Professional Documents
Culture Documents
This document reveals the scope of works, working procedure and technical
specifications. EGMF shall abide to the technical aspects, specifications and scope of
work as presented herein and as per the clients specifications.
SITE INSTALLATION
Indoor Installation
The FO optical distribution frame will be installed in the racks. All the fibre cores of the
cable shall be terminated into the ODF.
Outdoor installation
The Cable come in rolls and thus will be spliced in a junction box to provide continuity.
These junction boxes will only be placed where the new cable roll needs to start
The fibre cable will be terminated into each building in the ODF.
Splices and connections
Splices
An average 10 m coil of fibre cable shall be left for each splice junction for future
maintenance purpose.
A coil of cable on either side of each splice will be left. These coils serve two functions:
They provide spare of cable so that a splice can be remade if necessary, without pulling
an entire length.
They allow for splicing outside the man-hole as it is impossible to make splicing inside
the manhole.
Measurements will be made in both directions on both wavelengths of 1310 and 1550
nm from the link end points (ODFs)
The splice attenuation value is calculated by working out the average of the splice loss
measurements in both directions.
The connector attenuation value is calculated by working out the average of the
measurements in both directions.
Link budget
The optical budget of the passive support will be calculated and documented on
completion of the work using a reflectometer. The actual Insertion loss shall also be
measured using Laser power source on one end and optical power meter on the other
end to calculate and document the total loss.
1
OPTICAL FIBER NETWORK ACCEPTANCE TEST
Throughout the duration of the work, by regular checking, inspection shall be performed
of the following points, by the customer’s representative :
Acceptance testing consists of ensuring that the remarks made by the customer’s
representative during inspection carried out as work progresses are taken into
consideration.
The optical link budget of the passive support will be measured on completion of the
work using a relectrometer, programming it for a pulse width according to the length of
the section.
These tests have already been performed during installation and records could be
submitted to the Client for approval.
All these measurements will be recorded in the measurement book and will be used later
on by the Client for cable maintenance.
FINAL ACCEPTANCE
On expiry of the warranty period, all reservations notified on provisional acceptance shall
be withdrawn.
Conclusion
The acceptance tests chronology as defined provides precise step by step follow-up of
the network by the customer.
Close partnership between contractor and the client, throughout the construction and
commissioning phases, will enable the Client to perform acceptance testing operations
efficiently and precisely, and to acquire total knowledge of its network.
2
TECHNICAL SPECIFICATIONS
3
Technical Specifications
4
Termination Box (ODF)
Fibre Optic Patch Panels
5
Duplex SC/UPC – LC/UPC optical patch cords