Government of Nepal

National Reconstruction Authority


Central Level Project Implementation Unit (Education)
District Level Project Implementation Unit (Education),Gorkha
Emergency School Reconstruction Project (ESRP), JICA Loan No. : NE-P11
Contract Bills
FINAL INTERIM PAYMENT CERTIFICATE
Period: 15th November 2018 to 10th August 2020
Name of School: Shree Dharmawati S. S. School Payment Voucher no:
Name of Contractor:Sharma-A.M Joint Venture Date of payment:
Contract Number:ESRP/MOE/CLPIU/074/075-GORKHA-15 Page no of measurement book:
Serial no. of previous payment bills: 7
Voucher no.of previous payment bills:
Date of order for commencement of work: 3rd October,2018
Date of work to be completed: 2nd February,2020
Date of completion of work:

Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay Item
Description Unit % completion Remarks
No.
Quantity As per
Rate Amount Quantity Amount Quantity Amount Quantity Amount
BOQ
GENERAL
MOBILIZATION AND DEMOBILIZATION
1 Mobilization of the construction by constructing temporary L.S. 1.00 500,000.00 500,000.00 1.00 500,000.00 0.50 250,000.00 0.50 250,000.00 100.00%
acomodation for labours and site staff with required suitable
SITE OFFICE
facilities and keepingESTABLISHMENT
the same in good hygenic condition for
Providing and completion
Maintainingtime. Site Office of two Per
2 entire project Demolition of Rooms
the same having
and Month 21.00 25,000.00 525,000.00 21.00 525,000.00 22.00 550,000.00 (1.00) (25,000.00) 100.00%
total Area 20 sq.m for
cleaning the site after completion the useofoftheClient and Consultant
construction activities
including
all complete. office[Note:
chair, Table,
50% Lockable
payment file cabinet, Stationery
PROJECT INFORMATION BOARD shall be made after
3 Items (Ink, Paper,
completion Pen, Pencils etc.),
of Fixing
mobilization and 1Information
Computer
remaining and 50% 1 Printer
after nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 - - 100.00%
Providing and of Project board with
with all necessary
completionText
approved of works set up. all complete
as per contract]
in appropriate as per instruction
location including all requiredof
engineer. The
SAFETY SIGN Specification
BOARD of computer shall not be less than
4 fixing accessories as per drawing all complete. nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 - - 100.00%
(19.5"
Providingled and
monitor
Fixing with Core i5,
of Safety Sign7thBoard
Generation, 500 gb Hdd,
with approved Text
8gb ddr
and 4 ram),
Sinage Printerrequired
including should functionfixing ataccessories
least of Printing,
as per
BARRICADING
Scanningall WORKS
and Photocopy of A4 size documents. Providing and R.m
5 drawing
Barricading complete. 110.00 2,000.00 220,000.00 110.00 220,000.00 110.00 220,000.00 - - 100.00%
Maintaining allbetween
above items the onSchool
Rental BasisAcademicfor entire areaproject
and
Construction
completionMATERIALSarea with 1.8 m high CGI Sheet fixed to Bamboo
time.
SAFETY
support frame all complete&asSITE SAFETYof Engineer.
per instruction
6 Providing and Maintaining Construction Safety Measures in L.S. 1.00 100,000.00 100,000.00 1.00 100,000.00 1.17 117,000.00 (0.17) (17,000.00) 100.00%
Construction
LAB TEST(WATER Site withTEST) proper Safety measures to person and
7 work
Testingareaand (Helmet,
ProvidingShoes, Lab Test First Aid for
Report Kit,Quality
Clothing, Glove,
of Water in job 1.00 - - - 0.00 - - - 0.00%
Guard
Water Stream (Up and DownSafety
Rail for edge protection, streem) Net, located
Safety rope, near Fall
by
Protection etc.)site
TEMPORARY
Construction asTOILET
required
before by the Contract
Starting and after Clause GCC 24 and
completion of
8 Specification
Construction work.
construction ofdivision
temporary
This Test 1 toilet
"GENERAL
has to with
be done CGItoREQUIREMENT
Sheet
mark the fixed to
affect nos. 2.00 150,000.00 300,000.00 2.00 300,000.00 2.00 300,000.00 - - 100.00%
CLAUSE
Bamboo 8(C)".
support
of construction Thein and
frame
work number of Safety
waterallstream.
necesary itemsMaterials
including Personal
Septic
ROAD
Protecting
pit, REPAIR
Pipeline,Equipments
Toilet AND MAINTENANCE
Pan(PPE)
etc. forshall be minimum
entire but not limited
project completion time
9 Providing
to
all 35 sets. and
complete as Maintaining
Payment shall be the
per Instruction ofroads
made Engineer.as necessary
in Prorata RateBasis
shall avoid Km.
toinclude
for entire 2.00 50,000.00 100,000.00 2.00 100,000.00 1.86 93,000.00 0.14 7,000.00 100.00%
blockage
duration by
of Landslides
project. and Rockfall
all Material cost with fixing, construction charges and for regular transport of
construction
demolition &materials cleaning and of the sitesame
inspection during overall
after completion of the -
construction
CIVIL WORKS-
construction period.
activities Rate
BUILDING shall
all complete. include all Material cost with -
1 demolition
EARTH WORKS charges, cleaning, fixing & construction charges of -
the same after completion of the construction activities all
SITE CLEARANCE & MOBILIZATION:
complete.
1.1 Clearing and grubbing the site for construction by removing sq.m 1,076.98 100.00 107,698.00 1,141.90 114,190.12 1209.74 120,974.25 (67.84) (6,784.14) 106.03%
150mm
EARTHWORK thick top IN soilEXCAVATION
including bushes,: small trees, leveling of
1.2 undulated ground,
Excavation shortinginand
in foundations all stacking/storing
type of soils forselected top cu.m
foundation, 566.02 400.00 226,408.00 536.53 214,610.94 543.18 217,271.37 (6.65) (2,660.43) 94.79%
soil for reuse in landscaping
trenches, footing, pits etc. to the works,
requireddisposing
depth unsuitable
including
materials
dewatering from site,
by manual etc., all complete as
or :mechanical means etc. as per per drawings,
EARTH BACK FILLING
specifications and
specifications instructions of the Engineer. machinery and
1.3 Back filling inwith all contractor’s
foundation and sidesown of foundation with cu.m 340.79 300.00 102,237.00 349.92 104,976.82 297.88 89,364.00 52.04 15,612.82 102.68%
equipment's,
approved soil providing
obtained from crossing of track, at
the excavation shoring,
site andstrutting,
stacked
timbering
at and buttressing
site or brought from outsidewith in appropriate
layer not materials
exceeding and 15 cmall
BOULDER
such measures
thick (compactedSOLING
necessary : to retain
thickness) in position
including the sidesofofsoil,
transportation the
1.4 Providing
foundation and
spreading pit and
in laying
required uncoursed
including and hand
line refilling thepacked
level, excavated Dry material
sprinkling Rubble
water, cu.m 167.88 6,000.00 1,007,280.00 190.85 1,145,101.40 152.64 915,860.94 38.21 229,240.46 113.68%
Stone
ramming, soling
with watering, inramming,
compactingfoundation, under
leveling
with thefloor
mechanical plinth
siterammers,
and with
disposing out
testing, any
offetc.,
the
special dressing
surplus/unusable
all complete as per of drawing,
earth stone including
to outside the filling andinterstices
construction with
premises,
SAND
suitable FILLING
quarry : or stonespecification
waste chips or quarry
instructions
sand, watering,
of
etc. Engineer.
the all complete as per drawings, specifications and
1.5 Providing and
compacting usingfilling sand in mechanical
appropriate soak pit. allcompaction
complete as per cu.m
means 7.40 6,000.00 44,400.00 4.91 29,435.40 0.00 - 4.91 29,435.40 66.30%
instructions of the Engineer.
drawings, specifications and instruction
with all contractors materials, handling, placing etc. all of the Engineer.
complete as per drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay Item
Description Unit % completion Remarks
No.
Quantity As per
Rate Amount Quantity Amount Quantity Amount Quantity Amount
BOQ
CONCRETE WORKS
2.1 2.1 P.C.C cu.m 28.81 14,000.00 403,340.00 29.39 411,428.06 29.79 417,056.06 (0.40) (5,628.00) 102.01%
2.1.1 P.C.C (1:3:6)
Providing and laying machine mixed Plain Cement Concrete of
P.C.C
nominal(1:2:4)
mix 1:3:6WORKS (1 cement : 3 sand : 6 coarse aggregate ) for
2.1.2 Providing and laying
leveling course machine mixed
in foundations and under Plainfloor
Cement Concreteetc.
of building, of cu.m 48.15 16,000.00 770,400.00 46.42 742,685.74 36.31 580,940.16 10.11 161,745.58 96.40%
nominal mix 1:2:4
in all level with broken (1 cementstone: aggregate
2 sand : 4 of coarse
size aggregate
not more )than for
leveling
25 mmFOR course
of approvedin foundations and
quality including under floor of building,
formwork wherever etc.
P.C.C.
in R.C.C.
all level dewatering,
with broken WORKS :
stone aggregate of size not more than
2.2 necessary,
Providing laying inbatching, mixing,
machinetransporting, placing,
25 mm ofand
compacting, approved
curing,
position
quality
including allincluding
mixed and wherever
lead and(1formwork
lift,
machine
etc. all complete
cu.m 665.02 20,000.00 13,300,400.00 684.62 13,692,491.32 614.41 12,288,233.43 70.21 1,404,257.90 102.95%
vibrated
necessary, cement concrete
dewatering, of mix
batching, 1:1.5:3
mixing, cement:1.5
transporting, sand: 3
placing,
as per aggregate)
coarse drawings, specifications and the instructionsconcrete of the
SILICA
compacting,
Engineer.
CEMENTcuring,M20 gradeallforlead
ADMIXTURE
including reinforced
and lift, cement
etc. all complete
2.3 work kg 6,650.20 300.00 1,995,060.00 6,846.25 2,053,876.27 6144.15 1,843,245.82 702.10 210,630.45 102.95%
as perusing
Providing andapproved
drawings, mixing cement
Silica
specifications Cementwith 20themm
andAdmixture graded machine
of in structural
instructions of the
crushed stone aggregate of approved
concrete at the rate of 2.50% by weight of the cement for
Engineer. quality in various
STEEL
locationsREINFORCEMENT
promoting andworkability,
heights including improvingtransportation
strength, of concrete
achieving to
2.4 Providing and fixing
site of placing, compaction, in position Fe 500 steel
finished toprevention, reinforcement
required lineetc. and Silicaof
level, Mt. 106.42 130,000.00 13,834,600.00 107.73 14,004,637.71 113.70 14,781,592.04 (5.98) (776,954.34) 101.23%
waterproofing properties, bleeding
various
protection diameter
and confirming
curing, etc. to
all relevant
complete
Cement Admixture shall be the product of Silica Japan or IS as code
per in R.C.C.
drawings,
FORM
works WORKS
including
specifications straightening,
and the instructions cutting,ofbending, binding with
theas Engineer, but
superior and shall meet the requirements mentioned in
2.5 Supplying
20 SWG annealedandcostlaying
wire centering,
for tying shuttering
the of various
reinforcement pattern
bars at sq.m 4,399.99 800.00 3,519,992.00 4,656.76 3,725,410.41 4180.14 3,344,113.14 476.62 381,297.28 105.84%
excluding
specification the of centering,
of materials shuttering,
and Workmanship, and –each
reinforcement,
Division 4:
formworks
junctions
all complete with
(binding
as 19/12
per wire mmshall
drawings, thick water
not be
specifications proof
measured plyinstructions
and wood & steel
separately) of
Concrete Works, Article 2.4
adjustable
including
3.
theBRICK
Engineer. props
all for all
waste
MASONRY kinds
andWORKScut of RCC provision
pieces, works for for foundations,
adequate
3.1 columns,
numbers
3.1 BRICK ofshear walls,chairs,
spacers,
MASONRY beams,
WORKS slab,( 1staircase,
providing and
: 4 c/s lintel,
placing
) ONE sill,
cement
SIDE cu.m 184.75 20,000.00 3,695,000.00 - - - - 0.00%
pergola,
mortar (1:1)
FAIRFACE including
cover blocks nails,to keep
proppingthe barsscaffolding, staging,
in intended position
supporting
at all levels
Providing andand bracing
alllaying
completefirstinas proper
perselected
class lines and
drawings, level,pressed
sealingwire
specifications
factory the
and
CLEAR
joints
cut Fairwith
instructionsFaceSILICON
heavy
of brick duty
the Engineer. WATER-REPELLANT
brown
(machine self adhesive
(Authorized
made brick)
lapone tape,
length COATNG
aligning
or more
and for to
brick
the
7.2.3 sq.m 919.15 550.00 505,532.50 - - - - 0.00%
Providing
line wall and
and
bar length
thick levels Applying
exceeding
in cement including
10 Water
mortar
meter 1:4inRepellant
Ties,(1
length
cement Coating
PVCshall Spacer,
: 4coarse onProviding
be measuredExposed
sand)for in
Brick
POINTING
openings/ Surface
the payment,
,superstructure WORK
cutouts/ using IN
and pockets,
except to
other Silicone
BRICK
column). Base
MASONRY
applyingplaces
specified MC-Nisiwa
De-shuttering Providing
in all heights SH
chemical, or
and
and
8.1.1 equivalent
applying at or superior
allaslevels including
Pointing Works cleaning brick
in Cement surface
Mortar using
1:2 (1 sq.m 919.15 400.00 367,660.00 - - - - 0.00%
De-shuttering
level including approved
the cost ofby the
single Engineer
or multi etc.,
stagecomplete at all
self standing
brick
cement
levels cleaning
as:2perfine
scaffolding, chemical,
sand)
drawing,
soaking single
on the & or
specifications
bricks, curing, multi-stage
face of
andbrick
raking joints,scaffolding,
masonry
instructions
provision etc.
ofwall
the
for
BOQ Total of items 3.1., 7.2.3 8.1.1:
all complete
including mixing as per
mortar, manufacturer's
laying in instruction,
perfect
Engineer.openings, toothing etc., all complete as per drawing,
recesses, line, project
level and - - - -
specification
plumb
specifications and
andinstruction
and finishing in regular
instructions ofof the
and
theEngineer.
even surface ,all complete
Engineer.
as per drawing , specification and instruction of the Engineer.
Replaced items 3.1, 7.2.3 and 8.1.1 with following items for
- - - -
3-LaLiEACCr(F). 3-9C(SF) and Tc(S)

Brick Masonry Works (1:4 c/s) cu.m 18,000.00 - - - -


Cement Plaster Works on Outer Wall (1:6) sq.m 600.00 - - - -
Exterior Weather Coat Paint sq.m 350.00 - - - -
- - - -
BRICK MASONRY WORKS ( 1 : 4 c/s )
Providing and laying first class chimney fired brick one or
3.2 cu.m 121.32 18,000.00 2,183,760.00 298.98 5,381,583.42 244.02 4,392,293.09 54.96 989,290.33 246.44%
more brick thick wall in cement mortar 1:4 (1 cement : 4
coarse
HALF sand) BRICK in foundation
WORKS (up 1 :to4 plinth, superstructure
c/s ) Providing and layingand
3.3 other specifiedhalf
non-fairfaced places
brick in work
all heights
masonry and in level
cementincluding
mortarthe 1:4cost
(1 sq.m 71.94 1,500.00 107,910.00 87.62 131,435.69 44.75 67,119.00 42.88 64,316.69 121.80%
of single sand)
cement:4 or multi stage scaffolding,
in superstructure soaking bricks,
with approved first classcuring,
fired
raking joints,
bricks in COMB provision
perfect line for recesses,
& level, openings,
required size toothing etc.,
and shape at any all
HONEY
complete BRICK WORKS (1:3 c/s)
height andaslevel,
per drawing,
including specifications
the cost of and singleinstructions
or multi of the
stage
3.4 Engineer. Providing and laying honey comb cu.m 3.52 9,000.00 31,680.00 4.81 43,275.15 4.81 43,275.15 136.60%
scaffolding, cleaning, soaking of the bricks, packing of the
brick one or more brick thick wall in cement
joints, raking joints, provision for recesses, openings, curing, mortar 1:3
(1 cement
DOORS
providing :WINDOWS
3 coarse
&25x3mm GIsand) WORKS
Straps inFixed
soak pit in all heights
to columns at every and5th
4.1
levelMETAL
course including
of brick FRAMEthe cost
and 60mm of width
soaking 14 bricks,
gauge weldedcuring, Providing
raking
GI mesh
4.1 - - - -
and fixing
joints,
anchored in
provisionposition
to GI strap, in required
for recesses,
all complete line and
openings, level
as pertoothing pressed
design, etc., all
drawing,
(folded)
complete Steel
specifications door
as per and window
drawing,
instructions theframe
ofspecifications
Engineer.of sizeand shown in
instructions
drawings
4.1.1 of
DoortheFrame manufacture from galvanized iron sheet of 1.20 mm
Engineer. rm. 313.04 1,100.00 344,344.00 320.11 352,121.00 303.24 333,564.00 16.87 18,557.00 102.26%
4.1.2 thick
Window including
Frame hinges, jamb, lock jamb, head, base ties of 1.2 rm. 786.59 1,100.00 865,249.00 880.34 968,374.00 766.16 842,776.00 114.18 125,598.00 111.92%
mm pressed GI welded on rigidly fixed together by
4.2 METAL SHUTTER -
mechanical means, adjustable lugs with split end tail to each
WINDOW
jamb including SHUTTER
steel buttProviding,
hinges 2.5 fabrication
mm thick with and installation
mortar
4.2.1 in position 35 mm thick glazed window and ventilator shutter sq.m 171.18 7,500.00 1,283,850.00 144.90 1,086,749.25 171.18 1,283,850.00 (26.28) (197,100.75) 84.65%
guards, reinforcing to door hardware, strike-plate, shock
made withas1.2mm
absorbers thick
required, galvanized
factory applied ironZinc
sheet Richfolded
Primerin etc.,
4.3 WOODEN
required sizeSHUTTER
and -
all complete as pershape including
drawings, glazing with
specification and 5instruction
mm thick of
FLUSH
clear floatDOOR
the Engineer. glass SHUTTER
with glazing (32MM)
beads, Providing
washer and & fixing
special glazing
4.3.1 32mm thick solid
putty, required core flush
numbers and door
sizes shutters,
hardwareinlike single leaf tower-
hinges, or sq.m 120.78 8,000.00 966,240.00 117.98 943,812.40 0.00 - 117.98 943,812.40 97.68%
double leaf as per
bolts, handles, detailedapplying
eye-hook, drawing.primingThe flush coatdoors
withshall
Zincbe Rich
UPVC
factory
Primer of DOOR
made solid core
approved make,block
etc.,board shuttersas
all complete bonded with
per drawings,
4.4.1 SHUTTER/FRAME
phenol formaldehyde resin. The lipping shall be of teakwood sq.m 14.28 9,000.00 128,520.00 13.79 124,146.00 13.794 124,146.00 - - 96.60%
specification and instruction of the Engineer.
Providing
all-round the and
flushfixing
door towithdoor frames 24thickness
a minimum mm thickoffactory 12mm.
WINDOW
made PVC door GRILL shutterProviding,
made ofMS solid
styles bars
and(a)railsofofrequired
UPVC size
4.5 The following C.P. fittings shall be used: - 2-150 mm sq.m 102.09 2,500.00 255,225.00 151.68 379,199.75 95.86 239,650.00 55.82 139,549.75 148.57%
and fixing in position mild steel grille made with required MS
hollow section
Handles in eachofleaf;
size(b)59 Tower-bolt
x 24 mm and wallmm
– 300 thickness
long at2top mm 1� in
flats,
0.2 mmstrips,
with bars fabricated
inbuilt edging as
on per
both drawings,
sides. The fixing
stylesin and
position
rails
each leaf and 200 at
COLLAPSIBLE bottom in each leaf; ( c ) 1 no. 300 mm
GATE
using
motred approved
and fasteners
jointed including
at theGodrej
corners by2means
coat ofofenamel and Zinc
4.6 long C.P. Aldrops with made padlock; (d) 125 mm sq.m 20.35 10,000.00 203,500.00 19.99 199,856.25 19.9245 199,245.00 0.06 611.25 98.21%
Rich PrimerSupplying
base coat,
galvanized/plastic and
etc.,fixing
brackets allsizein75position
complete localhaving
as mm
detailed makein wall
heavy duty gate
collapsible GI But Hinges 3ofnos.
ofand
approved in each
sizesteel
and
x 220
make leaf. (rate shall
properly fabricated
drawing,
thickness specification and instructions of the Engineer.
include
with all1.0 mm
required doorstainless
hardware). screws. The styles of the
shutter reinforced by inserting galvanized tube of size 20centers
vertical double channels 20 x 10 x 2mm at 100mm x20
and braced with M.S. flat diagonal 20 x
mm and 1 mm � 0.1 mm wall thickness. The lock rail made of 5mm, with top and
bottom
Prepared by contractor railsaof
'H' section, T ironhollow
UPVC 40 x 40
Checked x 6mm
sectionby of with
size 38mm
Consultant,100 x 24 diamm
DSC steeland 2 Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
pulleys
mm� complete with bolts nuts locking arrangements steppers
handles
0.2 mm including
wall thickness applying
fixeda topriming
the shuttercoat styles
of ZincbyRich means Primer
of a
carriage hoisting alliron
plastic/galvanized complete
'U' cleats.as per
Thespecification
shutter frameand shall be
direction of the Engineer.
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay Item
Description Unit % completion Remarks
No.
Quantity As per
Rate Amount Quantity Amount Quantity Amount Quantity Amount
BOQ
5. FLOORING WORKS
5.1 HARDENED CEMENT CONCETE FLOOR sq.m 2168.59 900.00 1,951,731.00 2,153.38 1,938,039.30 2121.33 1,909,194.59 32.05 28,844.71 99.30%
Providing, laying in required line, level and
pattern 40 mm thick IPS floor finish with cement concrete of
mix 1:2:4
NEAT CEMENT(1 cementSKIRTING : 2 sand : 4 crushed stone aggregate 12
5.2 -mmdo and down grade)
- as above, but forlaid 100inmm alternate panel or providing glass
high skirting. r.m 1025.05 100.00 102,505.00 1,069.32 106,932.00 1132.031 113,203.10 (62.71) (6,271.10) 104.32%
dividing strips
TERRAZZO CAST-IN SITU and finished withDADO approved floor hardener
5.3 (Dreitop FH
Providing andoflaying
equivalent 25 mm floorthick hardener)
terrazzoapplied cast-in-situ as perdado up sq.m 72.27 1,500.00 108,404.99 94.85 142,268.25 89.948 134,922.00 4.90 7,346.25 131.24%
manufacturer's
to the height shown instructions
in drawing including
with marblemixingchips laying in required
rubbed and
6 slope,
ROOFING/
polished intrigal finishing
TERRACING
to granolithic using
finish WORKSappropriate power
under layer of 19 mm thick trowelling -
equipment,
cement concrete
METAL WORKS(TRUSS) etc. all complete
1:2:4 (1 cementas per
: 2drawing,
sand : 4 specification
crushed stone and
6.1 instructions
aggregate
Providing 10
andofmm theand
fixing Engineer.
down grade)
tubular base and
roof trusses withtop layer purlins,
rafters, of 6 mm kg 871.25 220.00 191,675.00 999.81 219,957.37 870.91 191,601.18 128.89 28,356.19 114.76%
thick with
wind required etc.,
ties, brackets colormade marble with chips of sizes
required grade from mild1 mm steelto 4
mm
tubesnominal
CGI and mild
SHEET sizesteel
ROOFINGlaidsections
in cement marble powder
of required mix 3:1 (3
sizes, including
6.2 cement
hoisting, : 1 marble
fixing in powder
position mix
with : 7
MS marble
bed chips)
plates, by
shoe
Providing & fixingvolume
angles, sq.m 57.90 2,000.00 115,800.00 58.93 117,854.00 57.90 115,800.00 1.03 2,054.00 101.77%
including
anchor
precoated bolts cement
etc., and
galvanized slurry, iron required
concreteprofile pigment,
grouting,
Terracota grinding,
concreting
colour sheets polishing,
nut bolts,
(size,
buffing
fabrication,
shape andandpitchapplying
fixing of and sealer
treated
corrugation coat, as etc.,
with twoallcoats
approved complete
byofEngineer) as per 0.52
anticorrosive
CGI SHEET ROOFING RIDGE
6.3 drawing,
paints all
mm +/- 5%&total specification
complete as
coated and
per instruction
drawings,
thicknessplain (TCT), of the
specifications Engineer.
Basematching and
Material to rm. 12.10 1,200.00 14,520.00 12.00 14,400.00 12.10 14,520.00 (0.10) (120.00) 99.17%
Providing laying prefinished (colour
instructions(BMT)
Thickness of the of Engineer.
0.50 Ridge
mm, Rate Zinc shall include
coating 120gsmpreparing shop
roofing
GI FACIA sheet) CGI Sheet
(EAVES) Cover of 0.52 mm +/-as5% per IS:
total
drawings,
277 , 5-7 obtaining
microns epoxyEngineer's
primer or
onClient's
bothThickness
sideapproval,
of the(BMT) supplying,
sheet and
6.4 coated thickness
Providing, (TCT),
fabrication Base Material
to required size and shape of
and kg 90.47 250.00 22,617.50 143.52 35,880.78 82.25 20,562.50 61.27 15,318.28 158.64%
fabricating,
polyester delivering
top coat 15-18 at site,
microns. hoisting and
Sheet should fixing in
havewithposition,
protective
0.50
fixingmm (Coating
in position andmm
1.2 Primer asGIabove)
thickCEILING folded over
plates ridge
of size all
shown
temporary
guard
CEMENT film staging,
of
BOARD preparation
25accessories
microns FALSE minimum of surface,
to avoid applying
scratches Zinc Rich
while
6.5 required
in drawing fixing
including theallcost like self tapping
fixing brackets, screw,
flats, clips,
screws, sq.m 30.88 1,500.00 46,320.00 48.40 72,600.00 38.55 57,825.00 9.85 14,775.00 156.74%
Primer
Providing of one
transportation and coat
and
fixing before
shouldat and
be one6coat
supplied
height mm inafter
single
thick erection
length
Cement including
up
Board to 6
clamps,
painting washer
with etc.all
enamel complete on building floors as per
two
meter
false coats
design, asofdesired
ordrawing,
ceiling, synthetic
including bywithenamel Zincpaint
Engineer.
providing
specifications
Rich
The
and ofPrimer,
approved
sheet
fixing
instructions shall
of
of
required
make
beEngineer.
frame
the fixed andusing
work
7. PLASTERING/
scaffolding allto work WALL
at any FINISHING
height, WORKS
color
self
made etc.
drilling
of special complete
/self tapping
sections aspower
per
screws ofetc.,
drawing,
pressed all complete
sizespecification
(5.5x
from 55mm)
MS as
and
sheet per
with
7.1 CEMENT
design, drawing, PLASTER
specifications WORKS instructions
instruction
EPDM
7.1.1 Galvanized seal of
etc.,the Engineer.
all complete
coating up any pitchofangle
toconsisting inthe Engineer.
horizontal/
ON INNERwith WALL zinc (1:6) and hanger of sq.m 1,967.29 600.00 1,180,374.00 2,061.55 1,236,932.00 1964.12 1,178,470.80 97.44 58,461.20 104.79%
vertical or curved
25x25x0.55 of and surfaces
required lengthexcluding
at 1250mm the cost of purlins, rafters
Providing applying at all levels andc/cshape fixed 20tomm purlins
and
with trusses
nut ans and
bolts including
and other cutting
end
thick cement plaster in building inside in specified cement ofto size
angle and
hanger shape beingwherever
fixed
required.
with nut and bolts to GI main channel 45x18x0.6 running at the
mortar
ON in two layers
CEILING (1:4)as 6 to 8 mm thick final coat with 1:6 (1
rate of 900mm c/c to cementwhich ceiling section 0.55mm thick thick
7.1.2 cement
12.5.mm, :6 fine thick sand) cement andmortar sand plasterover the work 12 toof 14 mixmm 1:4 (1 sq.m 1,393.11 500.00 696,555.00 1,705.21 852,607.43 1380.69 690,347.00 324.52 162,260.43 122.40%
bottom
1:6 (1 cementwedge of 45mm
: 6 coarse with tapered
sand)surface,
under coat flanges of
in allsurface26mm each
surfaceatatallall
cement & 4 sand) in concrete ceiling
having clips of 2.3mm at 613mm with ceiling section and
heightON
7.1.3 including mixing mortar, laying in perfect line, level
perimeter OUTER channels of WALL 0.5mm (1:6):
thick 25mm high having flanges
and plumb and finishing in regular and even surface including
7.1.3.1 EXTERNAL
of 20mm and 30mm
all necessary
PLASTER long, the perimeter of ceiling making fixedgrooves
to sq.m 1,142.89 600.00 685,734.00 1,728.56 1,037,136.00 1596.80 958,077.00 131.77 79,059.00 151.24%
Providingsingle
wall/partition and applying
with
or multi-stage
the help at all
of raw
scaffolding,
levels
plugs and
at shape
450mm
providing
20c/cmm with
and
thick
and recesses,
fixing
cement 200 mmthroating,
plaster wide
in 24 dusting,
building gaugeexteriorGIdripping,
Chicken
in specified wetting,
wirecement
mesh curing,
atmortar
finished 25mm
protection, providinglong drive chicken all screws
wire mesh@ 230mm at the interval,of
junction
junction
7.1.3.2 with
7.1.3.21:6do of
(1as R.C.C.
aboveto
cement and
:6for masonry,
fine Band
sand) making
Plaster
inpattern,
all surface grooves and
at allwith recesses,
height rm. 840.83 100.00 84,083.00 - - 0.00 - -
jointing
concrete and
and fixing
masonry in required
etc.,laying
allwetting,
complete finished
as line,
perprotection,
drawing , etc. all
7.1.4 throating,
ON INNER
including
recommended
dusting,
WALL
mixing dripping,
mortar,
filler, WITH
making CEMENT curing,
in perfect
openings forPUNNING
light[Rate level and
fittings, sq.m 36.14 700.00 25,298.00 36.14 25,298.00 37.08 25,959.36 (0.94) (661.36) 100.00%
specification
complete
plumb
7.2 PAINTING and
andasfinishing
per instruction
drawing
WORKS of the even
, specification
in regular and Engineer.and
surfaceinstruction. shallaccess
including also
[Rateall
panel,
include cutouts
for made
providing with
drips frame
band, ofmoulds,
perimeter channels
groove, chickensuitably
shall also
necessary
DISTEMPER include
singlePAINT for providing
orasmulti-stage drips band,
scaffolding, moulds,
making and grooveswire
groove,
7.2.1 fixed
mesh
chicken
and
all
at complete
junction
wire
recesses, mesh of
throating, atRCCper drawing
and
junction
dusting, masonry,
of
and specification
RCC etc.,
and to
masonry,complete etc., the
to sq.m 3360.40 200.00 672,080.00 3,815.17 763,033.64 3375.662 675,132.40 439.51 87,901.24 113.53%
Providing
direction of theand applying
Engineer but ordripping,
twoexcluding more coats thewetting,of washable
cost curing,
of painting.
works at any
complete
protection,
distemper the
paintheights].
works
providing atchicken
of approved any heights. wire mesh atand
manufacturer the shade
junction over of a
concrete
coat of and
alkali masonry
resistant
EXTERIOR WEATHER COAT PAINT etc.,
cement all complete
primer of as per
approved drawing ,
manufacturer
7.2..2 asspecification
per manufacturer's and instruction
Providing andof
specifications the Engineer.
applying to the or[Rate
twosurface moreofshallwall,also
coats of sq.m 1559.58 350.00 545,853.00 1,728.56 604,996.00 2187.75 765,712.50 (459.19) (160,716.50) 110.83%
include
ceiling,
first qualityfor
beams providing
columns,
hundred drips
percent band,
canopies,
acrylic moulds,
staircase,
paint of groove,
lobbies
approved chicken
etc.,
shadeallwire
mesh
ENAMEL
complete at junction
as PAINT
per of RCC
drawings, and masonry,
specifications etc.,
and to complete
instruction. the
The sq.m 919.15 400.00
7.2.4 and pattern to the exterior walls of buildings etc., The rates
worksshall
Providing at any and heights.
applying by ,spray/brush 367,660.00 996.18 398,470.40 819.33415 327,733.66 176.84 70,736.74 108.38%
rates
shall include include
for for scraping,
scrapping washing washing thetwo the or
surface more
surface coats
withwith water, of
water,
1st quality
surface
applying synthetic
preparation,
a coat enamel quality
scaffolding
of approved paint ofwater
etc., approved base manufacturer
all complete as perprimer,
cement the
8 MISCELLANEOUS
(Asian, Berger recommendations
manufacturer's or equivalent) over wooden
and as complete or metal
approved bysurface
thethe in -
surface preparation, scaffolding etc., all as per
CEMENT
required
Engineer.shade BOARD at anyWALL height, shape,
8.2 manufacturer's recommendations andincluding
as approved surfaceby the sq.m 3.30 6,500.00 21,450.00 2.34 15,210.00 2.173314 14,126.54 0.17 1,083.46 70.91%
preparation, Supplying, fabrication, fixing of cement board in
Engineer. fillers/putty, scaffolding, protection etc. all
position
completefor as internal
per drawings, and external made with
specifications and9mm thick cement
instructions. The
board
RAILING
finished (Shera
surface or Siam
shall give Cement evenBoard or equivalent)
and uniform surface.from both
8.3 sides fixed to 75mm
Providing, X 0.6mm
fabrication thick C-stud
as per fixed
design to U-Track
drawings and kg 4,149.09 220.00 912,799.80 4,129.83 908,562.96 2926.80 643,896.00 1,203.03 264,666.96 99.54%
with spacingin300mm
installation positiono/c Mildof horizontal
Steel railing frame, central core
in staircase, verandahfilled
withother
and cement areasmortarincludingwith PE granules
cutting having shape
to required combined density
and size,
PUMP
approximately
welding SHED
joints, 900 kg/m3, including
installation of base anchor sealing joints
plates of with fiber
appropriate nos.
8.4 Supply,
tapeswith
size andfabrication,
joint sealing
required installation
numbers compound, of filling
of expansion 2mx1.5m screw
bolts and 1m
ofheads high
required as per size, 1.00 80,000.00 1.00 80,000.00 1.00 80,000.00 - - 100.00%
pump
providing shedrequired
manufacturer's made with
size50x50x6
installation bends, MS Angle
guidelines,
finishing sealing
weld frame , covered
perimeter
joints gaps
to produce
outside
with silicon
smooth and
surface,roof
sealant, withetc.,
applying CGIall sheet,
one coatlocakable
complete as perdoor,
of Metal drawing,
Primer including
and twopad or
SEWER,
lock, coatsRAIN
base
specifications
more PCC and
of enamel AND
(1:2:4) WASTE
75mm
instructions
paint ofWATER
all
of requiredcomplete
the Engineer.
shade, INSTALLATION
as per Rate
etc., design,
allshall
complete
8.5 PVC
drawing,
include
as per SWR theand
drawings, (Soil,
cost Waste,
instructions
of metal
specifications Rain)
of the
framing, pipes
Engineer.
and joint with and
instruction all necessary
screw of head
the ring
sealing,
Engineer. R.m 90.10 1,500.00 135,150.00 83.00 124,500.00 77.00 115,500.00 6.00 9,000.00 92.12%
gaskets,
required PVC additional fittings, including MS
strengthening clamps,
member forhangers,
the wallcutting,length
jointing,
exceedingsealing, 3 meterinstallation
in length or ofaround
pipes and door specials
and window including
making
opening,holes sealing andperimeter
cutting grooves with silicon on walls sealant.or floorTotal and finished - -
C repairing
ELECTRICAL
wall thickness the same 93WORKS to its original finish. Pipes to be installed on
mm. - -
A. trenches
8.2.1
Common FOR orInstallation
walls or floor or duct as per drawings,
PARTITION - -
1.1 specifications,
Stand Alone 40 A DP MCB recommendations,
manufacturer's with Enclosure instructions, no. 2 12,000.00 24,000.00 2.00 24,000.00 2.00 24,000.00 - - 100.00%
cleaning of the system, testing and ready for operation. The
1.2 Stand Alone 6 A DP MCB with Enclosure no. 2 8,500.00 17,000.00 2.00 17,000.00 2.00 17,000.00 - - 100.00%
rate shall include for all labour and materials required. The
2 CABLES & shall
measurement WIRES be done for running meters, fittings etc not - -
payable seperately.
- 110 mm ED 6 kg/sqcm

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay Item
Description Unit % completion Remarks
No.
Quantity As per
Rate Amount Quantity Amount Quantity Amount Quantity Amount
BOQ
2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper
2.1 rm 100 800.00 80,000.00 101.00 80,800.00 101.00 80,800.00 - - 101.00%
conductor wires
2 Nos 2.5 Sq.mm + 1 No 1.5 Sq.mm mutistranded copper
2.2 rm 95 250.00 23,750.00 100.00 25,000.00 100.00 25,000.00 - - 105.26%
conductor wires
B School Blocks - -
1 DISTRIBUTION BOARDS - -
1.1 DB (DB-1) nos. 1 30,000.00 30,000.00 1.00 30,000.00 1.00 30,000.00 - - 100.00%
1.2 DB (DB-1) nos. 1 32,000.00 32,000.00 1.00 32,000.00 1.00 32,000.00 - - 100.00%
1.3 DB (DB-2) & DB (DB-3) nos. 2 22,000.00 44,000.00 2.00 44,000.00 2.00 44,000.00 - - 100.00%
1.4 DB (DB-2) nos. 1 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 - - 100.00%
1.5 DB (DB-3) nos. 1 30,000.00 30,000.00 1.00 30,000.00 1.00 30,000.00 - - 100.00%
1.6 6A DP MCB with Enclosure nos. 2 8,500.00 17,000.00 2.00 17,000.00 2.00 17,000.00 - - 100.00%
2 CABLES & WIRES - -
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm
2.1 r.m. 20 600.00 12,000.00 23.00 13,800.00 23.00 13,800.00 - - 115.00%
Multistranded Cu wire
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm
2.2 r.m. 15 500.00 7,500.00 14.00 7,000.00 14.00 7,000.00 - - 93.33%
Multistranded Cu wire
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.3 r.m. 30 250.00 7,500.00 28.00 7,000.00 28.00 7,000.00 - - 93.33%
Multistranded Cu wire
3 General Service Light Point Wiring - -
3.1 One Way Light Point pts. 143 700.00 100,100.00 142.00 99,400.00 142.00 99,400.00 - - 99.30%
3.2 Two Way Light Point pts. 4 900.00 3,600.00 4.00 3,600.00 4.00 3,600.00 - - 100.00%
3.3 Ceiling and Exhaust Fan Point pts. 4 900.00 3,600.00 4.00 3,600.00 4.00 3,600.00 - - 100.00%
4 6A Universal Pin Light Power Socket Wiring pts. 151 900.00 135,900.00 151.00 135,900.00 151.00 135,900.00 - - 100.00%
5 Switch Socket Outlets - -
5.1 6A Universal Power Switch Socket nos. 151 700.00 105,700.00 151.00 105,700.00 151.00 105,700.00 - - 100.00%
6 Sweep Ceiling/ Exhaust Fan/Wall Fan - -
6.1 400mm wall Fan nos. 78 3,500.00 273,000.00 78.00 273,000.00 76.00 266,000.00 2.00 7,000.00 100.00%
6.2 225mm dia M/D exhaust Fan nos. 4 6,000.00 24,000.00 4.00 24,000.00 4.00 24,000.00 - - 100.00%
7 Light Fixtures/Luminaires & Accessories - -
7.1 24 W LED Recessed Mounted Square type nos. 12 4,500.00 54,000.00 12.00 54,000.00 12.00 54,000.00 - - 100.00%
7.2 18 W LED Surface Mounted Square type nos. 68 2,700.00 183,600.00 68.00 183,600.00 68.00 183,600.00 - - 100.00%
7.3 12 W LED Surface Mounted Cylindrical type nos. 47 2,400.00 112,800.00 47.00 112,800.00 47.00 112,800.00 - - 100.00%
7.4 LED Wall Light nos. 4 1,800.00 7,200.00 4.00 7,200.00 4.00 7,200.00 - - 100.00%
7.5 9 W LED Surface Mounted Cylindrical type nos. 2 2,000.00 4,000.00 2.00 4,000.00 2.00 4,000.00 - - 100.00%
7.6 6 W LED Recessed Circular type nos. 6 1,800.00 10,800.00 6.00 10,800.00 6.00 10,800.00 - - 100.00%
7.7 7 W LED T5 Slim Mirror Light nos. 2 2,000.00 4,000.00 2.00 4,000.00 2.00 4,000.00 - - 100.00%
8 Pull Box - - - -
Junction Box At External Post Top Light nos. 6 700.00 4,200.00 6.00 4,200.00 6.00 4,200.00 - - 100.00%
9 External Post Top Light Pole nos. 6 7,500.00 45,000.00 6.00 45,000.00 6.00 45,000.00 - - 100.00%
10 Post Top External Light Fixtures nos. 6 9,800.00 58,800.00 6.00 58,800.00 6.00 58,800.00 - - 100.00%
11 Earthing & Lighting Protection - -
11.1 Chemical Earthing nos. 6 45,000.00 270,000.00 6.00 270,000.00 6.00 270,000.00 - - 100.00%
11.2 Earthing Bar nos. 6 2,200.00 13,200.00 6.00 13,200.00 6.00 13,200.00 - - 100.00%
12 Earthing Strip/Wires - -
12.3.1 25 x 3 mm GI strip Mtr. 130 300.00 39,000.00 132.00 39,600.00 132.00 39,600.00 - - 101.54%
12.3.2 12 SWG Cu wire Mtr. 30 200.00 6,000.00 28.00 5,600.00 28.00 5,600.00 - - 93.33%
13 Earth Test link nos. 2 1,500.00 3,000.00 2.00 3,000.00 2.00 3,000.00 - - 100.00%
14 Lightning Arrester nos. 2 7,500.00 15,000.00 2.00 15,000.00 2.00 15,000.00 - - 100.00%
C Solar PV System - -
1 Solar PV Panel nos. 8 26,000.00 208,000.00 8.00 208,000.00 8.00 208,000.00 - - 100.00%
2 Tubular Deep Cycle Battery nos. 4 30,000.00 120,000.00 4.00 120,000.00 4.00 120,000.00 - - 100.00%
3 Hybrid Inverter nos. 1 100,000.00 100,000.00 1.00 100,000.00 1.00 100,000.00 - - 100.00%
D Fire Extinguisher - -
a ABC Stored Pressure 5.0kg size nos. 6 8,000.00 48,000.00 6.00 48,000.00 6.00 48,000.00 - - 100.00%
b Dry Powder Fire Extinguisher nos. 1 8,000.00 8,000.00 1.00 8,000.00 1.00 8,000.00 - - 100.00%
- -
D SANITARY WORKS - -
1 WATER SUPPLY INSTALLATION - -
a CPVC pipes SDR-11 - -
40 mm r.m 180.00 1,600.00 288,000.00 185.00 296,000.00 185.00 296,000.00 - - 102.78%
20mm r.m 30.00 700.00 21,000.00 29.00 20,300.00 29.00 20,300.00 - - 96.67%

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay Item
Description Unit % completion Remarks
No.
Quantity As per
Rate Amount Quantity Amount Quantity Amount Quantity Amount
BOQ
15mm r.m 8.00 500.00 4,000.00 7.50 3,750.00 7.50 3,750.00 - - 93.75%
c CPVC Ball Valve - -
40 mm nos. 4.00 2,000.00 8,000.00 3.00 6,000.00 3.00 6,000.00 - - 75.00%
25 mm nos. 2.00 900.00 1,800.00 2.00 1,800.00 2.00 1,800.00 - - 100.00%
20mm nos. 2.00 400.00 800.00 2.00 800.00 2.00 800.00 - - 100.00%
d 40mm dia Gun Metal Check Valve nos. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 - - 100.00%
e Electrical Centrifugal Water Pump nos. 1.00 12,500.00 12,500.00 1.00 12,500.00 1.00 12,500.00 - - 100.00%
f 2000 litres Capacity Water Storage Tank nos. 1.00 34,000.00 34,000.00 1.00 34,000.00 1.00 34,000.00 - - 100.00%
2 Sewer, Rain and Waste Water Installation - -
110 mm r.m 42.00 1,400.00 58,800.00 41.00 57,400.00 41.00 57,400.00 - - 97.62%
75mm r.m 69.00 1,200.00 82,800.00 70.00 84,000.00 70.00 84,000.00 - - 101.45%
50mm r.m 22.00 350.00 7,700.00 21.00 7,350.00 21.00 7,350.00 - - 95.45%
B School Blocks - -
1 Sanitary Installation - -
a Lab Sink set 5.00 30,000.00 150,000.00 5.00 150,000.00 5.00 150,000.00 - - 100.00%
b Kitchen Sink set 1.00 35,000.00 35,000.00 1.00 35,000.00 1.00 35,000.00 - - 100.00%
c PVC Multi Floor Trap nos. 2.00 600.00 1,200.00 2.00 1,200.00 2.00 1,200.00 - - 100.00%
2 Sanitary Installation - -
a Water Closet Set set 2.00 34,000.00 68,000.00 2.00 68,000.00 2.00 68,000.00 - - 100.00%
b Orissa Pan set 4.00 3,100.00 12,400.00 4.00 12,400.00 4.00 12,400.00 - - 100.00%
c Hand Wash Basin set 2.00 8,000.00 16,000.00 2.00 16,000.00 2.00 16,000.00 - - 100.00%
d Ladies Urinal set 2.00 110,000.00 220,000.00 2.00 220,000.00 2.00 220,000.00 - - 100.00%
e Self Closing Bib Cock nos. 12.00 4,000.00 48,000.00 12.00 48,000.00 12.00 48,000.00 - - 100.00%
f CP Spreader in Urinal set 4.00 2,500.00 10,000.00 4.00 10,000.00 4.00 10,000.00 - - 100.00%
g Toilet Paper Holder nos. 2.00 2,600.00 5,200.00 2.00 5,200.00 2.00 5,200.00 - - 100.00%
h Commode Spray nos. 2.00 2,000.00 4,000.00 2.00 4,000.00 2.00 4,000.00 - - 100.00%
i PVC Multi Floor Trap nos. 10.00 600.00 6,000.00 10.00 6,000.00 10.00 6,000.00 - - 100.00%
j Waste Coupling and PVC Bottle Trap nos. 4.00 1,500.00 6,000.00 4.00 6,000.00 4.00 6,000.00 - - 100.00%
k 40mm SS Grab Bar-Side nos. 2.00 4,500.00 9,000.00 2.00 9,000.00 2.00 9,000.00 - - 100.00%
l 40mm SS Grab Bar-Rear nos. 2.00 4,500.00 9,000.00 2.00 9,000.00 2.00 9,000.00 - - 100.00%
m CP Foldable Hinge nos. 4.00 5,500.00 22,000.00 4.00 22,000.00 4.00 22,000.00 - - 100.00%
- -
- -
E CIVIL WORKS : SITE DEVELOPMENT - -
1 EARTHWORKS - -
1 SITE CLEARANCE AND MOBILIZATION Sq.m 453.13 100.00 45,313.00 499.95 49,995.00 499.95 49,995.00 - - 110.33%
2 EARTHWORK IN EXCAVATION Cu.m 96.77 400.00 38,708.00 439.03 175,613.40 439.03 175,613.40 - - 453.69%
3 EARTHBACK FILLING Cu.m 10.38 300.00 3,114.00 98.34 29,502.00 98.34 29,502.00 - - 947.40% For Additional
Retaining Wall
4 BOULDER SOLING Cu.m 49.83 6,000.00 298,980.00 65.58 393,507.00 65.58 393,507.00 - - 131.62% Works
5 P.C.C (1:3:6) Cu.m 1.09 14,000.00 15,260.00 15.44 216,202.00 15.44 216,202.00 - - 1416.79%
6 P.C.C (1:2:4) Cu.m 25.89 16,000.00 414,240.00 28.43 454,956.00 28.43 454,956.00 - - 109.83%
7 P.C.C FOR R.C.C WORK cu.m 0.99 20,000.00 19,800.00 0.99 19,766.20 0.99 19,766.20 - - 99.83%
8 SILICA CEMENT ADMIXTURE Kg 300 9.90 2,970.00 9.88 97.84 9.88 97.84 - - 3.29%
9 STEEL REINFORCEMENT Mt. 0.1 130,000.00 13,000.00 0.11 13,897.00 0.10 13,343.25 0.00 553.75 106.90%
10 FORM WORKS Sq.m 9.12 800.00 7,296.00 11.33 9,064.00 9.12 7,292.80 2.21 1,771.20 124.23%
13 BRICKS MASONRY WORKS (1:4 c/s) Cu.m 0.22 18,000.00 3,960.00 0.72 13,032.72 0.72 13,032.72 - - 329.11%
14 NEAT CEMENT SKIRTING r.m 4.72 100.00 472.00 4.40 440.00 4.40 440.00 - - 93.22%
15 METAL WORKS FOR FENCE k.g 2666.14 220.00 586,550.80 2,024.64 445,420.80 1982.36 436,119.20 42.28 9,301.60 75.94%
16 METAL WORKS FOR GATE k.g 130.78 220.00 28,771.60 123.31 27,128.20 118.89 26,155.45 4.42 972.75 94.29%
17 PLASTER ON OUTER WALL Sq.m 7.92 600.00 4,752.00 7.80 4,679.04 7.80 4,679.04 - - 98.46%
18 EXTERIOR WEATHER COAT PAINT Sq.m 8.87 350.00 3,104.50 8.27 2,895.20 8.27 2,895.20 - - 93.26%
19 CHAIN LINK FENCE Sq.m 295.46 1,000.00 295,460.00 294.00 294,000.00 294.00 294,000.00 - - 99.51%
20 FLAG POLE nos. 2 25,000.00 50,000.00 2.00 50,000.00 2.00 50,000.00 - - 100.00%
21 STONE MASONARY WORKS Cu.m 10,000.00 - 254.05 2,540,450.00 254.05 2,540,450.00
22 50MM DIA WEEP PIPE r.m 100.00 - 166.10 16,610.00 166.10 16,610.00
23 GEOTEXTILE Sq.m 200.00 - 149.00 29,800.00 149.00 29,800.00
- -
CIVIL WORKS-RESERVIOR TANK - -
SITE CLEARANCE & MOBILIZATION:
1.1 sq.m 22.31 50.00 2,231.00 22.31 1,115.50 22.31 1,115.50 - - 100.00%
Clearing and grubbing the site for construction by removing
150mm thick top soil including bushes, small trees, leveling of
undulated ground, shorting and stacking/storing selected top
soil for reuse in landscaping works, disposing unsuitable
materials from site, etc., all complete as per drawings,
specifications and instructions of the Engineer.
Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay Item
Description Unit % completion Remarks
No.
Quantity As per
Rate Amount Quantity Amount Quantity Amount Quantity Amount
BOQ
EARTHWORK IN EXCAVATION :
1.2 Excavation in foundations in all type of soils for foundation, cu.m 24.58 400.00 19,657.44 24.57 9,828.72 24.57 9,828.72 - - 99.97%
trenches, footing, pits etc. to the required depth including
dewatering by manual or mechanical means etc. as per
EARTH BACK
specifications withFILLING
all contractor’s: own machinery and
1.3 Back filling inproviding
equipment's, foundation and sides
crossing of foundation
of track, with
shoring, strutting, cu.m 4.02 300.00 2,405.70 4.01 1,202.85 4.01 1,202.85 - - 99.74%
approved
timbering soil and obtained
buttressing fromwiththeappropriate
excavationmaterials
at site andand stacked
all
at sitemeasures
such or brought from outside
necessary to retainin layer not exceeding
in position the sides15 ofcm
the
BOULDER
thick (compacted SOLING :
thickness) including transportation
foundation pit and including refilling the excavated material of soil,
1.4 Providing
spreading
with watering, andrequired
in laying
ramming, uncoursed
lineleveling
and level, hand packedand Dry
thesprinkling
site Rubbleoff the
water,
disposing cu.m 2.08 6,000.00 24,924.00 2.08 12,462.00 2.08 12,462.00 - - 99.86%
Stone
ramming, soling in foundation,
compacting
surplus/unusable earth with underthe
mechanical
to outside floor plinth
rammers,
construction withtesting,
out anyetc.,
premises,
special
all dressing
complete
etc.CONCRETE
2. all complete as per of
as stone
drawing, including
per drawings,
WORKS filling interstices
specification and with of
and instructions
specifications
suitable
the
2.1 quarry
Engineer.
instructions
P.C.C of the waste or stone chips or quarry sand, watering,
Engineer.
2.1.1 compacting
2.1.1 P.C.C using(1:3:6) appropriate mechanical compaction means cu.m 0.78 14,000.00 21,808.50 0.78 10,904.25 0.78 10,904.25 - - 99.86%
with all contractors
Providing and layingmaterials,
machine handling,
mixed Plain placing
Cement etc.Concrete
all of
completemix
nominal as per1:3:6 drawings,
(1 cement specifications
: 3 sand : 6 and coarse instruction
aggregate of)the
for
P.C.C.
leveling FOR
Engineer.course R.C.C.
The complete WORKS :
item including
in foundations and underallfloor leadof &building,
lift. etc.
Providing
in all leveland withlayingbroken in stone
position machine
aggregate ofmixed
size not and machine
more than
2.2 vibrated cu.m 7.42 20,000.00 296,590.00 7.41 148,295.00 7.41 148,295.00 - - 99.93%
25 mm ofcement approved concrete
quality ofincluding
mix 1:1.5:3 (1 cement:1.5
formwork wherever sand: 3
coarse aggregate) M20 grade for reinforced
necessary, dewatering, batching, mixing, transporting, placing, cement concrete
work
SILICA using
compacting, approved
CEMENT cement with
ADMIXTURE
curing, including 20 mm
all lead and graded
lift, etc.machine
all complete
2.3 crushed
Providing
as stone
and aggregate
per drawings, mixing of approved
Silica
specifications Cement
and the quality
Admixture in various
instructions of in
of structural
the kg 74.2 300.00 44,488.50 74.15 22,244.25 74.15 22,244.25 - - 99.93%
locations
concrete and heights including transportation
Engineer.at the rate of 2.50% by weight of the cement of concretefor to
site
promoting workability, improving strength, achieving level,
STEELof placing, compaction,
REINFORCEMENT finished to required line and
2.4 protection and and fixing
curing,inetc. all complete Mt. 1.46 130,000.00 396,477.53 1.47 191,574.92 1.58 204,902.61 (0.10) (13,327.69) 100.94%
Providing
waterproofing properties, position
bleeding 500 as
Feprevention, perreinforcement
steel drawings,
etc. Silica of
specifications
various
Cement diameter
FORM WORKS
Admixture andconfirming
the instructions
shall be the of theof
to relevant
product Engineer,
IS but or
code inJapan
Silica R.C.C.
excluding
works
superior and
Supplying the
including
and cost
shall of
laying centering,
straightening,
meetcentering, shuttering,
cutting,
the requirements
shuttering asofand
bending, reinforcement,
binding
mentioned
various inwith
pattern
2.5 all complete as sq.m 54.93 800.00 88,908.80 54.67 43,738.00 56.46 45,170.80 (1.79) (1,432.80) 99.53%
20 SWG annealed
formworks
specification of per
with drawings,
wire
19/12
materials mmforand specifications
tying
thick water
Workmanship, proofand
the reinforcement ply instructions
bars–&at
wood
Division of
each
4:steel
the Engineer.
junctions Works,
adjustable
Concrete (binding
props for wire shall
2.4 not
all kinds
Article of RCCbe measured
works for separately)
foundations,
3.1.1 INTERNAL
including all CEMENT
waste and cutPLASTER
pieces, (1:4) WITH
provision for PUNNING
adequate sq.m 33.66 700.00 48,389.70 33.66 23,565.25 35.46 24,824.45 (1.80) (1,259.20) 100.01%
columns, shear walls, beams, slab, staircase, lintel, sill,
4 WATERincluding
numbers
pergola, ofPROOF COATING
spacers,nails,chairs, providing
propping and placing
scaffolding, cement
staging, sq.m 33.66 550.00 38,020.48 33.66 18,515.55 35.46 19,504.93 (1.80) (989.37) 100.01%
mortar (1:1)and
supporting cover blocksintoproper
bracing keep the bars
lines andinlevel,
intended position
sealing the -
at all levels
Furniture
joints heavy duty brown self adhesive tape, aligningand
all
with Works complete as per drawings, specifications to Lot 1 5,500,000.00 5,500,000.00 1.00 5,500,000.00 1.00 5,500,000.00 - - 100.00%
instructions
line and levels of the Engineer.
including (Authorized
Ties,
TotalPVC Spacer, lap length
Providing and for the 67,664,499.34 70,539,377.91 63,304,730.40 7,234,647.52
bar length cutouts/
openings/ exceeding 10 meter
pockets, in length
applying shall be measured
De-shuttering chemical, for
the payment, except to column).
De-shuttering as approved by the Engineer etc., complete at all
levels as per drawing, specifications and instructions of the
Engineer.

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block 3-LaLiEACCr(F), Tc(S)
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
Abstract of Cost
Type Design
Pay Item Quantity Total
Description of Works Unit Rate (NRs.) Site Amount Remarks
No. in BOQ 3-LaLiEACCr(F)-A Qty-3-9C(SF). Tc(S) Water Tank Quantity
Development
GENERAL
1 MOBILIZATION AND DEMOBILIZATION L.S. 1.00 500,000.00 1.00 500,000.00
2 SITE OFFICE ESTABLISHMENT Per Month 21.00 25,000.00 21.00 525,000.00
3 PROJECT INFORMATION BOARD nos. 1.00 10,000.00 1.00 10,000.00
4 SAFETY SIGN BOARD nos. 1.00 10,000.00 1.00 10,000.00
5 BARRICADING WORKS R.m 110.00 2,000.00 110.00 220,000.00
6 SAFETY MATERIALS & SITE SAFETY L.S. 1.00 100,000.00 1.00 100,000.00
7 LAB TEST(WATER TEST) job 1.00 0.00 -
8 TEMPORARY TOILET nos. 2.00 150,000.00 2.00 300,000.00
9 ROAD REPAIR AND MAINTENANCE Km. 2.00 50,000.00 2.00 100,000.00

CIVIL WORKS- BUILDING 0.00 -


1 EARTH WORKS 0.00 -
1.1 SITE CLEARANCE & MOBILIZATION: sq.m 1,076.98 100.00 550.65 356.25 235.00 1,141.90 114,190.12
1.2 EARTHWORK IN EXCAVATION : cu.m 566.02 400.00 249.69 202.45 84.39 536.53 214,610.94
1.3 EARTH BACK FILLING : cu.m 340.79 300.00 171.13 111.72 67.07 349.92 104,976.82
1.4 BOULDER SOLING : cu.m 167.88 6,000.00 107.98 63.61 19.26 190.85 1,145,101.40
1.5 SAND FILLING : cu.m 7.40 6,000.00 4.91 4.91 29,435.40
CONCRETE WORKS
2.1 2.1 P.C.C cu.m 28.81 14,000.00 15.19 11.39 2.82 29.39 411,428.06
2.1.1 P.C.C (1:3:6)
2.1.2 P.C.C (1:2:4) WORKS cu.m 48.15 16,000.00 22.41 13.99 10.01 46.42 742,685.74
2.2 Providing
P.C.C. FOR andR.C.C.
laying WORKS
machine mixed
: Plain Cement Concrete cu.m 665.02 20,000.00 374.40 282.33 27.89 684.62 13,692,491.32
2.3 of nominal
SILICA mix 1:2:4ADMIXTURE
CEMENT (1 cement : 2 sand : 4 coarse aggregate ) kg 6,650.20 300.00 3,744.04 2,823.31 278.90 6,846.25 2,053,876.27
for leveling course in foundations and under floor of building,
2.4 STEEL
etc. in allREINFORCEMENT
level with broken stone aggregate of size not more Mt. 106.42 130,000.00 58.15 45.95 3.63 107.73 14,004,637.71
2.5 FORM
than 25WORKS mm of approved quality including formwork sq.m 4,399.99 800.00 2,433.42 2,000.51 222.83 4,656.76 3,725,410.41
3.1 3. BRICK MASONRY
wherever necessary, WORKSdewatering, batching, mixing, cu.m 184.75 20,000.00
7.2.3 3.1
CLEARBRICK
transporting, MASONRY
SILICON WORKScuring,
WATER-REPELLANT
placing, compacting, ( 1 : 4including
c/s ) ONEallSIDE
COATNG lead sq.m 919.15 550.00
8.1.1 FAIRFACE
and lift, etc.
POINTING WORK all complete as per drawings,
IN BRICK MASONRY specifications and sq.m 919.15 400.00
Providing
the and
instructions laying first
of the3.1., class selected factory pressed wire
Engineer.
BOQ Total of items 7.2.3 & 8.1.1:
cut Fair Face brick (machine made brick) one or more brick
Replaced
thick wall items 3.1, 7.2.3
in cement mortarand1:48.1.1 with following
(1 cement : 4coarseitems
sand) in
for 3-LaLiEACCr(F).
,superstructure and other3-9C(SF)
specified and Tc(S)in all heights and
places
Brick including
level Masonry Works
the cost(1:4 c/s) or multi stage self standing
of single cu.m 18,000.00
scaffolding,
Cement Plaster soaking
Worksbricks, curing,
on Outer Wall raking
(1:6) joints, provision sq.m 600.00
for recesses,
Exterior Weatheropenings,
Coat Painttoothing etc., all complete as per sq.m 350.00
drawing, specifications and instructions of the Engineer.
3.2 BRICK MASONRY WORKS ( 1 : 4 c/s ) cu.m 121.32 18,000.00 154.40 96.95 47.63 298.98 5,381,583.42
3.3 HALF BRICK WORKS ( 1 : 4 c/s ) sq.m 71.94 1,500.00 51.43 7.12 29.08 87.62 131,435.69
3.4 HONEY COMB BRICK WORKS (1:3 c/s) cu.m 3.52 9,000.00 3.21 1.59 4.81 43,275.15
DOORS & WINDOWS WORKS
4.1 4.1 METAL FRAME
4.1.1 Door Frame rm. 313.04 1,100.00 177.97 142.14 320.11 352,121.00
4.1.2 Window Frame rm. 786.59 1,100.00 468.08 412.26 880.34 968,374.00
4.2 METAL SHUTTER
4.2.1 WINDOW SHUTTER sq.m 171.18 7,500.00 97.07 47.83 144.90 1,086,749.25
4.3 WOODEN SHUTTER
4.3.1 FLUSH DOOR SHUTTER (32MM) sq.m 120.78 8,000.00 68.28 49.70 117.98 943,812.40
UPVC DOOR
4.4.1 SHUTTER/FRAME sq.m 14.28 9,000.00 13.79 13.79 124,146.00
4.5 WINDOW GRILL sq.m 102.09 2,500.00 97.62 47.83 6.23 151.68 379,199.75
4.6 COLLAPSIBLE GATE sq.m 20.35 10,000.00 9.90 10.09 19.99 199,856.25
5. FLOORING WORKS
5.1 HARDENED CEMENT CONCETE FLOOR sq.m 2168.59 900.00 1206.32 851.96 95.10 2,153.38 1,938,039.30
NEAT CEMENT SKIRTING
5.2 - do - as above, but for 100 mm high skirting. r.m 1025.05 100.00 564.86 480.86 23.60 1,069.32 106,932.00
5.3 TERRAZZO CAST-IN SITU DADO sq.m 72.27 1,500.00 28.66 2.40 63.79 94.85 142,268.25
6 ROOFING/ TERRACING WORKS 0.00 -
6.1 METAL WORKS(TRUSS) kg 871.25 220.00 999.81 999.81 219,957.37
6.2 CGI SHEET ROOFING sq.m 57.90 2,000.00 58.93 58.93 117,854.00
6.3 CGI SHEET ROOFING RIDGE rm. 12.10 1,200.00 12.00 12.00 14,400.00
6.4 GI FACIA (EAVES) kg 90.47 250.00 143.52 143.52 35,880.78
6.5 CEMENT BOARD FALSE CEILING sq.m 30.88 1,500.00 48.40 48.40 72,600.00
7. PLASTERING/ WALL FINISHING WORKS
7.1.1 7.1 CEMENT PLASTER WORKS sq.m 1,967.29 600.00 1178.52 749.01 134.02 2,061.55 1,236,932.00
ON INNER WALL (1:6)
7.1.2 ON CEILING (1:4) sq.m 1,393.11 500.00 833.56 836.63 35.03 1,705.21 852,607.43
7.1.3 ON OUTER WALL (1:6):
7.1.3.1 EXTERNAL PLASTER sq.m 1,142.89 600.00 966.72 655.50 106.34 1,728.56 1,037,136.00
7.1.3.2 7.1.3.2 do as above for Band Plaster rm. 840.83 100.00 0.00 -
7.1.4 ON INNER WALL WITH CEMENT PUNNING sq.m 36.14 700.00 36.14 36.14 25,298.00
7.2 PAINTING WORKS
7.2.1 DISTEMPER PAINT sq.m 3360.40 200.00 2012.08 1,585.64 217.44 3,815.17 763,033.64
7.2..2 EXTERIOR WEATHER COAT PAINT sq.m 1559.58 350.00 966.72 655.50 106.34 1,728.56 604,996.00
7.2.4 ENAMEL PAINT sq.m 919.15 400.00 545.73 437.99 12.46 996.18 398,470.40
8 MISCELLANEOUS 0.00 -
CEMENT BOARD WALL
8.2 sq.m 3.30 6,500.00 2.34 2.34 15,210.00
8.3 8.2.1 FOR PARTITION
RAILING kg 4,149.09 220.00 2,424.07 1,705.76 4,129.83 908,562.96
8.4 PUMP SHED nos. 1.00 80,000.00 1.00 1.00 80,000.00
SEWER, RAIN AND WASTE WATER INSTALLATION
8.5 R.m 90.10 1,500.00 41.80 41.20 83.00 124,500.00
0.00 -
C ELECTRICAL WORKS 0.00 -
A. Common Installation 0.00 -
1.1 Stand Alone 40 A DP MCB with Enclosure no. 2 12,000.00 1.00 1.00 2.00 24,000.00
1.2 Stand Alone 6 A DP MCB with Enclosure no. 2 8,500.00 2.00 2.00 17,000.00
2 CABLES & WIRES - 0.00 -
2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper
2.1 rm 100 800.00 49.00 52 101.00 80,800.00
conductor wires
2 Nos 2.5 Sq.mm + 1 No 1.5 Sq.mm mutistranded copper
2.2 rm 95 250.00 50.00 50 100.00 25,000.00
conductor wires
B School Blocks - 0.00 -
1 DISTRIBUTION BOARDS - 0.00 -
1.1 DB (DB-1) nos. 1 30,000.00 1.00 1.00 30,000.00

Prepared By: Checked By: Approved By:


Sharma AM JV Consultant Engineer DLPIU
Type Design
Pay Item Quantity Total
Description of Works Unit Rate (NRs.) Site Amount Remarks
No. in BOQ 3-LaLiEACCr(F)-A Qty-3-9C(SF). Tc(S) Water Tank Quantity
Development
1.2 DB (DB-1) nos. 1 32,000.00 1.00 1.00 32,000.00
1.3 DB (DB-2) & DB (DB-3) nos. 2 22,000.00 1.00 1.00 2.00 44,000.00
1.4 DB (DB-2) nos. 1 22,000.00 1.00 1.00 22,000.00
1.5 DB (DB-3) nos. 1 30,000.00 1.00 1.00 30,000.00
1.6 6A DP MCB with Enclosure nos. 2 8,500.00 2.00 2.00 17,000.00
2 CABLES & WIRES - 0.00 -
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm
2.1 r.m. 20 600.00 11.00 12.00 23.00 13,800.00
Multistranded Cu wire
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm
2.2 r.m. 15 500.00 8.00 6.00 14.00 7,000.00
Multistranded Cu wire
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.3 r.m. 30 250.00 14.00 14.00 28.00 7,000.00
Multistranded Cu wire
3 General Service Light Point Wiring - 0.00 -
3.1 One Way Light Point pts. 143 700.00 72.00 59.00 11.00 142.00 99,400.00
3.2 Two Way Light Point pts. 4 900.00 2.00 2.00 4.00 3,600.00
3.3 Ceiling and Exhaust Fan Point pts. 4 900.00 4.00 4.00 3,600.00
4 6A Universal Pin Light Power Socket Wiring pts. 151 900.00 97.00 54.00 151.00 135,900.00
5 Switch Socket Outlets - 0.00 -
5.1 6A Universal Power Switch Socket nos. 151 700.00 97.00 54.00 151.00 105,700.00
6 Sweep Ceiling/ Exhaust Fan/Wall Fan - 0.00 -
6.1 400mm wall Fan nos. 78 3,500.00 42.00 36 78.00 273,000.00
6.2 225mm dia M/D exhaust Fan nos. 4 6,000.00 4.00 4.00 24,000.00
7 Light Fixtures/Luminaires & Accessories - 0.00 -
7.1 24 W LED Surface Mounted Square type nos. 12 4,500.00 12.00 12.00 54,000.00
7.2 18 W LED Surface Mounted Square type nos. 68 2,700.00 32.00 36 68.00 183,600.00
7.3 12 W LED Surface Mounted Cylindrical type nos. 47 2,400.00 27.00 20 47.00 112,800.00
7.4 LED Wall Light nos. 4 1,800.00 1.00 1 2.00 4.00 7,200.00
7.5 9 W LED Surface Mounted Cylindrical type nos. 2 2,000.00 2.00 2.00 4,000.00
7.6 6 W LED Recessed Circular type nos. 6 1,800.00 6.00 6.00 10,800.00
7.7 7 W LED T5 Slim Mirror Light nos. 2 2,000.00 2.00 2.00 4,000.00
8 Pull Box - 0.00 -
Junction Box At External Post Top Light nos. 6 700.00 3.00 3 6.00 4,200.00
9 External Post Top Light Pole nos. 6 7,500.00 3.00 3.00 6.00 45,000.00
10 Post Top External Light Fixtures nos. 6 9,800.00 3.00 3.00 6.00 58,800.00
11 Earthing & Lighting Protection - 0.00 -
11.1 Chemical Earthing nos. 6 45,000.00 3.00 3 6.00 270,000.00
11.2 Earthing Bar nos. 6 2,200.00 3.00 3 6.00 13,200.00
12 Earthing Strip/Wires - 0.00 -
12.3.1 25 x 3 mm GI strip Mtr. 130 300.00 65.00 67 132.00 39,600.00
12.3.2 12 SWG Cu wire Mtr. 30 200.00 15.00 13 28.00 5,600.00
13 Earth Test link nos. 2 1,500.00 1.00 1 2.00 3,000.00
14 Lightning Arrester nos. 2 7,500.00 1.00 1 2.00 15,000.00
C Solar PV System - 0.00 -
1 Solar PV Panel nos. 8 26,000.00 8.00 8.00 208,000.00
2 Tubular Deep Cycle Battery nos. 4 30,000.00 4.00 4.00 120,000.00
3 Hybrid Inverter nos. 1 100,000.00 1.00 1.00 100,000.00
D Fire Extinguisher - 0.00 -
a ABC Stored Pressure 5.0kg size nos. 6 8,000.00 6.00 6.00 48,000.00
b Dry Powder Fire Extinguisher nos. 1 8,000.00 1.00 1.00 8,000.00
0.00 -
D SANITARY WORKS 0.00 -
1 WATER SUPPLY INSTALLATION 0.00 -
a CPVC pipes SDR-11 0.00 -
40 mm r.m 180.00 1,600.00 185.00 185.00 296,000.00
20mm r.m 30.00 700.00 29.00 29.00 20,300.00
15mm r.m 8.00 500.00 7.50 7.50 3,750.00
c CPVC Ball Valve 0.00 -
40 mm nos. 4.00 2,000.00 3.00 3.00 6,000.00
25 mm nos. 2.00 900.00 2.00 2.00 1,800.00
20mm nos. 2.00 400.00 2.00 2.00 800.00
d 40mm dia Gun Metal Check Valve nos. 1.00 4,500.00 1.00 1.00 4,500.00
e Electrical Centrifugal Water Pump nos. 1.00 12,500.00 1.00 1.00 12,500.00
f 2000 litres Capacity Water Storage Tank nos. 1.00 34,000.00 1.00 1.00 34,000.00
2 Sewer, Rain and Waste Water Installation 0.00 -
110 mm r.m 42.00 1,400.00 41.00 41.00 57,400.00
75mm r.m 69.00 1,200.00 70.00 70.00 84,000.00
50mm r.m 22.00 350.00 21.00 21.00 7,350.00
B School Blocks 0.00 -
1 Sanitary Installation 0.00 -
a Lab Sink set 5.00 30,000.00 5.00 5.00 150,000.00
b Kitchen Sink set 1.00 35,000.00 1.00 1.00 35,000.00
c PVC Multi Floor Trap nos. 2.00 600.00 2.00 2.00 1,200.00
2 Sanitary Installation 0.00 -
a Water Closet Set set 2.00 34,000.00 2.00 2.00 68,000.00
b Orissa Pan set 4.00 3,100.00 4.00 4.00 12,400.00
c Hand Wash Basin set 2.00 8,000.00 2.00 2.00 16,000.00
d Ladies Urinal set 2.00 110,000.00 2.00 2.00 220,000.00
e Self Closing Bib Cock nos. 12.00 4,000.00 12.00 12.00 48,000.00
f CP Spreader in Urinal set 4.00 2,500.00 4.00 4.00 10,000.00
g Toilet Paper Holder nos. 2.00 2,600.00 2.00 2.00 5,200.00
h Commode Spray nos. 2.00 2,000.00 2.00 2.00 4,000.00
i PVC Multi Floor Trap nos. 10.00 600.00 10.00 10.00 6,000.00
j Waste Coupling and PVC Bottle Trap nos. 4.00 1,500.00 4.00 4.00 6,000.00
k 40mm SS Grab Bar-Side nos. 2.00 4,500.00 2.00 2.00 9,000.00
l 40mm SS Grab Bar-Rear nos. 2.00 4,500.00 2.00 2.00 9,000.00
m CP Foldable Hinge nos. 4.00 5,500.00 4.00 4.00 22,000.00
0.00 -
0.00 -
E CIVIL WORKS : SITE DEVELOPMENT 0.00 -
1 EARTHWORKS 0.00 -
1 SITE CLEARANCE AND MOBILIZATION Sq.m 453.13 100.00 499.95 499.95 49,995.00
2 EARTHWORK IN EXCAVATION Cu.m 96.77 400.00 439.03 439.03 175,613.40
3 EARTHBACK FILLING Cu.m 10.38 300.00 98.34 98.34 29,502.00
4 BOULDER SOLING Cu.m 49.83 6,000.00 65.58 65.58 393,507.00
5 P.C.C (1:3:6) Cu.m 1.09 14,000.00 15.44 15.44 216,202.00
6 P.C.C (1:2:4) Cu.m 25.89 16,000.00 28.43 28.43 454,956.00
7 P.C.C FOR R.C.C WORK cu.m 0.99 20,000.00 0.99 0.99 19,766.20
8 SILICA CEMENT ADMIXTURE Kg 300 9.90 9.88 9.88 97.84
9 STEEL REINFORCEMENT Mt. 0.1 130,000.00 0.11 0.11 13,897.00
10 FORM WORKS Sq.m 9.12 800.00 11.33 11.33 9,064.00

Prepared By: Checked By: Approved By:


Sharma AM JV Consultant Engineer DLPIU
Type Design
Pay Item Quantity Total
Description of Works Unit Rate (NRs.) Site Amount Remarks
No. in BOQ 3-LaLiEACCr(F)-A Qty-3-9C(SF). Tc(S) Water Tank Quantity
Development
13 BRICKS MASONRY WORKS (1:4 c/s) Cu.m 0.22 18,000.00 0.72 0.72 13,032.72
14 NEAT CEMENT SKIRTING r.m 4.72 100.00 4.40 4.40 440.00
15 METAL WORKS FOR FENCE k.g 2666.14 220.00 2,024.64 2,024.64 445,420.80
16 METAL WORKS FOR GATE k.g 130.78 220.00 123.31 123.31 27,128.20
17 PLASTER ON OUTER WALL Sq.m 7.92 600.00 7.80 7.80 4,679.04
18 EXTERIOR WEATHER COAT PAINT Sq.m 8.87 350.00 8.27 8.27 2,895.20
19 CHAIN LINK FENCE Sq.m 295.46 1,000.00 294.00 294.00 294,000.00
20 FLAG POLE nos. 2 25,000.00 2.00 2.00 50,000.00
21 STONE MASONARY WORKS Cu.m 10,000.00 254.05 254.05 2,540,450.00
22 50MM DIA WEEP PIPE r.m 100.00 166.10 166.10 16,610.00
23 GEOTEXTILE Sq.m 200.00 149.00 149.00 29,800.00
0.00 -
CIVIL WORKS-RESERVIOR TANK 0.00 -
1.1 SITE CLEARANCE & MOBILIZATION: sq.m 22.31 50.00 22.31 22.31 1,115.50
1.2 EARTHWORK IN EXCAVATION : cu.m 24.58 400.00 24.57 24.57 9,828.72
1.3 EARTH BACK FILLING : cu.m 4.02 300.00 4.01 4.01 1,202.85
1.4 BOULDER SOLING : cu.m 2.08 6,000.00 2.08 2.08 12,462.00
2. CONCRETE WORKS
2.1.1 2.1 P.C.C cu.m 0.78 14,000.00 0.78 0.78 10,904.25
2.1.1 P.C.C (1:3:6)
2.2 P.C.C. FOR R.C.C. WORKS : cu.m 7.42 20,000.00 7.41 7.41 148,295.00
2.3 SILICA CEMENT ADMIXTURE kg 74.2 300.00 74.15 74.15 22,244.25
2.4 STEEL REINFORCEMENT Mt. 1.46 130,000.00 1.47 1.47 191,574.92
2.5 FORM WORKS sq.m 54.93 800.00 54.67 54.67 43,738.00
3.1.1 INTERNAL CEMENT PLASTER (1:4) WITH sq.m 33.66 700.00 33.66 33.66 23,565.25
4 PUNNING
WATER PROOF COATING sq.m 33.66 550.00 33.66 33.66 18,515.55
-
Furniture Works Lot 1 5,500,000.00 0.5 0.5 1.00 5,500,000.00
Total 70,539,377.91

Prepared By: Checked By: Approved By:


Sharma AM JV Consultant Engineer DLPIU
Project Name : Emergency School Reconstruction Project (ESRP)
Building: 3LaLiEACCr(F)-A
School Name : Shree Chaturmala Secondary School
Location : Muchhok-01, Gorkha

Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
1 EARTH WORKS
1.1 Site Clearance
Building 1 34.50 15.50 534.75
Soak Pit 1 15.90 Area 15.90
Total 550.65 sq.m

1.2 Earth Work Excavation


For Isolated Foundation
F1 2 2.80 2.80 1.50 23.52
F2 4 3.30 3.30 1.50 65.34
For Combined Foundation
CF1 3 2.10 5.30 1.50 50.09
CF2 1 3.30 5.30 1.50 26.24
CF3 2 3.10 5.30 1.50 49.29

Along Lower Tie Beam


Along Grid A & F 2 3.50 0.55 0.75 2.89
Along Grid B 1 3.30 0.55 0.75 1.36
Grid C & D 2 3.55 0.55 0.75 2.93
Along Grid E 1 3.25 0.55 0.75 1.34
Along Grid 1 1 12.50 0.55 0.75 5.16
Along Grid 2,3 2 15.10 0.55 0.75 12.46

Drain 1 29.00 0.60 0.05 0.87


Pavement Along Drain 1 29.00 0.75 0.15 3.26
External Steps 1 27.90 0.70 0.15 2.93

Ramp
For Slope 1 1.30 0.52 Area 0.67
Wall Along Grid B 1 0.50 0.45 0.45 0.10
Wall Parallel to Ramp 1 6.80 0.45 0.41 1.25
Total 249.69 cu.m

1.3 Earth Back Filling


Excavated Soil 249.69
Additional Quantities Required
Lab/ECD/Store/Pantry 4 6.70 5.70 0.18 26.73
Staircase 1 6.70 4.20 0.18 4.92
Corridor 4 5.70 2.20 0.18 8.78
1 4.20 2.20 0.18 1.62
Deductions 0.00
Boulder Soling -1 27.04 -27.04
PCC -1 15.19 -15.19
RCC -1 77.98 -77.98
Wall -1 0.40 -0.40
Total 171.13 cu.m

1.4 Boulder Soling


Footing
Isolated F1 2 2.50 2.50 0.20 2.50
Isolated F2 4 3.00 3.00 0.20 7.20
Combined CF1 3 1.80 5.00 0.20 5.40
Combined CF2 1 3.00 5.00 0.20 3.00
Combined CF3 2 2.80 5.00 0.20 5.60
Below Foundation Beam

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Along Grid A & F 2 3.50 0.55 0.75 2.89
Along Grid B 1 3.30 0.55 0.75 1.36
Grid C & D 2 3.55 0.55 0.75 2.93
Along Grid E 1 3.25 0.55 0.75 1.34
Along Grid 1 1 12.50 0.55 0.75 5.16
Along Grid 2,3 2 15.10 0.55 0.75 12.46

Pavement along Drain 1 29.00 1.00 0.10 2.90


Pebbels along Drain 1 29.00 0.60 0.05 0.87
External Steps 1 28.58 0.70 0.10 2.00
Ramp
Slopped Portion 1 1.30 1.36 Area 1.77
Wall Along Grid B 1 0.50 0.45 0.10 0.02
Wall Parallel to Ramp 1 6.80 0.45 0.10 0.31
Classroom
Lab/ECD/Store/Pantry 4 5.70 6.70 0.20 30.55
Corridor 4 5.70 2.20 0.20 10.03
1 4.20 2.20 0.20 1.85
Below Staircase 1 4.20 6.65 0.20 5.59
Inside of soak Pit 1 1.13 2.00 2.26
Total 107.98 cu.m

1.5 Sand Filling


Periphery ot Soak pit 1 2.07 Area 2.37 4.91
Total 4.91 cu.m

2 CONCRETE WORKS
2.1 P.C.C.
2.1.1 P.C.C.(1:3:6) Works
Footing
Isolated F1 2 2.50 2.50 0.10 1.25
Isolated F2 4 3.00 3.00 0.10 3.60
Combined CF1 3 1.80 5.00 0.10 2.70
Combined CF2 1 3.00 5.00 0.10 1.50
Combined CF3 2 2.80 5.00 0.10 2.80

Below Foundation Beam


Along Grid A,B,C,D,E,F/ 1-2 6 4.55 0.40 0.10 1.09
Along Grid 1 1 23.50 0.40 0.10 0.94
Along Grid 2,3 2 16.30 0.40 0.10 1.30
Total 15.19 cu.m

2.1.2 P.C.C.(1:2:4) Works


Pavement along Drain 1 29.00 1.00 0.05 1.45
Below External Steps 1 28.58 0.70 0.05 1.00
Above External Steps 1 27.08 0.90 0.05 1.22

Ramp
Sloped 1 1.30 0.51 Area 0.66
Wall Top 1 1.33 0.25 0.05 0.02
1 6.80 0.13 0.05 0.04
Lab/ECD/Store/Pantry 4 5.70 6.70 0.08 11.46
Corridor 4 5.70 2.20 0.08 3.76
1 4.20 2.20 0.08 0.69
Below Staircase 1 4.20 6.70 0.08 2.11
Total 22.41 cu.m

2.2 P.C.C For R.C.C. Works


A Foundation
Isolated F1 Base 2 2.50 2.50 0.25 3.13
Isolated F1 Slope 2 3.63 Area 0.35 2.54
Isolated F2 Base 4 3.00 3.00 0.25 9.00

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Isolated F2 Slope 4 5.00 Area 0.35 7.00
Combined CF1 3 1.80 5.00 0.60 16.20
Combined CF2 1 3.00 5.00 0.60 9.00
Combined CF3 2 2.80 5.00 0.60 16.80

B Beam
Foundation beam (300x400)
Along Grid A & F 2 3.50 0.30 0.40 0.84
Along Grid B 1 3.30 0.30 0.40 0.40
Grid C & D 2 3.55 0.30 0.40 0.85
Along Grid E 1 3.25 0.30 0.40 0.39
Along Grid 1 1 12.50 0.30 0.40 1.50
Along Grid 2,3 2 15.10 0.30 0.40 3.62

Plinth Tie beam(300x450)


Along grid 1,2,3 3 26.00 0.30 0.45 10.53
Along Grid A,B,C,D,E,F 6 8.50 0.30 0.45 6.89

First floor level (+3.00m Lvl)


Main beam
Along grid 1,2 & 3 3 26 0.3 0.4 9.36
Along grid A,B,C,D,E & F 6 8.5 0.3 0.4 6.12

Secondary beam
Along grid 1a 2 10.9 0.25 0.3 1.64
Along grid 1b 1 4.2 0.25 0.3 0.32
Along grid A1,B1,D1 & E1 4 8.9 0.25 0.3 2.67

Edge Beam(125x525)
Grid B,C 1 7.90 0.13 0.3 0.30

Second floor level (+6.00m Lvl)


Main beam
Along grid 1,2 & 3 3 26 0.3 0.4 9.36
Along grid A,B,C,D,E & F 6 8.5 0.3 0.4 6.12

Secondary beam
Along grid 1a 2 10.9 0.25 0.3 1.64
Along grid 1b 1 4.2 0.25 0.3 0.32
Along grid A1,B1,D1 & E1 4 8.9 0.25 0.3 2.67

Beam(Third floor level)


Main beam
Along grid 1,2 & 3 3 26 0.3 0.4 9.36
Along grid A,B,C,D,E & F 6 8.5 0.3 0.4 6.12

Secondary beam
Along grid 1a 2 10.9 0.25 0.3 1.64
Along grid 1b 1 4.2 0.25 0.3 0.32
Along grid A1,B1,D1 & E1 4 8.9 0.25 0.3 2.67

Beam(Roof level)
Main beam
Along grid 1,2 & 3 3 4 0.3 0.4 1.44
Along grid C & D 2 8.5 0.3 0.4 2.04

Secondary beam
Along grid 1a 1 4.2 0.25 0.3 0.32

C Column
Ground floor plan

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Total columns(500x500) 18 0.50 0.50 3.00 13.50

First floor plan


Total columns(500x500) 18 0.50 0.50 3.00 13.50

Second floor plan


Total columns(500x500) 18 0.50 0.50 3.00 13.50

Top Floor Plan


Total columns(500x500) 6 0.50 0.50 2.63 3.94

Column below Plinth level


Total columns(500x500) 18 0.50 0.50 1.05 4.73

D Slab
First floor level (+3.00m Lvl) 1 305.15 Area 0.13 38.14
Deduction
Column deduction -18 0.50 0.50 0.13 -0.56
Void deduction -1 4.78 4.20 0.13 -2.61
Projections
At Back 2 11.50 0.70 0.13 2.01
At Front 1 6.20 1.00 0.13 0.78

Slab(second floor level) 1 305.15 Area 0.13 38.14


Deduction
Column deduction -18 0.50 0.50 0.13 -0.56
Void deduction -1 4.78 4.20 0.13 -2.61
Projections
At Back 2 11.50 0.70 0.13 2.01

Slab(Third floor level) 1 305.15 Area 0.13 38.14


Cantilevered portion(back) 2 13.35 1.1 0.15 4.41
Cantievered portion(side) 2 9.7 1.1 0.15 3.20
Cantilevered portion(front) 1 31 1.1 0.15 5.12
Cantilever front(projection) 1 7 0.5 0.15 0.53

Roof floor level (+11.625m Lvl) 1 11.50 6.50 0.13 9.34


Column deduction -6 0.50 0.50 0.13 -0.19

E Staircase
Ground floor level
Bottom 1 2.07 2.00 0.20 0.83
Landing 1 2.20 2.00 0.20 0.88
1 2.00 2.10 0.20 0.84
Waist Slab 1 6.75 2.00 0.20 2.70
Steps 20 0.03 Area 2.00 1.20
Landing Beam 1 4.00 0.25 0.38 0.38

First floor level


Landing 1 2.20 2.00 0.20 0.88
1 2.00 2.10 0.20 0.84
External Slab 1 4.05 0.73 0.13 0.37
Waist Slab 1 6.75 2.00 0.21 2.77
Steps 20 0.03 Area 2.00 1.20
Landing Beam 1 4.05 0.25 0.38 0.38

Second floor level


Landing 1 2.20 2.00 0.20 0.88
1 2.00 2.10 0.20 0.84
External Slab 1 4.05 0.73 0.13 0.37
Waist Slab 1 6.75 2.00 0.21 2.77
Steps 20 0.03 Area 2.00 1.20

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Landing Beam 1 4.05 0.25 0.38 0.38
Projections 3 4.00 0.70 0.13 1.05

F Vertical support bands


Ground Floor level
Along Grid 2 7.00 0.08 0.23 2.48 0.30
First floor level
Along Grid 2 6.00 0.08 0.23 2.48 0.26
Second floor level
Along Grid 2 8.00 0.08 0.23 2.48 0.34

G Lintel Bands
Ground floor level
Short Span
Along grid A,C,D,E,F 5 6.50 0.23 0.08 0.56
Between B,C 1 4.70 0.125 0.08 0.04
1 2.05 0.23 0.08 0.04
Long Span
Along grid 1 1 22.20 0.23 0.08 0.38
Along grid 2 1 21.68 0.23 0.08 0.37

First floor level


Short Span
Along grid A,C,D,E,F 5 6.50 0.23 0.08 0.56
Between B,C 1 5.03 0.125 0.08 0.05
1 1.73 0.23 0.08 0.03
Long Span
Along grid 1 1 22.20 0.23 0.08 0.38
Along grid 2 1 21.75 0.23 0.08 0.38

Second floor level


Short Span
Along grid A,C,D,E,F 5 6.50 0.23 0.08 0.56
Between B,C 1 5.03 0.125 0.08 0.05
1 1.73 0.23 0.08 0.03
Long Span
Along grid 1 1 22.20 0.23 0.08 0.38
Along grid 2 1 21.75 0.23 0.08 0.38

Between Principal/Admin 1.00 1.50 0.23 0.08 0.03


1.00 4.25 0.13 0.08 0.04

Deduction of Doors/Windows for Lintels


Ground floor level
D1 -6 1.10 0.23 0.08 -0.11
D3 -1 1.00 0.23 0.08 -0.02
First floor level
D1 -6 1.10 0.23 0.08 -0.11
D3 -1 1.00 0.23 0.08 -0.02
Second floor level
D1 -8 1.10 0.23 0.08 -0.15
D3 -1 1.00 0.23 0.08 -0.02
G Sill Bands
Ground floor level
Short Span
Along grid A,C,D,E,F 5 6.50 0.23 0.08 0.56
Between B,C 1 2.05 0.23 0.08 0.04
1 4.70 0.125 0.08 0.04
Long Span
Along grid 1 1 26.20 0.23 0.08 0.45
Along grid 2 1 21.68 0.23 0.08 0.37

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Below staircase 1 4.23 0.125 0.08 0.04

First floor level


Short Span
Along grid A,C,D,E,F 5 6.50 0.23 0.08 0.56
Between B,C 1 5.03 0.125 0.08 0.05
1 1.73 0.23 0.08 0.03
Long Span
Along grid 1 1 26.20 0.23 0.08 0.45
Along grid 2 1 21.75 0.23 0.08 0.38

Second floor level


Short Span
Along grid A,C,D,E,F 5 6.50 0.23 0.08 0.56
Between B,C 1 5.03 0.125 0.08 0.05
1 1.73 0.23 0.08 0.03
Long Span
Along grid 1 1 26.20 0.23 0.08 0.45
Along grid 2 1 21.75 0.23 0.08 0.38

Between Principal/Admin 1.00 1.50 0.23 0.08 0.03


1.00 4.25 0.13 0.08 0.04
Top floor level
Along grid C,D 2.00 8.50 0.23 0.08 0.29
Along grid 1,3 2.00 4.00 0.23 0.08 0.14

Deduction of Doors For Sill


Ground floor level
D1 -6 1.10 0.23 0.08 -0.11
D3 -1 1.00 0.23 0.08 -0.02
D4 -1 1.00 0.125 0.08 -0.01
First floor level
D1 -6 1.10 0.23 0.08 -0.11
D3 -1 1.00 0.23 0.08 -0.02
Second floor level
D1 -8 1.10 0.23 0.08 -0.15
D3 -1 1.00 0.23 0.08 -0.02
Top floor level
D2 -2 1.10 0.23 0.08 -0.04

H Soak Pit
RCC slab 1 2.27 Area 0.15 0.34

I Pedestal
Base Block 14 0.50 0.25 0.25 0.44

J Parapet Wall
Top Floor 2.00 36.53 0.35 0.10 2.56
1.00 7.50 0.35 0.10 0.26
Roof Level 1.00 33.00 0.35 0.10 1.16

K Bench
Bench Top Slab 2 2.40 0.50 0.08 0.18
L Slab for In-built Furniture
Furniture Slab for Lab 4 1.80 0.90 0.10 0.65
Sink slab type-1 1 9.43 0.50 0.10 0.47
Sink slab type-2 1 5.75 0.50 0.10 0.29
Sink slab type-3 1 3.60 0.90 0.10 0.32
Furniture slab in preparation room 1 6.75 0.60 0.10 0.41
Sink Deduction
Sink slab type-1 -2 0.70 0.35 0.10 -0.05
Sink slab type-2 -2 0.70 0.35 0.10 -0.05

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Sink slab type-3 -1 0.70 0.35 0.10 -0.02
Total 374.40 cu.m

2.3 Silica Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10 374.40 3,744.04
Total 3,744.04 Kg

2.5 Formworks
Formworks for RCC
A Foundation
Isolated footing
Isolated F1 2 10.00 0.25 5.00
Isolated F2 4 12.00 0.25 12.00
Combined footing
Combined CF1 3 13.60 0.60 24.48
Combined CF2 1 16.00 0.60 9.60
Combined CF3 2 15.60 0.60 18.72

B Beam
Foundation beam (300x400)
Along Grid A & F 2 3.50 0.80 5.60
Along Grid B 1 3.30 0.80 2.64
Grid C & D 2 3.55 0.80 5.68
Along Grid E 1 3.25 0.80 2.60
Along Grid 1 1 12.50 0.80 10.00
Along Grid 2,3 2 15.10 0.80 24.16
Along Grid 1 1 26.00 0.80 20.80
Along Grid 2,3 2 26.00 0.80 41.60

Plinth Tie beam(300x450)


Along grid 1,2,3 3 26.00 0.90 70.20
Along Grid A,B,C,D,E,F 6 8.50 0.90 45.90
Deduction
Along grid 2 -1 2.00 0.20 -0.40
First floor level (+3.00m Lvl)
Main beam(300x525)
Along grid 1 1 22.00 1.23 26.95
1 4.00 1.45 5.80
Along grid 2 1 26.00 1.10 28.60
Along grid 3 1 20.80 1.23 25.48
1 5.20 1.10 5.72
Along Grid A & F 2 8.50 1.23 20.83
Along Grid B & E 2 8.50 1.10 18.70
Along Grid C,D 2 4.50 1.10 9.90
2 4.75 1.23 11.64

Secondary beam(250x425)
Grid 1a 4 5.45 0.85 18.53
Grid 1b 1 4.20 0.70 2.94
Grid A1,B1,D1,E1 4 8.90 0.85 30.26

Edge Beam(125x525)
Grid B,C 1 7.90 1.05 8.30

Second floor level (+6.00m Lvl)


Main beam(300x525)
Along grid 1 1 22.00 1.23 26.95
1 4.00 1.45 5.80
Along grid 2 1 26.00 1.10 28.60
Along grid 3 1 26.00 1.23 31.85
Along Grid A & F 2 8.50 1.23 20.83
Along Grid B & E 2 8.50 1.10 18.70

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Along Grid C,D 2 3.75 1.10 8.25
2 4.75 1.23 11.64

Secondary beam(250x425)
Grid 1a 4 5.45 0.85 18.53
Grid 1b 1 4.20 0.70 2.94
Grid A1,B1,D1,E1 4 8.90 0.85 30.26

Top floor level (+9.00m Lvl)


Main beam(300x525)
Along grid 1 1 22.00 1.08 23.65
1 4.00 1.45 5.80
Along grid 2 1 26.00 1.10 28.60
Along grid 3 1 26.00 1.08 27.95
Along Grid A & F 2 8.50 1.08 18.28
Along Grid B & E 2 8.50 1.10 18.70
Along Grid C,D 2 3.75 1.10 8.25
2 4.75 1.23 11.64
Secondary beam(250x425)
Grid 1a 4 5.45 0.85 18.53
Grid 1b 1 4.20 0.70 2.94
Grid A1,B1,D1,E1 4 8.90 0.85 30.26

Roof floor level (+11.625m Lvl)


Main beam(300x525)
Along grid 1,2,3 3 4.00 1.10 13.20
Along Grid C,D 2 8.50 1.10 18.70

Secondary beam(250x425)
Grid 1a 1 4.20 0.85 3.57
Landing beam 3 0.85 4.00 10.20

C Column
Ground floor plan
Total columns(500x500) 18 2.00 2.88 103.50

First floor plan


Total columns(500x500) 18 2.00 2.88 103.50

Second floor plan


Total columns(500x500) 18 2.00 2.88 103.50

Top Floor Plan


Total columns(500x500) 6 2.00 2.50 30.00

Column below Plinth level


Total columns(500x500) 18 2.00 1.05 37.80

D Slab
First floor level (+3.00m Lvl) 1 28.80 9.80 282.24
Cantilever slab back side 2 11.75 0.70 16.45
Cantilever slab front side 1 6.15 1.00 6.15
Deduction
Void deduction -1 4.75 4.20 -19.95

Main beam(300x500)
Along grid 1,2,3 -3 26.00 0.30 -23.40
Along Grid A,B,E,F -4 8.50 0.30 -10.20
Along Grid C,D -2 9.25 0.30 -5.55

Secondary beam(250x425)
Grid 1a -4 5.45 0.25 -5.45

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Grid 1b -1 4.20 0.25 -1.05
Grid A1,B1,D1,E1 -4 8.90 0.25 -8.90

Edge Beam(125x525)
Grid B,C -1 7.90 0.13 -0.99

Second floor level (+6.00m Lvl) 1 28.80 9.80 282.24


Cantilever slab 2 11.75 0.70 16.45
Deduction
Void deduction -1 4.75 4.20 -19.95

Main beam(300x525)
Along grid 1,2,3 -3 26.00 0.30 -23.40
Along Grid A,B,E,F -4 8.50 0.30 -10.20
Along Grid C,D -2 8.50 0.30 -5.10

Secondary beam(250x425)
Grid 1a -4 5.45 0.25 -5.45
Grid 1b -1 4.20 0.25 -1.05
Grid A1,B1,D1,E1 -4 8.90 0.25 -8.90

Top floor level (+9.00m Lvl) 1 370.45 Area 370.45


Edge around slab 1 84.70 0.15 12.71
Deduction
Void deduction -1 4.75 4.20 -19.95

Main beam(300x525)
Along grid 1,2,3 -3 26.00 0.30 -23.40
Along Grid A,B,E,F -4 8.50 0.30 -10.20
Along Grid C,D -2 8.50 0.30 -5.10

Secondary beam(250x425)
Grid 1a -4 5.45 0.25 -5.45
Grid 1b -1 4.20 0.25 -1.05
Grid A1,B1,D1,E1 -4 8.90 0.25 -8.90

Roof floor level (+11.625m Lvl) 1 6.50 11.50 74.75


Slab Edge 1 36.00 0.13 4.50
Deduction
Main beam(300x525)
Along grid 1,2,3 -3 4.00 0.30 -3.60
Along Grid C,D -2 8.50 0.30 -5.10

Secondary beam(250x425)
Grid 1a -1 4.20 0.25 -1.05
E Staircase
Ground floor level
Bottom 1 2.07 0.20 0.41
Waist Slab 1 6.75 2.00 13.50
Side 1 6.75 0.20 1.35
Landing 1 2.20 1.65 3.64
1 2.00 2.15 4.29
Side 1 3.80 0.15 0.57
Riser 20 2.00 0.15 6.00
Landing Beam 1 4.00 0.86 3.44

First floor level


External Slab 1 4.25 0.83 3.51
Waist Slab 1 6.75 2.00 13.50
Side 1 6.75 0.20 1.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Landing 1 2.20 1.65 3.64
1 2.00 2.15 4.29
Side 1 3.80 0.15 0.57
Riser 20 2.00 0.15 6.00
Landing Beam 1 4.00 0.71 2.82

Second floor level


Top Floor Passage 1 2.20 0.13 0.28
Waist Slab 1 6.75 2.00 13.50
Side 1 6.75 0.20 1.35
Landing 1 2.20 1.65 3.64
1 2.00 2.15 4.29
Side 1 3.80 0.15 0.57
Riser 20 2.00 0.15 6.00
Landing Beam 1 4.00 0.71 2.82

F Vertical support bands


Ground Floor level
Along Grid 2 7.00 0.40 2.48 6.93
First floor level
Along Grid 2 6.00 0.40 2.48 5.94
Second floor level
Along Grid 2 8.00 0.40 2.48 7.92

G Lintel Bands
Ground floor level
Along grid A,C,D,E,F 5.00 6.50 0.15 4.88
Along grid 1 1.00 22.20 0.15 3.33
Along grid 2 1.00 21.68 0.15 3.25
Between B,C 1.00 4.70 0.15 0.71
1.00 2.05 0.15 0.31
First floor level
Along grid A,C,D,E,F 5.00 6.50 0.15 4.88
Along grid 1 1.00 22.20 0.15 3.33
Along grid 2 1.00 21.75 0.15 3.26
Between B,C 1.00 5.03 0.15 0.75
1.00 1.73 0.15 0.26
Second floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.15 5.85
Along grid 1 1.00 22.20 0.15 3.33
Along grid 2 1.00 21.60 0.15 3.24
Between Principal/Admin 1.00 1.50 0.15 0.23
1.00 4.25 0.15 0.64

Deduction of Doors/Windows for Lintels


Ground floor level
D1 -6 1.10 0.15 -0.99
D3 -1 1.00 0.15 -0.15
First floor level
D1 -6 1.10 0.15 -0.99
D3 -1 1.00 0.15 -0.15
Second floor level
D1 -8 1.10 0.15 -1.32
D3 -1 1.00 0.15 -0.15
H Sill Bands
Ground floor level
Along grid A,C,D,E,F 5.00 6.50 0.15 4.88
Along grid 1 1.00 26.20 0.15 3.93
Along grid 2 1.00 21.68 0.15 3.25
Between B,C 1.00 2.05 0.15 0.31
1.00 4.70 0.15 0.71

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Below staircase 1.00 4.23 0.15 0.63
First floor level
Along grid A,C,D,E,F 5.00 6.50 0.15 4.88
Along grid 1 1.00 26.20 0.15 3.93
Along grid 2 1.00 21.75 0.15 3.26
Between B,C 1.00 5.03 0.15 0.75
1.00 1.73 0.15 0.26
Second floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.15 5.85
Along grid 1 1.00 26.20 0.15 3.93
Along grid 2 1.00 21.60 0.15 3.24
Between Principal/Admin 1.00 1.50 0.15 0.23
1.00 4.25 0.15 0.64
Top floor level
Along grid C,D 2.00 8.50 0.15 2.55
Along grid 1,3 2.00 4.00 0.15 1.20

Deduction of Doors For Sill


Ground floor level
D1 -6 1.10 0.15 -0.99
D3 -1 1.00 0.15 -0.15
D4 -1 1.00 0.15 -0.15
First floor level
D1 -6 1.10 0.15 -0.99
D3 -1 1.00 0.15 -0.15
Second floor level
D1 -8 1.10 0.15 -1.32
D3 -1 1.00 0.15 -0.15
Top floor level
D2 -2 1.10 0.15 -0.33

I Pedestal
Base Block 14 1.25 0.25 4.38

J Parapet Wall
Top Floor 2.00 36.53 0.25 18.27
1.00 7.50 0.25 1.88
Roof Level 1.00 33.00 0.25 8.25
K Bench
Bench Top Slab 2 5.80 Perimeter 0.075 0.87
Bottom 2 5.80 0.60 6.96
Deduction -4 0.13 0.50 -0.25
L Slab For In-built Furniture
Furniture Slab for Lab 4 1.80 0.90 6.48
4 5.40 0.10 2.16
Sink slab type-1 1 9.43 0.50 4.71
1 10.43 0.10 1.04
2 2.10 0.10 0.42
Sink deduction -2 0.70 0.35 -0.49
Sink slab type-2 1 5.75 0.50 2.88
1 6.75 0.10 0.68
2 2.10 0.10 0.42
Sink Deduction -2 0.70 0.35 -0.49
Sink slab type-3 1 3.60 0.90 3.24
1 9.00 0.10 0.90
1 2.10 0.10 0.21
Sink deduction -1 0.70 0.35 -0.25
Furniture slab in preparation room 1 6.75 0.60 4.05
1 6.75 0.10 0.68

M Soak Pit
RCC slab 1.00 1.13 Area 1.13

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Along Sides 1.00 5.34 0.15 0.80
Total 2,433.42 sq.m

3.2 BRICK MASONRY WORKS ( 1 : 4 c/s )


Brick Works upto Plinth Beam
Along grid A,B,C,D,E,F 6 8.50 0.23 0.20 2.35
Along grid 1, 2, 3/A-F 3 26.20 0.23 0.20 3.62

Brick Works above Plinth Beam


Ground floor level
Short Span
Along grid A,C,D,E,F 6 6.50 0.23 2.33 20.86
Long Span
Along grid 1 1 26.20 0.23 2.33 14.01
Along grid 2 1 22.20 0.23 2.33 11.87
Below staircase 1 4.23 0.23 1.82 1.77

First floor level


Short Span
Along grid A,C,D,E,F 6 6.50 0.23 2.33 20.86
Long Span
Along grid 1 1 26.20 0.23 2.33 14.01
Along grid 2 1 22.20 0.23 2.33 11.87

Second floor level


Short Span
Along grid A,C,D,E,F 6 6.50 0.23 2.33 20.86
Long Span
Along grid 1 1 26.20 0.23 2.33 14.01
Along grid 2 1 22.20 0.23 2.33 11.87

Between Principal/Admin 1 1.50 0.23 2.73 0.94


Computer Lab 2 3.60 0.23 1.20 1.99
Deduction
D3 -1 1.00 0.23 1.95 -0.45

Top floor level


Along grid C,D 2 8.50 0.23 2.03 7.92
Along grid 1 1 4.00 0.23 2.03 1.86
Along grid 3 1 4.00 0.23 2.03 1.86

Parapet Wall
Top Floor 2.00 36.53 0.23 0.80 13.44
1.00 7.50 0.23 1.40 2.42
Roof Level 1.00 33.00 0.23 0.90 6.83

Outside
Steps 1 28.58 0.60 0.15 2.57
1 28.58 0.30 0.15 1.29
Ramp
Wall Along -B 1 1.33 0.25 Area 0.33
1 6.91 0.17 Area 1.19

Deduction for doors and windows


Ground floor level
W1 -18 1.10 0.23 1.13 -5.12
V1 -18 1.10 0.23 0.53 -2.39
W3 -1 1.50 0.23 0.37 -0.13
D1 -6 1.10 0.23 2.33 -3.53
First floor level
W1 -17 1.10 0.23 1.13 -4.84
V1 -17 1.10 0.23 0.53 -2.26

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
W2 -1 1.50 0.23 1.00 -0.35
D1 -7 1.10 0.23 2.33 -4.12

Second floor level


W1 -16 1.10 0.23 1.13 -4.55
V1 -16 1.10 0.23 0.53 -2.13
W2 -1 1.50 0.23 1.00 -0.35
D1 -8 1.10 0.23 2.33 -4.71
Top floor level
W2 -1 1.50 0.23 1.00 -0.35
D2 -2 1.10 0.23 1.83 -0.92
Total 154.40 cu.m

3.3 Half Brick (125 mm) Works (1:4c/s)


Ground floor
Partition Wall 1 4.70 2.73 12.81
Below Staircase(Store)
1 1.57 Area 1.57
1 1.42 Area 1.42
1 2.00 1.59 3.18
Deductions D4 -1 1.00 1.55 -1.55
First floor 1 5.03 2.73 13.69
Second floor 1 4.25 2.73 11.58
Ramp
Grid 3AB
1 1.40 0.22 0.31
1 5.12 0.22 1.13
Bench
Below external bench 8 0.50 0.43 1.70

For In-built Furniture


Below Sink slab type-1 1 2.98 0.65 1.93
1 0.33 0.65 0.21
Below Sink slab type-2 1 2.98 0.65 1.93
Below Sink slab type-3 1 0.75 0.65 0.49
Furniture slab in preparation room 1 1.58 0.65 1.02
Total 51.43 Sq.m

3.4 Honey Comb Brick (350 mm) Works (1:3c/s)


Soak Pit Brick work 1 1.71 1.88 3.21
Total 3.21 cu.m

4 DOORS & WINDOWS


4.1 Metal Frame
4.1.1 Doors Frame
Ground floor
D1 6 7.07 Perimeter 42.42
D3 1 5.20 Perimeter 5.20
D4 1 4.10 Perimeter 4.10
First floor
D1 7 7.07 Perimeter 49.49
D3 1 5.20 Perimeter 5.20
Second floor
D1 8 7.07 Perimeter 56.56
D3 1 5.20 Perimeter 5.20
Top floor
D2 2 4.90 Perimeter 9.80
Total 177.97 r.m

4.1.2 Windows Frame


Ground floor
W1 18 5.58 Perimeter 100.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
V1 18 3.25 Perimeter 58.50
First Floor
W1 17 5.58 Perimeter 94.78
W2 1 6.00 Perimeter 6.00
V1 17 3.25 Perimeter 55.25
Second Floor
W1 16 5.58 Perimeter 89.20
W2 1 6.00 Perimeter 6.00
V1 16 3.25 Perimeter 52.00
Top floor
W2 1 6.00 Perimeter 6.00
Total 468.08 r.m

4.2 Metal Shutter


4.2.1 Windows shutter
W1 51 1.10 1.13 63.11
W2 3 1.50 1.00 4.50
V1 51 1.10 0.53 29.45
Total 97.07 sq.m

4.3 Wooden Shutter


4.3.1 Door Shutter
D1 21 1.10 2.44 56.25
D2 2 1.10 1.90 4.18
D3 3 1.00 2.10 6.30
D4 1 1.00 1.55 1.55
Total 68.28 sq.m
4.4 Window Grill
Shutter Area of Window
W1 51 1.10 1.13 63.11
W2 3 1.50 1.00 4.50
W3 1 1.50 0.37 0.56
V1 51 1.10 0.53 29.45
Total 97.62 sq.m
4.5 Collapsable Gate
1.00 4.00 2.48 9.90
Total 9.90 Sq.m

5 FLOORING WORKS
5.1 Hardened Cement Concrete Flooring (40mm) With Neat Cement Punning
Ground floor plan
Laboratory 1.00 9.43 6.75 63.62
Store 1.00 2.23 6.75 15.02
Class Room/Store,Pantry 2.00 5.75 6.75 77.63
Corridor 1.00 28.80 2.37 68.26
1.00 4.20 2.37 9.95
Staircase Below 1.00 6.625 4.2 27.83

Staircase
Staircase Tread 18.00 0.30 2.00 10.80
Riser 20.00 0.15 2.00 6.00
Staircase landing 1.00 2.00 2.20 4.40
1.00 2.13 2.00 4.25

Ramp 1 6.52 1.30 8.48


Exterior Steps 1 28.58 1.05 30.00

First floor plan


Library 1.00 9.43 6.75 63.62

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Store 1.00 2.23 6.75 15.02
Class Rooms 2.00 5.78 6.75 77.96
Corridor 1.00 28.80 2.37 68.26
1.00 4.20 2.37 9.95
Staircase
Staircase Tread 18.00 0.30 2.00 10.80
Riser 20.00 0.15 2.00 6.00
Staircase landing 1.00 2.00 2.20 4.40
1.00 2.13 2.00 4.25
Second floor plan
Computer lab 1.00 5.75 6.75 38.81
Class Room/Teacher's Room 2.00 5.78 6.75 77.96
Principal 1.00 5.75 3.55 20.41
Admin 1.00 5.75 3.25 18.69
Corridor 1.00 28.80 2.37 68.26
1.00 4.20 2.37 9.95
Staircase
Staircase Tread 18.00 0.30 2.00 10.80
Riser 20.00 0.15 2.00 6.00
Staircase landing 1.00 2.00 2.20 4.40
1.00 2.13 2.00 4.25
Top floor plan
Corridor 1.00 4.45 4.20 18.69
Top Floor Slab 1.00 283.86 Area 283.86

Roof plan
Roof Floor Slab 1.00 5.50 10.50 57.75
Total 1206.32 sq.m

5.2 Neat Cement Skirting works


Ground floor plan
Laboratory 1.00 32.75 32.75
Store 1.00 17.95 17.95
Store/Pantry/ECD 2.00 25.35 50.70
Column 6.00 2.00 12.00
Corridor 1.00 30.23 30.23
Store Below Landing 1.00 17.00 17.00
1.00 4.00 4.00
Staircase/Landing 1.00 14.25 14.25
Staircase Waist Slab 1.00 3.00 3.00
Deduction
D1 -12.00 1.10 -13.20
D3 -2.00 1.00 -2.00
D4 -2.00 1.00 -2.00
First floor plan
Library 1.00 32.75
Store 1.00 17.95 17.95
Class Room 2.00 25.35 50.70
Corridor 1.00 30.23 30.23
Column 2.00 0.80 1.60
4.00 1.30 5.20
Staircase/Landing 1.00 14.25 14.25
Staircase Waist Slab 1.00 3.00 3.00
Deduction
D1 -14.00 1.10 -15.40
D3 -2.00 1.00 -2.00
Second floor plan
Computer lab 1.00 25.30 25.30
Class Room/Teacher's Room 2.00 25.35 50.70
Principal 1.00 18.60 18.60
Admin 1.00 17.65 17.65
Column 2.00 0.80 1.60

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
4.00 1.30 5.20
Corridor 1.00 30.23 30.23
Staircase/Landing 1.00 14.25 14.25
Staircase Waist Slab 1.00 3.00 3.00
Deduction
D1 -16.00 1.10 -17.60
D3 -2.00 1.00 -2.00
Top floor Plan
Corridor 1.00 13.80 13.80
Top Floor Outer wall 1.00 106.35 106.35
Deduction
D2 -4.00 1.10 -4.40
Roof Plan
Along Wall 1.00 32.00 32.00
Total 564.86 r.m

5.3 25mm Terrazo Finishing


For In-built Furniture
Furniture Slab for Lab 4 2.00 1.10 8.80
Sink slab type-1 1 9.43 0.60 5.66
Sink slab type-2 1 5.95 0.60 3.57
Sink slab type-3 1 3.80 1.10 4.18
Furniture slab in preparation room 1 6.75 0.60 4.05
Bench 2 2.40 0.50 2.40
Total 28.66 sq.m

7 PLASTER WORKS
7.1 Internal Cement Plaster
7.1.1 Internal Plaster on Wall (1:6)
Ground Floor
Laboratory 1 32.75 2.88 94.16
Store 1 17.95 2.88 51.61
Store/Pantry/ECD 2 25.35 2.88 145.76

Staircase 1.00 17.45 2.88 50.17


Store Below Landing 2.00 1.57 Area 3.13
2.00 0.45 1.30 1.17
1.00 1.42 Area 1.42
2.00 1.96 1.59 6.23
Column
Grid 1A, 1F 2.00 0.15 2.88 0.86
Grid 1B,1E 2.00 0.80 2.88 4.61
Grid 1C,1D 2.00 0.45 2.88 2.60
Grid 2A,2F 2.00 1.25 2.88 7.19
Grid 2C,2D 2.00 1.54 2.88 8.86
Grid 2B,2E 2.00 1.31 2.88 7.53

Deductions
W1 -18 1.10 1.13 -11.14
V1 -18 1.10 0.53 -5.20
W3 -1 1.50 0.37 -0.28
D1 -6 1.10 2.44 -8.04
D3 -2 1.00 2.10 -2.10
D4 -2 1.00 1.55 -1.55

For In-built Furniture


Furniture Slab for Bottom 4 1.80 0.90 6.48
-8 0.60 0.25 -1.20
Wall 8 1.70 0.65 8.84
Sink slab type-1 Bottom 1 9.43 0.60 5.66

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Deduct Sink -2 0.95 0.43 -0.81
-4 0.43 0.13 -0.21
Wall 6 0.98 0.65 3.80
2 0.55 0.65 0.72
Sink slab type-2 1 6.75 0.10 0.68
Bottom 1 5.75 0.50 2.88
Deduct Sink -2 0.95 0.43 -0.81
-3 0.43 0.13 -0.16
Wall 7 0.98 0.65 4.44
Sink slab type-3 1 9.00 0.10 0.90
Bottom 1 3.60 0.90 3.24
Deduct Sink -1 0.75 0.35 -0.26
-2 0.75 0.25 -0.38
-1 0.75 0.13 -0.09
Wall 1 5.75 0.65 3.74
Furniture slab in Store room 1 6.75 0.70 4.73
Deduct Wall -3 0.53 0.13 -0.20
Wall 3 1.18 0.65 2.29

First floor plan


Library 1 32.75 2.88 94.16
Store 1 17.95 2.88 51.61
Class Room 2 25.35 2.88 145.76
Staircase 1.00 17.45 2.88 50.17
Column
Grid 2C,2D 2.00 1.23 2.88 7.04
Grid 2B,2E 2.00 0.75 2.88 4.31
Grid 1A, 1F 2.00 0.15 2.88 0.86
Grid 1B,1E 2.00 0.80 2.88 4.61
Grid 1C,1D 2.00 0.45 2.88 2.60
Grid 2A,2F 2.00 1.25 2.88 7.19
Grid 2C,2D 2.00 1.54 2.88 8.86
Grid 2B,2E 2.00 1.31 2.88 7.53
Deductions
W1 -18 1.10 1.13 -11.14
V1 -18 1.10 0.53 -5.20
W2 -1 1.50 1.00 -0.75
D1 -6 1.10 2.44 -8.04
D3 -2 1.00 2.10 -2.10
Second Floor
Computer lab 1 25.30 2.88 72.74
1200mm High Brick Wall 2 7.45 1.20 17.88
2 3.60 0.25 1.80
Class Room/Teacher's Room 2 25.05 2.88 144.04
Principal 1 18.25 2.88 52.47
Admin 1 18.25 2.88 52.47
Staircase 1.00 17.45 2.88 50.17
Column
Grid 1A, 1F 2.00 0.15 2.88 0.86
Grid 1B,1E 2.00 0.60 2.88 3.46
Grid 1C,1D 2.00 0.45 2.88 2.60
Grid 2A,2F 2.00 1.25 2.88 7.19
Grid 2C,2D 2.00 1.54 2.88 8.86
Grid 2B,2E 2.00 1.31 2.88 7.53
Deductions
W1 -16 1.10 1.13 -9.90
V1 -16 1.10 0.53 -4.62
W2 -1 1.50 1.00 -0.75
D1 -8 1.10 2.44 -10.71
D3 -2 1.00 2.10 -2.10
Top Floor
Along Grid 1&3/ C-D 2.00 4.00 2.10 8.40

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Along Grid C&D/ 1-3 2.00 9.65 2.10 20.27
Deductions
W2 -1 1.50 1.00 -0.75
D2 -2 1.10 1.90 -2.09
Total 1,178.52 sq.m

7.1.2 Internal Plaster on Ceiling (1:4)


First Floor Level (+3.00m Lvl)
Laboratory 1 9.425 6.75 63.62
Store 1 2.225 6.75 15.02
Class Room/Store,Pantry 2 5.78 6.75 38.98
Corridor 1 28.80 2.63 37.80
1 2.07 4.20 4.35
Staircase 1 6.75 2.00 6.75
Staircase Landing 1 1.90 4.20 3.99

Main Beam (300x525)


Grid 1 4 5.50 0.95 20.90
1 4.00 0.95 3.80
Grid 2 4 5.50 0.95 20.90
1 4.00 1.10 2.20
Grid 3/A-F 4 5.55 1.23 13.60
1 4.00 1.23 2.45
Grid A,B,C,D,E,F /2-3 6 2.00 1.10 6.60
Grid B,C,D,E /1-2 4 6.50 1.10 14.30
Grid A,F /1-2 2 6.50 0.48 3.09
Canopy With Edge Beam 1 6.15 1.93 5.92
2 0.88 1.05 0.92
1 6.15 0.98 3.00
Secondary Beam (250x425)
Grid A1,B1,D1,E1 1 8.90 0.60 2.67
Grid 1a 1 18.20 0.60 5.46
Grid 1b 1 4.20 0.60 1.26

Second Floor Level (+6.00m Lvl)


Library 1 9.43 6.75 31.81
Store 1 2.23 6.75 7.51
Class Rooms 2 5.78 6.75 38.98
Corridor 1 28.80 2.63 37.80
1 2.07 4.20 4.35
Staircase 1 6.75 2.00 6.75
Staircase Landing 1 1.90 4.20 3.99

Main Beam (300x525)


Grid 1 4 5.50 0.95 20.90
1 4.00 0.95 3.80
Grid 2 4 5.50 0.95 20.90
1 4.00 1.10 2.20
Grid 3/A-F 4 5.55 1.23 13.60
1 4.00 1.23 2.45
Grid A,B,C,D,E,F /2-3 6 2.00 1.10 6.60
Grid B,C,D,E /1-2 4 6.50 1.10 14.30
Grid A,F /1-2 2 6.50 0.48 3.09
Secondary Beam (250x425)
Grid A1,B1,D1,E1 1 8.90 0.60 2.67
Grid 1a 1 18.20 0.60 5.46
Grid 1b 1 4.20 0.60 1.26

Top Floor Level (+9.00m Lvl)


Computer lab 1 5.75 6.75 38.81
Class Room/Teacher's Room 2 5.78 6.75 77.96
Principal 1 5.75 3.55 20.41

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Admin 1 5.75 3.075 17.68
Corridor 1 28.80 2.63 37.80
1 2.07 4.20 4.35
Staircase 1 6.75 2.00 6.75
Staircase Landing 1 1.90 4.20 3.99

Main Beam (300x525)


Grid 1 4 5.50 0.95 20.90
1 4.00 0.95 3.80
Grid 2 4 5.50 0.95 20.90
1 4.00 1.10 2.20
Grid 3/A-F 4 5.55 1.23 13.60
1 4.00 1.23 2.45
Grid A,B,C,D,E,F /2-3 6 2.00 1.10 6.60
Grid B,C,D,E /1-2 4 6.50 1.10 14.30
Grid A,F /1-2 2 6.50 0.48 3.09

Secondary Beam (250x425)


Grid A1,B1,D1,E1 1 8.90 0.60 2.67
Grid 1a 1 18.20 0.60 5.46
Grid 1b 1 4.20 0.60 1.26

Roof Floor Level (+11.625m Lvl)


Staircase with Corridor 1 4.20 9.25 19.43

Main Beam (300x525)


Grid 2/C-D 1 4.00 0.95 1.90

Secondary Beam (250x425)


Grid 1a/C-D 1 4.20 0.60 1.26
Total 833.56 sq.m

7.1.3 External Plaster


Beam Plaster
First Floor Level
Main Beam (300x525)
Along grid 1 1.00 26.20 0.53 13.76
Slab Extension 1.00 23.50 1.23 28.79
Landing Beam 1.00 4.00 0.56 2.24
Along grid A,F 2.00 6.50 0.53 6.83

Second Floor Level


Main Beam (300x525)
Along grid 1 1.00 26.20 0.53 13.76
Slab Extension 1.00 23.50 1.23 28.79
Landing Beam 1.00 4.00 0.81 3.24
Landing Beam Extension 1.00 4.00 1.23 4.90
Along grid A and F 2.00 6.50 0.53 6.83

Third Floor Level


Main Beam (300x525)
Along grid 1 1.00 26.20 0.53 13.76
Slab Extension (All Sides) 1.00 88.77 Area 88.77
Slab Extension (Top Side) 1.00 20.45 Area 20.45
Landing Beam 1.00 4.00 0.81 3.24
Landing Beam Extension 1.00 4.00 1.23 4.90
Along grid A and F 2.00 6.50 0.53 6.83

Roof Floor Level


Main Beam (300x525)
Along Perimeter 1.00 25.00 0.53 13.13
Slab Extension (All Sides) 1.00 28.30 Area 28.30

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Slab Extension (Top Side) 1.00 8.75 Area 8.75

Column Plaster
Ground Floor
Along grid 1
Grid 1A,1F 2.00 1.25 3.00 7.50
Grid 1B,1C,1D,1E 4.00 0.75 3.00 9.00
Along grid 3
Grid 3A,3B,3C,3D,3E,3F 6.00 1.50 2.48 22.28
6.00 0.50 3.00 9.00
First Floor
Along grid 1
Grid 1A,1F 2.00 1.25 3.00 7.50
Grid 1B,1C,1D,1E 4.00 0.75 3.00 9.00
Along grid 3
Grid 3A,3B,3C,3D,3E,3F 6.00 1.50 2.48 22.28
6.00 0.50 3.00 9.00
Second Floor
Along grid 1
Grid 1A,1F 2.00 1.25 3.00 7.50
Grid 1B,1C,1D,1E 4.00 0.75 3.00 9.00
Along grid 3
Grid 3A,3B,3C,3D,3E,3F 6.00 1.50 2.48 22.28
6.00 0.50 3.00 9.00
Parapet Wall
Top Floor 2 35.90 0.80 57.44
1 7.50 1.40 10.50
Roof 1 32.00 0.90 28.80

On Outer walls
Ground floor level
Along grid A,F/1-2 2 6.50 2.48 32.18
Along grid 1 4 5.55 2.48 54.95
1 4.00 2.10 8.38
Along grid 2 4 5.55 2.48 54.95
First floor level
Along grid A,F/1-2 2 6.50 2.48 32.18
Along grid 1 4 5.55 2.48 54.95
1 4.00 2.10 8.38
Along grid 2 4 5.55 2.48 54.95
Second floor level
Along grid A,F/1-2 2 6.50 2.48 32.18
Along grid 1 4 5.55 2.48 54.95
1 4.00 2.10 8.38
Along grid 2 4 5.55 2.48 54.95
Top floor level
Along grid C,D/1-3 2 8.50 2.10 35.70
Along grid 1 1 4.00 2.10 8.40
Along grid 3 1 4.00 2.10 8.40

Deduction for doors and windows


Ground floor level
W1 -12 1.10 1.13 -14.85
V1 -12 1.10 0.53 -6.93
W3 -1 1.50 0.37 -0.56
First floor level
W1 -12 1.10 1.13 -14.85
V1 -12 1.10 0.53 -6.93
W2 -1 1.50 1.00 -1.50
Second floor level
W1 -12 1.10 1.13 -14.85

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
V1 -12 1.10 0.53 -6.93
W2 -1 1.50 1.00 -1.50
Top floor level
W2 -1 1.50 1.00 -1.50
D2 -2 1.10 1.83 -4.02
Total 966.72 sq.m

7.2 Painting Works


7.2.1 Distemper Painting Works
As per Internal plaster on wall 1.00 1178.52 Area 1,178.52
As per Internal plaster on ceiling 1.00 833.56 Area 833.56
Total 2,012.08 sq.m

7.2.2 Exterior Weather Coat Paint


External Plaster 1.00 966.72 Area 966.72
Total 966.72 sq.m

7.2.4 Enamel Painting


Doors Factor
Collapsable Gate 1.00 4.00 2.48 2.00 19.80
D1 21 1.10 2.44 2.00 112.50
D2 2 1.10 1.90 2.00 8.36
D3 3 1.00 2.10 2.00 12.60
D4 1 1.00 1.55 2.00 3.10
Window
W1 51 1.10 1.13 2.00 126.23
W2 3 1.50 1.00 2.00 9.00
V1 51 1.10 0.53 2.00 58.91
Window Grill
W1 51 1.10 1.13 2.00 126.23
W2 3 1.50 1.00 2.00 9.00
W3 1 1.50 0.37 2.00 1.11
V1 51 1.10 0.53 2.00 58.91
Total 545.73 sq.m

8 MISCELLANOUS
8.4 Railing
Total
Staircase Railing length Kg/m
Length
Horizontal ISNB 40M 1 22.818 22.82 3.56 81.23
Horizontal ISNB 40M (Top Floor) 1 2.125 2.13 3.56 7.57
Vertical 38mm Square Pipe 6 0.92 5.52 2.82 15.57
Vertical 38mm Square Pipe 20 0.95 19.00 2.82 53.58
Horizontal 25mm Square Pipe 4 22.818 91.27 0.85 77.58
Horizontal 25mm Square Pipe (Top Floor) 4 2.125 8.50 0.85 7.23
Balcony Railing
First Floor
Horizontal ISNB 40M 1 30.2 30.20 3.56 107.51
Horizontal ISNB 32M 2 30.2 60.40 3.10 187.24
Vertical ISNB 32M 23 1.14 26.22 3.10 81.28
Inclined ISNB 32M 23 0.134 3.08 3.10 9.55
Vertical 25mm Square Pipe 208 0.82 170.56 0.85 144.98

Second Floor
Horizontal ISNB 40M 1 30.2 30.20 3.56 107.51
Horizontal ISNB 32M 2 30.2 60.40 3.10 187.24
Vertical ISNB 32M 23 1.14 26.22 3.10 81.28
Inclined ISNB 32M 23 0.134 3.08 3.10 9.55
Vertical 25mm Square Pipe 208 0.82 170.56 0.85 144.98

Parapet Wall
ISNB 40M(Horizontal Bars) 2 36.53 73.06 3.56 260.09

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
ISNB 32M(Horizontal Bars) 2 36.53 73.06 3.10 226.49
Vertical ISNB 32M 60 0.40 24.00 3.10 74.40
Inclined ISNB 32M 60 0.134 8.04 3.10 24.92
Vertical 25mm Square Pipe 492 0.30 147.60 0.85 125.46

Pedestal
ISNB 40M Pedestal Bars 14 1.54 21.57 3.56 76.80
14 1.20 16.80 3.56 59.81
28 0.40 11.20 3.56 39.87
Base plate 185 0.00009375 0.02 7850 136.15
12 mm dia. Anchor Bolt, Nut 740 0.13 96.20
Total 2,424.07 k.g

8.5 Sewer, Rain and Waste Water Installation


- 110 mm 4 9.00 36.00
2 2.90 5.80
Total 41.80 R.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
1 For Footing
1.1 Footing (F1) 2
X- direction 16 17 2.60 88.40 1.59 140.56 0.1 2.4 0.1

Y- direction 16 17 2.60 88.40 1.59 140.56 0.1 2.4 0.1

1.2 Footing (F2) 4


X- direction 16 20 3.10 248.00 1.59 394.32 0.1 2..9 0.1

Y- direction 16 20 3.10 248.00 1.59 394.32 0.1 2.9 0.1

1.3 Combine Footing (CF1) 3


(BLL) 12 33 2.10 207.90 0.89 185.03 0.2 1.7 0.2

(BUL) 16 12 5.30 190.80 1.59 303.37 0.2 4.9 0.2

(TUL) 12 33 2.10 207.90 0.89 185.03 0.2 1.7 0.2

(TLL) 12 12 5.30 190.80 0.89 169.81 0.2 4.9 0.2

1.4 Stirrups 10 98 3.95 1161.30 0.62 720.01 1.375


0.1
0.5

1.5 Combine Footing (CF2) 1


(BLL) 12 33 3.30 108.90 0.89 96.92 0.2 2.9 0.2

(BUL) 16 20 5.30 106.00 1.59 168.54 0.2 4.9 0.2

(TLL) 16 20 5.30 106.00 1.59 168.54 0.2 4.9 0.2

(TUL) 12 33 3.30 108.90 0.89 96.92 0.2 2.9 0.2

1.6 Stirrups 10 98 5.15 504.70 0.62 312.91 1.975


0.1
0.5

1.7 Combine Footing (CF3) 2


(BLL) 12 33 3.10 204.60 0.89 182.09 0.2 2.7 0.2

(BUL) 16 19 5.30 201.40 1.59 320.23 0.2 4.9 0.2

(TLL) 12 19 5.30 201.40 0.89 179.25 0.2 2.7 0.2

(TUL) 12 33 3.10 102.30 0.89 91.05 0.2 4.9 0.2

1.8 Stirrups 10 98 5.10 999.60 0.62 619.75 0.1


0.5
1.95

2 Column
2.1 Grid 1 (A ,B,E &F) 4
Main Bar 16 6 3.59 86.11 1.59 136.92 16mm
16 6 6.59 158.11 1.59 251.40 6.18 3.18 16mm

0.10 0.1
0.31 0.31
2.2 Grid 1 ( C ) 1
Main Bar 20 4 4.07 16.27 2.47 40.19
16 2 3.59 7.18 1.59 11.41 20mm 16mm
16 6 6.59 39.53 1.59 62.85 16mm 6.18
3.42 3.18

0.12 0.1 0.1


0.53 0.31 0.31

2.3 Grid 1 ( D ) 1
Main Bar 20 6 4.07 24.42 2.47 60.32
20 6 7.07 42.41 2.47 104.75 20mm 20mm
6.42 3.42

0.12 0.12

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
0.53 0.53

2.4 Grid 2(A,B,E & F) 4


Main Bar 20 4 4.07 65.12 2.47 160.85
16 2 3.59 28.72 1.59 45.66 16mm
16 6 6.59 158.16 1.59 251.47 20mm 16mm 6.18
3.42 3.18

0.12 0.10 0.1


0.53 0.53 0.53

2.5 Grid 2 ( C &D) 2


20 6 4.07 48.84 2.47 120.63
20 6 7.07 84.82 2.47 209.50 20mm 20mm
3.42 6.42

0.12 0.12
0.53 0.53
2.6 Grid 3 (A,B,C,D,E & F) 6
Main Bar 20 6 4.07 146.52 2.47 361.90
20 6 7.26 261.23 2.47 645.23 20mm 20mm
3.42 6.42

0.12 0.12
0.53 0.53

2.7 Stirrups 18
For 18 columns 8 12 1.84 397.44 0.40 158.98 0.08
8 24 1.28 552.96 0.40 221.18 0.42 0.14 0.08
0.42
0.42
3 For Lower Tie Beam
3.1 Grid 1,2 & 3 3 8.73
Top Bar 16 2 10.04 60.24 1.59 95.78 0.96
0.35
End bar from both
direction
16 2 11.46 68.76 1.59 109.33 11.46
8.73
16 2 10.04 60.24 1.59 95.78 0.96
0.35
2.94
Middle bar 16 1 4.25 12.75 1.59 20.27 0.96
0.35

16 1 12.00 36.00 1.59 57.24


12

16 1 12.00 36.00 1.59 57.24


12
2.94
16 1 4.25 12.75 1.59 20.27 0.96
0.35
Bottom Bar
End bar from both direction 16 2 3.33 19.98 1.59 31.77
0.66
1.71 0.96

16 2 9.00 54.00 1.59 85.86 9

16 2 11.46 68.76 1.59 109.33 0.96 10.5

16 2 9.33 55.98 1.59 89.01


0.66
0.96 7.1

Middle Bar 16 1 5.37 16.11 1.59 25.61


0.66
3.75 0.96

16 1 11.84 35.51 1.59 56.45 11.835

16 1 10.55 31.64 1.59 50.30 9.585


0.96
0.66
16 1 5.37 16.11 1.59 25.61

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
0.96 3.75

3.2 Grid A,B,C, D,E & F 6


Top Bar 16 3 8.12 146.16 1.59 232.39 7.42
0.35 0.35

Bottom Bar 16 3 8.74 157.32 1.59 250.14


0.35 0.35
7.42

3.3 Stirrups (LTB)


1 8 1113 1.36 1513.68 0.40 605.47 0.8
0.35

0.25

4 Plinth tie beam


4.1 Grid 1,2 & 3 3 8.61 1.2
Top Bar 20 2 10.24 61.41 2.47 151.68
0.425
End bar from both
direction 20 2 11.70 70.20 2.47 173.39 11.7

8.61
20 2 10.24 61.41 2.47 151.68 1.2
0.425
2.94
Middle bar 16 1 4.33 12.98 1.59 20.63 0.96
0.425
16 1 12.00 36.00 1.59 57.24 12

16 1 12.00 36.00 1.59 57.24 12

2.94
16 1 4.33 12.98 1.59 20.63 0.96
0.425

Bottom Bar
End bar from both 20 2 11.65 69.90 2.47 172.65
0.94
direction 9.51 1.2

20 2 11.70 70.20 2.47 173.39 11.7

20 2 9.85 59.10 2.47 145.98


0.94
1.2 7.71

Middle Bar 16 1 9.33 27.99 1.59 44.50


0.66
7.71 0.96

16 1 11.46 34.38 1.59 54.66 11.46

0.66
16 1 11.37 34.11 1.59 54.23 0.96 9.75

4.2 Grid A,B,C,D,E & F 6


Top bar 20 2 11.17 134.04 2.47 331.08
9.92
0.625 0.625

16 1 11.17 67.02 1.59 106.56 9.92


0.625 0.625

Bottom bar 20 2 11.80 141.60 2.47 349.75


0.94 0.94
9.92

16 1 11.24 67.44 1.59 107.23


0.66 0.66
9.92

4.3 Stirrups 1 12 126 1.54 194.04 0.89 172.70 0.12 0.1


10 1113 1.50 1669.50 0.62 1035.09 0.4 0.4

0.25 0.25
5 Column ( Up To 1st Floor Level)
5.1 Grid 1 (A ,B,E & F) 4

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
Main Bar 16 6 6.96 167.04 1.59 265.59 16mm
6

0.96

5.2 Grid 1 ( C ) 1
Main Bar 20 4 7.20 28.80 2.47 71.14
16 2 6.96 13.92 1.59 22.13 20mm 16mm

0.12 0.96

5.3 Grid 1 ( D ) 1
Main Bar 20 6 7.20 43.20 2.47 106.70
6 20mm
2.47

1.2

5.4 Grid 2(A,B,E & F) 4


Main Bar 20 4 7.20 115.20 2.47 284.54
16 2 6.96 55.68 1.59 88.53 6 6.00 16mm
20mm

1.20 0.96

5.5 Grid 2 ( C &D) 2


20 6 7.20 86.40 2.47 213.41
20mm
6

1.2

5.6 Grid 3 (A,B,C,D,E & F) 6


Main Bar 20 6 7.20 259.20 2.47 640.22
20mm
6

1.20

5.7 Stirrups 18
For 18 columns 8 31 1.84 1026.72 0.40 410.69 0.08
8 62 1.28 1428.48 0.40 571.39 0.42 0.14 0.08
1.59 0.42
0.42
6 For Staircase
(Plinth level to 1st floor level)
1.703
Main Bar (top bar) 1 16 21 8.23 172.81 1.59 274.77 0.3

3.354
2.472
0.4

Bottom Bar 1 16 21 3.27 68.71 1.59 109.25

2.042 1.03
0.2

1
Extra Bar 1 16 21 2.00 42.00 1.59 66.78
1

1.853
Landing bottom bar 1 16 21 3.00 63.06 1.59 100.27 1 0.15

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

1.2
Landing Extra bar 1 16 21 2.20 46.20 1.59 73.46 1

Distribution Bar 1 10 23 4.16 95.68 0.62 59.32 4.16

Bar in middle of landing 1 16 4 1.84 7.34 1.59 11.67 1.8


(20cm gap)
1 10 65 1.96 127.40 0.62 78.99 1.96

Top Bar 1 16 21 8.13 170.81 1.59 271.59


1.54
0.4
3.397
2.497
0.3
Bottom Bar 1 16 21 3.30 69.24 1.59 110.09

1
2.147 0.15

1
Extra Bar 1 16 21 2.20 46.20 1.59 73.46 1.2

1.82
Bottom bar( Slab level) 1 16 21 3.02 63.42 1.59 100.84 0.2 1

Extra Bar 1 16 21 2.00 42.00 1.59 66.78 1


1

Distribution Bar 1 10 100 1.96 196.00 0.62 121.52 1.96

1 10 42 4.16 174.72 0.62 108.33 4.16


0.15 0.565 0.15
Nosing Ties(Plinth Level To 0.112 0.162 0.112
First Floor Level ) 0.15 0.15
First type 8 35 0.674 23.59 0.40 9.44 0.565 0.15
Second type 8 7 0.977 6.84 0.40 2.74 0.412
Third type 8 14 1.13 15.86 0.40 6.34 0.268 0.112
Forth type 8 7 0.83 5.81 0.40 2.32 0.15
Fifth type 8 7 0.674 4.72 0.40 1.89 0.268 0.15 0.15
0.262
0.15
Nosing Bar 2 10 10 1.96 39.20 0.62 24.30 1.96

4.92
6.1 Landing Beam 1 20 3 5.62 16.86 2.47 41.64 0.35 0.35

1 20 3 5.62 16.86 2.47 41.64 0.35 0.35


4.92
6.2 Sturriups 1 8 35 1.22 42.70 0.40 17.08
0.08
0.375

7 Main Beam (First Floor Level) 0.2

7.1 Grid A,B,C,D,E & F


Bottom bar (End Bar) 6 25 2 7.25 87.00 2.47 214.89 1.29

4.46 1.5

1.29
6 25 2 6.75 81.00 3.86 312.66 5.46

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

Bottom Bar (mid-bars) 6 20 2 11.80 141.60 2.47 349.75


0.94
0.94
9.92

Top Bar 6 20 3 11.80 212.40 2.47 524.63 9.92


0.94
0.94

Extra Bar 6 25 2 6.50 78.00 3.86 301.08 5.06 0.15


1.29

6 25 2 4.00 48.00 3.86 185.28 2.56 0.15


1.29

Torsion Bars (T/O) 6 16 2 9.80 117.60 1.59 186.98 9.8

7.2 Grid 1
0.94
Bottom Bar (end bar) 1 20 2 5.65 11.30 2.47 27.91 1.2
3.51

20 2 11.40 22.80 2.47 56.32 10.2 1.2

20 2 7.50 15.00 2.47 37.05 7.5

0.94
20 2 9.85 19.70 2.47 48.66
1.2 7.71

Middle Bar 16 2 3.33 6.66 1.59 10.59


0.66
1.71 0.96
16 2 9.00 18.00 1.59 28.62
9

16 2 11.46 22.92 1.59 36.44 10.5


0.96

16 2 9.33 18.66 1.59 29.67


0.66
0.96 7.71

Top Bar (End Bar) 16 2 10.35 20.70 1.59 32.91 8.73 0.96
0.66

16 2 11.46 22.92 1.59 36.44 11.46

0.96 8.73
16 2 10.35 20.70 1.59 32.91
0.66
2.94 0.96
Middle Bar 16 1 4.56 4.56 1.59 7.25
0.66
16 1 12.00 12.00 1.59 19.08 12

0.96
16 1 12.00 12.00 1.59 19.08 11.04
0.66
16 1 4.56 4.56 1.59 7.25 2.94
0.96

7.3 Grid 2 & 3


Bottom Bar 2 20 4 5.65 22.60 2.47 55.82
0.94
3.51 1.2

20 4 11.40 45.60 2.47 112.63 10.2


1.2

20 4 7.50 30.00 2.47 74.10 7.5

0.94

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
0.94
20 4 9.85 39.40 2.47 97.32
1.2 7.71
0.94
Middle Bar 20 4 3.85 15.40 2.47 38.04
1.2 1.71
20 4 9.00 36.00 2.47 88.92
9

20 4 9.90 39.60 2.47 97.81 8.7


1.2
0.94
20 4 11.65 46.60 2.47 115.10
1.2 9.51
1.2
Top Bar 20 4 10.75 43.00 2.47 106.21 8.61
0.94

20 4 11.70 46.80 2.47 115.60 11.7

20 4 10.75 43.00 2.47 106.21 1.2 8.61


0.94
3.06
20 2 5.20 10.40 2.47 25.69 .1.2
0.94

20 2 12.00 24.00 2.47 59.28 10.8


1.2
20 2 12.00 24.00 2.47 59.28
12
1.2
20 2 5.20 10.40 2.47 25.69 3.06
0.94
2.21
7.4 Extra Bar Along Grid 1,2 &3 3 25 4 3.65 43.80 3.86 169.07 0.15
1.29
4
3 25 4 4.30 51.60 3.86 199.18 0.15 0.15

3.5
3 25 4 3.80 45.60 3.86 176.02 0.15 0.15

7.5 Torision bars along grid 1,2 &3


1st arrangement 3 16 1 3.69 11.07 1.59 17.60 3.69

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 4.11 12.33 1.59 19.60 4.11

2nd arrangement 3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 6.84 20.52 1.59 32.63 6.84

7.6 Secondry Beam


Along Grid A1,B1,D1 & E1
0.35 0.35
Bottom Bar 4 16 3 10.45 125.40 1.59 199.39
9.75

Top Bar 4 16 3 10.45 125.40 1.59 199.39 9.75


0.35 0.35

Grid 1a (end bottom bar) 2 16 2 2.94 11.74 1.59 18.67


0.35
1.625 0.96
0.35
2 16 2 10.85 43.40 1.59 69.01
10.5

middle bar 2 16 1 8.81 17.62 1.59 28.02


0.35
7.5 0.96

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

0.35
2 16 1 4.98 9.95 1.59 15.82
4.625
top bar (end bar) 2 16 2 4.06 16.22 1.59 25.79
2.645 0.96
0.45

2 16 2 10.55 42.20 1.59 67.10 9.605


0.45

middle bar 2 16 1 4.06 8.11 1.59 12.89 2.645 0.96


0.45

2 16 1 10.06 20.11 1.59 31.97 9.605


0.45
grid 1b
bottom bar 1 12 4 5.45 21.80 0.89 19.40 0.35
0.35
4.75

4.75
top bar 1 12 3 5.65 16.95 0.89 15.09 0.45 0.45

7.7 Conceal Beam 2 20 6 1.61 19.32 0.89 17.19 1.21


0.4

7.8 Bent up Bar (hunch bar) 1 16 36 3.02 108.72 1.59 172.86


0.96 0.425 0.425 0.96

250

7.9 Stirriups( For Main Beam) 1 10 1125 1.65 1856.25 0.62 1150.88 0.10
0.425

0.25
7.10 For Secondry Beam 1 8 540 1.31 707.40 0.40 282.96
0.8
0.375

0.2

8 For Slab (First Floor)


8.1 Main Bars 0.375
Along short span 0.07
straight bar 1 8 76 10.93 830.30 0.40 332.12 10.48
0.375 1.5 1.75 1.705
Cranked bar 1 8 76 11.09 842.46 0.40 336.98 0.05
1.975 1.75 1.75
0.525
Along Long Span (grid 1 to grid2)
Straight bar 1 8 45 12.00 540.00 0.40 216.00 11.475
1 8 45 2.22 99.90 0.40 39.96 1.695 0.525
0.525 1.5 1.9
cranked bar 1 8 44 11.03 485.10 0.40 194.04 0.07 1.5
2.25 0.525
1 8 44 4.75 208.78 0.40 83.51 1.9 0.07
2.25
along long span Grid 2 to 3 0.525
Straight bar 1 8 7 12.00 84.00 0.40 33.60 11.475

1 8 7 12.00 84.00 0.40 33.60 12


0.525
1 8 7 7.20 50.40 0.40 20.16 6.675
0.525 1.5 1.15
cranked bar 1 8 7 10.38 72.63 0.40 29.05 1.5 1.5
2.35 1.5
1.15 1.875 1.875 1.15
1 8 7 11.72 82.04 0.40 32.82 1.5 2.25
1.5
1.15 1.5 0.525
1 8 7 10.38 72.63 0.40 29.05 1.5 1.5 1.5
2.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

Infront of stair case


Straight bar 1 8 15 5.69 85.35 0.40 34.14 6.33
1.875 1.095 0.75
Cranked bar 1 8 13 5.97 77.61 0.40 31.04 1.125 0.845 0.07

8.2 Distribution bars


Between Grid 1 &1a
along x-axis 1 8 96 2.72 261.12 0.40 104.45 2.72
along y- axis 1 8 80 3.20 256.00 0.40 102.40 3.2

Between grid 1a & 2


along x axis 1 8 96 2.72 261.12 0.40 104.45 2.72
along y axis 1 8 84 3.20 268.80 0.40 107.52 3.2

Between grid 2 & 3


except infront of staircas 2.72
along x axis 1 8 64 2.72 174.08 0.40 69.63 2.2
along y axis 1 8 88 2.20 193.60 0.40 77.44
Between grid 1b & 2 infront of
staicase
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 1.29 23.22 0.40 9.29 1.29

between 2 & 3
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 2.20 39.60 0.40 15.84 2.2

Cantilever Slab beyond grid 1


bottom bar 1 10 3 11.46 34.38 0.62 21.32 11.46
top bar 1 10 3 11.46 34.38 0.62 21.32 11.46

Cantilever slab at the front


top bar ( horizontal portion) 1 10 3 7.10 21.30 0.62 13.21 7.1
bottom bar 1 10 3 7.10 21.30 0.62 13.21 7.1

Vertical portion 1 10 4 7.86 31.44 0.62 19.49 7.86


1 10 4 7.86 31.44 0.62 19.49 7.86

8.3 Negative Bars


along Grid 1 2 8 35 2.05 143.50 0.40 57.40 2.05
along grid 1a 2 8 35 2.35 164.50 0.40 65.80 2.35
along grid 1b 1 8 7 1.08 7.56 0.40 3.02 1.08
along grid 2 (except infront of
stair case) 2 8 35 2.10 147.00 0.40 58.80 2.1
along grid 2 in front of
staircase 1 8 14 1.38 19.32 0.40 7.73 1.38
along grid a1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid b 1 8 28 2.10 58.80 0.40 23.52 2.1
along b1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid c&d 2 8 9 2.55 45.90 0.40 18.36 2.55
along grid d1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid e 1 8 28 2.10 58.80 0.40 23.52 2.1
along grid e1 1 8 28 2.05 57.40 0.40 22.96 2.05

9 Bands
Ground Floor
9.1 Sill Bands 0.75 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.464 0.075 5.5 0.075
1 10 2 4.50 9.00 0.62 5.58 4.5
0.75 0.75
1 10 2 5.65 11.30 0.62 7.006 0.075 4 0.075

Grid 2 4 10 2 1.81 14.48 0.62 8.9776 1.81

Grid A,,C,D,E&F 5 10 2 8.15 81.50 0.62 50.53 0.75 6.5 0.75


0.075 0.075
Partition wall in Laoratory 1 10 2 0.75 1.50 0.62 0.93 0.75
1 10 2 5.00 10.00 0.62 6.2 5

9.2 Lintel Band 0.75 5.5 0.75


Grid 1 4 10 2 7.15 57.20 0.62 35.464 0.075 0.075

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
Grid 2 4 10 2 1.81 14.48 0.62 8.9776 0.75 1.81 0.75
Grid A,C,D,E&F 5 10 2 8.15 81.50 0.62 50.53 0.075 6.5 0.075
Partition wall in Laoratory 1 10 2 6.75 13.50 0.62 8.37
6.75

9.3 Vertical Band 6 10 2 4.13 49.50 0.62 30.69 0.75 0.75


0.075 2.475 0.075
9.4 Sturriups 1 8 950 0.30 285.00 0.40 34.20 0.06 0.06
0.18
9.5 Laboratary In -Built Furniture
Type 1 1 8 5 3.25 16.25 0.40 6.50
Main Bar 1 8 2 2.60 5.20 0.40 2.08 0.06 3.15 0.06

0.7
0.95 0.95
Distribution Bar 1 8 63 0.82 51.66 0.40 20.66 0.06 0.7 0.06

1 8 18 0.18 3.24 0.40 1.30 0.06 0.06 0.06


Type 2
Main Bar 4 8 6 1.82 10.92 0.40 4.37 0.06 1.7 0.06

Distribution Bar 1 8 12 0.92 11.04 0.40 4.42 0.06 0.8 0.06

Type3
Main Bar 1 8 5 6.82 34.10 0.40 13.64 0.06 6.7 0.06

Distribution Bar 1 8 46 0.62 28.52 0.40 11.41 0.06 0.5 0.06

Type 4
Main Bar 1 8 5 0.45 2.25 0.40 0.90 0.06 0.45 0.06

1 8 5 3.15 15.75 0.40 6.30 0.06 3.1 0.06

1 8 5 4.23 21.13 0.40 8.45 0.06 4.225 0.06

Distribution Bar 1 8 55 0.57 31.35 0.40 12.54 0.06 0.45 0.06

Type 5
Main Bar 1 8 5 0.86 4.30 0.40 1.72 0.06 0.74 0.06

1 8 5 1.39 6.93 0.40 2.77 0.06 1.265 0.06

1 8 5 3.19 15.93 0.40 6.37 0.06 3.065 0.06

Distribution Bar 1 8 37 0.57 21.09 0.40 8.44 0.06 0.45 0.06


10 Column ( Up To 2nd Floor Level)

10.1 Grid 1 (A ,B,E & F) 4


Main Bar 16 6 6.96 167.04 1.59 265.59 16mm
6

0.96

10.2 Grid 1 ( C ) 1
Main Bar 20 4 7.20 28.80 2.47 71.14
16 2 6.96 13.92 1.59 22.13 20mm 16mm

0.12 0.96

10.3 Grid 1 ( D ) 1
Main Bar 20 6 7.20 43.20 2.47 106.70
6 20mm
2.47

1.2

10.4 Grid 2(A,B,E & F) 4


Main Bar 20 4 7.20 115.20 2.47 284.54
16 2 6.96 55.68 1.59 88.53 6 6.00 16mm

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
20mm

1.20 0.96

10.5 Grid 2 ( C &D) 2


20 6 7.20 86.40 2.47 213.41
20mm
6

1.2

10.6 Grid 3 (A,B,C,D,E & F) 6


Main Bar 20 6 7.20 259.20 2.47 640.22
20mm
6

1.20

10.7 Stirrups 18
For 18 columns 8 31 1.84 1026.72 0.40 410.69 0.08
8 62 1.28 1428.48 0.40 571.39 0.42 0.14 0.08
1.59 0.42
0.42

10.8 Band (First Floor)


Sill Bands 0.75 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.464 0.075 5.5 0.075
1 10 2 4.50 9.00 0.62 5.58 4.5
0.75 0.75
1 10 2 5.65 11.30 0.62 7.006 0.075 4 0.075

Grid 2 4 10 2 1.81 14.48 0.62 8.9776 1.81

Grid A,C,D,E&F 5 10 2 8.15 81.50 0.62 50.53 0.75 6.5 0.75


0.075 0.075
Partition wall in Library 1 10 2 0.75 1.50 0.62 0.93 0.75
1 10 2 5.00 10.00 0.62 6.2 5
Lintel Band 0.75 5.5 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.464 0.075 0.075
Grid 2 4 10 2 1.81 14.48 0.62 8.9776 0.75 1.81 0.75
Grid A,C,D,E&F 5 10 2 8.15 81.50 0.62 50.53 0.075 6.5 0.075
Partition wall in Library 1 10 2 6.75 13.50 0.62 8.37
6.75
Vertical Band 7 10 2 4.13 57.75 0.62 35.805 0.75 0.75
0.075 2.475 0.075

Sturriups 1 8 958 0.30 287.40 0.40 34.49 0.06 0.06


0.18

11 For Staircase
(1st Floor level to 2nd Floor Level)
1.703
Main Bar (top bar) 1 16 21 8.23 172.81 1.59 274.77 0.3

3.354
2.472
0.4

Bottom Bar 1 16 21 3.27 68.71 1.59 109.25

2.042 1.03
0.2

1
Extra Bar 1 16 21 2.00 42.00 1.59 66.78
1

1.853
Landing bottom bar 1 16 21 3.00 63.06 1.59 100.27 1 0.15

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

1.2
Landing Extra bar 1 16 21 2.20 46.20 1.59 73.46 1

Distribution Bar 1 10 23 4.16 95.68 0.62 59.32 4.16

Bar in middle of landing 1 16 4 1.84 7.34 1.59 11.67 1.8


(20cm gap)
1 10 65 1.96 127.40 0.62 78.99 1.96

Landing Level to First Floor level


Top Bar 1 16 21 8.13 170.81 1.59 271.59
1.54
0.4
3.397
2.497
0.3
Bottom Bar 1 16 21 3.30 69.24 1.59 110.09

1
2.147 0.15

1
Extra Bar 1 16 21 2.20 46.20 1.59 73.46 1.2

1.82
Bottom bar( Slab level) 1 16 21 3.02 63.42 1.59 100.84 0.2 1

Extra Bar 1 16 21 2.00 42.00 1.59 66.78 1


1

Distribution Bar 1 10 100 1.96 196.00 0.62 121.52 1.96

1 10 42 4.16 174.72 0.62 108.33 4.16


0.15 0.565 0.15
Nosing Ties(Plinth Level To 0.112 0.162 0.112
First Floor Level ) 0.15 0.15
First type 8 35 0.674 23.59 0.40 9.44 0.565 0.15
Second type 8 7 0.977 6.84 0.40 2.74 0.412
Third type 8 14 1.13 15.86 0.40 6.34 0.268 0.112
Forth type 8 7 0.83 5.81 0.40 2.32 0.15
Fifth type 8 7 0.674 4.72 0.40 1.89 0.268 0.15 0.15
0.262
0.15
Nosing Bar 2 10 10 1.96 39.20 0.62 24.30 1.96

11.1 Beam 4.92


Landing Beam 1 20 3 5.62 16.86 2.47 41.64 0.35 0.35

1 20 3 5.62 16.86 2.47 41.64 0.35 0.35


4.92
Sturriups 1 8 35 1.22 42.70 0.40 17.08
0.08
0.375

0.2
12 Main Beam(Second Floor Level)
12.1 Grid A,B,C,D,E & F
Bottom bar (End Bar) 6 25 2 7.25 87.00 2.47 214.89 1.29

4.46 1.5

1.29
6 25 2 6.75 81.00 3.86 312.66 5.46

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

Bottom Bar (mid-bars) 6 20 2 11.80 141.60 2.47 349.75


0.94
0.94
9.92

Top Bar 6 20 3 11.80 212.40 2.47 524.63 9.92


0.94
0.94

Extra Bar 6 25 2 6.50 78.00 3.86 301.08 5.06 0.15


1.29

6 25 2 4.00 48.00 3.86 185.28 2.56 0.15


1.29

Torsion Bars (T/O) 6 16 2 9.80 117.60 1.59 186.98 9.8

12.2 Grid 1
0.94
Bottom Bar (end bar) 1 20 2 5.65 11.30 2.47 27.91 1.2
3.51

20 2 11.40 22.80 2.47 56.32 10.2 1.2

20 2 7.50 15.00 2.47 37.05 7.5

0.94
20 2 9.85 19.70 2.47 48.66
1.2 7.71

Middle Bar 16 2 3.33 6.66 1.59 10.59


0.66
1.71 0.96
16 2 9.00 18.00 1.59 28.62
9

16 2 11.46 22.92 1.59 36.44 10.5


0.96

16 2 9.33 18.66 1.59 29.67


0.66
0.96 7.71

Top Bar (End Bar) 16 2 10.35 20.70 1.59 32.91 8.73 0.96
0.66

16 2 11.46 22.92 1.59 36.44 11.46

0.96 8.73
16 2 10.35 20.70 1.59 32.91
0.66
2.94 0.96
Middle Bar 16 1 4.56 4.56 1.59 7.25
0.66
16 1 12.00 12.00 1.59 19.08 12

0.96
16 1 12.00 12.00 1.59 19.08 11.04
0.66
16 1 4.56 4.56 1.59 7.25 2.94
0.96

12.3 Grid 2 & 3


Bottom Bar 2 20 4 5.65 22.60 2.47 55.82
0.94
3.51 1.2

20 4 11.40 45.60 2.47 112.63 10.2


1.2

20 4 7.50 30.00 2.47 74.10 7.5

0.94

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
0.94
20 4 9.85 39.40 2.47 97.32
1.2 7.71
0.94
Middle Bar 20 4 3.85 15.40 2.47 38.04
1.2 1.71
20 4 9.00 36.00 2.47 88.92
9

20 4 9.90 39.60 2.47 97.81 8.7


1.2
0.94
20 4 11.65 46.60 2.47 115.10
1.2 9.51
1.2
Top Bar 20 4 10.75 43.00 2.47 106.21 8.61
0.94

20 4 11.70 46.80 2.47 115.60 11.7

20 4 10.75 43.00 2.47 106.21 1.2 8.61


0.94
3.06
20 2 5.20 10.40 2.47 25.69 .1.2
0.94

20 2 12.00 24.00 2.47 59.28 10.8


1.2
20 2 12.00 24.00 2.47 59.28
12
1.2
20 2 5.20 10.40 2.47 25.69 3.06
0.94
2.21
12.4 Extra Bar Along Grid 1,2 &3 3 25 4 3.65 43.80 3.86 169.07 0.15
1.29
4
3 25 4 4.30 51.60 3.86 199.18 0.15 0.15

3.5
3 25 4 3.80 45.60 3.86 176.02 0.15 0.15

12.5 Torision bars along grid 1,2 &3


1st arrangement 3 16 1 3.69 11.07 1.59 17.60 3.69

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 4.11 12.33 1.59 19.60 4.11

2nd arrangement 3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 6.84 20.52 1.59 32.63 6.84

12.6 Secondry Beam


Along Grid A1,B1,D1 & E1
0.35 0.35
Bottom Bar 4 16 3 10.45 125.40 1.59 199.39
9.75

Top Bar 4 16 3 10.45 125.40 1.59 199.39 9.75


0.35 0.35

Grid 1a (end bottom bar) 2 16 2 2.94 11.74 1.59 18.67


0.35
1.625 0.96
0.35
2 16 2 10.85 43.40 1.59 69.01
10.5

middle bar 2 16 1 8.81 17.62 1.59 28.02


0.35
7.5 0.96

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

0.35
2 16 1 4.98 9.95 1.59 15.82
4.625
top bar (end bar) 2 16 2 4.06 16.22 1.59 25.79
2.645 0.96
0.45

2 16 2 10.55 42.20 1.59 67.10 9.605


0.45

middle bar 2 16 1 4.06 8.11 1.59 12.89 2.645 0.96


0.45

2 16 1 10.06 20.11 1.59 31.97 9.605


0.45
grid 1b
bottom bar 1 12 4 5.45 21.80 0.89 19.40 0.35
0.35
4.75

4.75
top bar 1 12 3 5.65 16.95 0.89 15.09 0.45 0.45

12.7 Bent up Bar (hunch bar) 1 16 36 3.02 108.72 1.59 172.86


0.96 0.425 0.425 0.96

250

12.8 Stirrups( For Main Beam) 1 10 1125 1.65 1856.25 0.62 1150.88 0.10
0.425

0.25
12.9 Stirrups ( For Secondry Beam) 1 8 540 1.31 707.40 0.40 282.96
0.8
0.375

0.2

13 For Slab (2nd Floor Level)


Main Bars 0.375
Along short span 0.07
straight bar 1 8 76 10.93 830.30 0.40 332.12 10.48
0.375 1.5 1.75 1.705
Cranked bar 1 8 76 11.09 842.46 0.40 336.98 0.05
1.975 1.75 1.75
0.525
Along Long Span (grid 1 to grid2)
Straight bar 1 8 45 12.00 540.00 0.40 216.00 11.475
1 8 45 2.22 99.90 0.40 39.96 1.695 0.525
0.525 1.5 1.9
cranked bar 1 8 44 11.03 485.10 0.40 194.04 0.07 1.5
2.25 0.525
1 8 44 4.75 208.78 0.40 83.51 1.9 0.07
2.25
along long span Grid 2 to 3 0.525
Straight bar 1 8 7 12.00 84.00 0.40 33.60 11.475

1 8 7 12.00 84.00 0.40 33.60 12


0.525
1 8 7 7.20 50.40 0.40 20.16 6.675
0.525 1.5 1.15
cranked bar 1 8 7 10.38 72.63 0.40 29.05 1.5 1.5
2.35 1.5
1.15 1.875 1.875 1.15
1 8 7 11.72 82.04 0.40 32.82 1.5 2.25
1.5
1.15 1.5 0.525
1 8 7 10.38 72.63 0.40 29.05 1.5 1.5 1.5
2.35

0.375
Infront of stair case
Straight bar 1 8 15 4.92 73.80 0.40 29.52 4.92

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
0.375 1.065 0.75
Cranked bar 1 8 13 5.12 66.56 0.40 26.62 1.875 0.845 0.07

Distribution bars
Between Grid 1 &1a
along x-axis 1 8 96 2.72 261.12 0.40 104.45 2.72
along y- axis 1 8 80 3.20 256.00 0.40 102.40 3.2

Between grid 1a & 2


along x axis 1 8 96 2.72 261.12 0.40 104.45 2.72
along y axis 1 8 84 3.20 268.80 0.40 107.52 3.2

Between grid 2 & 3


except infront of staircas 2.72
along x axis 1 8 64 2.72 174.08 0.40 69.63 2.2
along y axis 1 8 88 2.20 193.60 0.40 77.44
Between grid 1b & 2 infront of
staicase
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 1.29 23.22 0.40 9.29 1.29

between 2 & 3
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 2.20 39.60 0.40 15.84 2.2

Cantilever Slab beyond grid 1


bottom bar 1 10 3 11.46 34.38 0.62 21.32 11.46
top bar 1 10 3 11.46 34.38 0.62 21.32 11.46

Negative Bars
along Grid 1 2 8 35 2.05 143.50 0.40 57.40 2.05
along grid 1a 2 8 35 2.35 164.50 0.40 65.80 2.35
along grid 1b 1 8 7 1.08 7.56 0.40 3.02 1.08
along grid 2 (except infront of
stair case) 2 8 35 2.10 147.00 0.40 58.80 2.1
along grid 2 in front of
staircase 1 8 14 1.38 19.32 0.40 7.73 1.38
along grid a1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid b 1 8 28 2.10 58.80 0.40 23.52 2.1
along b1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid c&d 2 8 9 2.55 45.90 0.40 18.36 2.55
along grid d1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid e 1 8 28 2.10 58.80 0.40 23.52 2.1
along grid e1 1 8 28 2.05 57.40 0.40 22.96 2.05

14 Column ( Up to 3rd Floor Level)


14.1 Grid 1 (A ,B,E & F) 4
Main Bar 16 6 3.34 80.19 1.59 127.50 16mm
2.38

0.96

14.2 Grid 1 (C ) 1 16 6 5.97 35.82 1.59 56.95


5.00625 16mm

0.96

14.3 Grid 1 ( D ) 1
Main Bar 20 2 6.21 12.41 2.47 30.66
16 4 5.97 23.87 1.59 37.95 6 20mm 16mm
5.00625 5.00625

1.2 0.96

14.4 Grid 2(A,B,E & F) 4


Main bar 16 6 3.34 80.16 1.59 127.45 16mm
2.38

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

0.96

14.5 Grid 2 ( C &D) 2


20 2 6.21 24.83 2.47 61.32
16 4 5.97 47.73 1.59 75.89 20mm 5.00625 16mm
5.00625

1.2 0.96

14.6 Grid 3 (A,B,C,D,E & F) 6


Main Bar 20 2 3.58 42.98 2.47 106.15
16 4 3.34 80.16 1.59 127.45 2.38 20mm 2.38
16mm

1.20 0.96

14.7 Stirrups 18
For 18 columns 8 31 1.84 1026.72 0.40 410.69 0.08
8 62 1.28 1428.48 0.40 571.39 0.42 0.14 0.08
0.42
0.42
14.8 Band (Second Floor)
Sill Bands 0.75 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.464 0.075 5.5 0.075
1 10 2 4.50 9.00 0.62 5.58 4.5
0.75 0.75
1 10 2 5.65 11.30 0.62 7.006 0.075 4 0.075

Grid 2 4 10 2 1.81 14.48 0.62 8.9776 1.81


Partition wall between principal 1 10 2 4.50 9.00 0.62 5.58 4.5
and administration
Grid A,B,C,D,E&F 6 10 2 8.15 97.80 0.62 60.636 0.75 6.5 0.75
0.075 0.075
Lintel Band 0.75 5.5 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.464 0.075 0.075
Grid 2 4 10 2 1.81 14.48 0.62 8.9776 0.75 1.81 0.75
Partition wall between principal 1 10 2 4.50 9.00 0.62 5.58 4.5
and administration
Wall in computer Lab 2 10 2 3.60 14.40 0.62 8.928 3.6

Grid A,B,C,D,E&F 5 10 2 8.15 81.50 0.62 50.53 0.075 6.5 0.075


Vertical Band 8 10 2 4.13 66.00 0.62 40.92 0.75 0.75
0.075 2.475 0.075

Sturriups 1 8 1128 0.30 338.40 0.40 40.61 0.06 0.06


0.18

15 For Staircase
(2nd Floor to Top Foor)
1.703
Main Bar (top bar) 1 16 21 8.23 172.81 1.59 274.77 0.3

3.354
2.472
0.4

Bottom Bar 1 16 21 3.27 68.71 1.59 109.25

2.042 1.03
0.2

1
Extra Bar 1 16 21 2.00 42.00 1.59 66.78
1

1.853
Landing bottom bar 1 16 21 3.00 63.06 1.59 100.27 1 0.15

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

1.2
Landing Extra bar 1 16 21 2.20 46.20 1.59 73.46 1

Distribution Bar 1 10 23 4.16 95.68 0.62 59.32 4.16

Bar in middle of landing 1 16 4 1.84 7.34 1.59 11.67 1.8


(20cm gap)
1 10 65 1.96 127.40 0.62 78.99 1.96

Landing Level to +9000 level


Top Bar 1 16 21 8.13 170.81 1.59 271.59
1.54
0.4
3.397
2.497
0.3
Bottom Bar 1 16 21 3.30 69.24 1.59 110.09

1
2.147 0.15

1
Extra Bar 1 16 21 2.20 46.20 1.59 73.46 1.2

1.82
Bottom bar( Slab level) 1 16 21 3.02 63.42 1.59 100.84 0.2 1

Extra Bar 1 16 21 2.00 42.00 1.59 66.78 1


1

Distribution Bar 1 10 100 1.96 196.00 0.62 121.52 1.96

1 10 42 4.16 174.72 0.62 108.33 4.16


0.15 0.565 0.15
Nosing Ties(Plinth Level To 0.112 0.162 0.112
First Floor Level ) 0.15 0.15
First type 8 35 0.674 23.59 0.40 9.44 0.565 0.15
Second type 8 7 0.977 6.84 0.40 2.74 0.412
Third type 8 14 1.13 15.86 0.40 6.34 0.268 0.112
Forth type 8 7 0.83 5.81 0.40 2.32 0.15
Fifth type 8 7 0.674 4.72 0.40 1.89 0.268 0.15 0.15
0.262
0.15
Nosing Bar 2 10 10 1.96 39.20 0.62 24.30 1.96

4.92
15.1 Landing Beam 1 20 3 5.62 16.86 2.47 41.64 0.35 0.35

1 20 3 5.62 16.86 2.47 41.64 0.35 0.35


4.92
15.2 Sturriups 1 8 35 1.22 42.70 0.40 17.08
0.08
0.375

0.2
16 Main Beam (Top Floor Level))
16.1 Grid A,B,E & F
Bottom bar (mid bar) 4 20 2 10.87 86.96 2.47 214.79 0.475 0.475

9.92

0.475
0.475
End Bar 4 25 2 10.87 86.96 3.86 335.67 9.92

Bottom bar along C & D 2 25 2 7.25 29.00 3.86 111.94


1.29

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
1.29
4.46 1.5

2 20 2 6.75 27.00 3.86 104.22


5.46 1.29

0.94 0.94
Bottom Bar along C & D 2 20 2 11.80 47.20 2.47 116.58 0.92

6 20 3 11.80 212.40 2.47 524.63 0.94 9.92 0.94

16.2 Extra Bar 6 25 2 6.50 78.00 3.86 301.08 5.06 0.15


1.29

6 25 2 4.00 48.00 3.86 185.28 2.56 0.15


1.29

16.3 Torsion Bars (T/O) 6 16 2 9.80 117.60 1.59 186.98 9.8

16.4 Grid 1
0.475
Bottom Bar (end bar) 1 20 2 3.39 6.77 2.47 16.72 1.2
1.71

20 2 9.00 18.00 2.47 44.46 9

20 2 11.70 23.40 2.47 57.80 1.2 10.5

0.475
20 2 9.39 18.77 2.47 46.36
1.2 7.71

Middle Bar 16 2 3.15 6.29 1.59 10.00


0.475
1.71 0.96
16 2 9.00 18.00 1.59 28.62
9

16 2 11.46 22.92 1.59 36.44 10.5


0.96

16 2 9.15 18.29 1.59 29.08


0.475
0.96 7.71

Top Bar (End Bar) 16 2 10.35 20.70 1.59 32.91 8.73 0.96
0.66

16 2 11.46 22.92 1.59 36.44 11.46

0.96 8.73
16 2 10.35 20.70 1.59 32.91
0.66
2.94 0.96
Middle Bar 16 1 4.56 4.56 1.59 7.25
0.66
16 1 12.00 12.00 1.59 19.08 12

0.96
16 1 12.00 12.00 1.59 19.08 11.04
0.66
16 1 4.56 4.56 1.59 7.25 2.94
0.96

16.5 Extra Bar Along Grid 1 1 25 4 3.65 14.60 3.86 56.36 0.15
1.29
4
1 25 4 4.30 17.20 3.86 66.39 0.15 0.15

3.5

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
1 25 4 3.80 15.20 3.86 58.67 0.15 0.15

16.6 Grid 2 & 3


Bottom Bar 2 20 4 3.39 27.08 2.47 66.89
0.475
1.71 1.2

20 4 9.00 72.00 2.47 177.84 9

20 4 11.70 93.60 2.47 231.19 1.2 10.5

0.475
20 4 9.39 75.08 2.47 185.45
1.2 7.71
0.94
1.2
Top Bar (end Bar) 20 4 10.75 43.00 2.47 106.21 8.61
0.94

20 4 11.70 46.80 2.47 115.60 11.7

20 4 10.75 43.00 2.47 106.21 1.2 8.61


0.94
3.06
middle bar 20 2 5.20 10.40 2.47 25.69 .1.2
0.94

20 2 12.00 24.00 2.47 59.28 10.8


1.2
20 2 12.00 24.00 2.47 59.28
12
1.2
20 2 5.20 10.40 2.47 25.69 3.06
0.94
2.21
16.7 Extra Bar Along Grid 1,2 &3 2 20 4 3.65 29.20 2.47 72.12 0.15
1.29
4
2 20 4 4.30 34.40 2.47 84.97 0.15 0.15

3.5
2 20 4 3.80 30.40 2.47 75.09 0.15 0.15

16.8 Torision bars along grid 1,2 &3


1st arrangement 3 16 1 3.69 11.07 1.59 17.60 3.69

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 4.11 12.33 1.59 19.60 4.11

2nd arrangement 3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 6.84 20.52 1.59 32.63 6.84

16.9 Secondry Beam


Along Grid A1,B1,D1 & E1
0.35 0.35
Bottom Bar 4 16 3 10.45 125.40 1.59 199.39
9.75

Top Bar 4 16 3 10.45 125.40 1.59 199.39 9.75


0.35 0.35

Grid 1a (end bottom bar) 2 16 2 2.94 11.74 1.59 18.67


0.35
1.625 0.96
0.35
2 16 2 10.85 43.40 1.59 69.01
10.5

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

middle bar 2 16 1 8.81 17.62 1.59 28.02


0.35
7.5 0.96
0.35
2 16 1 4.98 9.95 1.59 15.82
4.625
top bar (end bar) 2 16 2 4.06 16.22 1.59 25.79
2.645 0.96
0.45

2 16 2 10.55 42.20 1.59 67.10 9.605


0.45

middle bar 2 16 1 4.06 8.11 1.59 12.89 2.645 0.96


0.45

2 16 1 10.06 20.11 1.59 31.97 9.605


0.45
grid 1b
bottom bar 1 12 4 5.45 21.80 0.89 19.40 0.35
0.35
4.75

4.75
top bar 1 12 3 5.65 16.95 0.89 15.09 0.45 0.45

16.10 Bent up Bar (hunch bar) 1 16 36 3.02 108.72 1.59 172.86 0.96 0.96

0.425 0.425
0.25

16.11 Stirriups( For Main Beam) 1 10 1125 1.65 1856.25 0.62 1150.88 0.10
0.425

0.25
16.12 For Secondry Beam 1 8 540 1.31 707.40 0.40 282.96
0.8
0.375

0.2

16.13 Beam under slab (250*150) 7.195


Near grid 1 2 12 4 9.09 72.68 0.89 64.69
1.89

7.215
2 12 4 8.41 67.28 0.89 59.88
1.64

7.195
2 12 4 9.09 72.68 0.89 64.69 1.89

6.325
2 12 4 7.97 63.72 0.89 56.71
1.64
10.15
Infront of Grid A & F 2 12 4 10.15 81.20 0.89 72.27

2 12 4 9.90 79.20 0.89 70.49 9.9

Infront of Grid 3 2 12 4 7.53 60.24 0.89 53.61 0.89

6.64
2 12 2 8.17 32.68 0.89 29.09 0.89
7.28

2 12 4 7.14 57.12 0.89 50.84 5.75


0.5
0.89

2 12 2 6.50 13.00 0.89 11.57 6.5

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)

2 12 2 6.00 12.00 0.89 10.68 6

16.14 Stirriups( beam 250*150 ) 1 8 546 0.76 414.96 0.40 165.98 0.0 0.1
8
0.2

17 For Slab (Top Floor)


17.1 Main Bars
Along short span
straight bar 1 8 76 12.00 912.00 0.40 364.80 12

2.025 1.5 1.75


Cranked bar 1 8 76 11.66 886.16 0.40 354.46 0.08 0.08 0.08 0.08 0.08
1.25 1.075 1.75
0.08 0.08
1.75 1.45
1 8 76 1.45 110.20 0.40 44.08 0.08

17.2 Along Long Span (grid 1 to grid2) 0.525


Straight bar 1 8 37 9.96 368.34 0.40 147.33 0.08 9.35

1 8 37 4.53 167.61 0.40 67.04 4.45 0.08

0.525 0.95
cranked bar 1 8 36 4.04 145.26 0.40 58.10 0.08 0.08
2.4

0.95 1.5 1.5


1 8 36 4.75 170.82 0.40 68.33 0.08 1.5 0.08 0.08 0.08
1.5
0.08 0.08 2 0.08
1.5
17.3 along long span Grid 2 to 3
Straight bar 1 8 26 10.45 271.70 0.40 108.68 0.08 10.45

1 8 26 10.90 283.40 0.40 113.36 10.9


0.08
1 8 26 10.45 271.70 0.40 108.68 10.45

2 1.5 1.5
cranked bar 1 8 24 11.01 264.24 0.40 105.70 0.08 0.08 0.08 0.08 0.08
1.5 1.5
0.08 0.08 0.95
1.5
0.95 1.875 1.875
1 8 24 11.38 273.12 0.40 109.25 0.08 0.08 0.08 2.25 0.08
1.5
0.08 0.08 0.95
1.5
0.95 1.5 1.5
1 8 24 11.01 264.24 0.40 105.70 0.08 0.08 0.08 1.5 0.08
1.5 2
0.08 1.5 0.08 0.08

17.4 Infront of stair case 0.08 6.11 0.08


Straight bar 1 8 15 6.27 94.05 0.40 37.62
2.405 1.095 0.91
Cranked bar 1 8 13 6.69 86.91 0.40 34.76 0.08 0.08 0.08 0.08 0.08
1.1 0.695
17.5 Distribution bars
Between Grid 1 &1a
along x-axis 1 8 80 2.70 216.00 0.40 86.40 2.7
along y- axis 1 8 74 3.20 236.80 0.40 94.72 3.2

Between grid 1a & 2


along x axis 1 8 80 2.70 216.00 0.40 86.40 2.7
along y axis 1 8 80 3.20 256.00 0.40 102.40 3.2

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
Between grid 2 & 3
except infront of staircas 2.7
along x axis 1 8 64 2.70 172.80 0.40 69.12 2.2
along y axis 1 8 68 2.20 149.60 0.40 59.84
Between grid 1b & 2 infront of
staicase
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 1.28 23.04 0.40 9.22 1.29

between 2 & 3
along x axis 1 8 8 4.20 33.60 0.40 13.44 4.2
along y axis 1 8 18 2.20 39.60 0.40 15.84 2.2

Top near Grid 1( in bottom) 2 10 5 12.00 120.00 0.62 74.40 12


2 10 5 2.20 22.00 0.62 13.64 2.2

Top near Grid 1( on Top) 2 10 4 12.00 96.00 0.62 59.52 12


2 10 4 2.20 17.60 0.62 10.91 2.2

Top near grid A & F (in bottom) 2 10 5 12.00 120.00 0.62 74.40 12
Top near grid A & F (on top) 2 10 4 12.00 96.00 0.62 59.52 12

Top infront of grid 3 (in bottom) 2 10 5 11.98 119.80 0.62 74.28 11.98
Top infront of grid 3 (on top) 2 10 4 11.98 95.84 0.62 59.42 11.98

Top infront of staircase (in bottom) 1 10 6 8.24 49.44 0.62 30.65 8.24
1 10 5 8.24 41.20 0.62 25.54 8.24

17.6 Negative Bars


along Grid 1 2 8 36 2.43 174.96 0.40 69.98 2.43
along grid 1a 2 8 36 2.35 169.20 0.40 67.68 2.35
along grid 1b 1 8 14 1.08 15.12 0.40 6.05 1.08
along grid 2 (except infront of
stair case) 2 8 36 2.10 151.20 0.40 60.48 2.1
along grid 2 in front of
staircase 1 8 14 1.37 19.18 0.40 7.67 1.38
Along grid 3 (except infront of
stair case) 1 8 72 2.13 153.36 0.40 61.34 2.13
Along grid 3 ( infront of
stair case) 1 8 14 2.53 35.42 0.40 14.17 2.53

Along grid A & F 2 8 28 2.28 127.68 0.40 51.07 2.28


along grid a1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid b 1 8 28 2.10 58.80 0.40 23.52 2.1
along b1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid c&d 2 8 10 2.55 51.00 0.40 20.40 2.55
along grid d1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid e 1 8 28 2.10 58.80 0.40 23.52 2.1
along grid e1 1 8 28 2.05 57.40 0.40 22.96 2.05

Band Parapet Wall Top Floor 7.195


Near grid 1 2 10 2 9.09 36.34 0.62 22.53
1.89

7.215
2 10 2 8.41 33.64 0.62 20.86
1.64

7.195
2 10 2 9.09 36.34 0.62 22.53 1.89

6.325
2 10 2 7.97 31.86 0.62 19.75
1.64
10.15
Infront of Grid A & F 2 10 2 10.15 40.60 0.62 25.17

2 10 2 9.90 39.60 0.62 24.55 9.9

Infront of Grid 3 2 10 2 7.53 30.12 0.62 18.67 0.89

6.64

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
2 10 2 8.17 32.68 0.62 20.26 0.89
7.28

2 10 2 7.14 28.56 0.62 17.71 5.75


0.5
0.89

2 10 2 6.50 13.00 0.62 8.06 6.5

2 10 2 6.00 12.00 0.62 7.44 6

Stirrups 2 8 540 0.30 162.00 0.40 64.80 0.06 0.06


0.18

18 Column ( Up to Roof Floor Level)


18.1 Grid 1 C 1
Main Bar 16 6 2.96 17.76 1.59 28.24 16mm
2.00

0.96

18.2 Grid 1 ( D ) 1
Main Bar 20 2 3.20 6.40 2.47 15.81
16 4 2.96 11.84 1.59 18.83 20mm 16mm
2 2

1.2 0.96

18.3 Grid 2 & 3 ( C &D) 4


20 2 3.20 25.60 2.47 63.23
16 4 2.96 47.36 1.59 75.30 2 20mm 2 16mm

1.2 0.96

18.4 Stirrups 6
For 6 columns 8 26 1.84 287.04 0.40 114.82 0.08
8 52 1.28 399.36 0.40 159.74 0.42 0.14 0.08
0.42
0.42
18.5 Band under wall (Grid C&D) 2 10 2 6.50 26.00 0.62 16.12 6.5
1 10 2 4.50 9.00 0.62 5.58 4.5
0.06 0.06
1 8 30 0.30 9.00 0.40 3.60 0.18
Stirrups 2 8 44 0.30 13.20 0.40 5.28 0.06 0.06
19 Slab Beam 0.18
19.1 Grid C & D
Bottom bar 2 20 2 10.87 43.48 2.47 107.40 0.475 0.475

9.92

0.475
0.475
2 16 1 10.87 21.74 1.59 34.57 9.92

Top Bar 2 20 2 11.80 47.20 2.47 116.58 0.94 9.92 0.94

2 16 1 11.24 22.48 1.59 35.74 0.66 9.92 0.66

19.2 Grid 1,2& 3 bottom bar


3 20 2 5.82 34.92 2.47 86.25 0.45 0.45
4.92

3 16 1 5.82 17.46 1.59 27.76 0.45 0.45

4.92
Top Bar

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
3 20 2 6.80 40.80 2.47 100.78 0.94 4.92 0.94

3 16 1 6.24 18.72 1.59 29.76 0.66 4.92 0.66

19.3 Secondry beam


Bottom bar along grid 1a 1 16 3 5.45 16.35 1.59 26.00 0.35 0.35
4.75

Top bar along grid 1a 1 16 3 5.65 16.95 1.59 26.95 0.35 4.75 0.45

19.4 Stirriups( For Main Beam) 1 10 180 1.65 297.00 0.62 184.14 0.10
0.425

0.25
19.5 For Secondry Beam 1 8 35 1.31 45.85 0.40 18.34
0.8
0.375

0.2

20 For Slab (Roof Floor)


20.1 Main Bars
Along long span
straight bar 1 8 14 11.62 162.68 0.40 65.07 0.08 11.46 0.08

1.605 1.5 1.75


Cranked bar 1 8 13 11.94 155.22 0.40 62.09 0.08 0.08 0.08 0.08
1.25 1.855 1.75
0.08 0.08
1.75
Along Short Span
straight bar 1 8 29 6.62 191.98 0.40 76.79 0.08 6.46 0.08

2.105 2.105
Cranked bar 1 8 28 6.48 181.44 0.40 72.58 0.08 0.08 0.08 0.08
1.95

20.2 Distribution bars


Between Grid 1 &1a
along x-axis 1 8 12 4.20 50.40 0.40 20.16 4.2
along y- axis 1 8 18 3.23 58.05 0.40 23.22 3.23

Between Grid 1a & 2


along x-axis 1 8 12 4.20 50.40 0.40 20.16 4.2
along y- axis 1 8 18 3.23 58.14 0.40 23.26 3.23

Between Grid 2 & 3


along x-axis 1 8 8 4.20 33.60 0.40 13.44 4.2
along y- axis 1 8 18 2.20 39.60 0.40 15.84 2.2

Top near grid 1 &3


bottom bar 2 8 5 6.46 64.60 0.40 25.84 6.46

Top Bar 2 8 4 6.46 51.68 0.40 20.67 6.46

Top in front of grid C & D


bottom bar 2 8 5 11.46 114.60 0.40 45.84 11.46

Top Bar 2 8 4 11.46 91.68 0.40 36.67 11.46

20.3 Negative Bars


along Grid 1 1 8 13 2.08 27.04 0.40 10.82 2.08
along grid 1a 1 8 13 2.35 30.55 0.40 12.22 2.35
along grid 2 1 8 13 2.10 27.30 0.40 10.92 2.1
along Grid 3 1 8 13 1.78 23.14 0.40 9.26 1.78
along grid C & D 2 8 26 2.48 128.96 0.40 51.58 2.48

21 Band (Roof Floor ) 5.95


Parapet Wall 2 10 2 7.15 28.6 0.62 17.732 0.6 0.6
2 10 2 11.95 47.8 0.62 29.636

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-LaliEACCr(F)-A
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Dia. of Cut
No. of Total Wt/m Weight
S. No. Description No. Bar Length Bar Shape
Bars Length (m) (Kg) (Kg)
(mm) (m)
11.95
Stirrups 2 8 238 0.30 71.40 0.40 28.56 0.06 0.06
Total 58147.14 kgs 0.18
58.15 MT

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: 3LaLiEACCr(F)-A
School Name : Shree Dharmawati Secondary School
Location : Choprak,Gorkha

Site
S. No. Description G.F F.F S.F TF Quantity Unit Remarks
Development
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure 1 1.00 nos.
2 CABLES & WIRES
2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded
2.1 49.00 r.m
copper conductor wires

2.2 2 Nos 2.5 Sq.mm mutistranded copper conductor 50.00 r.m


wires + 1 Nos. 1.5sq mm multistranded Cu wire
B School Blocks
1 DISTRIBUTION BOARDS 1 1 1 3.00 nos.
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4
2.1 11.00 r.m
Sq mm Multistranded Cu wire
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5
2.2 8.00 r.m
Sq mm Multistranded Cu wire
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No
2.3 14.00 r.m
1.5 Sq mm Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point 3 23 22 22 2 72.00 pts.
3.2 Two Way Light Point 1 1 2.00 pts.
3.3 Ceiling/Exhaust Fan Point wiring 0.00 pts.
4 6A Universal Pin Light Power Socket Wiring 22 20 55 97.00 pts.
5 Switch Socket Outlets
5.1 6A Universal Power Switch Socket 22 20 55 97.00 nos.
6 SweepCeiling/Exhaust Fan
6.1 400mm Wall Fan 12 12 18 42.00 nos.
7 Light Fixtures/Luminaires & Accessories
7.1 24 W LED Surface Mounted Square type 6.00 6.00 12.00 no.
7.2 18 W LED Surface Mounted Square type 8.00 8.00 16.00 32.00 no.
7.3 12 W LED Surface Mounted Cylindrical type 8.00 9.00 7.00 3.00 27.00 no.
7.4 LED Wall Light 1.00 1.00 no.
8 Pull Box
Junction Box At External Post Top Light 3 3.00 nos.
9 External Post Top Light Pole 3 3.00 nos.
10 Post Top External Light Fixtures 3 3.00 nos.
11 Earthing & Lighting Protection
11.1 Chemical Earthing 3 3.00 no.
11.2 Earthing Bar 3 3.00 no.
12 Earthing Strip/Wires
12.3.1 25 x 3 mm GI strip 65 65.00 r.m
12.3.2 12 SWG Cu wire 15 15.00 r.m
13 Earth Test link 1 1.00 nos.
14 Lightning Arrester 1 1.00 nos.
C Solar PV System
1 Solar PV Panel 8 8.00 nos.
2 Tubular Deep Cycle Battery 4 4.00 nos.
3 Hybrid Inverter 1 1.00 no.
D Fire Extinguisher
5.0kg Size ABC Stored Pressure Type Fire
A. 1 5 6.00 nos.
Extinguisher
B. Dry Powder Fire Extinguisher 1 1.00 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
School Name : Shree Dharmawati Secondary School
Location : Choprak,Gorkha

Building: 3LaLiEACCr(F)-A
S.N Furniture Description Symbol Qty Unit Remarks
Classroom
1 ECD Student Desk (6 Seater) D-03 3 nos.
2 Student Desk G1-2 (3 Seater) D-02A 22 nos.
3 Student Bench G1-2 (3 Seater) B-02A 22 nos.
4 Student Desk G3-5 (3 Seater) D-02B 11 nos.
5 Student Bench G3-5 (3 Seater) B-02B 11 nos.
6 Teacher's Table T-01 6 nos.
7 Soft Board F-01 1 nos.
8 Book Shelf F-02 3 nos.
9 Teacher's Chair C-01 6 nos.
10 White Board F-03 6 nos.
Library
11 Student Bench 6-12 (3 Seater) B-02C 14 nos.
12 Library Table T-02 7 nos.
13 Library Shelf F-04 5 nos.
Computer nos.
14 Computer Table T-04 12 nos.
15 Computer Shelf C-02 24 nos.
16 White Board with Stand F-05 1 nos.
Laboratory
17 Equipment Shelf F-07 3
18 Lab Stool F-08 31
Office
19 Cabinet F-06 7 nos.
20 Office Table (2 sides Drawe Unit) T-05 1 nos.
21 Office Table (1 sides Drawe Unit) T-06 2 nos.
22 Office Table T-07 12 nos.
23 Office Chair C-03 16 nos.
24 Office Chair- Headmaster C-04 1 nos.
25 Office Visitor Chair C-05 19 nos.
26 Dinning Table T-09 2 nos.
Miscellaneous
27 Cusions F-16 18 nos.
28 Carpet 27.43 sq.m
29 Equipment Cabinet F-09 5 nos.
30 File Cabinet F-10 2 nos.
31 Notice Board F-14 1 nos.
Total 274 nos.

Building: 3-9C(SF)
S.N Furniture Description Symbol Qty Unit Remarks
Classroom
1 Student Desk G3-5 (2 Seater) D-01B 30 nos.
2 Student Desk G6-12 (2 Seater) D-01C 105
3 Student Bench G3-5 (2 Seater) B-01B 30 nos.
4 Student Desk G6-12 (2 Seater) B-01C 105 nos.
5 Teacher's Table T-01 9 nos.
6 Teacher's Chair C-01 9 nos.
7 White Board F-03 9 nos.
Total 297 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block 3-9C(SF)
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha

Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
1 EARTH WORKS
1.1 Site Clearance 1 28.50 12.50 356.25
Total 356.25 sq.m

1.2 Earth Work Excavation


Isolated footing
F1 2 2.80 2.80 1.50 23.52
F2 3 3.30 3.30 1.50 49.01
Combined footing
CF1 2 5.30 2.10 1.50 33.39
CF2 1 5.30 3.30 1.50 26.24
CF3 2 5.30 3.10 1.50 49.29

For Lower Tie Beam


Along grid 1 1 9.80 0.55 0.70 3.77
Along grid 2 1 10.90 0.55 0.70 4.20
Along grid 3 1 10.90 0.55 0.70 4.20
Along grid A 1 2.50 0.55 0.70 0.96
Along grid B 1 2.30 0.55 0.70 0.89
Along grid C 1 2.55 0.55 0.70 0.98
Along grid D 1 2.55 0.55 0.70 0.98
Along grid E 1 2.50 0.55 0.70 0.96

Ramp
For Slope 1 3.50 1.03 0.28 0.99
Wall Along Grid B 1 0.70 0.45 0.45 0.14
Wall Parallel to Ramp 1 6.70 0.45 0.41 1.24
Outside Staircase 1 18.95 0.60 0.15 1.71
Total 202.45 cu.m

1.3 Earth Back Filling


Earthwork 202.45
Boulder Soling -1 22.44 -22.44
PCC -1 11.39 -11.39
RCC -1 81.14 -81.14
Brick masonry -1 -1.00
Class room 3 5.70 5.70 0.15 14.62
Stair case 1 5.70 4.20 0.15 3.59
Corridoor 1 21.30 2.20 0.15 7.03
Total 111.72 cu.m

1.4 Boulder Soling


Isolated footing
F1 2 2.50 2.50 0.20 2.50
F2 3 3.00 3.00 0.20 5.40
CF1 2 5.00 1.80 0.20 3.60
CF2 1 5.00 3.00 0.20 3.00

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
CF3 2 5.00 2.80 0.20 5.60

Below foundation beam


Along grid 1 1 18.70 0.40 0.10 0.75
Along grid 2 1 10.90 0.40 0.10 0.44
Along grid 3 1 10.90 0.40 0.10 0.44
Along grid A 1 3.58 0.40 0.10 0.14
Along grid B 1 3.63 0.40 0.10 0.15
Along grid C 1 3.63 0.40 0.10 0.15
Along grid D 1 3.63 0.40 0.10 0.15
Along grid E 1 3.63 0.40 0.10 0.15
Building Floor
Classrooms 3 5.70 5.70 0.20 19.49
Staircase 1 4.20 5.70 0.20 4.79
Corridor 1 21.30 2.20 0.20 9.37
Ramp
Slopped Portion 1 1.30 1.36 Area 1.77
Wall Along Grid B 1 0.50 0.45 0.10 0.02
Wall Parallel to Ramp 1 6.80 0.45 0.10 0.31
At Slope 1 22.93 0.99 0.10 2.26
Pebbles Compacted Earth 1 22.93 0.63 0.10 1.43
Outside Steps 1 22.95 0.68 0.10 1.55
1 2.50 0.68 0.10 0.17
Total 63.61 cu.m

2 CONCRETE WORKS
2.1 P.C.C. Works
2.1.1 P.C.C.(1:3:6) Works
Isolated footing
F1 2 2.50 2.50 0.10 1.25
F2 3 3.00 3.00 0.10 2.70
Combined Footings
CF1 2 5.00 1.80 0.10 1.80
CF2 1 5.00 3.00 0.10 1.50
CF3 2 5.00 2.80 0.10 2.80

Below Lower Tie Beam


Along grid 1 1 18.70 0.40 0.05 0.37
Along grid 2 1 10.90 0.40 0.05 0.22
Along grid 3 1 10.90 0.40 0.05 0.22
Along grid A 1 3.58 0.40 0.05 0.07
Along grid B 1 3.63 0.40 0.05 0.07
Along grid C 1 3.63 0.40 0.05 0.07
Along grid D 1 3.63 0.40 0.05 0.07
Along grid E 1 3.63 0.40 0.05 0.07

Ramp
Wall Along Grid B 1 0.50 0.45 0.05 0.01
Wall Parallel to Ramp 1 6.80 0.45 0.05 0.15
Total 11.39 cu.m

2.1.2 P.C.C.(1:2:4) Works


Classrooms 3 5.70 5.70 0.08 7.31
Staircase 1 4.20 5.70 0.08 1.80

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Corridor 1 21.30 2.20 0.08 3.51

Outside Steps 1 16.73 0.68 0.05 0.56


1 2.50 0.68 0.05 0.08
Ramp
Sloped 1 1.30 0.51 Area 0.66
Wall Top 1 1.33 0.25 0.05 0.02
1 6.80 0.13 0.05 0.04
Total 13.99 cu.m

2.2 P.C.C For R.C.C. Works


A Foundation
F1
Rectangular Part 2 2.50 2.50 0.25 3.13
Trapezoidal part 2 1.73 1.73 0.35 2.08
F2 1.00
Rectangular Part 3 3.00 3.00 0.25 6.75
Trapezoidal part 3 1.98 1.98 0.35 4.10
CF1 2 5.00 1.80 0.60 10.80
CF2 1 5.00 3.00 0.60 9.00
CF3 2 5.00 2.8 0.60 16.80

B Beam
Foundation Tie Beam(300X400)
Along grid 1,2,3 3 20.70 0.30 0.40 7.45
Along grid A,B,C,D,E 5 5.55 0.30 0.40 3.33

Plinth Beam(300x450)
Along grid 1,2,3 3 20.70 0.30 0.45 8.38
Along grid A,B,C,D,E 5 7.60 0.30 0.45 5.13

Beam at first,second and Third floor level


Main Beam(300x525)
Along grid 1,2,3 9 20.70 0.30 0.40 22.36
Along grid A,B,C,D,E 15 7.60 0.30 0.40 13.68

Secondary beam(250x425)
Along 1a 3 16.35 0.25 0.30 3.68
Along A1,B1,D1 9 7.60 0.25 0.30 5.13

Top Floor Level


Along Grid 1,2,3 3 4.20 0.30 0.40 1.51
Along Grid C,D 2 7.60 0.30 0.40 1.82
Along 1a 1 4.20 0.25 0.40 0.42

Edges Beam(150X525) 1 14.40 0.15 0.40 0.86


3 0.75 0.30 0.40 0.27
1 0.75 0.25 0.30 0.06

C Columns
Foundation to Plinth 15 0.45 0.45 1.05 3.19
Ground Floor 15 0.45 0.45 3.00 9.11
First Floor 15 0.45 0.45 3.00 9.11
Second Floor 15 0.45 0.45 3.00 9.11

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Top Floor(Staircase Cover) 6 0.45 0.45 2.60 3.16

D Slab
First Floor Level Slab 1 22.95 8.95 0.13 25.68
Projections at Back 1 11.55 0.60 0.13 0.87
1 5.55 0.60 0.13 0.42
Projections at Front 1 12.15 0.98 0.13 1.48
Second floor level slab 1 22.95 8.95 0.13 25.68
Projections 1 11.55 0.60 0.13 0.87
1 5.55 0.60 0.13 0.42
Projection at Staircase 2 4.05 0.60 0.13 0.61
Third floor level slab 1 22.95 8.95 0.13 25.68
Projections
Back of Bldg 1 13.38 1.00 0.13 1.74
1 7.38 1.00 0.13 0.96
Side of Bldg 2 8.95 1.00 0.13 2.33
Front of Bldg 2 6.00 1.08 0.13 1.68
1 12.95 1.58 0.13 2.65
Top Floor Slab(Staircase Cover) 1 10.45 6.45 0.15 10.11

Deduction
Staircase void -3 4.20 5.55 0.13 -8.74
Bench slab 2 2.40 0.50 0.08 0.18

E Staircase
Ground Floor to First Floor
Steps 20 0.023 Area 2.00 0.90
Waist Slab 1 3.35 2.00 0.20 1.34
1 3.35 2.00 0.20 1.34
Landing 1 4.20 1.95 0.20 1.64
1 4.05 1.03 0.30 1.25
Landing Beam 1 4.05 0.25 0.38 0.38

Fisrt Floor Level to Second floor


Steps 20 0.023 Area 2.00 0.90
Waist Slab 1 3.35 2.00 0.20 1.34
1 3.35 2.00 0.20 1.34
Landing 1 4.20 1.95 0.20 1.64
Landing Beam 1 4.05 0.25 0.38 0.38

Fisrt Second Level to Third floor


Steps 20 0.023 Area 2.00 0.90
Waist Slab 1 3.35 2.00 0.20 1.34
1 3.35 2.00 0.20 1.34
Landing 1 4.20 1.95 0.20 1.64
Landing Beam 1 4.08 0.25 0.38 0.39

F Lintel Band
Ground Floor
Along grid 1 1 16.50 0.23 0.08 0.28
Along grid 2 1 9.90 0.23 0.08 0.17
Along grid A,B,C,D,E 5 5.55 0.23 0.08 0.48

First Floor

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along grid 1 1 16.50 0.23 0.08 0.28
Along grid 2 1 9.90 0.23 0.08 0.17
Along grid A,B,C,D,E 5 5.55 0.23 0.08 0.48

Second Floor
Along grid 1 1 16.50 0.23 0.08 0.28
Along grid 2 1 9.90 0.23 0.08 0.17
Along grid A,B,C,D,E 5 5.55 0.23 0.08 0.48

G Sill band
Ground Floor
Along grid 1 1 20.55 0.23 0.08 0.35
Along grid 2 1 9.90 0.23 0.08 0.17
Along grid A,B,C,D,E 5 5.55 0.23 0.08 0.48

First Floor
Along grid 1 1 20.55 0.23 0.08 0.35
Along grid 2 1 9.90 0.23 0.08 0.17
Along grid A,B,C,D,E 5 5.55 0.23 0.08 0.48

Second Floor
Along grid 1 1 20.55 0.23 0.08 0.35
Along grid 2 1 9.90 0.23 0.08 0.17
Along grid A,B,C,D,E 5 5.55 0.23 0.08 0.48

Top Floor (Staircase Cover)


Along grid 1 1 4.05 0.23 0.08 0.07
Along grid 3 1 4.05 0.23 0.08 0.07
Along grid C,D 2 7.60 0.23 0.08 0.26
Deduction
D1 -18 1.10 0.23 0.08 -0.34
D2 -2 1.10 0.23 0.08 -0.04

Band at Parapet
1 49.46 0.35 0.10 1.73
1 13.75 0.35 0.10 0.48
1 30.16 0.36 0.10 1.09
Vertical band 18 2.48 0.23 0.08 0.77

H Pedestal
Base Block 11 0.50 0.25 0.25 0.34
Total 282.33 cu.m

2.3 Silica Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10 282.33 2,823.30
Total 2,823.31 Kg

2.5 Formworks
A Foundation
F1 2 10.00 0.25 5.00
F2 3 12.00 0.25 9.00
CF1 2 13.60 0.60 16.32
CF2 1 16.00 0.60 9.60
CF3 2 15.60 0.60 18.72

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
B Beam
Foundation Tie Beam(300X400)
Along grid 1,2 2 20.70 0.80 33.12
Along grid 3 1 20.70 0.80 16.56
Along grid A,B,C,D,E 5 5.55 0.80 22.20

Plinth Beam(300x450)
Along grid 1,2 2 20.70 1.20 49.68
Along grid 3 1 20.70 1.20 24.84
Along grid A,B,C,D,E 5 7.60 1.20 45.60

Beam at First,Second and Third floor level


Main beam(300x525)
Along grid 1,2,3 9 20.70 1.10 204.93
Along grid A,B,C,D,E 15 7.60 1.10 125.40

Secondary Beam(250x425)
Along A1,B1,D1 9 7.60 0.85 58.14
Along 1a 3 16.35 0.85 41.69

Top Floor Level


Along grid 1,2,3 3 4.20 1.10 13.86
Along grid C and D 2 7.60 1.10 16.72
Along 1a 1 4.20 0.85 3.57

Edges Beam(150X525) 1 14.40 0.95 13.68


3 0.75 0.95 2.14
1 0.75 0.75 0.56

C Column
Foundation to Plinth 15 1.80 1.05 28.35
Ground Floor 15 1.80 3.00 81.00
First Floor 15 1.80 3.00 81.00
Second Floor 15 1.80 3.00 81.00
Roof floor 6 1.80 2.62 28.30

D Slab
First Floor Level Slab 1 23.20 9.20 213.44
Projections at Back 1 11.80 0.73 8.56
1 5.55 0.60 3.33
Projections at Front 1 12.28 1.10 13.50
Second floor level slab 1 23.20 9.20 213.44
Projections 1 11.80 0.73 8.56
1 5.68 0.73 4.11
Projection at Staircase 2 4.18 0.73 6.05
Third floor level slab 1 23.20 9.20 213.44
Projections
Back of Bldg 1 13.50 1.13 15.19
1 7.50 1.13 8.44
Side of Bldg 2 9.20 1.13 20.70
Front of Bldg 2 6.13 1.20 14.70
1 13.08 1.70 22.23
Top Floor Slab(Staircase Cover) 1 10.70 6.70 71.69

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Deduction
Staircase void -3 4.20 5.55 -69.93

Bench slab 2 2.00 0.50 2.00


2 5.8 0.08 0.87

E Staircase
Upto first floor level
Steps 40 0.023 Area 0.90
Waist slab 1 3.35 2 6.71
1 3.35 2 6.71
Side formwork for waist slab 2 3.35 0.2 1.34
2 3.35 0.2 1.34
Landing 1 4.20 1.67 7.01
Side formwork for landing 1 3.34 0.21 0.68
Riser 20 2.00 0.15 6.00
Landing Beam 1 4.05 1.07 4.31

First to second floor


Steps 40 0.023 Area 0.90
Waist slab 1 3.35 2 6.71
1 3.35 2 6.71
Side formwork for waist slab 2 3.35 0.2 1.34
2 3.35 0.2 1.34
Landing 1 4.20 1.67 7.01
Side formwork for landing 1 8.18 0.21 1.68
Tread 20 2.00 0.15 6.00
Landing Beam 1 4.08 0.77 3.12
Projection on Landing Slab 1 4.08 0.6 2.45

Second to Third Floor


Steps 40 0.023 Area 0.90
Waist slab 1 3.35 2 6.71
1 3.35 2 6.71
Side formwork for waist slab 2 3.35 0.2 1.34
2 3.35 0.2 1.34
Landing 1 4.20 1.67 7.01
Side formwork for landing 1 8.18 0.21 1.68
Tread 20 2.00 0.15 6.00
Landing Beam 1 4.08 0.77 3.12
Projection on Landing Slab 1 4.08 0.6 2.45

F Lintel Band
Ground Floor
Along grid 1 1 16.50 0.15 2.48
Along grid 2 1 9.90 0.15 1.49
Along grid A,B,C,D,E 5 5.55 0.15 4.16

First Floor
Along grid 1 1 16.50 0.15 2.48
Along grid 2 1 9.90 0.15 1.49
Along grid A,B,C,D,E 5 5.55 0.15 4.16

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Second Floor
Along grid 1 1 16.50 0.15 2.48
Along grid 2 1 9.90 0.15 1.49
Along grid A,B,C,D,E 5 5.55 0.15 4.16

G Sill band
Ground Floor
Along grid 1 1 20.55 0.15 3.08
Along grid 2 1 9.90 0.15 1.49
Along grid A,B,C,D,E 5 5.55 0.15 4.16

First Floor
Along grid 1 1 20.55 0.15 3.08
Along grid 2 1 9.90 0.15 1.49
Along grid A,B,C,D,E 5 5.55 0.15 4.16

Second Floor
Along grid 1 1 20.55 0.15 3.08
Along grid 2 1 9.90 0.15 1.49
Along grid A,B,C,D,E 5 5.55 0.15 4.16

Top Floor (Staircase Cover)


Along grid 1 1 4.08 0.15 4.08
Along grid 3 1 4.08 0.15 4.08
Along grid C,D 2 4.48 0.15 8.95

Parapet banding 1 63.21 0.20 12.64


1 30.16 0.20 6.03
Deduction
D1 -18 1.10 0.15 -2.97
D2 -2 1.10 0.15 -0.33
Vertical band 18 2.48 0.15 6.68
Total 2,000.51 sq.m

3 BRICK WORKS
3.2 Full Brick (230 mm) Works (1:4c/s)
Below Plinth Level
Along Grid 1,2,3 3 20.70 0.23 0.20 2.86
Along Grid A,B,C,D,E 5 7.60 0.23 0.20 1.75

Ground floor
Ground Floor
Along grid 1 1 16.65 0.23 2.35 9.00
1 4.05 0.23 2.12 1.97
Along grid 2 1 16.65 0.23 2.35 9.00
Along Grid A,B,C,D,E 5 5.55 0.23 2.29 14.58

Deduction
D1 -6 1.10 0.23 2.33 -3.53
W1 -12 1.10 0.23 1.65 -5.01
W3 -2 1.50 0.23 0.37 -0.26

First Floor
Along grid 1 1 16.65 0.23 2.35 9.00

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1 4.05 0.23 2.05 1.90
Along grid 2 1 16.65 0.23 2.35 9.00
Along Grid A,B,C,D,E 5 5.55 0.23 2.29 14.58

Deduction
D1 -6 1.10 0.23 2.33 -3.53
W1 -12 1.10 0.23 1.65 -5.01
W2 -1 1.50 0.23 0.93 -0.32

Second Floor
Along grid 1 1 20.80 0.23 2.43 11.60
1 4.08 0.23 2.05 1.92
Along grid 2 1 20.80 0.23 2.43 11.60
Along Grid A,B,C,D,E 5 5.55 0.23 2.29 14.58

Deduction
D1 -6 1.10 0.23 2.33 -3.53
W1 -12 1.10 0.23 1.65 -5.01
W2 -1 1.50 0.23 0.93 -0.32

Top Floor
Along Grid 1 1 4.05 0.23 2.03 -1.89
Along grid 3 1 4.05 0.23 2.03 -1.89
Along C and D 2 7.60 0.23 2.03 -7.08

Deduction
D2 -2 1.10 0.23 1.08 -0.55
W2 -1 1.50 0.23 1.00 -0.35
Parapet Wall 1 63.00 0.23 0.80 11.59
1 30.00 0.23 0.90 6.21

Outside
Steps 1 19.00 0.30 0.10 0.57
1 18.50 0.30 0.25 1.39
1 0.60 0.50 0.30 0.09
1 0.50 0.50 0.30 0.08

Ramp
Wall Along -B 1 1.33 0.25 Area 0.33
1 6.91 0.23 Area 1.59
Total 96.95 cu.m

3.3 Half Brick (125 mm) Works (1:4c/s)


Below Staircase 1 1.28 Area 1.28
1 2.02 1.54 3.10
Bench 2 2.40 0.57 2.74
Total 7.12 sq.m

4 DOORS & WINDOWS


4.1 Metal Frame
4.1.1 Doors Frame
D1 18 7.08 127.44
D2 2 5.30 10.60
D3 1 4.10 4.10

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Total 142.14 r.m

4.1.2 Windows Frame


Windows Frame W1 36 7.79 280.26
W2 3 5.00 15.00
Ventilation V1 36 3.25 117.00
Total 412.26 r.m

4.2 Metal Shutter


4.2.1 Windows shutter
Windows W1 36 0.97 0.85 29.53
W2 2 1.37 0.91 2.48
Ventilation V1 36 1.01 0.44 15.82
Total 47.83 sq.m
4.3 Wooden Shutter
4.3.1 Flush Doors Shutter
Doors D1 18 1.01 2.43 44.18
D2 2 1.01 2.06 4.15
D3 1 0.91 1.51 1.37
Total 49.70 sq.m

4.5 Window Grill


Windows W1 36 0.97 0.85 29.53
W2 2 1.37 0.91 2.48
Ventilation V1 36 1.01 0.44 15.82
Total 47.83 Sq.m
4.6 Collapsable Gate
1 4.075 2.48 10.09
Total 10.09 Sq.m

5 FLOORING WORKS
5.1 Hardened Cement Concrete Flooring (40mm) With Neat Cement Punning
Ground floor
Classroom 3.00 5.75 5.75 99.19
Below staircase 1.00 5.65 4.20 23.73
Corridor 1.00 22.80 2.38 54.15

Staircase
Landing 1.00 4.20 2.00 8.40
Tread 19.00 2.00 0.30 11.40
Riser 20.00 2.00 0.15 6.00

First floor
Classroom 3.00 5.75 5.75 99.19
Corridor 1.00 22.80 2.38 54.15

Staircase
Landing 1.00 4.20 2.00 8.40
Tread 19.00 2.00 0.30 11.40
Riser 20.00 2.00 0.15 6.00
Second floor
Classroom 3.00 5.75 5.75 99.19
Corridor 1.00 22.80 2.38 54.15

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Staircase
Landing 1.00 4.20 2.00 8.40
Tread 19.00 2.00 0.30 11.40
Riser 20.00 2.00 0.15 6.00

Top Floor 1.00 12.625 9.95 125.62


1.00 6.625 9.95 65.92
Staircase cover 1.00 9.45 5.45 51.50

Outside
Outer steps 1 18.50 0.9 16.65
Ramp 1 8.2 Area 8.20

Slope at Back Side of Building 1 22.925 1 22.93


Total 851.96 sq.m

5.2 Neat cement skirting


Ground floor plan
Classroom 1,2 and 3 3 23.30 69.90
Column 5 2.00 10.00
Corridor 1 29.49 29.49
Store Below Landing 1 18.09 18.09
Staircase/Landing 1 16.40 16.40
Deduction
D1 -12 1.10 -13.20
D3 -2 1.00 -2.00
First floor plan
Classroom 4,5 and 6 3 23.30 69.90
Corridor 1 24.54 24.54
Column 3 1.80 5.40
2 0.80 1.60
Staircase/Landing 1 16.40 16.40
Deduction
D1 -12 1.10 -13.20
Second floor plan
Classroom 7,8 and 9 3 23.30 69.90
Corridor 1 24.54 24.54
Column 3 1.80 5.40
2 0.80 1.60
Staircase/Landing 1 16.40 16.40
Deduction
D1 -12 1.10 -13.20
Top floor Plan
Corridor 1 25.10 25.10
Top Floor Outer wall 1 92.40 92.40
Deduction
D1 -4 1.10 -4.40

Roof Plan
Along Wall 1 29.80 29.80
Total 480.86 r.m

5.3 25mm Terrazo Finishing


Bench 2 2.40 0.50 2.40

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Total 2.40 sq.m

7 PLASTER/PAINTING WORKS
7.1 Cement Plaster
7.1.1 Internal Plaster on Wall (1:6)
Ground floor
Classrooms 3 23.15 2.91 202.10
Staircase Area 1 15.67 3.04 47.56
Storage room below staircase 2 2.70 1.35 3.65
2 0.20 1.35 0.54
2 0.90 1.50 2.70
2 2.00 1.65 6.60
Deduction
D1 -6 1.10 2.50 -8.25
W1 -12 1.10 1.75 -11.55
W3 -1 1.50 0.33 -0.24
V1 -6 1.10 0.53 -1.73

First floor
Classrooms 3 23.15 2.91 202.10
Staircase Area 1 15.67 3.04 47.56

Deduction
D1 -6 1.10 2.50 -8.25
W1 -12 1.10 1.75 -11.55
W2 -1 1.50 1.08 -0.81
V1 -6 1.10 0.53 -1.73

Second floor
Classrooms 3 23.15 2.91 202.10
Staircase Area 1 15.67 3.04 47.56

Deduction
D1 -6 1.10 2.50 -8.25
W1 -12 1.10 1.75 -11.55
W2 -2 1.50 1.08 -1.61
V1 -6 1.10 0.53 -1.73

Top Floor
1 23.74 2.40 56.93
Deduction
W2 -1 1.50 1.08 -0.81
D2 -2 1.10 2.10 -2.31
Total 749.01 sq.m

7.1.2 Internal Plaster on Ceiling (1:4)


Ground floor
Classroom 1 4 2.73 2.73 29.70
Classroom 2 4 2.73 2.73 29.70
Classroom 3 4 2.73 2.73 29.70
Corridor 4 2.73 2.20 23.98
1 4.20 2.20 9.24
Staircase Area 1 4.20 1.05 4.41

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Main Beam
Classroom 1 4 5.55 0.40 8.88
Classroom 2 4 5.55 0.40 8.88
Classroom 3 4 5.55 0.40 8.88
Corridor; Along grid 2 , ( A-B) ,(B-C) & (D-E) 3 5.55 0.40 6.66
Corridor; Along grid 2 , ( C-D) 1 4.05 1.10 4.46
Corridor; Along grid 3 , ( A-B), (B-C) ,(C-D) & 1 20.70 0.70 14.49
Corridor; Along grid A, B, C,D and E; (2-3) 5 2.20 1.10 12.10
Staircase Area;Along grid C and D; (1-2) 2 5.30 0.40 4.24
Staircase Area ; Along grid 1 , ( C-D) 1 4.05 0.40 1.62

Secondary Beam
Along Grid A1,B1 & D1 3 7.65 0.85 19.51
Along Grid 1a 3 5.77 0.85 14.71

Below staircase
Waist slab 1 3.35 2.00 6.71
Landing 1 2.00 2.00 4.00
1 2.10 2.20 4.62
First floor
Classroom 4 4 2.73 2.73 29.70
Classroom 5 4 2.73 2.73 29.70
Classroom 6 4 2.73 2.73 29.70
Corridor 4 2.73 2.20 23.98
1 4.20 2.20 9.24
Staircase Area 1 4.20 0.88 3.68

Main Beam
Classroom 4 4 5.55 0.40 8.88
Classroom 5 4 5.55 0.40 8.88
Classroom 6 4 5.55 0.40 8.88
Corridor; Along grid 2 , ( A-B) ,(B-C) & (D-E) 3 5.55 0.40 6.66
Corridor; Along grid 2 , ( C-D) 1 4.05 1.10 4.46
Corridor; Along grid 3 , ( A-B), (B-C) ,(C-D) & 1 20.70 0.70 14.49
Corridor; Along grid A, B, C,D and E; (2-3) 5 2.20 1.10 12.10
Staircase Area;Along grid C and D; (1-2) 2 5.30 0.40 4.24
Staircase Area ; Along grid 1 , ( C-D) 1 4.05 0.40 1.62

Secondary Beam
Along Grid A1,B1 & D1 3 7.65 0.85 19.51
Along Grid 1a 3 5.77 0.85 14.71

Below staircase
Waist slab 1 3.35 2.00 6.71
Landing 1 2.00 2.00 4.00
1 2.10 2.20 4.62
Second floor
Classroom 7 4 2.73 2.73 29.70
Classroom 8 4 2.73 2.73 29.70
Classroom 9 4 2.73 2.73 29.70
Corridor 4 2.73 2.20 23.98
1 4.20 2.20 9.24
Staircase Area 1 4.20 0.88 3.68

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Main Beam
Classroom 7 4 5.55 0.40 8.88
Classroom 8 4 5.55 0.40 8.88
Classroom 9 4 5.55 0.40 8.88
Corridor; Along grid 2 , ( A-B) ,(B-C) & (D-E) 3 5.55 0.40 6.66
Corridor; Along grid 2 , ( C-D) 1 4.05 1.10 4.46
Corridor; Along grid 3 , ( A-B), (B-C) ,(C-D) & 1 20.70 0.70 14.49
Corridor; Along grid A, B, C,D and E; (2-3) 5 2.20 1.10 12.10
Staircase Area;Along grid C and D; (1-2) 2 5.30 0.40 4.24
Staircase Area ; Along grid 1 , ( C-D) 1 4.05 0.40 1.62

Secondary Beam
Along Grid A1,B1 & D1 3 7.65 0.85 19.51
Along Grid 1a 3 5.77 0.85 14.71

Below staircase
Waist slab 1 3.35 2.00 6.71
Landing 1 2.00 2.00 4.00

Top floor level beam


Along grid A1,B1,D1 3 15.80 0.450 21.33
Along grid 1a 1 32.70 0.450 14.72

At Staircase Cover
Slab 1.00 67.20 Area 67.20
Total 836.63 sq.m

7.1.3 External Plaster


7.1.3.1 Outer Plaster
Slab
Projected Slab at Staircase
First Floor 1.00 4.08 1.33 5.42
Second Floor 1.00 4.08 1.33 5.42
At Staircase Cover slab(At Level 11600) 1.00 29.20 1.15 33.58
Projected Slab at Third Floor Level(+9000) 1.00 60.88 1.88 114.45
Projected Slab at First Floor Level(+3000) 1.00 22.93 2.65 60.64

Outer Beam
First floor level beam
Along grid 1 1 20.70 0.55 11.39
Along grid A and E 2 5.55 0.55 6.11
Landing beam 1 4.05 0.60 2.41

Second floor level beam


Along grid 1 1 20.70 0.55 11.39
Along grid A and E 2 5.55 0.55 6.11
Landing beam 1 4.05 0.60 2.41

Third floor level


Along grid 1 1 20.70 0.55 11.39
Along grid A and E 2 5.55 0.55 6.11
Landing beam 1 4.05 0.60 2.41

Outer column

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Ground Floor
Class Room Corner 4 1.18 3.35 15.75
Intermediate Corner 6 0.70 3.45 14.49
Corridor Column 5 1.80 2.40 21.60

First Floor
Class Room Corner 4 1.18 3.00 14.10
Intermediate Corner 6 0.70 3.00 12.60
Corridor Column 5 1.90 3.00 28.50

Second Floor
Class Room Corner 4 1.18 3.00 14.10
Intermediate Corner 6 0.70 3.00 12.60
Corridor Column 5 1.90 3.00 28.50

Top Floor (Stair case Cover) 4 1.15 3.00 13.80

Outer Plaster on Walls


Ground Floor
Along grid 1 1 16.65 2.50 41.63
1 4.05 2.20 8.89
Along grid 2 1 16.65 2.50 41.63
Along grid A and E 2 5.55 2.50 27.75

Deduction
D1 -6 1.10 2.48 -16.34
W1 -12 1.10 1.73 -22.77
W3 -2 1.50 0.37 -1.11

First Floor
Along grid 1 1 16.65 2.50 41.63
1 4.05 2.12 8.59
Along grid 2 1 16.65 2.50 41.63
Along grid A and E 2 5.55 2.50 27.75

Deduction
D1 -6 1.10 2.48 -16.34
W1 -12 1.10 1.73 -22.77
W2 -1 1.50 1.00 -1.50

Second Floor
Along grid 1 1 20.80 2.50 52.00
1 4.08 2.12 8.64
Along grid 2 1 20.80 2.50 52.00
Along grid A and E 2 4.48 2.50 22.38

Deduction
D1 -6 1.10 2.48 -16.34
W1 -12 1.10 1.73 -22.77
W2 -1 1.50 1.00 -1.50

Top Floor
Along Grid 1 1 4.05 2.10 -8.51
Along grid 3 1 4.05 2.10 -8.51

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along C and D 2 7.60 2.10 -31.92

Deduction
D2 -2 1.10 1.08 -2.38
W2 -1 1.50 1.00 -1.50
Total 655.50 sq.m

7.2 Painting Works


7.2.1 Distemper Paint
As per Internal Plaster on Wall 1 749.01 749.01
As per Internal Plaster on Ceiling 1 836.63 836.63
Total 1,585.64 sq.m

7.2.2 Exterior Weather Coat Paint


As per External Plaster 1 655.50 655.50
Total 655.50 sq.m

7.2.4 Enamel Paint Factor


W1 36 1.10 1.73 2.00 136.62
W2 3 1.54 1.00 2.00 9.24
V1 36 1.10 0.53 2.00 41.58
D1 18 1.10 2.50 2.00 99.00
D2 2 1.00 2.10 2.00 8.40
D3 1 1.00 1.55 2.00 3.10
Window Grill(W1) 18 1.10 1.73 2.00 68.31
W2 3 1.50 1.00 2.00 9.00
W3 1 1.50 0.37 2.00 1.11
V1 36 1.10 0.53 2.00 41.58
Collapsable Gate 1 4.08 2.46 2.00 20.05
Total 437.99 sq.m

8 MISCELLANEOUS
Total
8.3 Railling Length kg/m
Length
A Staircase Railing
Ground Floor Lvl to First Floor Level
ISNB 40M(Horizontal Handrail) 1 6.70 6.70 3.56 23.85
25mm Square Pipe(Horizontal Bars) 4 6.58 26.32 0.85 22.37
Vertical 38mm Square Pipe 7 0.9 6.30 2.82 17.77

First Floor Lvl to Second Floor Level


ISNB 40M(Horizontal Handrail) 1 6.70 6.70 3.56 23.85
25mm Square Pipe(Horizontal Bars) 4 6.58 26.32 0.85 22.37
Vertical 38mm Square Pipe 6 0.9 5.40 2.82 15.23

Second Floor Lvl to Third Floor Level


ISNB 40M(Horizontal Handrail) 1 6.70 6.70 3.56 23.85
25mm Square Pipe(Horizontal Bars) 4 6.58 26.32 0.85 22.37
Vertical 38mm Square Pipe 7 0.9 6.30 2.82 17.77
Base plate 21 0.00009375 0.00 7850 15.45
12 mm dia Anchor Bolts and Nuts,Screw 84 0.13 10.92

B Parapet Railing
For First and Second Floor

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
ISNB 40M(Horizontal Bars) 2 24.80 49.60 3.56 176.58
ISNB 32M(Horizontal Bars) 4 24.80 99.20 3.10 307.52
ISNB 32M(Vertical Bars) 40 1.08 43.16 3.10 133.80
25mm Square Pipe(Vertical Bars) 338 0.82 277.16 0.85 235.59

For Terrace
ISNB 40M(Horizontal Bars) 1 50.26 50.26 3.56 178.92
ISNB 32M(Horizontal Bars) 1 50.26 50.26 3.10 155.80
ISNB 32M(Vertical Bars) 32 0.26 8.26 3.10 25.59
25mm Square Pipe(Vertical Bars) 294 0.16 46.45 0.85 39.48
Base plate 46 0.00009375 0.00 7850 33.85
12 mm dia Anchor Bolts and Nuts,Screw 184 0.13 23.92

C Pedestal
ISNB 40M Pedestal Bars 11 1.61 17.71 3.56 63.05
11 1.20 13.20 3.56 46.99
22 0.35 7.70 3.56 27.41
Base plate 33 0.00009375 0.00 7850 24.29
12 mm dia Anchor Bolts and Nuts,Screw 132 0.13 17.16
Total 1,705.76 Kg

8.5 Sewer, Rain and Waste Water Installation


- 110 mm ED 6 kg/sqcm 4 9.00 36.00
2 2.60 5.20
Total 41.20 R.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block 3-9C(SF)
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha

Bar Bending Schedule


Length
Unit
Dia Ø No of No of Unit Lap Total Total Wt
S.No. Description / Sketch Lap Weight Remarks
mm element Bar Length length Length (kg)
no kg/m
( m) (m) (m)
1 Isolated Footing (F1)
16mm Dia bar in X-Direction
16 2 17.00 2.60 88.40 1.58 139.67
0.1 2.4 0.1

16mm dia bar in Y-Direction


16 2 17.00 2.60 88.40 1.58 139.67
0.1 2.4 0.1

2 Isolated Footing (F2)


16mm Dia bar in X-Direction
16 3 20.33 3.10 189.10 1.58 298.78
0.1 2.9 0.1

16mm dia bar in Y-Direction


16 3 20.33 3.10 189.10 1.58 298.78
0.1 2.9 0.1

3 Combined Footing (CF1)


12mm dia bar in X-Direction(top & bottom)
12 2 33.67 1.90 127.93 0.89 113.73
0.1 1.7 0.1

0.1 1.7 0.1 12 2 33.67 1.90 127.93 0.89 113.73

12mm&16mm dia bar in Y-Direction(top & bottom)

0.1 4.9 0.1 12 2 12.33 5.10 125.80 0.89 111.84

0.1 4.9 0.1 16 2 12.33 5.10 125.80 1.58 198.76

10mm 4-Legged Stirrups


10 2 100.00 4.05 810.00 0.62 499.77
0.10 0.55

1.375

4 Combined Footing (CF2)


12mm dia bar in X-Direction(top & bottom)

0.1 2.9 0.1 12 1 33.67 3.10 104.37 0.89 92.78

0.1 2.9 0.1 12 1 33.67 3.10 104.37 0.89 92.78

12mm&16mm dia bar in Y-Direction(top & bottom)

0.1 4.9 0.1 12 1 20.33 5.10 103.70 0.89 92.19

0.1 4.9 0.1 16 1 20.33 5.10 103.70 1.58 163.85

10mm 4-Legged Stirrups

0.10 10 1 100.00 5.25 525.00 0.62 323.93


0.55

1.975

5 Combined Footing (CF3)


12mm dia bar in X-Direction(top & bottom)

0.1 2.7 0.1 12 2 33.67 2.90 195.27 0.89 173.59

0.1 2.7 0.1 12 2 33.67 2.90 195.27 0.89 173.59

12mm&16mm dia bar in Y-Direction(top & bottom)

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
0.1 4.9 0.1 12 2 19.00 5.10 193.80 0.89 172.29

0.1 4.9 0.1 16 2 19.00 5.10 193.80 1.58 306.20

10mm 4-Legged Stirrups

0.10 10 2 100.00 5.20 1040.00 0.62 641.68


0.55

1.975

6 Column
Column 1-1
Ground Floor
Grid A,E
16mm through bar
16 2 12.00 5.01 120.24 1.58 189.98
3

2.01

8mm dai Stirrups

0.08 0.08 8 2 47.50 1.64 155.80 0.40 61.54


0.37
8 2 95.00 1.20 228.00 0.40 90.06

0.15 0.37
Grid D
20mm through bar & 25mm through bar

3 3 20 1 8.00 5.25 42.00 2.47 103.70

2.25 2.55 25 1 4.00 5.55 22.20 3.86 85.65

8mm dai Stirrups

0.08 0.08 8 1 47.50 1.64 77.90 0.40 30.77


0.37
8 1 95.00 1.20 114.00 0.40 45.03
0.15 0.37

Grid C
20mm through bar
20 1 12.00 5.25 63.00 2.47 155.55
3

2.25

8mm dai Stirrups

0.08 0.08 8 1 47.50 1.64 77.90 0.40 30.77


0.37
8 1 95.00 1.20 114.00 0.40 45.03
0.15 0.37

Grid B
16mm through bar & 20mm through bar

3 3 16 1 8.00 5.01 40.08 1.58 63.33

2.01 2.25 20 1 4.00 5.25 21.00 2.47 51.85

8mm dai Stirrups

0.08 0.08 8 1 47.50 1.64 77.90 0.40 30.77


0.37
8 1 95.00 1.20 114.00 0.40 45.03
0.15 0.37

Column 2-2
Ground Floor
Grid A,B,C,D,E
20mm & 16 mm through bar
3 3
16 5 8.00 5.01 200.40 1.58 316.63

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
2.01 2.25 20 5 4.00 5.25 105.00 2.47 259.25

8mm dai Stirrups

0.08 0.08
8 5 47.50 1.64 389.50 0.40 153.85
0.37
0.15 0.37 8 5 95.00 1.20 570.00 0.40 225.15

Column 3-3
Ground Floor
Grid B,C,D
16mm & 20mm through bar

3 3 16 3 8.00 5.01 120.24 1.58 189.98

2.01 2.25 20 3 4.00 5.25 63.00 2.47 155.55

8mm dai Stirrups

0.08 0.08
8 3 47.50 1.64 233.70 0.40 92.31
0.37
0.15 0.37 8 3 95.00 1.20 342.00 0.40 135.09

Grid A,E
20mm through bar

3 20 2 12.00 5.25 126.00 2.47 311.09

2.25

8mm dai Stirrups

0.08 0.08 8 2 47.50 1.64 155.80 0.40 61.54


0.37
8 2 95.00 1.20 228.00 0.40 90.06
0.15 0.37

Column first floor


column 1-1
Ground Floor
Grid A,E
16mm through bar
16 2 12.00 3.96 95.04 1.58 150.16
3

0.96

8mm dai Stirrups

0.08 0.08 8 2 30.00 1.64 98.40 0.40 38.87


0.37
8 2 60.00 1.20 144.00 0.40 56.88

0.15 0.37
Grid D
20mm through bar & 25mm through bar

3 3 20 1 8.00 4.20 33.60 2.47 82.96

1.2 1.5 25 1 4.00 4.50 18.00 3.86 69.44

8mm dai Stirrups

0.08 0.08 8 1 30.00 1.64 49.20 0.40 19.43


0.37
8 1 60.00 1.20 72.00 0.40 28.44
0.15 0.37

Grid C
20mm through bar
20 1 12.00 4.20 50.40 2.47 124.44
3

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1.2

8mm dai Stirrups

0.08 0.08 8 1 30.00 1.64 49.20 0.40 19.43


0.37
8 1 60.00 1.20 72.00 0.40 28.44
0.15 0.37

Grid B
16mm through bar & 20mm through bar

3 3 16 1 8.00 3.96 31.68 1.58 50.05

0.96 1.2 20 1 4.00 4.20 16.80 2.47 41.48

8mm dai Stirrups

0.08 0.08 8 1 30.00 1.64 49.20 0.40 19.43


0.37
8 1 60.00 1.20 72.00 0.40 28.44
0.15 0.37

Column 2-2
Ground Floor
Grid A,B,C,D,E
20mm & 16 mm through bar

3 3 16 5 8.00 3.96 158.40 1.58 250.27


20 5 4.00 4.20 84.00 2.47 207.40
0.96 1.2

8mm dai Stirrups

0.08 0.08
8 5 30.00 1.64 246.00 0.40 97.17
0.37
0.15 0.37 8 5 60.00 1.20 360.00 0.40 142.20

Column 3-3
Ground Floor
Grid B,C,D
16mm & 20mm through bar

3 3 16 3 8.00 3.96 95.04 1.58 150.16

0.96 1.2 20 3 4.00 4.20 50.40 2.47 124.44

8mm dai Stirrups

0.08 0.08
8 3 30.00 1.64 147.60 0.40 58.30
0.37
0.15 0.37 8 3 60.00 1.20 216.00 0.40 85.32

Grid A,E
20mm through bar

3 20 2 12.00 4.20 100.80 2.47 248.88

1.2

8mm dai Stirrups

0.08 0.08 8 2 30.00 1.64 98.40 0.40 38.87


0.37
8 2 60.00 1.20 144.00 0.40 56.88
0.15 0.37

Column Second floor


column 3-3
Grid A & E
16mm & 20mm through bar

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1.12 1.4 16 2 4.00 4.56 0.96 1.00 36.44 1.58 57.58
20 2 8.00 5.08 1.20 1.00 81.20 2.47 200.48
2.475 2.475

0.96 1.2

8mm dai Stirrups

0.08 0.08 8 2 30.00 1.64 98.40 0.40 38.87


0.37
8 2 60.00 1.20 144.00 0.40 56.88
0.15 0.37

Grid B
16mm through bar
1.12
16 1 12.00 4.56 0.96 1.00 54.66 1.58 86.36
2.475

0.96

8mm dai Stirrups


8 1 30.00 1.64 49.20 0.40 19.43
0.08 0.08
8 1 60.00 1.20 72.00 0.40 28.44
0.37
0.15 0.37

Grid C & D
16mm through bar

3 16 2 12.00 3.96 0.96 1.00 95.04 1.58 150.16

0.96

8mm dai Stirrups

0.08 0.08 8 2 30.00 1.64 98.40 0.40 38.87


0.37
8 2 60.00 1.20 144.00 0.40 56.88
0.15 0.37
column 2-2
Grid A,B,C,D,E
16mm through bar

1.12 16 5 12.00 4.56 0.96 1.00 273.30 1.58 431.81

2.475

0.96

8mm dai Stirrups

0.08 0.08 8 5 30.00 1.64 246.00 0.40 97.17


0.37
8 5 60.00 1.20 360.00 0.40 142.20
0.15 0.37

Column 1-1
Grid A,B& E
16mm through bar

1.12 16 3 12.00 4.56 163.98 1.58 259.09

2.475

0.96

8mm dai Stirrups

0.08 0.08 8 3 30.00 1.64 147.60 0.40 58.30


0.37

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
0.08 0.08
0.37
8 3 60.00 1.20 216.00 0.40 85.32
0.15 0.37

Grid C
16mm & 20 mm bar

3 3
16 1 4.00 3.96 0.96 1.00 15.84 1.58 25.03
0.96 1.12
20 1 8.00 4.20 1.20 1.00 33.60 2.47 82.96

8mm dai Stirrups

0.08 0.08 8 1 30.00 1.64 49.20 0.40 19.43


0.37
8 1 60.00 1.20 72.00 0.40 28.44
0.15 0.37

Grid D
20mm through bar

20 1 12.00 4.20 1.20 1.00 50.40 2.47 124.44


3

1.2

8mm dai Stirrups

0.08 0.08 8 1 30.00 1.64 49.20 0.40 19.43


0.37
8 1 60.00 1.20 72.00 0.40 28.44
0.15 0.37

Roof level column


Grid 1-1
Grid C & D
16mm , 20mm dia bar

1.12 1.4 16 1 8.00 4.18 0.96 1.00 33.44 1.58 52.84


20 1 4.00 4.70 1.20 1.00 18.80 2.47 46.42
2.1 2.1

0.96 1.2

8mm dai Stirrups

0.08 0.08 8 2 26.25 1.64 86.10 0.40 34.01


0.37
8 2 52.50 1.20 126.00 0.40 49.77
0.15 0.37

Column 2-2
Grid C & D
16mm dia bar

1.12
16 2 12.00 4.18 100.32 1.58 158.51
2.1

0.96

8mm dai Stirrups

0.08 0.08 8 2 26.25 1.64 86.10 0.40 34.01


0.37
8 2 52.50 1.20 126.00 0.40 49.77
0.15 0.37

Column 3-3
Grid C & D
16mm & 20mm dia bar

1.12

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
16 2 12.00 4.18 100.32 1.58 158.51
2.1

0.96

8mm dai Stirrups

0.08 0.08 8 2 26.25 1.64 86.10 0.40 34.01


0.37
8 2 52.50 1.20 126.00 0.40 49.77
0.15 0.37

7 Foundation Beam
Grid 1-1,2-2,3-3
16mm through bar
1.12 1.12
23.97 16 3 3.00 26.21 0.96 2.00 235.89 1.58 372.71

1.12 23.97 1.12 16 3 3.00 26.21 0.96 2.00 235.89 1.58 372.71

8mm dia strrups

0.08 8 3 170.00 1.36 693.60 0.40 273.97


0.35
0.25

Grid AA,BB,CC,DD,EE
16mm through bar
1.12 1.12
8.05 16 5 3.00 10.29 154.35 1.58 243.87

1.12 8.05 1.12 16 5 3.00 10.29 154.35 1.58 243.87

8mm dia strrups

0.08 8 5 67.00 1.36 455.60 0.40 179.96


0.35
0.25

8 Plinth Beam
Grid 1-1,2-2,3-3
20mm through bar( top 2+bottom 2)
1.4 1.4
27.4
20 3 4.00 27.25 1.20 2.00 327.00 2.47 807.36
1.4 27.4 1.4

16mm through bar( top 1+bottom 1)


1.12 1.12
27.4
16 3 2.00 26.21 0.96 2.00 157.26 1.58 248.47
1.12 27.4 1.12

12mm dia strrups

0.12
12 3 177.00 1.54 817.74 0.89 726.97
0.4
0.25
Grid AA,BB,CC,DD,EE
20mm through bar( top 2+bottom 2)
1.4 1.4
9 20 5 4.00 10.85 217.00 2.47 535.77

1.4 9 1.4

16mm through bar( top 1+bottom 1)


1.12 1.12
9
16 5 2.00 10.29 102.90 1.58 162.58
1.12 9 1.12

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
12mm dia strrups

0.12
12 5 67.00 1.54 515.90 0.89 458.64
0.4
0.25

9 Main Beam
Ground Floor
Grid 1-1,2-2,3-3
20mm through bar( bottom 2)
20 3 2.00 27.25 1.20 2.00 163.50 2.47 403.68
1.4 27.4 1.4

16mm through bar( top 3+bottom 2)


1.12 1.12
26.92
16 3 5.00 26.21 0.96 2.00 393.15 1.58 621.18
1.12 26.92 1.12

16mm torsion bar


27.84 16 3 2.00 24.79 0.96 2.00 148.74 1.58 235.01
25mm Extra Bar

1.75 1.775 25 3 4.00 3.53 42.30 3.86 163.19

4 25 3 2.00 4.00 24.00 3.86 92.59

3.5 25 3 4.00 3.50 42.00 3.86 162.04


10mm dia strrups

0.10
10 3 177.00 1.65 876.15 0.62 540.59
0.475
0.25

Grid AA & EE
25mm through bar( bottom 2)
25 2 2.00 11.55 46.20 3.86 178.24
1.75 8.05 1.75

20MM ( 5 no.)
1.4 1.4
8.05 20 2 5.00 10.85 108.50 2.47 267.89

1.4 8.05 1.4

16mm torsion bar


8.87 16 2 2.00 8.87 35.48 1.58 56.06
25mm Extra Bar

1.75 4.275 25 2 2.00 6.03 24.10 3.86 92.98


2
1.75 25 2 2.00 3.75 15.00 3.86 57.87

10mm dia strrups

0.10
10 2 67.00 1.65 221.10 0.62 136.42
0.475
0.25

Grid BB,CC,DD
25mm through bar( bottom 2)

1.75 10.5 0.5 25 3 2.00 15.21 1.50 1.00 91.23 3.86 351.97

20MM ( 5 no.)
1.4 0.5
9 20 3 5.00 14.55 1.20 1.00 218.25 2.47 538.86

1.12 9 0.5

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
16mm torsion bar 16 3 2.00 9.77 58.62 1.58 92.62
9.92
25mm Extra Bar

0.5 5.85 25 3 2.00 6.35 38.10 3.86 146.99


2
1.75 25 3 2.00 3.75 22.50 3.86 86.81

10mm dia strrups

0.10
10 3 76.00 1.65 376.20 0.62 232.12
0.475
0.25

10 Secondary Beam
Ground Floor
Grid 1a
From A-C 16mm dia bar

0.5 13.26 0.5 16 1 7.00 14.26 0.96 1.00 99.82 1.58 157.72

0.5 15.26 0.5


10mm dia strrups

0.08
8 1 94.00 1.31 123.14 0.40 48.64
0.375
0.2

From D-E 16mm dia bar

0.5 6.3 0.5 16 1 7.00 7.30 51.10 1.58 80.74

0.5 6.3 0.5


10mm dia strrups

0.08
8 1 47.00 1.31 61.57 0.40 24.32
0.375
0.2

Grid A1 & D1
16mm dia bar

0.5 8.8 0.5 16 2 7.00 9.80 137.20 1.58 216.78

0.5 8.8 0.5


10mm dia strrups

0.08
8 2 67.00 1.31 175.54 0.40 69.34
0.375
0.2

Grid B1
16mm dia bar

0.5 9.7 0.5 16 1 7.00 10.70 74.90 1.58 118.34

0.5 9.7 0.5


10mm dia strrups

0.08
8 1 56.00 1.31 73.36 0.40 28.98
0.375
0.2

11 Landing Beam
First Floor
20 mm dia bar

1.4 6.8 1.4 20 1 6.00 6.80 40.80 2.47 100.74

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1.4 6.8 1.4
10mm dia strrups

0.08
8 1 36.00 1.22 43.92 0.40 17.35
0.33
0.2

12 Edge Beam
First Floor
12 mm dia bar

0.5 13.12 0.5


12 1 8.00 14.12 0.72 1.00 112.96 0.89 100.42
0.5 9.8 0.5
10mm dia strrups

0.08
8 1 115.00 1.31 150.65 0.40 59.51
0.475
0.1

First Floor
Grid 1-1,2-2,3-3
20mm through bar( bottom 2)
20 3 2.00 27.25 1.20 2.00 163.50 2.47 403.68
1.4 27.4 1.4

16mm through bar( top 3+bottom 2)


1.12 1.12
26.92
16 3 5.00 26.21 0.96 2.00 393.15 1.58 621.18
1.12 26.92 1.12

16mm torsion bar


27.84 16 3 2.00 24.79 0.96 2.00 148.74 1.58 235.01
25mm Extra Bar

1.75 1.775 25 3 4.00 3.53 42.30 3.86 163.19

4 25 3 2.00 4.00 24.00 3.86 92.59

3.5 25 3 4.00 3.50 42.00 3.86 162.04


10mm dia strrups

0.10
10 3 177.00 1.65 876.15 0.62 540.59
0.475
0.25

Grid AABB,CC,DD,EE
25mm through bar( bottom 2)
25 5 2.00 11.55 115.50 3.86 445.60
1.75 8.05 1.75

20MM ( 5 no.)
1.4 1.4
8.05 20 5 5.00 10.85 271.25 2.47 669.72

1.4 8.05 1.4

16mm torsion bar


8.87 16 5 2.00 8.87 88.70 1.58 140.15
25mm Extra Bar

1.75 4.275 25 5 2.00 6.03 60.25 3.86 232.45


2
1.75 25 5 2.00 3.75 37.50 3.86 144.68

10mm dia strrups

0.10
0.475

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
0.10
10 5 67.00 1.65 552.75 0.62 341.05
0.475
0.25

Secondary Beam
Ground Floor
Grid 1a
From A-C 16mm dia bar

0.5 13.26 0.5 16 1 7.00 14.26 0.96 1.00 99.82 1.58 157.72

0.5 15.26 0.5


10mm dia strrups

0.08
8 1 94.00 1.31 123.14 0.40 48.64
0.375
0.2

From D-E 16mm dia bar

0.5 6.3 0.5 16 1 7.00 7.30 51.10 1.58 80.74

0.5 6.3 0.5


10mm dia strrups

0.08
8 1 47.00 1.31 61.57 0.40 24.32
0.375
0.2

Grid A1,B1 & D1


16mm dia bar

0.5 8.8 0.5 16 3 7.00 9.80 205.80 1.58 325.16

0.5 8.8 0.5


10mm dia strrups

0.08
8 3 67.00 1.31 263.31 0.40 104.01
0.375
0.2

Landing Beam
First Floor
20 mm dia bar

1.4 6.8 1.4 20 1 6.00 6.80 40.80 2.47 100.74

1.4 6.8 1.4


10mm dia strrups

0.08
8 1 36.00 1.22 43.92 0.40 17.35
0.33
0.2

Second Floor
Grid 1-1,2-2,3-3
20mm through bar( bottom 2)
20 3 2.00 27.25 1.20 2.00 163.50 2.47 403.68
1.4 27.4 1.4

16mm through bar( top 3+bottom 2)


1.12 1.12
26.92
16 3 5.00 26.21 0.96 2.00 393.15 1.58 621.18
1.12 26.92 1.12

16mm torsion bar


27.84 16 3 2.00 24.79 0.96 2.00 148.74 1.58 235.01
25mm Extra Bar

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1.75 1.775 25 3 4.00 3.53 42.30 3.86 163.19

4 25 3 2.00 4.00 24.00 3.86 92.59

3.5 25 3 4.00 3.50 42.00 3.86 162.04


10mm dia strrups

0.10
10 3 177.00 1.65 876.15 0.62 540.59
0.475
0.25

Grid AABB,CC,DD,EE
25mm through bar( bottom 2)
25 5 2.00 11.55 115.50 3.86 445.60
1.75 8.05 1.75

20MM ( 5 no.)
1.4 1.4
8.05 20 5 5.00 10.85 271.25 2.47 669.72

1.4 8.05 1.4

16mm torsion bar


8.87 16 5 2.00 8.87 88.70 1.58 140.15
25mm Extra Bar

1.75 4.275 25 5 2.00 6.03 60.25 3.86 232.45


2
1.75 25 5 2.00 3.75 37.50 3.86 144.68

10mm dia strrups

0.10
10 5 67.00 1.65 552.75 0.62 341.05
0.475
0.25

Secondary Beam
Ground Floor
Grid 1a
From A-C 16mm dia bar

0.5 13.26 0.5 16 1 7.00 14.26 0.96 1.00 99.82 1.58 157.72

0.5 15.26 0.5


10mm dia strrups

0.08
8 1 94.00 1.31 123.14 0.40 48.64
0.375
0.2

From D-E 16mm dia bar

0.5 6.3 0.5 16 1 7.00 7.30 51.10 1.58 80.74

0.5 6.3 0.5


10mm dia strrups

0.08
8 1 47.00 1.31 61.57 0.40 24.32
0.375
0.2

Grid A1,B1 & D1


16mm dia bar

0.5 8.8 0.5 16 3 7.00 9.80 205.80 1.58 325.16

0.5 8.8 0.5


10mm dia strrups

0.08

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
0.08
8 3 67.00 1.31 263.31 0.40 104.01
0.375
0.2

Landing Beam
First Floor
20 mm dia bar

1.4 6.8 1.4 20 1 6.00 6.80 40.80 2.47 100.74

1.4 6.8 1.4


10mm dia strrups

0.08
8 1 36.00 1.22 43.92 0.40 17.35
0.33
0.2

Main Beam
Top Floor
Grid 1-1,2-2,3-3
20mm through bar( top 2)
20 3 2.00 6.80 40.80 2.47 100.74
1.4 4 1.4

16mm through bar( top 1+bottom 4)


1.12 1.12
4
16 3 5.00 6.24 93.60 1.58 147.89
1.12 4 1.12

16mm torsion bar


27.84 16 3 2.00 4.92 29.52 1.58 46.64
10mm dia strrups

0.10
10 3 36.00 1.65 178.20 0.62 109.95
0.475
0.25
Grid CC,DD
20mm through bar( top 2)
20 2 2.00 10.85 43.40 2.47 107.16
1.4 8.05 1.4

16MM ( 5 no.)
1.12 1.12
8.05
16 2 5.00 11.24 112.40 1.58 177.59
1.12 8.05 1.12

10mm dia strrups

0.10
10 2 67.00 1.65 221.10 0.62 136.42
0.475
0.25

Secondary Beam
Grid 1b
16 mm dia bar

0.5 4.8 0.5 16 1 7.00 5.80 40.60 1.58 64.15

0.5 4.8 0.5


10mm dia strrups

0.08
8 1 36.00 1.31 47.16 0.40 18.63
0.375
0.2

13 Stair case

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
first floor,second & third floor
16mm through bar @ top
1.878
0.1 16 3 19.00 6.53 372.32 1.58 588.27
3.354

1.3
0.1
16mm through bar @ bottom

1.3 1.2 16 3 19.00 2.48 141.08 1.58 222.90


0.1
16mm through bar
1.878
1.2 0.1 16 3 19.00 3.18 181.15 1.58 286.21
10mm distribution
4.15 10 6 13.67 4.15 340.30 0.62 209.97

10mm distribution @ bottom


1.95 10 3 36.97 1.95 216.26 0.62 133.43

16mm extra bar @ top & bottom


16 3 18.00 2.00 108.00 1.58 170.64
1 1
1.2 16 3 18.00 2.20 118.80 1.58 187.70
1
Top flight
16mm through bar @ top
1.15
0.1 16 3 19.00 6.93 394.78 1.58 623.76
3.354

2.422
0.1
16mm through bar @ bottom
16 3 19.00 3.60 205.03 1.58 323.95
2.422 1.2
0.1
16mm through bar
1.15 16 3 19.00 2.38 135.38 1.58 213.89
1.2 0.1
10mm distribution @ bottom
1.95 10 3 35.69 1.95 208.81 0.62 128.83

16mm extra bar @ top & bottom


16 3 18.00 2.00 108.00 1.58 170.64
1 1
0.925 16 3 18.00 1.93 103.95 1.58 164.24
1
8mm nosing bar
0.2 8 3 126.67 0.80 304.00 0.40 120.08
0.125 0.275
0.2
10mm nosing tie bar
1.95 10 3 20.00 1.95 117.00 0.62 72.19

14 Slab
Ground Floor
From A-C & 1-3
x-axis
12.88
8 1 53.67 13.78 0.48 1.00 739.26 0.40 292.01
0.45 0.45

0.45 0.45
Y-axis
14.83
8 1 33.67 9.88 332.46 0.40 131.32
0.525 0.525

8 1 42.67 10.53 449.07 0.40 177.38

0.525 0.525

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Top bar
X-axis 8 1 36.00 12.73 0.48 1.00 458.28 0.40 181.02

Y-axis
8 1 15.00 9.48 142.13 0.40 56.14
8 1 27.00 10.55 284.85 0.40 112.52
From D-E & 1-3
x-axis
7.35
8 1 52.00 7.25 377.00 0.40 148.92
0.525 0.525

0.525 0.525
Y-axis

8 1 36.33 9.88 358.79 0.40 141.72


0.525 0.525

8 1 5.67 10.53 59.64 0.40 23.56

0.525 0.525
Top bar
X-axis 8 1 36.00 6.25 225.00 0.40 88.88

Y-axis 8 1 15.00 9.45 141.75 0.40 55.99


8 1 8.00 9.75 78.00 0.40 30.81
From C-D & 1-3
x-axis
7.35
8 1 30.50 5.46 0.48 2.00 166.53 0.40 65.78
0.525 0.525

0.525 0.525
Y-axis

8 1 27.67 4.48 123.81 0.40 48.90


0.525 0.525

0.525 0.525
Top bar
X-axis
8 1 20.23 5.46 110.47 0.40 43.64

Y-axis
8 1 31.00 3.43 106.18 0.40 41.94
Extra Bar
Along A1 B1 & D1 8 3 12.67 2.05 77.90 0.40 30.77
2.05

Along B
2.1 8 1 12.67 2.10 26.60 0.40 10.51

Along 1a
2.35 8 1 31.33 2.05 64.23 0.40 25.37

Along 2
1.975
8 1 31.33 1.95 61.10 0.40 24.14
8 1 5.83 1.98 11.52 0.40 4.55
Along 3
2.05 8 1 44.00 2.05 90.20 0.40 35.63

Along 1
1.875 8 1 31.33 1.88 58.75 0.40 23.21

Along C & D
2.55

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
8 2 8.67 2.55 44.20 0.40 17.46

Connection between main and secondary beam

0.96 0.96 16 1 28.00 3.17 88.76 1.58 140.24

0.5 0.25 0.5

Slab
First Floor
From A-C & 1-3
x-axis
14.83
8 1 53.67 13.73 0.48 1.00 736.84 0.40 291.05
0.525 0.525

0.525 0.525
Y-axis
14.83
8 1 73.67 9.88 727.46 0.40 287.35
0.525 0.525

0.525 0.525
Top bar
X-axis 8 1 36.00 12.73 0.48 1.00 458.28 0.40 181.02

Y-axis
8 1 41.00 9.45 387.45 0.40 153.04

From D-E & 1-3


x-axis
7.35
8 1 52.00 7.25 377.00 0.40 148.92
0.525 0.525

0.525 0.525
Y-axis

8 1 37.33 9.88 368.67 0.40 145.62


0.525 0.525

0.525 0.525
Top bar
X-axis 8 1 36.00 6.25 225.00 0.40 88.88

Y-axis 8 1 21.50 9.45 203.18 0.40 80.25

From C-D & 1-3


x-axis
7.35
8 1 30.50 5.46 0.48 2.00 166.53 0.40 65.78
0.525 0.525

0.525 0.525
Y-axis

8 1 27.67 3.70 102.37 0.40 40.44


0.525 0.525

0.525 0.525
Top bar
X-axis
8 1 13.67 5.46 74.62 0.40 29.48

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Y-axis
8 1 33.00 4.28 141.08 0.40 55.73

Extra Bar
Along A1 B1 & D1 8 3 12.67 2.05 77.90 0.40 30.77
2.05

Along B
2.1 8 1 12.67 2.10 26.60 0.40 10.51

Along 1a
2.05 8 1 31.33 2.05 64.23 0.40 25.37

Along 2
1.95
8 1 31.33 1.95 61.10 0.40 24.14
8 1 5.83 1.98 11.52 0.40 4.55
Along 1
1.875 8 1 31.33 1.88 58.75 0.40 23.21

Along C & D
2.55
8 2 8.67 2.55 44.20 0.40 17.46

Connection between main and secondary beam

0.96 0.96 16 1 28.00 3.17 88.76 1.58 140.24

0.5 0.25 0.5

Slab
Second Floor
From A-C & 1-3
x-axis
15.905
8 1 66.33 14.31 0.48 1.00 948.90 0.40 374.82
0.525

0.525 0.525
Y-axis
11.8
8 1 27.67 10.80 298.80 0.40 118.03
0.525 0.525

8 1 41.67 11.78 0.48 1.00 490.83 0.40 193.88

0.525 0.525
Top bar
X-axis 8 1 30.00 13.86 415.65 0.40 164.18
Y-axis 8 1 19.00 10.80 205.20 0.40 81.05
8 1 31.00 11.28 349.68 0.40 138.12

From D-E & 1-3


x-axis
15.905
8 1 66.33 7.88 522.38 0.40 206.34
0.525

0.525 0.525
Y-axis
11.8 8 1 27.67 10.80 298.80 0.40 118.03

0.525 0.525
8 1 11.00 12.78 0.48 1.00 140.58 0.40 55.53

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
0.525 0.525
Top bar
X-axis 8 1 30.00 7.33 219.75 0.40 86.80
Y-axis 8 1 19.00 10.70 203.30 0.40 80.30
8 1 7.00 10.80 75.60 0.40 29.86
From C-D& 1-3
x-axis
15.905 8 1 35.33 5.96 0.48 2.00 210.59 0.40 83.18

0.525

0.525 0.525
Y-axis
11.8
8 1 13.83 5.15 71.24 0.40 28.14
0.525 0.525

0.525 0.525
Top bar
X-axis 8 1 17.17 5.96 102.31 0.40 40.41
Y-axis 8 1 19.00 5.15 97.85 0.40 38.65

Extra Bar
Along A1 B1 & D1 8 3 13.42 2.05 82.51 0.40 32.59
2.05

Along B
2.1 8 1 13.42 2.10 28.18 0.40 11.13

Along 1a
2.05 8 1 53.33 2.05 109.33 0.40 43.19

Along 2
2.1
8 1 31.33 1.95 61.10 0.40 24.14
8 1 5.83 1.98 11.52 0.40 4.55
Along 3
2.125 8 2 14.17 2.13 60.21 0.40 23.78
8 1 12.17 2.63 31.94 0.40 12.62
Along C & D
2.7
8 2 8.67 2.55 44.20 0.40 17.46
Along A & E
2.125 8 2 13.42 2.13 57.02 0.40 22.52

Along 1
2.45 8 1 31.33 2.28 71.28 0.40 28.16

10mm diasribution bar @ TOP


Along A & E 10 2 21.50 11.10 0.60 1.00 477.30 0.62 294.49
Along A-C & D-E 10 1 7.17 20.75 0.60 1.00 148.71 0.62 91.75
Along Grid 1 10 2 20.00 6.00 240.00 0.62 148.08
10 1 30.00 14.10 0.60 1.00 423.00 0.62 260.99
12mm consoal beam
12 2 4.00 10.65 85.20 0.89 75.74
12 1 4.00 25.24 0.72 1.00 100.96 0.89 89.75
12 1 4.00 22.62 0.72 1.00 90.48 0.89 80.44
8 mm stirrups 8 1 534.00 0.76 405.84 0.40 160.31

Connection between main and secondary beam

0.96 0.96 16 1 28.00 3.17 88.76 1.58 140.24

0.5 0.25 0.5

Slab
top floor level
From A-C & 1-3

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
x-axis
15.905 8 1 65.00 6.50 422.50 0.40 166.89

0.525

0.525 0.525
Y-axis
11.8
8 1 40.33 10.50 423.50 0.40 167.28
0.525 0.525

0.525 0.525
Top bar
X-axis 8 1 40.67 6.20 252.13 0.40 99.59
Y-axis 8 1 29.33 9.90 290.40 0.40 114.71

Extra Bar
Along 2
1.95
8 1 5.83 1.95 11.38 0.40 4.49

Along 1 &3
2.05
8 2 4.33 2.05 17.77 0.40 7.02

Along C & D
2.5
8 2 9.67 2.50 48.33 0.40 19.09

Connection between main and secondary beam

0.96 0.96 16 1 4.00 3.17 12.68 1.58 20.03

0.5 0.25 0.5


Bands
Vertical band
10mm & 8mm dia bar in vertical band in door

G.F 10 6 2.00 2.48 29.70 0.62 18.33


8 6 17.50 0.34 35.70 0.40 14.10
F.F 10 6 2.00 2.48 29.70 0.62 18.33
8 6 17.50 0.34 35.70 0.40 14.10
2.475
S.F 10 6 2.00 2.48 29.70 0.62 18.33
8 6 17.50 0.34 35.70 0.40 14.10

Vertical band @ parapet wall


band @ parapet 1 10 35 2.00 0.80 56.00 0.62 34.55
8 35 6.33 0.34 75.37 0.40 29.77
10 16 2.00 1.40 44.80 0.62 27.64
8 16 67.67 0.34 368.11 0.40 145.40
band @ parapet 2
10 22 2.00 0.90 39.60 0.62 24.43
8 22 7.00 0.34 52.36 0.40 20.68
Sill band
10mm & 8mm dia bar in Sill band
Ground Floor
Grid 1 10 1 2.00 20.65 41.30 0.62 25.48
8 1 138.67 0.34 47.15 0.40 18.62

Grid 2
10 1 2.00 10.05 20.10 0.62 12.40
8 1 68.00 0.34 23.12 0.40 9.13
Grid A,B,C,D,E 0.00 0.00 0.00
10 5 2.00 5.55 55.50 0.62 34.24
8 1 38.00 0.34 12.92 0.40 5.10
0.00 0.00 0.00
First Floor 0.00 0.00 0.00
Grid 1 10 1 2.00 16.65 33.30 0.62 20.55

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
8 1 112.00 0.34 38.08 0.40 15.04

Grid 2
10 1 2.00 10.05 20.10 0.62 12.40
8 1 68.00 0.34 23.12 0.40 9.13
Grid A,B,C,D,E 0.00 0.00 0.00
10 5 2.00 5.55 55.50 0.62 34.24
8 1 38.00 0.34 12.92 0.40 5.10

Second Floor
Grid 1 10 1 2.00 16.65 33.30 0.62 20.55
8 1 112.00 0.34 38.08 0.40 15.04

Grid 2
10 1 2.00 10.05 20.10 0.62 12.40
8 1 68.00 0.34 23.12 0.40 9.13
Grid A,B,C,D,E 0.00 0.00 0.00
10 5 2.00 5.55 55.50 0.62 34.24
8 1 38.00 0.34 12.92 0.40 5.10

Parapet wall 0.00 0.00 0.00


10 1 2.00 64.20 128.40 0.62 79.22
8 1 429.00 0.34 145.86 0.40 57.62
0.00 0.00 0.00
10 1 2.00 30.80 61.60 0.62 38.01
8 1 206.33 0.34 70.15 0.40 27.71
Lintel band 0.00 0.00 0.00
10mm & 8mm dia bar in Sill band 0.00 0.00 0.00
Ground Floor 0.00 0.00 0.00
Grid 1 10 1 2.00 16.65 33.30 0.62 20.55
8 1 112.00 0.34 38.08 0.40 15.04
0.00 0.00 0.00
Grid 2 0.00 0.00 0.00
10 1 2.00 10.05 20.10 0.62 12.40
8 1 68.00 0.34 23.12 0.40 9.13
Grid A,B,C,D,E 0.00 0.00 0.00
10 5 2.00 5.55 55.50 0.62 34.24
8 1 38.00 0.34 12.92 0.40 5.10

First Floor 0.00 0.00 0.00


Grid 1 10 1 2.00 16.65 33.30 0.62 20.55
8 1 112.00 0.34 38.08 0.40 15.04
0.00 0.00 0.00
Grid 2 0.00 0.00 0.00
10 1 2.00 10.05 20.10 0.62 12.40
8 1 68.00 0.34 23.12 0.40 9.13
Grid A,B,C,D,E 0.00 0.00 0.00
10 5 2.00 5.55 55.50 0.62 34.24
8 1 38.00 0.34 12.92 0.40 5.10

Second Floor 0.00 0.00 0.00


Grid 1 10 1 2.00 5.55 11.10 0.62 6.85
8 1 38.00 0.34 12.92 0.40 5.10

Grid 2
10 1 2.00 10.05 20.10 0.62 12.40
8 1 68.00 0.34 23.12 0.40 9.13
Grid A,B,C,D,E
10 5 2.00 5.55 55.50 0.62 34.24
8 1 38.00 0.34 12.92 0.40 5.10
Top floor
Grid 1-3 10 2 2.00 4.00 16.00 0.62 9.87
8 2 27.67 0.34 18.81 0.40 7.43

Grid C,D 10 2 2.00 6.45 25.80 0.62 15.92


8 2 44.00 0.34 29.92 0.40 11.82
Bench
8mm dia @ x-axis
8 2 18.00 2.55 91.80 0.40 36.26
8 2 5.00 0.65 6.50 0.40 2.57
Total 45946.823 kgs
45.95 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block 3-9C(SF)
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha

Site 3-9C(SF) Total


S. No. Description Unit Remarks
Development G.F F.F S.F TF Quantity
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure 1 1.00 nos.
2 CABLES & WIRES
2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded
2.1 52 r.m
copper conductor wires
2 Nos 2.5 Sq.mm + 1 No 1.5 Sq.mm mutistranded
2.2 50 r.m
copper conductor wires
B School Blocks
1 DISTRIBUTION BOARDS 1.00 1.00 1.00 3.00 nos.
1.5 6A DP MCB with Enclosure 0.00 nos.
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4
2.1 12.00 r.m
Sq mm Multistranded Cu wire
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5
2.2 6.00 r.m
Sq mm Multistranded Cu wire
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No
2.3 14.00 r.m
1.5 Sq mm Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point 6 17.00 17.00 17.00 2.00 59.00 pts.
3.2 Two Way Light Point 1.00 1.00 2.00 pts.
3.3 Ceiling Fan Point pts.
4 6A Universal Pin Light Power Socket Wiring 18.00 18.00 18.00 54.00 pts.
5 Switch Socket Outlets
5.1 6A Universal Power Switch Socket 18.00 18.00 18.00 54.00 nos.
6 Sweep Ceiling/ Exhaust Fan/Wall Fan
6 Wall Fan 12 12 12 36 nos.
7 Light Fixtures/Luminaires & Accessories
7.2 18 W LED Surface Mounted Square type 12 12 12 36 nos.
7.4 12 W LED Surface Mounted Cylindrical type 5 6 6 3 20 nos.
7.6 LED Wall Light 1 1 nos.
8 Pull Box nos.
Junction Box At External Post Top Light 3 3 no.
9 External Post Top Light Pole 3 3.00 nos.
10 Post Top External Light Fixtures 3 3.00 nos.
11 Earthing & Lighting Protection
11.1 Chemical Earthing 3 3 no.
11.2 Earthing Bar 3 3 no.
12 Earthing Strip/Wires
12.3.1 25 x 3 mm GI strip 67 r.m
12.3.2 12 SWG Cu wire 13 r.m
13 Earth Test link 1 1 nos.
14 Lightning Arrester 1 1 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
1 Earthworks
1.1 Site Clearance
Toilet Block 1 14.30 12.30 175.89
Septic Tank 1 8.75 3.95 34.56
Soak Pit 1 8.55 Area 8.55
Sewer Manhole (Rectangular) 4 2.00 2.00 16.00
Total 235.00 sq.m

1.2 Earthwork in excavation


Footing
F1 9 1.30 1.30 1.20 18.25
Excavation for lower tie beam
Grid 1 2 3.70 0.60 0.7 3.11
Grid 2 2 3.70 0.50 0.7 2.59
Grid 3 2 3.70 0.60 0.7 3.11
Between grid 2 and 3 2 4.45 0.60 0.7 3.74
Grid A-12 , B-12 and C-12 3 2.20 0.60 0.7 2.77
Along grid A-23 and C-23 2 1.20 0.50 0.7 0.84
Along grid B-23 1 1.20 0.60 0.7 0.50
Ramp
For Slope 2 1.58 1.03 0.28 0.89
Drain 1 11.45 0.63 0.23 1.61
1 11.45 0.58 0.38 2.52
Outside Steps 2 1.20 0.68 0.15 0.24

Septic Tank 1 6.75 1.95 2.72 35.78


Soak Pit 1 4.15 Area 1.55 6.44
For Sewer Manhole (Rectangular) 4 1.00 1.00 0.50 2.00
Total 84.39 cum

1.3 Earth Back filling


Total earthwork 84.39
Boulder soling -1 19.26 Vol. -19.26
PCC work -1 2.03 Vol. -2.03
RCC work -1 5.16 Vol. -5.16

Inside the room(Compacted) 2 4.70 3.20 0.18 5.41


Along lobby(Compacted) 2 4.70 2.20 0.18 3.72
Total 67.07 cum

1.4 Boulder soling


For Footing
F1 9 1.00 1.00 0.20 1.80
For Lower Tie Beam
Grid 1 and Grid 3 2 9.40 0.45 0.10 0.85
Grid 2 2 4.70 0.35 0.10 0.33
Between grid 2 and 3 2 4.45 0.45 0.10 0.40
Along grid A-12,B-12 & C-12 3 3.20 0.45 0.10 0.43
Along grid A-23 & C-23 2 2.20 0.35 0.10 0.15
Along grid B-23 1 2.20 0.45 0.10 0.10
Toilet Floors 2 4.75 3.25 0.20 6.18

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
Corridor Floors 2 4.75 0.88 0.20 1.66
Ramp
below ramp 2 6.77 1.03 0.20 2.78
For Outer Steps 2 1.20 0.60 0.1 0.14
Drain 1 11.45 1.20 0.10 1.37
Septic tank 1 6.75 1.95 0.1 1.32
For Sewer Manhole (Rectangular) 4 1.00 1.00 0.1 0.40
Soak pit ( Boulder packing) 1 1.13 Area 1.20 1.36
Total 19.26 cum

1.5 Sand Filling


Periphery of Soak pit 1 1.88 Area 1.55 2.92
Total 2.93 cu.m

2 Concrete Works
2.1 PCC
2.1.1 PCC work (1:3:6)
For Footing
F1 9 1.00 1.00 0.10 0.90
For Lower Tie Beam
Grid 1 and Grid 3 2 9.40 0.45 0.05 0.42
Grid 2 2 4.70 0.35 0.05 0.16
Between grid 2 and 3 2 4.45 0.45 0.05 0.20
Along grid A-12,B-12 & C-12 3 3.20 0.45 0.05 0.22
Along grid A-23 & C-23 2 2.20 0.35 0.05 0.08
Along grid B-23 1 2.20 0.45 0.05 0.05
Septic Tank 1 0.83 1.45 0.08 0.09
Sewer Manhole (Rectangular)
Bottom 4 1.00 1.00 0.10 0.40
PCC Benching 4 0.07 Area 1.00 0.30
Total 2.82 cum

2.1.2 P.C.C.(1:2:4) Works


Toilet 2 3.20 4.75 0.20 6.08
Corridor 2 1.20 4.75 0.20 2.28
Ramp
Below Ramp 2 6.77 1.03 0.08 1.04
For Outer Steps 2 1.20 0.60 0.05 0.07
2 1.20 0.30 0.05 0.04
Drain 1 11.45 0.58 0.075 0.49
Total 10.01 cu.m

2.2 PCC for RCC Works


For Footing
F1 9
Square portion 1.00 1.00 0.20 1.80
Trapazoid portion Area 0.63 0.15 0.84
Lower Tie Beam
Grid 1,2,3 3 9.40 0.25 0.25 1.76
Grid A-12,C-12 2 3.20 0.25 0.25 0.40
Grid B-13 1 5.70 0.25 0.25 0.36
Plinth Tie Beam
Grid 1,2,3 3 9.40 0.25 0.30 2.12
Grid A-12,C-12 2 3.20 0.25 0.30 0.48
Grid A-23,C-23 2 2.20 0.25 0.59 0.65

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
Grid B-13 1 5.70 0.25 0.30 0.43
Column
From lower to plinth tie beam 9 0.30 0.30 1.00 0.81
Ground Floor Column 9 0.30 0.30 3.00 2.43
Truss Beam
Grid 1 1 9.40 0.25 0.40 0.94
Grid 2-3 2 9.40 0.25 0.45 2.12
Grid A-12,B-12,C-12 3 3.20 0.25 0.40 0.96
Grid A-23,B-23,C-23 3 2.20 0.25 0.45 0.74
Slab
Corridor Slab 2 4.75 2.25 0.150 3.21
Lintel Bands,
Ground floor level
Grid 1,2,3 3 9.40 0.23 0.13 0.81
Grid A& C 2 3.20 0.23 0.13 0.18
Grid B 1 5.40 0.23 0.13 0.16
Partition Wall
Partition Wall for disable toilet 2 3.27 0.23 0.13 0.19
Partition wall for toilet short wall 2 1.32 0.13 0.13 0.04
Partition wall for toilet long wall 2 2.50 0.13 0.13 0.08
Sill Bands
Ground floor level
Grid 1,2,3 3 9.40 0.23 0.08 0.49
Grid A& C 2 3.20 0.23 0.08 0.11
Grid B 1 5.40 0.23 0.08 0.09
Partition Wall
Partition Wall for disable toilet 2 3.27 0.23 0.08 0.11
Partition wall for toilet short wall 2 1.32 0.13 0.08 0.02
Partition wall for toilet long wall 2 2.50 0.13 0.08 0.05
Along the incinerator 3 1.95 0.13 0.08 0.05
Deduction of Doors For Sill
Ground floor level
D1 -2 1.00 0.23 0.08 -0.03
D2 -2 0.90 0.23 0.08 -0.03
D3 -4 0.75 0.13 0.08 -0.03
Along the water trough 2 3.75 0.60 0.10 0.45
Water trough edge 2 5.40 0.20 0.10 0.22
at both end 2 0.48 0.20 0.10 0.02
at Center 1 0.50 0.20 0.10 0.01
Incinerators Slab 1 0.83 1.05 0.08 0.06
Septic Tank
At Bottom 1 6.30 2.25 0.15 2.13
Concealed Beam CB1 1 1.95 0.25 0.12 0.06
Concealed Beam CB 1 2.25 0.15 0.12 0.04
Top Cover 1 5.75 1.95 0.12 1.35
Deduction of Manhole -2 0.60 0.60 0.12 -0.09
Manhole Cover Slab 2 0.60 0.60 0.15 0.11
Manhole Cover Slab 1 0.75 0.75 0.15 0.08
Soak Pit
RCC slab 1 4.15 Area 0.13 0.52
Manhole/Waste Chamber
Top Cover 4 1.00 1.00 0.15 0.60
Total 27.89 cu.m

2.3 Silica Cement Admixture

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
10 Kg per cu.m. of R.C.C. M20 10 27.89 278.90
Total 278.90 Kg

2.5 Form Work


For Footing
F1 9 4.00 0.20 7.20
Lower Tie Beam
Grid 1,2,3 3 9.40 0.50 14.10
Grid A-12,C-12 2 3.20 0.50 3.20
Grid B-13 1 5.70 0.50 2.85
Pedestal column 9 1.00 1.20 10.80
Deduction1 at beam and column junction at LTB -24 0.25 0.25 -1.50
Deduction1 at beam and column junction at UTB -24 0.25 0.30 -1.80
Plinth Tie Beam
Grid 1,2,3 3 9.40 0.60 16.92
Grid A-12,C-12 2 3.20 0.60 3.84
Grid A-23,C-23 2 2.20 1.18 5.18
Grid B-13 1 5.70 0.60 3.42
Ground Floor Column 9 1.20 3.00 32.40
Deduction for Beam opening part -24 0.25 0.40 -2.40
Truss Beam
Grid 1-2-3 3 9.40 1.15 32.43
Grid A-12,B-12,C-12 3 3.20 1.05 10.08
Grid A-23,B-23,C-23 3 2.20 1.15 7.59
G.F. Slab
Corridor Slab 2 4.75 2.25 21.38
Lintel Bands,
Ground floor level
Grid 1,2,3 3 9.40 0.25 7.05
Grid A & C 2 3.20 0.25 1.60
Grid B 1 5.40 0.25 1.35
Partition Wall
Partition Wall for disable toilet 2 3.27 0.25 1.64
Partition wall for toilet short wall 2 1.32 0.25 0.66
Partition wall for toilet long wall 2 2.50 0.25 1.25
Sill Bands
Ground floor level
Grid 1,2,3 3 9.40 0.15 4.23
Grid A & C 2 3.20 0.15 0.96
Grid B 1 5.40 0.15 0.81
Partition Wall
Partition Wall for disable toilet 2 3.27 0.15 0.98
Partition wall for toilet short wall 2 1.32 0.15 0.40
Partition wall for toilet long wall 2 2.50 0.15 0.75
Along the incinerator 3 1.95 0.08 0.44
Deduction of Doors For Sill
Ground floor level
D1 -2 1.00 0.08 -0.15
D2 -2 0.90 0.08 -0.14
D3 -4 0.75 0.08 -0.23
Along the water trough
Along the water trough 2 3.75 0.60 4.50
Water trough edge 2 3.75 0.50 3.75
at both end 2 0.48 0.50 0.48
at Center 1 0.50 0.50 0.25

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
Incinerators Slab 1 0.53 0.90 0.47
1 2.70 0.08 0.20
Septic Tank
At Bottom 1 17.10 0.15 2.57
Concealed Beam CB1 1 1.95 0.49 0.96
Concealed Beam CB 1 2.25 0.24 0.54
Top Cover 1 5.75 1.95 11.21
1 15.40 0.12 1.85
Deduction of Manhole -2 2.40 0.12 -0.58
Manhole Cover Slab 2 2.40 0.15 0.72
Manhole Cover Slab 1 3.00 0.15 0.45
Side Formwork for void 2 2.40 0.15 0.72
Soak Pit
RCC slab 1 4.15 Area 4.15
1 7.22 0.13 0.90
Manhole/Waste Chamber 0.00
Top Cover 4 4.00 0.15 2.40
Total 222.83 sq.m

3 BrickWorks
3.2 Brick Masonary Works (1:4 c/s)
Below Plinth tie beam
Grid 1,2,3 3 9.40 0.35 0.40 3.95
9.40 0.10 0.55 1.55
Grid A-12, B-12 & C-12 3 3.20 0.35 0.40 1.34
3.20 0.10 0.55 0.53
Grid B-23 1 2.20 0.35 0.40 0.31
2.20 0.10 0.55 0.12
Along the ramp 2 4.70 0.35 0.68 2.22

Brick Work above Tie Beam


Ground floor
Grid A-12, B-12& C-12 3 3.20 0.23 2.40 5.30
Grid B-23 1 2.20 0.23 2.35 1.19
Grid 1&2 2 9.40 0.23 2.40 10.38
Grid 3 1 9.40 0.23 1.30 2.81
Partition Wall for disable toilet 2 3.27 0.23 2.80 4.21
Cross wall at Water trough 2 0.58 0.23 0.30 0.08
2 0.58 0.23 0.45 0.12
Drain 1 11.45 0.25 0.20 0.57
Outer Steps 2 1.20 0.60 0.15 0.22
2 1.20 0.30 0.15 0.11
Deduction for doors and windows
Ground floor
D1 -2 1.00 0.23 2.10 -0.97
D2 -2 0.90 0.23 2.10 -0.87
V1 -2 3.48 0.23 0.38 -0.60
V2 -2 3.48 0.23 0.33 -0.52
V3 -2 1.98 0.23 0.38 -0.34
V4 -2 1.98 0.23 0.33 -0.30
Incinerators 2 0.65 0.23 0.30 0.09
1 0.65 0.23 0.30 0.04
Septic Tank
Outer Wall 2 6.00 0.38 2.72 12.23
1 1.20 0.38 2.72 1.24

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
1 1.20 0.38 1.70 0.78
1 1.20 0.25 1.02 0.31
2 0.50 0.25 1.02 0.26
Baffle wall 1 1.20 0.25 2.72 0.82
Deduct openings -1 1.20 0.25 0.57 -0.17
Soak Pit 1 1.14 Area 0.55 0.63
Total 47.63 Cu.m.

3.3 Half Brick Work (1:4 c/s)


Toilet Room
Partition wall for toilet short wall 2 1.32 2.80 3.70
Partition wall for toilet long wall 2 2.50 2.80 14.00
Low wall Beside Urinal 2 0.60 1.20 1.44
Cross wall at Water trough 2 0.30 0.60 0.36
Incinerators 1 1.95 1.20 2.34
Drain 1 11.45 0.20 2.29
Deduction for doors and windows
D3 -4 0.75 2.10 -6.30
Septic Tank
Inlet wall 1 0.70 1.17 0.82
Manhole Cover wall 2 1.20 0.35 0.84
Manhole/Waste Chamber
Rectangular 4 4.00 0.60 9.60
Total 29.08 Sq.m.

3.4 Honey Comb Brick (350 mm) Works (1:3c/s)


Soak pit 1 1.14 Area 1.40 1.59
Total 1.59 Cu.m.

4 DOORS & WINDOWS WORKS


4.4 UPVC Doors
D1 2 0.98 2.09 4.10
D2 2 0.86 2.09 3.59
D3 4 0.73 2.09 6.10
Total 13.79 sq.m

4.5 Window Grill


Ventilation
Ventilation V1 2 2.48 0.38 1.86
Ventilation V2 2 2.48 0.33 1.61
Ventilation V3 2 1.98 0.38 1.48
Ventilation V4 2 1.98 0.33 1.28
Total 6.23 sq.m

5 FLOORING WORKS
5.1 Hard Concrete Flooring (40mm) With Neat Cement
Punning
Toilet Floors 2 4.75 3.25 30.88
Corridor Floors 2 4.75 1.27 12.07
Outside Staircase 2 1.20 1.05 2.52
Ramp
Slanted Portion 1 5.45 1.03 5.59
Horizontal Portion 1 1.20 1.03 1.23
Drain 1 11.45 1.48 16.95
Along the terrace 2 4.75 2.25 21.38
Water Trough 2 0.60 3.75 4.50

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
Total 95.10 sq.m

5.2 Cement Finishing Skirting works


Along the corridor and ramp 2 13.70 27.40
Deduction -2 1.90 -3.80
Total 23.60 r.m

5.3 Terrazo cast in Situ Dado (Tile works)


Along grid 1 2 4.84 1.20 11.62
Along grid 2 2 4.84 1.20 11.62
Deduction
D1 -2 0.98 1.20 -2.35
D2 -2 0.86 1.20 -2.06
Along grid A 1 3.34 1.20 4.01
Along grid B 2 3.34 1.20 8.02
Along grid C 1 3.34 1.20 4.01
Partition Wall for disable toilet 2 3.27 1.20 7.85
Partition wall for toilet short wall 4 1.32 1.20 6.34
Partition wall for toilet long wall 2 2.50 1.20 6.00
Urinal 4 1.30 1.20 6.24
Deduction
D3 -4 0.73 1.20 -3.50
Water trough 2 1.83 0.90 3.29
2 1.83 0.75 2.74
Total 63.79 sq.m

6 ROOFING/TERRACING WORKS
6.1 Metal Works
Truss 1 999.81
Total 999.81 kgs

6.2 CGI Sheet Roofing


Sheet Area 1 12.10 2.13 25.77
Sheet Area 1 12.10 2.74 33.15
Total 58.93 sq.m

6.3 CGI Sheet Roofing Ridge


Top Ridge cover 1 12.00 12.00
Total 12.00 r.m

6.4 GI facia (Eaves) Volume Density


Front and back sides 2 0.006 7850 98.78
Sides 4 0.001 7850 44.74
Total 143.52 k.g

6.5 False Ceiling


Inside portion 1 9.40 3.20 30.08
Outside portion 1 12.10 0.79 9.55
2 4.87 0.90 8.77
Total 48.40 sq.m

7 PLASTERING WALL FINISHING WORKS


7.1.1 CEMENT PLASTER WORKS ON INNER WALL (1:6)
Grid 1 & Grid 2 2 9.40 1.20 22.56
Grid 2 1 9.40 2.40 22.56

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
Grid 3 1 9.40 1.50 14.10
Grid A-12, B-12& C-12 4 3.20 1.40 17.92
Grid B-23 2 2.20 2.55 11.22
Partition Wall for disable toilet 4 3.27 1.80 23.54
Partition wall for toilet short wall 4 1.32 1.80 9.50
Partition wall for toilet long wall 4 2.50 1.80 18.00
Cross wall at Water trough 4 0.58 0.30 0.69
4 0.58 0.45 1.04
4 0.30 0.58 0.69
Deduction
D1 -2 1.00 2.10 -2.10
D2 -2 0.90 2.10 -1.89
V1 -2 3.48 0.38 -1.30
V2 -2 3.48 0.33 -1.13
V3 -2 1.98 0.38 -0.74
V4 -2 1.98 0.33 -0.64
Total 134.02 Sq.m.

7.1.2 CEMENT PLASTER WORKS ON CEILING (1:4)


Main Beam
Grid 1 & Grid 2 2 9.50 0.45 8.55
Grid A-12, B-12& C-12 3 3.25 0.40 3.90
Slab
Corridor Slab 1 9.50 2.25 21.38
Column Copla 8 0.05 3.00 1.20
Total 35.03 Sq.m.

7.1.3 External Plaster


Grid 1 1 9.40 2.60 24.44
Grid 3 1 9.40 1.50 14.10
Grid A-12 & C-12 2 3.20 1.85 11.84
Plinth Beam
Grid 1 & Grid 3 2 9.40 0.45 8.46
Grid A-12 & C-12 2 3.20 0.45 2.88

Main Beam Outer


Grid 1 1 9.40 0.40 3.76
Grid 2 1 9.40 0.55 5.17
Grid 3 1 9.40 1.00 9.40
Grid A-12 & C-12 2 3.20 0.40 2.56
Grid A-23 & C-23 2 2.20 1.00 4.40
Grid B-23 1 2.20 0.85 1.87
Column Outer
Grid 1 2 0.60 3.00 3.60
1 0.30 3.00 0.90
Grid 2 3 0.60 3.00 5.40
Grid 3 2 0.90 3.00 5.40
1 0.30 3.00 0.90
Column Copla 12 0.07 3.00 1.26
Total 106.34 Sq.m.

7.1.4 Internal Plaster on Wall (1:4) with Cement Punning


Inside Septic Tank Wall 1.00 11.30 2.25 25.40
Inner Wall of manhole 2.00 2.40 0.23 1.09
Inner Wall of Inlet 1.00 2.25 0.69 1.55

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
1.00 0.75 1.02 0.77
Baffle wall 2.00 1.20 1.45 3.48

Sewer Manhole (Rectangular)


Inside Sewer Manhole 2.00 3.00 0.33 1.98
Sewer Manhole (Circular)
Inside Sewer Manhole 2.00 2.83 0.33 1.87
Total 36.14 sq.m

7.2 Painting Works


7.2.1 Distemper Paint
Total of Interior Wall Plaster 1 134.02 Area 134.02
Total of Ceiling Plaster 1 35.03 Area 35.03
False Ceiling 1 48.40 Area 48.40
Total 217.44 sq.m

7.2.2 Exterior Weather Coat Paint


Total of External Wall Beam and Column Plain Plaster 1 106.34 Area 106.34
Total 106.34 sq.m

7.2.3 Enamel Painting


ForVentilation Factor
V1 2 2.48 0.38 2.00 3.71
V2 2 2.48 0.33 2.00 3.22
V3 2 1.98 0.38 2.00 2.96
V4 2 1.98 0.33 2.00 2.57
Total 12.46 sq.m

8 Miscellaneous
8.2 Cement Board Wall
For Partition
Gabel wall 2 1.17 Area 2.34
Total 2.34 sq.m

8.4 Pump Shed


1 1.00 1.00
Total 1.00 Nos.

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha

Length Breadth Height Quantity


S.N Material Description Nos. Quantity Units kg/unit
(m) (m) (m) (kg)
1 Truss
10mm thick plate Base Plate 12 0.3 0.3 0.01 0.011 cu.m. 7,850.00 84.78
10mm thick plate Truss stiffener 12 0.3 0.05 0.01 0.002 cu.m. 7,850.00 14.13
10mm thick plate 12 0.3 0.0865 0.01 0.003 cu.m. 7,850.00 24.44
10mm thick plate 12 0.05 0.085 0.01 0.001 cu.m. 7,850.00 4.00

16mm dia rod Anchor bolt 24 0.45 10.800 r.m. 1.58 17.07
16mm dia nut nut 24 24.000 no. 0.03 0.75

NB 40(M) Bottom Chord 5 3.9 19.500 r.m. 3.61 70.40


NB 40(M) Verticle Struts 5 0.561 2.805 r.m. 3.61 10.13
NB 40(M) Runner 1 10 10.000 r.m. 3.61 36.10

NB 50(M) Top Chord 5 2.036 10.180 r.m. 5.10 51.92


NB 50(M) 5 2.629 13.145 r.m. 5.10 67.04

NB 32(M) Inclined Struts 10 0.912 9.120 r.m. 3.15 28.73

NB65 (M) Purlins 6 10.1 60.600 r.m. 6.53 395.72

10mm thick plate Top chord cleat 30 0.2 0.09 0.01 0.005 cu.m. 7,850.00 42.39
10mm thick plate Purlin Cleat 60 0.2 0.09 0.01 0.011 cu.m. 7,850.00 84.78

10mm dia nut bolt (50mm) nut bolt 60 60.000 no. 0.05 2.91

10mm thick plate Runner plate 16 0.175 0.07 0.01 0.002 cu.m. 7,850.00 15.39
10mm thick plate Runner box 32 0.175 0.07 0.01 0.004 cu.m. 7,850.00 30.77
10mm thick plate 32 0.08 0.07 0.01 0.002 cu.m. 7,850.00 14.07

16mm dia nut bolt (50mm) Runner box 32 32.000 no. 0.13 4.30

Total Truss 999.81

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
BAR BENDING SCHEDULE
Piece
Dia. Spacing Wt./m Total Wt.
SN Description Bar Shape Nos. Length Weight (Kg) Remarks
(mm) (mm) (Kg) (Kg)
(m)

0.9
1 F1 Footing: Main bars 12 150 0.888 7 1.06 6.59
0.08

0.9
Distribution bars 12 150 0.888 7 1.06 6.59
0.08

for One footing = 13.18


for Nine footings = 118.60
2 Column C1, (300*300mm) (9 Columns)
0.42
Ld= d*60, Top= (Ld+10
Main Bars 12 0.888 8 5.12 36.34 327.03
(0.27+0.55+0.45+2.975) dia.)
0.06+0.39

0.22 0.08
100 &
Stirrups 8 0.395 30 1.04 12.32 110.92 Total height
150
0.22 for Stirrups= 3.25
0.15 0.08 & Ht. for 150 1.65
100 & spacing=
8 0.395 30 0.76 9.01 81.05
150
0.15
0.08 3 Nos. in
U shaped Stirrups & ties (total) 8 each 0.395 9 1.20 4.27 38.39
0.22
member
for One Column = 61.93
for Nine Columns = 557.40
3 Foundation Beams, 250*250

Main Bars (Long side beams); Along 10.0+0.3-2(0.06)


0.6 12 0.888 6 12.10 64.47 193.41 3 beams 1 Lap
Grid 1-1, 2-2, 3-3

0.15 0.08
100 &
Stirrups (for 250*250) 8 0.395 203 0.76 61.04 61.04 5 Stretches
150
0.15

0.15 0.08
8 150 0.395 32 0.76 9.71 9.71 1 Stretch (Section 2)
0.15

Main Bars (Short side beam); Along


0.6 6.0+0.3-2(0.06) 12 0.888 6 7.38 39.32 39.32 1 beam
Grid B-B

0.15 0.08
100 &
Stirrups (for 250*250) 8 0.395 48 0.76 14.41 14.41
150
0.15

Main Bars (Short side beams); Along


0.6 3.5+0.3-2(0.06) 12 0.888 6 4.88 26.00 52.00 2 beams
Grid A-A, C-C [Stretch 1-2]

0.15 0.08
100 &
Stirrups (for 250*250) 8 0.395 28 0.76 8.46 16.91
150
0.15

Main Bars (Short side beam); Along


2.5+0.3-2(0.06) 16 1.580 4 4.44 28.06 56.12 2 beams
Grid A-A, C-C [Stretch 2-3] 0.88

0.6 2.5+0.3-2(0.06) 12 0.888 2 3.88 6.89 13.78 2 beams

0.40 0.08
100 &
Stirrups (for 250*501) 8 0.395 20 1.26 9.87 19.74
150
0.15

4 Tie Beams, 250*300mm

Main Bars (Long side beams); Along 10.0+0.3-2(0.06)


0.6 12 0.888 6 12.10 64.47 193.41 3 beams 1 Lap
Grid 1-1, 2-2, 3-3

0.25 0.08
100 &
Stirrups (for 250*300) 8 0.395 203 1.06 85.14 85.14 5 Stretches
150
0.20

0.25 0.08
8 150 0.395 32 1.06 13.54 13.54 1 Stretch (Section 2)
0.20

Approved By:
Submitted By: Checked By: DLPIU Engineer
Sharma-AM J/V Consultant SE
Main Bars (Short side beam); Along
0.6 6.0+0.3-2(0.06) 12 0.888 6 7.38 39.32 39.32 1 beam
Grid B-B

0.25 0.08
100 &
Stirrups (for 250*300) 8 0.395 48 1.06 20.10 20.10
150
0.20

Main Bars (Short side beams); Along


0.6 3.5+0.3-2(0.062) 12 0.888 6 4.88 25.98 51.96 2 beams
Grid A-A, C-C [Stretch 1-2]

0.25 0.08
100 &
Stirrups (for 250*300) 8 0.395 28 1.06 11.79 23.59
150
0.20
Main Beams:
5 Long Beams: 250*450

Bottom Bars (Long side); Along 10.0+0.3-2(0.06)


0.4+0.2 12 0.888 2 12.10 21.49 64.47 3 beams 1 Lap
Grid 1-1, 2-2, 3-3

10.0+0.3-2(0.06)
0.4+0.48 16 1.580 2 12.90 40.76 122.29 1 Lap

0.88
Top Bars 10.0+0.3-2(0.06) 16 1.580 3 12.90 61.15 183.44 1 Lap

0.40 0.08
100 &
Stirrups (for 250*450) 8 0.395 244 1.36 131.08 131.08 6 Stretches
150
0.20
Short side beams:

6.0+0.3-2(0.06)
Bottom Bars 0.4+0.2 12 0.888 4 7.38 26.21 78.64 3 beams

0.6
Top Bars 6.0+0.3-2(0.062) 12 0.888 3 7.38 19.66 58.98

0.40 0.08
Stirrups (for 250*450) 8 100 0.395 23 1.36 12.36 37.07
0.20

0.35 0.08
100 &
Stirrups (for 250*400) 8 0.395 28 1.26 14.02 42.06
150
0.20

0.86
6 SLAB: Short Span 0.11 2.71 10 150 0.617 65 4.65 186.49 186.49 65

1.48
Long Span 10.21 10 300 0.617 9 13.95 77.46 77.46 1 Lapping 9
0.09

1.48
1 Lapping, & Cranked
10.21 10 300 0.617 9 14.17 78.69 78.69
0.09 over middle beam

3.25
Top Extra (Negative) Bar 8 300 0.395 9 3.25 11.55 11.55

10.21
Distribution Bar, Long Span 8 150 0.395 10 10.21 41.40 41.40

2.71
Distribution Bar, Short Span 8 150 0.395 41 2.71 43.53 43.53

Grand Total 2736.63 Kg


Grand Total 2.74 Mt.

Approved By:
Submitted By: Checked By: DLPIU Engineer
Sharma-AM J/V Consultant SE
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Dharmawati SS
Location : Choprak,Gorkha
Reinforcement of Septic and Soak pit tank
Total Total
S. No Item Description Dia Lot No length m wt/m Remarks
length Quantity
1 Septic tank
Beam
Long span

16 2 2 8.34 33.36 1.58 52.71


695 6950 695

12 2 1 7.78 15.56 0.89 13.82


415 6950 415

85 85 16 2 2 7.12 28.48 1.58 45.00


6950

85 85 12 2 1 7.12 14.24 0.89 12.65


6950
200

8 2 70 1.06 148.40 0.40 58.62


80
250

short span

16 1 2 5.79 11.58 1.58 18.30


695 4400 695

12 1 1 5.23 5.23 0.89 4.64


415 4400 415

85 85 16 2 2 4.57 18.28 1.58 28.88


4400

85 85 12 2 1 4.57 9.14 0.89 8.12

4400
200

8 1 45 1.06 47.70 0.40 18.84


80
250

slab
Along Y axis

110 8 1 45 5.12 230.40 0.40 91.01 Main Bar


5010

distribution bar 8 2 13 4.91 127.66 0.40 50.43


negetive bar 8 1 47 5.06 237.82 0.40 93.94
along X axis

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
1915
110 8 1 34 9.03 306.85 0.40 121.21 Main Bar
7000

distribution bar 8 2 10 7.00 140.00 0.40 55.30


Corner bars 10 12 3 0.60 21.60 0.62 13.33
Concealed beam
main bars 10 2 4 6.60 52.80 0.62 32.58
stirrups 8 2 41 0.56 45.92 0.40 18.14
Steps at septic tank 16 2 5 0.60 6.00 1.58 9.48
2 Soak pit
Beam 16 1 4 12.74 50.94 1.58 80.49
12 1 2 12.50 24.99 0.89 22.19
Slab 8 1 2 1.17 2.33 0.40 0.92
8 1 2 1.80 3.60 0.40 1.42
8 1 2 2.23 4.45 0.40 1.76
8 1 2 2.55 5.09 0.40 2.01
8 1 2 2.80 5.60 0.40 2.21
8 1 2 3.00 6.00 0.40 2.37
8 1 2 3.16 6.32 0.40 2.50
8 1 2 3.28 6.56 0.40 2.59
8 1 2 3.38 6.76 0.40 2.67
8 1 4 1.35 5.40 0.40 2.13
8 1 4 1.37 5.47 0.40 2.16
8 1 4 1.38 5.50 0.40 2.17
negetive bar 8 1 23 0.60 13.80 0.40 5.45
distribution bar 8 1 4 10.99 43.96 0.40 17.36
Total 897.38 Kg
Grand Total 0.90 Mt.

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Tc(S)
School Name : Shree Dharmawati Secondary School
Location : Choprak,Gorkha

Total
S. No. Description Tc(S) Unit Remarks
Quantity
A. Common Installation
1.2 Stand Alone 6 A DP MCB with Enclosure 2 2.00 nos.
B School Blocks
1 DISTRIBUTION BOARDS
1.5 6A DP MCB with Enclosure 2.00 2.00 nos.
3 General Service Light Point Wiring
3.1 One Way Light Point 11 11.00 pts.
3.3 Ceiling and Exhaust Fan Point 4 4.00 pts.
6 Sweep Ceiling/ Exhaust Fan/Wall Fan
6.2 225mm dia M/D exhaust Fan 4 4.00 nos.
7 Light Fixtures/Luminaires & Accessories
7.6 LED Wall Light 2 2.00 nos.
7.7 9 W LED Surface Mounted Cylindrical type 2 2.00 nos.
7.8 6 W LED Recessed Circular type 6 6.00 nos.
7.9 7 W LED T5 Slim Mirror Light 2 2.00 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Dharmawati Secondary School
Location : Choprak,Gorkha
Length
S. No. Description No. Quantity Unit Remarks
(m)
1 WATER SUPPLY INSTALLATION
a CPVC pipes SDR-11
40 mm 1 185 185.00 r.m
20mm 1 29 29.00 r.m
15mm 1 7.5 7.50 r.m
c CPVC Ball Valve
40 mm 3 3.00 nos.
25 mm 2 2.00 nos.
20mm 2 2.00 nos.
d 40mm dia Gun Metal Check Valve 1 1.00 nos.
e Electrical Centrifugal Water Pump 1 1.00 nos.
f 2000 litres Capacity Water Storage Tank 1 1.00 nos.
2 Sewer, Rain and Waste Water Installation
110 mm 1 41 41.00 r.m
75mm 1 70 70.00 r.m
50mm 1 21 21.00 r.m
B School Blocks
1 Sanitary Installation
a Lab Sink 5 5.00 set
b Kitchen Sink 1 1.00 set
c PVC Multi Floor Trap 2 2.00 nos.
2 Sanitary Installation
a Water Closet Set 2 2.00 set
b Orissa Pan 4 4.00 set
c Hand Wash Basin 2 2.00 set
d Ladies Urinal 2 2.00 set
e Self Closing Bib Cock 12 12.00 nos.
f CP Spreader in Urinal 4 4.00 set
g Toilet Paper Holder 2 2.00 nos.
h Commode Spray 2 2.00 nos.
i PVC Multi Floor Trap 10 10.00 nos.
j Waste Coupling and PVC Bottle Trap 4 4.00 nos.
k 40mm SS Grab Bar-Side 2 2.00 nos.
l 40mm SS Grab Bar-Rear 2 2.00 nos.
m CP Foldable Hinge 4 4.00 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job: Site Development
School Name : Shree Dharmawati Secondary School
Location : Choprak,Gorkha

Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)
1 Site Clearance
Column 2 0.90 0.90 1.62
Concrete Pavement
Infront of 3-9C(SF) 1 17.00 3.30 56.10
1 7.00 2.50 17.50
Side of 3-9C(SF) 1 6.50 2.00 13.00
Infront of 3LaLiEACCr(F)-A 1 20.00 3.20 64.00
1 6.70 1.50 10.05
Infront of Toilet 1 11.00 1.50 16.50
Side of Toilet 1 7.40 1.70 12.58
1 7.50 4.50 33.75
In Betn Toilet and 3LaLiEACCr(F)-A 1 4.30 5.50 23.65
In Betn Two Bldgs 1 4.20 6.50 27.30
At Gate 1 15.00 4.00 60.00
Retaining wall
For 2.5m height 1.00 56.00 2.20 123.20
1.00 18.50 2.20 40.70
Total 499.95 sq.m

2 Earth Work Excavation


Concrete Pavement
Infront of 3-9C(SF) 1 17.00 3.30 0.15 8.42
1 7.00 2.50 0.15 2.63
Side of 3-9C(SF) 1 6.50 2.00 0.15 1.95
Infront of 3LaLiEACCr(F)-A 1 20.00 3.20 0.15 9.60
1 6.70 1.50 0.15 1.51
Infront of Toilet 1 11.00 1.50 0.15 2.48
Side of Toilet 1 7.40 1.70 0.15 1.89
1 7.50 4.50 0.15 5.06
In Betn Toilet and 3LaLiEACCr(F)-A 1 4.30 5.50 0.15 3.55
In Betn Two Bldgs 1 4.20 6.50 0.15 4.10
At Gate 1 15.00 4.00 0.15 9.00

Excavation For Boundary Wall


Chain Link Fence 98 0.15 0.15 0.60 1.32
Excavation For Gate Column
Column 2 1.20 1.20 1.50 4.32
Excavation For Flag Pole
Flag Pole 2 0.60 0.60 1.00 0.72
2 1.10 0.50 0.15 0.17
2 1.60 0.25 0.15 0.12
1 0.60 0.40 0.15 0.04
Retaining wall
For 2.5m height 1.00 56.00 1.90 2.70 287.28
1.00 18.50 1.90 2.70 94.91
Total 439.03 cu.m

3 Earth Back Filling


Total Excavation (Retaining Wall) 1.00 439.03 382.19
For Retaining wall

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)
For 2.5m height
Deduction
Soling -1.00 14.90 Volume -14.90
PCC -1.00 14.90 Volume -14.90
Stone Masonary -1.00 254.05 Volume -254.05
Total 98.34 cu.m

4 Boulder Soling
Concrete Pavement
Infront of 3-9C(SF) 1 17.00 3.30 0.15 8.42
1 7.00 2.50 0.15 2.63
Side of 3-9C(SF) 1 6.50 2.00 0.15 1.95
Infront of 3LaLiEACCr(F)-A 1 20.00 3.20 0.15 9.60
1 6.70 1.50 0.15 1.51
Infront of Toilet 1 11.00 1.50 0.15 2.48
Side of Toilet 1 7.40 1.70 0.15 1.89
1 7.50 4.50 0.15 5.06
In Betn Toilet and 3LaLiEACCr(F)-A 1 4.30 5.50 0.15 3.55
In Betn Two Bldgs 1 4.20 6.50 0.15 4.10
At Gate 1 15.00 4.00 0.15 9.00

Column 2 0.90 0.90 0.20 0.32


Stone Soling for Flag Pole 1 0.70 0.80 0.35 0.20

For Retaining wall


For 2.5m height 1.00 56.00 2.00 0.10 11.20
1.00 18.50 2.00 0.10 3.70
Total 65.58 cu.m
5 P.C.C.(1:3:6) Works
PCC For Gate Column
Column 2 0.90 0.90 0.08 0.12
PCC For Flag Pole
Flag Pole 2 0.30 0.30 1.20 0.22
1 2.40 0.80 0.10 0.19
2 0.30 0.30 0.08 0.01

For Retaining wall


For 2.5m height 1 56.00 2.00 0.10 11.20
1 18.50 2.00 0.10 3.70
Total 15.44 cu.m
6 P.C.C.(1:2:4) Works
Concrete Pavement
Infront of 3-9C(SF) 1 17.00 3.30 0.08 4.21
1 7.00 2.50 0.08 1.31
Side of 3-9C(SF) 1 6.50 2.00 0.08 0.98
Infront of 3LaLiEACCr(F)-A 1 20.00 3.20 0.08 4.80
1 6.70 1.50 0.08 0.75
Infront of Toilet 1 11.00 1.50 0.08 1.24
Side of Toilet 1 7.40 1.70 0.08 0.94
1 7.50 4.50 0.08 2.53
In Betn Toilet and 3LaLiEACCr(F)-A 1 4.30 5.50 0.08 1.77
In Betn Two Bldgs 1 4.20 6.50 0.08 2.05
At Gate 1 15.00 4.00 0.08 4.50

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)
PCC Works For Stone Masonry Wall At
1.00 56.00
Top 0.45 0.10 2.52
1.00 18.50 0.45 0.10 0.83
Total 28.43 cu.m

7 P.C.C For R.C.C. Works


R.C.C. Works M20
A Foundation
Gate Column Footing
Footing 2 0.90 0.90 0.25 0.41

B Column
Gate Column 2 0.30 0.30 2.95 0.53
Top RCC Coping 2 0.59 0.59 0.05 0.03
2 0.175 0.05 0.02
Total 0.99 cu.m

8 Steel Reinforcement
For gate 1 106.90 106.9
Total 106.90 Kg
0.11 Tons

9 Silica Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10.00 0.98831 9.88
Total 9.88 Kg

10 Formworks
A Entrance Gate-Foundation 2 3.60 0.35 2.52
Gate Column 2 1.20 3.15 7.56
Flag Pole Steps 2 0.25 0.80 0.4
Flag Pole Masonry Top Surface 1 1.70 0.50 0.85
Total 11.33 sq.m

12 Full Brick (230 mm) Works (1:4c/s)


Gate Column 2 0.54 0.23 1.85 0.46
2 0.30 0.23 0.45 0.06
Flag Pole Base 2 0.80 0.23 0.55 0.20
Total 0.72 cu.m

13 Neat Cement Skirting works


Gate Column 2 2.20 4.40
Total 4.40 r.m

14 Metal Works (Fence)


Total
Description Nos length Kg/m Total
Length
Chain Link Fence
ISA 40x40x4mm 2 245 490.00 2.40 1,176.00
ISA 50x50x5mm 98 1.90 186.20 3.80 707.56
Bracing ISA 50x50x5mm 13 2.00 26.00 3.80 98.80
Incinerator Vent Pipe 1 2.416 17.5 42.28 M=17.5 Kg/m
Total 2,024.64 k.g

15 Metal work (Entrance Gate)


Metal Gate
50mm Dia MS Pipe 2 7.13 14.26 3.61 51.48

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)
25mm Dia MS Pipe 56 0.7 39.2 1.58 61.94
Middle sheet 1 0.74 0.0012 7850 6.97
Hole Fast 4 0.45 1.8 3.61 2.92
Total 123.31 k.g

16 Chain Link Fence(50x50 Mesh)


Fencing 1.00 245 1.20 294.00
Total 294.00 sq.m

17 External Plaster
Column Inside face 4 0.54 1.64 3.54
Column Outside face 2 1.2 0.20 0.48
4 0.54 1.70 3.67
Deduct -2 0.3 1.40 -0.84
Top Coping 2 2.36 0.05 0.24
4 0.59 0.30 0.71
Total 7.80 sq.m

18 Exterior Weather Coat Paint


As per Outside Plaster 1 7.8 7.80
Gate Column Skirting 2 2.36 0.10 0.47
Total 8.27 sq.m

19 Flag Pole
75 Dia GI Pipe 2.00 1 2.00
Total 2.00 nos

20 Stone Masonry Wall Works


For 2.5m high 1.00 56.00 1.10 3.10 190.96
1.00 18.50 1.10 3.10 63.09
Total 254.05 cu.m

21 50mm dia PVC weep Pipe


Retaining wall
For 2.5m high 76 0.90 67.95
76 1.30 98.15
Total 166.10 r.m

22 Geotextile
Retaining wall
For 2.5m high 1 56.00 2.00 112.00
1 18.50 2.00 37.00
Total 149.00 Sq.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Site Development
School Name : Shree Dharmawati Secondary School
Location : Choprak,Gorkha

Size Spacing c/c Structure Rebar Length/pc. Total Weight Per Total Weight
SN Description Shape Remarks
(mm) (mm) Nos Nos (mm) Length (m) Meter (Kg) (Kg)

1 Entrance Gate-Column
75 75
a 900*900 Foundation Mesh 850 10 150 2 12 1000 24 0.62 14.82

b 8-12 dia Column Reinforcement 12 2 8 3770 60.32 0.89 53.62


3050+Ld

220
8 mm dia at 150 c/c for column
c 7
220 8 150 2 26 1030 53.56 0.40 21.16
stirrups-Outer 5

1
7
7 3
8 mm dia at 150 c/c for column 5
d 8 150 2 26 842 43.784 0.40 17.3
stirrups-Outer

Total of Reinforcement Work 106.90 Kg


0.11 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job : Reservoir Water Tank
School Name : Shree Dharmawati Secondary School
Location : Choprak,Gorkha

Description Length Breadth Height


S. No. No. Quantity Unit Remarks
(m) (m) (m)
1 Earthworks
1.1 Site Clearance & Mobilization
For Water Tank 1 4.85 4.6 22.31
Total 22.31 sq.m

1.2 Earthwork in excavation


For Water Tank 1 3.65 3.40 1.98 24.57
Total 24.57 Cu.m.

1.3 Earthback Filling


Total Earthwork Excavated 24.57
Water Tank Volume -1 3.35 3.1 1.98 -20.56
Total 4.01 Cu.m.

1.4 Boulder soling


Below Water Tank 1 3.35 3.1 0.2 2.077
Total 2.08 Cu.m.
2 Concrete Works
2.1 PCC
2.1.1 PCC Work (1:3:6)
Below Water Tank 1 3.35 3.1 0.075 0.78
Total 0.78 Cu.m.

2.2 PCC for RCC Work 1:1.5:3


For Base Slab 1 3.35 3.10 0.18 1.82
For Water Tank Wall
Long Wall 2 3.35 0.18 1.68 1.96
Short Wall 2 2.75 0.18 1.68 1.61
Trianagle Portion
Long Wall 2 3.00 0.05 Area 0.27
Short Wall 2 2.75 0.05 Area 0.25
Slab 1 3.35 3.1 0.15 1.56
Manhole openings -1 0.6 0.6 0.15 -0.05
Total 7.41 Cu.m.

2.3 Silica Admixture


10 Kg per cu.m. of R.C.C. M20 10 7.41 74.15
Total 74.15 kg

2.5 Form works


For Base Slab 1 12.9 0.18 2.26
For Water Tank Wall
Outer Side
Long Wall 2 3.35 1.83 12.23 23.18

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Description Length Breadth Height
S. No. No. Quantity Unit Remarks
(m) (m) (m)
Short Wall 2 3.00 1.83 10.95
Inside wall
Long Wall 2 3.00 1.53 9.15
Short Wall 2 2.75 1.53 8.39
Trianagle Portion
Long Wall 2 3.00 0.30 1.80
Short Wall 2 2.75 0.30 1.65
Slab 1 3 2.75 8.25
Side for Manhole openings 1 2.4 0.15 0.36
Deduct Manhole openings -1 0.6 0.60 -0.36
Total 54.67 Sq.m.

3 PLASTERING WALL FINISHING WORKS


3.1.1 CEMENT PLASTER WORKS WITH PUNNING
Base Slab 1 2.30 2.13 4.90
For Water Tank Wall
Long Wall 2 3.05 1.37 8.36
Short Wall 2 2.78 1.37 7.62
Triangle Portion
Long Wall 2 3.00 0.42 2.54
Short Wall 2 2.78 0.42 2.36
Top Slab 1 3.00 2.75 8.25
Deduct Manhole openings -1 0.6 0.60 -0.36
Total 33.66 Sq.m.

4 Water Proof Coating


Inside Water tank 1 33.66
Total 33.66 sq.m

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job : Reservoir Water Tank
School Name : Shree Dharmawati Secondary School
Location : Choprak,Gorkha
Bar Bending Schedule
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)
A Outer Vertical Bars 1
1 Shorter Span 10 33 7.01 231.33 0.62 143.42 0.083 0.083

1.915 1.915

3.02

2 Longer span 10 28 7.286 204.008 0.62 126.48


0.083 0.083

1.915 1.915

3.29

B Inner Vertical Bars 2


1 Shorter Span 10 33 2.503 165.198 0.62 102.4228 0.079 0.079

1.884 1.884

0.05
0.49 0.49

2 Longer Span 10 28 2.503 170.204 0.62 105.5265 0.079 0.079

1.884 1.884

0.05
0.49 0.49

C. Extra Bars 2 10 62 1.79 221.96 0.62 137.62 0.6 0.6

0.592
0.592 0.6 0.6

D. Horizontal Bars(outer 4
0.3 0.3
1 Shorter Span 10 20 3.62 289.6 0.62 179.552

3.02 3.02

0.3 0.3

2 Longer Span 10 20 3.87 309.6 0.62 191.952 0.3 0.3

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)

3.27 3.27

0.3 0.3
E. Base Slab bar 4
1 Shorter Span 10 32 3.14 401.92 0.62 249.19 3.045
0.05 0.05

2 Longer Span 10 28 3.42 383.04 0.62 237.48 3.32


0.05 0.05
1473.65 Kg
1.47 Mt.

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer