You are on page 1of 7

Cement kiln inlet gas analysis

KilnLoq™
2 3

Gas analysis for a Benefits of gas analysis


competitive edge components measured
at the kiln inlet
Kiln inlet gas analysis systems In general, gas analysis gives you the Emission reduction
deliver essential data. Cement chance to deal with problems and The more complete the combustion
plants need reliable online issues as they arise at source – in the in the process, the less pollution your
analysis of the process gasses process itself. Below, are a few of the plant will produce. Gas analysis lets
most immediate ways effective gas you regulate the O2 and CO produced
at the kiln inlet if they are to
analysis can benefit your process and by your processes at source, so you
compete in a tough market. Use
put your business in shape to can optimise combustion and avoid
the data to optimise your safety,
compete. using expensive anti-emissions
operating costs, production and
equipment to remove pollutants at a
emissions – and compete with Kiln pyro control late stage in the process.
the best in the cement industry. Maintaining optimal levels of O2

Without kiln inlet gas analysis,


(oxygen) in the process not only Safety
removes the risk of explosion, it also If you are not in control of the levels
your kiln will consume too much prevents a toxic build-up of CO of O2, CO and CH4 (methane) in your
energy, pollute the environment (carbon monoxide). process, you are not in control of
and shut down more often. your pryro processes – and that can
With production losses and Kiln stop prevention have disastrous consequences for the
unnecessary wear on expensive Downtime costs – big time. And if O2, safety of your working environment.
equipment, that’s bad news for CO or SO2 (sulphuric acid) build up in
you; and great news for your your kiln, production has to be Quality clinker
competition. Installing a gas stopped for at least three hours. You Normally, clinker is tested for quality
analysis system will put you back will also have to heat up the process in the lab, two hours after the
in the ballpark. again – and that is not always a process is complete. Analysing gas
smooth, stable operation. Your such as NO (nitric oxide) while the
The payback of an on-line kiln through-put is bound to go down, process is still in the kiln allows you to
inlet gas analysis system from and the quality of your clinker may be make fine adjustments, saving you
FLSmidth is less than 200* affected too. With gas analysis, you handling time, and helping you avoid
days. After that, it is helping simply don’t have to stop your kiln. simple mistakes such as over burning
you extend your margins and the clinker.
Optimal fuel
overhaul the competition
consumption Control of volatiles
every day.
Gas analysis helps you control your The build-up of volatiles, such as SO2
levels of O2 so you can choose (sulphuric acid) in your process can
between burning fuel more slowly cause two expensive problems. The
and efficiently for lower production first: any volatiles condensing on the
costs, or burning it faster for a higher cool raw materials as they are fed into
through-put and greater capacity. the process will build up and cause
That gives you the flexibility to tailor blockages. The second: raw materials
your production strategy to the needs producing volatiles unchecked will
of the market – fast. get through the kiln’s brick lining and
corrode the steel structure. Both
require shutdown; and the second
can take days to fix. Gas analysis
detects the volatiles at source so you
can remove them before any damage
* depending on kiln size and design is done.
4 5

Reliable & efficient –


on-line kiln inlet gas
analysis
No kiln operator would trust Minimising downtime successful Air Blaster cleaning KilnLoq One-Pipe KilnLoq One-Pipe KilnLoq One-Pipe layout
data from an unreliable inlet Even with the best probes, blockages equipment. Just like an Air Blaster, Automatic cleaning maintenance A. Rear end access port

gas analysis system. The risks to occur. Unblocking your probe quickly One-Pipe has no bends, no kinks, no The KilnLoq One-Pipe system has three The One-Pipe sample path is easy to service B. Filter house body with heater
cleaning systems that work in harmony to and keep clear. The access port at the end of
safety and loss of production are and easily is essential to minimise bulges: just a length of smooth, C. Coaxial filter
clean the sample path thoroughly from end the One-Pipe length can be open in seconds,
expensive downtime. Other straight pipe. The probe runs the D. One-Pipe sample system (Green)
too great. Not only have our kiln to end. Firstly, the probe tip is cleaned to providing full access to the sample path’s
manufactures of extractive gas entire length of the pipe before remove any deposits that could reduce the entire length. If aggressive kiln operation E. Water cooled cooling Jacket
inlet gas analysis systems proven
analysis systems have added connecting to a solenoid valve and an effectiveness of the main One-Pipe cleaning blocks the probe, One-Pipe allows you to
F. Electrical heated sample probe
accurate and reliable, they are process. 2. A jet of compressed air is then clean out the entire length of the probe
mechanical devices, such as probe oversize air tank. Maintenance-
also easy to maintain, so you can friendly and capable of tackling any
blasted through the entire length of the in a couple of minutes. As a result, you
plungers or rotating probes, to a One-Pipe probe. 3+4. At the same time, air will rarely have to open the filter housing
cut down on time-consuming kiln inlet process, the air blaster-like is blown backward through the filter, during operation because you can carry out
design that is already over-complex.
maintenance checks. design makes cleaning the probe 3. lifting dust deposits off the filter all maintenance through the rear access
But we take a different approach.
filaments. This dust is swept up by the blasts port. A. And when the access port is open,
FLSmidth uses a patented One-Pipe quick and easy.
And, the accuracy of extractive of compressed air in the main body of the the sample path can be visually inspected
design to handle the hot, highly pipe and blown back into the kiln. in seconds. 1. This system is so effective
gas analysis systems is well How it works
corrosive, dust-filled process. It’s that some of the first KilnLoq probe systems
documented – and all the results It’s simple. The KilnLoq One Pipe installed in 2003 are still operating with
simple. And, since its introduction in
point to one conclusion: they are system samples gas in a straight pipe. their original filters.
2003, the FLSmidth KilnLoq gas
much more accurate than non- analysis system has become the There are no bends, obstacles or
extractive systems. cement industry’s probe system of deposits to get in the way of your
choice. sample. Opening the access port at
the end of the KilnLoq allows you to
100 times faster to clean look along the length of the probe at A
No matter what kiln inlet gas analysis the processes in the kiln. So now you
system you use, it's not a question of can carry out real-time visual
if but when it will get blocked. And, inspections of the probe.
any company claiming maintenance-
free gas analysis needs a reality check. The process gas enters the filter
For conventional gas analysis systems, housing through the centre of the 1 2
it can take anywhere between 30 and pipe, where it passes through a
120 minutes to clean the length of a coaxial filter for collection and
probe. The KilnLoq probe requires just analysis. The filter itself is built into a B
1 to 3 minutes. No other probe section of the One-Pipe sample line.
system on the market comes close. The entire sampling system is heated A D F
to 180°C to avoid condensation. C E
The patented On-Pipe design of the
KilnLoq probe was inspired by the

3 4
6 7

The benefits of One-Pipe’s Basic configuration of a KilnLoq probe and extrac-


tion device housing. The control panel is shown on

unique design the wall to the left

The KilnLoq One-Pipe design The One-Pipe probe design is simple. System configuration
is simplicity itself. Backed by And, since its introduction in 2003, 1. Utility air supply

FLSmidth’s 100+ years of process One-Pipe has proved how effective it 2. Probe cooling
is over and again: 3. Field controller cabinet
knowledge and site experience it
will not let you down. • Jets of compressed air blast all the 4. KilnLoq probe on extraction device

And now, a KilnLoq probe has dust and residue out of the sample 5. GASloq gas conditioning panel with
path in one go integrated controller
been successfully installed in the
world’s largest kiln. • The probe stays clean for longer
because there are no bends or
filters in the sample path to
trap dust KilnLoq shown with optional utility air supply and
probe cooling equipment that can be connected to
• A new cleaning process makes sure any existing analysis system
the probe’s tip stays free from
3
blockage during cleaning
• No need to dismantle any
machinery for cleaning or
maintenance
• Maintenance and cleaning takes less 4
than 3 minutes – up to 120 times
faster than anything else on
the market 2

• In seconds, you can view the entire


length of the probe’s sample path
1
– and carry out the industry’s fastest
visual inspection
• Adaptable cleaning sequence setup
to process conditions A complete system configuration showing gas
analysers and a gas conditioning system installed in 5
These benefits are unique. No other
a GASloq configuration with utility air supply and
gas analysis system on the market can probe cooling equipment
touch the One-Pipe system for speed
and ease of maintenance. That means
you can carry out all the gas analysis
you need to produce high quality
clinker more efficiently than your
competitors.
8 9

Simplicity by design

Simplicity lies at the core of our Probe Water Cooling Extraction Device Probe Cleaning Control Panel
approach to design... Why? The KilnLoq probe has a steel cooling The probe’s closed-loop water circuit The kiln inlet can be a dangerous The probe has its own cleaning The Control Panel allows the operator
jacket so it can resist the high is controlled by the probe cooling place, especially under off-set kiln system to remove the residue that to Communicate with the KilnLoq
Complex solutions are prone to temperatures in cement plants. Cold panel. Because the probe operates conditions. But gas analysis builds up during analysis. Three system. A color touch screen gives the
break down – and they can be water circulates in the jacket to keep best when it is cold, the cooling panel equipment is essential under off-set integrated cleaning devices work in operator access to a large range of
tricky to service in a hurry. the probe cool – conventional operates at a high cooling capacity kiln conditions, so continuous, safe harmony, making sure the probe can functions, including alarms, event lists
technology that is safe, easy and without any regulation of flow or operation is crucial. That is why we do its job even under the most and trend curves. A large symbol on
Simple equals reliable and cheap to maintain or replace. temperature by default. Many cement install the KilnLoq probe in an extreme conditions. During cleaning, the screen gives your maintenance
easy to fix. The central pipe where the gas is plants have a water supply with a extraction device. During off-set specially designed, fast-responding people a one-glance summary of the
sampled, and the filter housing, are high lime content, and this can affect conditions, when pressure in the kiln solenoid valves control the high- equipment’s status.
electrically heated to 180°C, so water the performance of the water cooling is high, anybody standing too close to pressure jets of air that blast deposits
or acid cannot condense. The probe is system. However, the closed-loop any opening in the process will be hit out of the One-Pipe probe and back The control panel comes integrated
ready for analysis just minutes after water circuit re-circulates water at a by a jet of super-heated dust. The into the body of the kiln. Installed in into GASloq cabinet or as a field
power-up, and does not rely on heat low temperature, so lime deposits are extraction device is equipped with an the extraction device, the valves are cabinet.
from the kiln – so it works even in a minimal, resulting in less maintenance automatic process shutter and besides arranged for short hose runs and
cold kiln during start-up or shutdown. and less need for a regular that the system allows the probe to powerful cleaning throughout the Communication to the control room
Cooling the steel probe prevents de-scaling. be operated from a safe distance so length of the pipe. is available as hardwire or as an
bending and distortion along its there is no risk of exposure. optional serial connections standards,
length. No matter what cooling media And, of course, simplicity is at the Gas Conditioning such as Modbus, Profibus, Ethernet
is used, the probe will be a cold spot core of the design. Installation and If the kiln operation is out of balance, Process gas generated by a cement TCP/IP, and they are all supported by
inside a kiln that can reach operation are kept as simple as material can build up around the kiln is very aggressive and corrosive. a fibre-optic uplink.
temperatures in excess of 1,200°C. possible. This reduces the need for probe. Under routine operation, most That is why FLSmidth’s extractive gas
This will cause volatiles in the process maintenance, and removes the need of these deposits are easily removed conditioning system has been
gas to condense on the cold surface for constant long-term adjustments by the probe’s back-and-forth developed for maximum safety. Not
and bond with the raw materials in that plague more complex designs. If movements. The quick cleaning only have all the components in the
the kiln to form a hard coating. But at the cold water supply to the cooling procedure – and the optional gas conditioning system been
FLSmidth, we have proven that the system fails, the extraction device air-blaster operation – are sufficient through extensive testing, they have
KilnLoq probe’s cool surface makes responds by retracting the probe to remove the rest. Any failure like also proven their reliability and
the condensation so brittle that it is from the kiln, so there is no risk of power failure or weak flow of cooling durability in action since 2003.
relatively easy to remove. damaging the probe. And, because water triggers the extraction device’s
the probe itself monitors the flow gear motor, extracting the probe Designed with simplicity in mind, the
The KilnLoq’s cold water cooling and temperature of the water in the before it gets too hot. This fail safe components are easy to service and
system means its probe is 20 percent cooling system, if your plant has an system works by using the optional maintain. And it comes with either a
stronger than probes that use hot existing water cooling system, you UPS or a UPS supplied by the peroxide dosing system, or an
water or oil cooling systems. The can save the cost of installing a probe customer. The gear motor is very optional super-chiller gas to keep
KilnLoq probe can also estimate the cooling panel. powerful – and it is also simple in maintenance to a minimum.
amount of residue building up in the design, so troubleshooting and repair The gas conditioning system is
kiln inlet. Before the build-up can is very easy, and rarely needed. integrated into the GASloq cabinet.
become large enough to cause a
blockage or interfere with sample
collection, the system sends a
message to maintenance.
This results in efficient kiln cleaning,
less downtime and better analysis.
10 11

New options • Placement: Kiln inlet side, from Be a competitive cement


for system centre line and 1m above; able to producer
install on either side of the kiln inlet
configuration chamber due to One-Pipe cleaning
It’s simple. Optimising your kiln
operation means installing a kiln inlet
The new KilnLoq probe is • Maximum process temperature: gas analysis system. Kiln inlet gas
modular by design, so you can 1,400°C analysis gives you fundamental data
configure the KilnLoq™ solution • Normal process temperature: to implement your production
that best meets the needs of 900-1,200°C strategy, be it lowest production cost,
your plant. highest through-put, lowest emission,
• Maximum dust load: 2,000 g/
best clinker quality or any
We deliver the basic KilnLoq Nm3
combination of these.
probe complete with an • Minimum pressure: -20 kPa
extraction device and control • Normal process flow: 20 m/s Without an effective, reliable gas
panel. So, if you have existing • Instrument air: needed at 6-7 bar, analysis system, your kiln operation
plant, you can invest in a new 3m3/h won’t achieve its full potential. With
KilnLoq gas analysis system its maintenance-friendly One-Pipe
• Quality of instrument air: dew
without having to purchase all design, our patented KilnLoq probe
point -20°C, according to ISO
system gives you the market-leading
the auxiliary equipment such as 8573-1 class 2
system for kiln inlet gas analysis – one
a utility air supply, of systems • Power requirements: that has been proven to pay back in
for water cooling and 3phx380/440V 50/60Hz or less than 200 days.
gas conditioning. 3phx460/460V 60Hz
• Approval according to: CE or UL Please contact one of our local sales
representatives in your area to find
out more about how FLSmidth
KilnLoq can help your operation
compete in the tough world of
cement.

The KilnLoq probe is available in the following standard configurations


Field controller Integrated KilnLoq Extraction Utility air Water Gas conditioning Analysers
cabinet controller probe device supply cooling panel
X X X (X) (X) (X) (X)
X X X (X) (X) X (X)
(x) Is optional equipment
CM 09-15 800-97-ENG V3

Copyright © 2015 FLSmidth A/S. ALL RIGHTS RESERVED. FLSmidth is a (registered) trademark of FLSmidth A/S. This brochure makes no offers, representations
or warranties (express or implied), and information and data contained in this brochure are for general reference only and may change at any time. www.flsmidth.com/gas

Project Centre Denmark Project Centre USA Project Centre India


FLSmidth A/S FLSmidth Inc. FLSmidth Private Limited
Vigerslev Allé 77 2040 Avenue C FLSmidth House
DK-2500 Valby Bethlehem, PA 18017-2188 34, Egatoor, Kelambakkam
Copenhague Tel: +1 610-264-6010 (Rajiv Gandhi Salai, Chennai)
Tel: +45 3618 1000 Fax: +1 610-264-6170 Tamil Nadu – 603 103
Fax: +45 3630 1820 E-mail: automation@flsmidth.com Tel: +91-44-4748 1000
E-mail: automation@flsmidth.com Fax: +91-44-2747 0301
E-mail: automation@flsmidth.com

You might also like