cement at site including form work , using soft water, labour charges for mixing, transporting and placing in position, compacting,
finishing and curing, working at depths, hire charges for tools and plants and incidental charges, etc., complete, as per standard
specifications (Super Structuer in RCC Girder) complete as per relevant MORT&H specifications 1000&2100.
1 Girder Bottom Flange Cum 1 1 22.260 0.625 0.250 3.478
2 Girder Bottom Haunch Cum 2 0.5 21.260 0.150 0.150 0.478
3 Girder vertical End Haunch Cum 4 0.5 1.000 0.225 1.620 0.729
4 Girder Top Haunch Cum 2 0.5 22.260 0.300 0.150 1.002
5 Girder Web Cum 1 1 22.260 0.325 1.520 10.996
6 Girder End Rect Portion Cum 2 1 2.000 0.625 1.770 4.425
7 Girder Top Haunch Side end portion Cum 4 1 1.070 0.150 0.075 0.048
RCC Girder Concrete M35 (Design mix), using 20mm ISS HBG metal including cost and conveyance of all Materials to site and
cement at site including form work , using soft water, labour charges for mixing, transporting and placing in position, compacting,
finishing and curing, working at depths, hire charges for tools and plants and incidental charges, etc., complete, as per standard
specifications (Super Structuer in RCC Deck Slab) complete as per relevant MORT&H specifications 1000&2100.
1 Deck Slab Deck Slab Cum 1 1 26.260 12.000 0.230 72.478