Professional Documents
Culture Documents
Chapter 1: Introduction
Senior T. A. Abdul Ghani Noori
Kandahar University
Engineering Faculty
Energy Engineering Department 7-Sep-19
Objectives
Understanding the relevant codes and standards that assist in designing safe
electrical systems.
2 7-Sep-19
Table of Contents
1.1 Introduction
3 7-Sep-19
1.1 Introduction
In buildings, most energy end-use systems such as lighting, air conditioning
equipment, and appliances require electrical power to operate.
Electricity can cause serious injury or death for people and significant damages
for equipment and property.
For eliminating the danger of electricity, almost each country has electrical
codes, which are called National Electrical Code (NEC).
4 7-Sep-19
Cont.
The latest version of NEC (for USA) is organized in nine chapters:
6 7-Sep-19
Cont.
Commercial Buildings
The electrical power distribution systems for large commercial buildings utilize
several components, including a network of step-down transformers, lighting and
power panels, protection devices, grounding systems, and wiring methods as
shown in the following figure
7 7-Sep-19
Cont.
Distribution Voltages
The specific voltages distributed and served to buildings vary significantly
worldwide and depend on the building types as shown in the following table.
8 7-Sep-19
Cont.
It is important to note that electrical equipment and devices are generally
sensitive to changes in supply voltage and frequency levels.
The supply of high voltage level can cause higher currents to flow through
electrical devices.
Simply doubling the voltage can double the current and a larger current flow
can result in higher heat to be dissipated in the device Q ͌ I2 / Q = RI2
In fact, most electrical devices cannot operate reliably with supply voltage
levels that are higher than 10% of their rated voltage.
9 7-Sep-19
1.3 General Design Approach
In order to specify the components for electrical distribution systems for
buildings, it is important to determine all the end-use loads that need to be served
by electricity as well as their rated voltages and frequencies.
Safety: safety should be the most important objective for specifying various
components of the power distribution systems for buildings.
11 7-Sep-19
Cont.
Flexibility: the system should be able to handle additional electrical loads due to
future expansion and/or change of end-use equipment or loads.
12 7-Sep-19
Cont.
Accessibility: The components of the power distribution systems should be
designed to be easily accessible in order to facilitate their maintenance, repair,
and replacement.
13 7-Sep-19
Cont.
Reliability: Electrical distribution systems should be designed to ensure that
they operate reliably without interruption under normal loading conditions.
14 7-Sep-19
Cont.
Energy Efficiency: To ensure efficient use of electricity, specifying high energy-
efficient components for the power distribution system should be considered.
15 7-Sep-19
Cont.
Design Team
For the construction industry, there are several project delivery methodologies
depending on the budget and time constraints as well as desired risk and quality
levels:
Design-build (DB) method: the design and construction services are contracted
by a single entity.
IDB method follows the design through the entire project life, from pre-design
through occupancy and into operation.
16 7-Sep-19
Cont.
In both DB and IDB architect typically plays the role of the main coordinator of the
design team.
17 7-Sep-19
Cont.
General Design Procedure
When specifying buildings and their systems, including electrical distribution
components, there are typically several phases during the design process:
Project conceptualization
Construction administration
18 7-Sep-19
Cont.
Based on the DBB method, the job of electrical engineer in each of the design
phases are as outlined below:
Project conceptualization:
Develop an idea (concept) for a facility by an owner/developer.
Procure funding through bank loans or donations.
19 7-Sep-19
Cont.
20 7-Sep-19
Cont.
21 7-Sep-19
Cont.
22 7-Sep-19
Cont.
23 7-Sep-19
Cont.
Construction administration
Plan and complete the ground breaking ceremony.
Finalize intermediate and final observations (i.e., punch-lists).
Prepare and finalize as-built documents..
24 7-Sep-19
Cont.
25
7-Sep-19
Cont. Riser Diagram Plan
26
7-Sep-19
Assignment-1
4-1, 4-5, 4-13, 4-21, 4-28, 4-35, 4-41, 4-44, 4-55, 4-59, 4-61, 4-65, 4,70,
4-, 4-72, 4-73, 4-79, 4-80 and 4-82.
Submit the assignment within one week from the date of completion.
27 7-Sep-19
Thank You!