You are on page 1of 5

C ase Study

of the Month

Er. P.K.Pattanaik, is presently


working with OPTCL as Dy.
General Manager (Elect) in E & MR
Division, Bhubaneswar- Odisha and
associated with the Protection and
Control schemes of Electrical systems.
He is having 25 years of technical
experience in Designing, Testing and Commissioning
of Protection Control and operational Schemes,
project Implementation, co-ordination, operations & VARIOUS CASE STUDIES
maintenance of Electrical Equipments at various LT/ HT/
EHT level Grid Sub- Stations. He has also published ON OPERATION AND CONTROL
around 70 technical papers in different national/ SCHEMES FOR GRID SUB-STATION
international seminars/journals.
Contd….
ele.pkpattanaik@optcl.co.in

1. Introduction: For the last few months, the response of the readers Sub-station it was found with tripping of one 132 KV outgoing
to the case studies on various incidents is overwhelming. Hence this feeder with fault on R phase.
month we are again choosing the write up on similar kind of studies Observations:
for developing the synchronisation of practical observation to the 1. The disturbance report was found with fault current rise on
theoretical concepts. The analysis of each incident being supported R phase and corresponding voltage dip on its phase.
by actual observations had been described during the situation to 2. The current being found 14.7 KA and tripping on Zone-1.
add awareness amongst the operation, testing and commissioning
3. As it was found with severe sound in the system, the system
engineers to know the cause of problems and be helpful for easy
was not allowed for charging and kept with observations.
rectification of the problems. This can also help to develop economic
schemes for the smooth running of the operation and control system 4. The field visit was done and found with arcing on Y phase
in the Grid Sub-Station. breaker limb as like shown in the figure 2.1.1.
2.1. Arcing on Breaker Limb: At one of the 220/132 Kv Grid 5. The tripping was instant in nature, the reason of Y phase
arcing could not be established.

48 ELECTRICAL MIR ROR || September 2020 || ||www.electricalmirror.net||


6. The Line patrolling engineer was asked to patrol the line Technical Analysis:
for any eventualities, but found with no any abnormality. 1. The bird on touching by the beak has some resistance as
the start current path and again the skin on its leg has
also some resistance path. So the current flow though
high is not like direct conducting path.

w w w. e l e c t r i c a l m i r r o r. n e t
Fig 2.1.1 Arcing of Y phase Limb
7. The Breaker limb and operation of the breaker was Fig 2.2.1 Bird Fault
checked thoroughly and tested before taking into the 2. Moreover this pole on investigation was also found with
system. no dedicated earthing for quick flow of current.
8. On detail investigation and testing the system was charged 3. However the current was sufficient for tripping of the
and stood OK. 33 KV line on Phase to ground fault.
Technical Analysis 4. In some instances, the fault current does not become
1. In this condition R Phase fault with ground had been sufficient for the tripping of the line due to the impedance
resulted causing voltage dip on the respective phase. fault in the system.
2. As per 3 Phase principle, during fault condition and dip 5. However it was advised to the discom wing not to provide
in voltage for any of the pages shall be causing the rise any extra extension for any creature to sit on the arm
of voltage on the healthy phase. Here this might have and to be in contact with the live wire.
been happened. 2.3. Effect of CT terminal opening: In one of the GIS grid and
3. The dust deposition might have tracked this due to due to space constraint and to meet the customer’s requirement,
decrease of Creepage distance. As tripping of the breaker 4 sq.mm wires were in connection to the CT terminal block.
of this limb might have been slight delayed causing the The TBs were found burnt along with cables due to CT opening
re-striking voltage and external arcing as like shown in at one of the terminal.
the figure 2.1.1. Observations:
2.2. 33 KV Bird Fault: one of the 33 KV feeder tripped on R 1. 33 KV GIS blocks are generally provided with combined
phase to ground fault. But the line was nearby to the electrical enclosed with less space area.
collection center. 2. The LCC (Local control Cubicle) panels are usually provided
Observations: as integrated part of the GIS module.
1. The 33 KV pole structure was extended with extra portion 3. In this grid Sub-station, this pattern of combined module
and the disc was connected to the internal part of the system was there with less space.
cross arm as like shown in the figure 2.2.1. 4. The secondary wires of the CT had been terminated to
2. One bird sitting on this extra portion comes in contact the terminal block in the LCC with less space.
to the live wire and electrocuted, resulting with tripping 5. But due to customer’s specific requirement, the internal
of the line. To the surprise, though the bird got burnt, wires had been provided with 4 sq. mm wires with that
but remained sticking to the conductor. limited space. The cables had also been routed in the
3. The construction design of the pole was changed with limited space region. The multi wires had also been run
no extra extension for sitting of any bird or creature. for secondary CTR control at the TBs in the LCC. So the

||www.electricalmirror.net|| || September 2020 || ELECTRICAL MIR ROR 49


Case Study

total system was clumsy. 2. The secondary CTR control should be at CT secondary
6. The TBs as shown in the figure 2.3.1 were also not strong Box, where space is factor to adjust.
enough to accommodate the multi-wire interconnection 2.4.1: Mistake in CT circuit: At one of 63 MVA AUTO transformer,
at on terminal. the facility of TURRET CT was available for developing of any
7. But the executor and supervisor for completion of the protection circuit. Problem developed during stability check
job, attempted the wiring and accommodated all the before commissioning of the transformer.
wires with the TBs. Observations:
8. In due course of service, it was found opening of one 1. This transformer was having two cores as the BCT (Bushing
Case Study of the month

CT terminal of the protection core during in-service CT) in each of the TURRET as like shown in the figure
condition. 2.4.1.
9. It was observed with high voltage and burning of the
particular terminal. Its further effect resulted the burning
of the cables and other adjacent TBs.
10. The root cause of such incident was due to space constraint
and accommodation of more wires in the limited space.
Technical Action:
1. The TBS were changed and 4 sq.mm wires were also
changed with 2.5 Sq.mm.
2. The space and number of TBs were reduced, due to
shifting of CTR control to the CT secondary box.
3. The number of cables were also reduced as CTR control
were shifted.
4. The shorting Link facility was also changed.
5. So the stress upon the TBs was reduced and system was 2. Each core has separate marking of s1 and s2. The wires
allowed to run smooth. connected from terminal finally marked with nomenclature
as 1s1, 1s2, 2s1, 2s2 from each of the secondary core.
Core one as 1s1 and 1s2, core 2 as 2s1 1nd 2s2.
3. The protection engineer as per the marking on the
external terminal developed the wiring connection for
the SEF (Sensitive Earth fault) relay connection as like
shown in fig 2.4.2 from core no-1. Core no 2 as not in
use was kept shorted.
4. But during stability checking, it was observed with some
peculiar behavior of reading as mentioned in the table
A.
5. R phase wire reading came ZERO, Y, B phase and neutral
reading came of same magnitude.
6. So to know the possibility of wrong connection, the joint
reading was taken by the combination wire by clamp
Fig 2.3.1 Clumsy TB Fig 2.3.2 Clean TB on ammeter. The values are mentioned in the table A.
arrangement arrangement The vector diagram, suspecting the possible interchange
Recommendation: of 1s2 and 2s1 were also drawn as shown in fig 2.4.5
1. The CT cables/ wires should be chosen as required. In 7. This was simply confirmed that some problem is there in
present days as we are using low burden numerical the R phase wire coming out of the BCT. It was suspected
relays and indicating meters, it is preferably to use 2.5 about the shorting of the terminals at BCT secondary Box.
sq.mm instead 4 sq.mm. So, BCT box was opened and found with no abnormality.

50 ELECTRICAL MIR ROR || September 2020 || ||www.electricalmirror.net||


Wires had been taken from 1s1, 1s2 and 2s1 and 2s2
were kept short.
8. Now the external wire connections from the R phase
BCT terminals at the secondary box were opened for
resistance checking of the windings.
9. The results were found with OPEN circuit for both the
core. So suspect was on the internal wires regarding
non-connection to the terminals or breakage of wire in
between. But obtaining of same result of OPEN circuit
for both the cores were not thought of impossible.
10. As actual circuit was taken with shorting of the 2nd
core and utilization of the first core, so, it was decided
for measurement of the resistance of the first core in
the same fashion. On doing so, when measurement for
first core was taken, the resistance value came double
as that of the value obtained with Y and B phase BCT
core.
11. So suspect was concentrated on the interchange of the
wires coming from BCT terminals and reporting to the
BCT secondary box.
12. The measurement of the combination wire readings were
also analysed and confirmed as the interchange of 1S2
with 2S1. (Refer fig 2.4.3 (This might have been done
by the electrician due to wrong way reading 1s2 as 2s1 14. Now the rectification in the form of original change of
and 2s1 as 1s2). wire internally was not possible. So with the external
13. The wrong way of reading 1s2 and 2s1 as 2s1 and 1s2 terminal, the shorting was done between 1S2 & 2S2
has been explained in fig 2.4.4. and wires to the relay was taken from 1S1 & 2S1.
15. After rectification, it was found with correct measurement
in the stability check of the transformer.
16. The transformer was successfully commissioned with the
system.
Table-A
Phase / Wire Current in m Ref. from Remarks
No. Amp. Vector Diagram
R ph. A111 0 Doubt?
Y ph. A131 18 OC O.K
B ph. A151 19 OE O.K
Neutral A71 18 OD=OC Doubt?
A111+ A131 18 OC O.K
A131+ A151 19 OD O.K
A111+ A151 18 OE O.K
A171+ A111 19 OD Doubt?
A171+ A131 32 OG=√3OC Doubt?
A171+ A151 31 OH=√3OE Doubt?

||www.electricalmirror.net|| || September 2020 || ELECTRICAL MIR ROR 51


Case Study

1 year to study the evolution of any objectionable gas


in the transformer.
5. The commissioning DGA value was kept for reference.
But surprisingly it was found with rise of CO2 gas in
the oil for all the testing conditions in drastic increasing
trend.
6. The result after one month was found more and again
at 3 month and 6 month.
Case Study of the month

7. As normal practices, the diverter switch oil is required


to be changed after every 6 months.
8. So in this case also, after 6 months of operation, the
diverter switch oil was planned for replacement.
9. The planned shutdown was availed. But when the operator
climbed top of the transformer for closing of the equalizing
2.5. Development of more CO2 in Main Tank Oil: One of the pipe valve, to his surprise he found the valve was closed
new 20 MVA 132/11KV transformer in the process plant was from the day of commissioning.
found with development more carbon dioxide content during
10. Now the valve was closed for the replacement of the
DGA testing of the oil.
OLTC tank oil.
Observations:
11. As Carbon dioxide content was also found dissolved with
1. This transformer had been commissioned for the last 8 the main tank, the main tank oil was also decided for
months. the total filtration with few days.
2. The transformer was used for the process plant and 12. After filtration, the transformer was charged and taken
provided with AVR (Automatic Voltage Controller Relay) into service. But this time, the closure of the equalization
to maintain the output voltage within the allowable limit, was done before allowing for taking the transformer into
by changing of the tap position by the OLTC provided. service.
3. In an average, the OLTC used to run for 5 to 6 times 13. The mistake of non-closure of the equalization valve,
daily. caused the mixing of diverter switch oil with main tank.
( The interconnecting pipe between Main Tank and OLTC
tank is called equalization pipe as shown in the figure
2.5.1)
14. Then due to frequent operation of OLTC to maintain
output voltage constant, the CO2 was getting generated
and getting mixed to the main tank oil.
15. This transformer was having OLTC conservator at the
same level of main tank conservator being partition of
the main conservator tank.
16. If it could have been taken with separate tank at low
level position, then it would have caused overflowing
of oil from the OLTC breather, indicating about the
interconnection of both main and OLTC oil tank.
17. So the status of equalization valve could not be known.
Only it was confirmed during time of attempt for
Fig 2.5.1 Equalization pipe with valve replacement of OLTC tank Oil.
4. As per the normal practice, DGA of the transformer had Recommendations:
been prescribed to do with time span of 1. Commissioning The equalization pipe need to be kept in CLOSED condition
time, after 1 Month, after 3 Months and 6 months and during the service of the transformer.

52 ELECTRICAL MIR ROR || September 2020 || ||www.electricalmirror.net||

You might also like