e Stirrups Along Grid 1, 2 & 3 8 150 3 34 960 97.92 0.395 38.69
200

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

200
80
f Stirrups Along A & B 8 150 2 40 960 76.8 0.395 30.35
200

2 Plinth Beam (250*300)

5000
a. Along Grid-1 -Top Bar 960 16 1 2 6920 13.84 1.580 21.88
960

5000
b 720 12 1 1 6440 6.44 0.889 5.73
720

5000
c Along Grid-1 -Bottom Bar 960 16 1 2 6920 13.84 1.580 21.88
960

5000
d 720 12 1 1 6440 6.44 0.889 5.73
720

e Along Grid-2 & 3-Top Bar 960 16 2 2 6920 27.68 1.580 43.75
5000 960

f 720 12 2 1 6920 13.84 0.889 12.31


5000 720

g Along Grid-2 & 3-Bottom Bar 960 16 2 2 6920 27.68 1.580 43.75
5000 960

h 720 12 2 1 6920 13.84 0.889 12.31


5000 720

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

6000
i Along Grid-A & B-Top Bar 12 2 3 7440 44.64 0.889 39.68
720 720

j Along Grid-A & B-Bottom Bar 720 12 2 4 7440 59.52 0.889 52.91
6000 720

200
80

k Stirrups Along Grid 1, 2 & 3 8 150 3 42 1360 171.36 0.395 67.70


400

200
80

l Stirrups Along Grid A & B 8 150 2 35 1360 95.2 0.395 37.61


400

3 FLOOR BEAM
LONGITUDINAL BARS
Along Grid 1,2&3

5200
a Top Bars 870 16 3 2 6940 41.64 1.580 65.81
870

5200
b Top Bars 12 3 1 6380 19.14 0.889 17.02
590 590

c Bottom Bars 350 16 3 2 5900 35.4 1.580 55.95


5200 350

d Bottom Bars 350 350 12 3 2 5900 35.4 0.889 31.47


5200

Along Grid A&B

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

6200
e Top Bars 12 2 3 7380 44.28 0.889 39.36
590 590

f Bottom Bars 350 12 2 4 6900 55.2 0.889 49.07


6200 350

STIRRUPS

200
8
0
g Stirrups for Beam Size 250*400 350 8 125 1 93 1260 117.18 0.395 46.30

200
80

h Stirrups for Beam Size 250*450 400 8 125 1 124 1360 168.64 0.395 66.63

E SLAB

850 850
a Main Bars Short Span 100 10 150 1 33 4600 151.8 0.617 93.71
100 2700

1475 1475
b Main Bars Long Span 100 10 150 1 16 8350 133.6 0.617 82.47
5200 100

c Distribution Bars Short Span 8 150 1 18 2700 48.6 0.395 19.20


2700

d Distribution Bars Long Span 8 150 1 10 5200 52 0.395 20.55


5200

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)
F STIRRUPS FOR COLUMN SIZE 300 x 300 ( From Plinth Level to Beam Bottom Level)

220
80

a Stirrups 220 8 125 6 21 1040 131.04 0.395 51.77

1
160 6
80 0
b Stirrups 8 125 6 21 800 100.8 0.395 39.83
1
6 160
0

G SOAKPIT

d=1850+Ld

a Middle Ring 8 200 1 1 6289 6.289 0.395 2.49 L=Pi*d

d=1450+Ld

b Inner Ring 8 200 1 1 5033 5.033 0.395 1.99 L=Pi*d

c Main Bar Along both Direction 8 200 1 2 1650 3.3 0.395 1.31
1650

d " 8 200 1 4 1600 6.4 0.395 2.53


1600
e " 8 200 1 4 1440 5.76 0.395 2.28
1440

f " 8 200 1 4 1130 4.52 0.395 1.79


1130

g " 8 200 1 4 400 1.6 0.395 0.64


400

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
400 (mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

h Top Bar Along Radial Direction 8 200 1 8 425 3.4 0.395 1.35
425
H SEPTIC TANK

200
6
a Stirrups for Concealed Beam 5 8 150 1 13 670 8.71 0.395 3.45
70

1850
b 10Ø Longitudional Bar for CB-Top Bar 10 1 2 1970 3.94 0.617 2.44

60
60

c 10Ø Longitudional Bar for CB-Bottom Bar 10 1 2 1970 3.94 0.617 2.44
60 1850
60
Bed RCC Bars

d Bottom Mesh Bar-Along Length Wise 8 200 1 12 5550 66.6 0.395 26.32
50 5450
50

e Bottom Mesh Bar-Along WIdth Wise 8 200 1 28 2300 64.4 0.395 25.45
50 2200 50
f Septic Tank Slab Cover

g 8Ø Bottom bar along Width wise 8 1 23 1970 45.31 0.395 17.91


60 1850 60

h 8 1 8 1050 8.4 0.395 3.32


60 930 60

i 8 1 8 450 3.6 0.395 1.43


60 330 60

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

1215 1475
j 8Ø Bottom bar along Length wise 8 1 9 7650 68.85 0.395 27.20
60 4840 60

1215
k 8 1 4 3780 15.12 0.395 5.98
60 2445 60

l 8 1 4 920 3.68 0.395 1.46


60 800 60

m 8 1 4 445 1.78 0.395 0.71


60 325 60

1
n Top Bars-Along Width Wise 0 8 1 8 620 4.96 0.395 1.96
0 520

o 100 8 1 8 620 4.96 0.395 1.96


520

p Top Bars-Along Length Wise 7 8 1 9 1250 11.25 0.395 4.45


5 1175

q 75 8 1 9 1250 11.25 0.395 4.45


1175

r Corner Bars 500 10 1 30 500 15 0.617 9.26

I SILL BAND
Longitudinal Bars

3400 75
800
800
a Grid 1/A-B ,Grid 3/A-B 10
75 2 2 6350 25.4 0.617 15.68
75 600 600

1175 75
1700
b Grid 2/A-B 10 1 2 2950 5.9 0.617 3.65
75

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
75 (mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

2650 75
425
425
c Grid A/1-2, B/1-2 10 2 2 4950 19.8 0.617 12.23
75
75 600 600

2150 75
175
175
d Grid A/2-3 10 1 2 3850 7.7 0.617 4.76
75
75 600 600

e Partition Wall between Grid A & Grid B 10 1 2 3600 7.2 0.617 4.45
3600

f Partition Wall between Incinerator Holes 10 1 2 1400 2.8 0.617 1.73


1400

g Partition Wall between along D3 10 1 2 900 1.8 0.617 1.12


525 375

h Partion Wall for Urinal 10 1 2 700 1.4 0.617 0.87


700

Ties

65 65
i Grid 1/A-B ,Grid 3/A-B 8 150 2 33 320 21.12 0.395 8.35
190

65 65
j Grid 2/A-B 8 150 1 20 320 6.4 0.395 2.53
190

65 65
k Grid A/1-2, B/1-2 8 150 2 23 320 14.72 0.395 5.82
190

65 65
l Grid A/2-3 8 150 1 16 320 5.12 0.395 2.03
190

65 65
m Partition Wall between Grid A & Grid B 8 150 1 23 320 7.36 0.395 2.91
190

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

50 50
n Partition Wall between Incinerator Holes 8 150 1 9 170 1.53 0.395 0.61
70

50 50
o Partition Wall between along D3 8 150 1 7 170 1.19 0.395 0.48
70

50 50
p Partion Wall for Urinal 8 150 1 5 170 0.85 0.395 0.34
70

J Lintel Band
Longitudinal Bars

3400 75
800
800

a Grid 1/A-B ,Grid 3/A-B 75


10 2 2 6350 25.4 0.617 15.68
75 600 600

3400 75
800
800

b Grid 2/A-B 10
75 1 2 6350 12.7 0.617 7.84
75 600 600

2650 75
425
425

c Grid A/1-2, B/1-2 10


75 2 2 4950 19.8 0.617 12.23
75 600 600

2150 75
175
175

d Grid A/2-3 10
75 1 2 3850 7.7 0.617 4.76
75 600 600

e Partition Wall between Grid A & Grid B 10 1 2 3700 7.4 0.617 4.57
3600

f Partition Wall between Incinerator Holes 1400 10 1 2 1500 3 0.617 1.86

g Partition Wall between along D3 10 1 2 2950 5.9 0.617 3.65


2950

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

h Partion Wall for Urinal 10 1 2 700 1.4 0.617 0.87


700
Ties

65 65
i Grid 1/A-B ,Grid 3/A-B 8 150 2 33 320 21.12 0.395 8.35
190

65 65
j Grid 2/A-B 8 150 1 33 320 10.56 0.395 4.18
190

65 65
k Grid A/1-2, B/1-2 8 150 2 23 320 14.72 0.395 5.82
190

65 65
l Grid A/2-3 8 150 1 16 320 5.12 0.395 2.03
190

65 65
m Partition Wall between Grid A & Grid B 8 150 1 23 320 7.36 0.395 2.91
190

50 50
n Partition Wall between Incinerator Holes 8 150 1 10 170 1.7 0.395 0.68
70

50 50
o Partition Wall between along D3 8 150 1 21 170 3.57 0.395 1.42
70

50 50
p Partion Wall for Urinal 8 150 1 5 170 0.85 0.395 0.34
70

K Wash Basin Slab


Left Portion

a At Long Side 250 8 150 1 5 2175 10.875 0.395 4.3


1825 100

b At Short Side 8 150 1 13 775 10.075 0.395 3.99


540 235

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)
Right Side Portion

c At Long Side 8 150 1 5 2325 11.625 0.395 4.6


250 1825 250

d At Short Side 8 150 1 13 775 10.075 0.395 3.99


540 235

L Manhole Cover Slab- Septic Tank ( 2 Nos )

a Along Long and Short Direction 8 150 2 10 750 15 0.395 5.93


50 650 50

M INCINERATOR
a 630*505 Grill Mesh

b 8 mm dia bar of length 630 8 25 1 21 630 13.23 0.395 5.23


630

c 8 mm dia bar of length 505 8 25 1 26 505 13.13 0.395 5.19


505

d Precast Cover Slab-Long Bar 8 150 1 5 1000 5 0.395 1.98


1000

e Precast Cover Slab-Short Bar 700 8 150 1 7 1000 7 0.395 2.77

Total of Reinforcement Work 2127.19 Kg


2.12719 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,T(S)F
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Truss Calculation Details-T(S)-F


Total Total Wt.
S.N Description Notation Nos Length Breadth Thickness Wt/m Wt/m3
Length (Kg)
1 Top Chord TP dia 40 M 3 4.665 13.995 5.03 70.4
2 Bottom Chord BC dia 40 M 3 3.75 11.25 3.56 40.05
3 Vertical Strut VS dia 40 M 3 0.561 1.683 3.56 6.00
4 Diagonal Strut DS dia 32 M 6 0.912 5.472 3.1 16.97
5 Purlin P dia 50 1 47.6 47.6 5.06 240.86
6 Truss Base Plate TBP 10 mm 12 0.25 3 0.25 0.01 7850 58.88
7 Truss Cleat for Purlin TCP 10 mm 140 0.2 28 0.09 0.01 7850 197.82
8 Purlin Eves Plate PEP 3 mm 12 0.125 1.5 0.075 0.003 7850 2.65
9 Truss Eves Plate TEP 3 mm 6 0.125 0.75 0.06 0.003 7850 1.06
10 Anchor Bolt AB 16 dia 16 0.45 7.2 1.58 11.38
11 Truss Base Plate Support SC 10 mm 12 0.114 1.368 0.025 0.01 7850 2.69
12 Runner Purlin Cleat RPC 10 mm 4 0.175 0.7 0.07 0.01 7850 3.85
13 Purlin Cleat 10 mm 16 0.175 2.8 0.075 0.01 7850 16.49
14 Truss Support Cleat 10 mm 32 0.063 2.016 0.04 0.01 7850 6.34
15 Runner Pipe NB 40 1 6.8 6.8 3.56 7850 24.21
Total of Truss Work 699.65

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,T(S)F
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Toilet
S. No. Description Quantity Unit Remarks
Block
A. Common Installation
1.2 Stand Alone 6 A DP MCB with Enclosure 1 1.00 nos.
B School Blocks
1 DISTRIBUTION BOARDS nos.
1.4 Stand Alone 6 A DP MCB with Enclosure 1.00 1.00 nos.
3.1 One Way Light Point 5.00 5.00 pts.
6 Sweep Ceiling/Exhaust Fans/ Wall Fan
6.1 225mm dia M/D Exhaust Fan 2 2.00 no.
7 Light Fixtures/Luminaires & Accessories
7.5 7W LED Wall Light 1.00 1.00 no.
7.6 9W LED Surface Mounted Cylindrical type 1.00 1.00 no.
7.7 6W LED Recessed Mounted Circular type 3.00 3.00 no.
7.8 7W LED T5 Slim Mirror Light 1.00 1.00 no.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: T(S)F
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha
Length
S. No. Description No. Quantity Unit Remarks
(m)
1 WATER SUPPLY INSTALLATION
a CPVC pipes SDR-11
40 mm 1 55 55.00 r.m
25mm 1 18 18.00 r.m
20mm 1 10 10.00 r.m
15mm 1 2.5 2.50 r.m
c CPVC Ball Valve
40 mm 2 2.00 nos.
25 mm 3 3.00 nos.
20 mm 3 3.00 nos.
d 40mm dia Gun Metal Check Valve 1 1.00 nos.
e Electrical Centrifugal Water Pump 1 1.00 nos.
f 1000 litres Capacity Water Storage Tank 1 1.00 nos.
2 Sewer, Rain and Waste Water Installation
110 mm 1 32 32.00 r.m
75mm 1 25 25.00 r.m
50mm 1 2 2.00 r.m
B School Blocks
1 SANITARY INSTALLATION
a Stainless Steel Kitchen Sink 1 1.00 Set
b CP self closing bib cock 1 1.00 No
c PVC Multi-floor trap with cover 1 1.00 No.
d CP Waste Coupling and PVC bottle trap for water trough 1 1.00 No.

Sanitary Installation
a Water Closet Set 1 1.00 set
b Orissa Pan 2 2.00 set
c Hand Wash Basin 1 1.00 set
d Ladies Urinal 2 2.00 set
e Self Closing Bib Cock 6 6.00 nos.
f CP Spreader in Urinal 2 2.00 set
g Toilet Paper Holder 1 1.00 nos.
h Commode Spray 1 1.00 nos.
i PVC Multi Floor Trap 5 5.00 nos.
j Waste Coupling and PVC Bottle Trap 2 2.00 nos.
k 40mm SS Grab Bar-Side 1 1.00 nos.
l 40mm SS Grab Bar-Rear 1 1.00 nos.
m CP Foldable Hinge 2 2.00 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Site Development
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Length Breadth Height


S.No Description No. Qty. Unit Remarks
(m) (m) (m)
1 Site Clearance
Infront of Bldg
3-6C(S) 1 6.52 1.50 9.78
1 10.05 2.50 25.13
Side of 3-6C(S) 1 5.45 1.50 8.18
2-4C(S) 1 5.70 1.00 5.70
1 10.05 2.50 25.13
Side of 2-4C(S) 1 5.42 1.00 5.42
1 6.82 1.00 6.82
Way to Toilet Block 1 38.64 1.50 57.96
Ramp between 3-6C(S) and 2-4C(S) 1 5.50 1.55 8.53
Total 152.63 sq.m
2 Earth Work Excavation
Infront of Bldg
3-6C(S) 1 6.52 1.5 0.15 1.47
1 10.05 2.5 0.15 3.77
Side of 3-6C(S) 1 5.45 1.5 0.15 1.23
2-4C(S) 1 5.70 1 0.15 0.86
1 10.05 2.5 0.15 3.77
Side of 2-4C(S) 1 5.42 1 0.15 0.81
1 6.82 1 0.15 1.02
Ramp between 3-6C(S) and 2-4C(S) 1 5.50 1.56 0.15 1.28

Excavation For Boundary Wall


Chain Link Fence 35 0.15 0.15 0.60 0.47
Excavation For Gate Column
Column 2 1.20 1.20 1.50 4.32
Excavation For Flag Pole
Flag Pole 2 0.60 0.60 1.00 0.72
2 1.10 0.50 0.15 0.17
2 1.60 0.25 0.15 0.12
1 0.60 0.40 0.15 0.04

For Stone Masonary 1 4.00 1.00 0.45 1.80


Total 21.84 cu.m

3 Earth Back Filling


Total Excavation Work 1 21.84 21.84
Deduction
Soling -1 0.52 Volume -0.52
P.C.C.(1:3:6) -1 1.14 Volume -1.14
RCC -1 0.99 Volume -0.99
Total 19.19 cu.m

4 Boulder Soling
Infront of Bldg
3-6C(S) 1 6.52 1.50 0.15 1.47
1 10.05 2.50 0.15 3.77
Side of 3-6C(S) 1 5.45 1.50 0.15 1.23

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
2-4C(S) 1 5.70 1.00 0.15 0.86
1 10.05 2.50 0.15 3.77
Side of 2-4C(S) 1 5.42 1.00 0.15 0.81
1 6.82 1.00 0.15 1.02
Way to Toilet Block 1 38.64 1.45 0.15 8.40
Ramp between 3-6C(S) and 2-4C(S) 1 5.50 1.55 0.15 1.28
Soling For Gate Column
Column 2 0.90 0.90 0.20 0.32
Stone Soling for Flag Pole 1 0.70 0.80 0.35 0.20

For Stone Masonary 1 4.00 1.00 0.15 0.60


Total 23.72 cu.m
5 P.C.C.(1:3:6) Works
PCC For Gate Column
Column 2 0.90 0.90 0.08 0.12
PCC For Flag Pole
Flag Pole 2 0.30 0.30 1.20 0.22
1 2.40 0.80 0.10 0.19
2 0.30 0.30 0.08 0.01
For Stone Masonary 1 4.00 1.00 0.15 0.60
Total 1.14 cu.m
6 P.C.C.(1:2:4) Works
Infront of Bldg
3-6C(S) 1 6.52 1.50 0.08 0.73
1 10.05 2.50 0.08 1.88
Side of 3-6C(S) 1 5.45 1.50 0.05 0.41
2-4C(S) 1 5.70 1.00 0.08 0.43
1 10.05 2.50 0.08 1.88
Side of 2-4C(S) 1 5.42 1.00 0.05 0.27
1 6.82 1.00 0.05 0.34
Way to Toilet Block 1 38.64 1.45 0.05 2.80
Ramp between 3-6C(S) and 2-4C(S) 1 5.50 1.55 0.08 0.64
Total 9.39 cu.m
7 P.C.C For R.C.C. Works
R.C.C. Works M20
A Foundation
Gate Column Footing
Footing 2 0.90 0.90 0.25 0.41
B Column
Gate Column 2 0.30 0.30 2.95 0.53
Top RCC Coping 2 0.59 0.59 0.05 0.03
2 0.175 0.05 0.02
Total 0.99 cu.m
8 Silica Cement Admixture
10 Kg per cu.m. of R.C.C. M20 10.00 0.99 9.90
Total 9.90 Kg
9 Steel Reinforcement
For gate 1 106.90 106.90
Total 106.90 Kg
0.11 Tons
10 Formworks
A Entrance Gate-Foundation 2 3.60 0.35 2.52
Gate Column 2 1.20 3.15 7.56
Flag Pole Steps 2 0.25 0.80 0.4

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
Flag Pole Masonry Top Surface 1 1.70 0.50 0.85
Total 11.33 sq.m

11 Stone Masonary Works


For Prevention of Septic Tank 1 4 0.73 1.5 4.35
Total 4.35 cum

3.2 BRICK MASONRY WORKS ( 1 : 4


c/s ) 2 0.54 0.23 1.85 0.46
Gate Column
2 0.3 0.23 0.45 0.06
Between two Bldgs 1 7.35 0.23 1.35 2.28
Curve portion 2 2.45 0.23 1.35 1.52
In side of Ramp 2 4.7 0.23 0.60 1.30
Infront of 2-4C(S) 1 17.2 0.23 0.45 1.78
1 1.65 0.23 1.35 0.51
7.91 cu.m
13 Full Brick (230 mm) Works (1:4c/s)
Flag Pole Base 2 0.8 0.23 0.55 0.20
Total 0.20 cu.m

14 Neat Cement Skirting works


Gate Column 2 2.36 4.72
Total 4.72 r.m

15 Metal Works (Fence)


Total
Description Nos length Kg/m Total
Length
Chain Link Fence
ISA 40x40x4mm 2 85 170.00 2.40 408.00
ISA 50x50x5mm 35 1.9 66.50 3.80 252.70
Bracings 7 2.5 17.50 2.40 42.00
Incinerator Vent Pipe 1 2.416 17.5 42.28 M=17.5 Kg/m
Total 744.98 k.g

16 Metal work (Entrance Gate)


Metal Gate
50mm Dia MS Pipe 2 7.13 14.26 3.61 51.48
25mm Dia MS Pipe 56 0.7 39.20 1.58 61.94
Middle sheet 1 0.74 0.0012 7850 6.97
Hole Fast 4 0.45 1.8 3.61 2.92
Total 123.31 k.g

17 External Plaster
Column Inside face 4 0.54 1.64 3.54
Column Outside face 2 1.2 0.20 0.48
4 0.54 1.70 3.67
Deduct -2 0.3 1.40 -0.84
Top Coping 2 2.36 0.05 0.24
4 0.59 0.30 0.71
Between two Bldgs 1 7.35 1.58 11.61
Curve portion 2 2.45 1.58 7.74
In side of Ramp 2 4.7 0.83 7.80
Infront of 2-4C(S) 1 17.2 0.68 11.70
1 1.65 1.58 2.61

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
Total 49.26 sq.m

18 Exterior Weather Coat Paint


As per Outside Plaster 1 7.8 7.80
Gate Column Skirting 2 2.36 0.10 0.47
Total 8.28 sq.m

19 Chain Link Fence(50x50 Mesh)


Fencing 1.00 85 1.20 102.00
Total 102.00 sq.m

20 Flag Pole
75 Dia GI Pipe 2.00 1 2.00
Total 2.00 nos

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Site Development
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Size Spacing c/c Structure Rebar Length/pc. Total Weight Per Total Weight
SN Description Shape Remarks
(mm) (mm) Nos Nos (mm) Length (m) Meter (Kg) (Kg)

1 Entrance Gate-Column
75 75
a 900*900 Foundation Mesh 850 10 150 2 12 1000 24 0.62 14.82

b 8-12 dia Column Reinforcement 12 2 8 3770 60.32 0.89 53.62


3050+Ld

220
8 mm dia at 150 c/c for column
c 7
220 8 150 2 26 1030 53.56 0.40 21.16
stirrups-Outer 5

1
7
7 3
8 mm dia at 150 c/c for column 5
d 8 150 2 26 842 43.784 0.40 17.3
stirrups-Outer

Total of Reinforcement Work 106.90 Kg


0.11 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job : Reservoir Water Tank
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Length Breadth Height


S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
1 Site Clearance & Mobilization
For Water Tank 1 4.85 4.6 22.31
Total 22.31 sq.m

2 Earthwork in excavation
For Water Tank 1 3.65 3.40 1.98 24.57
Total 24.57 Cu.m.

3 Earthback Filling
Total Earthwork Excavated 24.57
Water Tank Volume -1 3.35 3.1 1.98 -20.56
Total 4.01 Cu.m.

4 Boulder soling
Below Water Tank 1 3.35 3.1 0.2 2.077
Total 2.08 Cu.m.

5 PCC Work (1:3:6)


Below Water Tank 1 3.35 3.1 0.075 0.78
Total 0.78 Cu.m.

2.2 PCC for RCC Work 1:1.5:3


For Base Slab 1 3.35 3.10 0.18 1.82
For Water Tank Wall
Long Wall 2 3.35 0.18 1.68 1.96
Short Wall 2 2.75 0.18 1.68 1.61
Trianagle Portion
Long Wall 2 3.00 0.05 Area 0.27
Short Wall 2 2.75 0.05 Area 0.25
Slab 1 3.35 3.1 0.15 1.56
Manhole openings -1 0.6 0.6 0.15 -0.05
Total 7.41 Cu.m.

2.3 Silica Admixture


10 Kg per cu.m. of R.C.C. M20 10 7.41 74.15
Total 74.15 kg

2.5 Form works


For Base Slab 1 12.9 0.18 2.26
For Water Tank Wall
Outer Side
Long Wall 2 3.35 1.83 12.23
Short Wall 2 3.10 1.83 11.32
Inside wall
Long Wall 2 3.00 1.53 9.15
Short Wall 2 2.75 1.53 8.39
Trianagle Portion

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Long Wall 2 3.00 0.42 2.54
Short Wall 2 2.75 0.42 2.33
Slab 1 3 2.75 8.25
Side for Manhole openings 1 2.4 0.15 0.36
Deduct Manhole openings -1 0.6 0.60 -0.36
Total 56.46 Sq.m.

3 PLASTERING WALL FINISHING WORKS


3.1.1 CEMENT PLASTER WORKS WITH
PUNNING
Base Slab 1 2.40 2.15 5.16
For Water Tank Wall
Long Wall 2 3.00 1.53 9.15
Short Wall 2 2.75 1.53 8.39
Triangle Portion
Long Wall 2 3.00 0.42 2.54
Short Wall 2 2.75 0.42 2.33
Top Slab 1 3.00 2.75 8.25
Deduct Manhole openings -1 0.6 0.60 -0.36
Total 35.46 Sq.m.

4 Water Proof Coating


Inside Water tank 1 35.46
Total 35.46 sq.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job : Reservoir Water Tank
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha
Bar Bending Schedule
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)
A Outer Vertical Bars 1
1 Shorter Span 10 35 7.01 245.35 0.62 152.12 0.083 0.083

1.915 1.915

3.02

2 Longer span 10 32 7.286 233.152 0.62 144.55


0.083 0.083

1.915 1.915

3.29

B Inner Vertical Bars 2


1 Shorter Span 10 35 2.503 175.21 0.62 108.63 0.079

1.884

0.05
0.49 0.49

2 Longer Span 10 32 2.503 170.204 0.62 105.527 0.079

1.884

0.05
0.49 0.49

C. Extra Bars 2 10 67 1.79 239.86 0.62 148.71 0.6

0.592 0.6 0.6

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)

D. Horizontal Bars(outer 4
0.3 0.3
1 Shorter Span 10 21 3.62 304.08 0.62 188.53

3.02 3.02

0.3 0.3

2 Longer Span 10 21 3.87 325.08 0.62 201.55 0.3 0.3

3.27 3.27

0.3 0.3
E. Base Slab bar 4
1 Shorter Span 10 35 3.14 439.6 0.62 272.55 3.045
0.05 0.05

2 Longer Span 10 31 3.42 424.08 0.62 262.93 3.32


0.05 0.05
F Man Hole Rebar
1 horizontal Rebar -2 10 6 1.2 -14.4 0.62 -8.93 0.9 0.3
Total 1576.17 Kg
1.58 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job : Reservoir Water Tank
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha
Bar Bending Schedule
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)
A Outer Vertical Bars 1
1 Shorter Span 10 35 7.01 245.35 0.62 152.12 0.083 0.083

1.915 1.915

3.02

2 Longer span 10 32 7.286 233.152 0.62 144.55


0.083 0.083

1.915 1.915

3.29

B Inner Vertical Bars 2


1 Shorter Span 10 35 2.503 175.21 0.62 108.63 0.079 0.079

1.884 1.884

0.05
0.49 0.49

2 Longer Span 10 32 2.503 170.204 0.62 105.527 0.079 0.079

1.884 1.884

0.05
0.49 0.49

C. Extra Bars 2 10 67 1.79 239.86 0.62 148.71 0.6 0.6

0.592
0.592 0.6 0.6

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)

D. Horizontal Bars(outer 4
0.3 0.3
1 Shorter Span 10 21 3.62 304.08 0.62 188.53

3.02 3.02

0.3 0.3

2 Longer Span 10 21 3.87 325.08 0.62 201.55 0.3 0.3

3.27 3.27

0.3 0.3
E. Base Slab bar 4
1 Shorter Span 10 35 3.14 439.6 0.62 272.55 3.045
0.05 0.05

2 Longer Span 10 31 3.42 424.08 0.62 262.93 3.32


0.05 0.05
F Man Hole Rebar
1 horizontal Rebar -2 10 6 1.2 -14.4 0.62 -8.93 0.9 0.3
Total 1576.17 Kg
1.58 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer

You might also like