You are on page 1of 6

ADAPTATION OF A PROPYLENE REFRIGERATION

COMPRESSOR WITH DRY GAS SEALS

by
John R. Dugas, Jr.
Senior Engineer

Bich X. Tran
Senior Area Engineer

E. I. duPont deNemours & Company, Incorporated

Orange, Texas

and
James F. Southcott
Market Segment Manager, Type 28 Product Group

John Crane Inc.

Morton Grove, Illinois

sign installation, and troubleshooting. This included experience in


JohnR. (Johnny) Dugas is a Senior En­ fluid dynamics/turbomachinery.
gineer with DuPont's Chemicals Depart­ Mr. Southcott has a B.S.M.E. degree from the University of
ment in Orange, Texas. For the past ii Wisconsin.
years, he has been assigned to the Techni­
cal Department of the ethylene manufac­
turing facility where he is involved in repair,
troubleshooting, redesign, and specifica­
tion of turbomachinery and other process
equipment. He has worked at Du Pont
/. since graduating from the University of
Southwestern Louisiana with a B.S. degree
ABSTRACT
in Mechanical Engineering (1973 ). Previous activities with Du
Pont dealt with maintenance and construction of mechanical The retrofit of a 35000 hp, two-case centrifugal, propylene
equipment including assignments with Du Pont's Construction refrigeration compressor with tandem dry gas seals in Du Pont's
and Field Service Divisions. ethylene plant at Orange, Texas, is described. The installation of
these dry gas seals is one of the first applications to propylene
refrigeration service in the United States.
Bich X. Tran is a Senior Area Engineer The new seal design eliminated seal oil contamination of the
with E.i. duPont de Nemours and Compa­ compressor and downstream heat exchangers which led to de­
ny, incorporated. He joined Du Pont in creased efficiency, effectiveness, and subsequent loss of ethylene
i98i after receiving a B.S. degree in Me­ production. The seals also reduced the capital investment for a
chanical Engineering from the University flare system upgrade project $1.5MM, by decreasing propylene
of Missouri. He has been involved in spec­ losses during system shutdowns caused by existing seal system
ification, technical evaluation, redesign, shortcomings.
troubleshooting, and maintenance of vari­ This retrofit was unique in several ways. The original compres­
ous chemical processing equipment. Cur­ sor manufacturer had no experience with dry gas seals installed in
rently, he is assigned to the Technical their equipment. They were very willing to cooperate in this
Department of Du Pont's ethylene manu­ venture, but only to the point of providing dimensional data and
facturingfacility located at the SabineRiver Works site in Orange, engineering review. Due to the "sold-out" condition of the ethyl­
Texas. ene market, this installation had to be accomplished during a
limited shutdown. In order to minimize downtime, an innovative
installation method was developed which eliminated opening
James F. Southcott is the Market Seg­ compressor casings even though the new design required remov­
ment Manager, Type-28 Product Group, ing-a shaft sleeve. To demonstrate the feasibility of this method, a
for John Crane inc. His responsibilities mock up was built simulating working conditions to develop
with John Crane include the application techniques and tooling to remove the shaft sleeve.
and marketing of the dry gas seal and its
ancillary instrumentation/control systems
INTRODUCTION
to turbomachinery in the HPJ, Chemical Although the spiral groove dry gas seal technology has been
and Gas Transmission Segments. fully developed for over 10 years, it has only been used extensively
Prior to joining John Crane, he had over during the past five years. There are over 2000 of these dry gas
20 years of experience in a broad range of seals in use and the petrochemical and refining industries have had
mechanical equipment applications, de- excellent results with them. For example, the spiral groove dry seal

57
58 PROCEEDINGS OF THE TWENTIETH TURBOMACHINERY SYMPOSIUM

has more than four million hours running time on various hydro­ Using dry gas seals eliminated both of these problems. The seals
carbons. The longest continuous running time of a dry seal expe­ do not use oil, so oil contamination is no longer an issue. High
rienced to date is 43000 hr. The retrofit at the Orange facility is one Flux™ tubing can be used, reducing the overall modernization
of the first applications in the United States of these dry seals with costs by $3.1MM. The design of the dry seal allows the propylene
propylene. The advantages of the dry gas seal over conventional refrigeration system to settle-out at 70-80 psig, eliminating the
oil seals are: need to flare propylene during system shutdowns. The new flare
drum was eliminated and the project investment was reduced by
• Eliminating the seal oil support system including seal oil
$ 1.5MM.
pumps, reservoirs, filters, traps, coolers and consoles.
In addition, oil fouling of the overhead condensers in the
• Eliminating the parasitic losses from the wet seal system. propylene system currently reduces their capacity by 20 percent.
• Preventing process gas contamination with seal oil. Installing dry gas seals and cleaning the oil from the system will
return these condensers to rated capacity. Assuming conservative­
Reducing the process gas leaks (from 15 scfm and above for
ly that only 25 percent of this restricted capacity is recovered,

wet oil systems to one to three scfm for the dry gas seals).
$2.4MM/yr would be generated from the increased ethylene
• Reducing maintenance costs. production.
The ethylene refrigeration compressor has also experienced the
• Reducing unscheduled shutdowns and minimizing down­
oil contamination problem. Dry gas seals have been ordered for
time.
this compressor to eliminate that problem and enable the High
BACKGROUND Flux™ tubing technology to be used for this modernization project.

The initial propylene refrigeration compressor was installed in PRINCIPLES OF OPERATION


1967. However, it was replaced in 1985 to take advantage of new
The spiral groove dry gas seal provides a gas lubricated, self
technology for increasing compressor efficiencies (Figure 1). This
acting, noncontacting alternative to the oil seal. The main compo­
compressor, manufactured by an overseas supplier, has provided
nents of this seal are the stationary primary ring (usually carbon),
excellent service with the exception of a low settle out pressure
the mating ring (usually tungsten carbide) fixed to the rotating
required by the seals and process gas oil contamination problems
shaft, and the multiple spring mechanism to provide axial force on
experienced, due to a fundamental seal design shortcoming. This
the primary ring (Figure 2). These components are similar to
design problem was aggravated by process seal upsets and improp­
er operation of the seal system during unit outages.
A proposed ethylene modernization project for the plant includ­
ed capital investment for modernizing the flare system. The flare
system upgrade provided for handling the propylene vented from
the propylene refrigeration system during a shutdown. The normal
compressor settle out pressure is 70 to 80 psig, but the design limit
of the oil seals mandated that propylene be sent to the flare to
maintain the system pressure below 40 psig during shutdowns. A

Figure 1. Propylene Refrigeration Compressor.

Figure 2. Dry Gas Seal Cross Section.


new dry flare drum, estimated at $2.0MM, would be needed to
handle this additional load.
The modernization study also considered using High Flux™
tubing in heat exchangers downstream of the compressor to in­ conventional mechanical seals, except for the wider sealing faces
crease capacity at minimal cost. These tubes could improve heat and spiral grooves added to the mating ring.
transfer by tenfold, but they are highly susceptible to fouling. When the compressor is not running, the two rings are held in
Since the propylene refrigeration system has experienced severe contact by mechanical springs, allowing a minimal amount of
contamination by oil from the compressor seals, High Flux™ leakage. When the shaft is rotating, the rings separate, forming a
tubing could not be used. gap as the pressure rises in the spiral grooves.
ADAPTATION OF A PROPYLENE REFRIGERATION COMPRESSOR WITH DRY GAS SEALS 59

The logarithmic spiral grooves on the outside portion of the alloy materials. They use four or five axis CNC machines that have
mating ring face, shown in Figure 3, serve to "pump" the gas from machine position repeatability of 80 to 160 millionths of an inch
the outer diameter (O.D.) to the inner diameter (I.D.) of the faces. (Figure 5). These machines are combined into machining cells that
The inner surface of the ring acts as a sealing dam, providing a use distributed numerical control (DNC).
barrier to gas flow. This forms a restrictive plane at the apex of the The manufacturer's quality assurance facility has the capability
spiral grooves across which the gas begins to decrease in pressure to check and certify any component part to 100 millionths of an
and expand (O.D. to I.D.). The gap stabilizes when the hydrostatic inch and flatness to within one light band or 1 1.6 millionths of an
and hydrodynamic forces are equal. The face geometry is extreme­ inch (Figure 6). In addition, QA records very critical component
ly critical and must provide a gas film thick enough to prevent the dimension and surface finish are available for complete traceabil­
rings from physical contact, but thin enough to prevent excessive ity if required.
gas leakage. The gas leakage from these seals is less than 2 scfm The seal manufacturer provided estimates and guaranteed the
while the leakage from the oil seal systems is 15 scfm or greater. seal would not exceed predicted leakages. Each seal is tested both
The seal for this application is a tandem type, 9 5/8 in cartridge statically and dynamicall y at operating conditions. The
seal with a continuous face velocity of 185 ft/sec. The maximum manufacturer has molecular weight simulation capabilities with
axial float capability for transient conditions is± 0.100 in. Rotor air and helium mixing. The test cell setup also includes state-of­
position tolerance for seal installation is± 0.0 15 in, well within the-art software for pressure, temperature, speed, and leakage
typical compressor thrust bearing float. printouts (Figure 7).

Figure 4. Dry Gas Seal Manufacturing Facility.

Figure 3. Spiral Grooves in Dry Gas Seal Hardface.

SEAL MANUFACTURER
The seal manufacturer was selected based on the follow criteria:

• Dry gas seal engineering experience

• Manufacturing capabilities Figure 5. Seal Manufacturing Area-DNC Machines.


• Number of satisfied users

The spiral groove dry gas seal was developed in the 1970s and
the manufacturer has successfully engineered and designed these
EXECUTION
·seals for 14 years. The initial project of retrofitting the compressor with dry gas
The seal manufacturer has committed several million dollars at seals involved an engineering contractor, an overseas OEM, the
its facility, shown in Figure 4, for state-of-the-art equipment. The seal manufacturer, and the plant. The contractor insisted that the
manufacturing facility has the capability of machining extremely OEM guarantee the compressor performance with the dry gas seal.
tight toleranced part geometries from difficult, high temperature However, the OEM had no previous experience with these seals
60 PROCEEDINGS OF THE TWENTIETH TURBOMACHINERY SYMPOSIUM

from having to correct the problem during the limited shutdown


timing available.

MOCKUP
A cross section is shown in Figure 8 of one compressor case and
the oil seal components which were removed to accommodate the
new dry gas seal cartridge are illustrated. Limited availability of
the compressor for installing the dry gas seal during the shutdown
necessitated developing a method to remove a shaft sleeve without
splitting the compressor case. This sleeve needed to be removed in
order to provide a means of driving the seal. A mock up was
developed which simulated the working conditions on the com­
pressor floor. It consisted of a spare compressor rotor and a seal
bushing simulating the limited space for removing the shaft sleeve
and is shown in Figure 9.

Figure 6. QA Check During Seal Assembly.


COMPRESSOR CASING

SEAL
GLAND

COMPRESSOR CASING

Figure 7. Dry Gas Seal Testing Facility. SEAL


GLAND

and refused to guarantee the compressor performance. The plant


had to assume responsibility for managing the project and had to
work directly with the supplier.
The OEM provided the drawings and performed the bearing
stability and rotordynamic analysis based on using dry seals. They
provided the plant with sufficient information to conduct an
independent audit. The plant also used their company's worldwide Figure 8. Compressor Cross Section of Seal Area.
resources by developing a task team to work on the dry gas seal
project.
To ensure the quality and performance of the dry gas seals, all
seal components were inspected by the seal manufacturer and the Special fixtures and tooling were fabricated to facilitate remov­
results reviewed by the plant. All seals were shop tested to provide al of the shaft sleeve which included drill bits and 2.0 ft long taps.
a baseline reference for seal leakages. The tandem seal cartridges Guiding rings were used to control the drill bits and taps and then
were first tested statically and had very low leakage. Dynamic tests to secure the shaft sleeve with four bolts while two 19 in, 3/8 in all­
followed, where the seal chamber pressure and speed were varied thread studs were attached to a clamp ring puller. The first attempt
to simulate the maximum expected seal operating conditions. at removing the sleeve was successful, but revealed some short­
Leakages measured across seal faces were significantly less than comings with the technique and tooling. The 1/2 in thick guide was
the guaranteed leakages rate. After testing, the seals were disas­ too flimsy and distorted badly. Using four all thread studs for
sembled and the seal components inspected. No problems were pulling the sleeve, rather than two studs, would have helped
found. The seals were then reassembled and shipped to the plant prevent this distortion. In addition, heat had to be applied to the
site. shaft sleeve for final removal.
The utilization of the OEM to provide dimensional drawings After review of the first mock up procedure, the tooling was
and review the seal design provided benefits when it was discov­ modified and the trial was repeated. The guide tooling thickness
ered that a shaft 0-ring was located incorrectly. Even though the was increased from 1/2 in to 1 in, and additional tooling was used
seals had already been shipped, an alternate design was developed, to provide guidance for the drill bits. An "old man" was designed
the seals were returned to the seal vendor for modifications, and and fabricated to assist in the drilling procedure. The hole depth in
then reshipped in time for the shutdown. This prevented the plant the sleeve was increased from 1/2 in to 1- 1/4 in. The greater hole
ADAPTATION OF A PROPYLENE REFRIGERATION COMPRESSOR WITH DRY GAS SEALS 61

manufacturer and seal manufacturer participated in the installation


of the dry gas seals. Startup of the propylene compressor was
routine and operation of the seals has been excellent to date.

SUMMARY
The retrofit of the propylene refrigeration compressor with dry
gas seals was an enormous success. The original objectives of
eliminating oil contamination and correcting an inherent design
flaw in the existing seals were accomplished providing annual
savings of $2.4MM/yr and avoiding capital investments of $4.6MM.
By utilizing an innovative seal removal procedure, the seals were
installed on schedule, during the required shutdown timing con­
straints. In addition, by contracting with the compressor
manufacturer to provide dimensional data and an engineering
audit, by conducting our own engineering audit, and by using the
seal manufacturer's experience and quality assurance capabilities,
the seals were manufactured and installed with minimal problems
encountered and are providing outstanding performance.
Figure 9. Mock Up for Removing Shaft Sleeve.
Based on the success of this adaptation, dry gas seals will be
installed on the ethylene refrigeration compressor. Several addi­
depth appeared to relieve the sleeve and enabled it to be removed tional applications of this technology are being evaluated within
easily without being heated. This trial was very successful and Du Pont. The success of this application has opened the door for
convinced the team that the sleeve could indeed be removed during newer technologies, particularly combining dry gas seals with
the shutdown without splitting the compressor case. magnetic bearing technology to achieve totally dry, oil free com­
pressor train systems.
INSTALLATION
The ethylene plant shut down on May 30, 1991, for 21 days to REFERENCE
install the flare modernization project. The dry gas seals were
Sedy, J., "Improved Performance of Film Riding Gas Seals
installed during a 10 day "window" in the middle of this shutdown.
Through Enhancement of Hydrodynamic Effects," ASLE-78- LC-
After the propylene refrigeration compressor was blocked in and
3B- 1 ( 1978).
the system cleared of explosiveness, the existing oil seals were
removed. All four shaft sleeves were successfully removed, using
ACKNOWLEDGEMENTS
the procedure and tooling developed and proven by the mock up
prior to the shutdown. This procedure went very smoothly, taking The authors would like to acknowledge the contribution of
only eight hours to complete. The alternative procedure, which Angie Grimes and Jerry Wilkerson, E. I. du Pont de Nemours &
involved removing the compressor case, would have taken four to Co., Inc., Orange, Texas, and Siegfried M. Zierau, Exxon Chem­
six days. ical Company, Baytown, Texas, for their help in preparing this
The new dry gas seal installation was routine. The only special paper. In addition, the authors wish to acknowledge Robert Parker,
tools required for installation in the field were two threaded rods Doug Collier, and Jerry Smith, E. I. du Pont de Nemours & Co.,
and a backer plate. All four seals were installed and tested by the Inc., for their contributions in developing the mock up which led
tenth day of the shutdown. Representatives from the compressor to the success of this program.
62 PROCEEDINGS OF THE TWENTIETH TURBOMACHINERY SYMPOSIUM

You might also like