Professional Documents
Culture Documents
CA Ruling:
Facts: We rule in the negative. It is stated explicitly under Art. 2044 of the Civil Code that
the finality of the arbitrators’ award is not absolute and without exceptions. Where
the conditions described in Articles 2038, 2039 and 2040 applicable to both
Petitioner Chung Fu Industries (Philippines) and private respondent Roblecor
compromises and arbitrations are obtaining, the arbitrators’ award may be annulled
Philippines, Inc. forged a construction agreement whereby respondent contractor
or rescinded. Additionally, under Sections 24 and 25 of the Arbitration Law, there
committed to construct and finish petitioner corporation’s industrial/factory
are grounds for vacating, modifying or rescinding an arbitrator’s award. Thus, if and
complex. In the event of disputes arising from the performance of subject contract,
when the factual circumstances referred to in the above-cited provisions are
it was stipulated therein that the issue(s) shall be submitted for resolution before a
present, judicial review of the award is properly warranted.
single arbitrator chosen by both parties. Roblecor filed a petition for Compulsory
Arbitration with prayer for Temporary Restraining Order before respondent RTC to
claim the unsatisfied account and unpaid progress billings. Chung Fu moved to This is where the proper remedy is certiorari under Rule 65 of the Revised Rules of
dismiss the petition and further prayed for the quashing of the restraining order. Court. It is to be borne in mind, however, that this action will lie only where a grave
Subsequent negotiations between the parties eventually led to the formulation of abuse of discretion or an act without or in excess of jurisdiction on the part of the
an arbitration agreement which, among others, provides: The parties mutually voluntary arbitrator is clearly shown. It should be stressed, too, that voluntary
agree that the decision of the arbitrator shall be final and unappealable. arbitrators, by the nature of their functions, act in a quasi-judicial capacity. It stands
Therefore, there shall be no further judicial recourse if either party disagrees with to reason, therefore, that their decisions should not be beyond the scope of the
the whole or any part of the arbitrator’s award. Respondent RTC approved the power of judicial review of this Court.
arbitration agreement and thereafter, Engr. Willardo Asuncion was appointed as In the case at bar, petitioners assailed the arbitral award on the following grounds,
the sole arbitrator. Arbitrator Asuncion ordered petitioner to immediately pay most of which allege error on the part of the arbitrator in granting compensation
respondent contractor and further declared the award as final and unappealable. for various items which apparently are disputed by said petitioners. After closely
Roblecor then moved for the confirmation of said award which was accordingly studying the list of errors, as well as petitioners’ discussion of the same in their
confirmed and a writ of execution granted to it. Meanwhile, Chung Fu moved to Motion to Remand Case For Further Hearing and Reconsideration and Opposition to
remand the case for further hearing and asked for a reconsideration of the Motion for Confirmation of Award, we find that petitioners have amply made out a
judgment award claiming that Arbitrator Asuncion committed twelve (12) instances case where the voluntary arbitrator failed to apply the terms and provisions of the
of grave error by disregarding the provisions of the parties’ contract. Chung Fu’s Construction Agreement which forms part of the law applicable as between the
Motion was denied and similarly its motion for reconsiderationn. Chung Fu elevated parties, thus committing a grave abuse of discretion. Furthermore, in granting
the case via a petition for certiorari to respondent CA. The respondent appellate unjustified extra compensation to respondent for several items, he exceeded his
court concurred with the findings and conclusions of respondent trial court. A powers — all of which would have constituted ground for vacating the award under
motion for reconsideration of said resolution was filed by petitioner, but was Section 24 (d) of the Arbitration Law.
similarly denied.
Wherefore, the petition is granted. The Resolutions of the CA as well as the Orders
Issue: of respondent RTC are hereby SET ASIDE. Accordingly, this case is REMANDED to the
court of origin for further hearing on this matter. All incidents arising therefrom are
reverted to the status quo ante until such time as the trial court shall have passed
Whether or not petitioners are estopped from questioning the arbitration award
upon the merits of this case.
allegedly in view of the stipulations in the parties’ arbitration agreement that “the
decision of the arbitrator shall be final and unappealable” and that “there shall be
no further judicial recourse if either party disagrees with the whole or any part of
the arbitrator’s award.”
JORGE GONZALES and PANEL OF ARBITRATORS vs. CLIMAX MINING LTD., CLIMAX- In La Naval Drug Corporation v. Court of Appeals, the Court held that R.A. No. 876
ARIMCO MINING CORP. and AUSTRALASIAN PHILIPPINES MINING INC., G.R. explicitly confines the court's authority only to the determination of whether or not
No. 161957, January 22, 2007 there is an agreement in writing providing for arbitration. In the affirmative, the
statute ordains that the court shall issue an order "summarily directing the parties
Facts: This is a consolidation of two petitions rooted in the same disputed to proceed with the arbitration in accordance with the terms thereof." If the court,
Addendum Contract entered into by the parties. upon the other hand, finds that no such agreement exists, "the proceeding shall be
dismissed." The cited case also stressed that the proceedings are summary in
In one case, the Court held that the DENR Panel of Arbitrators had no jurisdiction nature.
over the complaint for the annulment of the Addendum Contract on grounds of
fraud and violation of the Constitution and that the action should have been Implicit in the summary nature of the judicial proceedings is the separable or
brought before the regular courts as it involved judicial issues. independent character of the arbitration clause or agreement.
Gonzales averred that the DENR Panel of Arbitrators Has jurisdiction because the The doctrine of separability or severability enunciates that an arbitration agreement
case involves a mining dispute that properly falls within the ambit of the Panel’s is independent of the main contract. The arbitration agreement is to be treated as
authority. a separate agreement and the arbitration agreement does not automatically
terminate when the contract of which it is part comes to an end.
Respondents Climax Mining Ltd., et al., on the other hand, seek
reconsideration/clarification on the decision holding that the case should not be The separability of the arbitration agreement is especially significant to the
brought for arbitration under R.A. No. 876. They argued that the arbitration clause determination of whether the invalidity of the main contract also nullifies the
in the Addendum Contract should be treated as an agreement independent of the arbitration clause. Indeed, the doctrine denotes that the invalidity of the main
other terms of the contract, and that a claimed rescission of the main contract does contract, also referred to as the “container” contract, does not affect the validity of
not avoid the duty to arbitrate. the arbitration agreement. Irrespective of the fact that the main contract is invalid,
the arbitration clause/agreement still remains valid and enforceable.
On another case, Gonzales challenged the order of the RTC requiring him to
proceed with the arbitration proceedings while the complaint for the nullification of The validity of the contract containing the agreement to submit to arbitration does
the Addendum Contract was pending before the DENR Panel of Arbitrators. He not affect the applicability of the arbitration clause itself. A contrary ruling would
contended that any issue as to the nullity, inoperativeness, or incapability of suggest that a party’s mere repudiation of the main contract is sufficient to avoid
performance of the arbitration clause/agreement raised by one of the parties to the arbitration. That is exactly the situation that the separability doctrine, as well as
alleged arbitration agreement must be determined by the court prior to referring jurisprudence applying it, seeks to avoid.
them to arbitration.
The Court added that when it declared that the case should not be brought for
While Climax-Arimco contended that an application to compel arbitration under arbitration, it should be clarified that the case referred to is the case actually filed
Sec. 6 of R.A. No. 876 confers on the trial court only a limited and special by Gonzales before the DENR Panel of Arbitrators, which was for the nullification of
jurisdiction, i.e., a jurisdiction solely to determine (a) whether or not the parties the main contract on the ground of fraud, as it had already been determined that
have a written contract to arbitrate, and (b) if the defendant has failed to comply the case should have been brought before the regular courts involving as it did
with that contract. judicial issues.
Issue: Whether or not arbitration is proper even though issues of validity and
nullity of the Addendum Contract and, consequently, of the arbitration clause were
raised.
Ruling: Positive.
guidance by this court in Batangas Transportation Company vs. Orlanes (52 Phil.,
455). If a route that was not entirely parallel in 1928 engendered ruinous
competition it is hard to understand why a more parallel route would not bring
improper competition in 1931. The Pasay Transportation Company, Inc., lays great
G.R. No. L-36893 February 24, 1933 stress upon the fact that its right to operate was not formally terminated, and
insists that it has a property right of value that can only be taken away after
MANILA ELECTRIC COMPANY, Petitioner-Appellant, vs. PASAY TRANSPORTATION hearing. (Bohol Land Transportation Co. vs. Jureidini, 53 Phil., 560.) It does not
COMPANY, INC., Respondent-Appellee. regard the other side of the picture that by receiving a grant it owes a duty to the
public to comply with the conditions and duties of the grant. It likewise treats of no
moment that it only used the permission in a meager way for a couple of days when
Ross, Lawrence & Selph and Guillermo Cabrera for appellant.
it asked for suspension and for almost three years it flouted and set at naught clear
Rivera and Francisco and L. D. Lockwood for appellee.
instructions of the Public Service Commission to resume operation under the
penalty of having its certificate cancelled. It made no investment for equipment and
STREET,HULL, J.: risked nothing trying to develop business. On September 18, 1931, it had at most a
mere technical right (Reyes vs. Orlanes & Banaag Transit Co., G. R. No. 35562) 1 The
The Pasay Transportation Company was granted by an order of the Public Service commission without any hearing, did not permit the resumption of the service but,
Commission, dated October 5, 1928, a certificate of public convenience and in fact, authorized the inauguration of a new line and to call such an action a
necessity for the operation of an auto-truck service along certain streets in the City modification of the certificate heretofore issued is hardly a recital of the true facts.
of Manila between the Divisoria Market and Velasquez. After a few days partial The orders of the commission of September 22, 1931, being issued without any
operation the company requested permission of the Public Service Commission to hearing and without receipt of any evidence, must be vacated and set aside as this
suspend operation of that line on account of the ruinous competition it was court upon review can not state that they are reasonably supported by the
meeting from the Manila Electric Company. On December 29, 1928, the permission evidence. With costs against the respondent and appellee. 2 So ordered.
was granted with the statement that if within slightly over thirty days, namely
January 31, 1929, the Pasay Transportation Company has not resumed its service on
said line they would proceed to the cancellation of the certificate involved. No
further action was taken by either the Pasay Transportation Company or the Public
Service Commission until September 17, 1931, when the company notified the
commission that they were going to resume operation on this line. On the 18th of
September, 1931, the company asked for a modification of the route formerly given
to a route that virtually duplicates that maintained by the Manila Electric Company
for over two years preceding and also requested authority to reduce their fares.
Without any hearing the Public Service Commission on September 22, 1931,
granted the requests of the Pasay Transportation Company, and the next day the
Manila Electric Company filed a motion requesting the revocation of the approval of
the commission of September 22, 1931, and that the order of December 29, 1928
be enforced. This motion was denied and the Manila Electric Company brings the
case here for review.chanroblesvirtualawlibrary chanrobles virtual law library
Formerly the Public Service Commission adopted the sound policy that duplicate
bus service through the crowded and narrow streets of the City of Manila would not
be in the public interest and permitted joint use of streets only when they were for
a short distance and merely incidental to the main route. In their present orders
they have, without any hearing and without taking any evidence whatsoever,
disregarded not only this sound principle, but also the principles laid down for their
rice cargo from abroad to the Philippines. These 2 isolated transactions do not
constitute engaging in business in the Philippines within the purview of Sections 68
and 69 of the Corporation Law so as to bar Eastboard from seeking redress in our
courts.
EASTBOARD NAVIGATION v. JUAN YSMAEL CO., INC.
G.R. No. L-9090 | September 1, 1957 (2) The defense of Ysmael Co. that the Decree may not be enforced in the
Philippines is predicated on the alleged fact that it was never served with notice,
Doctrine: The law of the forum governs procedural matters (such as notice summons, or process relative to the submission of the award of the arbitrators to
requirements). The law of the state where a foreign judgment is sought to be New York court, invoking the U.S. Arbitration Act. The law invoked, however, does
enforced cannot be invoked to impugn the validity of the proceedings where the not sustain Ysmael Co. pretense since the Arbitration Act does not necessarily
foreign judgment was made. Also, a foreign corporation has capacity to sue even require that service of notice of the application for confirmation be made on the
without a license to transact business if it is not engaged in business in the adverse party himself (in case of a non-resident), it being sufficient that it be made
Philippines. upon his attorney. In this case, a copy of notice of submission of the award to the
District Court of New York was served upon Ysmael Co.’s counsel who in due time
Facts: Juan Ysmael Co., Inc (Philippine corporation), through K. H. Hemady (its made of record their appearance and actually appeared when the case was heard. It
president and general manager), chartered Eastboard Navigation’s (Canadian is also significant that Ysmael Co.’s counsel never impugned the jurisdiction of the
corporation) vessel to load a cargo of scrap iron in the Philippines for Buenos Aires. court over defendant nor did they ever plead before it that they were bereft of
The charter party agreement contained a typewritten clause providing for authority to represent Ysmael Co. It cannot therefore defeat the effect of this
compulsory arbitration in the state of New York, in case of any disputes that may decision by alleging want of jurisdiction, or want of notice.
arise based on their agreement.
A dispute arose regarding the liability of Ysmael Co., Inc. for the payment of freight
and demurrage. An arbitration agreement was eventually executed in New York
between the 2 parties. The arbitration agreement was then presented by Eastboard
= to the U.S. District Court in New York for confirmation where said Court confirmed
and issued an Order and Final Decree.
Eastboard then brought this action in the Philippines to enforce the “Order and
Final Decree”. Ysmael Co. however argues that since Eastboard Navigation is a
foreign corporation without a license to do business in the Philippines, it has no
capacity to sue in this jurisdiction. Note that the stipulation of facts of the parties
stated that this transaction was the first business undertaken by Eastboard
Navigation in the Philippines.
Issues: (1) Whether Eastboard has capacity to sue in the Philippines? - YES
(2) Whether the court may enforce the Decree issued by the New York
District Court. - YES
Facts:
Petitioner filed with the RTC of Pasig a complaint for collection of the balance due
under the construction agreement. Shangri-la filed a motion to suspend
proceedings alleging that the formal trade contract for the construction of the
project provided for a clause requiring prior resort to arbitration before judicial
intervention could be invoked in any dispute arising from the contract. Petitioner
opposed said motion claiming that there was no formal contract between the
parties although they entered into an agreement defining their rights and
obligations in undertaking the project.
ISSUE
HELD
The Court finds that, upon a scrutiny of the records of this case, these requisites
were complied with in the contract in question. The Articles of Agreement, which
1. Whether or not there exists a controversy/dispute between Petitioner and
Respondent regarding the interpretation and implementation of the
Subcontract Agreement that requires prior recourse to voluntary
arbitration?;
2. In the affirmative, whether or not there is a need to file a request first with
LM Power Engineering Corporation vs. Capitol Industrial Construction Groups, the CIAC in order to vest it with jurisdiction to decide a construction
Inc. G.R. No. 141833 March 26, 2003) dispute?
RTC denied the Motion to Dismiss on the ground that the dispute did not involve In the instant case, the Subcontract has the following arbitral clause:
the interpretation or the implementation of the Agreement and was, therefore, not
covered by the arbitral clause. The RTC ruled that the take-over of some work items “6. The Parties hereto agree that any dispute or conflict
by Respondent was not equivalent to a termination, but a mere modification, of the as regards to interpretation and implementation of this
Subcontract. The latter was ordered to give full payment for the work completed by Agreement which cannot be settled between [respondent] and
Petitioner. [petitioner] amicably shall be settled by means of arbitration x x
x.”
CA reversed on appeal the RTC ruling and ordered the referral of the case to
arbitration. The CA held as arbitrable the issue of whether Respondent’s take-over Clearly, the resolution of the dispute between the parties herein requires a
of some work items had been intended to be a termination of the original contract referral to the provisions of their Agreement. Within the scope of the arbitration
under Letter “K” of the Subcontract. clause are discrepancies as to the amount of advances and billable
accomplishments, the application of the provision on termination, and the
Petitioner elevated the case to SC. consequent set-off of expenses.
ISSUES:
A review of the factual allegations of the parties reveals that they differ on the reiterated in National Irrigation Administration v. Court of Appeals [1999], from
following questions, the resolutions of which lies in the interpretation of the which SC quote thus:
provisions of the Subcontract Agreement:
“Under the present Rules of Procedure, for a particular
1. Did a take-over/termination occur? construction contract to fall within the jurisdiction of CIAC, it is merely
required that the parties agree to submit the same to voluntary arbitration
2. May the expenses incurred by Respondent in the take-over be set off unlike in the original version of Section 1, as applied in the Tesco case, the
against the amounts it owed Petitioner? law as it now stands does not provide that the parties should agree to
submit disputes arising from their agreement specifically to the CIAC for
3. How much were the advances and billable accomplishments? the latter to acquire jurisdiction over the same. Rather, it is plain and clear
that as long as the parties agree to submit to voluntary arbitration,
regardless of what forum they may choose, their agreement will fall within
Being an inexpensive, speedy and amicable method of settling disputes,
the jurisdiction of the CIAC, such that, even if they specifically choose
arbitration — along with mediation, conciliation and negotiation — is encouraged
another forum, the parties will not be precluded from electing to submit
by the SC. Aside from unclogging judicial dockets, arbitration also hastens the
their dispute before the CIAC because this right has been vested upon each
resolution of disputes, especially of the commercial kind. It is thus regarded as the
party by law, i.e., E.O. No. 1008.”
“wave of the future” in international civil and commercial disputes. Brushing aside a
contractual agreement calling for arbitration between the parties would be a step
backward. Clearly, there is no more need to file a request with the CIAC in order to
vest it with jurisdiction to decide a construction dispute.
Consistent with the above-mentioned policy of encouraging alternative
dispute resolution methods, courts should liberally construe arbitration clauses. The arbitral clause in the Agreement is a commitment on the part of the
Provided such clause is susceptible of an interpretation that covers the asserted parties to submit to arbitration the disputes covered therein. Because that clause is
dispute, an order to arbitrate should be granted. Any doubt should be resolved in binding, they are expected to abide by it in good faith. And because it covers the
favor of arbitration. dispute between the parties in the present case, either of them may compel the
other to arbitrate.
2.
Facts: RATIO:
Pursuant to a contract of sale executed between Puromines Inc (petitioner) Yes, petitioner is bound by the arbitration clause provided for in the
and Philipp Brothers Oceanic, Inc., (private respondent) as charterer of M/V Liliana contract. Arbitration has been held valid and constitutional. Even before the
Dimitrova, 3 Bills of Lading were executed bound for the Iloilo and Manila of 15,000 enactment of RA no. 876, the Supreme Court has countenanced the settlement of
metric tons of prilled urea. disputes through arbitration. The rule now is that unless the agreement is such
absolutely close the doors of the courts against the parties, which agreement would
However, upon reaching the port of Manila it was found out that the be void, the courts will look with favor upon such amicable arrangements and will
shipment (urea) were already contaminated with rust and dirt. only interfere with great reluctance to anticipate or nullify the action of the
arbitrator.
This prompted petitioner to file an action for breach of contract of carriage
against Maritime Factors, Inc as ship agent here in the Philippines for the owners of At the case at bar, the sales contract is comprehensive enough to include
M/V Liliana in the complaint moreover private respondent Philipp Brothers Oceanic claims for damages arising from carriage and delivery of the goods. Puromines, Inc
Inc., was impleaded as charterer of the said vessel. derived his right to the cargo from the bill of lading which is the contract of
affreihtment together with the sales contract. Consequently, Puromines is bound by
Private respondent, Philipp Brothers, instead of filing its answer filed a the provisions and terms of the bill of lading and of the arbitration clause.
motion to dismiss on the ground of no cause of action. Private respondent also
avers that Puromines Inc. should comply with the arbitration clause provided for in Moreover the court also ruled that, whether the liability of respondent
the sales contract. should be based on the sales contract or that of the bill of lading, the parties are
nevertheless obligated to respect the arbitration provisions on sales contract and/or
Facts show that the sales contract executed between Puromines Inc., and the bill of lading. Petitioner being a signatory and party to the sales contract cannot
Philipp Brothers Oceanic, Inc., provides for an arbitration clause wherein it states escape from his obligation under the arbitration clause as stated therein.
that:
for the installation and initial operation of the plant, PGSMC issued two postdated
As pointed out in the case of Mindanao Portland Cement Corp. vs Mc checks: (1) BPI Check No. 0316412 dated January 30, 1998 for PhP 4,500,000; and
Donough Construction Company of Florida the court ruled: (2) BPI Check No. 0316413 dated March 30, 1998 for PhP 4,500,000. When KOGIES
deposited the checks, these were dishonored for the reason PAYMENT STOPPED.
“With a written provision for arbitration as well as failure on respondent's part to Thus, on May 8, 1998, KOGIES sent a demand letter to PGSMC threatening criminal
comply, parties must proceed to their arbitration in accordance with the terms of action for violation of Batas Pambansa Blg. 22 in case of nonpayment. On the same
their agreement (Sec. 6, RA 876). Proceeding in court is merely a summary remedy date, the wife of PGSMCs President faxed a letter dated May 7, 1998 to KOGIES
to enforce the agreement to arbitrate. The duty of the court in this case is not to President who was then staying at a Makati City hotel. She complained that not only
resolve the merits of the parties' claims but only to determine if they should did KOGIES deliver a different brand of hydraulic press from that agreed upon but it
proceed to arbitration or not . And although it has been ruled that a frivolous or had not delivered several equipment parts already paid for.
patently baseless claim should not be ordered to arbitration it is also recognized
that the mere fact that a defense exist against a claim does not make it frivolous or Issue: Whether or not the arbitration clause in the contract of the parties should
baseless. govern.