Kamal Hamza Residential Building, Dubai, UAE TENDER PROGRAM 28-Oct-17 10:42

Activity ID Activity Name Original Start 2018 2019


Duration ay
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

KH Kamal Hamza
Hamz Residential Building, Dubai, UAE 456 01-Dec-17 01-Mar-19 01-Mar-19, KH Kam

KH.Al-1 Control Milestones 2 01-Dec-17 02-Dec-17 2-Dec-17, KH.Al-1 Control Milestones


A1000 Obtain Authority NOC Approvals 0 01-Dec-17 btain Authority NOC Approvals,
A1010 Issued IFC Drawings Obtain 0 01-Dec-17 sued IFC Drawings so Obtain,
A1020 Obtain building permit 0 02-Dec-17 btain building permit,

KH.Al-2 Contrac
Contractual Milestones 455 01-Dec-17 01-Mar-19 01-Mar-19, KH.Al-2
A1030 Project commencement date 0 01-Dec-17 oject commencement date,
A1040 Project completion 0 01-Mar-19 Project completion,
KH.Al-3 Prliminary
Prlimina 450 07-Dec-17 01-Mar-19 01-Mar-19, KH.Al-3

A1050 Mobilization 46 07-Dec-17 21-Jan-18 Mobilization


A1060 Priliminary 401 25-Jan-18 01-Mar-19 Priliminary
A1070 Demobilization 59 02-Jan-19 01-Mar-19 Demobilization
A1080 Obtain NOC for Shoring and Anchoring 37 20-Dec-17 25-Jan-18 Obtain NOC for Shoring and Anchoring
KH.Al-4 Engineering
Enginee & Procurement 347 20-Dec-17 01-Dec-18 01-Dec-18, KH.Al-4 Engineering & Procuremen

A1090 Prequalification submission and approval 92 20-Dec-17 21-Mar-18 Prequalification submission and approval
A1100 Material submission and approval 90 01-Feb-18 01-May-18 Material submission and approval
A1110 Shop drawing submission and approval 121 25-Jan-18 25-May-18 Shop drawing submission and approval
A1120 Procurement and delivery to site 300 05-Feb-18 01-Dec-18 Procurement and delivery to site

KH.Al-5 Provisio
Provisional Sum Item 336 15-Dec-17 15-Nov-18 15-Nov-18, KH.Al-5 Provisional Sum Item

KH.Al-5.1 Sanitary Fixture and Accessories 336 15-Dec-17 15-Nov-18 15-Nov-18, KH.Al-5.1 Sanitary Fixture and Accesso
A1130 Awarding of sanitary fixtures and accessories work package 0 15-Dec-17 Awarding of sanitary fixtures and accessories work package, 15-Dec-17
A1140 Contract finalization with the award subcontractor 31 16-Dec-17 15-Jan-18 Contract finalization with the award subcontractor
A1150 Enginnering and procurement 300 20-Jan-18 15-Nov-18 Enginnering and procurement
KH.Al-5.2 Gynasium
Gynasiu Equipment 292 15-Jan-18 02-Nov-18 02-Nov-18, KH.Al-5.2 Gynasium Equipment
A1160 Awarding of Gymnasium Equipment package 0 15-Jan-18 Awarding of Gymnasium Equipment package, 15-Jan-18
A1170 Contract finalization with the award subcontractor 37 20-Jan-18 25-Feb-18 Contract finalization with the award subcontractor
A1180 Engineering and prcurement 250 26-Feb-18 02-Nov-18 Engineering and prcurement
KH.Al-5.3 Light Fix
Fixture incl Pendant Fixture & Chandeliers 287 02-Jan-18 15-Oct-18 15-Oct-18, KH.Al-5.3 Light Fixture incl Pendant Fixture & Cha
A1190 Awarding of lighting fixtures work package 0 02-Jan-18 Awarding of lighting fixtures work package, 02-Jan-18
A1200 Contract finalization with the award subcoontractor 33 04-Jan-18 05-Feb-18 Contract finalization with the award subcoontractor
A1210 Engineering and procurement 251 07-Feb-18 15-Oct-18 Engineering and procurement
KH.Al-5.4 Service Signage Works 213 15-Jan-18 15-Aug-18 15-Aug-18, KH.Al-5.4 Service Signage Works
A1220 Awarding of service signage works package 0 15-Jan-18 Awarding of service signage works package, 15-Jan-18
A1230 Contract finalization with the award subcontractor 39 18-Jan-18 25-Feb-18 Contract finalization with the award subcontractor
A1240 Engineering and procurement 169 28-Feb-18 15-Aug-18 Engineering and procurement
KH.Al-6 Construction
Constru 339 26-Jan-18 30-Dec-18 30-Dec-18, KH.Al-6 Construction

KH.Al-6.1 Sub-Structure
Sub-Str 182 26-Jan-18 26-Jul-18 26-Jul-18, KH.Al-6.1 Sub-Structure
A1250 Shoring works 59 26-Jan-18 25-Mar-18 Shoring works
A1260 Dewatering 178 30-Jan-18 26-Jul-18 Dewatering
A1270 Excavation to formation level 40 25-Feb-18 05-Apr-18 Excavation to formation level
A1280 Basement foundation 48 08-Apr-18 25-May-18 Basement foundation
A1290 Basement walls and slab 41 26-May-18 05-Jul-18 Basement walls and slab
KH.Al-6.2 Super-Structure
Super-S 102 06-Jul-18 15-Oct-18 15-Oct-18, KH.Al-6.2 Super-Structure
A1300 GF vertical and slab 20 06-Jul-18 25-Jul-18 GF vertical and slab
A1310 1st to 4th floor vertical and slabs 73 20-Jul-18 30-Sep-18 1st to 4th floor vertical and slabs
A1320 Roof and upper roof 21 25-Sep-18 15-Oct-18 Roof and upper roof
KH.Al-6.3 Internal Finishes 108 15-Aug-18 30-Nov-18 30-Nov-18, KH.Al-6.3 Internal Finishes
A1330 Basement to roof 108 15-Aug-18 30-Nov-18 Basement to roof
KH.Al-6.4 MEP 225 20-May-18 30-Dec-18 30-Dec-18, KH.Al-6.4 MEP
A1340 Basement to roof 225 20-May-18 30-Dec-18 Basement to roof
KH.Al-6.5 External
Externa Finishes 107 15-Sep-18 30-Dec-18 30-Dec-18, KH.Al-6.5 External Finishe

Actual Level of Effort Remaining Work Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
Kamal Hamza Residential Building, Dubai, UAE TENDER PROGRAM 28-Oct-17 10:42
Activity ID Activity Name Original Start Finish 2018 2019
Duration ay
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
A1350 External Finishes 107 15-Sep-18 30-Dec-18 External Finishes
KH.1 Testing,Co
Testing,Commissioning and Handing Over 91 01-Dec-18 01-Mar-19 01-Mar-19, KH.1 T

A1360 As- built drawings and close out documents 90 01-Dec-18 28-Feb-19 As- built drawings a
A1370 Testing and commisioning 63 15-Dec-18 15-Feb-19 Testing and commisionin
A1380 Authorities handing over 58 02-Jan-19 28-Feb-19 Authorities handing
A1390 Cleaning snagging and project hand over 77 15-Dec-18 01-Mar-19 Cleaning snagging

Actual Level of Effort Remaining Work Page 2 of 2 TASK filter: All Activities