Professional Documents
Culture Documents
Book - Sustainable Urban Districts - 2015 Global Review PDF
Book - Sustainable Urban Districts - 2015 Global Review PDF
urban districts
2015 global review
Strategies to accelerate
sustainable urban development
May, 2015
FOREWORD
This project arose from the joint desire of WWF and To shape this report, a group of experienced and cred- Above all, we hope that this report will help inspire
Lafarge to contribute original research on the topic of ible stakeholders from across the construction sec- those within the construction sector to introduce more
sustainable construction. tor were engaged. Initially, it was intended for these sustainable technologies and ways of working – and
contributors to help guide the research and ensure to support those now creating the next generation of
Over the last 10 years, it has become increasingly ap- that the findings and recommendations were relevant sustainable district developments.
parent that sustainability gains can be derived from to their sector. However, each contributor has gone
improving systems, in addition to improvements well beyond this remit, developing and implementing Laila Petrie – Manager, Corporate Relations at WWF International
that can be made by individual actors or buildings. strategies to take forward these findings into their own Vincent Mages – Main Partnership Liaison Lafarge
This means two things: that sustainable construction industries and organisations. Thanks go to all those
is best understood from the perspective of cities or listed below for their valuable input, alongside our
districts; and the practices of a company or sector can delivery partners Except Integrated Sustainability.
be improved by understanding their role within the
interactions of a whole supply chain. All eleven projects that participated in our research
have shared their experiences and lessons in an open
This thinking inspired the form of this report. We and insightful way. Their experiences have been
analysed the experiences and approaches of existing, invaluable for building the recommendations in this re-
more sustainable urban districts, and focussed on the port. We hope that by grounding our research in these
interactions between the supply chain players – to credible and diverse case studies, our findings will be
draw lessons for the whole sector using a systems- practical, widely applicable and relevant to today’s
based lens. sustainable construction challenges.
François Baillon FIDIC Soraya Smaoun UNEP The opinion expressed in this report represents the culmination of the
steering group input and does not necessarily represent the opinion of
Jean Felix Chairman FIDIC Sust. Dev. Committee Curt Garrigan UNEP each individual organization.
Vallishree Murthy British Glass Jean-Paul Jeanrenaud WWF International
Clare Broadbent World Steel Carina Borgstrom Hansson WWF Switzerland
Phillippe Fonta WBCSD
executive summary
What strategies for the construction how is sustainable urban development strategies for sustainable development
sector speed up sustainable urban different?
development? Mind-shift: build to be resilient
Sustainable urban development is significantly more Sustainable development focuses on the full lifespan
ambitious than traditional development. It requires more of urban districts, from conception to demolition or
To answer this question we examined eleven projects and higher targets, requiring a mind shift beyond the replacement and beyond. This changes the mind set, role,
around the world with diverse ambitions and design, construction and marketing of property, towards and involvement of contributors and beneficiaries. To
sustainability targets using a systemic and holistic creating resilient, socially just, and environmentally activate this, resilient neighborhoods require new strategies
perspective. We extracted the success and failure responsible communities. This involves all stakeholders in for the following:
factors, and uncovered strategies that accelerate the construction supply chain.
sustainable development both on a project level and for › Ambition setting: Success indicators for sustainable
improvements across the building sector. holistic design and 360 degree scope urban development go beyond the specifications of
Sustainable living means living in harmony with natural buildings and the ability to sell property. Above all,
Sustainability targets influence the practice of urban resources as well as living a just, healthy, and happy life; sustainable urban development targets use-phase
development as well as the roles of contributors and a broader scope than a usual construction trajectory. This performance of the neighborhood and its ability
beneficiaries. The eleven studied projects demonstrate requires dealing with a wide range of issues such as CO2 to further improve over time. Using performance-
successful approaches that increased their sustainability emissions, energy use, renewable energy and material based goals helps to steer towards actual improved
performance. Implementing the lessons learned in sourcing. It also deals with aspects such as conservation functioning of a neighborhood throughout its
these projects will significantly speed up sustainable of ecosystems and species, contributions to local culture, lifetime.
development projects around the world. In addition, we’ve and catering to the needs of healthy and happy living.
found strategies to achieve improved performance in the › Involvement of occupants: Urban development
New finance and business models are essential to create induces and enables lifestyle change of occupants.
construction industry globally. incentives for communities to function well and meet all To achieve sustainability goals in the use-phase,
targets simultaneously. Taking all sustainability aspects into the support and active participation of occupants is
account simultaneously is a big challenge. essential. Focusing on and involving end-users from
vision to execution helps to achieve this.
Higher performance throughout
Most building standards today do not require the market › Team formation: Selecting a skilled and motivated
to deliver truly sustainable neighborhoods. Raising the design & development team is a key success factor
ambition to sustainable development is often considered to to meet both sustainability targets and local needs.
lead to less competitive real-estate prices, but case studies Successful teams include all disciplines and skills-
show that this is not true. They do show that reaching higher sets to deal with the full spectrum of sustainability
performance targets, including financial targets, requires from the start. In addition, they consist of involved
new strategies, commitment and perseverance. and intrinsically motivated professionals.
|5
› Business models: Linking reward systems to the Road map for Sector change › Responsible financing: The financial sector can
actual (not projected) financial performance of the Besides the above mentioned strategies to increase stimulate true sustainable urban development
neighborhood improves sustainability performance performance of development projects, sector wide by accrediting design approaches and business
in the use-phase. Business models that involve programs speed up sustainable development worldwide models that connect reward systems to the actual
full life-cycle incentives help to meet longer-term with the following strategies: performance of neighborhoods.
operational goals. The larger scope and demands
require financing of up-front process costs. These › Disseminate technologies and innovation:
› Fostering value awareness: There is a common belief Exchanging, connecting, and combining local and
can be covered by incentive structures throughout a
that higher sustainability targets will lead to lower global knowledge proved important for all studied
project’s life-cycle, and the project's value increase
financial gains. There are many examples that prove projects. There is no single construction method that
through improved performance and desirability.
that the opposite is true. Showcasing examples of performs best in all contexts and climates. Creating
› Work culture: All involved parties from the design successful business cases convinces key players awareness about adapting technologies to local
to the use (and end-of-life) phases contribute to the that sustainable development leads to prosperous contexts helps to achieve better implementation.
performance of neighborhoods. A cooperative setting business. They also help communicate how suppliers In many regions construction companies rely on
that encourages guidance and learning is essential in and project developers can best benefit from known and traditional construction methods, because
this multi-disciplinary and user-centered approach. sustainable development. experience with innovative methods is absent and
Also, exchanging and incorporating ideas from other barriers to introduce them locally is high. Lowering
› Cross-sector innovation: Cooperation between
parties and disciplines is critical to realize all the these barriers to new technology implementation
project developers, suppliers and financial
development goals simultaneously. is a major challenge to speed up sustainable
institutions enables the sector to link neighborhood
development in upcoming markets. Tools that help
performance to finance, risk, and reward systems. By
this are online learning platforms, easier to assemble
Surplus value making suppliers responsible for the performance
construction techniques, and remote guidance
A recurring pattern in successful sustainable projects is of their solutions in the use-phase, they are
systems (e.g. via mobile devices).
the pride and sense of purpose people have in their work. incentivized to realize long-term performance goals.
Adding social and other regional values proved beneficial This guarantees that operational goals will be met.
Substantiation of conclusions
for the studied projects in many ways. Apart from a New business models prove that this changing role of
motivated work force, advocacy for change and a drive to suppliers in the use-phase is possible and works. Part 1 of this report summarizes insights and strategies for
provide beneficial spillover effects make neighborhoods project developers, suppliers, and sector organizations to
attractive and contributes to their image and marketing. › Performance monitoring: As mentioned, the real speed up sustainable urban development.
People’s increased involvement in projects leads to stronger measures of success are related to the actual
commitment and active participation by third parties. Last sustainability performance of urban districts. To Part 2 of this report documents -in detail- how the studied
but not least sustainable development generates increased strengthen incentives towards neighborhoods projects successfully apply the presented strategies. These
political support due to its positive regional impacts, which that function well on all sustainability criteria, projects serve as inspiration and proof that the suggested
help speed up projects. development and implementation of performance strategies lead to significantly improved performance levels.
monitoring in the use-phase are of great importance.
contents
This report shows how embedding sustainability part 1 - Strategic Agenda part 2 - Research
goals changes urban development and offers strate-
gies and insights for companies and sector organiza-
tions to accelerate sustainable development. The
content presented is based on research of eleven
notable sustainable urban districts from around the Part 1 presents the main insights and conclusions Part 2 shows the lessons learned for each of the
world. This allowed us to base our recommendations gathered from the eleven projects, and present the projects in practice, including its process and systems
on real world experiences in urban development uncovered strategies. maps, their goals, and strategies.
trajectories.
Chapter 1 explains the central research question, Chapter 1 explains the method used to map the devel-
our view on sustainability, scope of research, and the opment processes in a visual model. This approach en-
method used. ables the reader to quickly read and extract important
information from the process maps used in chapter 2.
Chapter 2 addresses the difference between traditional
urban development and sustainable urban develop- Chapter 2 gives an overview from origination to
ment, and how practices change when sustainability realization of the eleven sustainable urban districts.
becomes an ambition. For each example the development steps, stakeholder
involvement and key impact decisions on the district’s
Chapter 3 presents innovative strategies for higher goals are presented.
performance levels. Urban development projects will
significantly improve when parties adapt these strate- Chapter 3 summarizes the key ‘lessons learned’ that
gies derived from the case studies. helped improve the impact of stakeholders and suppli-
Location of the 11 research projects.
ers on the sustainability performance of the districts.
Chapter 4 suggests strategies for sector organizations
and governments to accelerate change. Innovation and
project speed will be improved with these strategies,
if implemented sector wide in the construction sector
and other sectors, such as in finance and governance.
3.5 Enabling adaptation and flexibility 28 2.6 sonoma mountain village, USA 76
1. INTRODUCTION
›› A panorama of Lyon Confluence, a sustaianble district developed
from the old industrial area between the Rhone and Saone rivers
in Lyon, France.
Research method
district Selection
1 The districts set high and ambitious sustainability • Hammarby Sjöstad, Sweden
targets, also in comparison to other projects in Greenwich Millenium Village, UK • Eva Lanxmeer, the Netherlands
their region. • Lyon Confluence, France
2 A broad set of sustainability goals for the project
• Dockside Green, Canada
are formulated. • Jinshan, China
3 The projects have gained notoriety for their • Sonoma Mountain Village, USA • Masdar City, UAE
pioneering approach toward sustainability.
4 Diversity in geographical location to represent a • Karaikal Pondicherry, India
good mix of regions from around the world.
5 Diversity of large and small scale developments, as
well as bottom up and top down initiatives.
Materials
› Energy & Materials
Energy & › Species & Ecosystems
Materials › Culture & Economy
Energy
› Health & Happiness
Above: SiD's ELSIA diagram In part 2 of this report the goals and the develop-
ment process of the studied projects are described.
The goals are mapped in accordance with the ELSIA
framework. On a time line the key process steps are
presented that enabled the realization of the goals.
Holistic design and 360 degree scope 1. Mixed-use neighborhoods 2. Building resilience
Urban districts with true sustainability ambitions All neighborhoods can be identified as mixed-use. From a traditional business perspective, a project is
consider not just resource use and the environment, Mixed-use neighborhoods offer opportunities for local successful if the market value of the property is higher
but have a holistic approach that includes community employment, entrepreneurship, leisure, pleasant living than the investment necessary to create it. Even though
wellbeing and economic resilience. This performance and social involvement. The ‘everything nearby’ phi- this requirement remains valid, there is a visible shift
scope is much wider than common construction tra- losophy reduces the need for transportation, promotes in urban development towards more inclusive value
jectories. This broad scope includes material aspects local economic development, and adds the variety that propositions, including social, cultural, and natural
such as CO2 emissions, energy use, renewable energy makes a neighborhood attractive and lively. values. Doing so increases the diversity and resilience
and material sourcing, as well as conservation of eco- of a neighborhood and anchors the value of the project
systems and species, contributions to local culture, The development teams of exemplary projects do not into society, which will also make it financially more
and catering to the needs of healthy and happy living. just design buildings and infrastructure. They engage sustainable in the long run. A win-win situation on all
This increased scope has far reaching consequences and interact with future occupants, such as residents accounts.
and fundamentally changes the way urban develop- and entrepreneurs, to facilitate human scale solutions
ment is performed. for a wide range of neighborhood functions. To secure this, development of the district and the
realization of its goals do not stop when the buildings
Taking such a broad scope of goals into account simul- In the Pedra Branca and Menlyn Main projects life-style are delivered, the residents continue to shape the
taneously is a big challenge. To tackle this challenge, change is an essential part of the urban development development of the community together. This allows a
the projects used different methods to create and track vision. Residents and entrepreneurs are attracted neighborhood to adapt in time and continue to main-
their goals, such as One Planet Living principles and to these neighborhoods beyond their buildings and tain and increase its value. This continued and long-
LEED-ND certification for community development. facilities, drawn in by the integrated vision of an attrac- term development can be steered and facilitated, and
These strategies turn out to drive every project towards tive, desirable and local life-style that offers unique several strategies for this are presented in the projects.
becoming mixed-use and to focus on building resilient entrepreneurial, social and leisure opportunities. This These strategies change the involvement of both the
communities. results in neighborhoods that are found to be much urban developers as well as the occupants significantly.
more desirable and attractive, adding lasting commer-
cial value. Last but not least, mixed-use neighborhoods These strategies work best when projects include the
also increase a community’s resilience. (future) occupants during development, involving them
in the early design process and catering to their desires
and needs. The central question in this phase is: “What
will make the occupants truly happy?”
Universal patterns
The following increased standards can be seen in all
projects, detailed to the right:
1. Long term financial performance 2. sector-driven Positive impact 4. Long-term performance focus
Developers that realize that higher sustainability Many initiatives are launched to lower the impact of High standards for building materials, insulation and
targets are commercially attractive are driven to keep the construction sector on natural resources. The Cli- energy generation are crucial to enable low energy
improving and go beyond earlier successes. New mate Positive Initiative of the Clinton Foundation and consumption and carbon footprints in the use phase.
technologies with higher sustainability performance Cradle to Cradle© initiatives are clear examples of how At the same time, it is clear that the sustainability per-
and lower cost of ownership keep emerging to sup- the sector is moving towards a positive impact, benefit- formance is to a large extent determined by how the
port these strategies. Suppliers of these technologies ing those that are following these new sector goals. buildings are used, and the functioning of the district
work with developers to set new standards and have a as whole.
competitive advantage. This effect stimulates and ac- 3. Combining Comfortable and affordable
celerates innovation among front-runners, for example New materials, construction technologies, and techni- Business models that focus on performance criteria in
in Lyon Confluence. Proving innovative techniques in cal installations improve the quality of houses in many the use phase allow projects to distribute this respon-
front-runner projects paves the way towards broader ways, making comfortable living available to a larger sibility and reach the desired performance. Maintain-
application in the sector. part of the population. Although the quality of build- ing high performance levels is particularly supported
ings are improving, the costs of utilities and other when investment decisions are based on total cost of
monthly expenses are generally going up. This pres- ownership, as opposed to direct return on investment.
sures the sector to lower the cost of ownership and These business models enable long-term involvement
provide affordable living now and in the future. of developers and suppliers.
This chapter describes what new strategies are need- This broad sustainability scope impacts the develop-
ed to realize the broader scope and higher standards ment process on the following aspects, outlined in the
of sustainable developments successfully. following paragraphs:
The diagram on the next page shows an overview of 3.1 Ambition setting: design for life-style change
strategies found at the investigated projects for each
development phase. Paragraphs 3.1 to 3.6 describes 3.2 Involve occupants: ownership & continuity
these individual strategies in some detail.
3.3 Team formation: multi-disciplinary
Sustainability in its full scope applies to the construc-
tion, the life-style & behavior of occupants and to the 3.4 Responsible business models: true commitment
end-of-life phase. A full vision and design scope takes
into account at least: 3.5 Enabling adaptation and flexibility
› Energy consumption & Carbon emissions 3.6 Surplus values: Something to be proud of
› Production of renewable energy
› Material cycles & material sourcing
› Local ecosystem enhancement
› Social & (local) economic development
› Healthy and happy life-styles
› Optimal usage and continued development
| 19
PRE-
STRATEGIES USED INITIATION DESIGN CONSTRUCTION USE END OF LIFE
CONSTRUCTION
PERFORMANCE & END-USER Focus on community Guide the realization of Involvement and/or long-term vision includes
1 Share ambitions to enable co-creation
CENTRED VISIONS performance levels new building standards management by community end of life solutions
3.1 AMBITION
SETTING CERTIFICATION Communicate desired
2 Select desired certification standards Monitoring and due diligence
& LABELS performance levels
1 EARLY INVOLVEMENT Involve occupants as early as possible in goal setting and decision making
3.2 INVOLVEMENT
OF OCCUPANTS
2 COMMUNITY DEVELOPMENT Facilitate lifestyle changes by community management
1 SELECTING PARTNERS Strict selection criteria Enlist the right project partners
3.3 TEAM
2 MULTI-DISCIPLINARY TEAMS Co-creative design process Stakeholder cooperation
FORMATION
3 EMBED IN LOCAL CONTEXT Involve local parties & local expertise Use local resources & ecosystem services
1 FINANCE UP-FRONT PROCESS Return of investment through higher land and property Enable material mining
Pre-finance multi-disciplinary approach and involvement of all stakeholders
COSTS prices and/or lower costs of ownership and re-use
PERFORMANCE BASED Communicate responsi- Carrot and Stick solutions to warrant / secure Evaluation and profit
3 Monitoring
CONTRACTS bilities & accountability performance levels sharing
Make resilience an
1 EMBED RESILIENCE Ensure flexibility and diversity in all facets (program, form, scale, time) Enable super-use
explicit goal, get experts
3.5 ENABLING
Plan for learning and
ADAPTATION AND 2 CONTINUOUS LEARNING Open communication and willingness to share knowledge Performance monitoring and evaluation
improvement
FLEXIBILITY
Identify gaps in knowledge Maintenance of technical
3 GUIDANCE AND TRAINING Support project partners
and skill installations
› Above; Strategies for sustainable development, divided into action points for the phases of the development process
The stakeholders should not be guided to make the For occupants, weaving their dreams and ideas into
design decisions themselves necessarily, but to deter- the neighborhood design and community programs “Sustainability is inherently not
mine the performance criteria and operational wishes enables the implementation of functions and life- competitive but cooperative.”
that can be used by a skilled design team to develop style options that maximize value for them. This often
the plan. Feedback on this plan is then used to jointly results in design choices that are not necessarily the
work towards a design that achieves the ambition and cheapest, but that reflect the values that truly matter to – Silvia Lenzi (Pedra Branca)
has a strong and unified design. the occupants.
| 23
To ensure that performance of a sustainable urban as result-based reward systems, ensure that realizing
district is realized and not just stated on paper, or de- the long-term goals is beneficial for all.
grading over time, long-term incentives can be built
in. Business models that support the ambitions of the In many projects, performance-based contracts are
project and incentivize each stakeholder to deliver used to enable profit sharing or to impose penalties
to the best of their abilities is a successful strategy. based on the realization of goals. Linking the total cost
This performance-oriented development is triggered of ownership or the costs of living to the benefits of
by embedding financial incentives for all parties to the suppliers and the project developer, ensures that
secure the goals in the use phase. the required operational performance levels will be
met.
Some of the studied projects apply carrot and stick in-
centives to reward or impose penalties to stakeholders
for the design phase, which works well. These incen-
tives ensure involvement of the parties well beyond
the design phase. The incentive stimulates parties to
correct design mistakes and it stimulates the designers
to guide the construction and use phase to ensure that
new technologies will be installed and used in accor-
dance to the design specifications.
› Transparent local autonomy › Plan for learning and knowledge sharing › Identify gaps in knowledge and skill
If the neighborhood can make its own decisions and is Investing resources at the start of the project to orga- Investing time at the start of each phase to assess the
responsible for its own basic resources such as water, nize learning and knowledge sharing helps to prevent capabilities of project partners helps to determine the
energy and waste, it can adapt faster to changing condi- set-backs in later project phases, and creates opportu- need for support. Not addressing a lack of knowledge
tions and adapt the neighborhood to local needs. nity to make improvements. and experience often leads to mistakes, project delays
› Flexibility and diversity › Performance monitoring and evaluation and high failure costs.
Flexibility is important to be able to change the pro- Monitoring the progress in the realization of the district › Interaction between designers, suppliers, installation
gram of buildings and urban spaces to suit new uses, as goals helps to identify and solve bottlenecks as early as and maintenance companies
well as future re-purposing of the site. This is best real- possible throughout the project. Involving suppliers, maintenance companies, and con-
ized through a high level of diversity (in scale, program, struction and installation workers to ensure that new
occupants, etc) rather than modularity, allowing for a Example technologies are properly installed and used is vital in
richer and more vibrant urban environment. The CONCERTO program in Lyon Confluence shows the guaranteeing continued sustainability performance of
› Circular resource networks importance of supporting the design process with environ- the district.
By closing energy and material cycles in the neighbor- mental and energy expertise. Initially, architects ques-
hood, increased options are available in the future to tioned if sustainable goals could be aligned with other Example
reconnect these cycles in different ways to balance design ambitions. Contemporary building designs now The structural involvement of international sustainability
energy and resource use, making it more resilient. accommodate highly innovative sustainable technologies. experts to support local project partners proved to be a
In the following development phases design teams were key success factor to increase local awareness and knowl-
Example required to have sustainability experts at the core of a edge on sustainability in almost all studied projects. This
The Eva-Lanxmeer project offers a wide variety of hous- multi-stakeholder design process. allowed for more efficient management of the project and
ing typologies, technologies and program. This diversity more effective contribution of local design partners.
makes it exciting and inspiring to live in as well as visit,
increasing its value. As demographics in society shift,
many options are available for a variety of occupant types,
incluing elderly, children, students, and families.
We asked one of the architects of one of the projects for Disassembly’ cannot be based on the future value and its suppliers are just beginning to think about this,
the question whether they had thought about the of the materials either. The biggest advantage of ‘De- barely scraping the surface of what’s possible. From a
recovery of materials at the end of the life cycle of sign for Disassembly’ for these products lies in a much material as well as a cost perspective there is untapped
the construction. The architect jokingly answered: easier and faster assembly process. For buildings, this potential to create easy to assemble and disassemble
“I’d rather not think about people destroying my extends to more flexible changes over time. building concepts. For foreign construction companies,
creation.” This answer illustrates why most buildings these concepts may even pave the way towards enter-
today are designed without giving thought to recap- Design for disassembly was discussed in the context ing markets in developing countries.
turing materials at the end of the buildings’ life cycle. of the researched projects, but the construction sector
They have been designed without regard to an end-of
life scenario, as if they were for eternity.
4. Sector-wide approach “If the neighborhood is successful, the people that live in it are happy, live healthy
and shopkeepers benefit from the people that want to come visit. These are good
examples of the real indicators for successful urban development.”
- Marcello Gomes, Pedra Branca
The impact of sustainability on urban development
and the strategies identified in chapters 3 affect the
design and construction sector in many ways. The
innovative strategies and the new ways of working
require fundamental changes of the design and con-
struction sector. This chapter describes approaches
that enable large scale implementation of the strate-
gies for sustainable development sector-wide.
1 good neighborhoods boost value portunities for residents and businesses over time. This Rasing awareness of the impact and advantages
forces the involved parties to think about the relations In general, the awareness of these core values in the
The construction sector creates buildings, public between different people, buildings, shops, meeting industry is still low. The strategies discussed in chapter
spaces and roads, but the most important impact of places, streets, and traffic. Stimulating higher diversity 3 show that awareness affects the entire development
urban development is the wellbeing and appreciation in planning across a region, nation and internationally approach. It changes the way we measure success, it
of the people that visit or live in the neighborhood. improves performance of the sector. requires more disciplines to be involved early on, and
Occupants’ appreciation reflects upon the image of it changes the roles and manner in which professionals
the region and affects the property prices and the Impact on the sector interact.
success of commercial activities in the district as a Embedding core values in urban development requires
whole. Their lifestyle and behavior affects the actual the sector to prioritize long-term performance goals Change can best be stimulated by providing examples
sustainability performance of the neighborhood: the over short-term construction objectives. As more par- that prove that sustainable design approaches outper-
core values one hopes to achieve. Creating awareness ties play a role in the design phase, the role of urban form traditional urban development approaches.
about this across the sector, supported by clear use developers and architects changes significantly, which
cases that demonstrate increased financial benefits, should be reflected in educational programs and sector
is one of the most potent means to improve the sec- training.
tor as a whole.
changing role of investors KEY RECOMMENDATIONS
Effect on design principles The role of investors shifts from creating marketable
The core values of wellbeing and happiness are the property to “Responsible urban financing”: committing › Share and create examples that prove that
real indicators for successful urban development and to the creation of resilient and flourishing districts. This a focus on core values is beneficial in the
are directly related to how the neighborhood func- boosts both financial return, and resilient investments short-term and the long-term.
tions. A well performing district enables people to in the long term. A trend is visible for banks and inves-
live desirable life-styles that allow for social contact, tors towards ‘Socially Responsible Investment’. Stake- › Innovate development processes for
development of economic opportunities, fair costs of holders in the finance sector want to show that they early involvement of stakeholders and
living, comfort, and safety. It creates ownership among invest in sustainable projects, and this can be done by neighboring communities to incorporate the
the stakeholders and allows them to take responsibility including performance targets related to sustainability demands and wishes of (future) occupants.
of the neighborhood, which in turn enables continued in their investment criteria and valuing structural cost Ask residents, shopkeepers and businesses
development. savings. what they want, before designing buildings.
stimulate diverse and functional neighborhoods In addition, the value of a project is influenced by › Focus attention and support parties to
Diversity is key. Many of the studied projects focus incentives that enforce or stimulate the realization deal with a broad scope of sustainability
on mixed-use development. They build for a mixed of its performance goals. Banks and investors benefit goals. Steer away from a single-focus
group of residents, with different income levels, social greatly when they utilize ‘Life-Cycle Business Models’ development. Challenge the sector to
backgrounds, etc. In addition, functions are mixed (live, and ‘Performance Contracts’ as described on page 27, develop mixed-use and functional districts.
work, leisure, shopping, etc.) to lower transportation as they lower risk in projects and strengthen projects in
needs, make them more interesting and offer more op- realizing their upfront formulated performance goals.
2 Cross-sector innovation
Urban development is not just about managing the which each party has a clear, more or less independent, standard from abroad and roll it out sector wide.
expectations of what the district will look like, it’s as confined task. The projects discussed in part 2 of this
much about managing the expectations of how it will report rely on a collaborative approach, with input from Team creation and work methods
function. The issues that need to be addressed for a broad team with many different experts in the design Parties working together have to be willing to share
this range from cost of living, minimization of energy and creation process. ideas and learn from each other. Functional solutions
use, production of renewable energy, social develop- are best created through team-effort and consequently
ment, development of local economy, impact on the Changing roles and dynamic cooperation visualized and materialized by architects. This way
environment, to even the impact on the life-style of A network-approach significantly changes the dynamic of working requires a culture change towards more
occupants. As a consequence, the skills needed in of teams and the roles of their members, e.g. the role of cross-sector cooperation and a cross-sector innovation
projects accumulate. Encouraging all project partners the architect and the need for more cooperation in the mentality. We consider this to be one of the biggest
to collaborate requires a mind-set for cooperation, researched projects. The development manager plays challenges for the sector.
exchange of ideas and willingness to work together a central role to facilitate cooperation and informa-
in cross-sector innovation projects. This requires the tion exchange between all required stakeholders. This
breaking down of walls across the sector and partner- can be supported by good knowledge management
ships to create new forms of collaboration. tools, standardized cooperation contracts, collaborative
Building Information Management (BIM)software, and KEY RECOMMENDATIONS
Breaking down walls to enable open cooperation regular face to face update sessions. Aiding the sector
The broad sustainability scope and high ambition by providing these tools and proper training greatly › Stimulate cooperation of disciplines, with
levels for urban development require a network-ap- helps the sector. For example, the usage of BIM wildly specific attention to change an open
proach, or collaborative structure. This approach steers varies across the world, even among western countries. cooperative culture.
away from the linear structure in which the majority Countries that lag behind in BIM implementation can
of design and construction processes are organized, in leapfrog into a better position by choosing a proven › Foster the creation of cooperative work
environments in which all parties take
part in the decision making processes.
The construction sector avoids failure costs and is Less complex construction methods build coalitions with different types of suppliers that
reluctant to offer clients sustainable innovations The studied projects show that in many cases tradi- together co-create designs that deliver unprecedented
that they have little experience with. The construc- tional construction methods are used when the skills performance. New renovation concepts now allow for
tion sector is also traditionally organized in a linear for more innovative construction methods are locally a complete home makeover in 5 to 7 days. These result
process where construction techniques, materials unavailable. Innovative construction methods are in houses that look new, are energy neutral, and lower
and installations are combined in a one-off process simply too complex: they require specific knowledge, the cost of living for residents from the day they move
from start to finish. Consequently, each construction equipment or experience. Innovation in the sector is in. This supports the performance scope of newbuild
process has its own challenges and its own risks of accelerated if suppliers offer easier to assemble build- projects, as trends in consumer preference are chang-
failure, and sustainable innovation doesn’t drive risk ing techniques. Design for Disassembly is an approach ing faster and faster.
directly. This skewed perception is widely recognized used in other industries to improve this. It has also
as an essential barrier for innovation. proven to lower assembly cost. In addition, application
in the construction sector will enable better re-use of
Guidandance, support and guarantees materials. KEY RECOMMENDATIONS
The supply chain can lower the barrier for innovation
› Stimulate cross-sector innovation to enable
by taking financial responsibility for the final perfor- Cross-sector innovation
easier to apply techniques with high
mance of projects. The failure rates for innovative The sector is scattered into many different industries
performance levels.
technologies are reduced if the construction workers (eg. glass, steel, concrete, wood, plaster, energy and
are better trained and guided in their work. This can be ventilation installations, domotica, insulation, etc.). › Create solutions that can be adapted to
aided by new tools and mobile devices that allow sup- Cross-sector innovation speeds up the implementation different circumstances, climates and
pliers to guide the construction and train remotely. of highly sustainable techniques if more integrated environments.
solutions are offered with high performance levels for › Use new media techniques for remote
energy-use, indoor air quality, natural light and/ or guidance to allow the use of innovative
shading etc. techniques on construction sites.
› Design for re-use and disassembly to make
cross-supply chain innovation Example the assembly of buildings and structures
In the Netherlands a new form of social housing easier.
renovation is made possible by changing the way
› There is not one construction method or
housing corporations assign projects to construction
material that should be used in all projects.
companies. The construction companies are challenged
What works if suppliers of different materials
to offer solutions that improve the business case for and techniques work together to create an
housing companies, lower the cost of living for resi- array of integrated construction and design
dents, while improving comfort and health standards. techniques.
These performance targets changed the role of con-
struction companies completely. In their new role they
Knowledge and experience are crucial for innovation. the suppliers were asked to deliver solutions that out- Benefits of knowledge sharing
Knowledge sharing within projects is essential to perform the (local) market in sustainability and enable Innovative projects often serve as demonstration
allow all disciplines to work together and design in- good business cases. Suppliers and developers shared projects. They are truly valuable if they share their
tegrated solutions. Across the sector, sharing knowl- knowledge and invested in the learning process to de- experiences and document work methods, lessons
edge with third parties contributes to spin-off in the velop products with better sustainability qualifications learned and the barriers they encountered. The studied
region and/or in other projects abroad. and lower the construction cost. projects that did share their knowledge benefited in
turn from extra attention, that actually enabled them to
Goal-oriented projects get high innovation levels We learned that in sharp contrast to limiting the range learn as well.
Fostering the use of performance and goal oriented of solutions through adding detailed specifications,
design greatly enhances the performance of the sec- better results are achieved if developers share their Greenwich and Dockside Green contributed to new
tor as a whole. Asking suppliers the right questions ambition and challenge suppliers to come up with the legislation. Eva-Lanxmeer provided documentation that
enables true innovation and valuable cooperation. best possible solutions to meet that ambition. was used in other projects in the region. These projects
Narrow questions result in limited options, whereas benefited from the positive image and the increased
open questions can lead to innovative solutions. For Mixing international and local knowledge support.
example, if a developer asks his suppliers to build a A much used strategy is to create a project team with
LEED Silver building, he will get a design for just that. If local and international / non-local professionals. This
he asks for the best possible option to realize property allows for a broader range of knowledge and knowl-
with a competitive commercial business case and high edge exchange and enables the team to really under- KEY RECOMMENDATIONS
sustainability performance, the final proposition may stand the local context. In addition, it stimulates the
very well have a higher LEED standard and include fi- development of local expertise. To allow learning, work › Enable learning in any work process
nance structures to allow for higher initial investments, methods are chosen that encourage close cooperation by: asking the right questions, allowing
and retain its value longer. In Masdar and Menlyn Main, and sharing of knowledge. time for learning, and by choosing work
methods that support learning and open
cooperation.
5 Performance monitoring
Monitoring systems can be applied on many levels, the performance of a single object to a much more Consolidate labels and certifications standards
i.e. dealing with the origination and impact of a effective system level, the sector will gain support in There is an abundance of labels and certification
single material, installation performance, energy the realization of their urban visions and community standards, most of which contain many advantages
systems in a building, or monitoring community development. and useful elements. However, consolidating the
development and happiness levels of the people that labeling systems will benefit the sector, as simultane-
live and work in a district. Stimulating standards for Provide feedback to stakeholders ously maintaining multiple labelling and certification
monitoring reduces the threshold for monitoring Behavioral changes take time and require active in- standards is cumbersome for suppliers. Actively orga-
implementation for projects across the sector. volvement of stakeholders. Monitoring systems prove nizing cooperative, streamlined certification standards
to be highly effective in raising awareness and affect- will relieve this issue while safeguarding the focus on
Monitor how the district functions ing the decision making process of occupants in their specific, essential content for projects.
The monitor system is closely related to the vision and everyday activities. Communicating and sharing com-
central goal of the project, namely to create a function- munity performance levels over time will keep stake-
al neighborhood. This goal requires monitoring systems holders involved, ensure that important aspects of the
that use the right indicators that reflect how successful vision are remembered and it will encourage them to KEY RECOMMENDATIONS
the district is for all its stakeholders. Through evolving actively pursue continued development.
monitoring systems and broadening their scope from › Foster the application of active monitoring
of the performance of districts. This creates
a better learning experience and a mind-set
to steer towards functional neighborhoods.
6 Responsible financing
Align the incentives of all parties across the sector developers indicated that apart from financial Finance multidisciplinary design approaches
and supply chain using business models that steer involvement, the experience of operating their Involving more disciplines and professionals in the
towards long-term sustainable development. Busi- own buildings enabled them to design better design phase may require extra process costs. However,
ness models that will benefit from positive long-term buildings for subsequent projects. doing so also prevents failure costs and adds signifi-
performance will automatically steer towards more cant value, as is shown in the studied projects. In fact,
(hands on) inclusion in the use phase and adopt mea- The sector can accelerate sustainable building by in long-term development projects, the cooperation
sures to stimulate continued development. This can changing the business models and contracts to enforce enabled design teams to lower the initial investment
be done by: long-term involvement. for sustainable buildings by over 30% (e.g. Menlyn
Main).
› Coupling the income of the developer to i.e. the Responsible financing
turn-over in the shops. In Pedra Branca the com- Investors significantly influence the way we build. Fi- There are different ways to finance the up-front process
mercial success of shops is directly linked to the nancial contracts can involve guidelines to align the fi- costs to involve all the required disciplines:
rent the project developer will receive. This way nancial incentives with truly sustainable development,
the incentive to create a functional neighborhood i.e. responsible financing. Through initiating programs 1 Pre-finance the design costs and allow payback
will be shared by all parties. to develop such guidelines, the sector can stimulate in- via higher land and property prices (i.e. Eva-
vestors to abide by them and invest accordingly whilst Lanxmeer). This approach requires one party,
› Direct involvement in community management. In gaining better return on investment. the developer or municipality, to finance the
many projects a company was set up to design and upfront costs. Per project this will require an
build the district and to develop the community. extra, small, initial investment, which will avoid
The continued involvement changes the mind-set. failure costs and add more value. Hence, this
It focuses the attention of the developer to the use investment can be done via a revolving fund. Pre-
phase, and not just to the completion and sale of “Longer-term and close cooperation financing in the studied examples was sometimes
the building. done by municipalities, but also by investors
between architects, engineers and that understood how the desired performance
› Make developers responsible for operational construction companies enabled us to indicators result in financial advantages.
performance. If developers build via DBFMO
lower the initial investment for a highly
(Design, Build, Finance, Maintain, Operate) 2 Work with long-term performance contracts to
contracts, their business cases benefit from sustainable building by as much as include reward or penalty systems. This approach
an optimal total costs of ownership (TCO). 30%.” requires all parties that contribute to the design
This extends their financial horizon to include of a functional district to invest in the process and
operational costs. The building benefits from - Jurgens van Huyssteen bear part of the risk. In turn, the involved parties
an optimal TCO as well if the developer remains (project developer Menlyn Main) can benefit from designs that meet the desired
the owner. In addition, a positive reputation of performance levels.
the district affects the price of the property. The
| 39
Invest in re-use and recovery of materials A few projects (e.g. Karaikak Pondicherry and Sonoma The challenge for the design and construction sector is
In Masdar, the aluminium and concrete used for Mountain Village) paid special attention to finding and to develop techniques that enable easy (dis)assembly
construction contained high percentages of recycled re-using locally available waste materials. In general, that allow for high recovery rates, and keep costs low,
materials. Material suppliers are making progress to however, design and construction methods seem to with a focus to make the assembly of buildings easier
further increase these. pay little attention to reclaiming, recovering and re- and cheaper. This also accelerates the penetration of
using materials. In other sectors (i.e. office furniture, innovative construction methods in developing coun-
In contrast, only a few building designs today take footwear, automotive, etc) Design for Disassembly tries.
measures to enable re-use and recovery of construc- proves to be valuable. The main benefit within these
tion materials. When asked if any end-of-life measures sectors is the advantage of easy and cheap assembly.
were taken for material recovery in his specific building The sustainability benefit of material re-use is consid-
design, one architect made the noteworthy remark that ered to be a nice secondary effect.
he did not like to think about how his creations were
taken apart or demolished. Material recovery and re-use is an important issue,
given the expected amount of construction worldwide,
From the developers (and architects) point of view, and the amount of construction material that is still go-
shortage of construction materials is generally not ing to landfills. It should be dealt with by more parties
considered to be an urgent issue. Similarly, investing than just material suppliers. KEY RECOMMENDATIONS
in material recovery is not considered to be profitable,
as materials will be used in buildings for extensive › Change business models to align long-
periods of time. term performance incentives.
5. epilogue
››Part II - Research
1. Introduction
Detailed environmental assessment commences as part of the 75% of capital is provided by Proposal won by Windmill development: “Van Belleghem’s resolve and “big Interdisciplinary groups
1.4 district model
preparation of a business case for the property
Phase 1 “Synergy”
For each district in this study we developed a graphical
workshops involving many citizen groups Master Plan is prepared by
Bugsby Perkins + Will Contractors & specialists seleted, work is highly collaborative
completed 2008
model of the development process. This model is divided
P r oc e s s »
The initial development concept includes market analysis and Phase 2 “Inspiration”
outlines vision, including sustainable planning principles $350k given to support the
development of innovative
Developers agree to pay $1 million penalty if LEED PLatinum is not achieved completed in 2008
into two main parts; a process description, and a collection
City launches a 40-day competition for development of the infrastructure City amends zoning and land use to aid development Phases 3+4 completed
of key moments. Taken together with the central time-line
D e sc r iption
property. An RFP is sent to pre-qualified developers in 2011
DGL hires staff member to guide development review and contributed
Government
M unicipal Governm ent ! The Process Description is intended to provide an objective
overview of the district’s development, and the roles played
Project Developer ! ! !
ABC Developers
by key stakeholders. We found it important to provide an
!
Local Government
C ity of Victoria ! ! ! ! overview of the major activities in the development process
because it allows a basic contextual understanding of how
Future Occupants !
the Greater Public
! the district evolved.
Arc hi tects & Master Planner
ABC Architects
Financing
ABC Bank
! ! • A time line of the project, including project phases
• Clearly identified stakeholder groups
Workshops include a broad range of "It was Van! Belleghem’s resolve on a ! Continuous investment Real Estate market crashed. Dockside
!
• Each stakeholder's involvement over time
groups including native groups ‘big vision’ that inspired the project” into organisation improves Green still manages to sell units at a
communication and planning competitive price.
!
Strict “Triple Bottom Line” criteria ! Funding offset costs for LEED,
set for all development proposals,
LEED Silver is minimum standard for
and bureaucracy for waste water
treatment system.
Wide involvement and feedbak from
the public in defining the community
! Phase 2 (Inspiration) gets 1st LEED
Neighbourhood Development • (Annotated) points of interaction, achievements,
K e y Momen ts »
all buildings plan certification
©Desvigne Conseil - Jean-Philippe Restoy. Exploitation rights -SPLA Lyon Confluence ©Aurélie Leplatre. Exploitation rights -SPLA Lyon Confluence
©Jérôme Boucherat. Exploitation rights -SPLA Lyon Confluence ©Jérôme Boucherat. Exploitation rights -SPLA Lyon Confluence
Lead architect and landscaper ZAC 1: Pre-construction Start construction CONCERTO Public discussion master plan
ZAC 1 selected (2001) (2003) Block A, B, and C (2005) ZAC 2 (2008)
Environmental assessment CONCERTO proposal ac- Start monitoring CONCERTO Start eco-renovation Saint- Partnership agreement Smart
Public consultation "Lyon Con- master-plan (2002) cepted (2004) buildings: Energy use and Blandine districts (2009) Community (2011)
fluence: Projet Urbain” (1997) occupation issues (2006)
Working group "energy use Financing by EU CONCERTO Green living and working in- Master plan ZAC 2 devel-
Development company SEM in master-plan" (2003) and ADEME (2004) Start educational programs formation campaigns (2010) oped; start land sales (2012)
Lyon Confluence established CONCERTO residents and
(1999) CONCERTO proposal submit- CONCERTO monitoring pro- workers (2006) Delivery of CONCERTO Block Initial assessment Smart
P ro ce ss D e s c r i p t i o n » ted (2003) cess established (2004) A, B, and C (2010) Community (2013)
Office and information centre Lead architect and landscaper
Maison de la Confluence estab- Master plan accepted by CONCERTO developer teams ZAC 2 selected; development WWF partnership: One Planet First developer team ZAC 2
lished (1999) Greater Lyon (2003) selected (2005) master plan ZAC 2 (2008) Living (2010) selected (2013)
D eve l o p e rs
C O N C E RT O D e v e l o p e r s ( L ea d ) ! !
B o u y g u e s I m m o b i l i e r ( Z AC 1 & 2 )
A D E M E ( F ra n c e )
NEDO (Japan)
D eve l o p m e n t Co m p a n y
S P L Ly o n C o n fl u e n c e ! ! ! ! !!
L o c a l G ove r n m e n t
L o ca l Au t h o r i t y G r ea t e r Ly o n
! !
F u t u re O cc u p a n t s ! !
A rc h i t e c t s & U r b a n P l a n n i n g
F ra n c o i s G r e t h e ( Z AC 1 )
H e r z o g & d e M e u r o n ( Z AC 2 )
M i c h e l D e s v i n e ( Z AC 1 & 2 )
N G O’ s
Hespul
W W F F ra n c e
E x t e r n a l Ad v i s o rs
Enertech
TRIBU
!
ALE
CETHI Inhabitants fully support plans to Perception: good architecture Development in skills of construction Maintenance contracts contain no leverage
! develop the Lyon Confluence area !
and renewable energy systems ! workers in energy-efficient building !
for reaching CONCERTO targets (2009)
(1997) incompatible (2002) needed (2005)
Lack of on-site communication hinders
Key M o m e n t s » Political will and commitment for Working group "energy-use" to inform On-site "green" construction trainings ! solving during construction and
problem
! project Lyon Confluence (1999) and educate designers (2002) ! lay foundation for future work (2006) delivery (2009)
Public drive to create high quality CONCERTO inspires ambitious Maintenance companies involved Occupants very receptive to "lifestyle"
!
neighborhood: social and functional
!
(renewable) energy use targets (2003) ! in monitoring and problem solving ! training during their first year (2012)
mix, public transport, ecological (2006)
restoration, and exemplary design CONCERTO objectives enforced ZAC 2: One Planet Living. Neutral and
(1999)
! through contractual commitments All key stakeholders involved at the !positive energy building (2010)
with developers (2004) start of developing masterplan ZAC
2 (2008)
| 49
› Building in different phases allowed to make a reflection of what the neighborhood › New building materials and traditional materials
stakeholders to apply their learning, increasing should be. used in sustainable construction require a high
project ambitions and improving project skill level to be properly used and implemented.
approach. › Architects play an important role in connecting Education and training was necessary to enable
design and technology. To enable good contractors to implement new technologies.
› Sharing responsibility by involving key cooperation, architects needs to be open-
stakeholders in project monitoring and minded and willing to involve engineers in the › Integrating sustainability targets into building
evaluation, created a shared understanding and design stage. design includes a more careful consideration
a problem solving mind-set. of materials and their use. Because material
› Investing time and finances to educate and selection frequently happens at this stage, there
› Embedding sustainability in the project required train stakeholders in sustainable design and is an opportunity for suppliers to inform and
involving key stakeholders at the start of the construction proved to be effective, increasing assist designers in their choices.
design phase. Good process management and professional performance and establishing a
intensive cooperation is essential for a multi- knowledge base for future work. › Late involvement of subcontractors in
stakeholder process to properly utilize the the design process may lead to a low
different skills of professionals. › With every new project phase and transfer of sense of commitment to the project goals.
responsibility between stakeholders, there Subcontractors may have lower motivation
› Investing time to review and reach stakeholder is risk of miscommunication, mismatch in to apply more ambitious approaches or are
consensus on environmental design ambitions knowledge and skills, and lack of follow up on not fully capable of realizing the project's
early in the design phase promotes good established goals. In order to reduce these risks ambitions.
progression in later project phases. it will be necessary to plan ahead for these
moments, while also stimulating stakeholder
› Integrating performance targets into CONCERTO motivation, communication, and interaction.
contractual agreements with designers and
developers ensured commitment towards › Detailed process, design, and even “how-
realizing the original environmental goals. to-built” specifications helped stakeholders
Ownership can be facilitated by finding creative understand their responsibilities and supported
“carrot-and-stick” type of solutions that both a better translation of the urban design
engage and oblige stakeholders to deliver to the into reality. Monitoring project process and
desired performance level. implementation by financial, administrative, and
technical committees facilitated a more steady
process and allowed problems to be identified
› The developer has a key role in ensuring that and solved early on.
the conceptual image of the project meets the
desired performance criteria. The idea in the
start-up phase is to not make a “picture”, but
Success Factors to anticipate and deal with barriers during the design, apartments were combined in the buildings, and
construction, and delivery of the each of the following children from the schools in both areas were required
1 The efforts and ability of SPL Lyon Confluence and project phases of Lyon Confluence. to move between neighborhoods.
TRIBU to communicate and educate key stakeholders
6 Barriers encountered during the CONCERTO 11 With the establishment of “SPL” Lyon Confluence its
on sustainable design and building encouraged
project proved to be essential collective learning focus shifted more towards attending the needs of the
stakeholder learning and involvement. At each step
moments. The project was a statement of success local public and working towards creating a healthy
of the process efforts were undertaken to support
for the participants, laying the foundation for higher livable environment. In addition, developers in ZAC
stakeholders in their professional activities. This
sustainability ambitions in Lyon Confluence. 2 are required to provide additional services after
enabled the SPL Lyon Confluence to increase
finishing construction activities. This public focus was
sustainability performance, and explore and 7 The experiences from CONCERTO showed the
seen as necessary to encourage social interaction,
implement innovations such as constructing zero importance of integrating environmental and energy
involvement of residents, and the continued
energy and energy positive buildings. expertise in the design process. This insight was
progression of the area.
applied in the design phase of ZAC 2, establishing
2 Funding provided opportunity for SPL Lyon
sustainability at the core of a multi-stakeholder design
Confluence to reach their ambitions; upfront
process. preconditions
financing ensured cooperation on designs during the
competition, meetings and workshops were organized 8 The high profile and pursuit of architectural quality in
to support key stakeholders in their professional Lyon Confluence ensured that developers were keen 1 Strong political and citizen support for developing the
activities, and finances were used to explore urban to buy land and pursue further eco-innovation. confluence area and extending the city center.
innovations (e.g. Smart Community Lyon Confluence).
9 The design process for Lyon Confluence was set- 2 A centrally strong coordinating function of SPL Lyon
3 The lead developers in CONCERTO were made up to establish a multi-disciplinary approach to Confluence throughout the development process.
partner in the project to create co-responsibility developing the urban plan and individual building
3 The willingness of stakeholders to explore and learn
towards realizing the programs targets. In addition, designs. An important reason for doing so was the
beyond what they are accustomed to.
architects and developers were required to accept relative dominance of the architect in the French
the design and energy specifications, further securing design process. By involving developers and 4 Good working relation between French and Japanese
CONCERTO’s ambitions. construction companies into the initial design stages, national development companies (ADEME and NEDO).
the teams were stimulated to coordinate and think
4 The continued involvement of SPL Lyon Confluence
about the outcome and users of the project i.e. “First
and members of the Consortium Steering Group
functionality, than design”.
ensured that political, financial, administrative, and
technical requirements and targets were managed. 10 The SPL Lyon Confluence implemented measures
to promote social and cultural mixing within the
5 The knowledge partners (e.g. TRIBU, ENERTECH, ALE)
buildings of Lyon Confluence, and between the old
participating in CONCERTO were effectively involved
Perrache area and Lyon Confluence; social and private
| 51
Pedra Branca in Figures develop Pedra Branca as a sustainable city. Jaime Lerner
(former Major of Curitiba, SC Brazil) was also invited to Energy & Materials
Total site area: 300 hectares › Buildings designed and constructed with low environmental impact,
Built Area: 180 hectares host inspiring workshops to change the way local parties low energy consumption, and low generation of greenhouse effect
Commercial space: 30%, 30.000 jobs worked. In a long-term partnership a setting was created gases (best solar and dominating wind orientation)
for architects to share and exchange ideas. For each section › Intense use of natural light and ventilation, solar heating, the use of
Residential space: 70% rain water
Projected population: 40.000 that is developed sessions are organized to invite future › Low car use: walking, biking, everything nearby – car sharing
Number of students: 10.000 occupants to exchange ideas and learn about their wishes › Encourage material reuse and recycling - ZERO Waste
and demands. › Climate positive development
Website: cidadepedrabranca.com.br
2000. Out of respect for the land Pedra Branca wanted to In 2009 a new partnership with ESPB (Espirito Santo
create value with respect for nature and the site’s heritage. Property Brasil) was established to create Pedra Branca
Culture & Economy
The development process accelerated as Unisul University S/A. This enabled the further development of the new
› Mix-use: schools, university, shops, businesses, residential
settled on the site and founded the Pedra Branca campus in neighborhood center (in 2010), where people will live, › Housing diversity aimes at coexistence of people from different
a partnership with Pedra Branca. work, study and enjoy entertainment all in the same place, classes, ages, cultures and races
the primordial concept behind Sustainable Urbanism. The › Balance density and diversity (better energy performance, water,
electricity, phone, public transport and land occupation).
From the start the idea was to create a mixed neighborhood Block-by-Block approach for the development of new › Social program (encouragement of participation, / active
with commerce, businesses, parks and residential areas. apartments in the next 20 years aims to facilitate 40.000 citizenship, social awareness (keep streets clean, etc.), and cultural
manifestations.
From 2000 to 2005 parts of the land were sold and residents, 30.000 workers, 10.000 students.
developed with predominantly single-family houses, a
business centre and a shopping mall. Silvia Lenzi (architect and consultant for Pedra Branca), eng.
Health & Happiness
Dilnei Bittencourt (Pedra Branca S/A), Valdir Tomazzi and
› High quality internal environments
In 2005, at a conference in the USA, the president of Pedra the Unisul University have been involved from the start, and › Everything you need nearby (familiarity)
Branca learned about the ‘New Urbanism’ principles. This are still involved in the development of Pedra Branca today. › Bicycle & pedestrian friendly (wide tree-lined sidewalks to provide
shade)
changed the course of the development dramatically. Their long-term involvement provides continuity in the › Internet & telephone interaction / communication with
From then on the New Urbanism principles were adopted development process. representatives of the city / state
› Accessibility in public areas (mobility for all)
in an integrated approach for urban development. DPZ › Potable tap water
(Max Rumis and Marcela Rumis) were invited to help › Consume local produce
| 53
Initiation in 1997 as the city grew around the In 2005 New Urbanism is adopted as an In May 2009 Pedra Branca is announced as one Second Block 'Patio das Flores' is developed in
farm land and Unisul University wanted to settle integrated urban development approach. of the 18 founding projects for the Climate 2011; and the third block 'Office Green' (LEED
on the site. Positive Development Initiatives. Silver standard) in 2012.
DPZ and Jaime Lerner get involved to
In 2000 Pedra Branca ltda was Founded to incorporate New Urbanism through urban Partnership between Pedra Branca ltda. and In 2013 retail on ground floors and 'Passeio
develop the land. planning and stakeholder involvement. ESPB to create Pedra Branca S/A. Pedra Branca (30 shops) are opened.
2003: Opening of Business Center; 2004: Unisul In 2010 sustainable urbanism plan designed for Development is ongoing and will continue
Process Description » inaugurates its shopping mall and Technopark. a new neighborhood center (40.000 residents, beyond 2025.
30.000 workers, 10.000 students).
Roadmap for Climate Positive Impact to be
In 2010 the first Block 'Patio da Pedra' is developed.
developed.
Occupants
Unisul University
! !
Residents
Clean Tech Campus
Government
Architec t
Gehl Architec ts (Ulrik N ielsen) ! !
8 local architec t firms
NGO
Clinton Foundation
! Strong bond between the land and its
owners (cattle ranch) paved the way for
! principles is adopted for
New Urbanism
integrated sustainable approach.
Sustainbility goals set and widely
supported through workshops by ARUP. !Drinkable tap water through cost
competitative private water
sustainble developement. supply and waste water treatment
Key Moments » DPZ and Jaime Lerner attracted for Clinton foundation supports goal
setting, !benchmarking and ideas for
system.
! Partnership and district of Unisul is
anchor point for the development.
implementation.
implementation. Operation of buildings and
Workshops with local architects to create ! communicty development is set
!
!
Phase 1 of the Technopark sold out (32
non-pollutant businesses on site).
open workspace and share ideas.
!
Material choices based on low impact,
LEED requirements and future value
up by Pedra Branca S/A, after
about two years management is
Good understanding and interaction with (through re-use and cyling). transferred to residents / building
!local communicty / people (=local market owners.
needs) are key for project success. Upfront agreement about the
!contribution by each resident to the
maintanance (costs) of public areas.
1 The original land owner’s respect for the land. This 8 Pedra Branca S/A is responsible for the urban / 1 The district of Unisul University served as an anchor
steered the project towards sustainable development. building design, manages the construction and point for the development. Today the University
Even though some were sceptical, now the Pedra manages the first years of operating the buildings. The still serves as a valuable knowledge partner. The
Branca vision is acknowledged. Persistence paid off. active role in all phases of the project enabled them connection between the programs at Unisul and
to improve execution of all project phases. Organizing Pedra Branca a beneficial for both the region and the
2 Continued involvement over time of local
the operation and management of the buildings and University.
professionals in the core development team has
public spaces generated valuable information to
enabled learning and it added good knowledge and 2 Strategic partnership with ESPB provided a sound
improve the design process in the next projects.
understanding of local needs and desires. financial basis for the development.
9 After a period of about two years the operational
3 The ‘New Urbanism Principles’ formed an sound 3 High involvement and support from the municipality.
management of the building and comunity
philosophy that made sense to the developers and
development is organized by Pedra Branca S/A.
enabled meaningful urban development.
Over time, the management tasks are then slowly
4 International expertise on urban development transferred to the occupants / building owners. The
was combined with local architects to exchange experience of Pedra Branca in the initial organization
professional expertise on sustainable urban ensures a proper management structure. The long-
development and local knowledge about the region. term involvement of building owners provides an
autonomous continuation of everything that has been
5 Through a long-term partnership a setting was created built and organized. It also results in a high level of
for 8 local architects to work together. Architects no involvement.
longer needed to compete with their ideas. They work
together to realize a shared mission. 10 International agents like the Clinton Foundation, and
involvement of ARUP and Gehl Architects brought
6 DPZ organized many workshops to invite local parties specific knowlegde and examples that initiated
to contribute and help with the development. The planning for shared spaces, waste management
open process, high involvement of the municipality systems and the construction of a private tap water
and future occupants provided valuable input. In and waste water treatment and management system.
addition, it created support for the development.
11 The use of standards like LEED enabled good selection
7 Clear up-front rules on (financial) participation of of suppliers and clear communication about project
residents to maintain the neighborhood provided goals.
a solid foundation for continued maintenance and
development of the neighborhoods.
| 57
Credits › Nilto Bogo (resident of Pedra Branca neighboorhood) › Mary Yamakawa (Consultores)
› Marcelo Gomes (Pedra Branca, Executive Director) › Valdir José Tomazzi (Valdir José Tomazzi Eireli - Me) › Maíra Pires (Consultores)
› Valério Gomes (Pedra Branca, President) › Nelson Teixeira Netto (Arquitetura Urbanismo) › Mary Yamakawa (LEED Consultant)
› Vânio Pacheco de Abreu (Pedra Branca Team - › Mariana Schwartz (Architect) › Maíra Pires (LEED Consultant)
Infrastructure) › Juliana Castro (Architect) › Olavo Kucker (DUX)
› Ramiro Nilson (Pedra Branca Team - Infrastructure) › Silvia Lenzi (Architect / Project Advisor) › José Renato Dellagnelo (INAITEC)
› Dilnei Silva Bittencourt (Pedra Branca Team - › Luciano Rodrigues Marcelino (Unisul) › Giovani Bonetti (Marchetti Bonetti)
Consultant) › Ingo Hermann (Unisul) › Camilo Martins (Mayor of Palhoça)
› Richard Schmidt (Pedra Branca Team – Engineer) › Geraldo Campos (Unisul) › Photos: Pedra Branca S/A
› Giane Formigoni (Pedra Branca Team – Engineer) › Henrique da Cunha Sant'Ana (Resiliens)
EVA-Lanxmeer in figures The next step was involving project professionals with all
required disciplines to enable the development of a plan Energy & Material
Total site area: 24 hectares
that met all the sustainability goals. As the process map › Low carbon / Low energy buildings
Built Area: 100 hectares › Eco-buildings,
New houses: 200 shows, all actors were involved in the development of the › Closing material cycles (for building and usage phase)
Income mix: 30% social, 20% mid class, concept for Eva-Lanxmeer. A natural selection of eager and › Prevent droughts and flooding (infiltration, controlled water
drainage)
50% free sector committed professionals and individuals ensured continuity
› Separation of waste water flows and local wastewater treatment in
Ecological offices: 40.000 m2 BVO of people in the process. natural landscape
› Renewable energy (Solar and wind)
Schools: 30.000 m2
Urban farms: 48.000 m2 (Caetshage) The central project team initiated specific workgroups (eg.
Website: www.eva-lanxmeer.nl to develop energy concepts, the landscaping, etc.) with
Ecosystems & Biodiversity
professional contractors to develop concepts that met the
› Strengthen and re-cultivation of historical ecosystems, waterways
central vision. Concepts and plans were only adopted if
the story of Eva-Lanxmeer the residents agreed to them. This ensured a high level of
and archeological structures
› Quality landscape
awareness and a high level of quality from the end-user › Connecting architecture and nature through a color concept
› Functional green spaces: meeting areas and permaculture
Eva-Lanxmeer is developed as an experiment and perspective. › Maintenance and arrangement of public areas by residents (leading
demonstration for integrated sustainable urban philosophy: the entire neighborhood as your own back-yard).
development. Marleen Kapteins (a professional The qualities in the urban plan, architecture, the building
environmental consultant) initiated the process. Her dream principles and landscaping, resulted in an attractive
was to realize a neighborhood founded on a broad and neighborhood with high market value property compared Culture & Economy
integrated set of sustainability goals. to the construction costs. Eva-Lanxmeer is a good example › Urban Integration
of how early involvement of residents and all required › Social mix of residents
Kapteins started developing her vision in 1994 and › Sustainable office and school buildings
specialists results in high value property and sustainable › High level of communication and involvement of neighboring areas
presented it throughout the Netherlands. Through many housing and lifestyle changes. › Documentation of the process to enable spin-off projects
talks, meetings and conferences she gathered a group of › Professional Urban Farming
› Education centre (planned)
capable and persistent people that wanted to commit their
time to initiate Eva-Lanxmeer.
U t i l i t y co m p a n i e s
Wa t e r b e d r i j f G e l d e r l a n d
Opmaat
Nuon / GGR-gas / Core (Energy)
Landscaping
D e Wa a r d e ( P e r m a cu l t u r e )
Copijn (design) !
P ro j e c t D eve l o p e r ( E v a Fo u n d a t i o n )
M a r l e e n Ka p t e i n
Construction supervisor
L o c a l G ove r n m e n t
M u n i c i p a l i t y Cu l e m b o r g ! ! !
H e i n St r u b e n ( p r o j . l ea d e r )
!
Building Supervision (M. Bouwmeester)
C O R E PA RT I E S F u t u re O cc u p a n t s ! ! !
Fu t u r e r e s i d e n t s
! !
Kl e u r r i j k w o n e n ( H o u s i n g c o r p o ra t i o n )
B E L ( R e s i d e n t ' s A s s o c i a t i o n Eva - La n x m e e r )
F o u n d a t i o n T e r ra B e ll a
! ! ! !
C o m p a n i e s ( o ffi c e b u i l d i n gs )
A rc h i t e c t s & U r b a n P l a n n i n g
Bugel Hajame
Joachim Eble
! ! !
O r ta At i l i e r
Copijn
Others
L o c a l Fo o d M a n a ge m e n t
P r o f e s s i o n a l U r b a n Fa r m ( Ca e t s h a g e )
E x t e r n a l Ad v i s o rs
Financial Advisors !
Technology advisors
Clear set of principles and goals envisioned,
!
e.g. Eco-building (use of sustainable materials)
! Coordination, guidelines and materials handbook
for eco-building. enable architects to design to
! Superintendent guides construction & drives
innovation in materials and techniques
! Consistent philosophy & good communication
throughout the process
principles
! Full participation of future residents. ! change after residents buy their land
Attitude
!
High property values & goal achieved for sustain-
! community support for urban plan
Full able mobility
Interdisciplinary and strict selection to gain Designs checked to ensure eco-building and
! capable and ambitious project members Process leader manages learning processes & !sustainability goals
(process costs pre-financed by municipality) ! facilitates coordination. Workgroups for each !
Residents coordinate further targeted develop-
ment, e.g.: local organic food has social &
Key M o m e n t s » Residents don’t give full support to first urban
sustainability theme provide innovative solutions
!Goals achieved for: construction, low-energy,
materials, bio-ecological building sustainable
economical function, workgroup “Dry Feet”
analyzed and resolved flooding in cellars, local
plan!(Joachim Eble involved to fine tune and gain High stakeholder involvement by making them
residential support for the final urban plan)
! responsible for adaptation & realization of ideas
water & energy management, historical values
& beautiful environment.
energy company founded by residents to
provide more sustainable energy
› The integrated and broad sustainability › Overall goals for sustainability are set by the
perspective resulted in an attractive and high initiators of the project. Within these choices
quality neighbourhood with relatively high many embedded goals for material use are
property value and sustainability performance. included already.
› Early involvement of residents resulted in local › Architects play a dominant role in selecting the
initiatives from residents (e.g. local energy final materials for buildings. They are the main
company, urban farming, maintenance of public audience for material suppliers to communicate
green, social program and life-style program for advantages of new materials and technologies.
sustainable living).
› Risks and learning curves to apply new
› Early and intensive involvement of residents materials and technologies posed a significant
resulted in strong social links and successful barrier. Scorecards to demand performance and
local economic program. quality guarantees throughout the construction
and usage phase, significantly contributed to
› Taking enough time for concept development, the application of new materials.
project definition, planning and design paid off.
› No two project are the same. To ensure proper
› Involving true innovators (material and building application of new materials and technologies
experts) from early start all the way till usage extensive testing and support in many different
phase enabled the realization of innovative situations is required.
concepts.
› Training construction and installation workers
› Once residents own the land their attitude will on a project level is necessary. Assisting
change. The initial attitude of (future) residents them on the job to guide them through their
was open minded and flexible, after purchase of learning curve is the best way to prevent "bad
land the residents became more protective and experiences" that will only result in higher
demanding. reluctance to use new technologies.
› Making suppliers of new materials and › High-level goals for material use are set and
technologies responsible for the final maintained by internal professionals with
performance of the solutions, proved to work perseverance. These professionals are the
well in selecting solid partners and to overcome "internal ambassadors" within the project that
fear of working with new technologies. ensure the right level of support and knowledge
throughout the design and construction process.
Success Factors The central project group connected all aspects and Preconditions
secured that the integrated solution lived up to the
1 Clear and ambitious goals that were carried through vision. 1 Pre-financing of the process costs by the municipality
the entire process. The main and central people was key to enable the stakeholder involvement and
7 The central workgroup appointed a superintendent
remained present in all phases (from ideation until the iterative development process. This resulted in
for the building process (construction administrator).
usage and maintenance phase). high added value (high market value compared to
This enabled continuity and quality control directly
foundation and construction costs). The costs of the
2 Strong and exciting goals that all stakeholders wanted tied in with the goals and philosophy of the project.
process were paid back by residents through the
to commit and contribute to. The construction administrator also supported the
land. This shows that local governments can play a
builders working with new materials and techniques
3 Involvement of all required disciplines from the early significant role and enable participation of residents.
(e.g. working with low weight concrete and high
start. The project group was made up of people to
insulation standards). This prevented elimination of 2 Political will, vision, commitment and active
span all necessary disciplines (energy, eco-building,
innovative concepts in the construction process as a involvement ensured the support by the municipality
food, water, nature/green spaces, residents, social and
result of a lack of experience with the new materials throughout the process.
urban planning).
or techniques.
3 An open and flexible planning process is required.
4 A thorough selection of capable people with profound
8 Inclusion of all residential demands resulted in high Allowing a learning process and the wish for early
knowledge, craftsmanship, determination, persistence,
quality neighbourhood with good property values. involvement of residents (to get their full support)
a strong desire to contribute to the sustainability goals
Once the building cost were clear, taxation of the resulted in the iterative process. To keep costs under
and the ability to deliver results. Selecting the right
property to be build showed that a good margin could control, a time plan was made, allowing for learning
suppliers was done via personal talks. Selecting the
be made. and iteration while meeting deadlines.
right suppliers and parties to involve also took into
account their ability to adhere to the process and their 4 The process manager must be able to deal with
ability to cooperate within the team. distributed responsibility, learning processes, and
facilitate participation while coordinating central
5 Iterative process with residents from the start (as early
planning and steering toward goal realization.
as the ideation phase). This process allowed flexibility
in selecting options with residential support, open 5 High level of communication throughout the process
communication, learning, trust, thinking from the to inform and involve all crucial parties and get their
perspective of maintenance and the involvement of all full support.
parties during the usage phase.
6 A strong will to work with a result-oriented attitude
6 Specific workgroups for each sustainability theme with a consumer (not property) centred focus.
were responsible for developing innovative concepts.
Each workgroup had the responsibility to gain the
support of the future residents for their final plans.
| 63
Credits
› Hein Struben
image credits
dockside green in figures BPW prepared the master plan in 2005, adopting an
integrated design approach, which included a wide range Energy & Material
Total site area: 61.000 m2
of specialists in ecological design and engineering. From › Low embodied carbon and low-energy use buildings
Built area: 26 buildings › Eco-buildings with integrated rainwater management
Functional mix: 70% residential, the start a development and finance team coordinated › Maximize closed material cycles (for construction and use)
30% commercial roundtable meetings between all parties on how to best › Renewable energy generation on-site
› Separation of waste water flows and local wastewater treatment in
Income mix: 30% affordable housing achieve the vision set by Windmill.
natural landscapes
Population: 2.500 residents › Waste to energy plant and biogas production
D eve lo pe r
W i n d mill We st De ve l op me n t
! !
P ro j e c t D eve lo pe r
Dock side G r e e n L imite d
! !! ! !
L o c al G ove rn me n t
!
City of Victor ia ! ! ! !
Fu t u re O cc u pan t s !
the G r eate r Pub l ic
!
A rchitects & Mast e r P lan n e r
Busb y Pe r k in s + Will
F i n an c i n g
Van City
! !
F e d e ra t i o n o f Can adian M un icip al itie s
Key Mome n t s »
Ambitious ! and extensive goals are
! Concept demanded sustainability
innovation from developers,
set. Strong leadership helps build
commitment
! Local materials sourced extensively,
chosen to ‘work with ecosystem
! Biomass plant operated by new
micro-utility
including material use functions’ improves liveability and
! Deferring payment for land allows infrastructure performance ! Affordable living due to a variety of
! City makes results visible by for greater financial freedom in savings passed along to residents
demanding a public presentation development
!Phase 1 (Synergy) achieves LEED
Platinum certification, sells 85% of
Van City collaborates as a partner in Integrated design approach and $1 units in 3 hours
the new venture, providing ongoing million penalty committment among
support all parties created a united vision,
responsibility, and accountability
| 67
› A visionary plan, strong commitment, and an › Strict material selection and sourcing criteria
integrated and collaborative approach helped helped in attaining some of the highest LEED
to keep output high, while simultaneously certificates in the world. Multiple performance
embracing new and somewhat risky innovations. criteria were generated from the integrated
approach taken by developer teams, and
› Strict triple bottom line standards and pre- included regionally-sourced and ecosystem-
selection process laid the groundwork for appropriate materials.
serious, high-impact proposals, while effectively
filtering out greenwashing. › It is often the case that materials for
construction can be sourced from waste.
› The decision to force developers to make a Successful examples of material reclamation
public presentation helped make developers were included on the site, including using
accountable for their plans. In the case of sunken logs from a local reservoir. The project
Windmill’s winning proposal, the public gave a used recycled materials extensively.
standing ovation, garnering public support and
interest in the project. › Materials can serve many functions, and help
achieve important sustainability criteria. Exterior
› Up-front funding (75% provided by Van City) surfaces and materials were often required
and developer penalty commitments ($1 million to have a functional relationship with the
each) were effective financial instruments to ecosystem at Dockside. For example, integrated
ensure sustainability and innovation goals were grey water management was achieved through
achieved. Up-front investment helped tackle porous surfaces integrated with buildings.
bureaucratic hurdles specifically.
1 A clear vision from the outset, set by Windmill 1 Largely private financing, with the majority available
Developments in their project proposal. The vision early in the process allowed developers to sign off
and ambition were carried through effectively, quickly on bureaucratic and tasking processes (ie.
and developer teams remained committed to their LEED documentation).
individual responsibilities.
2 Leadership on behalf of the local government to
2 A public presentation that outlined the ambitious develop an ambitious redevelopment concept,
goals for redevelopment. This initial public support containing culturally inclusive public vision exercises.
fostered local interest and likely led to higher sales
3 A multi-phased planning program helped speed the
due to the demand.
return on investment. High performing buildings
3 Involvement of all required disciplines from the and clear savings for tenants kept demand very high
early phases of the masterplan development. The through subsequent phases
development team was made up of people that cover
4 Wide involvement of the public during the
all disciplines (energy, eco-building, water, waste,
development of the community plan further attracted
and urban planning). Teams intensively brainstormed
local interest and demand. Dockside is favorably
and workshopped different solutions to arrive at an
looked upon in Vancouver as an example of ‘new
optimal outcome.
urbanism’.
4 Strict triple bottom line criteria set by the city was an
5 High ambition for top sustainability performance led
effective instrument to filter through only “serious”
to the first ever LEED for Neighborhoods Platinum
parties that were committed to real sustainable
certification. The international media attention that
impact.
resulted was an excellent showcase for innovation.
5 Developers agreed to pay a $1 million penalty if
6 Investment in organizational capacity provided the
they did not achieve their goals. This created a
human resources infrastructure for an integrated and
performance-driven culture that embraced innovation.
collaborative approach. Investment in development
6 A clear value proposition is made for the homeowner and accounting staff were an important organisational
due to savings associated with eco-innovation. This element.
propelled Dockside through a real estate crisis (almost
all units sold before completion), and delivers a
compelling argument for the marriage of affordability
and sustainability.
| 69
karaikal pondicherry In figures technique.) Together, the designs for the homes covered a
comprehensive set of sustainability criteria. Energy & Materials
Total site area: 69.000 m2
› Focus on local or on-site material sourcing, processing, and
Houses: 909 construction
Website: karaikal.gov.in Post-disaster constraints made self-reliance an absolute › Materials should work with nature and withstand regional ecological
necessity going forward. Well over 100 artisans, professionals, pressures
and small businesses cooperated to fulfil the demands of
the story of karaikal pondicherry the project. A strong focus was placed on investing in local
The tsunami of December 26th, 2004 caused extensive knowledge and capacity building, including local youth placed
damage to the South and East coasts of India. The with professionals in training trajectories. When construction
immediate challenge in response to this disaster was to commenced the project faced many barriers. Contractors often
Ecosystems & Biodiversity
provide shelter to the affected population. The Swiss Red had insufficient financial capacity, and lacked skills for the
› Minimized ecosystem impact during reconstruction
Cross (SRC) and Initiatives in Development Support (IIDS) type and scale of construction necessary. This led to intensive › Design sanitation and waste services that reduce ecosystem stress
made a first appraisal of the damage. This appraisal served engagement with the contractors for training, planning and › Design Ecological buffer areas to protect community from recurring
management support. There were also a number of cases tsunamis
as a basis for the local government’s redevelopment plans.
where the difficult decision was made to reverse contracts,
The primary goals for reconstruction were: either in part or entirely. For future development projects
Karaikal Pondicherry is working with the local building centre
› Provision of a safe and sustainable habitat for 909
at Puvam to provide training to new entrepreneurs and
families, from 3 villages;
artisans. Culture & Economy
› Build the capacity of village communities to derive › Reconstruction of sustainable homes for 909 families
long term economic benefits, manage community From June 2005 to September 2008, 9 local contractors › Invest to build capacity for communities, individuals, and local
businesses to derive ongoing economic benefits
assets and apply knowledge on appropriate building completed 909 houses. Four contractors belong to Karaikal,
practices. while the others are from neighboring districts in Tamil Nadu.
In addition to the homes themselves, the project addresses the
The SRC coordinated the redevelopment effort amongst health and hygiene needs of the villages. INTACH Puducherry
supporting parties. It was decided from early on that set up a solid waste management system, which will be carried
the site plan would be developed in consultation with forward in the post reconstruction phase. Furthermore, the
the villagers. The SRC formed Village Reconstruction project established systems for long term management of the Health & Happiness
Committees (VRCs) which served to develop site plans and › Safe homes to protect against future ecological disasters
new assets, including a ‘Maintenance Cell’ which addressed
› Participation and co-development of community design and practices
house designs, taking into account culture, lifestyle, comfort necessary repairs and guides the process for house additions
and safety requirements in an iterative process. This was and expansions.
an additional layer on top of the primary goals of structural
safety, use of environmentally sound construction materials,
and technologies (such as fly ash based bricks and rat trap
| 71
for the SRC proposal VRC's formed focus groups, aiding design, Focused on building future capacity to manage
construction technology and services, operation and develop the district in the long run.
and maintenance, and negotiation with the
government infrastructure
P ro j e c t I mple me nt at i o n
Develop ment Alternatives, India
!
P ro j e c t D eve l o pe r/ Ove rs i g ht
Swiss Red Cross
! ! ! ! ! !
F ut ure Re s i de nt s
V i ll age Rec onstruc tion Committees
! !
Gove rnme nt
Government of Puduc herry
!
Co n t ra c t ors & S pe c i ali s t s
S KAT Swi t z er lan d (tec hnical bac k stopping )
! !
Lo cal M aterials suppliers
9 local c ontrac tors
KS M c onsultants ( arc hitec ts)
E P C c onsultants ( detailing )
Fi na nc i ng
Swiss Solidarity
! !
! SRC steers and manages projects covering ! Researching alternatives for construction ! VRC’s are are time intensive and iterative.
! The speed and timing of
the entire gamut of relief, rehabilitation technology and non-negotiable rules for Reconstruction projects should factor in reconstruction placed heavy
and development work technical performance engaged VRC’s for requirements at the inception stage pressure on local production
sourcing and spurred entrepreneurialism system for fly ash blocks
! in 3 villages are
909 families ! process had to address
Planning
Key M o m e nts » rehabilitated in safe habitat in a
sustainable manner, enhanced capacity
! Financial instruments in place (ie.
securiy deposit, conditions) ensured
the likely ecological impacts and
increased load on essential services and
! Drop in VRC committment during
construction because they didnt
of village communities to derive long performance goals for sustainability were infrastructure feel attached to the individual
term economic benefits addressed properly home
! Reconstruction heavily relied on local
! Speedy development of rehabilitation/ Demonstrating alternative technologies competency to address the immediate ! Goal Achieved: Embodied energy
reconstruction policies and guidelines and building materials facilitated capacity needs consumed by this development is
which incorporated experiences from adoption by beneficiaries 40% of conventional construction.
earlier disasters
Learning !adapted goals: Health and
! Materials sourced locally, and from
waste materials (ie. fly-ash bricks)
SRC organized a group-based strategy hygiene was designed and implemented
that reached out to the community as a key goal ! The overall financial arrangement
through village reconstruction facilitated the achievement of the main
committees (VRC) goals
| 73
› The project decided on a strategy to work › The project introduced appropriate alternatives
via village community representative groups. for construction technology and manufacturing.
These groups were comprised of traditional Local manufacturers and artisans also
Panchayats, the representatives of women, comprised the entire workforce. This allowed
disaster-affected groups, and minority for a number of benefits, including reduced
groups. This enhanced community ownership embodied energy in materials, local economic
towards the reconstruction process and their and social support, and reduced risk through the
participation in supervision of quality of supply chain.
construction.
› Families were exposed to alternative
› The project focused heavily on local job construction systems and building materials,
creation and skill development throughout when in the design phase of the homes. The
the reconstruction process. Almost 70 masons demonstration of these materials at the outset
working at local contractors have been trained aided the selection process and feeling of
and benefited from the opportunity offered by ownership over the final product.
the reconstruction process.
› A strong emphasis was laid on environmentally
› SRC designed a strategy to strengthen the friendly materials and construction
management capacities of local organisations. technologies. Waste from a nearby industrial
This strategy ensured their effective area was used for fly-ash brick production.
participation in the implementation, and also This was a three-fold success: introducing fly
enabled them to exercise their new capacities in ash blocks into the construction vocabulary of
future development work within the villages. the region, demonstrating high quality walling
materials using waste, and influencing the local
government and local users to incorporate and
promote the technology.
success Factors project management and the freedom to deal with up- Preconditions
front investment costs.
1 Speedy response to the initial tsunami by the Swiss 1 Openness and learning to an adapting situation.
Red Cross and the Initiatives in Development Support. Because post-disaster reconstruction efforts are
The comprehensive appraisal was vital in early plagued with unexpected variables, the capacity for
decision making by the government the team to recognize and quickly address problems
was key precondition for a successful process. For
2 The creation of quite strong (sometime non-
example, material sourcing, manufacturing, and
negotiable) guidelines and policies by the government
sanitation capacity were all successfully addressed
incorporated learning from previous reconstruction
mid-process.
efforts. These guidelines put sustainability criteria in
the forefront, and allocated clear leadership over the 2 A clear leadership structure and excellent
entire process. communication through the entire process is critical.
The SRC effectively oversaw the entire process of
3 The initial goal to invest in local resources, assets,
relief, rehabilitation, and development work, and
and labour force was key in assisting local economic
strictly monitored the performance of construction -
recovery, building public support, and exploiting
often times cutting back on the scope of projects to
local ‘know-how’. Job creation and practical skill
ensure quality.
development will likely create a positive impact well
after the construction of the district. 3 The support and participation of the community was
a precursor to a successful process. VRC members
4 The decision to found Village Reconstruction
took ownership of reconstruction, and assisted with
Committees (VRCs) was instrumental in gaining broad
a number of design and planning elements. The
public support, and ensured that the design and
imparted local knowledge was a key instrument for a
planning phases appropriately addressed social and
smooth process, but such organized participation also
cultural sensitivities.
empowerd citizens with ownership in the project.
5 Investment in local manufacturing capacity and
4 Training was provided to local youth in building trades
regionally appropriate materials cut out the need for
such as painting, plumbing, and electrical works.
logistics operations tied to importing. Not only was
Working placement programs allowed 18 youth to
this critical in reducing risks and costs, but helped
work and learn directly with contractors.
boost the local economy and cut-out the embodied
energy associated with the transport of materials.
Credits
› Babette Pfander (Swiss Red Cross)
› Amitabh Sharma (Swiss Red Cross)
image credits
› Swiss Red Cross
› Skat
› Development Alternatives
sonoma mountain village In figures › Analysis and assessment, including both state
sanctioned reports and private studies to maximize Energy & Materials
Total site area: 81.000 m2
› Renewable Energy on-site
Houses: 1.500 One Planet goals. › Zero carbon operations in use-phase
Projected population: 5.000 › Reduction or elimination of waste in construction
The City Council approved the Environmental Impact › Maximum use of reclaimed, re-used materials
Commercial area: 77.000 m2 › Maximum on-site material manufacturing with renewable energy
Website: sonomamountainvillage.com Report, General Plan Amendment, and certified the
Development Agreement for Sonoma Mountain Village.
the story of sonoma mountain village
A substantial emphasis was placed on on-site
Sonoma Mountain Village (SOMO) exists on a 175 acre
manufacturing and retrofitting instead of new-build. Ecosystems & Biodiversity
property formerly owned by Hewlett-Packard and Agilent.
Codding construction manufactures high quality steel- › Exceed storm water runoff standards
Codding Enterprises initialized the project with the intent of
frame construction on-site, powered by renewable energy, › Intelligent use of grey water
providing solar power to the neighboring community. Two › Minimum 50% reduction in drinking water use in all retrofitted
and a successful material recovery program contributed
phases of PV arrays were installed over two years. During spaces relative to national Energy Policy Act of 19923 by reducing
both structural and hardware components. wasted water
this time, SOMO was approached by Bioregional North › Offsite conservation to mitigate development footprint
America in order to develop a “One Planet Action Plan” for › Integrate biodiversity into the urban areas
Despite being struck hard by the real-estate crisis in
the community. The concept envisions 1,900 homes and
California, Codding established a non-profit green business
significant retail, commercial and office space. The plan
incubator (Sonoma Mountain Business Cluster) with goals
also lays out environmental goals, including 100% heat, Culture & Economy
to assist over 100 startups to create 2,000+ jobs. 358,000
electricity, cooling, and lighting from on site renewable
square feet of buildings have undergone retrofit, and › Maximize sustainable transport
energy sources. Social goals were key for Codding, and this › Maximize local food production and sales in community
342,000 square feet still to be renovated. › Create a community oriented culture
was reflected in extensive public involvement through the
› Provide a One Planet Center on the Town Square
development process. › Establish non-profit green business incubator
At this time, Sonoma Mountain Village functions primarily
› Assist 100+ startups to create 2,000+ jobs
as a business park with some 700+ workers on site. › 25% affordable housing, exceeding municipal requirements
Planning was quick to start, mostly thanks to funding
Construction of the entire community is expected to finish › 4,400 new jobs
provided privately by Codding. Planning concepts
in 2025.
developed quickly and resulted in a number of key
developments:
› A Standard Construction Specification guide, showing Health & Happiness
how tenants can improve and outfit their properties. › EcoTrails program, fitness infrastructure
› Provide services and facilities on site that meet local needs
› Legislative activism, appealing for exemption or › Integrate health infrastructure into the design
modifications to state policies perceived as barriers › Create facilities for all age groups, including teenagers
to development.
| 77
P ro j ec t Devel o p e r / O ve rsig h t
Cod d in g En t e r p r ise s
!! !! ! ! !
Fu t ure O ccup an ts
R e sid e n t g r oup s
!
G ove r n me n t
Sta t e of Ca l ifor n ia
F in an cin g ! ! ! ! ! !
Cod d in g En t e r p r ise s
Pr iva t e source s
! to install 1 PV array to
Commitment ! Broad public support and collaboration Trained entire design and construction
! 30 tons of asphalt and
power the community on living plan team on green building and LEED gives concrete were reused in LEED-CI
key learning to the team Platinum retrofit.
! Private Capital helps give sustainability a ! Material performance analysis evaluates
Real! Estate bubble hits California hard.
Key Moments » primary focus sustainability broadly
Delays building, slows progress on
!
Engage architects to better
understand and optimize the
!1.14 MW PV Installed on November Standard metering plan for tenants sustainability targets package of low-energy materials
encourages responsibility from public.
BioRegional expands Codding’s focus on
sustainability to include broader goals
Highly engaging community workshops
address sustainability issues. (Schools
! Extensive material inventory program
is a key success: includes structural
! Goal Achieved: 97% reduction
in construction waste, currently
Comprehensive sustainability goals set, invited to present steel, insulation, piping, and hardware manufacturing 20% of materials
incl. LEED!Platinum standard components on site in a solar powered factory
! Design out waste: recycling materials,
prefab walls built onsite. (75%
Construction waste reduction minimum,
! Prefab Steel frame system used for
retrofitting (uses 40% of standard
25% affordable housing,
! exceeding municipal requirements
90% min over time) construction
| 79
› Early involvement of residents was not only a › Resourcefulness in regard to material use was
successful strategy for continued engagement a central philosophy, from sourcing, through
and community cohesion, but it also attracted manufacturing, construction, and usage.
tourism. SOMO has been established as a major
green destination in Sonoma County, with 3-5 › Prefabricated structural components allowed for
events each week at the existing Event Center rapid construction.
that deal with environmental themes (last year
› A strong re-use policy, and a focus on
alone, 200 events).
optimizing on-site manufacturing techniques
› On-site production and assembly of modular led to an extremely high reduction of job site
components for construction significantly waste. This also allowed developers to save
reduced the embodied carbon in materials, due money in the construction process.
to the already-installed PV. Codding happens
to own the largest biodiesel production plant
in California, which has been able to provide
fuel for construction vehicles, further lowering
embodied carbon.
1 Collaboration with BioRegional facilitated a broader 1 Private financing and private development (using in-
approach to ‘sustainable community development’ house expertise in development and construction) by
and set a number of exciting goals that motivated the Codding was key to developing quickly.
community and developers.
2 An open and engaging community process to
2 Open involvement of the community through determine community planning and overcome
workshops. Often creative approaches were taken to sustainability problems. Encouraging a learning
“rethink” problems and develop solutions. This was process and early involvement of residents resulted in
critical in maintaining support high participation and support throughout the process.
3 Codding adopted a type of “developer advocacy” to 3 The range and depth of Codding’s “developer
lobby to amend or earn exemption from planning advocacy” philosophy has had impressive results in
legislation. This helps set precedents and build paving the way for greater change in two ways:
political support on a larger scale.
› Lobbying and engaging both nationally and locally to
4 Strong focus and execution on on-site manufacturing, amend laws that block sustainable development, and;
retrofitting, waste recovery allows resources to be
used intelligently. › Encourage them to reduce the impact of public
operations (ie. shared services and infrastructure that
5 Sustainability Performance Analysis for building individuals cannot influence)
materials helps determine the most appropriate
material for the construction application. 4 The early creation of the Standard Construction
Specification guide was key in achieving goals later
6 The first use inventory of reclaimed materials has
in the construction phase. Designers and builders
been a huge success, with the majority of reclaimed
followed the guide, which required that reclaimed
materials already re-used in the retrofit of the existing
materials from on-site sources were to be used first,
buildings. For example, 30 tons of asphalt and
as well as easily recyclable materials. This program
concrete were reused as part of the LEED-CI Platinum
has been successful, such that the inventory has been
retrofit.
largely used up in retrofitting the existing buildings.
7 Codding continues to work with architects to design
model homes that can be used in planning and
permitting, and allow Codding to better understand
the package of low-energy materials that need to be
used.
| 81
Credits
› Geoffrey Syphers (Codding Enterprises)
image credits
› One Planet Communities
Hammarby Sjöstad in Figures It provides an elegant solution for integrating the local
municipal solid waste and wastewater management system Energy & Material
Site area: 200 hectares
to generate electricity, heat, and cooling for Hammarby › Heating supply based on waste to energy or renewable energy
Houses: 11000 houses, 46% rentals › Green electricity from grid
Commercial space: 20 hectares Sjöstad. The City of Stockholm did not win the Olympic › Residents will produce 50% of own energy needs
People: 25.000 bid, but enough momentum for Hammarby Sjöstad was › 100 liters water consumption per person per day
› 95% reuse of phosphorus in wastewater on agricultural land
Website: hammarbysjostad.se generated for the project to continue.
› 15% domestic waste reduction
› Maximum 10% construction waste to landfill
At the moment there are some 9.000 houses built. The
The Story of Hammarby SJöstad construction costs of the houses were 5% higher due to
The Hammarby Sjöstad development is situated on the environmental program, but the market value of houses
the south side of Hammarby Lake near the city centre Ecosystems & Biodiversity
was 15-20% higher. The remaining houses and construction
of Stockholm. The project redeveloped a brown-field › Sanitary redevelopment and reuse of old brown-field sites into
activities are scheduled for completion towards the end of beautiful parks and green public spaces
industrial location to a compact mixed use neighborhood 2017. › Development of green public spaces is compensated in the form of
that expands the inner city across the water. In 1996 the biotopes that benefit the biological diversity in the immediate area
› Natural areas of particular value shall be protected from
first plans to develop the area were made by the City of development
Stockholm.
Stockholm’s bid for the 2004 Olympic Games was an Health & Happiness
important catalyst for the environmental program in › Minimum of 15m² of courtyard space and a total of 25–30m² of
courtyard space and park area within 300m of every apartment.
Hammarby Sjöstad. The national and local environmental › Minimum of 15 % of the courtyard space shall be sunlit for at least
policy targets were augmented and included an ambitious 4–5 hours at the spring and autumn equinoxes.
“eco-cycle” model for local sustainable resource use. The › Glass House citizen information, education and encouragement
Strategic Master Plan and Athens wins 2004 Olympic Bid over
Hammerby Sjöstad inspired by idea environmental program "Twice as Stockholm (1997)
to develop North Bank of Hammarby Good" developed (1996) First houses in "Sickla Udde" sub- Sub-districts Sickla Udde, Sickla Kaj
Lake (1990) Olympic facillities removed to create district ready (2001) and Sickla Kanal fully developed
First proposal "circulair metabolism" full mixed-used neighborhood plan (2007)
City Planning Bureau presents first (1996) (1997) Start construction on other sub-
detailed local area development plan districts (2002) Environmental Load Profile for
for Hammarby Sjöstad (1991) Joint planning and design process "Right-green" municipal government sub-districts Sickla Udde, Sickla Kaj,
"parallel sketching" starts (1996) elected (1998) GlasHusEtt opens (2002) Lugnet and Proppen (2008)
"Left-green" municipal government
elected (1994) Environmental Load Profile tool tracks Start construction on "Sickla Udde" "Left-green" municipal government Evaluation environmental load profile
P ro ce ss D e s c r i p t i o n » progress "Twice as Good" (1997) sub-district (1999) elected (2002) Hammarby Sjöstad (2008)
Stockholm Olympic Bid proposes
Hammarby Sjöstad as Olympic Village Second proposal "circulair Application of Environmental Load Regular progress meetings for Sjöstadens Homestead Association
(1995) metabolism" accepted (1997) Profile tool (1999) residents (2004) (SHA) formed (2010)
D eve l o p e rs
T ea m s o f a rc h i t e c t s & d e v e l o p e r s
! ! !
F u t u re O cc u p a n t s
Residents
! ! !
Building Owners
G ove r n m e n t
C i t y o f St o c k h o l m
! ! ! ! !! ! ! ! !
C i t y P l a n n i n g B u r ea u
R ea l E s ta t e a n d P u b l i c W o r k A d m i n i s t ra t i o n
E n v i r o n m e n ta l A d m i n i s t ra t i o n
I n f ra s t r u c t u re & U t i l i t i e s ( P u b l i c )
St o c k h o l m T ra n s p o r t
St o c k h o l m Wa t e r A B
St o c k h o l m E n e r g y A B ( B i r ka E n e r g y )
!
S K A FA B wa s t e t r ea t m e n t
Co n s u l t a n t s & S p e c i a l i s t s
Grondmij
R o ya l I n s t i t u t e o f T e c h n o l o g y
Strong coordinating and management Infrastructure companies maintain Suppliers and contractors selected Politics: lowered social housing share
! role City (1991) ! momentum despite loosing Olympic ! based on material and construction ! parking spaces (2002)
and more
Bid (1997) procurement policies (1998)
Leasehold land system allows City Survey: Residents attracted
! to lead planning and design process Infrastructure companies collaborate Detailed design codes ensure high ! to aesthetics and less for the
Key M o m e n t s » (1991) for "circular metabolism" (1997) ! qulaity translation of masterplan environmental aspects (2005)
(1999)
!
Olympic bid inspires ambitious
environmental targets (1996) ! High environmental ambitions
maintained after Olympic bids (1997) Environmental targets not all reached
Energy targets adjusted from 100 kWh/
m2 to! 60 kWh/m2 due to cost (2005)
! in "Sikkla Udde" but seen as important
Key stakeholders particpate "parallel Decreased political interest: Less firts step (2001) Energy targets adjusted for new
sketching" process (1996) ! control on land sale and energy
public !
buildings from 100 kWh/m2 to 60
targets (1998) GlasHusEtt central to support kWh/m2 (2009)
Stakeholder participation and ! residents in environmental lifestyle
! confidence through familiarity
"parrallel sketching" process (1996)
Minimum leverage with developers to
! environmental targets (1998)
secure
(2002)
! GlasHusEtt residential point for
government lobbying (2010)
| 85
Credits
› Stellan Fryxell
Architect & partner, Tengbom Architects
› Björn Cederquist
Project Manager Social City, Stockholm City
image credits
› Björn Lofterud
› Malena Karlsson
Co n s t r u c t i o n
C h i n a Sta t e C o n s t r u c t i o n E n g i n e e r i n g C o r p o ra t i o n !
P ro j e c t D eve l o p e r / O ve rs i g h t
CMPD
! ! ! ! !
F u t u re Re s i d e n t s
Residents !
G ove r n m e n t
C i t y G ov e r n m e n t G u a n gz h o u ! ! !
A rc h i t e c t s & U r b a n P l a n n e rs
JEMER & Guangdong Design Institute (Master planner) !
A EC O M ( La n d s ca p e r )
H a n h u a A rc h i t e c t s
E x t e r n a l Ad v i s o rs
Ts i n g h u a U n i v e r s i t y ( A c h i t e c t u r e I n s t i t u t e )
! !
BioRegional
DHV
› When including a broad set of sustainability goals › The decision to select or to exclude certain
for a district, it will be important to involve all key construction materials is often made part of the
stakeholders at the start of the design phase. A design process. Material suppliers can support
collective exploration and discussion on all the this selection process by participating earlier
project ambitions and approach will stimulate a in the development process and by catering
greater understanding for the project, and allows to the information needs of the stakeholders
potential bottlenecks and their solutions to be participating in the design process.
identified early on in the process.
› Project developers often make use of
› Monitoring is an essential activity to track and point-based methods or rating schemes
ensure best possible performance in each stage for sustainable design and construction.
of development. Much of the sustainability Constructors can select their own materials
goals are achieved in the construction and use as long as they achieve the desired
phase, and often by stakeholders external to the performance standard. Material suppliers have
organization in charge of the project. This creates an opportunity here to align their offer of
performance risks as they may not prioritize the materials and information on materials to these
project ambitions due to lack of legal leverage, performance standards, facilitating the choice
lack of ownership, or other economic reasons. process for project developers.
Monitoring helps safeguard the original design
criteria.
Success Factors appointed project managers for each of the ten One Preconditions
Planet Living principles, improving coordination on
1 A broad range of public and private stakeholders the different sustainability aspects of the project. 1 Strong drive for sustainability
participated in a joint design workshop to develop The establishment of a company-wide sustainability
2 The willingness of stakeholders to explore and learn
the sustainability ambitions and solutions for Jinshan. department based on these managers is a further sign
beyond what they are accustomed to.
Central to the workshop was the discussion and of the learning mindset the CMPD adopted in Jinshan.
exploration of the 10 One Planet Living principles. This 3 Sufficient project financing to pursue and implement
helped spread knowledge on sustainability, identify sustainability solutions
knowledge gaps, and created shared understanding of
the project goals. The outcomes of the workshop were
translated into a sustainability action plan and finally
used as basis for the urban master plan.
Menlyn Maine in Figures first 5 green start certified building. The Epsilon building
followed in 2012 with 4 green stars. Energy & Material
Total site area: 165.000 m2
› Low carbon, low energy buildings and road map toward carbon
Floor space: 307,000 m2 negative impact
Residential area: 85.000 m2 A long-term relationship between Menlyn Maine and WBHO › Green Star Buildings 4 stars or higher “by design” and “as build”
Commercial area: 40.000 m2 construction was initiated to allow a mutual investment › Local sourcing of material
in the learning process to enable high-level sustainable › Waste management and recycling programs
Retail area: 30.000 m2 › Water saving and grey water systems
Community space: 10.000 m2 parklands building. Together with highly qualified design teams › Preparations are made for application of renewable energy (solar and
Urban farms: 800 m2 on roof top (called ‘the A-teams’) Menlyn Maine managed to lower wind) in the next 5 to 10 years.
P ro p e r t y A ss o c i a t i o n
M e n ly n M a i n e P r o p e r t y O w n e r ' s A s s o c i a t i o n
! !
A rc h i t e c t s
B o o g e r t m a n & Pa r t n e r s ( O ffi c e s & R e ta i l )
G L H & A s s o c i a t e s A rc h i t e c t s ( R e s i d e n t i a l )
P ro j e c t D eve l o p e r / O ve rs i g h t
M e n ly n M a i n e I n v e s t m e n t H o l d i n g
F u t u re O cc u p a n t s ! ! !! ! ! ! !
Nedbank (Building Owner)
Sage VIP (Building Owner)
Professional tenants
Fu t u r e r e s i d e n t s
G ove r n m e n t
L o ca l G ov e r n m e n t
NGOs
Climate Positive Foundation
G r e e n B u i l d i n g C o u n c i l S o u t h A f r i ca
Co n t ra c t o rs !
W B H O C o n s t r u c t i o n ( M a i n c o n t ra c t o r )
P e n ta d Q u a n t i t y S u r v e y o r s ( S u r v e y o r )
Ra w l i n s Wa l e s & Pa r t n e r s ( El e c t r i ca l )
C 3 C o n s u l t i n g ( M e c h a n i ca l )
!
I n f ra s t r u c t u re a n d U t i l i t i e s
Municipal utlities !
Energy companies
E x t e r n a l Ad v i s o rs
W S P G r e e n b y D e s i g n ( S u s ta i n a b i l i t y )
S o l i d G r e e n ( S u s ta i n a b i l i t y )
G o l d e r & A s s o c i a t e s A f r i ca ( e n v i r o n m e n ta l )
Ca i r n m ea d ( S a f e t y )
CKR Consulting Engineers (wet services)
T WC E C o n s u l t i n g E n g i n e e r s ( fi r e s a f e t y )
!
I n t e r d e s i g n / I n s i g h t ( La n d s ca p e r s )
Financing
P r i va t e I n v e s t o r s
› Sustainable building concepts with high › Applying sustainability goals initially required
certification standards can have commercially perseverance and commitment. As projects
attractive propositions for end-users. evolve the desire to raise the level of
sustainability seems to grow. This triggers new
› Architects and contractors need to go
and more stringent demands on all materials
through a learning phase together, to enable
used. As the bar is being raised, more and more
them to design cheaper buildings with high
materials and installations will be evaluated on
sustainability performance.
different aspects of sustainability, for instance:
› A hands-on approach to check out new materials locally sourced, ability to recycle, optimal
and building concepts in practice will enable composition (e.g. of cement), etc.
high performance standards and lower the risk
in the development phase. › In big projects the main contractor is
responsible for finding and selecting
› Performance warranties of sustainable materials subcontractors. The main contractor will select
(such as the endurance of paints) challenge and determine how and where the actual
suppliers to deliver sustainable products. materials are being sourced.
Performance guarantees result in lower risk for
the project developer, making it more attractive › Local presence in demonstration projects and
to apply innovative sustainable solutions. having local dealers present with a solid track
record is key to implementing in a developing
› Involvement of the Green Building Council and
market. The most convincing way to “sell” new
sustainability experts speed up the learning
concepts is to invite people to come and see
process of the design teams.
the actual application with their own eyes.
› The advantages of sustainable development
proved to be beneficial. It triggered the › A learning process is required to become
development team to raise its own goals for sustainable with minimal extra up-front costs.
sustainability. In the process the motivation and New materials, installations, and proper design
the willingness to invest in high performance of sustainable buildings require experience
levels grew. and practice. The learning-curve is a crucial
process that architects, project developers, and
› The slow-down in the real estate market
construction companies have to go through.
also affected Menlyn Main which made it
Suppliers can cater to this need by providing
more difficult to operate the buildings to full
high quality training.
economic capacity. However, Menlyn Maine
managed to outperform the market due to its
sustainable image.
Key Success Factors achievements and want to outperform the market. 2 Flexible urban planning and adapting design to meet
Moreover, the mutual long-term commitment allowed local market demands requires the willingness to
1 Menlyn Maine Investment Holdings considers itself both companies to invest time in their learning curve enter into long approval processes from the local
fortunate to have strong support from investors for the to optimise the way they design and build. This way government each time the plan is adjusted.
sustainability goals. This support only grew stronger as they managed to significantly lower the up-front cost
3 There needs to be good relationships and trust
the project evolved and the multiple benefits became to build sustainably.
among investors, project developers, architects and
even more apparent.
6 Guidelines and regulation, together with as-early-as- contractors. They need to allow each other time to
2 In South Africa this development is one of the leading possible involvement of future residents, building learn and they need to work together to collectively
sustainability developments. Even worldwide the owners and tenants ensures that the sustainability build smart and deliver sustainable buildings at
project's certification standards and participation in goals are adopted in the usage phase. commercially competitive prices ranges.
the Clinton Climate Initiative attract special attention.
7 Different design team are formed for residential areas 4 Good project management also deals with getting the
This also attracts experienced and highly qualified
and retail / office areas. right parties and qualities in the project team. This
professionals that can and want to deliver projects
requires an open attitude that recognizes the need to
that are on the forefront of the sustainable building 8 Objectives are set relative to the current and future
involve experts that may change the way companies
market. viability of certain technologies. At the moment,
would build normally.
renewable energy is not commercially viable in
3 The ambitious goals set the project apart and attracts
South Africa because the energy prices are too low. 5 All parties need to subscribe to maintaining the
parties interested in high-level sustainable building.
However, the design of the buildings take future increased sustainability goals. They need to be
Increased focus and demand for sustainable buildings
implementation of PV arrays into consideration. 40% adopted to all aspects of the building, from building
together with clever design and good management led
of the roof space is reserved for solar and/or wind materials such as concrete, wood, insulation, paints,
to Menlyn Maine overcoming commercial challenges
power. Menlyn also developed a strategy to actively waste management, all the way into the operational
when delivered, and into the foreseeable future.
monitor investment opportunities in solar and wind phase of the building.
Although the real estate market has slowed down,
power to offset the energy use in the near future.
Menlyn Maine visibly outperforms the market. 6 Parties need to be able to not just copy design
These options are laid out in a road map delivered in
choices, but really adapt the plan to local conditions
4 Menlyn Maine organized strong teams and added 2014 to the Clinton Foundation.
and demands.
specific knowledge from the Green Building Council
in South Africa and other sustainability consultants. 7 The local market needs to develop a demand for
Using (mainly) proven technologies enabled high
Preconditions
sustainable buildings. There need to be enough local
performance building at minimal risk. suppliers and buyers / tenants with a specific interest
1 Investors for this project were convicted that
in sustainability.
5 Developing a good and long-term relationship for the sustainable buildings, despite higher initial costs,
entire development with the main contractor proved result in commercially viable and even more attractive
productive. Both companies pride themselves in their business cases.
| 99
Credits
› Jurgens van Huyssteen (project developer, Menlyn
Main)
image credits
› Menlyn Maine
› www.fgprop.co.za
› www.easterntimes.co.za
Greenwich Peninsula in Figures Village Ltd and Meridian Delta Ltd as private development
partners for GMV and Meridian Delta site respectively. Energy & Material
Site area: 121 hectares
Their challenge was to establish a new and ambitious › Codes for Sustainable Homes level 4 or better
Built surface area: 78 hectares › Building for Life Standard; London Housing Design Standards
New homes: 13.000; sustainability standard for urban development on an › BREEAM “very good” or better
~ 32% affordable housing isolated brown-field site. This proved to be difficult for the › 80% reduction in primary energy consumption (GMV)
› 50% reduction in embodied energy (GMV)
Commercial & office space: 38 hectares first two phases of GMV in particular.
› 50% reduction in construction waste (GMV)
Projected population: 30.000 › 30% reduction in water use (GMV)
Most of the originally proposed sustainability goals were
Website: www.gmv.gb.com
reconsidered due to high expected costs, resulting in
lowered performance targets and use of traditional on-site
The story of Greenwich Peninsula construction over novel standardized off-site construction
Ecosystems & Biodiversity
› Regeneration of local area
The Greenwich Peninsula development is located on techniques. Despite these initial difficulties the project is › Protect and enhance local environment capital
the river Thames in the London Borough of Greenwich. now well on its the way to achieve its sustainability targets, › Public gardens and connected greenways between neighborhoods
The project is one of the major regeneration projects and in addition, successfully managed to push national
in the United Kingdom, redeveloping what was once policy to adopt ambitious sustainable design criteria for all
Europe’s largest gasworks site into a dense mixed-use new urban developments.
neighborhood. The plan for the area was initiated in 1997
by former Deputy Prime Minister John Prescott, who Greenwich Millennium Village and the Meridian Delta
asked English Partnerships, the government’s national site are expected to be completed in 2015 and 2035 Culture & Economy
regeneration agency, to carry out the project. respectively. › 30% reduction in construction costs (GMV)
› 25% reduction in construction time (GMV)
› Affordable housing
The Peninsula master plan is designed by a high profile and › Mixed use community
multi-disciplinary team lead by Richard Rogers Partnership. › Mixed income community
It includes two main areas: the Greenwich Millennium
Village (GMV) to the south, and the Meridian Delta site
to the north. The designs focus on creating a high quality
modern mixed-use urban community. The project aims for
a level four or higher of the Code for Sustainable Homes Health & Happiness
and a BREEAM rating of “very good” or “excellent” for non- › Public green
› Greenways for cyclists and pedestrians
residential units. As part of the Millennium Communities
Program, the design for GMV emphasized sustainability in
particular.
Engineering
W S At k i n s
JPM Consulting
H o a r e L ea
P ro j e c t D eve l o p e r
G r e e n w i c h M i ll e n i u m V i ll a g e LT D ! ! ! ! ! !
M e r i d i a n D e l ta Lt d
A n s c h u t z E n t e r ta i n m e n t G r o u p Eu r o p e
F u t u re O cc u p a n t s
Aggregates processing wharf
Residents ! !
G r e e n w i c h M i ll e n n i u m V i ll a g e M a n a g e m e n t Lt d
G ove r n m e n t
E n g l i s h Pa r t n e r s h i p s
!! ! !
London Borough of Greenwich
D e p a r t m e n t f o r c o m m u n i t i e s a n d l o ca l g ov e r n m e n t
A rc h i t e c t s & U r b a n P l a n n e rs
H u n t T h o m p s o n A s s o c i a t e s ( G MV )
Ra l p h E r s k i n e / T ova t t A rc h i t e c t s ( G MV )
J e s t i c o & W i l e s ( G MV )
N i c h o l a s P ea r s o n A s s o c i a t e s ( G MV )
T e r r y Fa r r e ll a n d Pa r t n e r s ( M D )
R i c h a r d R o g e r s Pa r t n e r s h i p ( M D )
D e s v i g n e & D a l n o k y ( La n d s ca p i n g )
E x t e r n a l Ad v i s o rs
T r u s t f o r U r b a n Ec o l o g y
!
Sustainability criteria for GMV "Code for Sustainable Homes" level 4
included !in contractual agreement ! GMV Management Limited
established for the long-term
!
included in contractual agreements
Consultation events with residents
GMV for input in design phase III, IV
with developers (1997) management of community (2000) (2006) & V (2011)
Key stakeholder team worked TRUE takes over management of National policy inspired to adopt Local heat system GMV supports
together on development masterplan ! Greenwich Ecology Park (2002)
! higher sustainability criteria (2006) !collective management and
Greenwich Peninsula (1997) community organisation (2011)
Key M o m e n t s » Large service costs in GMV due Aggregates processing wharf legally
! planning application GMV
Originally proposed sustainability ! opposed
!
performance targets adjusted or
to not properly functioning novel
cladding and building facades due to noise levels (2007) ! Financial investment by Knight
Dragon in Meridan Delta Limited
omitted due to expected costs (1998) (2002) ensures continued development
› Involving key stakeholders in the design process › There are significant financial and performance
helps ensure that sustainability goals are risks involved when applying new building
realistic and supported. This reduces the risk of materials and techniques, such as the novel
them being diluted or omitted in subsequent cladding and building facades used in GMV.
phases due to financial reasons or lack of know- Reducing these risks requires testing and local
how. know-how on how to apply such innovations.
Suppliers can influence the successful
› Including “performance provisions” into implementation of new construction techniques
contractual agreements with developers and new materials by providing better technical
provided leverage for project initiators to guidelines and parameters on their proper use.
adjust the level of sustainability performance
for each new planning application. This creates › The “Code for Sustainable Homes” design guide
opportunity to ensure that sustainability targets was central to the Greenwich Peninsula project.
will reflect new advances and regulatory In the standard there is space for construction
standards that come into effect. companies to select the materials they think
appropriate to reach the desired performance
› The phased development of Greenwich level. Materials suppliers can facilitate this
Millennium Village created space for the selection process by providing detailed and
developers to organize consultation events comparable information and by aligning their
with the residents. This allowed them to offer of materials to the required performance
collect valuable feedback on the design and levels.
implementation process. Planning for and
capturing such “learning” is therefore essential
for achieving the best results.
Masdar City In figures Many international parties and partners were attracted to
develop Masdar. And, many more will be involved as the Energy & Material
Total planned area: 600 hectares
development is planned to continue up to 2025. In turn, › 30% less embodied energy in materials (550 kg CO2 / m2)
Residential area: 6.000 m2 › >50% less energy use compared to BAU (i.e. passive design, high-
Commercial: 1.500 businesses Masdar is now providing consultancy services to enable efficiency appliances, shading to minimize air-conditioning needs).
Retail space: 250 m2 sustainable development in other regions. › Renewable energy production: 75% hot water, near 100%
renewable electricity. Solar (130 MW), CSP (in exploration), wind
Community space: 1.000 m2 farms, (20 MW), geothermal and there are plans for a hydrogen
Projected population: 45.000 The first six buildings of the Masdar Institute of Science and power plant.
Projected communters: 50.000 Technology campus are completed and fully operational. › 60% water reduction (80% recycling and reuse) low-flow showers,
a water tariff, smart water meters, grey-water for crop irrigation and
Website: www.masdar.ue They include three residential buildings, classrooms, two other purposes).
laboratory buildings and a Knowledge Centre – a total › Recycled materials and waste reduction: attempt to go to zero-
of 35,000 m2 of gross floor area. Students live in the waste. Biological waste to create nutrient-rich soil and fertiliser,
some may be incinerated as an additional power source.
The story of Masdar City on-campus housing within Masdar City. There are retail, › Efficient logistics, minimal need for transport through mixed
Masdar means “the source” in Arabic and refers to Masdar services and food and beverage outlets and Masdar City functions and low carbon transport (personal rapid transit).
the company, including Masdar City. The development hosts a monthly organic farmers market and street fair from
of Masdar is initiated by the Abu Dhabi government to April to October every year.
create economic diversification and knowledge-economy
Construction of the second phase of Masdar Institute is Ecosystems & Biodiversity
jobs. Masdar City is designed and operated to provide
ongoing was set to be completed by the middle of 2014; › Preserve local wild life and local vegetation
the highest quality of life with the lowest environmental › Biodiversity protection area
footprint – all in a manner that is commercially viable. the 10,000 m2 Courtyard Building, which will be the first › Treated waste-water that is recycled for plant irrigation ensures water
Masdar is designed to be the source of many things commercial building in the city, is handed over by mid-2014, conservation
including knowledge, innovation and human capital while the 23,100 m2 Siemens Middle East Headquarters
development in the areas of renewable energy and clean Building was completed by the end of 2013. These present
technologies. three projects that tripled the size of the city, from 35,000 Culture & Economy
m2 to approximately 110,000 m2 by the end of 2014. › Diversify Abu Dhabi’s economy
› Business innovation hub for renewable energy, sustainable
The development started in 2006 when the Abu Dhabi innovation & education
government and Mubadala (a 100% government owned At full build-out by 2025, the city is expected to have › Local procurement
40,000 residents and 50,000 commuters. › Develop the UAE local market and impact other projects through the
company) created the subsidiary Masdar that consists of development of local regulations for sustainable building.
four business units (Masdar City, Masdar Capital, Clean
Tech and the Masdar Institute of Technology and Science).
The goal of the development is to create a internationally Health & Happiness
leading clean-tech hub for renewable energy and › Maximize quality of live while minimizing environmental impact
› Healthy buildings with air quality monitoring
sustainable living. › High quality living and working environment
› Less and clean-tech commuting
| 107
Co ns tr uc ti o n
Al H ac Madi a ( Contra ctor P h ase 1 ) !
Arabi Constru cti on Company
A lfara a
! !
F uture Res i dents
Masdar I nsti tu te
Si emens
!! !
Re s idents & Ca mpu s stu dents
Gover nm ent !
UA E
A bu Dh a bi
E ng i neer i ng
Mo t t MacD o n ald (E n gineeri ng & env i ronmental)
Am an a Wallbri dg e ( pre-constru cti on)
Mas d ar In s t it ut e of Sci ence & tech nolog y
First investment capital for development Additional capital in clean-tech fund via Masdar Energy design guidelines (MEDG) - 100% sustainably sourced timber
! of a new innovation hub with mixed-use. ! Consensus Business Group, Credit Suisse ! encompass supply chain impact and !- 90% recycled-content
and Siemens Venture Capital. serve as a mandatory framework for aluminium used for the inner
Strategic goals and development coordi- designing energy-efficient buildings. façade
nated with Abu Dhabi Executive Council. Dust from construction activities require - 30-40% lower carbon footprint
!
measures to secure air quality.
Initial goals are set to create innovation !Masdar Insitute moves in first
operational building the first tenant.
concrete applied
- Water-based paints that have no
hub with! mixed use, providing the Due to the impact of the financial crisis volatile organic compound, which - harm
Key M om e nt s » highest quality of life with the lowest en- ! 1 is delayed to be completed in
phase Strategic partnership with Siemens and human health
vironmental footprint. Zero Carbon, Zero 2015. The final completion is scheduled ! Mitsubushi for long-term commitment. - Reinforcing bars made of 100%
Waste, car free city and energy positive. to occur between 2020 and 2025. recycled steel.
The Future Build tool assists architects,
Attract and make inventory of needs of IRENA chooses Masdar as the location for ! engineers and contractors in identifying Siemens Building (LEED
strategic partners and future occupants !its headquarters. and sourcing building products and ! Platinum & Pearl 3 standard)
(companies, etc.). materials with low environmental impact. wins several prestegious
design awards
| 109
› Buildings can be made sustainable and › The Masdar project proved that higher recycling
economically viable. rates for i.e. concrete and aluminium are
possible.
› Building sustainably can be done by
understanding integrated holistic design and › Breakthroughs can be achieved by working
by working with very cross-disciplinary teams. It across the value chain. In Masdar this was done
requires teams with a wide range of expertise. by working together with Siemens, Mitsubishi,
In Masdar 25+ disciplines were involved in the Honeywell, General Electric, etc. Developers
planning and design phase. can challenge suppliers to push the envelope
and create win-win situations. Co-innovation
› It is crucial to work with passion. Urban requires an investment from both parties.
development is all about people. This is why
lead designers need to put the people at › Don’t build ‘one size fits all’ buildings.
the centre and bring them together. An open Australia’s 18 climate zones and provided
attitude towards learning from each other and Masdar with experience in designing specific
from different experts is key. solutions for different zones, city and market.
› Setting inspiring goals drives people to develop › The sector must re-examine traditional building
expertise and to go the extra mile. techniques and use them to inspire modern
buildings and capitalise on maximum efficiency.
› Large project have the potential to impact the The goals is to find the sweet spot between
entire region. These projects can be beneficial good design, effective technologies, and good
for (local) governments by contributing to new performance. For instance, in Masdar extra-
buildings standards. In addition, they can be thick walls funnel wind into rooms with towers
beneficial for the local market by building local known as Al Barajeel. These traditional design
knowledge and expertise. principles are valuable, simple, passive and
hence efficient.
› Expertise from around the world was necessary
to create Masdar. The expertise and adaptation
of international knowledge to local solutions
enables Masdar to now export knowledge to
regions with similar climate conditions.
Key Success Factors growth of local suppliers and the local economy. It 1 The exterior wood used throughout the city is
resulted in spin-off policies that affects all new build palmwood, a hardwood-substitute developed by
1 Determination to realize economically viable projects in the UAE. Pacific Green using plantation coconut palms that no
sustainable development and the continuous drive to longer bear fruit.
5 Masdar Energy Design Guidelines proved to be a
raise the bar. Reach for the limits to make buildings
powerful instrument for suppliers to make sound 2 Concrete– The ready-mix concrete used to build
more sustainable and economically viable. The
material choices and provide information about Masdar City contributes significantly to the carbon
knowledge generated proves to be very valuable for
sustainable material sourcing. footprint; however, a variety of steps were taken
all parties involved in this project and in all future
projects. 6 Passion and People. Promoting health and wellbeing to improve the sustainability of this concrete with
attracts the aligned parties. Their experience adds regard to the sourcing of the materials and innovative
2 Understanding integrated holistic design. This requires design mixes and systems. All mix designs use
to the project, and promotes the willingness to learn
cross-disciplinary processes with a very broad range granulated blast furnace slag (GGBS) as a 40% to
from each other.
of disciplines. Doing this requires an open attitude 60% replacement for Portland cement. As GGBS is
to discuss and integrate sollutions in the design. a by-product of the process to produce steel and
The project's scope document encompasses 25+ Preconditions is typically directed to landfills, using this material
disciplines. The lead designer creates a team and as raw material for another process reduces waste,
organizes workshops to develop the right concept. 1 Long-term visions, commitment and a strong financial improves the concrete’s strength and durability, and
basis to create an international hub. When the project reduces water and embodied carbon.
3 Close cooperation with suppliers to improve the
was announced in 2008 Abu Dhabi committed itself
sustainability performance of their production process 3 Aluminium– Masdar City worked with local and
to investing $15 billion in Masdar, making it the
and the quality of materials. For example, the city international suppliers and partners to develop
largest single government investment of its kind,
developed or brought to the local market a range recycled aluminium for use in the Masdar Institute
encompassing 440 million sq. ft. of facilities when
of green materials, including low-carbon cement; buildings’ façades. The façades use 90%-recycled
completed.
high-recycled-content aluminum; sustainably sourced aluminium for an embedded carbon number of 0.98
timber; water-based, low-VOC paints; and 100% kg CO2e/kg, less than 10% of conventional aluminium.
recycled steel reinforcing bars. Working across the Technical and material innovations Extrusions for windows and door frames have been
value chain, they challenged companies and created Masdar is a special project in this book’s line-up in developed for the Masdar headquarters building with
partnerships (with eg. Siemens, Honeywell, General the sense that it is built to develop a business hub for an 81% post-consumer and post-industrial recycled
Electric, Mitsubishi, Alcoa). Through cooperation sustainable technology. This is why Masdar spends extra aluminium for an embedded carbon number of
win-win situations are created as the Masdar attention on the implementation of new technologies. 5.96kg CO2/kg, nearly 50% less than conventional
Projects are international showcases and result in a Because the development and implementation of aluminium.
leading position for economically viable commercial innovative technological achievements is of special interest,
development. we’ve listed some (not all) of the noteworthy achievements
4 Steel– Steel reinforcing bars used in the first Masdar
of the project below:
Institute buildings were made with recycled scrap
4 Educate and develop the local markets. Results in sourced from electric arc furnace (EAF) steel mills
| 111
The eleven case studies offer a wide range of lessons 3.1 Design for lifestyle change
learned, and examples of decisions or approaches Early involvement of occupants
that helped optimize their sustainability perfor- Set and enforce high sustainability goals Hein Struben from Eva-Lanxmeer said: “In most
mance. In this chapter the key observations from the A clear and appealing vision with ambitious sustain- development projects people forget to ask the most
case studies are described, and illustrated to show ability goals helped developers to attract the project important question: “what makes people truly happy?”
the relations between these strategic topics. These partners that shared their aspirations, were willing Answering this question requires involving future oc-
observations are used to identify the main trends that to learn, and work on the forefront of sustainable cupants in the process as early as possible and giving
drive the sector and the strategic topics that need to development. Ambitious project goals stimulated a them sufficient decision-making power to influence the
be considered in order to innovate further towards high level of involvement, long-term commitment and final designs. Early involvement led to higher property
sustainability. (financial) support for the project. The projects show value, and to a high degree of “ownership” and involve-
that high sustainability goals can be met commercially. ment necessary for maintaining and improving the
In Menlyn Main, the sustainability goals even made the district during its use.
project more resilient to the financial crisis.
The local community can also be a valuable asset to
Labels versus creativity developers. In Karaikal Pondicherry, local residents
Labels, such as LEED and GreenCalc, are important used their expertise to add value to programs such as
tools in urban development, and are often essential in material sourcing, home and neighborhood design,
selecting material suppliers. Where labels were used procuring workforce, and mediation over various socio-
they offered many advantages, providing a way to set cultural barriers. In many cases involvement of the
clear standards, enforce performance, and help com- local community has brought the additional benefit of
municate the sustainability ambitions of the districts. positive media attention. In both Dockside Green and
They may even push the market to new and higher Sonoma Mountain Village, community involvement
standards. Material suppliers often communicate created an environment of inspiration which has suc-
the desire to outperform existing labels and market cessfully generated media attention and even attracted
demands. This pro-active attitude pushes the sector to- tourism to the site.
wards innovation. However, using labels may also lead
to a “lazy” attitude. For example, project developers
wanting to build ‘green’ can use labels to give the per- 3.2 Design requirements
ception of building sustainably while labels are never
a guarantee for this to be so. Creativity and thinking Strict selection of motivated parties
beyond labels is required in the design process. There is a critical moment at the beginning of every
| 113
Early
Early involvement
of all required project where the selection of developers and other
Set and involvement of
enforce high occupants disciplines project partners takes place. This often takes place
Linear to non-
sustainability
linear supply in the form of a government tender or request for
goals
chain proposal. The projects show repeatedly that adopting
strict pre-conditions, terms, or non-negotiable criteria
in the selection process will lead to better team perfor-
Labels matter! Strict selection mance and overall results. In order to optimally contrib-
creativity Proximity of
of motivated
dilemma suppliers
Local sourcing ute to the project, project partners must be capable,
partners and production
have an intrinsic drive to realize the ambitions of the
project, and be willing to carry the risk in delivering the
required performance.
ENABLING ADAPTATION
Remote
Early involvement of all required disciplines
AND LEARNING Ensure
services scalability
To come up with a good mix of solutions there needs
to be a high level of interaction between all disciplines.
Anticipate Cross-pollination between technologies and design op-
continuous
tions will result in a smarter mix of solutions to reach
learning
all sustainability goals.
Finance upfront
process costs
Lifetime services More interaction in startup phase will lead to better
and participation results and more integrated planning. Most projects
New business
models rely on a central party that involves disciplines at dif-
ferent stages in the process. In the examined examples
we have seen that involving multiple disciplines early
Advocacy for
change and spill Performance
on in the process lead to more successful plans, better
Carrots and
over based service support and higher market value of the property. Ar-
sticks
contracts chitects and project developers benefit from involving
more people and disciplines from the start.
SURPLUS VALUE
NEW BUSINESS MODELS
From linear to non-linear supply chain
In many ways the construction industry is still quite
Overview of the main observations from the case studies
traditional. In the automobile industry car parts are bodied energy of construction materials. This demand through higher ground and property prices.
designed and innovated by involving many different for local and recycled materials challenges suppliers
parties in the supply chain. In the construction sector to find innovative ways to increase the supply of ap- Lifetime services
vertical and horizontal integration and co-production propriate materials. In Karaikal Pondicherry, industrial Suppliers should deliver solutions and services that
in the supply chain is still limited. Higher sustainability waste was successfully repurposed into fly ash bricks will relief future owners of buildings from end-of life
targets can be achieved if more cross-sector concepts used for construction. These materials were locally worries and costs. This requires long-term involvement
and solutions are available and offered to the market. produced from locally sourced waste, eliminating the of suppliers allowing them to manage costs and ensure
need for import. Similarly, Sonoma Mountain Village the proper functioning of materials and installations
Proximity of suppliers manufactured their own patented steel frames on-site throughout the life-cycle of a building. To organize this
Material suppliers and construction companies often in a factory powered by photovoltaic panels. construction parties and material suppliers need to
have no real role in the initiation and design phase. develop smart ‘full lifetime service concepts’.
Many project decisions are made prior to inviting Scalability
construction companies and material suppliers. After Achieving higher sustainability levels requires low New business models for material suppliers
developing the project goals and designs, materials cost solutions and availability of effective technolo- Resource scarcity increases market opportunity and de-
suppliers and construction companies are approached gies. Economies of scale can contribute to achieving mand for alternative business models to optimize the
to deliver the materials and techniques necessary to low cost “standardized” solutions. However, there are use of materials in society. Large volumes of waste and
implement the designs, leaving little space for them to no one-size-fits-all solutions since climates and other materials from renovation and redevelopment cycles
develop innovative concepts. The case studies provide contextual factors are different around the world. can be found locally. For material suppliers, there is
several examples where project developers did not Local sourcing and production also imposes limits to significant opportunity in reclaiming these materials
ask for specific solutions, but asked for an ‘as high as the economy of scale that can be achieved due to the and repurposing or otherwise extracting value from
possible’ performance level such as e.g. energy positive availability of local materials and expertise. them. Such innovations produce sustainability gains in
buildings and high recycling rates for materials. This many of the studied projects. Structuring businesses
initiated an open design process that led to unex- to collect and add value to end-of-life construction
pected innovative solutions. The ability of suppliers to 3.3 New business models materials is an emerging trend with real economic and
interact with architects, developers, and other project environmental benefits.
partners is crucial to successfully embed innovative Finance up-front process costs
concepts into urban plans and designs. New business models are required to finance the start- Performance based contracts
up phase for sustainable urban development to allow Project developers require ‘no worry’ type of solu-
Local sourcing and production for a high participatory design process. Governments tions to stimulate them to apply innovative materials
A major environmental impact in construction stems can stimulate such a design process by using public and technologies. In order for suppliers of construc-
from the type of materials used and their embodied revolving funds, while the private sector is able to cre- tion materials and building concepts to provide such
energy. Developers that intend to build sustainably will ate new finance structures by itself. In Eva-Lanxmeer, performance guarantees good insight is needed into
look to reduce embodied energy by sourcing locally Menlyn Main, and other examples it became evident the functioning of innovations. A high level of co-
as well as increasing the use of recycled, re-used, and that organizing an intensive start-up phase with high production and co-innovation within the supply chain
even waste materials. Local or even on-site production involvement of project partners led to higher added allows the necessary knowledge and experience to be
of materials can help to significantly reduce the em- value of the project. The initial costs were earned back developed to achieve this.
| 115
Colofon
Project lead Michiel van der Vight Project lead Laila Petrie
WWF partner Vincent Mages (Lafarge)
Research Michiel van der Vight
Elias van der Valk Steering Group
Matthew Fraser Laila Petrie (WWF)
Tom Bosschaert Vincent Mages (Lafarge)
François Baillon (FIDIC)
Design Tom Bosschaert Vallishree Murthy (British Glass)
Matthew Fraser Clare Broadbent (World Steel)
Phillippe Fonta (WBCSD)
Editing Rachel Visser Soraya Smaoun (UNEP)
Tom Bosschaert Curt Garrigan (UNEP)
Laila Petrie (WWF) Jean-Paul Jeanrenaud (WWF International)
Carina Borgstrom Hansson (WWF Sweden)
Contact Contact
Except Integrated Sustainability Laila Petrie
info@except.nl lpetrie@wwfint.org
www.except.nl
WWF International
Stadhuisplein 15 Avenue du Mont-Blanc
3012 AR Rotterdam, the Netherlands 1196 Gland, Switzerland
+31 10 7370215 wwf.panda.org
| 117
Image credits
This document is covered by a Creative Commons Attribution-
ShareAlike 4.0 International (CC BY-SA 4.0) license. View the
page Image credit license here: creativecommons.org/licenses/by-sa/4.0/legalcode
2 Community Garden Gabriel Kamener
9 Glashus Bjorn Lofterud You are free to:
14 New York Skyline Anthony Quintano
16 Menlyn Maine Building Carlu Swart › Share — copy and redistribute the material in any
35 Tech Share Nationaal Historisch medium or format
Museum › Adapt — remix, transform, and build upon the material
83 Sjostad Marlena Karlsson for any purpose, even commercially.
83 Bridge Marlena Karlsson
87 Winter morning Marlena Karlsson The licensor cannot revoke these freedoms as long as you follow
101 Greenwich Flash Forward the license terms. Under the following terms:
107 Masdar Siemens Masdar
› Attribution — You must give appropriate credit,
Other images: Except Integrated
provide a link to the license, and indicate if changes
Sustainability
were made. You may do so in any reasonable manner,
The greatest possible care has been taken to identify all but not in any way that suggests the licensor endorses
image copyright holders correctly and attain permission for you or your use.
image usage rights. However, if we have omitted to do so in › ShareAlike — If you remix, transform, or build upon the
any individual instances, we should be most grateful if these material, you must distribute your contributions under
copyright holders would inform us forthwith to rectify the issue. the same license as the original.
› No additional restrictions — You may not apply legal
terms or technological measures that legally restrict
others from doing anything the license permits.
Notices:
No warranties are given. The license may not give you all of the
permissions necessary for your intended use. For example, other
rights such as publicity, privacy, or moral rights may limit how
you use the material. Copyright of individual images and texts
remain with the original copyright holder.