Date : 03-10-2020
1 Pile to Baseplate 18 18 0
2 Rib to Baseplate 18 11 4
3 Baseplate to Beam (Wf 400) 18 16 0
4 Beam (Wf 400) to Beam (Wf 400) 32 28 0
5 Beam (Wf 300) to Beam (Wf 400) 48 42 0
6 Beam (Wf 150) to Beam (Wf 400) 30 26 0
7 Beam (Wf 150) to Beam (Wf 300) 30 26 0
Manpower : Jumlah
1 Welder 3
2 Fitter 0
3 Helper 1
4 SPV 1
5 Koordinator 1
6 Operator Genset 1
Total 7
*Note
: Requirement berubah mengikuti kontrak yang real dan aktual dilapangan