Professional Documents
Culture Documents
Problem 1
AOA Network
2
E
A
J
D 5 7
START
1 F
B I
3
C G 6
BACK
NEXT SOLUTION
AON Network
A E
D
START
B F
J
END
G
C H I
PREVIOUS SOLUTION NEXT SOLUTION
Problem 2
AOA Network
6
f
h i
2
c
a 5
g
7
1
d
3
b
AON Network
a f
c
START
d h i END
e
b g
Problem 3
Duration
Activity Predecessor (weeks)
a - 2
b a 3
c a 6
d a 4
e b 3
f b 8
g c,e 6
h f,g 3
i d 4
j h,I 2
3
b:3 f:8
e:3
a:2 c:6 h:3 j:2
1 2 4 6 7 8
g:6
d:4
5 i:4
BACK NEXT
PREVIOUS SOLUTION
Problem 4
BACK
NEXT SOLUTION
AOA Network
D
F
A C G
3 5 6
B E
NEXT
PREVIOUS SOLUTION NEXT SOLUTION
Problem 5
Duration
Activity Predecessor (weeks)
a - 8
b a 3
c a 6
d a 4
e b 5
f b 4
g c,e 6
h d 6
i f 6
j d 4
k g,h,i 3
l j,k 3
g:6 l:3
a:8 c:6 k:3
1 2 4 7 8 9
h:6
d:4
j:4
5
(b) The critical path here is 1-2-3-4-7-8-9 which amounts to 28 weeks, therefore
the firm cannot meet the deadline.
(d) Reduction cost would be Rs.30,000 (3 weeks are to be reduced to meet the
commitments) while the penalty payment would be Rs.21,000 (for 3 weeks of
delay) and a fixed amount of Rs. 20,000. Hence the firm should invest in
efforts to bring down the duration of the project by 3 weeks
BACK NEXT
PREVIOUS SOLUTION NEXT SOLUTION
Problem 6
Duration
Activity Predecessor (weeks)
a - 6
b a 3
c a 4
d a 6
e c 4
f b 2
g d,e,f 2
3
f:2
b:3
d:6
Duration
(b) Activity Predecessor (weeks) ES EF LS LF Slack
a - 6 0 6 0 6 0
b a 3 6 9 9 12 3
c a 4 6 10 6 10 0
d a 6 6 12 8 14 2
e c 4 10 14 10 14 0
f b 2 9 11 12 14 3
g d,e,f 2 14 16 14 16 0
BACK NEXT
NEXT SOLUTION
PREVIOUS SOLUTION NEXT SOLUTION
Problem 7
Duration - 3 estimates
Most
Optimistic Likely Pessimistic
Activity Predecessor (months) (months) (months)
a - 2 4 9
b - 2 3 8
c b 4 7 14
d a 4 5 16
e b 5 7 12
f c,d 2 4 8
g c,d 6 8 14
h e,f 6 7 14
i g,h 2 3 9
Estimated
(a) Activity Time Variance S.D.
a 4.50 1.361 1.17
b 3.67 1.000 1.00
c 7.67 2.778 1.67
d 6.67 4.000 2.00
e 7.50 1.361 1.17
f 4.33 1.000 1.00
g 8.67 1.778 1.33
h 8.00 1.778 1.33
I 3.83 1.361 1.17
a:4.50 2 d:6.67
1 g:8.67 i:3.83
4 6 7
c:7.67
f:4.33
b:3.67
3 5 h:8.00
e:7.50
Estimated
(c) Path Time Variance S.D.
3.83 1-2-4-6-7 23.67 8.500 2.92
0.17 1-2-4-5-6-7 27.33 9.500 3.08
27.50 1-3-4-5-6-7 27.50 7.917 2.81
3.67 1-3-4-6-7 23.83 6.917 2.63
4.50 1-3-5-6-7 23.00 5.500 2.35
From the above table we see that the critical path is 1-2-
4-5-6-7 and the nearly critical path is 1-3-4-5-6-7
Problem 8
AON Network 4
g
a c 3
2
: 5 e
6 j FINISH
i
START 4
f
b d 4
4 3
h
9
We evaluate our options by the
following table:
Sum of the normal costs for all the activities in the above table constitutes
the direct cost without crashing
The indirect cost is @ Rs. 6000 per week charged for the project duration of
20 weeks
Crashable No. of
Activities on Activitiy weeks Direct Project Indirect
No. Critical path Crashed crashed Cost Duration Cost Total Cost
1 a,c,e,i,j None 0 179,000 20 120,000 299,000
2 a,c,e,i j 1 180,000 19 114,000 294,000
3 a,c,i e 2 186,000 17 102,000 288,000
4 c,i a 1 191,000 16 96,000 287,000
Therefore we find the optimum cost to be (Rs.) 287,000
Savings obtained by crashing activities (Rs.) 12,000
Problem 9
Manpowe 3
Duration r f:2
Activity Predecessor (weeks) required b:3
a - 6 80
b a 3 30 a:6 c:4 e:4 g:2
1 2 4 5 6
c a 4 30
d a 6 40
e c 4 30
f b 2 40 d:6
g d,e,f 2 80
Duration Total
Activity Predecessor (weeks) ES EF LS LF Slack
a - 6 0 6 0 6 0
b a 3 6 9 9 12 3
c a 4 6 10 6 10 0
d a 6 6 12 8 14 2
e c 4 10 14 10 14 0
f b 2 9 11 12 14 3
g d,e,f 2 14 16 14 16 0
a c e g
0 2 4 6 8 10 12 14 16
d
d
2 a 80 10
120
3 a 80 10
100 4 a 80 10
5 a 80 10
80 6 a 80 10
60 7 b,c,d 100 30
8 b,c,d 100 30
40 9 b,c,d 100 30
10 c,d,f 110 40
20
11 d,e,f 110 40
0 12 d,e 70 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 13 e 30 -40
14 e 30 -40
Weeks 15 g 80 10
16 g 80 10
(b)
Alternative representation of activities
Slack in the path
b f
a c e g
0 2 4 6 8 10 12 14 16
d
Week no. Activities Alternate Hiring/layoff
Alternative Scheduling 1 a 80 10
2 a 80 10
3 a 80 10
Manpower
120
4 a 80 10
100 5 a 80 10
6 a 80 10
80 7 b,c,d 100 30
60 8 b,c,d 100 30
9 b,c,d 100 30
40 10 c,d 70 0
11 d,e 70 0
20
12 d,e 70 0
0 13 e,f 70 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 14 e,f 70 0
15 g 80 10
Weeks
16 g 80 10
PREVIOUS SOLUTION
PREVIOUS SOLUTION NEXT SOLUTION
Problem 7
Duration - 3 estimates
Most
Optimistic Likely Pessimistic
Activity Predecessor (months) (months) (months)
A - 3 6 15
B - 2 4 14
C A 5 8 12
D A 3 6 9
E C 6 10 18
F B 2 4 12
G C 3 5 9
H D,E,F 4 6 14
I B 6 9 20
J G,H 2 4 6
Estimated
(a) Activity Time Variance S.D.
A 7.00 4.000 2.00
B 5.33 4.000 2.00
C 8.17 1.361 1.17
D 6.00 1.000 1.00 a:7.00
E 10.67 4.000 2.00 1
F 5.00 2.778 1.67
G 5.33 1.000 1.00 b:5.33
H 7.00 2.778 1.67
I 10.33 5.444 2.33
J 4.00 0.444 0.67
Estimated
Path Time Variance S.D.
10.34 1-2-4-6-7 26.50 6.806 2.61
36.84 1-2-4-5-6-7 36.84 17.583 4.19
12.84 1-2-5-6-7 24.00 13.222 3.64
15.51 1-3-5-6-7 21.33 10.000 3.16
21.18 1-3-7 15.66 9.444 3.07
From the above table we see that the critical path is 1-2-
4-5-6-7 and the nearly critical path is 1-2-4-6-7. The
project is likely to take 36.84 weeks to complete.
(d) Since the other firm is working for a long time, they will
have no uncertainty. We can rework the above problem with
most likely times only. (see chart alongside for details)
(e) With a standard add-in package, @RISK one can answer this
question by running a monte carlo simulation. Setup @RISK
and run it for 10,000 times to make some observations.
BACK
AOA Network (PERT)
4
c:8.17 g:5.33
e:10.67
2 d:6.00
j:4.00
5 h:7.00 7
6
f:5.00
3
i:10.33
45 weeks
36.84 weeks
4.19
1.946
97.42 %
4
c:8 g:5
e:10
a:6 2 d:6
1 h:6 j:4
5
6
b:4
f:4
3
i:9
7