Professional Documents
Culture Documents
Contents
1 Scope................................................................. 2
2 Conflicts and Deviations..................................... 3
3 References......................................................... 3
4 Terms and Definitions........................................ 5
5 GOSP Product Specifications........................... 10
6 Overall Process Design.................................... 11
7 GOSP Equipment Design Requirement…….... 17
8 Auxiliary Systems............................................. 38
9 GOSP De-Bottlenecking................................... 43
Appendix I – Production forecast and reservoir
composition template.................................. 44
Appendix II – Simplified Schematic of
Satellite On-Shore GOSP........................... 47
Appendix III – Simplified Schematic of
Satellite Off-Shore GOSP............................ 48
Appendix IV – Simplified Schematic of
Simple GOSP with Gas Compression…..… 49
Appendix V – Simplified Schematic of Complex
GOSP with Gas Compression
and Crude Oil Stabilization……….……..… 50
Appendix VI – Simplified Schematic of
Hot Oil System............................................. 51
Appendix VII – Salt Mass Balance Template........... 52
1 Scope
1.1 This Standard provides the minimum mandatory requirement for process design
of a grass root Gas Oil Separation Plant (GOSP).
1.2 The standard also provides the minimum requirement for debottlenecking
process design of an existing GOSP.
1.3.1 This standard does not apply to crude oil stabilization units that are
regulated by SAES-A-011.
1.3.1 This standard does not apply to produced water treatment and disposal
units that are regulated by SAES-A-012.
1.3.3 Other support systems that are part of the GOSPs (e.g. Fire water
system, Fire & Gas detection, Plant alerting & Alarm system, Safety
equipment, Flare system, etc.) are also excluded from this standard.
2.1 Any conflicts between this standard and other applicable Saudi Aramco
Engineering Standards (SAESs), Materials System Specifications (SAMSSs),
Standard Drawing (SASDs), or industry standards, codes, and forms shall be
resolved in writing by the Company or Buyer's Representative through the
Manager, P&CSD of Saudi Aramco, Dhahran.
2.2 Direct all requests to deviate from this standard in writing to the Company or
Buyer's Representative, who shall follow internal company procedure SAEP-302
and forward such requests to the Manager, P&CSD of Saudi Aramco.
3 References
All referenced Specifications, standards, Codes, Forms, Drawings and similar material
shall be considered part of this standard and shall be the latest issue (including all
revisions, addenda and supplements unless stated otherwise).
Crude Types: (Degree API: Typical range for various Saudi Aramco crudes)
ASL : Arab Super Light (49º - 52º API)
AXL : Arab Extra Light (36º - 41º API)
AL : Arab Light (32º - 34º API)
AM : Arab Medium (29º - 32º API)
AH : Arab Heavy (26º - 29º API)
Dehydrator & Desalter: Electrostatic Coalescers for removal of majority of water and
salt from crude oil
Disposal Water: Treated produced water for downhole/surface disposal/injection
Dissolved Oil: It is the portion of total oil that is not removed by filtration. Dissolved
oil can be removed by biological treatment, chemical oxidation or activated carbon
adsorption.
ECC: Electronic Capacity Control
E&P: Exploration and Production
EIV: Emergency Isolation Valve
Flowline: Pipeline connected to a single oil, gas or water well for production or
Injection
Formation (Produced) Water: Water produced from Reservoir with Oil and Gas
production
GC: Liquid hydrocarbon condensate that is produced from Non Associated Gas Wells
(e.g. Khuff Condensate)
GOR: Gas Oil Ratio in Standard Cubic Feet of Gas per Barrel of Stock Tank Oil
GOSP (Satellite): Onshore and Offshore Gas Oil Separation Plant that is used for oil
field production.
High Efficiency Mixing System: inline skid composed of pipe & fittings, injection
cone and injection pipe spool, injection quill, housing and internal mixing cylinder with
option of manual, pneumatic, or electric actuator for mixing water or chemicals with
crude oil.
Injection (Power) Water: Treated Sea Water or aquifer water injected into a reservoir
for pressure support
Liquid Retention Time (two-phase): Time defined as volume between vessel bottom
and Normal Liquid Level divided by dry oil actual volumetric flow
Oil Hold-up Time: Time defined as the duration that the vessel can supply oil to
downstream equipment if incoming flow is cut-off. It is calculated as volume between
Low Liquid Level and Normal Liquid Level divided by incoming dry oil actual
volumetric flow
Oil Retention Time (three-phase): Time defined as volume between Normal Liquid
Level and Normal Interface Level divided by dry oil actual volumetric flow
Oil Surge Time: The duration that the vessel can accommodate inlet flowrate if
outgoing oil flow cuts off. It is calculated as volume between Normal Liquid Level and
High Liquid Level divided by incoming dry oil actual volumetric flow
Operator Intervention Time: The duration between level where alarms are initiated
and levels where trips are triggered. It is calculated as volume between alarms level
(Low Liquid Level or Low Interface Level) and shutdown level (e.g. Low Low Liquid
Level or Low Low Liquid Level) divided by oil or water actual volumetric flow.
Overall Operating Factor: Factor accounting for shrinkage and downtime (Fraction)
Overfilling Time: The duration required to fill up the vessel if all outgoing flow cuts
off and High High Liquid Level shutdown fails. It is calculated as volume between
HHLL and vessel top divided by total incoming volumetric flow (oil + water).
Remote Header: Piping Manifold where trunklines / flowlines combine into one
trunkline outside the GOSP fence to feed the GOSP Production Manifold
Stock Tank Oil: Stabilized dry oil as it exists at atmospheric conditions in a stock tank.
TSS: (Total Suspended Solids) It is the amount of suspended matter removed by filter. It
is reported in mg/l. Inorganic particles such as clay or grit as well as organic particles
contribute to TSS.
Turndown: The ratio of the maximum flow expected during normal operation to
minimum controllable flow of the GOSP, expressed in a percentage
Wash Water: Low salinity water used to wash the crude oil and dilute the formation
water in the crude desalting process.
Water cut (Percent): Produced water rate*100/(Crude rate+ Produced water Rate)
Water Hold-up Time: Time defined as the duration that the vessel can supply water to
downstream equipment if incoming flow is cut-off. It is calculated as volume between
Low Interface Level and Normal Interface Level divided by incoming water actual
volumetric flow
Water Retention Time (three-phase): Time defined as volume between vessel bottom
and NIL divided by water actual volumetric flow
Water Surge Time: The duration that the vessel can accommodate inlet flowrate if
outgoing water flow cuts off. It is calculated as volume between Normal Interface Level
and High Interface Level divided by incoming water actual volumetric flow
WOSEP: Water Oil Separator. Oily water separator to collect and treat separated
water mainly from the three-phase separators and dehydrator in order to remove the
entrained oil before disposal.
6.1 In accordance with FEL Manual, the GOSP design shall progress through
Process Study (FEL-2 Study), DBSP Development (FEL-2 DBSP), Project
Proposal (FEL-3 Project Proposal) followed by Detailed Design and
Construction (Project Execution).
The required data to develop GOSP design during the various project phases
shall be provided as follows:
Pipeline Design
Contractor
Water Disposal
Water disposal pressure psig
Design Contractor
RMD / P&FDD /
NA PED / SA PED
Disposal water oil-in-water content ppm (vol.)
/ EPD
SAES-A-012
Downstream
Associated gas delivery pressure psig Pipeline Design
Contractor
Downstream
Gas condensate delivery pressure (if applicable) psig Pipeline Design
Contractor
Water content of associated gas (if applicable) lb/MMSCF SAES-A-014
Downstream
Hydrocarbon dew-point of associated gas
ºF Pipeline Design
(if applicable)
Contractor
Operating Factor % PMT
Downstream
Associated gas delivery pressure psig Pipeline Design
Contractor
Downstream
Gas condensate delivery pressure (if applicable) psig Pipeline Design
Contractor
Water content of associated gas (if applicable) lb/MMSCF SAES-A-014
Downstream
Hydrocarbon dew-point of associated gas
ºF Pipeline Design
(if applicable)
Contractor
Operating Factor % PMT
6.3.1 Steady State Simulation shall be developed during DBSP (FEL-2) and
updated during Project Proposal (FEL-3) and Detail Design phase by
Design Contractor and shall be based on the latest version of approved
simulation software package based on SAEP-364. The process
simulation software package that will be used in the project shall be
concurred by P&CSD/APSD/PM&OU.
6.3.2 The GOSP simulations shall be carried out for summer and winter case
at Initial Water Cut, Intermediate Water Cut (Optional), Design Water
Cut and Design GOR conditions.
6.3.7 The Transient Dynamic simulations of the gas compression system shall
be reviewed and approved by P&CSD/APSD/PM&OU and
CSD/RED/C>G. The final dynamic Simulation Models shall be
delivered to P&CSD’s CML coordinator as part of the MCC.
6.3.8 All final process equipment sizing and hydraulic calculations shall be
included as project deliverables during Detailed Design phase.
Saudi Aramco: Company General Use
Page 13 of 52
Document Responsibility: Process Engineering Standards Committee SAES-A-010
Issue Date: 24 May 2018
Next Planned Update: 24 May 2021 Gas Oil Separation Plants (GOSPs)
6.3.9 CFD models and software that will be used in the project shall be
concurred by R&DC and P&CSD.
6.4 PFDs
6.4.1 PFDs showing Heat & Material Balance for Summer and Winter
conditions of the whole processing facilities within GOSP battery limits
including GOSP, Crude Oil Stabilization (if applicable), Gas
Compression and Conditioning system (if applicable) shall be developed
for the following cases:
6.4.2 Stream data table for Summer, Winter conditions for Initial Water Cut,
Intermediate Water Cut (optional), Design Water Cut and Design GOR
case shall be provided in the PFDs.
6.5 P&IDs
Figure 6.1
e) Level Gauge- Type of Level Gauge, backlighting requirement
f) Temperature Transmitter- Type of Temperature Transmitters and
Range. Alarm setting on the DCS block or display
g) Temperature Gauge- Range of Temperature Gauge
h) Pressure Transmitter/Gauge- Range of the Pressure
Transmitter/gauge. Alarm settings on the DCS block.
i) All shutdown and alarm settings
j) All transmitters used for shutdown actions shall be shown
connected to the relevant ESD block logic in accordance with
Cause and Effect Matrix.
6.6 The turndown of GOSPs shall be considered in accordance with the turndown of
each individual equipment. For GOSPs with crude oil stabilization, the stabilizer
column turndown will be the controlling factor for the GOSP turndown.
6.7 All GOSPs shall be designed for sour service for potential souring of the
production field during the life cycle unless data provided by RMD can confirm
otherwise.
6.9 Each main process line within the GOSP battery limit shall be provided with
flowmeter in order to carry-out the overall plant mass balance in accordance
with SAEP-83 (see example in Figure 6.2).
Note: Crude feed stream flowrate can be estimated by performing mass balance
around the inlet separators provided that each outlet stream is equipped
with flow measurement (see example in Figure 6.2)
Figure 6.2
7.1.1 The GOSP Production Manifold and the inlet Header to the last block
valve at the inlet of the first Production Trap shall be designed for the
maximum well shut-in pressure of the field.
Note: For new Flowlines / Trunklines connected to existing GOSP’ s
manifold and inlet header, the installation of a safety instrumented
system for overpressure protection shall be considered if replacing
the GOSP production manifold / inlet header is not practical.
7.1.4 No more than two parallel Production Traps shall be connected to one
GOSP Production Manifold. The piping arrangement downstream of
the "T" dividing the flow to the two Production Traps shall be
symmetrical to minimize uneven liquid flow distribution to the two
parallel Production Traps. Also, Production Traps connected to the
same GOSP Production Manifold shall be installed at the same
elevation in order to avoid uneven liquid flow distribution.
7.2.2 Production Traps are horizontal cylindrical vessels used for crude
degassing through pressure reduction in a GOSP. Production Traps can
be either two-phase (if they are used only for gas/liquid separation) or
three-phase separators (if they provide also oil-water separation) and
shall be designed in accordance with SAES-D-001.
7.2.3 Crude oil heat exchanger shall not be located between the production
manifold and the first Production Trap at the inlet of a GOSP.
7.2.5 The first Production Trap receiving the well production fluids from the
GOSP Production Manifold shall be equipped with suitable inlet
device suitable for the incoming fluid momentum under design, startup
and upset conditions. Impingement plates shall not be used to avoid
shearing of droplets that have negative impact on separation
performance.
7.2.6 The inlet device of first Production Trap shall be designed to withstand
the forces over the full range of operating conditions based on transient
simulation of the flowlines / trunklines network. Finite Elements
Analysis (FEA) based on applied hydraulic forces estimated with
100% produced water in the slug feed stream shall be conducted to
assess the mechanical and structural integrity of the separator inlet
device and its supporting frame.
7.2.7 Bolting for inlet device and supporting frame shall use locknuts or
double nuts with tack weld to avoid loosening due to the dynamic
loads from the slugs. The bolting arrangement shall be reviewed and
concurred by CSD / Pressure Vessels and Tanks Group.
7.2.8 The first Production Trap receiving the well production fluids from the
GOSP Production Manifold shall be equipped with jetting water
system to fluidize and remove mud and sludge accumulation.
Note: If the first Production Trap is designed as 2-phase separator,
provisions and nozzle for future installation of jetting water system
can be provided.
7.2.9 The bottom of the feed inlet nozzle of each Production Trap shall be at
least 6” above the High High Liquid Level shutdown (HHLL)
7.2.12 Non-Slam type check valve shall be provided on common gas outlet of
each GOSP Production Trap.
7.2.13 All Production Trap’s internals shall be removable and pass through
manways.
Below 35º
Figure 7.1
7.3.5 One vessel diameter shall be subtracted from separation length while
performing separated droplet size calculation to take into account
turbulence at the inlet of separator.
7.3.8 The normal oil level in the Three-phase Production Traps shall be at
least 6” above the weir top. The High Interface level alarm setting
shall be at least 6” below the weir top.
7.3.9 Following are the minimum cumulative hold-up and surge time
requirements for Three-phase Production Traps (see Figure 7.2):
Between High Liquid Level alarm and Low Liquid Level alarm: 6
minutes
Between High interface and Low interface alarms: 5 minutes or
1’ height, whichever provides the greater time for operator
response
Figure 7.2
7.3.12 The Low Low Liquid Level and the Low Low Interface Level
shutdowns shall be minimum 12” above the bottom of the vessels.
7.3.13 The nozzles for the interface level instruments shall be located close to
the water weir. Whenever possible, the nozzles for the interface level
instruments shall not be taken from the bottom of the vessel. However,
when used, bottom vessel connections shall include an internal nozzle
extension to reduce bottom solids from entering the standpipe.
7.3.14 The nozzles for the oil level instruments shall be located into the oil
collection compartment. Whenever possible, the nozzles for the oil
level instruments shall not be taken from the bottom of the vessel.
However, when used, bottom vessel connections shall include an
internal nozzle extension to reduce bottom solids from entering the
standpipe.
7.3.15 Spare interface level connection shall be installed for future expansion
of interface level range.
7.3.17 The selected Three-phase Production Trap’s size and design shall be
approved by P&CSD.
7.4.2 The liquid retention time for Two-phase Production Traps shall be
minimum 5 minutes (as defined in Figure 7.3).
Figure 7.3
𝜌𝐿 − 𝜌𝐺 𝐿 0.56
𝑉 𝐶 = 𝐾√ ( )
𝜌𝐺 10
Between High High Liquid Level shutdown and High Liquid Level
alarm: 2 minutes
Between Low Liquid Level alarm and Low Low Liquid shutdown:
2 minutes
Figure 7.4
7.4.8 The Low Low Liquid Level shutdowns shall be minimum 12” above the
bottom of the vessels.
Note: When Two-phase Production Traps are provided with provisions and
connections (e.g. water outlet nozzle, weir support, interface level tap
connections, etc.) to allow future conversion of the vessel into a
three-phase separator, the basis for vessel sizing shall be evaluated
and concurred by P&CSD.
7.4.9 Whenever possible, the nozzles for the oil level instruments shall not
be taken from the bottom of the vessel. However, when used, bottom
vessel connections shall include an internal nozzle extension to reduce
bottom solids from entering the standpipe.
7.4.11 The selected Two-phase Production Trap’s size and design shall be
approved by P&CSD.
7.5.1 Low Pressure Degassing Tanks are low pressure fixed roof tank used
for crude degassing and to provide significant surge and hold-up time
to crude processing facilities.
7.5.4 The inlet and outlet nozzles of Low Pressure Degassing Tanks shall be
located on opposite sides in order to use the whole length (diameter) of
the tank and avoid internal channeling (see example in Figure 7.5).
Figure 7.5
7.5.5 Following are the minimum cumulative hold-up and surge time
requirements for Low Pressure Degassing Tanks (see Figure 7.6):
Between High Liquid Level alarm and Low Liquid Level alarm: 1
hour
Between High Interface and Low Interface alarms: 30 minutes
Saudi Aramco: Company General Use
Page 24 of 52
Document Responsibility: Oil and Gas Process Engineering Standards Committee SAES-A-010
Issue Date: 24 May 2018
Next Planned Update: 24 May 2021 Gas Oil Separation Plants (GOSPs)
Figure 7.6
7.5.8 Low Low Liquid Level shall be minimum 3.3 feet (1 meter) above High
Interface Liquid Level.
7.5.9 The bottom of the feed inlet distributor of each Low Pressure Degassing
Tank shall be at least 3.3 feet (1 meter) above the High High Liquid
Level shutdown (HHLL).
7.5.11 CFD shall be performed on each Low Pressure Degassing Tank during
Detailed Design by Tank’s internals supplier in order to confirm design
of Tank’s internals (e.g. inlet device, baffles, etc.) and avoid internal
channeling.
7.5.12 Bolting for inlet device and supporting frame shall use locknuts or
double nuts with tack weld to avoid loosening due to the dynamic
loads from the slugs. The bolting arrangement shall be reviewed and
concurred by CSD / Pressure Vessels and Tanks Group.
7.5.13 The selected Low Pressure Degassing Tank’s size and design shall be
approved by P&CSD.
7.5.14 All Low Pressure Degassing Tank internals shall be removable and
pass through manways.
7.6.2 Crude charge pumps shall be vertical can type and shall be designed in
accordance with SAES-G-005.
7.6.4 Crude charge pump discharge pressure at pump shut-off shall not
exceed the design pressure of the dehydrator and desalter vessels.
7.6.5 Crude charge pump seals shall be flushed by dry crude oil or other
suitable buffer fluid.
7.8.1 For GOSPs processing AXL and AL crude grades, minimum two stage
dehydration/desalting shall be provided to minimize instances of off-
Saudi Aramco: Company General Use
Page 26 of 52
Document Responsibility: Oil and Gas Process Engineering Standards Committee SAES-A-010
Issue Date: 24 May 2018
Next Planned Update: 24 May 2021 Gas Oil Separation Plants (GOSPs)
7.8.2 For GOSPs processing AM and AH crude grades minimum three stage
dehydration/desalting shall be provided.
Note: For ASL crude grade and Gas Condensate (e.g. Khuff Condensate)
processing, the need of crude desalting shall be evaluated and
concurred by P&CSD on case by case.
7.8.4 Dehydrators and 1st Stage Desalters shall be designed for 30% water
cut at full design crude rate. Two different interface level control
valves shall be installed in parallel to cover low and high water cut
ranges.
7.8.5 The dry crude viscosity in all desalting vessels shall be below 10 cP
and preferably below 5cP. The feed to the dehydrator/desalter shall be
heated to achieve the desired viscosity.
7.8.7 The operating pressure of the last stage desalting vessel shall be at least
25 psig above the vapor pressure of the crude at the operating
temperature. Power to the electrical grids shall be switched off after a
time delay of 20 sec if the last stage desalter pressure drops to 10 psig
above the crude vapor pressure. The system shall be designed to allow
for a 20 sec delay for 10 psi below vapor pressure.
Figure 7.7
Figure 7.8
- If 3 independent grid sections are provided, each section shall cover
one third of the vessel length and shall be connected to only one
transformer (see example in Figure 7.9).
Figure 7.9
7.8.16 Carbon Steel Plate electrostatic grids shall be provided for AC/DC and
Modulated AC/DC. The electrode plates shall be oriented transverse
the length of the Dehydrator/Desalter and installed vertically. The use
of AC/DC Technologies shall be limited to 0-10% water cut due to
lack of arc control which could potentially damage the carbon steel
plates. The Modulated AC/DC Technologies are equipped with arc
control and additionally will drop out majority of the water before it
reaches the grids. Composite plates shall not be used due to the short
service life.
7.8.17 Oil immersed High pressure entrance bushings rated above the
maximum secondary voltage of the transformer shall be provided to
connect the transformer secondary to the vessel internal grids.
7.8.18 Vessel nozzle size for the entrance bushing shall be minimum 6”, 300#
rating. The vessel nozzle connected to the entrance bushing standpipe
shall be equipped with a vent to eliminate vapor. The vent can be either
welded directly on the nozzle flange or on a spacer installed between
the vessel nozzle and entrance bushing standpipe (see examples in
Figure 7.10). The vent shall be connected to the oil outlet pipe.
Figure 7.10
7.8.24 Internal interface skimming header and water (sand) jetting header
shall be provided.
7.8.25 All dehydrator / desalter internal piping except the oil outlet manifold
shall be internally and externally coated in accordance with SAES-H-
002.
7.8.31 For Modulated AC/DC Technologies the control system cabinet and
station shall be installed indoor and all feed-back signals and control
signals that are displayed in the control system panel shall be
interfaced to the DCS system.
7.8.32 All GOSPs shall be provided with an off-spec recycle line at the outlet
of the Desalters to recycle off-spec crude during plant start-up. The
off-spec recycle line shall be internally coated in accordance with
SAES-H-001 and SAES-H-002 requirements.
7.8.34 Online BS&W analyzer shall be provided at the outlet of the desalter.
Insertion type sample take off installed on vertical main pipe shall be
provided for representative stream. BS&W analyzers shall be designed
in accordance with SAES-J-510 requirements.
7.8.35 Manual sample points shall be installed on the same sampling line as
the BS&W Analyzer.
7.7.38 Desalter Effluent Treatment Unit for ground water conservation shall be
provided when required by SAES-A-012.
7.9.1 If crude oil stabilization is not done within the battery limits of the
GOSP, Trim Heat Exchangers shall be used to heat the wet crude to the
dehydrator/desalter to achieve the desired temperature and viscosity.
7.9.2 Hot oil or steam can be either used as heating medium for Trim Heat
Exchangers.
7.9.3 If crude oil stabilization is done within the battery limits of the GOSP,
then hot stabilized crude shall be used to heat the wet crude to the
dehydrator/desalter to achieve the desired temperature and viscosity. If
the hot stabilized crude is not sufficient to heat the wet crude and
achieve the desired temperature and viscosity, Trim Heat Exchangers
shall also be used in addition to Wet Dry Crude Heat Exchangers.
Note: If Trim Heat Exchangers are not installed, provisions and plot space
shall be provided for future installation.
7.9.4 If Wet Dry Crude and Trim Heat Exchanger are both provided. Wet/Dry
Crude Heat Exchanger shall be installed upstream of Low Pressure Degassing
Tank (if any) and Trim Heat Exchanger shall be installed upstream of
Dehydrator.
7.9.5 Wet Dry Crude and Trim Heat Exchangers shall be designed in a
staged manner with provisions and plot space to install additional units
for future water load increase.
7.9.6 Wet Dry Crude and Trim Heat Exchanger shall be designed in
accordance with SAES-E-004.
7.10.1 The type of booster (if applicable) and shipping pumps shall be
selected and designed in accordance with SAES-G-005.
7.11.1 Each GOSP gas compression stage shall be provided with its own
Suction KO Drum and After-cooler / Inter-cooler.
7.11.2 For compression stages in series within the same plant, the need for
dedicated Compressor Discharge KO Drum for each compression
section shall be reviewed with P&CSD based on amount of liquids
formed after compression and cooling.
7.11.4 Clearance distance between the top of the mist eliminator and the gas
outlet nozzle shall be selected to have a minimum angle of 45º as per
Figure 7.11.
Figure 7.11
7.11.9 CFD shall be performed on the Compressor Suction KO Drum with the
vessel’s internal supplier to confirm the internals selection and the
liquid removal efficiency over the full operating range.
7.12.1 GOSP’ Gas dehydration systems shall be provided for the following
applications:
In a GOSP equipped with Lift Gas Compression Systems for crude
producing wells.
In a GOSP exporting the compressed associated gas through a sub-
sea gas pipeline.
In a GOSP exporting the compressed associated gas through on-
shore gas pipelines:
7.12.4 Hydrocarbon dew point control units shall be designed to condition the
gas at a temperature 10 ºF lower than actual gas hydrocarbon dew-
point as predicted by Flow Assurance Study.
7.13.2 The spec breaks between two piping classes shall be shown on P&IDs.
7.13.4 All bypass lines of control valves, ESD valves, Relief valves and other
similar applications shall be sloped for self-draining on both sides.
8 Auxiliary Systems
8.1.1 Wash water systems design for crude oil desalting shall be performed
based on the following input:
- Crude oil rate
- Formation water TDS
- Wash water TDS
- BS&W at the inlet of Desalters
- BS&W and salt-in-crude specification of the desalted crude
- Mixing efficiency
8.1.2 Wash water can be supplied from aquifer wells, from water treatment
systems (e.g. Reverse Osmosis Plant), Desalination Plants or Flash
Evaporation Units.
8.1.5 50% mixing efficiency shall be considered for wash water systems
design.
8.1.6 High Efficiency Mixing Systems shall be installed for mixing wash
water and recycled water with the crude at the inlet of Dehydrators /
Desalters. Mixing pressure drop range shall be 7 - 11 psi.
8.1.10 The need for online oxygen analyzer for produced water streams shall
be evaluated during Design Basis Scoping Paper (FEL-2) and Project
Proposal (FEL-3). Online oxygen analyzer shall be designed in
accordance with SAES-J-510.
8.1.11 Minimum flow recycle line with flow control valve shall be provided
for wash water pumps to allow low wash water rates at low crude rates.
8.1.12 A gas blanketed surge drum or tank shall be provided to receive the
wash water from its source. The wash water shall be pumped from the
Wash Water surge drum or tank by the Wash Water pumps to the
desalting facility.
8.1.14 Jetting water header take off shall be upstream of the wash water flow
meter if wash water systems is supplied by aquifer water wells. If wash
water is supplied by water treatment systems, the desalter recycle
pump discharge water can be used as jetting water.
8.2.1 All GOSPs shall be provided with facilities for bulk storage (tanks) and
injection of Demulsifier, Corrosion Inhibitor and Scale inhibitor.
8.2.2 The need for Biocide, Oxygen Scavenger and Methanol injection
systems shall be evaluated on a case by case basis.
8.2.3 All chemical storage tanks and injection skids shall be located at one
location. Large chemical storage tanks shall be accessible for road
tankers.
8.2.5 Each chemical dosage point shall have its own dedicated pump or
pumps discharge manifold for dedicating the pumps to one injection
point. Each chemical dosage point shall be provided with a flow meter
to monitor the chemical dosage rate and Low Flow Alarm.
8.2.7 With the exception of Demulsifier and Methanol, all other chemical
dosage rates and injection locations shall be finalized in consultation
with CSD and Producing Department Corrosion Engineers. Refer to
SABP-A-018 and Refer to SABP-A-036.
8.2.10 Required space shall be provided for on-line coupon retrieval and
installation tools. Refer to SABP-A-018 and SABP-A-036.
8.2.12 Corrosion inhibitor injection systems inside GOSPs shall not be used
for injection points at the Remote Header.
8.2.13 Separate corrosion Inhibitor injection (Pump, flow meter and Injection
tubing) for the crude oil leaving the GOSP to the crude oil pipeline
shall be provided. Refer to SABP-A-015, SABP-A-018 and SABP-A-
036.
Note: To ensure good mixing the pipeline corrosion inhibitor injection point
can be upstream of the crude tie-line control Valve or suction of the
shipping pump.
8.2.19 All chemical injection skids shall be equipped with online remote
monitoring for flow rate, tank level and pump status.
8.2.20 Minimum one month storage capacity shall be provided for the
demulsifier based on demulsifier injection pump’s design rate.
8.3.1 Hot Oil fluids including Diesel can be used for heating the crude oil in
the GOSPs. Hot oil fluids shall be selected with low potential of
chemical degradation, low tendencies of scale and coke formation and
with an auto ignition temperature at least 90 ºF (50 ºC) above the max
operating temperature.
8.3.2 Hot Oil Expansion vessel shall be provided. The Hot oil Expansion
vessel shall be provided with inert gas blanket.
8.3.3 The Hot oil return shall flow into the Hot Oil Expansion vessel.
The Hot oil circulating pumps shall take suction from the Hot Oil
expansion vessel.
8.3.4 The hot oil pump suction temperature shall be connected to the DCS.
8.3.5 The wet crude shall be flowing through the tube side and the hot oil
through the shell side of the hot oil heat exchanger.
8.3.6 The Hot Oil fluid pressure shall be at least 50 psig higher than the cold
process fluid (wet Crude) pressure in the hot oil heat exchanger to
avoid chances of process fluids leaking into the hot oil system.
8.4.1 All on-shore GOSPs shall be provided with Closed Drain System per
SAES-A-400/SAES-A-401 and Oily Water Drain Systems per
SAES-S-020.
8.4.2 All off-shore GOSPs, Well Platforms shall be provided with Closed
Drain Systems per SAES-A-400/SAES-A-403 and Oily Water Drain
System per SAES-S-020.
Note: For existing GOSPs the conversion of the existing Pressure Sewer
and Gravity Sewer Systems into Closed Drain System and Oily
Water Drain System shall be evaluated on case by case basis.
8.4.3 The closed drain header from GOSP production manifold shall be run
separately to the CDS drum and shall not be connected with other low
pressure closed drain headers.
Saudi Aramco: Company General Use
Page 41 of 52
Document Responsibility: Process Engineering Standards Committee SAES-A-010
Issue Date: 24 May 2018
Next Planned Update: 24 May 2021 Gas Oil Separation Plants (GOSPs)
8.5.2 Plant air connection shall be provided at all utility stations besides
nitrogen, LP steam and water connections.
9 GOSP De-Bottlenecking
9.1 Process study (FEL-2 Study) shall be performed to identify process equipment
modifications to de-bottleneck processing facilities based on operating and
future crude production forecast.
9.2 Flare and Relief assessment shall be conducted to identify the required
modifications to the Flare and Blowdown System to support the modifications
of the main process systems.
9.4 If required hydraulic study shall be performed to identify any impact on the
downstream pipeline systems.
9.5 If it is required to exceed the GOSP nominal plant capacity without conducting a
process study, a Flare and Relief Capacity Assessment shall be conducted to
establish the maximum crude capacity of the GOSP and a Plant Test shall be
conducted (based on Flare and Relief capacity assessment) to identify equipment
limitations.
Revision Summary
Salt Mass Balance Templates are available in the Corporate Model Library by using the
following link: Corporate Model Library