PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800

PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
0 ACP Jembatan 1 36.5 days Sun 11/10/19 Fri 12/13/19 Mon 11/11/19 Tue 12/17/19 56% 11/23/19

1 START 1 day Sun 11/10/19 Sun 11/10/19 Mon 11/11/19 Mon 11/11/19 100%
2 ERECTION GIRDER 12 days Mon 11/11/19 Wed 11/20/19 Mon 11/11/19 Fri 11/22/19 100%
3 SPAN A1-P1 11 days Tue 11/12/19 Wed 11/20/19 Tue 11/12/19 Fri 11/22/19 100%
4 Bongkar dan Install Shoring 2 days Tue 11/12/19 Wed 11/13/19 Tue 11/12/19 Wed 11/13/19 100%

5 Girder 1 1.8 days Thu 11/14/19 Thu 11/14/19 Fri 11/15/19 Sat 11/16/19 100%
6 Girder 2 1 day Fri 11/15/19 Fri 11/15/19 Sun 11/17/19 Sun 11/17/19 100%
7 Girder 3 1 day Sat 11/16/19 Sat 11/16/19 Sun 11/17/19 Sun 11/17/19 100%
8 Girder 4 1 day Sun 11/17/19 Sun 11/17/19 Mon 11/18/19 Mon 11/18/19 100%
9 Girder 5 1 day Mon 11/18/19 Mon 11/18/19 Wed 11/20/19 Wed 11/20/19 100%
10 Pembongkaran Shoring dan 1 day Tue 11/19/19 Wed 11/20/19 Fri 11/22/19 Fri 11/22/19 100%
Demob
11 SPAN P1-P2 3 days Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Wed 11/13/19 100%
12 Girder Ke-5 2.5 days Mon 11/11/19 Mon 11/11/19Mon 11/11/19Wed 11/13/19100%
13 SPAN P2-P3 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
14 SPAN P3-P4 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
15 SPAN P4-P5 3 days Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Wed 11/13/19 100%
16 Girder Ke-5 2.7 days Mon 11/11/19 Mon 11/11/19Mon 11/11/19Wed 11/13/19100%
17 SPAN P5-A2 11 days Tue 11/12/19 Wed 11/20/19 Tue 11/12/19 Fri 11/22/19 100%
18 Bongkar dan Install Shoring 1 day Tue 11/12/19 Wed 11/13/19 Tue 11/12/19 Wed 11/13/19 100%

19 Girder 1 1 day Thu 11/14/19 Thu 11/14/19 Thu 11/14/19 Fri 11/15/19 100%
20 Girder 2 1 day Fri 11/15/19 Fri 11/15/19 Sun 11/17/19 Sun 11/17/19 100%
21 Girder 3 1 day Sat 11/16/19 Sat 11/16/19 Mon 11/18/19 Mon 11/18/19 100%
22 Girder 4 1 day Sun 11/17/19 Sun 11/17/19 Tue 11/19/19 Tue 11/19/19 100%
23 Girder 5 1 day Mon 11/18/19 Mon 11/18/19 Wed 11/20/19 Wed 11/20/19 100%
24 Pembongkaran Shoring dan 2 days Tue 11/19/19 Wed 11/20/19 Thu 11/21/19 Fri 11/22/19 100%
Demob
25 LANTAI JEMBATAN 36.5 days Mon 11/11/19 Fri 12/13/19 Mon 11/11/19 Tue 12/17/19 52%
26 SPAN A1-P1 24.7 days Mon 11/11/19 Thu 12/12/19 Fri 11/15/19 Mon 12/9/19 45%
27 Bearingpad 2.8 days Tue 11/19/19 Tue 11/19/19 Fri 11/15/19 Sat 11/23/19 100%
28 Pemasangan Diafragma 1 day Wed 11/20/19 Thu 11/21/19 Thu 11/21/19 Thu 11/21/19 100%
29 Stressing Diafragma 1 day Wed 11/20/19 Thu 11/21/19 Sat 11/23/19 Sat 11/23/19 100%
30 Grouting Diafragma 2 days Wed 11/20/19 Thu 11/21/19 Sat 11/23/19 Sun 11/24/19 0%
31 Besi Diafragma 0.5 days Wed 11/20/19 Wed 11/20/19 Fri 11/22/19 Sat 11/23/19 100%
32 Besi Backwall 1 day Wed 11/20/19 Thu 11/21/19 Sat 11/23/19 Sat 11/23/19 100%
33 Bekisting Diafgrama 1 day Wed 11/20/19 Fri 11/22/19 Sat 11/23/19 Sat 11/23/19 100%
34 Bekisting Backwall 3 days Wed 11/20/19 Fri 11/22/19 Sat 11/23/19 Mon 11/25/19 0%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
35 Pengecoran Difragma 1 day Sat 11/23/19 Sat 11/23/19 Tue 11/26/19 Tue 11/26/19 0% 11/23/19

36 Pengecoran Backwall 1 day Sun 11/24/19 Sun 11/24/19 Wed 11/27/19 Wed 11/27/19 0%
37 Deckslab 1 day Tue 11/19/19 Sat 11/23/19 Fri 11/22/19 Fri 11/22/19 100%
38 Langsir 1 day Tue 11/19/19 Tue 11/19/19 Fri 11/22/19 Fri 11/22/19 100%
39 pemasangan 1 day Sat 11/23/19 Sat 11/23/19 Fri 11/22/19 Fri 11/22/19 100%
40 kantilever 4.2 days Mon 11/11/19 Thu 11/28/19 Fri 11/22/19 Tue 11/26/19 70%
41 scaffolding 1 day Mon 11/11/19 Wed 11/20/19 Fri 11/22/19 Fri 11/22/19 100%
42 Langsir komponen 1 day Mon 11/11/19 Tue 11/12/19 Fri 11/22/19 Fri 11/22/19 100%
43 Pemasangan 1 day Wed 11/20/19 Wed 11/20/19 Fri 11/22/19 Fri 11/22/19 100%
44 Kayu Kaso 1 day Mon 11/11/19 Thu 11/21/19 Fri 11/22/19 Fri 11/22/19 100%
45 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Fri 11/22/19 Fri 11/22/19 100%
46 Pemasangan 1 day Thu 11/21/19 Thu 11/21/19 Fri 11/22/19 Fri 11/22/19 100%
47 Hollo / Kayu 6/12 2 days Mon 11/11/19 Sat 11/23/19 Fri 11/22/19 Sat 11/23/19 100%
48 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Fri 11/22/19 Fri 11/22/19 100%
49 Pemasangan 1 day Fri 11/22/19 Sat 11/23/19 Sat 11/23/19 Sat 11/23/19 100%
50 Triplek 3.2 days Mon 11/11/19 Wed 11/27/19 Fri 11/22/19 Mon 11/25/19 83%
51 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Fri 11/22/19 Fri 11/22/19 100%
52 Pemasangan Lantai Bawah 1 day Sun 11/24/19 Sun 11/24/19 Sat 11/23/19 Sat 11/23/19 100%

53 Pemasangan Stoper 1 day Wed 11/27/19 Wed 11/27/19 Sat 11/23/19 Mon 11/25/19 50%
samping
54 Pipa Drainase 2 days Mon 11/11/19 Sun 11/24/19 Sat 11/23/19 Sun 11/24/19 0%
55 Langsir 1 day Mon 11/11/19 Mon 11/11/19 Sat 11/23/19 Sat 11/23/19 0%
56 Pemasangan 1 day Sun 11/24/19 Sun 11/24/19 Sun 11/24/19 Sun 11/24/19 0%
57 Pembesian 3.2 days Mon 11/11/19 Wed 11/27/19 Fri 11/22/19 Mon 11/25/19 80%
58 Pabrikasi 2 days Mon 11/11/19 Mon 11/11/19 Fri 11/22/19 Sat 11/23/19 100%
59 Mobilisasi 1 day Sun 11/24/19 Mon 11/25/19 Fri 11/22/19 Sat 11/23/19 100%
60 Lifting 1 day Sun 11/24/19 Mon 11/25/19 Sat 11/23/19 Sat 11/23/19 100%
61 Pemasangan 2 days Tue 11/26/19 Wed 11/27/19 Sat 11/23/19 Mon 11/25/19 40%
62 Beton 1 day Thu 11/28/19 Thu 11/28/19 Mon 11/25/19 Tue 11/26/19 0%
63 Checklist 1 day Thu 11/28/19 Thu 11/28/19 Mon 11/25/19 Tue 11/26/19 0%
64 Pengecoran Lantai 1 day Thu 11/28/19 Thu 11/28/19 Mon 11/25/19 Tue 11/26/19 0%
65 Parapet (Kiri Kanan) 10.7 days Sun 11/24/19 Fri 12/6/19 Sat 11/23/19 Tue 12/3/19 10%
66 Pembesian 4 days Sun 11/24/19 Wed 11/27/19 Sat 11/23/19 Tue 11/26/19 25%
67 Langsir Besi 2 days Sun 11/24/19 Mon 11/25/19 Sat 11/23/19 Sun 11/24/19 50%
68 Pemasangan Besi 2 days Tue 11/26/19 Wed 11/27/19 Mon 11/25/19 Tue 11/26/19 0%
69 Molding 2.5 days Sat 11/30/19 Mon 12/2/19 Wed 11/27/19 Fri 11/29/19 0%
70 Langsir 1 day Sat 11/30/19 Sat 11/30/19 Wed 11/27/19 Thu 11/28/19 0%
Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
71 Pemasangan Molding 2 days Sat 11/30/19 Mon 12/2/19 Wed 11/27/19 Fri 11/29/19 0% 11/23/19

72 Beton 2 days Tue 12/3/19 Thu 12/5/19 Sat 11/30/19 Mon 12/2/19 0%
73 Checklist 1 day Tue 12/3/19 Wed 12/4/19 Sat 11/30/19 Sun 12/1/19 0%
74 Pengecoran 1 day Wed 12/4/19 Thu 12/5/19 Sun 12/1/19 Mon 12/2/19 0%
75 Bongkar Molding 1 day Thu 12/5/19 Fri 12/6/19 Mon 12/2/19 Tue 12/3/19 0%
76 Kanstin 10.5 days Fri 11/29/19 Mon 12/9/19 Tue 11/26/19 Fri 12/6/19 0%
77 Langsir 1 day Fri 11/29/19 Fri 11/29/19 Tue 11/26/19 Wed 11/27/19 0%
78 Pemasangan 2 days Sat 12/7/19 Mon 12/9/19 Wed 12/4/19 Fri 12/6/19 0%
79 Trotoar 13.5 days Fri 11/29/19 Thu 12/12/19 Tue 11/26/19 Mon 12/9/19 0%
80 Langsir Paving 1 day Fri 11/29/19 Fri 11/29/19 Tue 11/26/19 Wed 11/27/19 0%
81 Pasang Pasir 1 day Mon 12/9/19 Tue 12/10/19 Fri 12/6/19 Sat 12/7/19 0%
82 Pasang Paving 2 days Tue 12/10/19 Thu 12/12/19 Sat 12/7/19 Mon 12/9/19 0%
83 SPAN P1-P2 27.5 days Mon 11/11/19 Thu 12/5/19 Tue 11/12/19 Mon 12/9/19 53%
84 Bearingpad 0.6 days Tue 11/12/19 Tue 11/12/19 Tue 11/12/19 Wed 11/13/19 100%
85 Pemasangan Diafragma 2 days Wed 11/13/19 Thu 11/14/19 Sun 11/17/19 Mon 11/18/19 100%

86 Stressing Diafragma 1 day Wed 11/13/19 Thu 11/14/19 Wed 11/20/19 Wed 11/20/19 100%
87 Grouting Diafragma 2 days Wed 11/13/19 Thu 11/14/19 Sat 11/23/19 Sun 11/24/19 0%
88 Besi Diafragma 0.5 days Wed 11/13/19 Wed 11/13/19 Wed 11/20/19 Sat 11/23/19 100%
89 Besi Backwall 2 days Wed 11/13/19 Thu 11/14/19 Sat 11/23/19 Sun 11/24/19 75%
90 Bekisting Diafgrama 2 days Wed 11/13/19 Fri 11/15/19 Fri 11/22/19 Sat 11/23/19 100%
91 Bekisting Backwall 3 days Wed 11/13/19 Fri 11/15/19 Sat 11/23/19 Mon 11/25/19 0%
92 Pengecoran Difragma 1 day Sat 11/16/19 Sat 11/16/19 Tue 11/26/19 Tue 11/26/19 0%
93 Pengecoran Backwall 1 day Sun 11/17/19 Sun 11/17/19 Wed 11/27/19 Wed 11/27/19 0%
94 Deckslab 2 days Tue 11/12/19 Sat 11/16/19 Mon 11/18/19 Tue 11/19/19 100%
95 Langsir 1 day Tue 11/12/19 Tue 11/12/19 Mon 11/18/19 Mon 11/18/19 100%

96 pemasangan 0.75 days Sat 11/16/19 Sat 11/16/19 Mon 11/18/19 Tue 11/19/19 100%
97 kantilever 6 days Mon 11/11/19 Thu 11/21/19 Wed 11/20/19 Mon 11/25/19 81%
98 scaffolding 1 day Mon 11/11/19 Wed 11/13/19 Wed 11/20/19 Wed 11/20/19 100%
99 Langsir komponen 1 day Mon 11/11/19 Tue 11/12/19 Wed 11/20/19 Wed 11/20/19 100%
100 Pemasangan 1 day Wed 11/13/19 Wed 11/13/19 Wed 11/20/19 Wed 11/20/19 100%
101 Kayu Kaso 1 day Mon 11/11/19 Thu 11/14/19 Wed 11/20/19 Wed 11/20/19 100%
102 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Wed 11/20/19 Wed 11/20/19 100%
103 Pemasangan 1 day Thu 11/14/19 Thu 11/14/19 Wed 11/20/19 Wed 11/20/19 100%
104 Hollo / Kayu 6/12 1 day Mon 11/11/19 Sat 11/16/19 Wed 11/20/19 Wed 11/20/19 100%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
105 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Wed 11/20/19 Wed 11/20/19 100% 11/23/19

106 Pemasangan 1 day Fri 11/15/19 Sat 11/16/19 Wed 11/20/19 Wed 11/20/19 100%
107 Triplek 5 days Mon 11/11/19 Wed 11/20/19 Wed 11/20/19 Sun 11/24/19 92%
108 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Wed 11/20/19 Wed 11/20/19 100%
109 Pemasangan Lantai Bawah 1 day Sun 11/17/19 Sun 11/17/19 Wed 11/20/19 Wed 11/20/19 100%

110 Pemasangan Stoper 1 day Wed 11/20/19 Wed 11/20/19 Sat 11/23/19 Sun 11/24/19 75%
samping
111 Pipa Drainase 1.5 days Mon 11/11/19 Sun 11/17/19 Sat 11/23/19 Sun 11/24/19 50%
112 Langsir 1 day Mon 11/11/19 Mon 11/11/19 Sat 11/23/19 Sat 11/23/19 50%
113 Pemasangan 1 day Sun 11/17/19 Sun 11/17/19 Sat 11/23/19 Sun 11/24/19 50%
114 Pembesian 4 days Tue 11/12/19 Wed 11/20/19 Thu 11/21/19 Sun 11/24/19 93%
115 Pabrikasi 1 day Tue 11/12/19 Tue 11/12/19 Thu 11/21/19 Thu 11/21/19 100%
116 Mobilisasi 1 day Wed 11/13/19 Thu 11/14/19 Thu 11/21/19 Thu 11/21/19 100%
117 Lifting 1 day Wed 11/13/19 Thu 11/14/19 Thu 11/21/19 Thu 11/21/19 100%
118 Pemasangan 3 days Mon 11/18/19 Wed 11/20/19 Fri 11/22/19 Sun 11/24/19 85%
119 Beton 1 day Thu 11/21/19 Thu 11/21/19 Mon 11/25/19 Mon 11/25/19 0%
120 Checklist 1 day Thu 11/21/19 Thu 11/21/19 Mon 11/25/19 Mon 11/25/19 0%
121 Pengecoran Lantai 1 day Thu 11/21/19 Thu 11/21/19 Mon 11/25/19 Mon 11/25/19 0%
122 Parapet (Kiri Kanan) 18.5 days Wed 11/13/19 Thu 12/5/19 Thu 11/21/19 Mon 12/9/19 19%
123 Pembesian 4 days Wed 11/13/19 Thu 11/14/19 Thu 11/21/19 Sun 11/24/19 82%
124 Langsir Besi 2 days Wed 11/13/19 Thu 11/14/19 Thu 11/21/19 Fri 11/22/19 100%
125 Pemasangan Besi 2 days Wed 11/13/19 Thu 11/14/19 Sat 11/23/19 Sun 11/24/19 63%
126 Molding 2.5 days Sat 11/23/19 Mon 11/25/19 Wed 11/27/19 Fri 11/29/19 0%
127 Langsir 1 day Sat 11/23/19 Sat 11/23/19 Wed 11/27/19 Wed 11/27/19 0%
128 Pemasangan Molding 2 days Sat 11/23/19 Mon 11/25/19 Wed 11/27/19 Fri 11/29/19 0%

129 Beton 2 days Tue 11/26/19 Thu 11/28/19 Sat 11/30/19 Mon 12/2/19 0%
130 Checklist 1 day Tue 11/26/19 Wed 11/27/19 Sat 11/30/19 Sun 12/1/19 0%
131 Pengecoran 1 day Wed 11/27/19 Thu 11/28/19 Sun 12/1/19 Mon 12/2/19 0%
132 Bongkar Molding 1 day Thu 11/28/19 Fri 11/29/19 Mon 12/2/19 Tue 12/3/19 0%
133 Kanstin 8.5 days Sun 11/24/19 Mon 12/2/19 Thu 11/28/19 Fri 12/6/19 0%
134 Langsir 1 day Sun 11/24/19 Sun 11/24/19 Thu 11/28/19 Thu 11/28/19 0%
135 Pemasangan 2 days Sat 11/30/19 Mon 12/2/19 Wed 12/4/19 Fri 12/6/19 0%
136 Trotoar 11.5 days Sun 11/24/19 Thu 12/5/19 Thu 11/28/19 Mon 12/9/19 0%
137 Langsir Paving 1 day Sun 11/24/19 Sun 11/24/19 Thu 11/28/19 Thu 11/28/19 0%
138 Pasang Pasir 1 day Mon 12/2/19 Tue 12/3/19 Fri 12/6/19 Sat 12/7/19 0%
139 Pasang Paving 2 days Tue 12/3/19 Thu 12/5/19 Sat 12/7/19 Mon 12/9/19 0%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
140 SPAN P2-P3 24.5 days Mon 11/11/19 Wed 12/4/19 Mon 11/11/19 Thu 12/5/19 73% 11/23/19

141 Bearingpad 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
142 Pemasangan Diafragma 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
143 Stressing Diafragma 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
144 Grouting Diafragma 1 day Mon 11/11/19 Tue 11/12/19 Mon 11/18/19 Mon 11/18/19 100%
145 Besi Diafragma 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
146 Besi Backwall 1 day Mon 11/11/19 Tue 11/12/19 Wed 11/13/19 Wed 11/13/19 100%
147 Bekisting Diafgrama 1 day Mon 11/11/19 Wed 11/13/19 Tue 11/12/19 Tue 11/12/19 100%
148 Bekisting Backwall 1 day Mon 11/11/19 Wed 11/13/19 Fri 11/15/19 Fri 11/15/19 100%
149 Pengecoran Difragma 1 day Thu 11/14/19 Thu 11/14/19 Tue 11/12/19 Tue 11/12/19 100%
150 Pengecoran Backwall 1 day Fri 11/15/19 Fri 11/15/19 Mon 11/18/19 Mon 11/18/19 100%
151 Deckslab 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
152 Langsir 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
153 pemasangan 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
154 kantilever 10 days Mon 11/11/19 Wed 11/20/19 Mon 11/11/19 Wed 11/20/19 100%
155 scaffolding 6.25 days Mon 11/11/19 Wed 11/13/19 Mon 11/11/19 Sun 11/17/19 100%
156 Langsir komponen 2 days Mon 11/11/19 Tue 11/12/19 Mon 11/11/19 Tue 11/12/19 100%
157 Pemasangan 0.5 days Mon 11/11/19 Wed 11/13/19 Fri 11/15/19 Sun 11/17/19 100%
158 Kayu Kaso 7 days Mon 11/11/19 Thu 11/14/19 Tue 11/12/19 Mon 11/18/19 100%
159 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Tue 11/12/19 Tue 11/12/19 100%
160 Pemasangan 2.25 days Wed 11/13/19 Thu 11/14/19 Wed 11/13/19 Mon 11/18/19 100%
161 Hollo / Kayu 6/12 6 days Mon 11/11/19 Sat 11/16/19 Wed 11/13/19 Mon 11/18/19 100%
162 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Wed 11/13/19 Wed 11/13/19 100%
163 Pemasangan 1 day Thu 11/14/19 Sat 11/16/19 Wed 11/13/19 Mon 11/18/19 100%
164 Triplek 4 days Mon 11/11/19 Tue 11/19/19 Fri 11/15/19 Mon 11/18/19 100%
165 Langsir 3.5 days Mon 11/11/19 Tue 11/12/19 Fri 11/15/19 Mon 11/18/19 100%
166 Pemasangan Lantai Bawah 1 day Sat 11/16/19 Sun 11/17/19 Mon 11/18/19 Mon 11/18/19 100%

167 Pemasangan Stoper 1 day Mon 11/18/19 Tue 11/19/19 Mon 11/18/19 Mon 11/18/19 100%
samping
168 Pipa Drainase 1 day Mon 11/11/19 Sun 11/17/19 Mon 11/18/19 Mon 11/18/19 100%
169 Langsir 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/18/19 Mon 11/18/19 100%
170 Pemasangan 1 day Sat 11/16/19 Sun 11/17/19 Mon 11/18/19 Mon 11/18/19 100%
171 Pembesian 7 days Mon 11/11/19 Tue 11/19/19 Tue 11/12/19 Mon 11/18/19 100%
172 Pabrikasi 1 day Mon 11/11/19 Mon 11/11/19 Tue 11/12/19 Tue 11/12/19 100%
173 Mobilisasi 1 day Tue 11/12/19 Wed 11/13/19 Tue 11/12/19 Tue 11/12/19 100%
174 Lifting 1 day Tue 11/12/19 Wed 11/13/19 Mon 11/18/19 Mon 11/18/19 100%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 5 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
175 Pemasangan 1 day Sun 11/17/19 Tue 11/19/19 Mon 11/18/19 Mon 11/18/19 100% 11/23/19

176 Beton 3 days Tue 11/19/19 Wed 11/20/19 Mon 11/18/19 Wed 11/20/19 100%
177 Checklist 1 day Tue 11/19/19 Wed 11/20/19 Mon 11/18/19 Mon 11/18/19 100%
178 Pengecoran Lantai 1 day Tue 11/19/19 Wed 11/20/19 Wed 11/20/19 Wed 11/20/19 100%
179 Parapet (Kiri Kanan) 22.5 days Tue 11/12/19 Wed 12/4/19 Wed 11/13/19 Thu 12/5/19 13%
180 Pembesian 6 days Tue 11/12/19 Wed 11/13/19 Wed 11/13/19 Mon 11/18/19 100%
181 Langsir Besi 1 day Tue 11/12/19 Wed 11/13/19 Wed 11/13/19 Wed 11/13/19 100%
182 Pemasangan Besi 1 day Tue 11/12/19 Wed 11/13/19 Mon 11/18/19 Mon 11/18/19 100%
183 Molding 2.5 days Thu 11/21/19 Sun 11/24/19 Sat 11/23/19 Mon 11/25/19 0%
184 Langsir 1 day Thu 11/21/19 Fri 11/22/19 Sat 11/23/19 Sat 11/23/19 0%
185 Pemasangan Molding 2 days Fri 11/22/19 Sun 11/24/19 Sat 11/23/19 Mon 11/25/19 0%

186 Beton 2 days Mon 11/25/19 Wed 11/27/19 Tue 11/26/19 Thu 11/28/19 0%
187 Checklist 1 day Mon 11/25/19 Tue 11/26/19 Tue 11/26/19 Wed 11/27/19 0%
188 Pengecoran 1 day Tue 11/26/19 Wed 11/27/19 Wed 11/27/19 Thu 11/28/19 0%
189 Bongkar Molding 1 day Wed 11/27/19 Thu 11/28/19 Thu 11/28/19 Fri 11/29/19 0%
190 Kanstin 8.5 days Fri 11/22/19 Sun 12/1/19 Sun 11/24/19 Mon 12/2/19 0%
191 Langsir 1 day Fri 11/22/19 Sat 11/23/19 Sun 11/24/19 Sun 11/24/19 0%
192 Pemasangan 2 days Fri 11/29/19 Sun 12/1/19 Sat 11/30/19 Mon 12/2/19 0%
193 Trotoar 11.5 days Fri 11/22/19 Wed 12/4/19 Sun 11/24/19 Thu 12/5/19 0%
194 Langsir Paving 1 day Fri 11/22/19 Sat 11/23/19 Sun 11/24/19 Sun 11/24/19 0%
195 Pasang Pasir 1 day Sun 12/1/19 Mon 12/2/19 Mon 12/2/19 Tue 12/3/19 0%
196 Pasang Paving 2 days Mon 12/2/19 Wed 12/4/19 Tue 12/3/19 Thu 12/5/19 0%
197 SPAN P3-P4 24 days Mon 11/11/19 Tue 12/3/19 Mon 11/11/19 Wed 12/4/19 74%
198 Bearingpad 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
199 Pemasangan Diafragma 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
200 Stressing Diafragma 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
201 Grouting Diafragma 1 day Mon 11/11/19 Tue 11/12/19 Mon 11/18/19 Mon 11/18/19 100%
202 Besi Diafragma 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
203 Besi Backwall 1 day Mon 11/11/19 Tue 11/12/19 Wed 11/13/19 Wed 11/13/19 100%
204 Bekisting Diafgrama 1 day Mon 11/11/19 Wed 11/13/19 Tue 11/12/19 Tue 11/12/19 100%
205 Bekisting Backwall 1 day Mon 11/11/19 Wed 11/13/19 Thu 11/14/19 Thu 11/14/19 100%
206 Pengecoran Difragma 1 day Thu 11/14/19 Thu 11/14/19 Tue 11/12/19 Tue 11/12/19 100%
207 Pengecoran Backwall 1 day Fri 11/15/19 Fri 11/15/19 Fri 11/15/19 Fri 11/15/19 100%
208 Deckslab 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
209 Langsir 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
210 pemasangan 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 6 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
211 kantilever 10 days Mon 11/11/19 Tue 11/19/19 Mon 11/11/19 Wed 11/20/19 100% 11/23/19

212 scaffolding 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
213 Langsir komponen 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
214 Pemasangan 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
215 Kayu Kaso 3 days Mon 11/11/19 Wed 11/13/19 Mon 11/11/19 Wed 11/13/19 100%
216 Langsir 2 days Mon 11/11/19 Tue 11/12/19 Mon 11/11/19 Tue 11/12/19 100%
217 Pemasangan 1 day Wed 11/13/19 Wed 11/13/19 Wed 11/13/19 Wed 11/13/19 100%
218 Hollo / Kayu 6/12 3 days Mon 11/11/19 Fri 11/15/19 Mon 11/11/19 Wed 11/13/19 100%
219 Langsir 2 days Mon 11/11/19 Tue 11/12/19 Mon 11/11/19 Tue 11/12/19 100%
220 Pemasangan 1 day Thu 11/14/19 Fri 11/15/19 Wed 11/13/19 Wed 11/13/19 100%
221 Triplek 6 days Mon 11/11/19 Mon 11/18/19 Wed 11/13/19 Mon 11/18/19 100%
222 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Wed 11/13/19 Wed 11/13/19 100%
223 Pemasangan Lantai Bawah 1.5 days Sat 11/16/19 Sat 11/16/19 Wed 11/13/19 Fri 11/15/19 100%

224 Pemasangan Stoper 1 day Mon 11/18/19 Mon 11/18/19 Mon 11/18/19 Mon 11/18/19 100%
samping
225 Pipa Drainase 1 day Mon 11/11/19 Sat 11/16/19 Tue 11/19/19 Tue 11/19/19 100%
226 Langsir 1 day Mon 11/11/19 Mon 11/11/19 Tue 11/19/19 Tue 11/19/19 100%
227 Pemasangan 1 day Sat 11/16/19 Sat 11/16/19 Tue 11/19/19 Tue 11/19/19 100%
228 Pembesian 7 days Mon 11/11/19 Mon 11/18/19 Mon 11/11/19 Sun 11/17/19 100%
229 Pabrikasi 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 Mon 11/11/19 100%
230 Mobilisasi 1 day Tue 11/12/19 Wed 11/13/19 Tue 11/12/19 Tue 11/12/19 100%
231 Lifting 1 day Tue 11/12/19 Wed 11/13/19 Wed 11/13/19 Wed 11/13/19 100%
232 Pemasangan 2.6 days Sun 11/17/19 Mon 11/18/19 Fri 11/15/19 Sun 11/17/19 100%
233 Beton 2 days Tue 11/19/19 Tue 11/19/19 Tue 11/19/19 Wed 11/20/19 100%
234 Checklist 1 day Tue 11/19/19 Tue 11/19/19 Tue 11/19/19 Tue 11/19/19 100%
235 Pengecoran Lantai 1 day Tue 11/19/19 Tue 11/19/19 Wed 11/20/19 Wed 11/20/19 100%
236 Parapet (Kiri Kanan) 19 days Tue 11/12/19 Tue 12/3/19 Sat 11/16/19 Wed 12/4/19 17%
237 Pembesian 2 days Tue 11/12/19 Wed 11/13/19 Sat 11/16/19 Sun 11/17/19 100%
238 Langsir Besi 1 day Tue 11/12/19 Wed 11/13/19 Sat 11/16/19 Sat 11/16/19 100%
239 Pemasangan Besi 1 day Tue 11/12/19 Wed 11/13/19 Sun 11/17/19 Sun 11/17/19 100%
240 Molding 4 days Thu 11/21/19 Sat 11/23/19 Thu 11/21/19 Sun 11/24/19 17%
241 Langsir 1 day Thu 11/21/19 Thu 11/21/19 Thu 11/21/19 Sat 11/23/19 50%
242 Pemasangan Molding 2 days Thu 11/21/19 Sat 11/23/19 Sat 11/23/19 Sun 11/24/19 0%

243 Beton 2 days Sun 11/24/19 Tue 11/26/19 Tue 11/26/19 Wed 11/27/19 0%
244 Checklist 1 day Sun 11/24/19 Mon 11/25/19 Tue 11/26/19 Tue 11/26/19 0%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 7 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
245 Pengecoran 1 day Mon 11/25/19 Tue 11/26/19 Wed 11/27/19 Wed 11/27/19 0% 11/23/19

246 Bongkar Molding 1 day Tue 11/26/19 Wed 11/27/19 Thu 11/28/19 Thu 11/28/19 0%
247 Kanstin 8.5 days Fri 11/22/19 Sat 11/30/19 Sat 11/23/19 Sun 12/1/19 0%
248 Langsir 1 day Fri 11/22/19 Fri 11/22/19 Sat 11/23/19 Sun 11/24/19 0%
249 Pemasangan 2 days Thu 11/28/19 Sat 11/30/19 Sat 11/30/19 Sun 12/1/19 0%
250 Trotoar 11.5 days Fri 11/22/19 Tue 12/3/19 Sat 11/23/19 Wed 12/4/19 0%
251 Langsir Paving 1 day Fri 11/22/19 Fri 11/22/19 Sat 11/23/19 Sun 11/24/19 0%
252 Pasang Pasir 1 day Sat 11/30/19 Sun 12/1/19 Mon 12/2/19 Mon 12/2/19 0%
253 Pasang Paving 2 days Sun 12/1/19 Tue 12/3/19 Tue 12/3/19 Wed 12/4/19 0%
254 SPAN P4-P5 26.5 days Mon 11/11/19 Tue 12/3/19 Tue 11/12/19 Sun 12/8/19 72%
255 Bearingpad 0.6 days Tue 11/12/19 Tue 11/12/19 Tue 11/12/19 Wed 11/13/19 100%
256 Pemasangan Diafragma 1 day Wed 11/13/19 Thu 11/14/19 Thu 11/14/19 Thu 11/14/19 100%
257 Stressing Diafragma 1 day Wed 11/13/19 Thu 11/14/19 Sun 11/17/19 Sun 11/17/19 100%
258 Grouting Diafragma 2 days Wed 11/13/19 Thu 11/14/19 Sat 11/23/19 Sun 11/24/19 0%
259 Besi Diafragma 2.88 days Wed 11/13/19 Wed 11/13/19 Thu 11/14/19 Sun 11/17/19 100%
260 Besi Backwall 2.6 days Wed 11/13/19 Thu 11/14/19 Sun 11/17/19 Tue 11/19/19 100%
261 Bekisting Diafgrama 3.64 days Wed 11/13/19 Fri 11/15/19 Thu 11/14/19 Sun 11/17/19 100%
262 Bekisting Backwall 1 day Wed 11/13/19 Fri 11/15/19 Thu 11/21/19 Thu 11/21/19 100%
263 Pengecoran Difragma 1 day Sat 11/16/19 Sat 11/16/19 Tue 11/19/19 Tue 11/19/19 100%
264 Pengecoran Backwall 1 day Sun 11/17/19 Sun 11/17/19 Thu 11/21/19 Thu 11/21/19 100%
265 Deckslab 4 days Tue 11/12/19 Sat 11/16/19 Tue 11/12/19 Fri 11/15/19 100%
266 Langsir 1 day Tue 11/12/19 Tue 11/12/19 Tue 11/12/19 Tue 11/12/19 100%
267 pemasangan 1 day Sat 11/16/19 Sat 11/16/19 Fri 11/15/19 Fri 11/15/19 100%
268 kantilever 11 days Mon 11/11/19 Tue 11/19/19 Thu 11/14/19 Sun 11/24/19 100%
269 scaffolding 5 days Mon 11/11/19 Wed 11/13/19 Thu 11/14/19 Mon 11/18/19 100%
270 Langsir komponen 1 day Mon 11/11/19 Tue 11/12/19 Thu 11/14/19 Thu 11/14/19 100%
271 Pemasangan 0.85 days Wed 11/13/19 Wed 11/13/19 Fri 11/15/19 Mon 11/18/19 100%
272 Kayu Kaso 1 day Mon 11/11/19 Thu 11/14/19 Mon 11/18/19 Mon 11/18/19 100%
273 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Mon 11/18/19 Mon 11/18/19 100%
274 Pemasangan 1 day Thu 11/14/19 Thu 11/14/19 Mon 11/18/19 Mon 11/18/19 100%
275 Hollo / Kayu 6/12 1 day Mon 11/11/19 Fri 11/15/19 Mon 11/18/19 Mon 11/18/19 100%
276 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Mon 11/18/19 Mon 11/18/19 100%
277 Pemasangan 1 day Thu 11/14/19 Fri 11/15/19 Mon 11/18/19 Mon 11/18/19 100%
278 Triplek 1 day Mon 11/11/19 Mon 11/18/19 Mon 11/18/19 Mon 11/18/19 100%
279 Langsir 1 day Mon 11/11/19 Tue 11/12/19 Mon 11/18/19 Mon 11/18/19 100%
280 Pemasangan Lantai Bawah 1 day Sat 11/16/19 Sat 11/16/19 Mon 11/18/19 Mon 11/18/19 100%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 8 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
281 Pemasangan Stoper 1 day Mon 11/18/19 Mon 11/18/19 Mon 11/18/19 Mon 11/18/19 100% 11/23/19
samping
282 Pipa Drainase 1 day Mon 11/11/19 Sat 11/16/19 Mon 11/18/19 Mon 11/18/19 100%
283 Langsir 1 day Mon 11/11/19 Mon 11/11/19 Mon 11/18/19 Mon 11/18/19 100%
284 Pemasangan 1 day Sat 11/16/19 Sat 11/16/19 Mon 11/18/19 Mon 11/18/19 100%
285 Pembesian 6 days Mon 11/11/19 Mon 11/18/19 Thu 11/14/19 Tue 11/19/19 100%
286 Pabrikasi 1.3 days Mon 11/11/19 Mon 11/11/19 Thu 11/14/19 Tue 11/19/19 100%
287 Mobilisasi 1 day Tue 11/12/19 Wed 11/13/19 Tue 11/19/19 Tue 11/19/19 100%
288 Lifting 1 day Tue 11/12/19 Wed 11/13/19 Tue 11/19/19 Tue 11/19/19 100%
289 Pemasangan 1 day Sun 11/17/19 Mon 11/18/19 Tue 11/19/19 Tue 11/19/19 100%
290 Beton 4 days Tue 11/19/19 Tue 11/19/19 Thu 11/21/19 Sun 11/24/19 100%
291 Checklist 1 day Tue 11/19/19 Tue 11/19/19 Thu 11/21/19 Thu 11/21/19 100%
292 Pengecoran Lantai 2 days Tue 11/19/19 Tue 11/19/19 Sat 11/23/19 Sun 11/24/19 100%
293 Parapet (Kiri Kanan) 17.5 days Tue 11/12/19 Tue 12/3/19 Thu 11/21/19 Sun 12/8/19 19%
294 Pembesian 2 days Tue 11/12/19 Wed 11/13/19 Thu 11/21/19 Fri 11/22/19 100%
295 Langsir Besi 1 day Tue 11/12/19 Wed 11/13/19 Thu 11/21/19 Thu 11/21/19 100%
296 Pemasangan Besi 2 days Tue 11/12/19 Wed 11/13/19 Thu 11/21/19 Fri 11/22/19 100%
297 Molding 2.5 days Thu 11/21/19 Sat 11/23/19 Tue 11/26/19 Thu 11/28/19 0%
298 Langsir 1 day Thu 11/21/19 Thu 11/21/19 Tue 11/26/19 Tue 11/26/19 0%
299 Pemasangan Molding 2 days Thu 11/21/19 Sat 11/23/19 Tue 11/26/19 Thu 11/28/19 0%

300 Beton 2 days Sun 11/24/19 Tue 11/26/19 Fri 11/29/19 Sun 12/1/19 0%
301 Checklist 1 day Sun 11/24/19 Mon 11/25/19 Fri 11/29/19 Sat 11/30/19 0%
302 Pengecoran 1 day Mon 11/25/19 Tue 11/26/19 Sat 11/30/19 Sun 12/1/19 0%
303 Bongkar Molding 1 day Tue 11/26/19 Wed 11/27/19 Sun 12/1/19 Mon 12/2/19 0%
304 Kanstin 8.5 days Fri 11/22/19 Sat 11/30/19 Wed 11/27/19 Thu 12/5/19 0%
305 Langsir 1 day Fri 11/22/19 Fri 11/22/19 Wed 11/27/19 Wed 11/27/19 0%
306 Pemasangan 2 days Thu 11/28/19 Sat 11/30/19 Tue 12/3/19 Thu 12/5/19 0%
307 Trotoar 11.5 days Fri 11/22/19 Tue 12/3/19 Wed 11/27/19 Sun 12/8/19 0%
308 Langsir Paving 1 day Fri 11/22/19 Fri 11/22/19 Wed 11/27/19 Wed 11/27/19 0%
309 Pasang Pasir 1 day Sat 11/30/19 Sun 12/1/19 Thu 12/5/19 Fri 12/6/19 0%
310 Pasang Paving 2 days Sun 12/1/19 Tue 12/3/19 Fri 12/6/19 Sun 12/8/19 0%
311 SPAN P5-A2 25.5 days Mon 11/11/19 Thu 12/12/19 Thu 11/21/19 Mon 12/16/19 9%
312 Bearingpad 0.5 days Tue 11/19/19 Tue 11/19/19 Thu 11/21/19 Thu 11/21/19 100%
313 Pemasangan Diafragma 1 day Wed 11/20/19 Thu 11/21/19 Fri 11/22/19 Fri 11/22/19 100%
314 Stressing Diafragma 1 day Wed 11/20/19 Thu 11/21/19 Sat 11/23/19 Sat 11/23/19 100%
315 Grouting Diafragma 2 days Wed 11/20/19 Thu 11/21/19 Sat 11/23/19 Sun 11/24/19 0%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 9 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
316 Besi Diafragma 1 day Wed 11/20/19 Wed 11/20/19 Sat 11/23/19 Sat 11/23/19 0% 11/23/19

317 Besi Backwall 2 days Wed 11/20/19 Thu 11/21/19 Sat 11/23/19 Sun 11/24/19 0%
318 Bekisting Diafgrama 3 days Wed 11/20/19 Fri 11/22/19 Sat 11/23/19 Mon 11/25/19 0%
319 Bekisting Backwall 3 days Wed 11/20/19 Fri 11/22/19 Sat 11/23/19 Mon 11/25/19 0%
320 Pengecoran Difragma 1 day Sat 11/23/19 Sat 11/23/19 Tue 11/26/19 Tue 11/26/19 0%
321 Pengecoran Backwall 1 day Sun 11/24/19 Sun 11/24/19 Wed 11/27/19 Wed 11/27/19 0%
322 Deckslab 4 days Tue 11/19/19 Sat 11/23/19 Sat 11/23/19 Tue 11/26/19 78%
323 Langsir 1 day Tue 11/19/19 Tue 11/19/19 Sat 11/23/19 Sat 11/23/19 78%
324 pemasangan 1 day Sat 11/23/19 Sat 11/23/19 Sat 11/23/19 Tue 11/26/19 78%
325 kantilever 10 days Mon 11/11/19 Thu 11/28/19 Sat 11/23/19 Mon 12/2/19 4%
326 scaffolding 2 days Mon 11/11/19 Wed 11/20/19 Sat 11/23/19 Sun 11/24/19 50%
327 Langsir komponen 1 day Mon 11/11/19 Tue 11/12/19 Sat 11/23/19 Sat 11/23/19 100%
328 Pemasangan 1 day Wed 11/20/19 Wed 11/20/19 Sun 11/24/19 Sun 11/24/19 0%
329 Kayu Kaso 3 days Mon 11/11/19 Thu 11/21/19 Sat 11/23/19 Mon 11/25/19 0%
330 Langsir 2 days Mon 11/11/19 Tue 11/12/19 Sat 11/23/19 Sun 11/24/19 0%
331 Pemasangan 1 day Thu 11/21/19 Thu 11/21/19 Mon 11/25/19 Mon 11/25/19 0%
332 Hollo / Kayu 6/12 5 days Mon 11/11/19 Sat 11/23/19 Sat 11/23/19 Wed 11/27/19 0%
333 Langsir 2 days Mon 11/11/19 Tue 11/12/19 Sat 11/23/19 Sun 11/24/19 0%
334 Pemasangan 2 days Fri 11/22/19 Sat 11/23/19 Tue 11/26/19 Wed 11/27/19 0%
335 Triplek 9 days Mon 11/11/19 Wed 11/27/19 Sat 11/23/19 Sun 12/1/19 0%
336 Langsir 2 days Mon 11/11/19 Tue 11/12/19 Sat 11/23/19 Sun 11/24/19 0%
337 Pemasangan Lantai Bawah 1 day Sun 11/24/19 Sun 11/24/19 Thu 11/28/19 Thu 11/28/19 0%

338 Pemasangan Stoper 1 day Wed 11/27/19 Wed 11/27/19 Sun 12/1/19 Sun 12/1/19 0%
samping
339 Pipa Drainase 6 days Mon 11/11/19 Sun 11/24/19 Sat 11/23/19 Thu 11/28/19 0%
340 Langsir 1 day Mon 11/11/19 Mon 11/11/19 Sat 11/23/19 Sat 11/23/19 0%
341 Pemasangan 1 day Sun 11/24/19 Sun 11/24/19 Thu 11/28/19 Thu 11/28/19 0%
342 Pembesian 9 days Mon 11/11/19 Wed 11/27/19 Sat 11/23/19 Sun 12/1/19 0%
343 Pabrikasi 1 day Mon 11/11/19 Mon 11/11/19 Sat 11/23/19 Sat 11/23/19 0%
344 Mobilisasi 2 days Tue 11/12/19 Wed 11/13/19 Sun 11/24/19 Mon 11/25/19 0%
345 Lifting 2 days Tue 11/12/19 Wed 11/13/19 Sun 11/24/19 Mon 11/25/19 0%
346 Pemasangan 3 days Mon 11/25/19 Wed 11/27/19 Fri 11/29/19 Sun 12/1/19 0%
347 Beton 1 day Thu 11/28/19 Thu 11/28/19 Mon 12/2/19 Mon 12/2/19 0%
348 Checklist 1 day Thu 11/28/19 Thu 11/28/19 Mon 12/2/19 Mon 12/2/19 0%
349 Pengecoran Lantai 1 day Thu 11/28/19 Thu 11/28/19 Mon 12/2/19 Mon 12/2/19 0%
350 Parapet (Kiri Kanan) 22.5 days Tue 11/12/19 Thu 12/12/19 Sun 11/24/19 Mon 12/16/19 0%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 10 By : Engineering SC-4 yang Paling Oke


PROYEK PEMBANGUNAN JALAN BARU BATAS KOTA SINGARAJA - MENGWITANI kM 47+800
PAKET SC-4

ID Task Mode Task Name Duration Baseline Start Baseline Finish Start Finish %'19
Nov 3, Nov 10, '19 Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19
Complete S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
351 Pembesian 2 days Tue 11/12/19 Wed 11/13/19 Sun 11/24/19 Mon 11/25/19 0% 11/23/19

352 Langsir Besi 2 days Tue 11/12/19 Wed 11/13/19 Sun 11/24/19 Mon 11/25/19 0%
353 Pemasangan Besi 2 days Tue 11/12/19 Wed 11/13/19 Sun 11/24/19 Mon 11/25/19 0%
354 Molding 2.5 days Sat 11/30/19 Mon 12/2/19 Wed 12/4/19 Fri 12/6/19 0%
355 Langsir 1 day Sat 11/30/19 Sat 11/30/19 Wed 12/4/19 Wed 12/4/19 0%
356 Pemasangan Molding 2 days Sat 11/30/19 Mon 12/2/19 Wed 12/4/19 Fri 12/6/19 0%

357 Beton 2 days Tue 12/3/19 Thu 12/5/19 Sat 12/7/19 Mon 12/9/19 0%
358 Checklist 1 day Tue 12/3/19 Wed 12/4/19 Sat 12/7/19 Sun 12/8/19 0%
359 Pengecoran 1 day Wed 12/4/19 Thu 12/5/19 Sun 12/8/19 Mon 12/9/19 0%
360 Bongkar Molding 1 day Thu 12/5/19 Fri 12/6/19 Mon 12/9/19 Tue 12/10/19 0%
361 Kanstin 8.5 days Sun 12/1/19 Mon 12/9/19 Thu 12/5/19 Fri 12/13/19 0%
362 Langsir 1 day Sun 12/1/19 Sun 12/1/19 Thu 12/5/19 Thu 12/5/19 0%
363 Pemasangan 2 days Sat 12/7/19 Mon 12/9/19 Wed 12/11/19 Fri 12/13/19 0%
364 Trotoar 11.5 days Sun 12/1/19 Thu 12/12/19 Thu 12/5/19 Mon 12/16/19 0%
365 Langsir Paving 1 day Sun 12/1/19 Sun 12/1/19 Thu 12/5/19 Thu 12/5/19 0%
366 Pasang Pasir 1 day Mon 12/9/19 Tue 12/10/19 Fri 12/13/19 Sat 12/14/19 0%
367 Pasang Paving 2 days Tue 12/10/19 Thu 12/12/19 Sat 12/14/19 Mon 12/16/19 0%
368 SELESAI 1 day Thu 12/12/19 Fri 12/13/19 Mon 12/16/19 Tue 12/17/19 0%

Task Project Summary Manual Task Start-only Deadline

Project: ACP Jembatan 1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/24/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 11 By : Engineering SC-4 yang Paling Oke