Health and Satety
Executive
80 The following issues should be considered and included within the design
documentation:
|B alternative modes of plant operation using differing flow routes;
requirements for intrusive plant operations (for example filter change-out,
sampling or removal of pipeline pigs from launchers and receivers) and
requirements for access into equipment for inspection and/or maintenance; and
the detail of isolation arrangements, Including valve types, spacers/spading
points or spectacle blinds, test points and associated vents and drains for
venting, flushing and purging,
Positive isolation requirements
81 Design of new plant should include facilities for positive isolation {including
the vaNed isolation to install the positive isolation) in the following situations:
for vessel entty, where @ requirement for entry cannot be elitinated by
equipment design (see paragraph 97);
1m for isolation of toxic fulds; or
to control segregation of patts of the plant which, in allemative operating
‘modes, inight otherwise be exposed to overpressure conditions. This applies
where it is not reasonably practicable for the installed safety systems to protect
all foreseeable operating configurations, for example the separation of a
high-pressure plant from its drainage system.
Plant Identification
2 A scheme to uniquely identity all process plant, piping, and valves should be
drawn up. Alliterns should be readily identflable on the plant and referenced on the
piping and instrumentation iagrarns (P&IDs). In addition, you should permanently
label key iterns of equipment. Formal, simple, easly visible and unambiguous
labeling should be provided wherever mistakes in Kfentiication could occur and
could result in significant consequences."
Pipework
33. Pipework layout should minimise trapped inventories and allow easy removal of
fluid for isolation purposes. Ensure that pipework:
ms of sufficient size and design to minimise the possibilty of becoming blocked
in service; and
ms robust and able, where appropriate, to cope with the repetitive stresses:
imposed by vibration, pulsating pressure and temperature cycling.”
4 Any piece of pipework intended for physical disconnection should be
easily teinovable. Pipework supports should provide adequate support during
disconnection, Provide supports where temporary hoses will be requited for bleoding,
Valves
85 ‘Specify suitable isolation valves for the service fluid and operating conditions
(see Appendix 4). Ensure that you can indicate and effectively secure the
position of manually operated valves,
Pressure safety valves
36 Isolation valves should be provided downstream of pressure safely valves for
safe isolation from a shared flare or vent systomn if intrusive maintonance is intended
at any time when the rernainder of the flare or vent system Is in operation. Also,
where an isolation valve is downstream from a pressure safety valve, you should be
able to secure the isolation valve in the open position at all times when the pressure
safety valve fs on-line, Standards for safety systems in Unfired pressure vessels ate
given in BS EN 764-7.
The sa lscaton of plant and equipment Page Qt 8