Professional Documents
Culture Documents
by
John R. Dugas, Jr.
Senior Engineer
Bich X. Tran
Senior Area Engineer
Orange, Texas
and
James F. Southcott
Market Segment Manager, Type 28 Product Group
57
58 PROCEEDINGS OF THE TWENTIETH TURBOMACHINERY SYMPOSIUM
has more than four million hours running time on various hydro Using dry gas seals eliminated both of these problems. The seals
carbons. The longest continuous running time of a dry seal expe do not use oil, so oil contamination is no longer an issue. High
rienced to date is 43000 hr. The retrofit at the Orange facility is one Flux™ tubing can be used, reducing the overall modernization
of the first applications in the United States of these dry seals with costs by $3.1MM. The design of the dry seal allows the propylene
propylene. The advantages of the dry gas seal over conventional refrigeration system to settle-out at 70-80 psig, eliminating the
oil seals are: need to flare propylene during system shutdowns. The new flare
drum was eliminated and the project investment was reduced by
• Eliminating the seal oil support system including seal oil
$ 1.5MM.
pumps, reservoirs, filters, traps, coolers and consoles.
In addition, oil fouling of the overhead condensers in the
• Eliminating the parasitic losses from the wet seal system. propylene system currently reduces their capacity by 20 percent.
• Preventing process gas contamination with seal oil. Installing dry gas seals and cleaning the oil from the system will
return these condensers to rated capacity. Assuming conservative
Reducing the process gas leaks (from 15 scfm and above for
ly that only 25 percent of this restricted capacity is recovered,
•
wet oil systems to one to three scfm for the dry gas seals).
$2.4MM/yr would be generated from the increased ethylene
• Reducing maintenance costs. production.
The ethylene refrigeration compressor has also experienced the
• Reducing unscheduled shutdowns and minimizing down
oil contamination problem. Dry gas seals have been ordered for
time.
this compressor to eliminate that problem and enable the High
BACKGROUND Flux™ tubing technology to be used for this modernization project.
The logarithmic spiral grooves on the outside portion of the alloy materials. They use four or five axis CNC machines that have
mating ring face, shown in Figure 3, serve to "pump" the gas from machine position repeatability of 80 to 160 millionths of an inch
the outer diameter (O.D.) to the inner diameter (I.D.) of the faces. (Figure 5). These machines are combined into machining cells that
The inner surface of the ring acts as a sealing dam, providing a use distributed numerical control (DNC).
barrier to gas flow. This forms a restrictive plane at the apex of the The manufacturer's quality assurance facility has the capability
spiral grooves across which the gas begins to decrease in pressure to check and certify any component part to 100 millionths of an
and expand (O.D. to I.D.). The gap stabilizes when the hydrostatic inch and flatness to within one light band or 1 1.6 millionths of an
and hydrodynamic forces are equal. The face geometry is extreme inch (Figure 6). In addition, QA records very critical component
ly critical and must provide a gas film thick enough to prevent the dimension and surface finish are available for complete traceabil
rings from physical contact, but thin enough to prevent excessive ity if required.
gas leakage. The gas leakage from these seals is less than 2 scfm The seal manufacturer provided estimates and guaranteed the
while the leakage from the oil seal systems is 15 scfm or greater. seal would not exceed predicted leakages. Each seal is tested both
The seal for this application is a tandem type, 9 5/8 in cartridge statically and dynamicall y at operating conditions. The
seal with a continuous face velocity of 185 ft/sec. The maximum manufacturer has molecular weight simulation capabilities with
axial float capability for transient conditions is± 0.100 in. Rotor air and helium mixing. The test cell setup also includes state-of
position tolerance for seal installation is± 0.0 15 in, well within the-art software for pressure, temperature, speed, and leakage
typical compressor thrust bearing float. printouts (Figure 7).
SEAL MANUFACTURER
The seal manufacturer was selected based on the follow criteria:
The spiral groove dry gas seal was developed in the 1970s and
the manufacturer has successfully engineered and designed these
EXECUTION
·seals for 14 years. The initial project of retrofitting the compressor with dry gas
The seal manufacturer has committed several million dollars at seals involved an engineering contractor, an overseas OEM, the
its facility, shown in Figure 4, for state-of-the-art equipment. The seal manufacturer, and the plant. The contractor insisted that the
manufacturing facility has the capability of machining extremely OEM guarantee the compressor performance with the dry gas seal.
tight toleranced part geometries from difficult, high temperature However, the OEM had no previous experience with these seals
60 PROCEEDINGS OF THE TWENTIETH TURBOMACHINERY SYMPOSIUM
MOCKUP
A cross section is shown in Figure 8 of one compressor case and
the oil seal components which were removed to accommodate the
new dry gas seal cartridge are illustrated. Limited availability of
the compressor for installing the dry gas seal during the shutdown
necessitated developing a method to remove a shaft sleeve without
splitting the compressor case. This sleeve needed to be removed in
order to provide a means of driving the seal. A mock up was
developed which simulated the working conditions on the com
pressor floor. It consisted of a spare compressor rotor and a seal
bushing simulating the limited space for removing the shaft sleeve
and is shown in Figure 9.
SEAL
GLAND
COMPRESSOR CASING
SUMMARY
The retrofit of the propylene refrigeration compressor with dry
gas seals was an enormous success. The original objectives of
eliminating oil contamination and correcting an inherent design
flaw in the existing seals were accomplished providing annual
savings of $2.4MM/yr and avoiding capital investments of $4.6MM.
By utilizing an innovative seal removal procedure, the seals were
installed on schedule, during the required shutdown timing con
straints. In addition, by contracting with the compressor
manufacturer to provide dimensional data and an engineering
audit, by conducting our own engineering audit, and by using the
seal manufacturer's experience and quality assurance capabilities,
the seals were manufactured and installed with minimal problems
encountered and are providing outstanding performance.
Figure 9. Mock Up for Removing Shaft Sleeve.
Based on the success of this adaptation, dry gas seals will be
installed on the ethylene refrigeration compressor. Several addi
depth appeared to relieve the sleeve and enabled it to be removed tional applications of this technology are being evaluated within
easily without being heated. This trial was very successful and Du Pont. The success of this application has opened the door for
convinced the team that the sleeve could indeed be removed during newer technologies, particularly combining dry gas seals with
the shutdown without splitting the compressor case. magnetic bearing technology to achieve totally dry, oil free com
pressor train systems.
INSTALLATION
The ethylene plant shut down on May 30, 1991, for 21 days to REFERENCE
install the flare modernization project. The dry gas seals were
Sedy, J., "Improved Performance of Film Riding Gas Seals
installed during a 10 day "window" in the middle of this shutdown.
Through Enhancement of Hydrodynamic Effects," ASLE-78- LC-
After the propylene refrigeration compressor was blocked in and
3B- 1 ( 1978).
the system cleared of explosiveness, the existing oil seals were
removed. All four shaft sleeves were successfully removed, using
ACKNOWLEDGEMENTS
the procedure and tooling developed and proven by the mock up
prior to the shutdown. This procedure went very smoothly, taking The authors would like to acknowledge the contribution of
only eight hours to complete. The alternative procedure, which Angie Grimes and Jerry Wilkerson, E. I. du Pont de Nemours &
involved removing the compressor case, would have taken four to Co., Inc., Orange, Texas, and Siegfried M. Zierau, Exxon Chem
six days. ical Company, Baytown, Texas, for their help in preparing this
The new dry gas seal installation was routine. The only special paper. In addition, the authors wish to acknowledge Robert Parker,
tools required for installation in the field were two threaded rods Doug Collier, and Jerry Smith, E. I. du Pont de Nemours & Co.,
and a backer plate. All four seals were installed and tested by the Inc., for their contributions in developing the mock up which led
tenth day of the shutdown. Representatives from the compressor to the success of this program.
62 PROCEEDINGS OF THE TWENTIETH TURBOMACHINERY SYMPOSIUM