Prepared by :
SITE PT CERIA NUGRAHA INDOTAMA MINE TECHNICAL CONTROL
PIT BOUNDARY MAP
MINE CONDITION
LOADING POINT
BANK SOIL
DISPOSAL
CUMMULATIVE PLAN VS ACTUAL UNIT
EQUIPMENT
ITEM JAM KERJA HARGA/JAM BIAYA/ BCM BIAYA/$ BCM/0,5 km
JENIS JUMLAH (UNIT)
EXC. PC200 1 75 Rp 500,000.00 Rp 37,585,253.46
EQUIPMENT PLAN $ 4,745.62
DT 1 75 Rp 352,273.73 Rp 26,480,594.86
EQUIPMENT
ITEM JAM KERJA HARGA/JAM BIAYA/ BCM BIAYA/$ BCM/Ha
JENIS JUMLAH (UNIT)
EXC. PC200 1 18 Rp 500,000.00 Rp 9,215,240.49
EQUIPMENT PLAN $ 1,808.92
DOZER 1 18 Rp 825,000.00 Rp 15,205,146.80
ITEM JENIS HM HARGA/JAM TOTAL RENT COST FUEL CONSUMPTION TOTAL FUEL COST TOTAL COST BIAYA/$ BCM
◼ Accident/Incident :-
SAFETY TALK :
TANGGAL LOKASI JUMLAH PESERTA PEMBICARA MATERI FOTO
GSI Senin, 09 Maret 2020 Selasa, 10 Maret 2020 Rabu, 11 Maret 2020 Kamis, 12 Maret 2020 Jumat, 13 Maret 2020 Sabtu, 14 Maret 2020 Minggu, 15 Maret 2020
1 MAN POWER 29 29 28 27 29 29 27
1 MAN HOUR 261 261 252 243 261 261 243
CONSTRAIN FOR MINING ACTIVITY
• Kurangnya support alat berat seperti tidak adanya dozer dan dumptruck sehingga dapat
menghambat pekerjaan dari plan waktu.
• Belum siapnya towerlamp sehingga kegiatan malam belum dapat di lakukan.
• Kurangnya Operator untuk EXCA 213 (PC 195) mengakibatkan kurang nya Hoursmeter
pada alat tersebut.
• Breakdown nya PC 300 mengurangi produktivitas kerja.
TERIMA KASIH