You are on page 1of 10

Noell Whessoe, Inc. v. Independent Testing (Stephenson).

However, it averred that it later


Consultants, Inc., G.R. No. 199851, received a letter from Noell Whessoe
November 7, 2018 ( Art. 1729) withdrawing its approval for Independent
Testing Consultants' continued services.
Facts:
Independent Testing Consultants' services
Independent Testing Consultants is engaged in allegedly failed to satisfy the standards set by
the business of conducting non-destructive the OIS and Stephenson. Petrotech further
testing on the gas pipes and vessels of its claimed that due to Independent Testing
industrial customers. Consultants' poor performance, it incurred
additional costs. Thus, it prayed that
Sometime in June 1998, Petrotech, a Independent Testing Consultants be ordered to
subcontractor of Liquigaz, engaged the services pay the additional costs as actual damages.
of Independent Testing Consultants to conduct
non-destructive testing on Liquigaz's piping Issue: WON petitioner is solidarily liable with
systems and liquefied petroleum gas storage Liquigaz and Petrotech.
tanks located in Barangay Alas-Asin, Mariveles,
Ruling:
Bataan. Independent Testing Consultants
conducted the agreed tests. It later billed No. Under Article 1729, respondent Independent
Petrotech, on separate invoices, the amounts of Testing Consultants had a cause of action
P474,617.22 and P588,848.48 for its services. against Liquigaz and petitioner, even if its
However, despite demand, Petrotech refused to contract was only with Petrotech. The Regional
pay. Independent Testing Consultants filed a Trial Court and the Court of Appeals, therefore,
Complaint for collection of sum of money with did not err in concluding that petitioner was
damages against Petrotech, Liquigaz, and Noell solidarily liable with Liquigaz and Petrotech for
Whessoe for P1,063,465.70 plus legal interest. It unpaid fees to respondent Independent Testing
joined Noell Whessoe as a defendant, alleging Consultants. Article 1729 creates a solidary
that it was Liquigaz's contractor that liability between the owner, the contractor, and
subcontracted Petrotech the subcontractor. A solidary obligation is "one
in which each debtor is liable for the entire
In its Answer,Liquigaz argued that Independent
obligation, and each creditor is entitled to
Testing Consultants had no cause of action
demand the whole obligation."[84] Respondent
against it since there were no contractual
Independent Testing Consultants may demand
relations between them and that any contract that
payment for all of its unpaid fees from Liquigaz,
Independent Testing Consultants had was with
petitioner, or Petrotech, even if its contract was
its subcontractors.Noell Whessoe, on the other
only with the latter. However, Article 1729,
hand, denied that it was Liquigaz's contractor
while serving as an exception to the general rule
and that its basic role was merely to supervise
on the privity of contracts, likewise provides for
the construction of its gas plants. It argued that
an exception to this exception. The contractor is
any privity of contract was only with Petrotech.
solidarily liable with the owner and
Thus, it asserted that Petrotech alone should be
subcontractor for any liabilities against a
liable to Independent Testing Consultants... or
supplier despite the absence of contract between
its part, Petrotech alleged that upon Noell
the contractor and the supplier, except when the
Whessoe's approval, Independent Testing
subcontractor has already been fully paid for its
Consultants was chosen to conduct the non-
services. Here, the Court of Appeals found that
destructive testing on Liquigaz's liquefied
there was "uncontroverted evidence that
petroleum gas storage vessel under the
PETROTECH had already been paid for its
supervision of OIS, an inspection firm from the
services
United Kingdom, and of Nick Stephenson
Since Whessoe UK and petitioner should be Andrada Construction opposed the claim for
considered the same entity for the purposes of lack of legal and factual basis.On September 6,
the Mariveles Terminal Expansion Project, 1996, Andrada Construction wrote to Metro
Whessoe UK's full payment to Petrotech would Bottled Water contesting E.S. De Castro and
serve as a valid defense against petitioner's Associates’ Special Report. The works
solidary liability. Thus, petitioner still cannot be performed by Andrada Construction were
held solidarily liable with Liquigaz and inspected by Metro Bottled Water and E.S. De
Petrotech for any remaining receivables from Castro and Associates. Punch lists were
respondent Independent Testing Consultants. prepared to monitor Andrada Construction’s
Any remaining obligations to it should be rectifications.[ Andrada Construction sent letters
solidarily borne by the owner, Liquigaz, and the to Metro Bottled Water requesting for payment
subcontractor, Petrotech. of unpaid work accomplishments amounting to
P7,292,721.27. Metro Bottled Water refused to
pay.On August 6, 2001, Andrada Construction
2. Metro Bottled Water Corp. v. Andrada filed a Request for Arbitration before the
Construction & Development Corp., Inc., Construction Industry Arbitration Commission,
G.R. No. 202430, March 6, 2019 (1724) alleging that Metro Bottled Water refused to pay
its unpaid work accomplishment amounting to
Facts: P7,954,961.10, with interest of P494,297.31.
Metro Bottled Water and Andrada Construction Petitioner argues that the Court of Appeals erred
entered into a Construction Agreement for the in applying the principle of unjust enrichment,
construction of a reinforced concrete considering that Article 1724 of the Civil
manufacturing plant in Gateway Business Park, Code provides the requisites for the recovery of
General Trias, Cavite for the contract price of the costs of additional work. It contends that
P45,570,237.90. The Construction Agreement Article 1724 requires both the written authority
covered all materials, labor, equipment, and of the owner allowing the changes and a written
tools, including any other works required. The agreement by the parties as to the increase in
project was to be completed within 150 calendar costs, neither of which were present in this case.
days or by October 10, 1995, to be reckoned Even the Construction Agreement, it asserts,
from Andrada Construction’s posting of a requires a written order to the contractor signed
Performance Bond to answer for liquidated by the owner, authorizing work changes or
damages, costs to complete the project, and third adjustments on the contract price or contract
party claims. The Performance Bond was issued period—to which respondent did not comply.
by Intra Strata Assurance Corporation (Intra Issue: Whether or not the Construction Industry
Strata).On May 10, 1995, Metro Bottled Water Arbitration Commission and the Court of
extended the period of completion to November Appeals erred in finding that petitioner Metro
30, 1995 upon Andrada Construction’s request, Bottled Water Corporation was liable to
due to the movement of one (1) bay of the plant respondent Andrada Consumption &
building, weather conditions, and change Development Corporation, Inc. for unpaid work
orders.On November 14, 1995, E.S. De Castro accomplishment.
and Associates, Metro Bottled Water’s
consultant for the project, recommended the Ruling:
forfeiture of the Performance Bond to answer for
No. Petitioner contends that the arbitral tribunal
the completion and correction of the project, as
should first apply Article 1724 when resolving
well as liquidated damages for delay.On May 2,
the issue of whether respondent should be
1996, Metro Bottled Water filed a claim against
compensated for costs incurred in Change Order
the Performance Bond issued by Intra Strata.
Nos. 39 to 109. Petitioner, however, fails to
recognize that there was no need to apply Article Exasperated, CECON served notice upon ACI
1724, since salient points of the provision had that it would avail of arbitration. On January 29,
already been embodied in the Construction 2004, it filed with the CIAC its Request for
Agreement. It is settled that the contract is the Adjudication. It prayed that a total sum of
law between the parties. Without any ambiguity P183,910,176.92 representing adjusted project
in Item No. 8 of the Construction Agreement, costs be awarded in its favor.
there was no need to resort to other aids in
Issue: Whether or not the Court of Appeals
interpretation, such as Article 1724 of the Civil
correctly held that the CIAC Arbitral Tribunal
Code, to resolve the issue.
acted beyond its jurisdiction in holding that the
3. CE Construction Corp. v. Araneta price of P1,540,000,000.00 did not bind the
Center, Inc., G.R. No. 192725, [August 9, parties as an immutable lump-sum.
2017], 816 PHIL 221-287 (Arts 1715, 1724)
Ruling:
Facts:
No. No extraordinary technical or legal
Petitioner CECON was a construction proficiency is required to see that it would be the
contractor, which, for more than 25 years, had height of absurdity and injustice to insist on the
been doing business with respondent ACI, the payment of an amount the consideration of
developer of Araneta Center, Cubao, Quezon which has been reduced to a distant memory.
City. ACI's invocation of Article 1724 is useless as
the premises for its application are absent. ACI's
In June 2002, ACI sent invitations to different position is an invitation for this Court to lend its
construction companies, including CECON, for imprimatur to unjust enrichment enabled by the
them to bid on a project identified as "Package gradual wilting of what should have been a
#4 Structure/Mechanical, Electrical, and reliable contractual relation. Basic decency
Plumbing/Finishes (excluding Part A impels this Court to not give in to ACI's
Substructure)," a part of its redevelopment plan advances and instead sustain the CIAC Arbitral
for Araneta Center Complex. The project would Tribunal's conclusion that the amount due to
eventually be the Gateway Mall. As described CECON has become susceptible to reasonable
by ACI, "[t]he Project involved the design, adjustment.
coordination, construction and completion of all
architectural and structural portions of Part B of
the Works[;] and the construction of the 4. Loadstar Shipping Co., Inc. v. Malayan
architectural and structural portions of Part A of Insurance Co., Inc., G.R. No. 185565
the Works known as Package 4 of the Araneta (Resolution), [April 26, 2017], 809 PHIL 736-
Center Redevelopment Project. Despite ACI's 750 (Arts 1732-1735)
undertaking, no formal contract documents were
delivered to CECON or otherwise executed Facts:
between ACI and CECON. With many changes Loadstar International Shipping, Inc. (Loadstar
to the project and ACI's delays in delivering Shipping) and Philippine Associated Smelting
drawings and specifications, CECON and Refining Corporation (PASAR) entered into
increasingly found itself unable to complete the a Contract of Affreightment for domestic bulk
project on January 10, 2004. It noted that it had transport of the latter’s copper concentrates
to file a total of 15 Requests for Time Extension which were loaded in Cargo Hold Nos. 1 and 2
from June 10, 2003 to December 15, 2003, all of of MV “Bobcat”, a marine vessel owned by
which ACI failed to timely act on. Loadstar International Shipping Co., Inc.
(Loadstar International) and operated by goods. The right of subrogation stems from
Loadstar Shipping under a charter party Article 2207 of the New Civil Code. The rights
agreement.  The cargo was insured with of a subrogee cannot be superior to the rights
Malayan Insurance Company, Inc. (Malayan).  possessed by a subrogor. In other words, a
subrogee cannot succeed to a right not possessed
The vessel’s chief officer on routine inspection
by the subrogor.  A subrogee in effect steps into
found a crack on starboard side of the main deck
the shoes of the insured and can recover only if
which caused seawater to enter and wet the
the insured likewise could have recovered.
cargo. Upon inspection, the Elite Adjusters and
Consequently, an insurer indemnifies the insured
Surveyor, Inc. (Elite Surveyor) confirmed that
based on the loss or injury the latter actually
samples of copper concentrates from Cargo
suffered from.  If there is no loss or injury, then
Hold No. 2 were contaminated by seawater.
there is no obligation on the part of the insurer to
PASAR sent a formal notice of claim in the indemnify the insured. Should the insurer pay
amount of [P]37,477,361.31 to Loadstar the insured and it turns out that indemnification
Shipping. On the basis of the Elite Surveyor’s is not due, or if due, the amount paid is
recommendation, Malayan paid PASAR the excessive, the insurer takes the risk of not being
amount of [P]32,351,102.32. PASAR signed a able to seek recompense from the alleged
subrogation receipt in favor of Malayan.  To wrongdoer.  This is because the supposed
recover the amount paid and in the exercise of subrogor did not possess the right to be
its right of subrogation, Malayan demanded indemnified and therefore, no right to collect is
reimbursement from Loadstar Shipping, which passed on to the subrogee.
refused to comply.  Consequently, on September
19, 2001, Malayan instituted with the RTC a
As regards the determination of actual damages,
complaint for damages. In its complaint,
“[i]t is axiomatic that actual damages must be
Malayan mainly alleged that as a direct and
proved with reasonable degree of certainty and a
natural consequence of the unseaworthiness of
party is entitled only to such compensation for
the vessel, PASAR suffered loss of the cargo.
the pecuniary loss that was duly proven. As
Loadstar Shipping and Loadstar International
Malayan is claiming for actual damages, it bears
denied respondent’s allegations and averred that
the burden of proof to substantiate its claim.
respondent’s payment to PASAR, on the basis of
Actual damages are not presumed.  The claimant
the latter’s fraudulent claim, does not entitle
must prove the actual amount of loss with a
respondent automatic right of recovery by virtue
reasonable degree of certainty premised upon
of subrogation.
competent proof and on the best evidence
obtainable.  Specific facts that could afford a
basis for measuring whatever compensatory or
Issue: actual damages are borne must be pointed out. 
WON respondent is entitled to the right of Actual damages cannot be anchored on mere
recovery by virtue of subrogation against surmises, speculations or conjectures.
petitioners, on the basis of PASAR’s claim.
It is not disputed that the copper concentrates
carried by M/V Bobcat from Poro Point, La
Ruling: Union to Isabel, Leyte were indeed
contaminated with seawater.  The issue lies on
Malayan’s claim against the petitioners is based
whether such contamination resulted to damage,
on subrogation to the rights possessed by
and the costs thereof, if any, incurred by the
PASAR as consignee of the allegedly damaged
insured PASAR. In this case, Malayan, as the
insurer of PASAR, neither stated nor proved that abrasions on the abdomen.12 She also suffered
the goods are rendered useless or unfit for the multiple rib fractures.13 The immediate cause of
purpose intended by PASAR due to death, stated in her Certificate of Death,14 is
contamination with seawater.  Hence, there is no "Cardio-Pulmonary Arrest Sec. to Vehicular
basis for the goods’ rejection under Article 365 Accident."
of the Code of Commerce.  Clearly, it is
Issue: Whether ES Trucking is a common
erroneous for Malayan to reimburse PASAR as
carrier required by law to observe extraordinary
though the latter suffered from total loss of
diligence in the carriage of passengers and
goods in the absence of proof that PASAR
goods.
sustained such kind of loss.
Ruling:
Yes. Article 1732 of the Civil Code defines
5. Heirs of Mendoza v. ES Trucking and
common carriers as persons, corporations, firms
Forwarders, G.R. No. 243237, February 17,
or associations engaged in the business of
2020 (Art 1732)
carrying or transporting passengers or goods or
Facts: both, by land, water, or air, for compensation,
offering their services to the public. In this case,
On June 13, 2013, at around noontime, Catalina
the Heirs of Catalina established through
P. Mendoza (Catalina) was walking along Sta.
preponderance of evidence that, at the time of
Maria Road after visiting a lotto outlet nearby.
the incident, the vehicle was being used as a
While she was at the center of the road and
truck for hire without securing the necessary
attempting to cross its second half, she was
franchise from the LTFRB. ES Trucking
sideswiped by a 14-wheeler prime mover truck
engaged in a truck for hire business, offering
at the junction of Gov. Ramos Street and Sta.
their vehicles to transport the cargo of its
Maria Road in Zamboanga City. The prime
customers. Noticeably, Edgardo Ruste admitted
mover truck bore body no. 5 and green plate no.
that they filed an application to have the vehicle
NAO 152, while the trailer attached to it had
included in their Certificate of Public
yellow plate no. JZA163. The vehicle is
Convenience yet their application was never
registered under the name of ES Trucking and
granted. This is inconsistent with his own claim
Forwarders (ES Trucking) with Sumarni Asprer
that ES Trucking does not need to register with
Ruste as its sole proprietor. At the time of the
the LTFRB because it is not a common carrier
incident, the vehicle was driven by Clin Timtim
but a private company. The fact that they
(Timtim), a holder of professional driver's
considered applying for the inclusion of the
license no. 104-99-069007.
vehicle in their Certificate of Public
Moments before the incident, Timtim claimed Convenience signifies that they are aware of the
that he stopped the vehicle at the crossing lane franchise requirement of the LTFRB. ES
as the tricycle in front of the prime mover truck Trucking cannot be excused simply because it is
stopped and only began to accelerate once the not registered with the LTFRB and it is a private
tricycle started moving. company. ES Trucking cannot be exonerated
from liability and benefit from its own violation
The two sons of Catalina picked her up from of the laws and rules governing trucks for hire.
under the fuel tank of the prime mover truck
behind its front left tire and brought her to 6. Federal Express Corporation, v.
Ciudad Medical Zamboanga where she was Luwalhati R. Antonino and Eliza Bettina
pronounced dead.11 Catalina suffered multiple Ricasa Antonino GR. No. 199455, June 27,
abrasions and contusions in the clavicle area, 2018 (1733)
lacerated wound on the cheek, and multiple
Facts: On December 15, 2003, Luwalhati and of public policy, are bound to observe
Eliza were in the Philippines. As the monthly extraordinary diligence in the vigilance over the
common charges on the Unit had become due, goods and for the safety of the passengers
they decided to send several Citibank checks to transported by them, according to all the
Veronica Z. Sison, who was based in New York. circumstances of each case."Extraordinary
Citibank checks allegedly amounting to diligence is that extreme measure of care and
US$17,726.18 for the payment of monthly caution which persons of unusual prudence and
charges and US$11,619.35 for the payment of circumspection use for securing and preserving
real estate taxes were sent by Luwalhati through their own property or rights." Consistent with
FedEx with Account No. x2546-4948-1 and the mandate of extraordinary diligence, the Civil
Tracking No. 8442 4588 4268. The package was Code stipulates that in case of loss or damage to
addressed to Sison who was tasked to deliver the goods, common carriers are presumed to be
checks payable to Maxwell-Kates, Inc. and to negligent or at fault. Petitioner is unable to
the New York County Department of Finance. prove that it exercised extraordinary diligence in
Sison allegedly did not receive the package, ensuring delivery of the package to its
resulting in the non-payment of Luwalhati and designated consignee. It claims to have made a
Eliza's obligations and the foreclosure of the delivery but it even admits that it was not to the
Unit. designated consignee. It asserts instead that it
was authorized to release the package without
Upon learning that the checks were sent on
the signature of the designated recipient and that
December 15, 2003, Sison contacted FedEx on
the neighbor of the consignee, one identified
February 9, 2004 to inquire about the non-
only as "LGAA 385507," received it This fails
delivery. She was informed that the package was
to impress.
delivered to her neighbor but there was no
signed receipt. The assertion that receipt was made by "LGAA
385507" amounts to little, if any, value in
On March 14, 2004, Luwalhati and Eliza,
proving petitioner's successful discharge of its
through their counsel, sent a demand letter to
duty. "LGAA 385507" is nothing but an
FedEx for payment of damages due to the non-
alphanumeric code that outside of petitioner's
delivery of the package, but FedEx refused to
personnel and internal systems signifies nothing.
heed their demand. Hence, on April 5, 2004,
This code does not represent a definite, readily
they filed their Complaint for damages.
identifiable person, contrary to how commonly
Issue: Whether or not petitioner Federal Express accepted identifiers, such as numbers attached to
Corporation may be held liable for damages on official, public, or professional identifications
account of its failure to deliver the checks like social security numbers and professional
shipped by respondents Luwalhati R. Antonino license numbers, function. Reliance on this code
and Eliza Bettina Ricasa Antonino to the is tantamount to reliance on nothing more than
consignee Veronica Sison petitioner's bare, self-serving allegations.
Certainly, this cannot satisfy the requisite of
Ruling: extraordinary diligence consummated through
Yes. Petitioner is liable for this loss. It failed to delivery to none but "the person who has a right
ensure that the package was delivered to the to receive" the package.
named consignee. The Civil Code mandates 7. Unitrans International Forwarders,
common carriers to observe extraordinary Inc. v. Insurance Company of North
diligence in caring for the goods they are America, G.R. No. 203865, March 13, 2019
transporting:Article 1733. Common carriers, (Art 1735 in relation to 1733)
from the nature of their business and for reasons
Facts: foregoing circumstances to exculpate them from
liability
In Melbourne, Australia, South East Asia
Container Line (SEACOL) solicited and Ruling:
received shipment of musical instruments from
No. A common carrier is presumed to have been
shipper Dominant Musical Instrument for
negligent if it fails to prove that it exercised
transportation to and delivery at the port of
extraordinary vigilance over the goods it
Manila. The aforesaid shipment was insured
transported. When the goods shipped are either
with respondent Insurance Company of North
lost or arrived in damaged condition, a
America (ICNA) against all risk in favor of the
presumption arises against the carrier of its
consignee, San Miguel Foundation for the
failure to observe that diligence, and there need
Performing Arts (San Miguel). SEACOL then
not be an express finding of negligence to hold it
loaded the insured shipment on board M/S
liable. To overcome the presumption of
Buxcrown for transportation from Melbourne to
negligence, the common carrier must establish
Singapore. In Singapore, the shipment was
by adequate proof that it exercised extraordinary
transferred from M/S Buxcrown to M/S Doris
diligence over the goods. It must do more than
Wullf for final transportation to the port of
merely show that some other party could be
Manila.
responsible for the damage. In the instant case,
Upon arrival in Manila, the container van was considering that it is undisputed that the subject
discharged from the vessel and was received by goods were severely damaged, the presumption
petitioner Unitrans International Forwarders of negligence on the part of the common carrier,
(Unitrans), and upon stripping, it was found that i.e., Unitrans, arose. Hence, it had to discharge
two of the cartons containing the musical the burden, by way of adequate proof, that it
instruments were in a bad condition. Despite exercised extraordinary diligence over the
such, Unitrans delivered the subject shipment to goods; it is not enough to show that some other
the consignee. After further inspection, it was party might have been responsible for the
found out that two units of musical instruments damage. Unitrans failed to discharge this
were damaged and could no longer be used for burden. Hence, it cannot escape liability
their intended purpose, hence were declared a
Hence, extraordinary diligence was not
total loss. Despite repeated demands, Unitrans
observed.
refused to pay the damages sustained.
Subsequently, ICNA, as the insurer, paid for and
was subrogated the rights to collect from
Unitrans. ICNA filed an amended complaint for 8. Keihin-Everett Forwarding Co., Inc. v.
collection of sum of money against South East Tokio Marine Malayan Insurance Co., Inc.,
Asia Container Line (SEACOL) and the G.R. No. 212107, [January 28, 2019]) (1733-
unknown owner/charterer of the vessel M/S 1736)
Buxcrown, both doing business in the Facts:
Philippines through its local ship agent,
petitioner Unitrans International Forwarders Honda Trading Phils. Ecozone Corporation
(Unitrans); and against the unknown charterer of (Honda Trading) ordered 80 bundles of
M/S Doris Wullf, doing business through its Aluminum Alloy Ingots from PT Molten
local ship agent respondent TMS Ship Agencies Aluminum Producer Indonesia. Honda Trading
(TSA). insured the entire shipment with Tokio Marine
& Nichido Fire Insurance Co., Inc. (TMNFIC).
Issue: Whether or not Unitrans was able to It also engaged the services of Keihin-Everett to
exercise the diligence necessary under the clear and withdraw the cargo from the pier and
to transport and deliver the same to its until they are delivered, actually or
warehouse in Biñan, Laguna. Meanwhile, constructively, by the carrier to the consignee, or
Keihin-Everett had an Accreditation Agreement to the person who has a right to receive them.
with Sunfreight Forwarders whereby the latter
Hence, at the time Keihin-Everett turned over
undertook to render common carrier services for
the custody of the cargoes to Sunfreight
the former and to transport inland goods within
Forwarders for inland transportation, it is still
the Philippines. Shipment was released from the
required to observe extraordinary diligence in
pier by Keihin-Everett and turned over to
the vigilance of the goods. Failure to
Sunfreight Forwarders for delivery to Honda
successfully establish this carries with it the
Trading. En route to the latter's warehouse, the
presumption of fault or negligence, thus,
truck carrying the containers was hijacked and
rendering Keihin-Everett liable to Honda
the container van with Serial No. TEXU
Trading for breach of contract.
389360-5 was reportedly taken away. Honda
Trading suffered losses in the total amount of 9. Faj Construction v. Saulog, G.R. No.
P2,121,917.04, representing the value of the lost 200759, March 25, 2015 (Art. 1715)
40 bundles of Aluminum Alloy Ingots. Claiming
to have paid Honda Trading's insurance claim Facts:
for the loss it suffered, Tokio Marine filed a On June 15, 1999, petitioner FAJ Construction
complaint for damages against Keihin-Everett. and Development Corporation and respondent
Issue: WON Keihin-Everett is liable? Susan M. Saulog entered into an
Agreement6 (construction agreement) for the
Ruling: construction of a residential building in San
Lorenzo Village, Makati City for a contract
Yes. Keihin-Everett is liable notwithstanding
price of P12,500,000.00. Payment to petitioner
that the cargoes were in the possession of
contractor shall be on a progress billing basis,
Sunfreight Forwarders when they were hijacked.
after inspection of the work by respondent.
As correctly held by the CA, there was no
Construction of the building commenced, and
privity of contract between Honda Trading (to
respondent made a corresponding total payment
whose rights Tokio Marine was subrogated) and
to petitioner in the amount of P10,592,194.80.
Sunfreight Forwarders. Hence, Keihin-Everett,
However, for the October 31 and November 6,
as the common carrier, remained responsible to
2000 progress billing statements sent by
Honda Trading for the lost cargoes.
petitioner in the total amount of P851,601.58,
In this light, Keihin-Everett, as a common respondent refused to pay. After performing
carrier, is mandated to observe, under Article additional work, petitioner made another request
1733 of the Civil Code, extraordinary diligence for payment, but respondent again refused to
in the vigilance over the goods it transports pay, prompting petitioner to terminate the
according to all the circumstances of each case. construction contract pursuant to Article 27(b)
In the event that the goods are lost, destroyed or of the Uniform General Conditions of Contract
deteriorated, it is presumed to have been at fault for Private Construction (or Document 102) of
or to have acted negligently, unless it proves that the Construction Industry Authority of the
it observed extraordinary diligence. To be sure, Philippines, Department of Trade and Industry.7
under Article 1736 of the Civil Code, a common
Petitioner then sent demand letters to respondent
carrier's extraordinary responsibility over the
on November 24, 2000 and September 28, 2001.
shipper's goods lasts from the time these goods
In reply, respondent claimed that petitioner’s
are unconditionally placed in the possession of,
work was defective, and that it should instead be
and received by, the carrier for transportation,
made liable thereon.
Issue: WON Saulog adequately prove her right to pay the penalty for delay after appellee no
to actual damages for rectification of appellant’s longer agreed to any further extension.
defective work
Ruling:
Yes. Article 1715 of the Civil Code provides
10. Shangri-La Properties, Inc. v. BF Corp.,
that the contractor shall execute the work in such
G.R. Nos. 187552-53 & 187608-09, October
a manner that it has the qualities agreed upon
15, 2019 (Art. 1724)
and has no defects which destroy or lessen its
value or fitness for its ordinary or stipulated use. Facts:
Should the work be not of such quality, the
employer may require that the contractor remove The present controversy originated from the
the defect or execute another work. If the agreement of Shangri-la Properties, Inc. (SLPI)
contractor fails or refuses to comply with this and BF Corporation (BFC) for the execution of
obligation, the employer may have the defect the builder's work for Phases I and II, and the
removed or another work executed, at the Car Parking Structure (Carpark) of the EDSA
contractor’s cost.Evidently, Article 1715 gives Plaza Project (Project) in Mandaluyong City,
the employer the options to require the removal embodied in the parties' contract documents.
of the work, to rectify the flaws in their work, or SLPI was the project owner and BFC was the
to have the work done at the expense of the trade contractor. BFC sued SLPI and the
contractor. members of the latter's board of directors
(Alfredo C. Ramos, Rufo B. Colayco, Antonio
Here, the defective workmanship was amply B. Olbes, Gerardo O. Lanuza Jr., Maximo G.
proven by Architect Rhodora Calinawan’s Licauco III and Benjamin C. Ramos) for the
testimony and documentary evidence i.e., collection of P228,630,807.80. The case was
photographs, receipts, and list of the expenses docketed as Civil Case No. 63400 in the
needed to rectify appellant’s poorly crafted Regional Trial Court of Pasig City (Branch 157).
work. Hence, We sustain the award of actual The proceedings before the trial court was
damages based on these testimonial and stayed by this court, as affirmed by the Supreme
documentary evidence. Court, until termination of an arbitration
proceeding as required in their contract.
Regarding the penalty for delay in the amount of
One Million Three Hundred Eighty Seven BFC filed a request for arbitration with the
Thousand Five Hundred Pesos (P1,387,500.00), Construction Industry Arbitration Commission
the same should also be sustained. A contract is (CIAC), but the same was eventually dismissed,
the law between the parties, and they are bound without prejudice, on the ground that the
by its stipulations so long as they are not arbitration between BFC and SLPI must be
contrary to law, customs, public policy and undertaken in accordance with Republic Act No.
public morals. The penalty for delay is agreed 876. Subsequently, the trial court revived the
upon by the parties themselves. The fact that case and directed the parties to proceed with the
appellant was already delayed in the completion arbitration proceeding in accordance with
of the duplex is undisputed. In fact, record R.A. No. 876. Engr. Eliseo Evangelista, Ms.
shows that on January 24, 2000, appellee Alicia Tiongson and Atty. Mario Eugenio Lim
approved the extension requested by appellant. were tasked to resolve the controversy as
This request for extension, by itself, is already members of the Arbitral Tribunal.
proof of delay. Thus, at the time appellant
abandoned the project, it already incurred delay. Issue: WON the court of appeals gravely erred
Verily, it is only proper that appellant be made when it denied the claims of bfc for variation
works it was compelled to perform upon the
instructions of SLPI.
Ruling:
Yes. The Court upholds the Arbitral Tribunal. In
our view, the. CA wrongly disregarded the
specific variation orders that carried the
conformity of SLPI, which, when coupled with
the letter dated May 9, 1991, satisfied the
requisites under Article 1724. Accordingly, the
Court reinstates the Arbitral Tribunal's awards in
favor of BFC for variation orders included in
progress billings amounting to
P9,513,987.91 and for change orders not
included in progress billings amounting to
P6,201,278.50. The Arbitral Tribunal correctly
ruled that BFC had complied with the twin
requirements imposed by Article 1724 of the
Civil Code. Article 1724 governs the recovery of
costs for any additional work because of a
subsequent change in the original plans. The
underlying purpose of the provision is to prevent
unnecessary litigation for additional costs
incurred by reason of additions or changes in the
original plan. The provision was undoubtedly
adopted to serve as a safeguard or as a
substantive condition precedent to recovery.  As
such, added costs can only be allowed upon: (a)
the written authority from the developer or
project owner ordering or allowing the changes
in work; and (b) upon written agreement of the
parties on the increase in price or cost due to the
change in work or design modification.
Compliance with the requisites is a condition
precedent for recovery; the absence of one
requisite bars the claim for additional costs.
Notably, neither the authority for the changes
made nor the additional price to be paid therefor
may be proved by any evidence other than the
written authority and agreement as above-stated.

You might also like