Details of Concrete Quantity in Flyover Structure - Girder (20.0m Span - Straight)


Traingle
Sl No Description Description Parts Units Nos Length Width Depth Quantity
Portion
RCC Girder Concrete M35 (Design mix), using 20mm ISS HBG metal including cost and conveyance of all Materials to site and
cement at site including form work , using soft water, labour charges for mixing, transporting and placing in position, compacting,
finishing and curing, working at depths, hire charges for tools and plants and incidental charges, etc., complete, as per standard
specifications (Super Structuer in RCC Girder) complete as per relevant MORT&H specifications 1000&2100.
1 Girder Bottom Flange Cum 1 1 15.960 0.625 0.250 2.494
2 Girder Bottom Haunch Cum 2 0.5 14.960 0.150 0.150 0.337
3 Girder vertical End Haunch Cum 4 0.5 1.000 0.150 1.170 0.351
4 Girder Top Haunch Cum 2 0.5 15.960 0.300 0.150 0.718
5 Girder Web Cum 1 1 15.960 0.325 1.320 6.847
6 Girder End Rect Portion Cum 2 1 2.000 0.625 1.570 3.925
7 Girder Top Haunch Side end portion Cum 4 0.5 1.070 0.150 0.075 0.024

Nos of Girdrs 4 14.696 58.784


1 Cross Girder End Cross Girder Cum 1 1 12.000 0.6 1.904 13.712
2 Cross Girder Deduction Slope Cum -2 0.5 1 0.6 1.559 -0.936
3 Cross Girder Deduction Girder End Portion Cum -4 1 0.625 0.6 1.570 -2.355

Nos of End Cross Girdrs 2 10.421 20.842


1 Cross Girder Mid Cross Girder Cum 3 1 2.675 0.300 1.170 2.817

Nos of Mid Cross Girdrs 1 2.817 2.817

Total Quantity of Concrete in Girder with Diaphragm 82.443

RCC Girder Concrete M35 (Design mix), using 20mm ISS HBG metal including cost and conveyance of all Materials to site and
cement at site including form work , using soft water, labour charges for mixing, transporting and placing in position, compacting,
finishing and curing, working at depths, hire charges for tools and plants and incidental charges, etc., complete, as per standard
specifications (Super Structuer in RCC Deck Slab) complete as per relevant MORT&H specifications 1000&2100.
1 Deck Slab Deck Slab Cum 1 1 19.960 12.000 0.230 55.090

Total Quantity of Concrete in Deck Slab 55.090