Project : ALVEO SALES OFFICE

Location : FILINVEST, MUNTINLUPA CITY

Subject : COST PROPOSAL

NO. DESCRIPTION QUANTITY UNIT

1 GENERAL REQUIREMENTS
PERMITS AND PROFESSIONAL FEES LEGWORK
subtotal
2 MOBILIZATION/DEMOBILIZATION
subtotal
3 WALLS AND PARTITIONS
3.1 GYPSUM BOARD (Double Wall Cladding)
Lounge and Reception 29.75 m²
Workstation 84.66 m²
Conference Room 20.78 m²
Sales Director's Office 19.34 m²
3.2 4" CHB WALL
Pantry 14.84 m²
Toilet 12.19 m²
subtotal
4 FLOORING AND FLOORING SURFACE PREPARATION
4.1 CARPET TILES FOR SLAB
Lounge and Reception 17.55 m²
Workstation 185.90 m²
Conference Room 12.84 m²
Sales Director's Office 6.72 m²
4.2 CERAMIC FLOOR TILES (600x600mm)
Pantry 7.84 m²
Toilet 2.72 m²
subtotal
5 PLUMBING WORKS
5.1 ROUGHING-INS 1 lot
5.2 WATER CLOSET
Toilet 1 set
5.3 LAVATORY
Toilet 1 set
5.4 URINAL
Unit 3A 1 set
5.5 WATER PROOFING
Toilet 2.72 m²
5.6 GOOSENECK FAUCET 1 set
5.7 KITCHEN SINK 1 set
subtotal
6 WALL FINISHES
6.1 SATIN PAINT FINISH (White)
Lounge and Reception 45.74 m²
Workstation 217.28 m²
Conference Room 34.80 m²
Sales Director's Office 26.36 m²
Pantry 30.26 m²
Toilet 9.38 m²
6.2 CERAMIC WALL TILES
Toilet 6.96 m²
subtotal
7 DOORS AND GLASS WINDOWS
7.1 12mm THK TEMPERED CLEAR W/ TOP AND BOTTOM PATCH
FITTINGS
Entrance Lobby 1 set
SINGLE LEAF - SINGLE SWING HOLLOW CORE DOOR WITH
7.2 GLASS PANEL (800x2100mm)
Conference Room 1 set
Sales Director's Office 1 set
SINGLE LEAF - SINGLE SWING HOLLOW CORE DOOR
7.3 (800x2100mm)
Toilet 1 set
SINGLE LEAF - SINGLE SWING HOLLOW CORE DOOR
7.4 (700X2100mm)
Pantry 1 set
subtotal
8 ELECTRICAL WORKS
8.1 ROUGHING-INS 1 lot
8.2 DUPLEX CONVINIENCE OUTLET 3 PRONG WIDE SERIES
Lounge and Reception 3 pcs.
Conference Room 3 pcs.
Sales Director's Office 3 pcs.
Workstation 85 pcs.
Pantry 3 pcs.
8.3 LED PINLIGHT - 9W w/ HOUSING
Lounge and Reception 7 pcs.
Conference Room 6 pcs.
Sales Director's Office 4 pcs.
Toilet 1 pc.
8.4 LIGHT SWITCHES AND FIXTURES
1 - Gang Light Switch 2 pcs.
2 - Gang Light Switch 2 pcs.
3 - Gang Light Switch 1 pcs.
2 - Way Light Switch 2 pcs.
8.5 LED LINEAR LIGHTS
Workstation 14 pcs.
subtotal
9 MECHANICAL DUCTING AND EXHAUST WORKS lot
subtotal
10 SPECIALITY WORKS
10.1 CABINET
Pantry 2.72 m²
10.2 JET BLACK COUNTERTOP
Pantry 1.92 m²
subtotal
11 GRAPHICOTE GLASS PANELS 5.46 m²
subtotal
12 OFFICE SYSTEM AND FURNITURE osm
subtotal
13 OTHERS
SECURITY BOND 1 lot
subtotal
MATERIAL LABOR
MATERIAL Unit Rate Total Amount
UNIT COST UNIT COST LABOR COST
COST

154.53

27.03

223.01

10.56
363.82