Professional Documents
Culture Documents
Entitled as
STRUCTURAL ANALYSIS
Submitted by:
De Guzman, Ave C.
Tuazon, Christine S.
Submitted to:
1.1 Introduction
Each community aims to reach a sustainable progress in which innovation and modernization is
being utilized. Together with this progress comes the demand in various aspects such as the need of
manpower. Basically, the level of economic development of a country or community is directly depending
opportunities. They improve mobility, efficiency and productivity of labor. Moreover, larger investment,
The proposed project is categorized as a four-storey office building. The structure will be a gateway
for job opportunities in the developing community of the location. This infrastructure will be significant for
those who are seeking job inside their community. The structure is also classified under the occupancy
square meters with dimensions 22 meters by 26 meters. The basic floor area of the building is 400 square
The building will consist of four levels namely, ground floor, second floor, third floor and fourth floor with an
FLOOR
DESCRIPTION NO. OF ROOMS AREA (m2)
LEVEL
RESTROOM 1 19.25
FIRST FLOOR
CAFETERIA 1 50.1
CHAPEL 1 17.5
LOCKER ROOM 1 20
HR DEPARTMENT 1 39.05
PANTRY 1 25
RESTROOM 1 19.25
LOBBY 1 35
RESTROOM 1 19.25
MAIL AREA 1 12
LIBRARY 1 37
LAPTOP STATION 1 25
CLINIC 1 19.28
PANTRY 1 14.53
FOURTH
ACTIVITY/OPEN AREA 1 400
FLOOR
as the center of commercial industry and establishment of the MRT-7 bound to San Jose Del Monte to
North Avenue.
1. The project was designed in accordance to the National Structural Code of the Philippines
2. All architectural plans (floor plans and elevations) and structural plans (framing and load
3. Analysis using the two methods with the help of Microsoft Excel in solving for the unknowns.
2. Limited analysis of frames using Slope Deflection Method (SDM) with side sway and Moment
3. On the structural analysis, grid C and grid 3 are the frames to be examine
CHAPTER 2
DESIGN PLANS
CHAPTER 2
DESIGN PLANS
CHAPTER 3
DESIGN LOADS
Dead loads are gravity loads of constant magnitudes and fixed position that act permanently on the
structure. Such loads consist of self-weight of the structural system and of all material and equipment
permanently attached to the structural system.
The minimum design loads were selected based from the National Structural Code of the
Philippines (NSCP) 2015 Table 204-2. The values selected are associated based on our design structure.
The following
were the steps
used in determining
the design dead
loads:
PART I. Choosing of
Minimum
Design Dead Loads
1. We select
the values of
minimum design dead loads on Table 204-2 in NSCP 2015 which corresponds to our design
structure. Select values for each corresponding components, ceilings, coverings (roof and wall),
floor and floor finishes and frame partitions.
2. Compute for the total dead load.
3. Determine the dimensions of each structural member; walls, beams, columns, and slabs.
kn
1. Determine the unit weight of the material used. γ concrete=23.6
m3
2. Compute for the weight of the structure by multiplying the dimension to the unit weight of concrete.
3. For each floor, calculate the sum of weight of slab and dead loads.
W dl +s=W dl + W s
Note: The weight of 2nd floor and 3rd floor is different from that of roof deck.
1. Based on the load distribution plan, you can already determine if it is one way or two-way slab.
wL
For two way slab, the triangular area has a formula of W dl +s= ( ¿ while for one way slab, use
3
the formula w(T w ¿ .
Note: Only the weight of slab plus dead load should be applied in the formula.
2. Compute for the total weight on the floor by using the formula:
W T =W beam+W wall +W dl+ s
3. Compute for both longitudinal and transverse frame separately.
The minimum design live loads were selected based from the National Structural Code of the
Philippines (NSCP) 2015 Table 205-1. The values selected are associated based on our design structure
which only includes residential with basic floor area and roof deck values only.
1. We select values of minimum design live loads on Table 205-1 in NSCP 2015 which corresponds
to our design structure.
PART II. Calculating the Total Weight in Each Floor Level
1. Based on the load distribution plan, you can already determine if it is one way or two-way slab.
wL
For two-way slab, the triangular area has a formula of W T = ( ¿ while for one-way slab, use the
3
formula W T = w(T w ¿ .
2. Compute for both longitudinal and transverse frame separately.
The magnitudes of wind loads that may act on a structure depends on the geographical location of
the structure, obstruction in its surrounding terrain, such as nearby buildings, and the geometry and the
vibrational characteristics of the structure itself.
The wind load calculation is based on NSCP 2015. Different parameters needed were based on
the tables and provided by the code. The values of wind loads for both transverse and longitudinal frames
are equal since the height and dimensions of the structure are the same.
SYMBOLS NOTATIONS
Q Velocity pressure (kpa)
kz Velocity pressure exposure coefficient at height z
k zt Topographic factor
kd Wind directionality factor (Table 207-A.6-1)
V Basic wind speed obtained (Table 207-A.5-1A,B&C) (kph)
Iw Importance factor
zg Nominal height of the atmospheric boundary layer (Table 207A.9-1)
α 3 second gust speed power law exponent (Table 207A.9-1)
Cp External pressure coefficient to be used in determination of wind loads of buildings
G Gust effect factor
GC p Product of external pressure and gust effect factor
GC pi Product of internal pressure coefficient and gust effect factor
z Height above ground level
The following are the design procedure in calculating the wind loads of the structure:
1. The basic wind speed V and wind directionality factor k d shall be determined in accordance with
Section 207A.5.1 and Table 207A.6 respectively.
Since the location is Bulacan, the corresponding basic wind speed was 260 kph. K d was
determined based on the type of structure which was Main Wind Force Resisting Sytem (MWFRS)
with a value of 0.85.
We then compute the value of k z in each floor level using the formula and condition below.
If z < 4.5m;
4.5 m α2
k Z =2.01( )
Zg
If 4.5m ≤ z ≤ Z g
z 2α
k Z =2.01( )
Zg
4. A topographic factor k zt shall be determined in accordance with Section 207A.8-1.
According to the code, the value of k zt is 1.0 for this type of building and its exposure type.
9. Velocity pressure q Z or q h as applicable shall be determined in accordance with Section 207B.3.2
The velocity pressure was computed using the formula below for each level.
10. Design with load p or F shall be determined in accordance with Section 207B.4
We then calculate the design pressure in each surface direction, namely, windward wall, leeward
wall and sidewall. The calculated P is in kPa for each floor level. For windward wall, the values in
each floor is different. For both leeward and sidewall, the value of P is the same all throughout the
floor levels.
p = q c GC p −q h GC pi
the last step is to calculate the design wind force, F in each floor level. The formula
to be used is:
The seismic loads on the structure during an earthquake result from inertia forces which were
created by ground accelerations. The magnitude of these loads is a function of the following factors: mass
of the building, dynamic properties of the building, the intensity, duration, and frequency content of the
ground motion, and soil-structure interaction.
The following were the steps used to determine the Earthquake Loads acting on the structure.
1. Get the area of each component i.e. structural members and rooms.
2. Get the total weight of each structural members by multiplying the dimensions, quantity and area
while for the rooms, multiply the area and SDL in each room.
3. Solve for the total weight in each floor by summation of all the component’s weights.
ANALYSIS
DEAD LOADS
Parameters
Cement tile 0.77
Gypsum sheathing, 13mm 0.10
Coverings, Roof and Wall
Fiberboard 0.0028
Bituminous, smooth surface 0.07
Floor Fills Lightweight concrete, per mm 0.015
S3.1
HR Department = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN Slab = (23.6) (0.4) = 9.44 KN
S3.1 = 43.22 KN
S3.2
Employee’s Lounge = (2.5) (2.4) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 15.39 KN
S3.2 = 29.92 KN
S3.3
Employee’s Lounge = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5 + 5) (0.1) = 1.34 KN Slab = (23.6) (0.4) = 9.44 KN
S3.3 = 42.84 KN
S3.4
Print and Copy Area = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
S3.4 = 43.67 KN
S3.5
HR Department = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5) (0.1) = 0.45 KN
S3.5 = 43.22KN
S3.6
Office Area = (2.5) (2.4) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 15.39 KN
S3.6 = 29.92 KN
S3.7
Office Area = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
S3.7 = 42.8 KN
S3.8
Office Area = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (5) (0.1) = 0.895 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN Slab = (23.6) (0.4) = 9.44 KN
S3.8 = 43.67 KN
Third Floor Transverse
Grid T3
T3.1
Clinic = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5) (0.1) = 0.45 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN Slab = (23.6) (0.4) = 9.44 KN
T3.1 = 43.22 KN
T3.2
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12
Small Meeting Place = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 15.39 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.9 + 2.5) (0.1) = 1.41 KN
Slab = (23.6) (0.4) = 9.44 KN
T3.2 = 30.36 KN
T3.3
Break Area = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5 + 5 + 2.5) (0.1) = 1.79 KN
Slab = (23.6) (0.4) = 9.44 KN
T3.3 = 43.29 KN
T3.4
Security Office = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (5) (0.1) = 0.895 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
Slab = (23.6) (0.4) = 9.44 KN
T3.4 = 43.67 KN
T3.5
Brainstorm Room = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5) (0.1) = 0.45 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN Slab = (23.6) (0.4) = 9.44 KN
T3.5 = 43.22 KN
T3.6
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12
Audio Visual Room = (2.5) (2.4) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 15.39 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.9) (0.1) = 0.97 KN
Slab = (23.6) (0.4) = 9.44 KN
T3.6 = 29.92 KN
T3.7
Office Area = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5 + 5) (0.1) = 1.34 KN
Slab = (23.6) (0.4) = 9.44 KN
T3.7 = 42.84 KN
T3.8
Audio Visual Room = (2.5) (5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (5) (0.1) = 0.895 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
Slab = (23.6) (0.4) = 9.44 KN
T3.8 = 43.67 KN
T4.2
Hallway = (5) (2.5) (0.015 + 0.77 + 0.07) = 10.7
T4.2 = 10.7 KN
T4.3
Hallway = (5) (2.5) (0.015 + 0.77) = 10.7
T4.3 = 10.7 KN
T4.4
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
Hallway = (5) (2.5) (0.015 + 0.77 + 0.07) = 10.7
T4.4 = 11.97 KN
T4.5
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
Slab = (23.6) (0.4) = 9.44 KN
Hallway = (5) (2.5) (0.015 + 0.77 + 0.07) = 10.7
T4.5 = 21.41 KN
T4.6
Hallway = (5) (2.5) (0.015 + 0.77 + 0.07) = 10.7
T4.6 = 10.7 KN
T4.7
Hallway = (5) (2.5) (0.015 + 0.77 + 0.07) = 10.7
T4.7 = 10.7 KN
T4.8
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
Hallway = (5) (2.5) (0.015 + 0.77 + 0.07) = 10.7
T4.8 = 11.97 KN
SC.1
Conference Room = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5) (0.1) = 0.45 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
Slab = (23.6) (0.4) = 9.44 KN
SC.1 = 43.22 KN
SC.2
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
Employee’s Lounge = (2.5) (2.9) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 18.60 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.5) (0.1) = 0.90 KN
Slab = (23.6) (0.4) = 9.44 KN
SC.2 = 33.06 KN
SC.3
Office Area = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.5) (0.1) =
0.90 KN
Slab = (23.6) (0.4) = 9.44 KN
SC.3 = 42.4 KN
SC.4
Assistance Office = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5) (0.1) = 0.45 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN Slab = (23.6) (0.4) = 9.44 KN
SC.4 = 43.22 KN
SC.6
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
Employee’s Lounge = (2.5) (2.9) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 18.60 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.5) (0.1) = 0.90 KN
Slab = (23.6) (0.4) = 9.44 KN
SC.6 = 33.06 KN
SC.7
Office Area = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.5) (0.1) = 0.90 KN
Slab = (23.6) (0.4) = 9.44 KN
SC.7 = 42.4 KN
SC.8
Office of CEO = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Slab = (23.6) (0.4) = 9.44 KN
SC.8 = 41.5 KN
TC.1
Library = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5) (0.1) = 0.45 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
Slab = (23.6) (0.4) = 9.44 KN
TC.1 = 43.22 KN
TC.2
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
Small Meeting Room = (2.5) (2.9) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 18.60 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.5) (0.1) = 0.90 KN
Slab = (23.6) (0.4) = 9.44 KN
TC.2 = 33.06 KN
TC.3
Audio Visual Room = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.5) (0.1) = 0.90 KN
Slab = (23.6) (0.4) = 9.44 KN
TC.3 = 42.4 KN
TC.4
Office Area = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5) (0.1) = 0.45 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
Slab = (23.6) (0.4) = 9.44 KN
TC.4 = 43.22 KN
TC.5
Library = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5) (0.1) = 0.45 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
Slab = (23.6) (0.4) = 9.44 KN
TC.5 = 43.22 KN
TC.6
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
Break Area = (2.5) (2.9) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 18.60 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.5) (0.1) = 0.90 KN
Slab = (23.6) (0.4) = 9.44 KN
TC.6= 33.06 KN
TC.7
Audio Visual Room = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Concrete Masonry Unit = (1.79) (2.5 + 2.5) (0.1) = 0.90 KN
Slab = (23.6) (0.4) = 9.44 KN
TC.7 = 42.4 KN
TC.8
Office Area = (5) (2.5) (0.77 + 0.10 + 0.015 + 0.77 + 0.53 + 0.38) = 32.06 KN
Slab = (23.6) (0.4) = 9.4
TC.8 = 41.5 KN
RC.2
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
RC.2 = 4.12 KN
RC.3
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
RC.3 = 4.12 KN
RC.4
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
RC.4 = 5.39 KN
RC.5
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
RC.5 = 5.39 KN
RC.6
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
RC.6= 4.12 KN
RC.7
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
RC.7 = 4.12 KN
RC.8
Hallway = (2.1) (2.5) (0.015 + 0.77) = 4.12 KN
Concrete Masonry Unit = (2.54) (2.5) (0.2) = 1.27 KN
RC.8 = 5.39 K
First Floor Transverse
3AB
F3.1 = 43.22 KN F3.5 = 43.22 KN
F3.1 + F3.5 = 43.22 + 43.22
= 86.44 KN / 5m
= 17.288 KN/m (triangular load) Convert to Uniform Load = 1/3 (5) (17.288)
= 29.8 KN/m
3BC
F3.2 = 29.92 KN F3.6 = 29.92 KN
F3.2 + F3.6 = 29.92 + 29.92
= 59.84 KN / 5m
= 11.968 KN/m (triangular load) Convert to Uniform Load = 1/3 (5) (11.968)
= 19.95 KN/m
3CD
F3.3 = 42.84 KN F3.7 = 42.84 KN
F3.3 + F3.7 = 42.84 + 42.84
= 85.68 KN / 5m
= 17.136 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (17.136)
= 28.56 KN/m
3DE
F3.4 = 43.74 KN F3.8 = 43.74 KN
F3.4 + F3.8 = 43.74 + 43.74
= 87.48 KN / 5m
= 17.496 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (17.496)
= 29.16 KN/m
3BC
S3.2 = 29.92 KN S3.6 = 29.92 KN
S3.2 + S3.6 = 29.92 + 29.92
= 59.84 KN / 5m
= 11.968 KN/m (triangular load) Convert to Uniform Load = 1/3 (5) (11.968)
= 19.95 KN/m
3CD
S3.3 = 42.84 KN S3.7 = 42.84 KN
S3.3 + S3.7 = 42.84 + 42.84
= 85.68 KN / 5m
= 17.136 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (17.136)
= 28.56 KN/m
3DE
S3.4 = 43.67 KN S3.8 = 43.67 KN
S3.4 + S3.8 = 43.67 + 43.67
= 87.34 KN / 5m
= 17.468 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (17.496)
= 29.16 KN/m
3BC
T3.2 = 30.36 KN T3.6 = 29.92 KN.
T3.2 + T3.6 = 30.36 + 29.92
= 60.28 KN / 5m
= 12.056 KN/m (triangular load) Convert to Uniform Load = 1/3 (5) (12.056)
= 20.09 KN/m
3CD
T3.3 = 43.29 KN T3.7 = 42.84 KN
T3.3 + T3.7 = 43.29 + 42.84
= 86.13 KN / 5m
= 17.226 KN/m (triangular load) Convert to Uniform Load = ½ (5) (17.226)
= 28.71 KN/m
3DE
T3.4 = 43.67 KN T3.8 = 43.67 KN
T3.4 + T3.8 = 43.67 + 43.67
= 87.34 KN / 5m
= 17.468 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (17.468)
= 29.11 KN/m
3BC
R3.2 = 10.7 KN R3.6 = 10.7 KN.
R3.2 + R3.6 = 10.7 + 10.7
= 21.4 KN / 5m
= 4.28 KN/m (triangular load) Convert to Uniform Load = 1/3 (5) (4.28)
= 7.13 KN/m
3CD
R3.3 = 10.7 KN R3.7 = 10.7 KN
R3.3 + R3.7 = 10.7 + 10.7
= 21.4 KN / 5m
= 4.28 KN/m (triangular load) Convert to Uniform Load = 1/3 (5) (4.28)
= 7.13 KN/m
3DE
R3.4 = 11.27 KN R3.8 = 11.27 KN
R3.4 + R3.8 = 11.27 + 11.27
= 22.54 / 5m
= 4.508 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (4.508)
= 7.51 KN/m
C23
FC.2 = 33.06 KN FC.6= 33.06 KN
FC.2 + FC.6 = 33.06 + 33.06
= 66.12KN / 5m
= 13.224 KN/m (triangular load) Convert to Uniform Load = 1/3 (5) (13.224)
= 22.04 KN/m
C34
FC.3 = 42.4 KN FC.7 = 42.4 KN
FC.3 + FC.7 = 42.4 + 42.4
= 84.8 KN / 5m
= 16.96 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (16.96)
= 28.27 KN/m
C45
FC.4 = 19.25 KN FC.8 = 19.25 KN
FC.4 + FC.8 = 19.25 + 19.25
= 38.5 KN / 5m
= 7.7 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (7.7)
= 12.83 KN/m
C23
SC.2 = 33.06 KN SC.6 = 33.06 KN
SC.2 + SC.6 = 33.06 + 33.06
= 66.12KN / 5m
= 13.224 KN/m (triangular load) Convert to Uniform Load = 1/3 (5) (13.224)
= 22.04 KN/m
C34
SC.3 = 42.4 KN SC.7 = 42.4 KN
SC.3 + SC.7 = 42.4 + 42.4
= 84.8 KN / 5m
= 16.96 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (16.96)
= 28.27 KN/m
C45
SC.4 = 43.22 KN SC.8 = 41.5 KN
SC.4 + SC.8 = 43.22 + 41.5
= 84.72 KN / 5m
= 16.944 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (13.692)
= 28.24 KN/m
C23
TC.2 = 33.06 KN TC.6 = 33.06 KN.
TC.2 + TC.6 = 33.06 + 33.06
= 66.12KN / 5m
= 13.224 KN/m (triangular load) Convert to Uniform Load 1/3 (5) (13.224)
= 22.04 KN/m
C34
TC.3 = 42.4 KN TC.7 = 42.4 KN
TC.3 + TC.7 = 42.4 + 42.4
= 84.8 KN / 5m
= 16.96 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (16.96)
= 28.27 KN/m
CDE
TC.4 = 43.22 KN TC.8 = 41.5 KN
TC.4 + TC.8 = 43.22 + 41.5
= 84.72 KN / 5m
= 16.944 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (13.692)
= 28.24 KN/m
C34
RC.3 = 4.12 KN RC.7 = 4.12 KN
RC.3 + RC.7 = 4.12 + 4.12
= 8.24 KN / 5m
= 1.648 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (1.648)
= 2.75 KN/m
CDE
RC.4 = 5.39 KN RC.8 = 5.39 KN
RC.4 + RC.8 = 5.39 + 5.39
= 10.78 KN / 5m
= 2.156 KN / m (triangular load) Convert to Uniform Load = 1/3 (5) (2.156)
= 3.6 KN/m
LIVE LOAD
OFFICE USE
Parameters
Location Bulacan
Terrain Flat
Exposure Category B
: Enclosed Building
Enclosure Classification
± GCpi = 0.18
Computing K z
EARTHQUAKE LOADS
THIRD FLOOR
WEIGHT
The project site is 2.8 km away from the Valley Fault System.
Third Floor
Fourth Floor
SECOND FLOOR
THIRD FLOOR
FOURTH FLOOR
SECOND FLOOR
THIRD FLOOR
FOURTH FLOOR
DIAGRAMS