Professional Documents
Culture Documents
Abstract-This paper proposes a hybrid Critical Clearing are also called as direct methods or transient energy function
Time(CCT) evaluation method. This method isbased on an methods have been discussed in [1]-[4]. In these methods CCT
integrated approach of Bisection andSingle Machine Equivalent or stability of the system is assessed by calculation of pre and
(SIME) technique.In this method initially a time interval in post-fault energy stored in the system. But for these methods
which actual CCT lies is identified followed by applying bisection there is a need for computation of accurate critical energy
method for estimation of exact CCT. The method uses SIME which is a difficult task and requires greater computation.
based rotor-speed early stop criteria for detection offirst- swing
Automatic learning(AL) approaches used for TSA are of two
stability, thus reducing the computation time required. The
types namely, supervised and unsupervised which requires
hybrid technique is applied to WSCC 9bus, IEEE 14 bus, IEEE
long-time for off-line training process. In[5] a transient energy
30 bus and New England 39 bus test system. The obtained CCT
based direct method forevaluation of transient stability is
results are compared with the results of conventional Time
Domain Simulation (TDS) approach. The proposed Bisection and
discussed. In literature [6] CCT is computed using an
SIME based integrated approach computes the CCT faster
integrated approach of Potential Energy Boundary Surface
compared to conventional TDS approach.
method and time domain simulation method. Initially an
approximate CCT is estimated using energy function approach
Keywords-Critical Clearing Time(CCT); One Machine and is used as a starting fault clearing time for time domain
Infinite Bus(OMIB); Single Machine Equivalent(SIME);Time simulation to evaluate accurate CCT. In [7] the authors propose
Domain Sim ulation(TDS);Transient Stability Assessment(TSA). an energy comparison method for finding the severely
disturbed machines (SDM) and hence to find CCT based on
I. INTRODUCTION extension of equal area criterion for transient stability analysis
The power system transient stability assessment is very of multi-machine power systems. In [8] a radial basis function
important in power system planning and system studies. network (RBFN) based ANN method is used for estimation of
Transient stability problems caused by large disturbances are of CCT.An online transient stability prediction scheme based on
concernfor secure operation of power system. Transient live synchrophasor data is proposed in [9]. Here the transient
stability is the ability of the power system to maintain stability is predictedbased on only few sample fault data
synchronism after subjected to a large disturbance such as a received by PMUs without solving computationally extensive
short circuit on a transmission line [I]. Modem power systems electromechanical dynamics. In [10] a critical trajectory based
being complex are operated under pressure. The operating minimization problem is formulated for evaluation of CCT.The
stability limit evaluation is an important issue for present day authors in [II] propose two new methods based on clustering
competitive deregulated environment. The Critical Clearing identification for real time computation of CCT. The CCT is
Time (CCT) gives the boundary of transient stability for a estimated using power angle and acceleration curves by
particular fault condition. When the power system is subjected transformation of multi-machine system into single machine
to a large disturbance, CCT distinguishes the operating equivalent. An algorithm for deriving a uniform transient
condition as stable or unstable. It is very essential to estimate stability index using single time, time-domain simulation is
the CCT in order to avoid cascading outages or blackouts due proposed in [12]. In [13] a method for transient stability
to occurrence of large disturbances which may result in large assessment of the stable cases using the deceleration area of the
excursions of rotor angles of synchronous machines leading to power-angle representation of SIME method is proposed.A
lossof synchronism. SIME method based algorithm for integrationwith standard
time domain simulation program to search for stability limits is
The transient stability assessment methods are generally proposed in [14]. In literature [I5] an educational graphical
classified into time domain simulation, direct and automatic user interface tool for evaluation of multi-machine transient
learning approaches. In time domain simulation method the stability combining the SIME method with MATLAB and
nonlinear equations are solved simultaneously. The TDS Simulink is described.
approach simulates the system dynamics in the during-fault and
post-fault configurations. The during-fault time period is very In this paper a SIME based hybrid method for transient
small whereas post-fault period may be much longer leading to stability analysis is presented. Consider the phase plane
a very time consuming CCT evaluation process. The estimation trajectories of an OMlB system as shown in figure 1. Three
of CCT using Liapunov's type energy function methods which different types of trajectories corresponding to a 'stable' case, a
'critically stable' case and an 'unstable' case have been shown.
- - - � J __ i - ----:-
criteria. a
-O.04L-+------,'SO;;---.,.;100;-0--,-!'SO;-0+--c;!20-,-!2Sc;;-0---.l
0.01 Delta [deg]
�EP
Omega of OM B
0.025 .---
I --�-r_-r_-r_-r_-r_t_r---.----.--_____,
:if -0.01
ro �
�--�--!--!--!--!--�
/
0.02
I
-«IOM1B
E
a
__ � _ � _ � __ � : _ � __ � _ � - - � - - � - -
I I I I I I
-0.02
I I I I I I I
0.015
-0.0
3 -- ./
/
0.01 -
I
I- - - -I- -
1-
- +-- -
I OMIB I I
- - -l- - - -+ -
I I I
- --l- - - --I - - --I - -
I
_l __l_�l J J
-
I I I
-ooj,.'no---o--7-----;S"'o---·,*'oo,---·,"'So,---""2o
Delta [deg] �
a
-- -- -- I I I I I
Delta
Delta [deg]
[deg]
= I
-
I I
1
ocCt) = - LkEC Mk 0kCt) ........ (4)
Me
Omega OM B Omega of
of OMIB
0.025 r--:- I
----:--:--jh=====j]
II '
0.025 ----;---;-----:----:--t-;====;']
11
I _ _ C,
- '"
OMIB
The COA for non-critical machines, N:
I I I I
I L--'M' "
I I I I
I I
I I I I I 1
O�
0.02 ----�---- - -�t ----
--- _~__
� ----
- - -�t
I ----
-- ON(t) = - LjEN Mj OJ(t) ........ (5)
II :
----
I MN
,
I
�~ OOMIB =
OOMIB = c(t) -- ON
o0cCt) (t) ........
ONCt) ........ (6)
r�
T -00.4," , ,
I I
oo
Similarly equivalent OMIB
Similarly OMlB rotor speed is expressed
expressed as:
____ l ____ l ____
__ L ____ l ____
____ l
l ____
___ _ J ____
1
I II I II I
wc(t) = - LkEC Mk Wk(t) ........ (7)
Me
1
0.1
0.1 0.2
0.2 0.3
0.3 0.4
0.4 0.5
0.5 0.6
0.6 WN(t) = - LjEN Mj wlt) ........ (8)
Time[s]
lime [s] MN
WOMIB =
WOMIB wc(t) -- WN(t)
= Wc(t) ........
........ (9)
(9)
Fig. 3. Fault-on trajectory and corresponding
corresponding speed of OMlB
OMIB for an unstable
unstable
case
OMlB mechanical and electrical power are
The equivalent OMIB
The rotor angles and speed thus obtained can be converted given by
from synchronousreference frame to center-of-inertia (COL) or
center-of-angle (COA) reference frame using the following Pm(t) = M (~LkEC Pmk(t) _..2... LjEN Pmj(t)) .. , .. (10)
equations. Me MN
8; = 0i
8i = 0; -- 0
000 ~
� ........
........ (3)
(3) Pe(t) = M (~LkEC Pek(t) - LjEN Pej(t) ) ..... II)
..... ((11)
w;i =
M1
W Bi =
= 8; W; -
= Wi - wo) Me N
where: McMN
8;
8 i - Angular displacement relative to COA Mc = ) Mk ; MN = ) Mj ;
M = Mc +MN
w; -
Wi - Angular velocity relative to COA kEC jE N
Step 4: Starting with the initial fault clearing time find tl and t2
The net accelerating power of the OMlB is such that at tl the system is stable and att2 the system
is unstable by repeating steps 2 & 3. Use OMIB
PaCt) = PmCt) - Pe(t) . . . . . . .. (12)
omega curve for assessing the stability as described
in section II.
Step 5: Calculate the mid point tmid and check for stability of
C. MOD determination (Mc5-criterion) [12]
the system at tmid.
TheM8-criterion is used for identification of critical and Step 6: If the system is found stable at tl11id,then replace tmidby
non-critical group of machines. The maximum inertia-weighted
tlor if the system is found unstable at tmid replace
angle gap criterion is applied at the fault clearing time of te/.
tmidbyt2 .
The machines are sorted in descending order according to the
Step 7: Again with the replaced value of fault clearing time
M8 product. i.e. M o = Mi' OiCtca. The maximum gap between
,
continue to bisect the interval until the difference
sorted Mc5ivalues is identified and machines before the gap
forms the critical group (C) , whereas the machines after the between tJ and t2 becomes less than or equal to G.
gap forms non-critical group (N). Step 8: Stop the simulation when the above said criterian is
reached. The fault clearing timetl will be the required
IV. CCT EVALUATION BY PROPOSED METHOD CCT.
A. Bisection Method
The bisection method in mathematics is used to reduce the Initialization
computation time required for finding the root of an equation.
Initially take an interval [a, b] such that f(a) and feb) have
opposite signs, find the midpoint of [a, b], and then decide
Initial FCT: tl= 10 msec,
whether the root lies on [a, (a + b)l2] or [(a + b)l2, b].Repeat
until the interval is sufficiently small. The same concept can be t2= tl+a,
used for reducing the computation time required for CCT Tolerance = E
evaluation. As shown in figure 4, an initial fault c1earingtime is
assumed(FCT=lO sec) and then thelimits are chosen such that
the system is stable at lower value tland unstable at higher
valuet2.0nce again the stability of thesystem is evaluated at an
average value or mid-pointtmid. If the system is stable,
theaverage value (tmid)is replaced by lower limit (tl).
Stable at t]&
Otherwise,the average value (tmid) is replaced by higher value
Unstable at t2?
(t2) in the nextcalculation. The above procedure is repeated
until the bisected time interval becomes lessthan the specified
tolerance G. Then the lower value tlis the required CCT.
Stable o stable
I
-1 tmid
I
tl
�
FCT (sec)
Yes
Stable at lmiP
No
Step 1: Solve the initial load now todetermine the initial bus
voltage magnitudesand phase angles.
Step 2: Run the conventional TDS with initial fault clearing
time.
Step 3: After each time step of integration obtain the
equivalent OMIB rotor speed of the multi-machine
Fig. 5. Estimation of CCT using Bisection method
system using equations (7) to (9).
Figure 5 gives the t10wchart of the methodology for tripped. The third and fourth columns respectively give the
calculation of CCT using the integrated approach of bisection estimated CCT value and the corresponding execution time by
and SIME method. In this paper a starting fault clearing time of conventional time domain simulation method for CCT
10 msec (which is a stable case), (J = 100 msec and <; Imsec is = evaluation. The fifth and sixth columns give the estimated
used for CCT estimation. value of CCT and corresponding execution time for CCT
evaluation by the proposed method. Here the execution time is
V. SIMULATION AND RESULTS the run time for computation of CCT for single contingency.
The proposed method for estimation of CCT is tested on
different test systems of varying size. The CCT obtained by TABLE IV. ESTIMATED CCT VALUES AND THE EXECUTION TIME FOR IEEE
39 Bus TEST SYSTEM
time domain simulation method and by the proposed method
have been compared. The results obtained by the proposed
Faulted Removed TDSMethod Proposed Method
method are fairly matching with the CCT values obtained by Bus Line CCT (sec) Time (sec) CCT (sec) Time (sec)
time domain simulation method. The proposed method is used
for CCT evaluation of WSCC 9 Bus, IEEE 14 Bus, IEEE 30 1 1-2 0.240 13.269 0.240 0.557
Bus and IEEE 39 Bus New England test systems. The 5 4-5 0.207 11.155 0.208 0.280
estimated values of critical clearing time and the execution
8 8-9 0.199 10.004 0.199 0.256
time taken for estimation of CCT for few contingencies of the
above mentioned test systems are as given in tables I to IV 10 10-13 0.202 10.418 0.202 0.288
respectively. 13 13-14 0.211 10.780 0.212 0.285
Faulted Removed TDSMethod Proposed Method 39 1-39 0.293 15.275 0.293 0.274
Bus Line CCT (sec) Time (sec) CCT (sec) Time (sec)
7 5-7 0.162 5.520 0.162 0.196
For CCT evaluation using conventional TDS method,
simulation is started by clearing the fault immediately and the
9 9-6 0.212 6.814 0.212 0.247 stability is checked by inspection of angular difference. Then
7 7-8 0.181 5.515 0.181 0.206 the fault clearing time is increased until the instability is
detected. For example for a three phase fault at bus number 4,
6 9-6 0.389 13.093 0.389 0.234
of the WSCC 9 Bus system, the line connected between buses
4 4-6 0.308 11.389 0.308 0.236 4 and 6 is tripped for clearing the fault. The corresponding
CCT value is found to be 0.308 seconds. The execution time
TABLE II. ESTIMATED CCT VALUES AND THE EXECUTION TIME FOR IEEE taken for CCT evaluation by proposed method is 0.236
14 Bus TEST SYSTEM
seconds, whereas the execution time taken by TDS method is
TDSMethod Proposed Method 11.389 seconds. From the comparison of execution time taken
Faulted Removed
by both the methods it is observed that time taken for CCT
Bus Line CCT (sec) Time (sec) CCT (sec) Time (sec)
evaluation using proposed method is very less than the
6 5-6 0.369 13.744 0.368 0.302 conventional TDS method. This indicates the computational
7 4-7 0.350 12.868 0.349 0.318
speed of the proposed method. The simulation is carried out in
MATLAB. The computer configuration used for simulation is
5 4-5 0.129 4.954 0.127 0.257
lntel(R), Core i5, 2.5-GHz CPU with 4 GB of RAM.
7 7-9 0.353 12.405 0.349 0.309
Phase angles of machines w.r.t. COl
9 9-14 0.425 15.797 0.424 0.341 80 r--.---.---r--.--�===
TABLE ITT. ESTIMATED CCT VALUES AND THE EXECUTION TIME FOR IEEE
30 Bus TEST SYSTEM
The first column indicates the faulted bus number and the
second column gives the line number of the connected line Fig. 6. Rotor angles of the machines W.f.t COL for a stable case
Figures 6 to 8 shows respectively the plots of rotor angles be stopped saving the computation time. This is the novelty of
of the machines W.r.t. COL reference frame, rotor angle delta of the proposed method.
the equivalent OMIB and omega of the OMIB for a stable case.
Phase angles of machines w.r.t. COl
The fault is applied to bus 7 of WSCC 9 bus system and is 25DD r----r---,----.---.--.-�=c==�
cleared by opening the connected line 5-7at 100 msec, which is
a stable case corresponding to CCT of 162 msec. 2000 I I I I I I I I
-------------------------
__ 0,
I I I I I I I I __
0,
Delta of OMIB
9 D r--;��---;---;---;---;--;---;r==�� �oo --� --� --� --+--+-- +-- +-- �
: -- ()OMIB
-500
40
-100°'\- ----;;'." ----,;;'.4;- ----;;';.6� ----,."' 8 ,-------;�--"' ." --�fl.4;- ---,."; 6 �---.,.,.� 8 -----o\
30 __ L __ L _ 0 02 D D D 12 1
I Time[s1
20 __ L __ L __
Fig. 9. Rotor angles of the machines W.r.t COT for an unstable case
1D�--� � ---� �� L ��L --�L- --� �--�lL ��lL �� � --�
D D.2 D.4 D.6 D.8 1.2 .4 .6 1 .8
Time[s]
Delta of OMIB
3DDD
,-,--:-,--,-,--:-,--:r=�==jj
Fig. 7. Delta of OMlB for a stable case
2500
Omega afOMIB
D.D15 ,-,-,- --,-,-,- --:;=====jj
, , I w __
OMIB moo � -- � -- � -- � -- � -- � -- � -- � -
I --
I 1500
1000
� 500
a
Time[s1
E
the equilent OMIB will cross the zero-axis indicating the stable o 0.06 --1 --1 --
methods. The novelty of the proposed method is its fastness to [9] Hazra, J.; Reddi, R.K.; Das, K.; Seetharam, D.P.; Sinha, AK., "Power
grid transient stability prediction using wide area synchrophasor
detect stability and accurate evaluation of CCT. Comparison of
measurements," Innovative Smart Grid Technologies (ISGT Europe),
the results indicates the fast computation of the CCT by 2012 3rd IEEE PES International Conference and Exhibition on , vol.,
proposed method as compared to conventional time domain no., pp.I,8, 14-17 Oct. 2012
simulation method. doi: 10.1109/ISGTEurope.2012.6465752
[10] Yorino, N.; Priyadi, A.; Kakui, H.; Takeshita, M., "A New Method for
REFERENCES Obtaining Critical Clearing Time for Transient Stability," Power
Systems, IEEE Transactions on, vo1.25, no.3, pp.1620,1626, Aug. 2010
[II P. Kundur. Power System Stability and Control, 2nd ed. New York,
doi: 10.1109ITPWRS.2009.2040003
NY, USA: McGraw-Hill, 1994.
[I I] Dinh, Hung Nguyen, Minh Y. Nguyen, and Yong Tae Yoon. "Novel
[2] P. M. Anderson and A A Fouad, Power System Control and Techniques for Real Time Computing Critical Clearing Time SIME-B
Stability.New York: IEEE Press, 1994. and CCS-B ." Journal of' Electrical Engineering & Technology 8.2
[31 Mania Pavella and P. G. Murthy. Transient stability of power systems: (2013): 197-205.
theory and practice. (1994). [12] Kyriakidis, T.; Lanz, G.; Cherkaoui, R.; Kayal, M., "A transient stability
[4] Mania Pavella, Damien Ernst, and Daniel Ruiz-Vega. Transient stability assessment method using post-fault trajectories," PowerTech
of'power systems: a unified approach to assessment and control. Vol. (POWERTECH), 2013 IEEE Grenoble, vol., no., pp.I,4, 16-20 June
581. Springer, 2000. 2013
[5] Athay, T.; Podmore, R.; Virmani, S., "A Practical Method for the Direct doi: 10.11 09/PTC.20 13.6652132
Analysis of Transient Stability," Power Apparatus and Systems, IEEE [13] Suzuki, M.; Fujii, W.; Iwamoto, S., "Consideration on transient stability
Transactions on , voI.PAS-98, no.2, pp.573,584, March 1979 assessment using deceleration area by the SIME," Power Engineering
doi: 1O.1109ITPAS.1979.319407. Society General Meeting, 2005. IEEE, vol., no., pp.1695, 1700 Vol. 2,
[6] Saharoy, B.K.; Pradhan, AK.; Sinha, A.K., "Computation of critical 12-16 June 2005
clearing time using an integrated approach," Power Systems, 2009. ICPS doi: 10.1109/PES.2005.14895I I
'09. International Conference on, vol., no., pp.I,5, 27-29 Dec. 2009 [14] Tan, H.M.; Zivanovic, R., "Integrating the SIME method with standard
doi: 10.1109/ICPWS.2009.5442676. time domain simulation software to search for transient stability
[7] AI Marhoon, H.H.; Leevongwat, 1.; Rastgoufard, P., "A practical method limits," Power Engineering Conference, 2008. AUPEC '08. Australasian
for power systems transient stability and security Universities, vol., no., pp.I,7, 14-17 Dec. 2008
analysis," Transmission and Distribution Conference and Exposition [15] Bhat, S., et al. "A transient stability tool combining the SIME method
(T&D), 2012 IEEE PES, vol., no., pp.l,6, 7-10 May 2012 with MATLAB and SIMULTNK." International journal of electrical
doi: 1O.1109ITDC.2012.6281553. engineering education 43.2 (2006): 119-133.