You are on page 1of 30

1

INDEX
Sl.No. Description Page No.
01 Cover Sheet 01
02 Index 02
03 Preface 03
04 Foreword 04
05 Approval Sheet 05
06 Important Note 06
07 Status of Amendments 07
08 Table of Contents 08
3
BHEL – POWER SECTOR 5
IMPORTANT

THIS HEAT TREATMENT MANUAL PROVIDES BROAD BASED GUIDELINES FOR


HEAT TREATMENT WORK AT SITES. HOWEVER, SITES MUST ENSURE
ADHERENCE TO THE PRIMARY DOCUMENTS LIKE CONTRACT DRAWINGS,
ERECTION WELDING SCHEDULE, PLANT / CORPORATE STANDARDS,
WHEREVER SUPPLIED, STATUTORY DOCUMENTS, WELDING PROCEDURE
SPECIFICATIONS, CONTRACTUAL OBLIGATIONS, IF ANY AND SPECIAL
INSTRUCTIONS ISSUED BY RESPECTIVE MANUFACTURING UNITS SPECIFIC TO
THE PROJECT.

BHEL – POWER SECTOR 6


STATUS OF AMENDMENTS

Sl.No. Description Remarks

BHEL – POWER SECTOR 7


TABLE OF CONTENTS

Chapter Description Page No.

1 Heat Treatment Procedure - Boiler and Auxiliaries 8 - 23

Heat Treatment Procedure - Steam Turbine, Turbo-


2 24 - 25
Generator and Auxiliaries

3 General 26

1. Testing of Temperature Indicating Crayons 27

2. Compatibility Test for Heat Treatment System 28 - 29

4 Pre heat & PWHT of Critical Piping with Turbine & Auxiliaries 30

BHEL – POWER SECTOR 8


CHAPTER-1

HEAT TREATMENT PROCEDURE - BOILER AND AUXILIARIES

BHEL – POWER SECTOR 9


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

1.0 PURPOSE:

1.1 This procedure provides information, method and control for Pre-Heat, Post Heat and
Post Weld Heat Treatment (PWHT) of welds at sites.

2.0 DOCUMENT:

2.1 The following documents are referred in preparation of this procedure:

2.1.1 ASME Sec.I

2.1.2 ASME B31.1

2.1.3 Indian Boiler Regulations

2.1.4 AWS D1.1

2.1.5 Welding Manual

2.2 The following are to be referred as Primary Documents:

- Contract drawings
- Erection Welding Schedule or equivalent

- Plant / Corporate standards, where supplied

- Welding procedure specification


- Contractual obligations, if any.

2.2.1 Where parameter for Pre-Heat ,Post Heat and PWHT are not available in the primary
documents, reference may be made to this procedure.

2.2.2 Where such parameters are not contained either in the primary documents or in this
procedure, reference may be made to Manufacturing Units.

3.0 PROCEDURE:

3.1 Pre Heating :

3.1.1 When parts of two different thicknesses are welded together, the preheating requirements
of the thicker shall rule

BHEL – POWER SECTOR 10


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

3.1.2 When parts of two different P numbers are joined together, the material requiring higher
preheat shall govern (please refer Welding Manual for P numbers).

3.1.3 It is recommended to use thermocouples with temperature recorder for recording


pre heating . Where temperature recorder is not possible to use, Preheating shall be
checked using thermal chalk (temperature indicating crayons) prior to start of
welding as well as at frequent intervals during welding
3.1.4 In case of any power interruption during welding, the joint shall be wrapped with dry
thermal insulating blankets to ensure slow and uniform cooling. Requirement of
uninterrupted power supply shall be ensured for materials like P-91, T-91 &
BS EN 10025
3.1.5 Preheating & Post Heating Methods:

3.1.5.1 Preheating & Post Heating shall be applied by any of the methods given below:
a. Electrical resistance heating
b. Induction heating

c. Oxy-acetylene or other gas torches


3.2 Post Weld Heat Treatment (PWHT):

3.2.1 The method shall be by locally heating a circumferential band including the entire weld
and adjacent area of base metal, by induction or electrical resistance heating.
3.2.2 Heat band for PWHT:
3.2.2.1 For Boilers:

a. When heat treating welded joints in components in the boiler proper, width of the
heated circumferential band (W) on either side of the weld, W = 3 times the width
of the widest part of the weld groove but in no case less than twice the width of
weld at reinforcement.
b. When used in post weld heat treatment in sections - W = 3 times the plate
thickness.
c. For nozzle and other welded attachments - W must be wider than the nozzle or
attachment or 3 times the wall thickness.

3.2.2.2 For Piping:

W = 3 times the wall thickness (of thickest part ) on each side from the centre of the
weld. In case of nozzles and attachment welds, the width of the heat band shall extend
beyond the nozzle or the attachment wall on each side by at least twice the higher
thickness and shall extend completely around the header.

BHEL – POWER SECTOR 11


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

3.2.2.3 Other Pressure Vessels:


Heat bandwidth, placement of thermocouple, preheat and PWHT information shall be
obtained from the supplier.
3.3 Condition of Welded Joints:
3.3.1 The weldment shall be free of grease, oil etc. prior to Pre-Heat / PWHT.
3.4 Temperature Measurement for PWHT:
3.4.1 Post weld heat treatment temperature cycle shall be measured and monitored by use
of thermocouples with calibrated recorders.
3.4.2 The periodicity of calibration of the equipment shall be as per calibration procedure.
3.4.3 Where the soaking temperature is found to be lesser than specified, the PWHT cycle
shall be repeated.
3.4.4 In case of interruption during PWHT, the following actions are to be taken, depending
on the stage during which interruption occurred.
a.Interruption during heating cycle:
- The whole operation to be repeated from the beginning.
b.Interruption during soaking:
- The joint can be treated subsequently for the balance left over soaking
period.
c.Interruption during cooling:
- Ensure slow cooling by covering with insulation to a minimum width of 1.5 times
the outer diameter applied equally about the centre line of weld, till the
temperature reaches around 300°C.
3.5 Thermocouple (t/c) Fixing:

3.5.1 Thermocouples shall be used for recording Post Weld Heat Treatment temperatures.

3.5.1.1 Following are guidelines regarding number and placement of thermocouples:

3.5.1.2 Minimum of two thermocouples per weld joint.

3.5.1.3 Thermocouples located 180° apart.

3.5.1.4 Thermocouples located at top and bottom of weld joint.

3.5.1.5 Thermocouples located at a distance of approximately 1.5 times of the wall thickness
about the centre line of weld.
3.5.1.6 One point of the 6/12 points recorder shall be used for recording ambient temperature.

BHEL – POWER SECTOR 12


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

3.5.2 The following guidelines may be used for attaching thermocouples to job:

a. For capacitor discharge method: Thermocouple elements should be attached


within 6 mm of each other.
b. For other type of t/c: Insert the elements in a SS tube of internal diameter
approximately 6 mm. Apply force on tube and crimp it. Place this t/c and weld the
crimped button to the pipe in area of interest. Do not weld the elements.
c. Insulate the t/c leads suitably and protect t/c ends from direct radiation from
heating elements.
3.5.3 For Bunched Tubes:

3.5.3.1 Where a bunch of closely placed tube welds (e.g. Super Heater / Reheater Coils)
require to be Post Weld Heat Treated, the same shall be grouped together as if they
form a single component.

3.5.3.2 In such cases attachment of a minimum of three thermocouples, two at the end tubes
and one at the middle is recommended.

3.6 Soaking Time:

3.6.1 Wherever not specified the soaking time shall be as per Tables I, II and III.

3.6.2 The following guidelines shall be used to determine the thickness and subsequent
selection of the soaking time of PWHT:

a. For butt welds, the thickness shall be the thickness of the material at the weld.
For bar stock, the thickness shall be the diameter.
b. For fillet welds, the thickness shall be the throat thickness.
c. For partial penetration branch welds, the thickness shall be the depth of the
groove prior to welding.
d. For repairs, the thickness shall be the depth of the groove as prepared for repair
welding.
e. For combination of different welds in a component, the maximum thickness in the
definitions given above shall govern.

3.6.3 Soaking time is to be reckoned from the time temperature of the joint crosses the
recommended lower temperature of the cycle, to the time it comes down below the
same recommended lower temperature of the cycle.

3.7 Heating and Cooling Rates:

3.7.1 Wherever not specified, the heating rate above 300°C and cooling rate after soaking
upto 300°C shall be as follows: This is applicable for all materials.

BHEL – POWER SECTOR 13


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

Thickness of Material Maximum Heating Rate Above Maximum Cooling


300°C
Rate Upto 300°C

25 mm 220°C/hour 220°C/hour

> 25  50 mm 110°C/hour 110°C/hour

> 50  75 mm 75°C/hour 75°C/hour

> 75mm 55°C/hour 55°C/hour *

* For structural - 65°C/ hour (Max.)


3.8 Temperature Records:
3.8.1 All the heat treatment cycles may be controlled within ±10°C around the
midpoint of the recommended range of temperature for the material.

4.0 POST WELD HEAT TREATMENT (PWHT) JOB CARD:

4.1 Prior to start of PWHT operations, a job card may be prepared including details of
weld reference, soaking time, soaking temperature, maximum rates of heating and
cooling, temperature recorder details, date of PWHT as per sample format.

4.2 On completion of PWHT the actual parameters shall be recorded on the job card.

4.3 A chart number shall be given to each chart.

5.0 HEAT TREATMENT OF P-91 WELDS :

5.1 Please refer Welding Manual vide document No. PSQ-WDM-COM for heat treatment of
welds in P-91 materials.

5.2 HEAT TREATMENT OF T-91 WELDS:

5.3 Please refer Welding Manual vide document No. PSQ-WDM-COM for heat treatment of
welds in T-91 materials

BHEL – POWER SECTOR 14


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

5.4 HEAT TREATMENT OPERATOR REQUIREMENTS:

The operator for the Heat Treatment shall be a qualified Electrician and should be
conversant in the operation & maintenance of heat treatment machines & Process. He
should be trained properly by the concerned Welding / Electrical Engineer in order to
handle/ maintain the machines / process without any trouble / problem.

6.0 LIST OF TABLES:

Table-I Weld preheat and PWHT for tubes and pipes outside diameter 102 mm.

Table-II Weld preheat and PWHT for Boiler Header welds.

Table-III Weld preheat and PWHT for pipes outside diameter > 102 mm.

Table-IV P Number and Group Number for Base Materials.

Table-V Pre-heat and PWHT for Non-Pressure Parts including Structural.

Table-VI Preheat for Flame Cutting.

7.0 RECORDS :

7.1 Pertinent Records like Job card, PWHT Charts, shall be maintained.

BHEL – POWER SECTOR 15


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

POST WELD HEAT TREATMENT (PWHT) JOB CARD

Project : ____________________

Card No. : ____________________ Date : ________________________


Unit No. : _____________________ Package : _____________________
Description : ___________________ Temp. Recorder Details :
Weld Reference : _______________ 1. Make : _____________________
Material Spec. : ________________ 2. Type : _____________________
Size : Dia __________________ mm 3. Sl.No.: _____________________
Thick (t) ______________ mm 4. Chart speed: ________ mm / hour
NDE Cleared on :_______________ 5. Calibration Due on : __________
Report No. : _______________

Thermocouple Locations :

Minimum 2
d = 1.5 x t from weld centre
Heating Band = 6 x t
Insulation Band = 12 x t

Date of PWHT _________________ Chart No. : _____________________


Start Time : ___________________ End Time : _____________________

Required Actual

Rate of Heating (Max) °C/h

Soaking Temperature °C

Soaking Time (Minutes)


Rate of cooling (Max) C

Ambient temperature recorded on the PWHT Chart: ____________

Contractor BHEL

Results : Accepted / Not Accepted Released for further processing

BHEL – POWER SECTOR 16


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

TABLE - I
WELD PRE HEAT AND PWHT FOR TUBES & PIPES
OUTSIDE DIAMETER 102 mm
(Applicable For Butt Welds And Socket Welds)

P. No. of Thickness
Preheat °C PWHT °C
Material (mm)

P1 Gr 1& SA 106
 19 Nil Nil
Gr C (Note 1)

9 Nil Nil
P1 Gr 2
>9 Nil 620 - 650

 13 Nil Nil
P3 Gr 1
> 13 80 (Note 2) 620 - 650

 13 150 Nil (Note 3)


P4 Gr 1
> 13 150 640 - 670

8 150 Nil (Note 3)


P5 A Gr 1
>8 150 680 -710

P15 E Gr 1
All 220 750 – 770
(Note 4)

P8 All Nil Nil

12 x 1M All 220 730 - 760

Note 1 : For SA 106 Gr .C with less than 0.25 % carbon content .

Note 2 : Pre-heating is necessary for t >16mm.

Note 3 : Less than 0.15 % carbon content .

Note 4 : 9 Cr 1 Mo ¼ V Steel ( P-91, T-91 )

BHEL – POWER SECTOR 17


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1
TABLE - II
WELD PREHEAT AND PWHT FOR BOILER HEADER WELDS
(NOTE - 3)
(Applicable For Welding of Header to Header Joints)

P. No. of Thickness Preheat Post Heating PWHT


Header Material (mm) °C °C °C
t  19 Nil Nil Nil
P1Gr 1 19 < t 5 Nil Nil 595 - 625
25 < t  75 100 Nil 595 - 625
t > 75 150 Nil 595 - 625
t 9 Nil Nil 620 – 650
150
19 < t 5 Nil 620 - 650
P1Gr 2 for 2 hours
150
25 < t  75 100 620 - 650
for 2 hours
t > 75 150 150
620 - 650
for 2 hours
P4 Gr 1 All 150 Nil 640 - 670

P5 A (Note 1) All 150 250 for 2 hours 680 - 710

12 x 1M  All 220 Nil 710-740


Note :

1. All P5A headers shall be inter stage heat treated at 700 - 750°C for 30 minutes
soaking prior to any cold straightening operation. In lieu of this, the straightening
can be done after final PWHT. Any P5A Header with weld thickness above
50mm requires inter stage H.T. at 700-750°C for 30 minutes soaking minimum
(max. shall be limited to 2.5 minutes/mm of thickness).

2. Soaking for PWHT shall be at the rate of 1 hour per 25 mm of thickest weld (but
not less than 30 minutes for carbon steel and 1 hour for alloy steel). Soaking
time for 12 x 1 M header material shall be 4 minutes per mm of the applicable
thickness with a minimum of 180 minutes.
3. Seal welding of Hand Hole Plates, Radiographic plugs and Screws can be
carried out after final PWHT, provided the preheat is carried out as per the
table.
4. For P number and Group number refer Table - IV.

BHEL – POWER SECTOR 18


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

TABLE - III
WELD PREHEAT AND PWHT FOR PIPES
OUTSIDE DIAMETER >102 mm
BUTT WELDS Stub and Attachment welds Post
Note 1 & 2 heat
P No. of Thickness
Throat  19 mm Throat > 19 mm C
Material (mm) Preheat PWHT
C C Preheat PWHT Preheat PWHT (Note
C C C C 3)
595 -
 19 Nil Nil Nil Nil Nil Nil
625

P1 Gr 1 595 - 595 -
>1925 Nil Nil Nil Nil Nil
& SA106 Gr C 625 625
595 - 595 -
>2575 150 150 Nil 150 Nil
625 625
595 - 595- 595 -
>75 150 150 150 Nil
625 625 625
620 -
9 Nil Nil Nil Nil Nil Nil
650
P1 Gr 2
620 - 620- 620 -
& SA 106 Gr C >919 Nil Nil Nil Nil
650 650 650
150
620- 620- 620 -
>19 150 150 150 for 2
650 650 650
hrs
640- 640- 640-
All 150 150 150 Nil
P4 Gr 1 670 670 670

Pipes 250
680 - 680- 680-
150 150 150 for 2
Castings & 710 710 710
P5 A hrs
Forgings

280
750- 750- 750-
P15 E Gr1 All 220 220 220 for 2
770 770 770
hrs

280
P15 E Gr1 730- 730- 730-
All 220 220 220 for 2
+ 760 760 760
hrs
P5 A

Note :

1. Irrespective of the stub or attachment materials, the PWHT cycle shall be governed by the pipe
material.

2. Throat shall be specified in the drawing. Wherever flanges are welded to pipes combined throat
shall be taken into consideration.

3. Post heating shall be done immediately after welding.

BHEL – POWER SECTOR 19


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

4. For butt welds of different P group combinations, PWHT temp. may be as follows:

P1 + P3 - 620 to 650°C

P1 + P4 - 640 to 670°C

P4 + P5A - 680 to 710°C

(For other P Group combinations, refer to Engineering)

5. a. For P1 & P3 materials soaking time shall be 1 hour per 25mm up to 50mm
thickness and 2 hours + 15 minutes for each 25mm thickness over 50mm.
b. For P4 & P5 materials, soaking time shall be 1 hour per 25mm up to 125mm
thickness and 5 hours + 15 minutes for each 25mm thickness over 125mm.

6. For P number and Group number refer Table IV.

BHEL – POWER SECTOR 20


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

TABLE - IV
P NUMBER AND GROUP NUMBER FOR BASE MATERIALS

Grou
P.No Common Name Tubes Pipes Plates Forgings Castings Fittings
p No.
SA192 SA106GRB SA36 SA266CL SA216WC SA234

SA210GRA1 SA515GR55 1 A
SA352LC WPB
Carbon
Steels SA515GR60 A
SA352LC
P1 1 SA515GR65 B

SA516GR55

SA516GR60

SA516GR65
SA210GRC SA106GRC SA515GR70 SA266CL SA216WC SA105
P1 2 Carbon Steels SA516GR70 2 B
SA216WC SA234
SA299 C
SA352LC WPC

SA209T1 SA335P1 C
SA217WC
Carbon-Moly
P3 1
Steels 1
½Cr½Mo Steels
P3 1 SA213T2 SA335P2 SA387GR2
1Cr½Mo/
SA213T12/ SA335P12 SA387GR12 SA182F1 SA217WC SA234
P4 1 1¼Cr½Mo Steels
SA213T11 SA335P11 2
SA387GR11 SA182F1 6 WP12
SA234
2¼Cr1Mo Steels 1 WP11
P5A 1 SA213T22 SA335P22 SA387GR22 SA182F2 SA217WC SA234
9Cr1MoV Steels 2 9 WP22
P15 SA213T91 SA335P91 SA387GR91 SA182F91 SA234
2
E WP91
Gr 1 18Cr-8Ni Steels
SA213TP304 SA376TP304 SA240TP304 SA182F3 SA351CF SA403
SA213TP304 SA376TP304H SA240TP321 04
SA182F3 3
SA351CF
H
SA213TP347 SA376TP321 SA240TP347 21
SA182F3 8
SA351CF
P8 1
SA213TP347 SA376TP347 47
SA336F3 3M
SA351CF
H
SA213TP321 SA376TP347H 04
SA336F3 8M
SA351CF
21
SA336F3 10
SA351CF
25Cr-20Ni Steel
P8 2 SA240TP310 47
SA182F310 10M
SA351CK
(Type 310)
20

Note : IS1239 & API 5L GR B Pipes, IS2062 Plates may be treated as P No.1 Gr No.1 material.

BHEL – POWER SECTOR 21


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

TABLE - V
PREHEAT AND PWHT FOR NON PRESSURE PARTS INCLUDING STRUCTURALS

P.No. of Gas Cutting Welding


Material /
Material Thickness Preheat Thickness Preheat PWHT
Specification (mm) °C (mm) °C °C
595-625
 25 Nil  38 Nil
a)All butt welds > 50
P1 / IS 2062 > 38  63 100 mm thick
> 25 100 > 63 150 b)Any welds to a
tension member
IS 8500 –
Fe 540 620- 650 ( Soaking
– –  150 time 2.5 Mts. Per mm.
( Ceiling Minimum 120 Mins)
Girder )

BS EN 620 – 650 ( Soaking


10025 Gr time 2.5 Mts. Per mm.
420 N - -  220
( Ceiling Minimum 120 Mins. )
Girder )
640-670
a)All butt welds in
tension member
P4 Gr 1 All 150 All 150
b)All fabricated com-
ponents > 16mm
thick (Note 3)
680-710
(Note 3)
P5 A All 150 All 150 All welds
(Note 4)

NOTE :
1. All gas cut edges may be chipped off, ground or machined to remove the HAZ with
3mm minimum removal.
2. Clip angles above 10mm, used for beam connections, which are sheared to length,
shall require heat treatment.
3. All fabricated structural components of P-4 material, with any member above
16mm thickness, the entire assembly shall be post weld heat treated.
4. All welds of P5 A material shall be post heated at 250°C for 2 hours immediately
following welding.
5. Soaking time shall be as below :
a. P1 and P3 materials one hour per 25mm up to 50mm thickness and
2 hours + 15 minutes for each 25mm thickness over 50mm.
b. P4 and P5 materials one hour per 25mm up to 125mm thickness and
BHEL – POWER SECTOR
5 hours 22 thickness over 125mm.
+ 15 minutes for each 25mm
HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -1

TABLE - VI

PREHEAT FOR FLAME CUTTING

P.No. of Material Thickness (mm) Preheat °C


P1 Gr 1 < 25 Nil
(Note 1)  25 100
P1 Gr 2
All 150
(Note 1)
P3
All 150
(Note 1)
P4
All 150
(Note 1)
P5 A
All 150
(Note 2)

NOTE :
1. For P1, P3 and P4 materials, when the flame cut edge will be machined
after cutting and when no forming operation is required after cutting, no
preheat is required for flame cutting.

2. P5 A materials, except when the part is scheduled for hot forming, shall
be inter stage heat treated at 680-710°C for 30 minutes minimum after
flame cutting and prior to any welding. Subsequent to this heat
treatment, a minimum 3 mm of the gas cut edge shall be removed by
machining / grinding.

BHEL – POWER SECTOR 23


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -2

CHAPTER -2

HEAT TREATMENT PROCEDURE -

STEAM TURBINE, TURBO-GENERATOR AND AUXILIARIES

BHEL - POWER SECTOR 24


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -2

2. HEAT TREATMENT PROCEDURE -

STEAM TURBINE, TURBO-GENERATOR AND AUXILIARIES

1 Procedure for Post Weld Heat Please refer Plant Standard, HEEP,
treatment of Pressure Vessel as Haridwar - HW 0980814
per ASME code Section VIII,
Div.I

2 For other Components Please refer Heat treatment Procedure-


Boiler and Auxiliaries of Chapter-I

BHEL – POWER SECTOR 25


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -3

CHAPTER - 3

GENERAL

BHEL - POWER SECTOR 26


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -3

3. GENERAL

1. TESTING OF TEMPERATURE INDICATING CRAYONS

1.0 SCOPE :

1.1 This procedure details the method of batch testing of Temperature indicating Crayons
(Thermal chalks).

2.0 PROCEDURE :

2.1 Setup:

2.1.1 Rig a test heating arrangement including a test pipe/plate heating arrangements with
controls and a calibrated temperature recorder/thermometer.
2.2 Heat the test pipe / plate (specimen) to a temperature 10 lower than the rated
temperature of the thermal chalk in study, monitoring the temperature through
thermometer/recorder.
2.3 Stroke the thermal chalk as close to the sensing point on the specimen.
2.4 Raise the temperature of the specimen gradually up to 10% higher than the rated
temperature of the thermal chalk in study, stroking the thermal chalk on the specimen
during this period.
2.4.1 When the thermal chalk changes to the specified colour or melts (depending on the
type), within ±5 of the rated temperature, the thermal chalk is acceptable.
2.5 Consistent results for 2% of any brand and temperature will qualify the brand for the
rated temperature.
2.6 Where thermal chalks are accepted brand wise, they shall undergo this test at least
once a year.

3.0 RETESTS :

3.1 Any failure in the 2% sample chosen, will call for additional 4% for qualification of the
brand for the rated temperature.
3.2 Where retest results in further non-acceptance, the brand shall stand rejected for the
particular temperature.

4.0 RECORDS :
4.1 Records of testing and brands accepted/rejected including details of calibrated
devices used in the setup shall be maintained.

BHEL - POWER SECTOR 27


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -3

2. COMPATIBILITY TEST FOR HEAT TREATMENT SYSTEM

1.0 SCOPE :

1.1 This procedure provides for checking the compatibility and accuracy of
thermocouples, compensating cables, temperature recorder, connected in Heat
Treatment (HT) operations at sites.

2.0 HT TEST SYSTEM :

2.1 The thermocouple (type k-chromal-Alumel is generally used at sites) attached to a test
specimen with heating arrangements and controls, compensating cables, a calibrated
temperature recorder rigged together for the test HT system.
2.2 A calibrated (accuracy ±0.5%) direct-reading thermometer (like a digital thermometer
with sensor) is used for verification.

2.0 PROCEDURE :

3.1 Attach the thermocouple as detailed in Chapter I of this manual.


3.2 Raise the temperature of the test specimen to around 200° C and maintain the same.
3.3 Place the sensor of the direct reading thermometer as close to the thermocouple
junction as possible.
3.4 Wait till the temperature is stabilized.
3.5 Note reading of the thermometer and that of the temperature recorder.
3.6 Repeat steps 3.2 to 3.5 for test specimen temperatures of 400° C and 600° C
3.7 Where the temperature read by the temperature recorder is within ±10° C with
respect to the thermometer, the HT system is compatible.
3.7.1 Where the results are not within the tolerance specified above, further tests are to be
repeated to identify the fault either in thermocouple or compensating cable or both.
3.8 Adequate insulation of thermocouple, sensor from direct radiation of heat elements
shall be ensured as a precaution throughout the test.
3.9 This compatibility is recommended for each of the thermocouple available for use; this
procedure validates the thermocouple also.

4.0 RECORDS :

4.1 Records pertaining to the test shall be prepared and maintained.

BHEL - POWER SECTOR 28


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -3

Compatibility Test for HT System

Site: Report No.

Date :

Details Temperature Recorder Thermometer

Make:

Model:

Sl. No.:

Range:

Test Results

Temperature Reading °C
Sl. No. t/c No. C/C. No. Difference °C Results*
Recorder Thermometer

Record results (Accepted/Rejected) where rejected, record the faulty component as


required by 3.7.1

Witnessed by

(Name & Signature)

BHEL - POWER SECTOR 29


HEAT TREATMENT MANUAL FOR POWER SECTOR
CHAPTER -3

Pre heat & PWHT of Critical Piping with Turbine & Auxiliaries

Sl Material Material OD Thic Type Pre PWHT Holding


no Spec 1 Spec 2 knes of heat Temp. time
s Weld Deg. C Deg. C minimum
(minutes)
1 GS 17 SA335 ≥110 >30 G 200 TO 690+10 240
CrMoV 511 P91 300 (Notes)
2 G17 CrMo 9 SA335 ≥110 >30 G 200 TO 690+10 240
10 P22 300 (Notes)
3 21 Cr Mo Ni SA335 ≥110 >30 G 200 TO 690+10 240
V47 P22 300 (Notes)

Notes :- Rate of heating 50 Deg. C per hour above 300 °C


Rate of cooling 30 Deg. C per hour up to 300 °C
This is as per BHEL HEEP - Hardwar recommendation.

***********

BHEL - POWER SECTOR 30

You might also like