Cut and Fill Table

Section Station Design Level Ground

1 0 583 575.2----------574.3

2 180 567.5 571.9----------571.0

3 240 574.3 574.8----------574.0

4 420 567.6 576.1----------575.2

5 560 563.9 563.5----------563.5

6 640 563.0 559.2----------559.2

7 710 563.15 563.0----------563.7

8 820 564.7 572.0----------573.0

9 980 569.6 570.5----------571.8

10 1150 574.91 574.3----------575.4

11 1400 577.9 573.5----------574.4

12 1540 579.5 579.0----------580.0

13 1640 580.7 583.2----------583.2

14 1800 582.7 584.5----------584.5


Quantity Surveying:
Total price=price per unit*unit
1-Fill (3JD/m³):-
Total price =87761*3 = 263,283 JD
2-cut (2JD/m³):-
Total price =61719*2 = 123,438 JD
3-sub base (2JD/m³):-
Total price =0.15*2000*10*2 = 6,000 JD
4-base (3JD/m³):-
Total price =0.1*2000*10*3 = 6,000 JD
5-surface HMA (6JD/m³):-
Total price =0.1*2000*10*3 = 6,000 JD
6-prim coat (1JD/Kg):-
Total price = 30,000 JD