Client: Jabal Omar Dev.

Corp PMC: Hill Interna ti onal M ain Consu lta nt : Ehaf Consultin g Contractor : Sa udi RCC

METHOD STATEMENT FOR GR. 25 MASS CONCRETE FILLING AND WATERPROOFING BELOW RAFT FOUNDATION
AND TUNNEL WALL AT PART 3-5 AND 5-5 IN ZONE S10

Introduction:

The area beside the existing Tunnel Walls, which partially built by the previous contractor left some raft
foundation unconstructed including the waterproofing. The existing condition at site that rock was cast over by a
mass concrete with two stages of waterproofing. In this regard we will carry out the same sequence in to
complete till to the raft as follows :

1. Remove unsuitable materials and other debris in the area over the rock and beside the Tunnel Wall and
offer to the consultant for inspection of ground preparation/readiness.
2. Once approved, fill the area/void with Gr. 25 mass concrete in stages (as per .the attached t,ke'*hl \a_: th: ~
area is uneven and the existing concrete Tunnel Wall height~~~~J~~ ~"<)QG'T ~ ~ f~'-"'-J.d
3. Last stage of mass concrete fill ing sh ~he existing rebars (which protrude from the
existing Tunnel Wall) in order to allow for a working space during waterproofing works below those dowel
bars.
4. After casting and the area is cured, an inspection will be offered to the consultant for approval prior to the
f irst stage of waterproofing (as per the approved details) . Once HOPE is laid, consultant will inspect for it
readiness prior to casting of lOOmm blinding.

Page 1 of 4
11111
Client: Jabal Omar Dev. Corp PMC: Hill International Main Consu ltant : Ehaf Consulting

5. Blinding will be laid over by the 2"d stage of waterproofing as per details and sequence of the work.
~~ is laid below HOPE and will be inspected by the consultant prior to covering by another layer of
~ V(\"- geotextile and SOmm screed will then to proceed for protection of the waterproofing membrane.
~~ 6. All the termination or end of waterproofing shall be tuck in the existing Tunnel Wall and will be sealed
using approved joint sealant materials. An Aluminum flashing shall be installed for the whole length prior
to casting of raft foundation.
7. Prior to casting of raft foundation, the gap below the existing started bars of Tunnel Wall, which having a
large concrete cover, a single a layer of bars (both ways in X andY direction) will be provided for provision
of crack control at this portion.
8. Construction of raft shall be then carried out thereafter and will be submitted the Method Statement in a
separate submittal.

Page 2 of 4
Client: Jabal Omar Dev. Corp PMC: Hill Internat ional M ain Consultant: Ehaf Consulting

--

MASS CO CRETE FILLING USING GR. 25 BELOW RAFT FOUNDATION & TUN EL WALL
AND WATERPROOF! G DETAILS PROPOSAL

Page 3 of 4
Client: Jabal Omar Dev. Corp PMC: Hi ll Internationa l Main Consultant: Ehaf Consulting

.
..
@ _ ...

-
Page 4 of 4
1111 Civil C
• t 'It '
na trv t n
>U .. ,.J
JABAL OMAR DEVELOPMENT INSPECTION AND TEST PLAN
PROJECT- PHASE IV (MASS CONCRETE FILLING AND WATERPROOFING WORKS
ZONE S09, S10 AND Sll BELOW RAFT FOUNDATION NEAR TUNNEL WALL AT S10)

Casting of Gr. 25 in fill mass concrete over the rock/below raft foundation near Tunnel Wall at part 3-5 &
WORK SCOPE
5-5 in S10.
MAIN CONSULTANT EHAF

MAIN CONTRACTOR RUWAD CIVIL CONSTRUCTION

PART 1- APPROVALS REQUIRED PRIOR TO COMMENCEMENT OF THE WORKS

Item Frequency of Hold, or Witness Point


Description of Operation/Inspection, Test and Approval Records Generated
No. Inspection & Test Plan Subcont. RCC EHAF
1 Waterproofing Drawings and Details Once Approved Drawings Sub* R R&A
Mix Design, Data
Materials Submittals- Gr. 25 Concrete Mix,
2 Once Sheets, Product Sub R R&A
Waterproofing Materials (geotextile/HDPE/Accessories)
Certificates
Method Statement, Inspection & Test Plan {this
3 Once MS & ITP Sub R R&A
documents)
Approved Drawings,
5 Survey reference and Bench Marks {drawings) Once Sub** R R&A
Control Point
Permits, licenses, NOC's and Authority Approvals (if
6 Once Approval of work Sub** R R&A
required)

Page 1 of 2
.. .

11111 -
R.C.C

JABAL OMAR DEVELOPMENT INSPECTION AND TEST PLAN


PROJ ECT- PHASE IV (MASS CONCRETE FILLING AND WATERPROOF IN G WORKS
ZONE S09, S10 AND S11 BELOW RAFT FOUNDATION NEAR TUNNE L WA LL AT S10)

Note *· Al l deviation from the approved drawings/ documents to be recorded and discussed with the Main Consultant prior to
proceeding . • Other subcontracto r/sub consulta nt engaged by RCC. •• By RCC

PART 2- INSPECTION AND TEST DURING CONSTRUCTION WO RKS (MASS CONCRETE, WATERPROOFING, BLINDING & SCREED)

Item Freq uency of Hold, or Witness Point


Description of Operation/I nspection, Test and Approval Records Generated
No. Inspect ion & Test Plan
Subcon RCC EHAF
Cleaning and Preparation of ground - read iness of the
1 By Area/Stages/Layout IR H H RC
area
Consultant Inspection and Approval for cleanl iness of By Area/Stages/Layo ut
gro und prior to casting, concrete surface preparation,
2 IR H H I&A
laying of HD PE waterproofing (stages), blinding and
screed .
Waterproofing works- Laying of geotextile, HDPE, joint By Area/Stages/Layout IR H H I&A
3
sealant, welding j oint and insta ll at ion off
Concrete Order and Casting- Bli nd ing and Screed, By Area/Stages/Layout
Delivery notes, Pour
4 H H I
Sam pling on site : Sl ump/Flow , Temperature . Record
Abbreviations : Sub- SUBM IT, H- HOLD, R&A- REVI EW & APPROVE, RC- RANDO M CHECK, !&A-INSPECT & APPROVE, S- SURVEILANCE,
CL= CHECKLIST, IR- INSPECTION REQUEST, 1- INSPECT