BOBOT PHISIK PEKERJAAN TERMYN KE 4

PROYEK : Rumah tinggal


TYPE : 1 unit rumah tipe 130 (O6) + 2 unit type 85 (M5)
LOKASI : Perumahan Nirwana Regency Kav. 621-750-751
Kontraktor : CV. Andalas
PROSENTASE PROGRESS BOBOT
NO. URAIAN PEKERJAAN
BOBOT PHISIK PHISIK
I PEKERJAAN PERSIAPAN
1 Direksi kit 0.4381% 100% 0.4381%
2 Setting out & bouwplank 0.2264% 100% 0.2264%

II PEKERJAAN TANAH
1 Galian tanah 0.5842% 100% 0.5842%
2 Urugan sirtu 9.0490% 100% 9.0490%

III PEKERJAAN PONDASI


1 Aanstamping batu kali 1.2932% 100% 1.2932%
2 Pondasi batu kali 7.6418% 100% 7.6418%
3 Cor sloof 15/20
a. Beton 0.7810% 100% 0.7810%
b. Besi beton 1.0717% 100% 1.0717%
c. Begisting 0.8733% 100% 0.8733%

IV PEKERJAAN KONSTRUKSI BETON


1 Kolom beton praktis 12/12 4o8
a. Beton 0.5589% 100% 0.5589%
b. Besi beton 1.4040% 100% 1.4040%
c. Bekisting 1.5557% 100% 1.5557%
2 Balok & kantilever beton
a. Beton 0.3680% 100% 0.3680%
b. Besi beton 0.8881% 100% 0.8881%
c. Bekisting 0.6784% 100% 0.6784%
3 Ring balk
a. Beton 0.5258% 100% 0.5258%
b. Besi beton 1.0096% 100% 1.0096%
c. Bekisting 0.7156% 100% 0.7156%
4 Cor meja dapur 0.0876% 100% 0.0876%
5 Rabat beton lantai 5 cm 1:3:5 1.1133% 95% 1.0576%

V PEKERJAAN PASANGAN
1 Pasang bata trasraam 1.8683% 100% 1.8683%
2 Pasang bata 1:6 7.6813% 100% 7.6813%
3 Roolag pasangan bata 0.15880% 100% 0.1588%
4 Plesteran trasraam 1.1388% 0.0000%
5 Plesteran biasa 1:6 3.7561% 85% 3.1927%
6 Plint bawah dinding 0.2775% 0.0000%
7 Locis pintu 0.0913% 0.0000%
8 Benangan 1.0988% 100% 1.0988%
9 Tali air kusen 0.3009% 35% 0.1053%

VI PEKERJAAN KAYU
1 Kusen kamper 5.6057% 100% 5.6057%
2 Daun pintu 4.0345% 0.0000%
3 Daun jendela meranti 2.5404% 10% 0.2540%

VII PEKERJAAN KUNCI DAN PENGGANTUNG


1 Kunci pintu 0.5476% 0.0000%
2 Engsel pintu 1.3511% 0.0000%
3 Ikatan angin jendela 0.3467% 0.0000%
4 Grendel spring knife 0.2142% 0.0000%
5 Nako 0.2142% 0.0000%
PROSENTASE PROGRESS BOBOT
NO. URAIAN PEKERJAAN
BOBOT PHISIK PHISIK
VIII PEKERJAAN KACA
1 Kaca 5 mm 0.7655% 0.0000%
2 Kaca nako 5 mm 0.1542% 0.0000%

IX PEKERJAAN PLAFON
1 Rangka plafon. 1.6885% 0.0000%
2 Gypsum board 9 mm 0.6078% 0.0000%
3 Lis gypsum 5x5 0.5744% 0.0000%

X PEKERJAAN ATAP & TALANG


1 Rangka atap. 6.3859% 90% 5.7473%
2 Lisplang wood plank 0.9006% 0% 0.0000%
3 Genteng M Class 3.8597% 30% 1.1579%
4 Talang seng BJLS 030 0.9366% 60% 0.5620%
5 Talang tegak PVC C3" 0.4168% 100% 0.4168%

XI PEKERJAAN KERAMIK
1 Keramik lantai Milan 1.7466% 0.0000%
2 Keramik KM/WC Keluarga 2.8191% 0% 0.0000%
3 Keramik KM/WC Pembantu 0.3895% 60% 0.2337%

XII PEK. SANITAIR & SEPTICTANK


1 Pas. Pipa PVC AW 3/4" + 1/2" 0.3597% 90% 0.3237%
2 Saluran WC PVC D 4" 0.9886% 100% 0.9886%
3 Sal. Air hujan/air kotor PVC C4" 0.7099% 100% 0.7099%
4 Bak kontrol 0.2556% 90% 0.2300%
5 Septictank + peresap 1.6694% 100% 1.6694%
6 Closet Mono blok 1.5609% 0.0000%
7 Closet jongkok 0.1095% 0.0000%
8 Kitchen Sink 0.3651% 0.0000%
9 Kran dinding 0.5421% 0.0000%
10 Kran bebek 0.1597% 0.0000%
11 Floor stainer 0.0822% 0.0000%

XIII PEKERJAAN CAT


1 Cat dinding 1.9697% 0.0000%
2 Cat plafon 1.2122% 0.0000%
3 Cat kusen 1.0527% 0.0000%
4 Cat pintu/jendela 1.6856% 0.0000%

XIV PEKERJAAN INSTALASI LISTRIK


1 Pas. Inst. Lampu/stop kontak 0.4655% 15% 0.0698%
2 Stop kontak/skakelar Broco 0.6381% 0.0000%
3 Box sekring 0.0730% 0.0000%

XV PEKERJAAN PAGAR DEPAN


1 Galian 0.0511% 100% 0.0511%
2 Pas. Bt. Kali got depan 0.6044% 100% 0.6044%
3 Sloof 15/20 0.1942% 100% 0.1942%
4 Pas. Bata merah 0.2783% 100% 0.2783%
5 Plesteran 0.2531% 100% 0.2531%
6 Benangan 0.2019% 100% 0.2019%
7 Plat beton jembatan 0.2312% 100% 0.2312%
8 Pagar besi 0.6098% 0.0000%
9 Car port 0.3414% 50% 0.1707%

JUMLAH 100.00% 64.8671%


Surabaya, 28 April 2014

Eddy Santoso