Professional Documents
Culture Documents
of the Month
1. Introduction: For the last few months, the response of the readers Sub-station it was found with tripping of one 132 KV outgoing
to the case studies on various incidents is overwhelming. Hence this feeder with fault on R phase.
month we are again choosing the write up on similar kind of studies Observations:
for developing the synchronisation of practical observation to the 1. The disturbance report was found with fault current rise on
theoretical concepts. The analysis of each incident being supported R phase and corresponding voltage dip on its phase.
by actual observations had been described during the situation to 2. The current being found 14.7 KA and tripping on Zone-1.
add awareness amongst the operation, testing and commissioning
3. As it was found with severe sound in the system, the system
engineers to know the cause of problems and be helpful for easy
was not allowed for charging and kept with observations.
rectification of the problems. This can also help to develop economic
schemes for the smooth running of the operation and control system 4. The field visit was done and found with arcing on Y phase
in the Grid Sub-Station. breaker limb as like shown in the figure 2.1.1.
2.1. Arcing on Breaker Limb: At one of the 220/132 Kv Grid 5. The tripping was instant in nature, the reason of Y phase
arcing could not be established.
w w w. e l e c t r i c a l m i r r o r. n e t
Fig 2.1.1 Arcing of Y phase Limb
7. The Breaker limb and operation of the breaker was Fig 2.2.1 Bird Fault
checked thoroughly and tested before taking into the 2. Moreover this pole on investigation was also found with
system. no dedicated earthing for quick flow of current.
8. On detail investigation and testing the system was charged 3. However the current was sufficient for tripping of the
and stood OK. 33 KV line on Phase to ground fault.
Technical Analysis 4. In some instances, the fault current does not become
1. In this condition R Phase fault with ground had been sufficient for the tripping of the line due to the impedance
resulted causing voltage dip on the respective phase. fault in the system.
2. As per 3 Phase principle, during fault condition and dip 5. However it was advised to the discom wing not to provide
in voltage for any of the pages shall be causing the rise any extra extension for any creature to sit on the arm
of voltage on the healthy phase. Here this might have and to be in contact with the live wire.
been happened. 2.3. Effect of CT terminal opening: In one of the GIS grid and
3. The dust deposition might have tracked this due to due to space constraint and to meet the customer’s requirement,
decrease of Creepage distance. As tripping of the breaker 4 sq.mm wires were in connection to the CT terminal block.
of this limb might have been slight delayed causing the The TBs were found burnt along with cables due to CT opening
re-striking voltage and external arcing as like shown in at one of the terminal.
the figure 2.1.1. Observations:
2.2. 33 KV Bird Fault: one of the 33 KV feeder tripped on R 1. 33 KV GIS blocks are generally provided with combined
phase to ground fault. But the line was nearby to the electrical enclosed with less space area.
collection center. 2. The LCC (Local control Cubicle) panels are usually provided
Observations: as integrated part of the GIS module.
1. The 33 KV pole structure was extended with extra portion 3. In this grid Sub-station, this pattern of combined module
and the disc was connected to the internal part of the system was there with less space.
cross arm as like shown in the figure 2.2.1. 4. The secondary wires of the CT had been terminated to
2. One bird sitting on this extra portion comes in contact the terminal block in the LCC with less space.
to the live wire and electrocuted, resulting with tripping 5. But due to customer’s specific requirement, the internal
of the line. To the surprise, though the bird got burnt, wires had been provided with 4 sq. mm wires with that
but remained sticking to the conductor. limited space. The cables had also been routed in the
3. The construction design of the pole was changed with limited space region. The multi wires had also been run
no extra extension for sitting of any bird or creature. for secondary CTR control at the TBs in the LCC. So the
total system was clumsy. 2. The secondary CTR control should be at CT secondary
6. The TBs as shown in the figure 2.3.1 were also not strong Box, where space is factor to adjust.
enough to accommodate the multi-wire interconnection 2.4.1: Mistake in CT circuit: At one of 63 MVA AUTO transformer,
at on terminal. the facility of TURRET CT was available for developing of any
7. But the executor and supervisor for completion of the protection circuit. Problem developed during stability check
job, attempted the wiring and accommodated all the before commissioning of the transformer.
wires with the TBs. Observations:
8. In due course of service, it was found opening of one 1. This transformer was having two cores as the BCT (Bushing
Case Study of the month
CT terminal of the protection core during in-service CT) in each of the TURRET as like shown in the figure
condition. 2.4.1.
9. It was observed with high voltage and burning of the
particular terminal. Its further effect resulted the burning
of the cables and other adjacent TBs.
10. The root cause of such incident was due to space constraint
and accommodation of more wires in the limited space.
Technical Action:
1. The TBS were changed and 4 sq.mm wires were also
changed with 2.5 Sq.mm.
2. The space and number of TBs were reduced, due to
shifting of CTR control to the CT secondary box.
3. The number of cables were also reduced as CTR control
were shifted.
4. The shorting Link facility was also changed.
5. So the stress upon the TBs was reduced and system was 2. Each core has separate marking of s1 and s2. The wires
allowed to run smooth. connected from terminal finally marked with nomenclature
as 1s1, 1s2, 2s1, 2s2 from each of the secondary core.
Core one as 1s1 and 1s2, core 2 as 2s1 1nd 2s2.
3. The protection engineer as per the marking on the
external terminal developed the wiring connection for
the SEF (Sensitive Earth fault) relay connection as like
shown in fig 2.4.2 from core no-1. Core no 2 as not in
use was kept shorted.
4. But during stability checking, it was observed with some
peculiar behavior of reading as mentioned in the table
A.
5. R phase wire reading came ZERO, Y, B phase and neutral
reading came of same magnitude.
6. So to know the possibility of wrong connection, the joint
reading was taken by the combination wire by clamp
Fig 2.3.1 Clumsy TB Fig 2.3.2 Clean TB on ammeter. The values are mentioned in the table A.
arrangement arrangement The vector diagram, suspecting the possible interchange
Recommendation: of 1s2 and 2s1 were also drawn as shown in fig 2.4.5
1. The CT cables/ wires should be chosen as required. In 7. This was simply confirmed that some problem is there in
present days as we are using low burden numerical the R phase wire coming out of the BCT. It was suspected
relays and indicating meters, it is preferably to use 2.5 about the shorting of the terminals at BCT secondary Box.
sq.mm instead 4 sq.mm. So, BCT box was opened and found with no abnormality.