REFERENCE DATA

ENTERPRISE 1 ENTERPRISE 2
BUILDING NAME
53,000.00 48,000.00
CFA

BUILDING 1,752,975,000.00 1,587,600,000.00

ELECTRICAL SERVICES 262,350,000.00 237,600,000.00

MECHANICAL SERVICES 238,500,000.00 216,000,000.00

FIRE SERVICES 51,675,000.00 46,800,000.00

LIFT/ESCALATOR 119,250,000.00 108,000,000.00

PLUMBING SERVICES 71,550,000.00 64,800,000.00


编制 bernard
# Includes raised floor and ceiling to tenanted areas but excludes office carpets (normally under tenant's fit-out)
Rates are exclusive of contingencies Offices of average standard are built to the following provisions:
(i) Curtain wall/window wall facade (ii) Tenant are with screeded floor, painted wall and ceiling
Rates exclude VAT and contingencies.
Transformer, included in Electrical Services, Generally without A/C

M & E MAJOR PLANT COSTS FOR THE PHILIPPINES unit Cost Php
1. Water cooled electric chiller per TR 16,000 – 28,000
2. Air-cooled electric chillers per TR 25,000 – 35,000
3. Cooling Towers; induced draft per GPM 2,300 – 3,000
4. Air Handling Units (AHU) per TR 13,000 – 19,000
5. Packaged Water-Cooled units (PWCU) per TR 18,000 – 27,000
6. Fire Pumps; electric motor driven per HP 17,000 – 22,000
7. Fire Pumps; diesel engine driven per HP 22,000 – 26,000
8. Standby generator sets per KVA 5,500 – 9,500
9. Power transformers, with built-in per KVA 1,600 – 6,000
primary protections; padmount
10. Power transformers, with primary per KVA 1,300 – 4,400
protection; silicon oil filled
11. Power transformers, with primary per KVA 2,000 – 5,000
protection cast resin
12. Sewage Treatment Plant, per m3/day 20,000 – 30,000
Sequencing Batch Reactor including civil works
编制 bernard
2015
TOTAL