Professional Documents
Culture Documents
A)
Determine the total Loading Unit (L.U.) of the system
Given the design flow rate, demand time, frequency of use of each sanitary fitment, demand
unit of each fitment can be found.
𝑑𝑒𝑚𝑎𝑛𝑑 𝑡𝑖𝑚𝑒
Usage ratio = 𝑓𝑟𝑒𝑞𝑢𝑒𝑛𝑐𝑦 𝑜𝑓 𝑢𝑠𝑒
Since the demand of one basin is 1 Loading Unit (L.U.), one basin is our base appliance.
𝑢𝑠𝑎𝑔𝑒 𝑟𝑎𝑡𝑖𝑜
Proportion of base appliance ratio = 𝑢𝑠𝑎𝑔𝑒 𝑟𝑎𝑡𝑖𝑜 𝑜𝑓 𝑡ℎ𝑒 𝑏𝑎𝑠𝑒 𝑎𝑝𝑝𝑙𝑖𝑎𝑛𝑐𝑒 ( 0.017)
𝑓𝑙𝑜𝑤 𝑟𝑎𝑡𝑒
Proportion of base appliance flow rate = 𝑓𝑙𝑜𝑤 𝑟𝑎𝑡𝑒 𝑜𝑓 𝑡ℎ𝑒 𝑏𝑎𝑠𝑒 𝑎𝑝𝑝𝑙𝑖𝑎𝑛𝑐𝑒 (0.12)
Demand figure = proportion of base appliance ratio x proportion of base appliance flow rate
Demand unit = round up number of the demand figure = loading unit of each fitment
Hence, the total Loading Unit (L.U.) of the system = 10 +10 +50+ 10 = 80
Determine the simultaneous demand in L/s of the system
P= Usage Probability of
Fitment n ratio m occurrence Accumulating
Basin 10 0.017 0 P0= 0.845
1 P1= 0.143 0.989
2 P2= 0.011 0.999
cloth
washer 2 0.05 0 P0= 0.903
1 P1= 0.095 0.998
Based on probability theory, probability of having a sanitary fitment in use at a certain time
can be calculated.
𝑛!
𝑃𝑚 = ( ) 𝑥 𝑃𝑚 (1 − 𝑃)𝑛−𝑚
𝑚! (𝑛 − 𝑚)!
Where n = total number of fittings having the same probability
m= number of fitting in use at any one time
Pm = probability of occurrence
Consider the first case where a group of 10 basins, with a certain design demand time and
frequency of use, the probability factor of a particular number of draw off points occurring at
any one time, P indicated above the chart on the third column from the left, can be computed.
𝑑𝑒𝑚𝑎𝑛𝑑 𝑡𝑖𝑚𝑒
P = 𝑓𝑟𝑒𝑞𝑢𝑒𝑛𝑐𝑦 𝑜𝑓 𝑢𝑠𝑒
Since the design intent is to serve 99% of all conditions, in the “accumulating” column as
long as shows nearly close to 0.99 meaning with this number of fitments or less in use at one
single time can serve 99% of all times.
Consider three floors below (17/F, 18/F, and 19/F) and ignore the top three floors for a
moment.
Given maximum residual pressure 4.5bar = 45mH
Head gain from the booster system (20/F) to 17/F = 3.5mH x3=10.5mH
Pump cut-out pressure = 45m-10.5 + 0.1x3.5x3 = 35.55mH
Consider three floors above (21/F, 22/F and 23/F) and ignore the down three floors for a
moment.
Given minimum residual pressure 1.0 bar = 10mH
Head loss from the booster system (20/F) to 23/F = 3.5mH x3=10.5mH
Pump Cut-in pressure= 10mH+10.5+ 0.1x3.5mx3H= 21.55mH
To sum up, pump cut-in pressure is 21.55mH and pump cut-out pressure is 35.55mH in the
booster system which is acceptable since their pressure difference is within the range of 10 -
20 mH.
Each floor has a male, female and disabled toilet: 4 basins for male, 5 basins for female and
1 basin for disabled toilet. Therefore, each floor has 10 basins.
Since the booster system serves the basins in toilets three floors above and three floors below,
The simultaneous demand for 6 floors = 1 LU x 6 floors x 10 basins = 60 LU
Flow rate based on 60LU (See Pipe sizing Chart on the next page, graph 3)
For a 10 minute cut-out cycle, this ‘effective volume’ = 0.9 L/s x 10min x 60sec =540 L
0.9 L/s
4500
4000
3500
Consumption (L)
3000
2500
1000
500
0
9:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
Hour (hr)
Peak litres litres per Peak litres litres per
hours used hour hours used hour
1 4620 4620 14 26695 1907
2 8820 4410 15 28710 1914
3 12600 4200 16 30390 1899
4 15960 3990 17 31230 1837
5 18730 3746 18 31400 1744
6 20830 3472 19 31650 1666
7 22930 3276 20 31810 1591
8 24015 3002 21 31980 1523
9 25105 2789 22 32570 1480
10 25610 2561 23 33830 1471
11 25695 2336 24 35510 1480
12 25775 2148
13 26025 2002 24hr average:
35510/24 = 1479.6 =1480 L/hr
Table B: Peak hourly loads (above)
5000
Storage make-up ratio curve peak hour 1
peak hour 2
4500 peak hour 3
peak hour 4
peak hour 5
4000 peak hour 6
peak hour 7
3500 peak hour 8
peak hour 9
Recovery/storage curve
peak hour 10
3000 peak hour 11
Recovery (L/hr)
peak hour 12
2500 peak hour 13
peak hour 14
peak hour 15
2000 peak hour 16
Min recovery rate =1480 L/hr peak hour 17
1500 peak hour 18
peak hour 19
peak hour 20
1000 peak hour 21
peak hour 22
peak hour 23
500
peak hour 24
0
0 5000 10000 15000 20000 25000 30000 35000 40000
Storage-litres (L)
Given that
-Existing hot water tank = 8000 L
-Existing hot water heater Q= 120kW
-Design cold and hot water temperature = Tw=10°C & Th= 65°C
-Heat capacity of water, cp= 4.2 kJ/kgK
Assume water density as 1kg/L
𝑄 = 𝑚𝑐∆𝑇
4.2𝑘𝐽
120𝑘𝑊 = 𝑚 𝑥 (65 − 10)
𝑘𝑔𝐾
𝑚 = 0.52 𝑘𝑔/𝑠
𝑘𝑔
0.52
𝑟𝑒𝑐𝑜𝑣𝑒𝑟𝑦 = 𝑠 𝑥3600 𝑠/ℎ𝑟
1 𝑘𝑔/𝐿
1872𝐿
𝑟𝑒𝑐𝑜𝑣𝑒𝑟𝑦 =
ℎ𝑟
In the existing system, the 8000L hot water tank is at a recovery rate of 1872L/hr. However, in
the storage make-up ratio curve, under the condition of a 8000L hot water demand, the required
recovery rate is at least roughly 2300L/hr. Hence, the existing system is not sufficient for the
present hot water demand.
Recommendations:
If the hot water tank storage to 8000L is kept,
𝑄 = 𝑚𝑐∆𝑇
8000𝐿 1ℎ𝑟 1𝑘𝑔 4.2𝑘𝐽
𝑄= 𝑥 𝑥 𝑥 𝑥 (65 − 10)
1ℎ𝑟 3600𝑠 1𝐿 𝑘𝑔𝐾
𝑄 = 147.6𝑘𝑊
The power output of the heater requires to be larger so as to satisfy the required hot water
demand instead of the existing smaller power output of 120kW. Moreover, finding a heater with
a recovery rate of exactly 2300 L/hr on the existing market is not very possible although
2300L/hr recovery rate is the theoretical value based on the plot. Perhaps, we can pick a
2500L/hr recovery rate heater that should be available on the market for our need.
Or if the power output of the heater is kept to 120kW, with 1872L/hr recovery rate, based on the
storage make-up ratio, the hot water tank should require around 12000L
B) Sizing the primary and secondary pipework
Consider a primary circuit of a hot water system,
Design flow rate = 2.0 L/s
Cold water = 20 °C (density 998 kg/ m3)
Hot water = 65° C (density 980 kg/m3)
The height difference between boiler and calorifier = 8m
Pressure difference of two columns of water=∆𝑝𝑔ℎ= (998 – 980) x 9.81x 8 = 1413 Pa
Assume the overall hydraulic length of the pipe = 24m (measured pipe length + length of fittings)
Allowable pressure drop = 1413Pa/ 24m = 59 Pa/m
From the pipe sizing chart for copper pipe, at design flow =2.0L/s,
Based on average 989kg/m3,
𝑃𝑎 10 𝑚𝐻
Head loss per meter run = 59 𝑚 𝑥 = 0.006 𝑚𝐻/𝑚,
100𝑘𝑃𝑎
(see Pipe Sizing Chart on the next page) 76mm pipe suits the requirement.
For secondary
supply circuit
(red)
For primary
circuit (orange)
𝑑 5 𝑥ℎ
𝑄 = 0.0071√
𝑠𝑥𝑙
Where Q = flow (m3/hr),
d= diameter of pipe (mm),
h =pressure drop (mbar), assume 100 Pa = 1mbar,
l= length of pipe (m), in this case, measured length of pipe: 5+8+1 =14m, length of fitting around
4m
s =specific gravity of gas (town gas =0.52)
𝑑 5 𝑥1
8.89 = 0.0071√
0.52𝑥18
𝑑 = 27𝑚𝑚
Gas supply pipes from the gas meter to the individual appliances = 32mm (available on the
market)
B) Determine pressure drop of steam pipe work and then size the steam pipe
Given:
A boiler plant producing 180°C superheated steam at 600kPa (absolute) = 6 bar
Minimum pressure at the heater at 150 °C = 475kPa =4.75 bar (absolute) from steam table
Pressure drop of steam pipe work = 6bar -4.75 bar = 1.25bar (absolute)
Steam loading of the heater =300kg/hr
Overall equivalent length of the steam pipe = 40m
Consider the heat loss from pipework = 3.5% of heater load per 100m
Hence, revised steam load = 300kg/hr + 300 x(3.5% x 40/100)=304kg/hr
𝑃1 − 𝑃2
𝐹=
𝐿
where F= pressure factor, P1 = factor based on the
inlet pressure, P2 = factor based on the pressure at a
distance of L metres, L= equivalent length of pipe (m)
43.54−29.77
𝐹= 40
𝐹 = 0.34
𝑑0.6
= 𝑝𝑟𝑜𝑝𝑜𝑟𝑡𝑖𝑜𝑛𝑎𝑙 𝑑𝑒𝑝𝑡ℎ = 0.6
𝐷
𝑣0.6
= 1.05
𝑣
𝑣 = 1.2 / 1.05 = 1.14𝑚/𝑠
𝐷2
𝑓𝑢𝑙𝑙 𝑏𝑜𝑟𝑒 𝐴𝑟𝑒𝑎, 𝐴 = 𝑝𝑖
4
2
0.45
= 𝑝𝑖
4
= 0.159 𝑚2
𝑓𝑢𝑙𝑙 𝑏𝑜𝑟𝑒 𝑓𝑙𝑜𝑤 𝑟𝑎𝑡𝑒, 𝑄 = 𝑣𝐴
𝑚
𝑄 = 1.14 𝑥 0.159𝑚2
𝑠
𝑄 = 0.181𝑚3 /𝑠
𝑄 = 181𝐿/𝑠
𝑄0.6
= 0.65
𝑄
𝑄0.6
= 0.65
181
𝑒𝑥𝑖𝑠𝑡𝑖𝑛𝑔 𝑓𝑙𝑜𝑤 𝑟𝑎𝑡𝑒, 𝑄0.6 = 118 𝐿/𝑠
Lets assume full potential as ¾ bore flow.
𝑄0.75
= 0.9
𝑄
𝑄0.75 = 0.181 𝑥 0.9
𝑄0.75 = 0.1629𝑚3 /𝑠
𝑄0.75 = 162.9 𝐿/𝑠
Determine the extreme mean intensity of the rainfall, i , for a 10 year rainstorm return period
603
𝑖=
(𝑡𝑑 + 4.4)0.44
Where td duration of rainfall in min. In this case td is equal to tc at a peak discharge of the
rainstorm system
603
𝑖=
(1.37𝑚𝑖𝑛 + 4.4)0.44
𝑖 = 279 𝑚𝑚/ℎ𝑟
Determine stormwater flow rate to be handled by the system, Q
𝑄 = 𝐶𝑥𝐴𝑥𝐼𝑥 0.278𝐿/𝑠
Where Q is rain water flow (L/s)
C is the impermeability factor or run-off coefficient, in this case, assume 0.95 for roof
A is drainage or catchment area (m2)
I is rainfall intensity (m/hr)
0.95𝑥100𝑥279
𝑄= 𝑥0.278
1000
𝐿
𝑄 = 7.36
𝑠
Determine the expected bore flow of the storm water pipe
Based on empirical formula of vertical stacks
8
𝑄 = 𝑘𝐷3
Where Q is rain water flow (L/s), k is a coefficient to determine which bore flow is expected, D
is the diameter of pipe (mm)
8
7.36 = 𝑘(100)3
𝑘 = 3.4 𝑥 10−5
So 1 / 4 bore full is expected of the storm water pipe.