Size of Plot
2) change construction rate.
3) change Material Quantity Area of Plot
Construction Cost
Building Construction Cost
S. No. (Material) % Amount
1 Cement 12.8 96000
2 Steel 11 84375
3 Sand 6.2 46800
4 Gravel 4 30375
Finishing
Color
5 10 77430
Tiles
Bricks
Fittings
Windows
6 Doors 8 60000
Plumbing
Electrical
Sanitary
Material Cost 53 394980
Labour Cost 37 280020
Engineers/architect 10 75000
Total Construction Cost ₹ 750,000
Length Width Construction Rate Normal Quality
25 30 ft Rate per Sq. ft. 1000
750 Sq. ft
750,000 ₹
Building Construction Materials
S.No. Material Qty Rate
0.4 1 Cement (Bags) 300 320
2.5 2 Steel (Kg) 1875 45
1.2 3 Sand (Cu.ft.) 900 52
1.35 4 Gravel (Cu. ft.) 1012.5 30
7.32 5 Bricks (Nos.) 5,490 7
0.7 6 Tiles (Sq. ft.) 525 40
0.12 7 Color (Liters) 90 200
Total Cost
n Materials
Amount
96000
84375
46800
30375
38430
21000
18000
334,980 ₹