COURT OF additionally hear and decide in the summary proceedings Yao's
APPEALS and WILSON C. YAO claim for damages, it having itself filed similarly its own G.R. No. 103200 August 31, 1994 counterclaim with the court a quo. VITUG, J.: FACTS: ISSUES: Respondent Yao was the owner of a commercial building, a 1. WON the court a quo has jurisdiction to decide the claim on portion of which is leased to herein petitioner. However, the two damages in summary proceeding involving an arbitration disagreed on the rental rate so they submitted their disagreement controversy. to arbitration pursuant to Sec. 6 of RA 876 (Arbitration Law) and HELD: par. 7 of their lease contract. Alamarez and Atty. Sabile has been No, the court a quo has no jurisdiction. appointed by each of the parties as arbitrator while the Jurisdiction over the person must be seasonably raised, appointment of Tupang as the third one was held in abeyance i.e., that it is pleaded in a motion to dismiss or by way of an because La Naval Drug defer the same until its Board of affirmative defense in an answer. Voluntary appearance shall be Directors could convene and approve it. Yao contended that is deemed a waiver of this defense. The assertion, however, of only a dilatory tactics, hence, he prayed that a summary hearing affirmative defenses shall not be constructed as an estoppel or be conducted and direct the 2 arbitrators to proceed by as a waiver of such appointing and confirming the appointment of the Third Arbitrator defense. and immediately convene and resolve the controversy before it. Where the court itself clearly has no jurisdiction over the La Naval Drug averred that Yao has no cause of action subject matter or the nature of the action, the invocation of this against it as the 2 arbiters have the free hand in choosing the defense may be done at any time. It is neither for the courts nor third member; hence, it included a counterclaim. Consequently, the parties to violate or disregard that rule, let alone to confer that Yao filed an amendment for payment of unpaid rents and jurisdiction, this matter being legislative in character. Barring damages which was admitted. La Naval Drug argued that the highly meritorious and exceptional circumstances, such as amended petition must be dismissed as Yao's proposition for a hereinbefore exemplified, neither estoppel nor waiver shall apply. summary hearing of the arbitration issue and separate trial for his In the case at bench, the want of jurisdiction by the court is claim for damages is procedurally untenable and implausible. indisputable, given the nature of the controversy. The arbitration In its assailed Order, the CA held that Yao’s claim is law explicitly confines the court's authority only to pass predicated on the alleged interference and dilatory tactics, thus, upon the issue of whether there is or there is no agreement compelled the herein respondent to ask the CA for redress and in writing providing for arbitration. In the affirmative, the the counterclaim may be entertained in a hearing, not summary, statute ordains that the court shall issue an order for the purpose. A preliminary hearing of the special and "summarily directing the parties to proceed with the affirmative defense to show that Yao has no cause of action is arbitration in accordance with the terms thereof." If the denied. court, upon the other hand, finds that no such agreement On MR, petitioner argued that the respondent court sits exists, "the proceeding shall be dismissed." The as a special court exercising limited jurisdiction and is not proceedings are summary in nature. competent to act on Yao's claim for damages, which poses an All considered, the court a quo must then refrain from issue litigable in an ordinary civil action. However, CA denied the taking up the claims of the contending parties for damages, MR. Although the CA agreed that under Sec 6 of RA 876, a which, upon the other hand, may be ventilated in separate court, acting within the limits of its special jurisdiction, may in this regular proceedings at an opportune time and venue. The case solely determine the issue of whether the litigants should circumstances obtaining in this case are far, we hold, from proceed or not to arbitration, it, however, considered La Naval justifying the application of estoppel against either party. Drug in estoppel from questioning the competence of the court to (2) ORMOC SUGARCANE PLANTERS' ASSOCIATION, INC. arbitration is the entry by the parties into a valid agreement to (OSPA), ET. AL. vs. COURT OF APPEALS, ET. AL. arbitrate. An agreement to arbitrate is a contract, the relation of G.R. NO. 156660 : August 24, 2009 the parties is contractual, and the rights and liabilities of the LEONARDO-DE CASTRO, J.: parties are controlled by the law of contracts. In an agreement for FACTS: arbitration, the ordinary elements of a valid contract must appear, Petitioners (OSPA, OLFAMCA, UNIFARM, and ONDIMCO) are including an agreement to arbitrate some specific thing, and an associations organized by and whose members are individual agreement to abide by the award, either in express language or sugar planters. Respondents Hideco Sugar Milling Co., Inc. by implication. The requirements that an arbitration agreement (Hideco) and Ormoc Sugar Milling Co, Inc. (OSCO) are sugar must be written and subscribed by the parties thereto were centrals, who may or may not be members of an association enunciated by the Court in B.F. Corporation v. CA such as petitioners. Sec 2 of RA 786 speaks of two modes of arbitration: (a) Petitioners assert that the relationship between an agreement to submit to arbitration some future dispute, respondents and the individual sugar planters is governed by usually stipulated upon in a civil contract between the parties, milling contracts which provides sharing ratio of 34:65:1 for and (b) an agreement submitting an existing matter of difference centrals, planters, and planter’s association, respectively. If the to arbitrators, termed the submission agreement. Except where Planter was not a member of any association, then the said 1% a compulsory arbitration is provided by statute, the first step shall revert to the centrals. The said contract also provides for toward the settlement of a difference by arbitration is the entry by arbitration in case of disagreement between the parties thereto. the parties into a valid agreement to arbitrate. In 1999, petitioners, without impleading any of their In the case at bar, Article XX of the milling contract is an individual members, filed twin petitions with the RTC for agreement to submit to arbitration because it was made in Arbitration under RA 876 against HIDECO and OSCO for anticipation of a dispute that might arise between the parties after violating the Milling Contract when the latter gave to independent the contract's execution. Yet, there is no legal basis for planters who do not belong to any association the 1% share, petitioners' purported right to demand arbitration when they are instead of reverting said share to the centrals. not parties to the milling contracts, especially when the arbitration Respondents filed a motion to dismiss on ground of lack clause expressly grants the right to demand arbitration only to the of cause of action as it was the individual Planters, and not parties to the contract. petitioners, who were the signatories of the milling contract and Sec 4 of RA 786 requires that an arbitration agreement had legal standing to invoke the arbitration clause therein. must be in writing and subscribed by the party sought to be RTC denied the motion to dismiss. MR also denied. On charged, or by his lawful agent. In this case, the individual appeal, the CA set aside the Orders of the lower court and held Planter and the appropriate central were the only signatories to that petitioners neither had an existing contract with respondents the contracts and there is no provision in the milling contracts nor were they privy to the milling contracts between respondents that the individual Planter is authorizing the association to and the individual Planters. With their MR denied, petitioners represent him/her in a legal action in case of a dispute over the elevated the case before the SC via special civil action for milling contracts. certiorari. Petitioners could not initiate arbitration proceedings in ISSUE: WON the petitioners have legal personality to file a suit their own name. As mere agents, they should have brought the against, or demand arbitration from, respondents in their own suit in the name of the principals that they purportedly represent. name without impleading the individual Planters. Even if Sec 4 of RA 876 allows the agreement to arbitrate to be HELD: signed by a representative, the principal, being the real-party-in- No, petitioners have no legal standing. interest, is still the one who has the right to demand arbitration. Except where a compulsory arbitration is provided by More so, they need a power-of-attorney to represent the Planters statute, the first step toward the settlement of a difference by whether in the lawsuit or to demand arbitration. (3) KOREA TECHNOLOGIES CO., LTD vs. HON. ALBERTO LERMA Established in this jurisdiction is the rule that the law of the place & PACIFIC GENERAL STEEL MANUFACTURING CORP where the contract is made governs. Lex loci contractus. The G.R. No. 143581: January 7, 2008 contract in this case was perfected here in the Philippines. VELASCO, JR., J.: Therefore, our laws ought to govern. Nonetheless, Art. 2044 of FACTS: the Civil Code sanctions the validity of mutually agreed arbitral KOGIES and PGSMC executed a contract whereby the clause or the finality and binding effect of an arbitral award. Art. former would set up an LPG Cylinder Manufacturing Plant in 2044 provides, “Any stipulation that the arbitrators’ award or Carmona, Cavite. The contract and its subsequent amendment decision shall be final, is valid xxx.” stipulated a total contract price of $1.53M. Then, the In this case, it has not been shown that the agreement is machineries, equipment and facilities for the manufacturing were against law, moral, good customs, public order or public policy. delivered and installed in the Carmona plant and PGSMC paid The mutually agreed stipulation that the arbitration must be done $1.224M to KOGIES. However, the initial operation did not push in Seoul, Korea in accordance with Commercial Arbitration Rules through because of PGSMC’ financial difficulties. For the of the KCAB and that the arbitral award if final and binding is not remaining balance of the contract, it issued 2 post-dated checks contrary to public policy. After all, foreign arbitral awards while but they were dishonoured for reason payment stopped. KOGIES mutually stipulated by the parties in the arbitration clause to be sent a demand letter with a threat of litigation under BP 22 in final and binding are not immediately enforceable or cannot be case of non-payment. PGSMC replied that the payment was implemented immediately. Sec. 35 of the UNCITRAL Model Law stopped due to the cancellation of the contract as the quantity stipulates the requirement for the arbitral award to be recognized and quality of the equipment delivered was altered, a reason that by a competent court for enforcement, which court may refuse was made known to KOGIES. PGSMC further said that those recognition or enforcement. equipment will be dismantled and transferred from the plant. Foreign arbitral awards when confirmed by the RTC are PGSMC filed an Affidavit-Complaint for Estafa against the deemed not as a judgment of a foreign court but as a foreign President of KOGIES. The latter averred that PGSMC cannot arbitral award, and when confirmed, are enforced as final and unilaterally rescind and insisted that they settle their dispute by executory decisions of our courts of law. Thus, it can be gleaned arbitration pursuant to Article 15 of their contract but to no avail. that the concept of a final and binding arbitral award is similar to Hence, KOGIES filed an application for arbitration before the judgments or awards given by some of our quasi-judicial bodies, Korean Commercial Abitration Board (KCAB) in Seoul, Korea like the NLRC and Mines Adjudication Board, whose final and filed a complaint for specific performance against PGSMC judgments are stipulated to be final and binding, but not before the RTC-Muntinlupa. The RTC issued a TRO and PGSMC immediately executory in the sense that they may still be opposed the same on the argument that the arbitration clause in judicially reviewed, upon the instance of any party. Therefore, the the contract was null and void for being contrary to public policy. final foreign arbitral awards are similarly situated in that they Later, the RTC ruled in favour of PGSMC and denied the need first to be confirmed by the RTC. application for a writ of prelim injunction as KOGIES was already paid $1.2M and no longer has proprietary rights over the equipment. It also ruled that the arbitration clause in the contract is void as it tended to oust the trial court jurisdiction over any dispute that may arise between the parties. The same was affirmed by the CA. Hence, a review on certiorari was filed. ISSUE: WON the arbitration clause is valid. HELD: No, the arbitration clause is valid and not contrary to public policy. (4) KOPPEL, INC. v MAKATI ROTARY CLUB FOUNDATION, INC. the Panel of Arbitrators is proper only when there is a G.R. No. 198075. September 4, 2013. disagreement between the parties as to some provisions of the PEREZ, J.: contract between them, which needs the interpretation and the FACTS: application of that particular knowledge and expertise possessed Fedders Koppel, Incorporated (FKI) was owner of a by members of that Panel. It is not proper when one of the parcel of land in Parañaque City. In 1975, it donated the same to parties repudiates the existence or validity of such contract or herein respondent subject to the condition that it will be leased agreement on the ground of fraud or oppression as in this case. back to FKI under the terms specified in the Deed of Donation. XXX Allegations of fraud and duress in the execution of a The Deed provides that the lease is for 25 years, renewable for contract are matters within the jurisdiction of the ordinary courts another 25 years upon mutual agreement. of law. These questions are legal in nature and require the 2 days before expiration of the lease, FKI and the application and interpretation of laws and jurisprudence which is respondent entered into a 5-year lease (2000 Lease Contract), necessarily a judicial function.” and subsequently, agreed for another 5 years under the 2005 Under the doctrine of separability, an arbitration Lease Contract. The 2005 contract provides that aside from the agreement is considered as independent of the main contract. rentals, FKI will be giving donations to respondent ranging from Being a separate contract in itself, the arbitration agreement may 3M-3.9M and that any disagreement as to the interpretation, thus be invoked regardless of the possible nullity or invalidity of application or execution of the same shall be arbitrated and the the main contract. In Cargill Philippines v. San Fernando decision thereupon shall be binding among the parties. Regal Trading Inc, the SC held that even the very party who In 2008, petitioner Koppel, Inc. bought FKI and became repudiates the main contract may invoke its arbitration clause. the assignee of the lease and donation with Makati Rotary. The Hence, even Koppel Inc. who assails the validity of the lease following year, Koppel discontinued the payment of rent and contract may invoke the arbitration clause thereunder. donation under the 2005 Lease Contract on the argument that A, the arbitration clause is not defeated by the failure to the said lease contract, as well as the 2000 Lease Contract, file a formal request or application with the MeTC. The filing of violated material conditions of the donation providing for a 25-yr request under Sec 2 of RA 9285 is not the sole means of lease, renewable for another 25 yr-lease. More so, the donation invoking arbitration as the provision uses the word “may”. Non- also provided for rules and limitations for the fixing of rentals compliance with an arbitration agreement is a valid defense to which was allegedly not followed. Despite 2 demand letters from any offending suit and, as such, may even be raised in an Makati Rotary, Koppel refused to pay and instead filed a answer as provided in our ordinary rules of procedure. Thus, complaint for rescission or cancellation of the Deed of Donation Koppel’s invocation in the Answer with Counterclaim is enough. and the Amended Deed of Donation with the RTC-Parañaque. The fact that a JDR proceeding before the RTC was done Meanwhile, Makati Rotary filed and ejectment case before will not render the subsequent arbitration between the parties the MeTC- Parañaque. The MeTC ruled in favour of Koppel for unnecessary. The JDR framework is based on the processes of insufficiency of respondent’s demand and the nullity of the 2005 mediation, conciliation or early neutral evaluation which entails Lease Contract. On appeal, the RTC reversed the same. CA the submission of a dispute before a “JDR judge” who shall affirmed the RTC. Hence, this appeal was filed. merely “facilitate settlement” between the parties in conflict or ISSUE: WON the case should be subjected to arbitration. make a “non-binding evaluation or assessment of the chances of HELD: each party’s case.” Thus in JDR, the JDR judge lacks the Yes, the MeTC, RTC, and CA overlooked the significance authority to render a resolution of the dispute that is binding upon of arbitration clause in the 2005 Lease Contract. the parties in conflict. In arbitration, on the other hand, the Contrary to argument that the invalidity of contract is per dispute is submitted to an arbitrator/s — a neutral third person or se non-arbitrable, the Court held that the ruling in Gonzales v. a group of thereof — who shall have the authority to render a Climax Mining, Ltd was taken out of context. “Arbitration before resolution binding upon the parties.