II PEKERJAAN TANAH
1 Galian tanah 0.5842% 100% 0.5842%
2 Urugan sirtu 9.0490% 100% 9.0490%
V PEKERJAAN PASANGAN
1 Pasang bata trasraam 1.8683% 100% 1.8683%
2 Pasang bata 1:6 7.6813% 100% 7.6813%
3 Roolag pasangan bata 0.15880% 100% 0.1588%
4 Plesteran trasraam 1.1388% 0.0000%
5 Plesteran biasa 1:6 3.7561% 85% 3.1927%
6 Plint bawah dinding 0.2775% 0.0000%
7 Locis pintu 0.0913% 0.0000%
8 Benangan 1.0988% 100% 1.0988%
9 Tali air kusen 0.3009% 35% 0.1053%
VI PEKERJAAN KAYU
1 Kusen kamper 5.6057% 100% 5.6057%
2 Daun pintu 4.0345% 0.0000%
3 Daun jendela meranti 2.5404% 10% 0.2540%
IX PEKERJAAN PLAFON
1 Rangka plafon. 1.6885% 0.0000%
2 Gypsum board 9 mm 0.6078% 0.0000%
3 Lis gypsum 5x5 0.5744% 0.0000%
XI PEKERJAAN KERAMIK
1 Keramik lantai Milan 1.7466% 0.0000%
2 Keramik KM/WC Keluarga 2.8191% 0% 0.0000%
3 Keramik KM/WC Pembantu 0.3895% 60% 0.2337%
Eddy Santoso