You are on page 1of 6

Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.

2020

SR. NO. ZONE AREA NAME HVAC completion Date PlumbingDate


completion Fire Completion Date Electrical Completion
Date
Civil Work completion
Date Falseceiling Status REMARKS

Ground floor

COMPLETED BUT COMPLETED BUT COMPLETED BUT


1 GF-ZONE-1 Nulcear Medicine Hold CHECKLIST NOT CHECKLIST NOT CHECKLIST NOT HOLD
SUBMITTED SUBMITTED SUBMITTED

2 GF-ZONE-2 Admitting services COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED

Central Cooridoor + COMPLETED BUT COMPLETED BUT


3 GF-ZONE-3 elevator lobbies COMPLETED COMPLETED COMPLETED CHECKLIST NOT CHECKLIST NOT
SUBMITTED SUBMITTED

4 GF-ZONE-4 / PART-1 Dialysis COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED

5 GF-ZONE-4 / PART-1A Café + seating Lounge COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED

COMPLETED BUT
6 GF-ZONE-4 / PART-2 Administration 25.12.20 COMPLETED COMPLETED COMPLETED CHECKLIST NOT
SUBMITTED
COMPLETED BUT COMPLETED BUT COMPLETED BUT Date not provided by
7 GF-ZONE-5 MRI & Imaging Hold CHECKLIST NOT CHECKLIST NOT CHECKLIST NOT civil team
SUBMITTED SUBMITTED SUBMITTED

Central Cooridoor + Date not provided by Date not provided by Date not provided by
8 GF-ZONE-6 elevator lobbies COMPLETED PHE team FF team Hold civil team

COMPLETED BUT
9 GF-ZONE-7 Labs COMPLETED COMPLETED COMPLETED CHECKLIST NOT Date not provided by
SUBMITTED civil team

Date not provided by Date not provided by COMPLETED BUT Date not provided by
10 GF-ZONE-8 Emergency Hold PHE team FF team CHECKLIST NOT civil team
SUBMITTED

80% completed. Date not provided by


11 GF-ZONE-9 Auditorium Hold 15.12.20 15.12.20 Power work Hold civil team

12 GF-ZONE-10 Kitchen Hold Hold Hold Hold HOLD

13 GF-ZONE-11 Maintainence 25.12.20 15.12.20 15.12.20 Date not provided by Date not provided by
civil team civil team

14 GF-ZONE-12 Laundry Hold Hold Hold Hold HOLD

First floor
Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.2020

SR. NO. ZONE AREA NAME HVAC completion Date PlumbingDate


completion Fire Completion Date Electrical Completion
Date
Civil Work completion
Date Falseceiling Status REMARKS

COMPLETED BUT Date not provided by


1 1F-ZONE-1 Endoscopy + cath Hold COMPLETED COMPLETED CHECKLIST NOT
SUBMITTED civil team

Conveyed to Civil team for


2 1F-ZONE-2 ICU COMPLETED COMPLETED COMPLETED COMPLETED 02.11.20 WIP parallel completion

Central Cooridoor + COMPLETED BUT


3 1F-ZONE-3 elevator lobbies 15.12.20 COMPLETED COMPLETED CHECKLIST NOT 18.11.20
SUBMITTED

4 1F-ZONE-4 / PART-1 ICU COMPLETED COMPLETED COMPLETED COMPLETED 02.11.20 WIP Conveyed to Civil team for
parallel completion

Conveyed to Civil team for


5 1F-ZONE-4 / PART-2 Pre Op area COMPLETED COMPLETED COMPLETED COMPLETED 04.11.20 WIP parallel completion

6 1F-ZONE-5 OT Hold Date not provided by Date not provided by 07.12.20 Date not provided by
PHE team FF team civil team

7 1F-ZONE-6 Central Cooridoor + 15.12.20 COMPLETED COMPLETED 07.12.20 Date not provided by
elevator lobbies civil team

COMPLETED BUT
8 1F-ZONE-7 Endoscopy Hold COMPLETED COMPLETED CHECKLIST NOT Date not provided by
SUBMITTED civil team

9 1F-ZONE-8 OT + Post OP Hold Date not provided by Date not provided by 07.12.20 Date not provided by
PHE team FF team civil team

Date not provided by Date not provided by COMPLETED BUT Date not provided by
10 1F-ZONE-9 Dining Hold PHE team FF team CHECKLIST NOT civil team
SUBMITTED
COMPLETED BUT
11 1F-ZONE-10 Pharmacy Hold COMPLETED COMPLETED CHECKLIST NOT Date not provided by
SUBMITTED civil team

Anesthesia support + Date not provided by


12 1F-ZONE-11 staff lounge Hold 15.12.20 15.12.20 07.12.20 civil team

Date not provided by


13 1F-ZONE-12 CSSD Hold COMPLETED COMPLETED Hold civil team
Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.2020

SR. NO. ZONE AREA NAME HVAC completion Date PlumbingDate


completion Fire Completion Date Electrical Completion
Date
Civil Work completion
Date Falseceiling Status REMARKS

Second Floor

Conveyed to Civil team for


1 2F-ZONE-1 Staff & Prof. room COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED WIP parallel completion

2 2F-ZONE-2 ICU COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED WIP Conveyed to Civil team for
parallel completion

Central Cooridoor + Date not provided by


3 2F-ZONE-3 elevator lobbies 10.12.20 COMPLETED COMPLETED 05.12.20 civil team

4 2F-ZONE-4 Staff & Prof. room COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED WIP Conveyed to Civil team for
parallel completion

Central Cooridoor + COMPLETED BUT Date not provided by Conveyed to Civil team for
6 2F-ZONE-6 elevator lobbies 10.12.20 COMPLETED COMPLETED CHECKLIST NOT civil team parallel completion
SUBMITTED
COMPLETED BUT Conveyed to Civil team for
7 2F-ZONE-7 ICU COMPLETED COMPLETED COMPLETED CHECKLIST NOT COMPLETED WIP
SUBMITTED parallel completion

8 2F-ZONE-8 Staff & Prof. room 25.09.2020 COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED Conveyed to Civil team for
parallel completion
Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.2020

SR. NO. ZONE AREA NAME HVAC completion Date PlumbingDate


completion Fire Completion Date Electrical Completion
Date
Civil Work completion
Date Falseceiling Status REMARKS

Third Floor

36 S.S BEDS Date not provided by Conveyed to Civil team for


1 3F-ZONE-1 COMPLETED COMPLETED COMPLETED COMPLETED parallel completion
MALE/FEMALE WARD civil team 01/11/20

COMPLETED BUT Conveyed to Civil team for


2 3F-ZONE-2 55 S.S BEDS FEMALE 03.12.20 COMPLETED COMPLETED CHECKLIST NOT Date not provided by parallel completion
WARD SUBMITTED civil team 01/11/20

Central Cooridoor + COMPLETED BUT Date not provided by


3 3F-ZONE-3 elevator lobbies 09.12.20 COMPLETED COMPLETED CHECKLIST NOT civil team
SUBMITTED
COMPLETED BUT Date not provided by Conveyed to Civil team for
4 3F-ZONE-4 NICU Hold COMPLETED COMPLETED CHECKLIST NOT
SUBMITTED civil team parallel completion

Date not provided by


5 3F-ZONE-5 Birthing Centre Hold COMPLETED COMPLETED 05.12.20 civil team

Central Cooridoor + COMPLETED BUT Date not provided by


6 3F-ZONE-6 09.12.20 COMPLETED COMPLETED CHECKLIST NOT
elevator lobbies SUBMITTED civil team

55 S.S BEDS FEMALE COMPLETED BUT Date not provided by Conveyed to Civil team for
7 3F-ZONE-7 WARD COMPLETED COMPLETED COMPLETED CHECKLIST NOT civil team parallel completion
SUBMITTED 01/11/20

36 S.S BEDS COMPLETED BUT COMPLETED BUT Date not provided by Conveyed to Civil team for
8 3F-ZONE-8 MALE/FEMALE WARD CHECKLIST NOT 15.12.20 15.12.20 CHECKLIST NOT civil team parallel completion
SUBMITTED SUBMITTED 01/11/20
Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.2020

SR. NO. ZONE AREA NAME HVAC completion Date PlumbingDate


completion Fire Completion Date Electrical Completion
Date
Civil Work completion
Date Falseceiling Status REMARKS

Fourth Floor

Date not provided by


1 4F-ZONE-1 56 Beds female ward 10.12.20 10.12.20 10.12.20 13.12.20 civil team

2 4F-ZONE-2 55 Gen bed male Ward 10.12.20 05.12.20 05.12.20 13.12.20 07.12.20

Central Cooridoor + COMPLETED BUT Date not provided by


3 4F-ZONE-3 elevator lobbies 15.12.20 05.12.20 05.12.20 CHECKLIST NOT civil team
SUBMITTED
COMPLETED BUT Date not provided by Conveyed to Civil team for
4 4F-ZONE-4 58 Gen bed male Ward 05.12.20 COMPLETED COMPLETED CHECKLIST NOT parallel completion
SUBMITTED civil team 01/11/20

58 Gen bed female


5 4F-ZONE-5 Ward 15.12.20 COMPLETED COMPLETED 05.12.20 07.12.20

Central Cooridoor + COMPLETED BUT


6 4F-ZONE-6 15.12.20 07.12.20 07.12.20 CHECKLIST NOT 07.12.20
elevator lobbies SUBMITTED

56 Gen bed female COMPLETED BUT COMPLETED BUT


7 4F-ZONE-7 Ward CHECKLIST NOT 02.12.20 02.12.20 CHECKLIST NOT 07.12.20
SUBMITTED SUBMITTED

COMPLETED BUT
8 4F-ZONE-8 56 Gen bed male Ward 05.12.20 10.12.20 10.12.20 CHECKLIST NOT 07.12.20
SUBMITTED
Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.2020

SR. NO. ZONE AREA NAME HVAC completion Date PlumbingDate


completion Fire Completion Date Electrical Completion
Date
Civil Work completion
Date Falseceiling Status REMARKS

Fifth Floor

52 SS Bed Female
1 5F-ZONE-1 Ward 15.12.20 15.12.20 15.12.20 10.12.20 22.12.20

2 5F-ZONE-2 51 SS Bed male Ward 15.12.20 15.12.20 15.12.20 10.12.20 17.12.20

Central Cooridoor + COMPLETED BUT


3 5F-ZONE-3 elevator lobbies 20.12.20 15.12.20 15.12.20 CHECKLIST NOT 22.12.20
SUBMITTED

58 Gen bed SS male COMPLETED BUT Date not provided by


4 5F-ZONE-4 CHECKLIST NOT 07.12.20 07.12.20 07.12.20
Ward SUBMITTED Electrical team

Central Cooridoor +
6 5F-ZONE-6 elevator lobbies 20.12.20 15.12.20 15.12.20 05.12.20 23.12.20

52 SS Bed Female COMPLETED BUT


7 5F-ZONE-7 CHECKLIST NOT 07.12.20 07.12.20 30.11.20 08.12.20
Ward SUBMITTED

8 5F-ZONE-8 52 SS Bed male Ward 30.12.20 15.12.20 15.12.20 10.12.20 22.12.20

You might also like