2020
Ground floor
5 GF-ZONE-4 / PART-1A Café + seating Lounge COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED
COMPLETED BUT
6 GF-ZONE-4 / PART-2 Administration 25.12.20 COMPLETED COMPLETED COMPLETED CHECKLIST NOT
SUBMITTED
COMPLETED BUT COMPLETED BUT COMPLETED BUT Date not provided by
7 GF-ZONE-5 MRI & Imaging Hold CHECKLIST NOT CHECKLIST NOT CHECKLIST NOT civil team
SUBMITTED SUBMITTED SUBMITTED
Central Cooridoor + Date not provided by Date not provided by Date not provided by
8 GF-ZONE-6 elevator lobbies COMPLETED PHE team FF team Hold civil team
COMPLETED BUT
9 GF-ZONE-7 Labs COMPLETED COMPLETED COMPLETED CHECKLIST NOT Date not provided by
SUBMITTED civil team
Date not provided by Date not provided by COMPLETED BUT Date not provided by
10 GF-ZONE-8 Emergency Hold PHE team FF team CHECKLIST NOT civil team
SUBMITTED
13 GF-ZONE-11 Maintainence 25.12.20 15.12.20 15.12.20 Date not provided by Date not provided by
civil team civil team
First floor
Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.2020
4 1F-ZONE-4 / PART-1 ICU COMPLETED COMPLETED COMPLETED COMPLETED 02.11.20 WIP Conveyed to Civil team for
parallel completion
6 1F-ZONE-5 OT Hold Date not provided by Date not provided by 07.12.20 Date not provided by
PHE team FF team civil team
7 1F-ZONE-6 Central Cooridoor + 15.12.20 COMPLETED COMPLETED 07.12.20 Date not provided by
elevator lobbies civil team
COMPLETED BUT
8 1F-ZONE-7 Endoscopy Hold COMPLETED COMPLETED CHECKLIST NOT Date not provided by
SUBMITTED civil team
9 1F-ZONE-8 OT + Post OP Hold Date not provided by Date not provided by 07.12.20 Date not provided by
PHE team FF team civil team
Date not provided by Date not provided by COMPLETED BUT Date not provided by
10 1F-ZONE-9 Dining Hold PHE team FF team CHECKLIST NOT civil team
SUBMITTED
COMPLETED BUT
11 1F-ZONE-10 Pharmacy Hold COMPLETED COMPLETED CHECKLIST NOT Date not provided by
SUBMITTED civil team
Second Floor
2 2F-ZONE-2 ICU COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED WIP Conveyed to Civil team for
parallel completion
4 2F-ZONE-4 Staff & Prof. room COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED WIP Conveyed to Civil team for
parallel completion
Central Cooridoor + COMPLETED BUT Date not provided by Conveyed to Civil team for
6 2F-ZONE-6 elevator lobbies 10.12.20 COMPLETED COMPLETED CHECKLIST NOT civil team parallel completion
SUBMITTED
COMPLETED BUT Conveyed to Civil team for
7 2F-ZONE-7 ICU COMPLETED COMPLETED COMPLETED CHECKLIST NOT COMPLETED WIP
SUBMITTED parallel completion
8 2F-ZONE-8 Staff & Prof. room 25.09.2020 COMPLETED COMPLETED COMPLETED COMPLETED COMPLETED Conveyed to Civil team for
parallel completion
Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.2020
Third Floor
55 S.S BEDS FEMALE COMPLETED BUT Date not provided by Conveyed to Civil team for
7 3F-ZONE-7 WARD COMPLETED COMPLETED COMPLETED CHECKLIST NOT civil team parallel completion
SUBMITTED 01/11/20
36 S.S BEDS COMPLETED BUT COMPLETED BUT Date not provided by Conveyed to Civil team for
8 3F-ZONE-8 MALE/FEMALE WARD CHECKLIST NOT 15.12.20 15.12.20 CHECKLIST NOT civil team parallel completion
SUBMITTED SUBMITTED 01/11/20
Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.2020
Fourth Floor
2 4F-ZONE-2 55 Gen bed male Ward 10.12.20 05.12.20 05.12.20 13.12.20 07.12.20
COMPLETED BUT
8 4F-ZONE-8 56 Gen bed male Ward 05.12.20 10.12.20 10.12.20 CHECKLIST NOT 07.12.20
SUBMITTED
Completion Schedule of IPD falseceiling work, AIIMS DATE:- 03.12.2020
Fifth Floor
52 SS Bed Female
1 5F-ZONE-1 Ward 15.12.20 15.12.20 15.12.20 10.12.20 22.12.20
Central Cooridoor +
6 5F-ZONE-6 elevator lobbies 20.12.20 15.12.20 15.12.20 05.12.20 23.12.20