Professional Documents
Culture Documents
Herff College of Engineering Entry to the Herff College of Engineering 2015 Reinforced
2015 Reinforced Concrete Competition Concrete Competition requires:
30 in.
SWRAdjusted is computed as:
In designing the reinforced concrete beam groups may
consider the use of admixtures, various types of
SWRAdjusted SWR Cost Factor reinforcement, various types of cements and aggregates,
and non-rectangular cross-sections.
CIVL 1112 Reinforced Concrete Beam - Project Description 2/4
The reinforced concrete beam problem poses The reinforced concrete beam project schedule:
several challenges to the student:
Date Activity
February 24-26 Introduction; concrete beam #1
1. selection of the shape and size of the cross-section of
March 3-5 Break beam #1; develop concrete beam #2
the beam;
March 9-13 Spring Break
2. design of a concrete mix based on strength and
workability; March 17-19 Break beam #2; develop concrete beam #3
3. design of the reinforcement (type of reinforcement, March 24-26 Break beam #3; develop concrete beam #4
amount, and position in the beam), and March 31 and April 1-2 Break beam #4; develop final beam
4. the prediction of the SWR of the beam. April 7-9 Break final concrete beam
The cost of each beam will be estimated using the The cost of steel may be estimated as follows:
following data:
As L lb. $1,007 ton
Cost of steel 490 ft.3 ton 2,000 lb.
3
Material Cost
1,728 in. 3
Portland Type I cement $116/ton ft.
For example, if one #5 rebar in placed in the beam Consider the following mix for a cubic yard of
the steel cost is estimated as: concrete developed using the ACI mix design
procedure.
Bar # Diameter (in) As (in2)
2 0.125 0.0245 Cost of steel
3 0.375 0.11 Component Amount (lb.)
4 0.500 0.20
Water
5 0.625 0.31 (0.31 in.2 )(30in.) lb. $1,007 ton 304
6 0.750 0.44 490 ft.3 ton 2,000 lb.
1,728 in. 3 Cement 708
3
7 0.875 0.60
8 1.000 0.79 ft.
9 1.128 1.00 Coarse aggregate 1,824
10 1.270 1.27
Fine aggregate 1,131
$1.33
11 1.410 1.56
CIVL 1112 Reinforced Concrete Beam - Project Description 3/4
The cost of the concrete required for a 4 in. by 6 in. The cost of the concrete required for a 4 in. by 6 in.
by 30 in. beam is estimated as: by 30 in. beam is estimated as:
4in.(6in.)30in. 708 lb. $116 ton 4in.(6in.)30in. 1,131 lb. $10 ton
Cost of cement 3 Cost of fine aggregate 3
1,728 in. 3 27 ft . ton 2,000 lb. 1,728 in. 3 27 ft . ton 2,000 lb.
3 3
ft. ft.
$0.63 $0.09
4in.(6in.)30in. 1,824 lb. $18 ton The cost concrete is estimated as: $0.96
Cost of coarse aggregate 3 3
1,728 in. 3 27 ft . ton 2,000 lb.
ft.
The cost reinforced concrete beam is estimated as:
$0.24 $2.28
The cost adjustment for the reinforced concrete For example, if the unadjusted SWR for a beam is
beam is : 510 and the cost is $2.24, then the cost adjusted
SWR is:
If cost < $3.00 then: Cost Factor = 1
$3.00
SWRAdjusted 510 355
$4.31
CIVL 1112 Reinforced Concrete Beam - Project Description 4/4
Any questions?