ID TaskName Duration Start Finish Predecessors

Mode Nov '20 Dec '20 Jan '21


9 16 23 30 7 14 21 28 4 11 18
1 COPPER TELLURIDE TANK (TK-V32) STEAM COIL AND 44.5 Mon 11/23/20 7:00 AM Wed 1/13/21 11:00 AM
SHELL REPLACEMENT days
2 Preparation 1 day Mon 11/23/20 7:00 AM Mon 11/23/20 4:00 PM
3 Mobilization (Assist for the withdrawal of 1 day Mon 11/23/20 7:00 AM Mon 11/23/20 4:00 PM
materials at warehouse)
4 Permitting ,Installation of Safety Signages 0.5 days Mon 11/23/20 7:00 AM Mon 11/23/20 11:00 AM 3SS
5 Lay-out, Inspection and Establish Reference point 0.5 days Mon 11/23/20 11:00 AM Mon 11/23/20 4:00 PM 4

6 Fabrication Works 6 days Mon 11/23/20 11:00 AM Mon 11/30/20 11:00 AM


7 Assist on Bending Pipes at Fabrication Area 6 days Mon 11/23/20 11:00 AM Mon 11/30/20 11:00 AM 4
8 Demolition & Installation of New Structure 18 days Mon 11/23/20 11:00 AM Mon 12/14/20 11:00 AM
9 Install Temporary Working Platforms and 2 days Mon 11/23/20 11:00 AM Wed 11/25/20 11:00 AM 4
Ladders/Scaffolding (136 cu.m)
10 Installation of Temporary supports (800 kgs.) 6 days Mon 11/23/20 11:00 AM Mon 11/30/20 11:00 AM 9SS
11 Removal/Cutting of Corroded Structural 6 days Mon 11/30/20 11:00 AM Mon 12/7/20 11:00 AM 9,10
Members (1500 Kgs)
12 Installation/Welding of new Structural Members 6 days Mon 12/7/20 11:00 AM Mon 12/14/20 11:00 AM 11
(1500 Kgs)
13 Painting of New Structural members (Primer, Tie coat 7 days Mon 12/14/20 11:00 AM Tue 12/22/20 11:00 AM
and Top Coat) (20 sq.m)
14 Painting of Primer 2 days Mon 12/14/20 11:00 AM Wed 12/16/20 11:00 AM 12
15 Painting of Tie Coat 2 days Wed 12/16/20 11:00 AM Fri 12/18/20 11:00 AM 14

Task Inactive Task Finish-only


Split Inactive Milestone External Tasks
Milestone Inactive Summary External Milestone
Slippage Manual Task Deadline
Summary Duration-only Critical
Project Summary Manual Summary Rollup Critical Split
Rolled Up Critical Manual Summary Progress
Rolled Up Critical Split Start-only
ID TaskName Duration Start Finish Predecessors
Mode Nov '20 Dec '20 Jan '21
9 16 23 30 7 14 21 28 4 11 18
16 Painting of Top Coat 2 days Fri 12/18/20 11:00 AM Mon 12/21/20 11:00 AM 15
17 Curing 1 day Mon 12/21/20 11:00 AM Tue 12/22/20 11:00 AM 14,15,16
18 Tank Repair 26 days Mon 12/14/20 11:00 AM Wed 1/13/21 11:00 AM
19 Provision of tank Supports 6 days Mon 12/14/20 11:00 AM Mon 12/21/20 11:00 AM 12
20 Lifting of tank 1 day Mon 12/21/20 11:00 AM Tue 12/22/20 11:00 AM 19
21 Cutting of Bottom Plate 2 days Tue 12/22/20 11:00 AM Thu 12/24/20 11:00 AM 20
22 Chipping of Concrete base/pedestal 3 days Thu 12/24/20 11:00 AM Mon 12/28/20 11:00 AM 21
23 Replacement of Rebars 3 days Mon 12/28/20 11:00 AM Thu 12/31/20 11:00 AM 22
24 Pouring of Concrete/Curing (1 cu.m) 1 day Thu 12/31/20 11:00 AM Fri 1/1/21 11:00 AM 22,23
25 Acid Proofing Installation 4 days Fri 1/1/21 11:00 AM Wed 1/6/21 11:00 AM 24
26 Installation of PVC Plates 2 days Thu 12/24/20 11:00 AM Sat 12/26/20 11:00 AM 21
27 Welding of new bottom plate and installation of 5 days Sat 12/26/20 11:00 AM Fri 1/1/21 11:00 AM 26
porcelain bricks
28 Removal/Cutting of Existing steam coils 3 days Fri 1/1/21 11:00 AM Tue 1/5/21 11:00 AM 27
29 Transfer of Pipes to Inside of Tank 2 days Tue 1/5/21 11:00 AM Thu 1/7/21 11:00 AM 28
30 Assemble of pipes 2 days Tue 1/5/21 11:00 AM Thu 1/7/21 11:00 AM 29SS
31 Installation/Welding of Pipes (14 Joints) 4 days Thu 1/7/21 11:00 AM Tue 1/12/21 11:00 AM 29,30
32 Housekeeping 1 day Tue 1/12/21 11:00 AM Wed 1/13/21 11:00 AM 31

Task Inactive Task Finish-only


Split Inactive Milestone External Tasks
Milestone Inactive Summary External Milestone
Slippage Manual Task Deadline
Summary Duration-only Critical
Project Summary Manual Summary Rollup Critical Split
Rolled Up Critical Manual Summary Progress
Rolled Up Critical Split Start-only
Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21 Oct '21 Nov '21 Dec '21 Jan '22 Feb '22
18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7

Task Inactive Task Finish-only


Split Inactive Milestone External Tasks
Milestone Inactive Summary External Milestone
Slippage Manual Task Deadline
Summary Duration-only Critical
Project Summary Manual Summary Rollup Critical Split
Rolled Up Critical Manual Summary Progress
Rolled Up Critical Split Start-only
Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21 Oct '21 Nov '21 Dec '21 Jan '22 Feb '22
18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7

Task Inactive Task Finish-only


Split Inactive Milestone External Tasks
Milestone Inactive Summary External Milestone
Slippage Manual Task Deadline
Summary Duration-only Critical
Project Summary Manual Summary Rollup Critical Split
Rolled Up Critical Manual Summary Progress
Rolled Up Critical Split Start-only

You might also like