SUMMARY

(By Contract)

Project : CONSTRUCTION OF 24 CU.M. CONCRETE RESERVOIR

Location :
Date :

TOTAL ESTIMATED DIRECT COST: INDIRECT COST:


Materials P 613,408.85 OCM (10% of EDC) P 8,829.77
Labor P 143,618.00 Profit (8% of EDC) P 69,950.15
Equipment Rental P 116,200.00 P 78,779.92
Fuel / Oil P 9,750.00
P 882,976.85

VAT:

5% of Estimated Direct Cost P 44,148.84


5% of Indirect Cost P 3,939.00
P 48,087.84

BUDGET FOR THE CONTRACT ------------------------------------------------------------------------------- P 1,009,844.61