Professional Documents
Culture Documents
Document
Document
Project Controlling
5.1 Project Scheduling
In real- life projects involve hundreds of activities, it is important to identify the group of critical
activity so that special care is taken to make sure they are not delayed. All these statements
are the basic objectives of the scheduling process, who is adds a time dimension to the planning
process. In other words, we can briefly state that:
Scheduling = Planning + Time
Scheduling is the determination of timing of the activities comprising the project to enable
managers to execute the project in a timely manner.
Project scheduling is the process of converting a general or outline plan for a project into a
time – based graphic presentation given information on available resources and time
constraints.
In other we can say that – project scheduling is the process of identifying and organizing the
tasks of a project into a sequence of events ensuring a harmonious completion of the venture.
Path: Path is the series of connected activities between any two events in a network.
Critical Activities, events, or paths which, if delayed, will delay the completion of the
project. A project's critical path is understand to mean that sequence of critical
activities that connects the project's start event to its finish event and which cannot to
be delayed without delaying the project.
To transform a project plan into a network, one must know what activities comprise the
project and, for each activity, what its predecessors are. An activity can be in any of
these condition: (1) it may have a successor(s) but no predecessor(s); (2) it may have a
predecessor(s); and (3) it may have both predecessor(s) and successor(s).
The first of these is an activity that starts a network.
The second ends a network.
The third is in the middle.
Fig:1
a) Predecessor activity: Activities that must be completed immediately prior to the start of
another activity are called as Predecessor Activity.
b) Successor activity: Activities which that cannot be started until one or more of other
activities are completed, but immediately succeed them are called Successor Activity.
c) Concurrent activity: Activities which can be accomplished concurrently are known as
concurrent activities.
d) Dummy activity: In mist projects many activities can be performed concurrently or
simultaneously. It is possible that two activities could be drawn by the same beginning
and end events. In such situation when two or more activities can be performed
concurrently, the concept of dummy activity is introduced to resolve this problem. Thus,
can activity which does not consume any kind of resource but merely depicts the
technological dependence is termed as dummy activity.
Dummy Activities is inserted in the network to clarify the activity pattern in the
following two situation:
To make activities with common starting and finishing points distinguishable.
To identify and maintain proper precedence relationship between activities
those are not connected by events.
Example: Consider a situation where A and B are concurrent activities C is dependent
on A and D is dependent on both A and B. Such a situation can be handled using a dummy
activity as follows:
a) Total float: The amount of time by which the completion of an activity could be
delayed beyond the earliest expected completion time without affecting the overall
project duration time. This float is concerned with overall project duration.
b) Free float: The amount of time by which the completion of an activity could be
delayed beyond the earliest expected completion time without affecting the earliest
start of a succeeding activity. This float is concern with the commencement of the
succeeding activity.
5. Path: Path is the series of connected activities between any two events in a network. By
the term path we mean a sequence of activities such that it begins at the starting event
and end at the final event. The length of a path is the sum of the individual time of the
activities lying on a path.
Critical Path: Critical path can be defined as “ the sequence of critical activities in a network
“. Critical path is the sequence of critical activities, which decide the total project duration.
A critical path consumes maximum resource. It is the longest path and consumes maximum
time. It is the one, which connects the events having zero minimum float.
OR
The critical path is the longest path in the network from starting event to ending event and
defines the minimum time required to complete the project.
The early start schedule: Early start schedule refers to the schedule in which all activities start
as early as possible. In this schedule
Are event rear at their earliest because all activities start at their earliest starting
time and finish at their earliest finishing time.
There may be time legs between the completion of certain activities and the
occurrence of events which these activities lead to and
All activities emanating from an event at the same time.
It suggest a cautious attitude towards the project and a desire to minimize the possibility of
delay. It provides a greater measure of protection against uncertainties and adverse
circumstances. Such a schedule however, calls for an earlier application of resources. A model
for early start schedule is given below:
The late start schedule: It refers to the schedule arrived at when all activities are started as late
as possible. In this schedule,
All events occur at their latest because all activities start at their latest
starting time and finish at their latest finishing time.
Some activities may start after a time lag subsequent to the occurrence of
the proceeding events.
All activities to an event are completed at the same time.
The late start schedule reflects a desire to commit resources late as late a possible. However,
such a schedule provides no elbow room in the wake of adverse developments. Any
unanticipated delay results in increased project duration. A modal for late start schedule is
given below:
The latest start schedule
Both are invaluable in forcing a Project Team to think through the detail of what needs to be
done, what the priorities and linkages are, and then as a mean of communicating intentions to
others in a diagram or picture.