You are on page 1of 225

DAFTAR HARGA SEWA ALAT BERAT

TAHUN 2019

HARGA
NO NAMA BARANG SATUAN
Rp
1 2 3 4

1 Asphalt Mixing Plant Jam 5,146,022.47


2 Asphalt Finisher Jam 507,700.00
3 Asphalt Sprayer Jam 115,346.00
4 Bulldozer 100-150 HP Jam 435,566.00
5 Compressor 4000-6500 L\M Jam 170,800.00
6 Concrete Mixer 0.3-0.6 M3 Jam 85,573.00
7 Mixer Kyukuto Hino Kapasitas 7 m3 / 25 hari 95,000,000.00
kerja / 200
jam
8 Mixer Kyukuto Hino Kapasitas 2,5 m3 / 25 hari 62,500,000.00
kerja / 200
jam
9 Crane 10-15 TON Jam 521,072.00
10 Dump Truck 3-4 M3 Jam 249,651.00
11 Dump Truck Jam 387,651.00
12 Excavator 80-140 HP Jam 470,000.00
13 Flat Bed Truck 3-4 M3 Jam 373,577.00
14 Generator Set Jam 419,800.00
15 Motor Grader >100 HP Jam 455,299.00
16 Track Loader 75-100 HP Jam 378,324.00
17 Wheel Loader 1.0-1.6 M3 Jam 335,000.00
18 Loader WA 200-1 / 25 hari
kerja / 200
jam
19 Sift Loader dengan Crane / Hiap Crane 8 ton / 8 jam 4,500,000.00
20 Sift Loader dengan Crane / Hiap Crane 5 ton / 8 jam 3,880,000.00
21 Dolly Scania 18 ton / 8 jam 3,885,000.00
22 Three Wheel Roller 6-8 T Jam 302,037.00
23 Tandem Roller 6-8 T. Jam 320,300.00
24 Tire Roller 8-10 T. Jam 298,200.00
25 Vibratory Roller 5-8 T. Jam 497,000.00
26 Concrete Vibrator Jam 50,200.00
27 Stone Crusher Jam 735,332.00
28 Water Pump 70-100 mm Jam 46,600.00
29 Water Tanker 3000-4500 L. Jam 253,386.00
30 Pedestrian Roller Jam 74,338.00
31 Tamper Jam 58,096.00
32 Jack Hammer Jam 78,800.00
33 Fulvi Mixer Jam 148,400.00
34 Concrete Pump Jam 308,178.00
35 Concrate Pump Standart IHI IPF 8E 21, 21 m / 25 hari 65,000,000.00
kerja / 200
jam
HARGA
NO NAMA BARANG SATUAN
Rp
1 2 3 4
36 Concrate Pump Long Boom IHI IPF 8 N 29, 29 m / 25 hari
kerja / 200 60,000,000.00
jam
37 Concrate Pump Mini IHI IPN4N17, 17 m / 25 hari
kerja / 200 50,000,000.00
jam
38 Trailer 20 TON Jam 285,292.00
39 Pile Driver + Hammer Jam 193,967.00
40 Crane on Track 35 TON Jam 399,665.00
41 Welding Set Jam 165,293.00
42 Bore Pile Machine Jam 993,707.00
43 Asphalt Liquid Mixer Jam 85,865.00
44 Trailer Jam 355,050.00
45 Cold Milling Jam 493,500.00
46 Rock Drill Breaker Jam 60,810.00
47 Alat Stressing Jam 13,500.00
48 Alat Grouting Jam 18,000.00
49 Baro Mixer Jam 65,000.00
50 Bole Mixer Jam 65,000.00
51 Prenater Jam 65,000.00
52 Asphalt Cutter Jam 62,111.00
53 Concrete Pan Mixer Jam 456,635.00
54 Truck Mixer Jam 546,182.00
55 Blending Equipment Jam 192,768.87
56 Asphalt Distributor Jam 348,305.00
57 Crane Tadano Bulan 115,000,000.00
58 Crane Tadano Bulan 97,000,000.00
59 Crane Tadano Bulan 90,000,000.00
60 Crane Tadano Bulan 85,000,000.00
61 Crane Tadano Bulan 60,000,000.00
62 Crane Tadano Hari 15,000,000.00
63 Crane Tadano Hari 10,000,000.00
64 Crane Tadano Hari 9,500,000.00
65 Crane Tadano Hari 8,500,000.00
66 Crane Tadano Hari 7,000,000.00
67 Excavator PC.200-8 / MO Jam 570,000.00
68 Excavator PC.200-8 / MO Jam 500,000.00
69 Mobilisasi Excavator PC.200-8 (Denpasar, Kuta, Nusa Dua) LS 4,000,000.00
70 Excavator PC.78 UU (breaker) Jam 450,000.00
71 Excavator PC.78 UU (bucket) Jam 390,000.00
72 Mobilisasi Excavator PC.78 UU (Denpasar, Kuta, Nusa Dua) LS 2,500,000.00
73 Sewa TC Potain MC 205B made in Prancis, jib length 60 m Bulan 120,000,000.00
kapasitas 2,4 ton
74 Jaminan Angkur TC Potain MC 205B Set 60,000,000.00
75 Pasang Angkur TC Potain MC 205B Set 6,500,000.00
76 Erexsion TC Potain MC 205B Set 50,000,000.00
HARGA
NO NAMA BARANG SATUAN
Rp
1 2 3 4
77 Dismantling Normal TC Potain MC 205B Set 50,000,000.00
78 Mob-Demob TC Potain MC 205B wilayah Bali Set 95,000,000.00
79 Gaji Operator TC Potain MC 205B / bulan 3,500,000.00
80 Sewa Mesin Bor Jam 65,000.00
81 Alat Bantu Pekerjaan Pengeboran Bored Pile LS 4,500,000.00
82 Batching Plant (di luar genset, listrik dan loader) / 1 bulan / 30 115,000,000.00
Hari

Catatan : Harga Belum Termasuk PPN dan Apabila dikemudian hari terdapat kekeliruan, akan dilakukan revisi /
penyesuaian
DAFTAR HARGA SEWA
SCAFOLDING
KOTA DENPASAR TAHUN 2019

HARGA
NO NAMA BAHAN SAT
(RP)
1 2 3 4
1 Main Frame m3 7,500.00
2 Cross brace 220 m3 4,500.00
3 End Frame m3 5,500.00
4 Join Pen m3 1,500.00
5 U-Head m3 4,500.00
6 Jack Base m3 4,500.00
DAFTAR HARGA SATUAN BAHAN
TAHUN 2019

A. Harga Satuan Bahan

NAMA TOKO
HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp) UD. Astiti Merta TB. Aneka Makmur UD. Kusuma Indah

1 2 3 4 5 6 7 8 9 10 11

BIDANG UMUM
1 Jaring Sungar m2 170,000.00 165,000.00 150,000.00 170,000.00
2 Tali Seling m' 9,500.00 8,000.00 7,500.00 9,500.00
3 Tali m' 5,600.00 4,500.00 5,000.00 5,600.00
4 Sekop Datar bh 165,000.00 145,000.00 165,000.00 150,000.00
5 Selang Air m' 8,000.00 7,500.00 7,000.00 8,000.00
6 Terpal m2 9,500.00 8,500.00 9,000.00 9,500.00

BIDANG BINA MARGA


1 Uditch 1000 x 1000 x 1200 K 350 unit 1,950,000.00 1,950,000.00 1,900,000.00
2 Uditch 1200 x 1200 x 1200 K 350 unit 2,950,000.00 2,820,000.00 2,950,000.00 2,900,000.00
3 Plat Penutup 400 x 1200 K 350 unit 450,000.00 450,000.00 500,000.00 475,000.00
4 Plat Penutup 1200 x 1200 x 1200 K 350 unit 1,250,000.00 1,250,000.00 1,350,000.00 1,370,000.00
5 Frame Manhole 1200 x 1200 unit 950,000.00 965,000.00 970,000.00 950,000.00
6 Cover Manhole 1200 x 1200 unit 950,000.00 965,000.00 970,000.00 950,000.00
7 Abu Batu m3 256,000.00 255,000.00 265,000.00

BAHAN K3
A Alat Pelindung Diri
1 Topi Pelindung (safety Helmet) bh 55,000.00 50,000.00 45,000.00 55,000.00
2 Pelindung Mata (Goggles, Spectacles) bh 95,000.00 80,000.00 95,000.00
3 Tameng Mata (face Shield) bh 215,000.00 215,000.00
4 Masker Selam (Breathing Apparatus) bh 350,000.00 340,000.00 350,000.00
5 Pelindung Telinga (Ear Plug, Ear Muff) bh 250,000.00 211,000.00 250,000.00
6 Pelindung Pernafasan dan Mulut (Masker) bh 45,000.00 45,000.00 40,000.00
7 Sarung Tangan (Safety Gloves) bh 40,000.00 30,000.00 35,000.00 40,000.00
8 Penunjang Seluruh Tubuh (Full Body Harness) bh 130,000.00 100,000.00 110,000.00 130,000.00
9 Jaket Pelampung (Life Vest) bh 150,000.00 140,000.00 145,000.00 150,000.00
10 Celemek (Apron/Coverralls) bh 90,000.00 77,500.00 87,000.00 90,000.00
11 Pelindung Jatuh (Fall Arrester) bh 990,000.00 770,000.00 990,000.00

B Rambu-Rambu K3 bh 150,000.00 150,000.00


1 Rambu Petunjuk bh 150,000.00 150,000.00
2 Rambu Larangan bh 150,000.00 150,000.00
3 Rambu Peringatan bh 150,000.00 150,000.00
4 Rambu Kewajiban bh 150,000.00 150,000.00
5 Rambu Informasi bh 150,000.00 150,000.00
6 Rambu Pekerjaan Sementara bh 150,000.00 150,000.00
7 Tongkat Pengatur Lalu Lintas (Warning Light Stck) bh 60,000.00 53,000.00 60,000.00
8 Kerucut Lalu Lintas (Traffic Cone) bh 125,000.00 115,000.00 125,000.00
9 Lampu Putar (Rotary Lamp) bh 97,000.00 95,000.00 95,000.00 97,000.00
10 Lampu Selang Lalu Lintas bh

C Pengendaliang Resiko K3
1 Alat Pemadam Api Ringan (APAR) bh 550,000.00 450,000.00 550,000.00
NAMA TOKO
HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp) UD. Astiti Merta TB. Aneka Makmur UD. Kusuma Indah

1 2 3 4 5 6 7 8 9 10 11
2 Sirine bh 450,000.00 400,000.00 450,000.00
NAMA TOKO
HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp) UD. Astiti Merta TB. Aneka Makmur UD. Kusuma Indah

1 2 3 4 5 6 7 8 9 10 11
3 Bendera K3 bh
4 Lampu Darurat (Emergency Lamp) bh 170,000.00 162,000.00 170,000.00

BAHAN TAMBAHAN
1 List Gypsum Profil 5 cm m' 11,500.00 11,000.00 11,500.00
2 Bubungan Genteng glazur bh 44,651.10 41,730.00 44,651.10
3 Tempat Sabun bh 149,800.00 149,800.00 151,000.00 150,000.00
4 Kusen Aluminum m' 110,000.00 110,000.00 115,000.00
5 Rangka Jendela Aluminium m' 115,500.00 115,500.00 115,500.00 117,000.00
6 Rangka Pintu Aliminium m' 121,000.00 121,000.00 125,000.00
7 Door Stoper bh 210,000.00 200,000.00 210,000.00 215,000.00
8 Door Closer bh 380,000.00 375,000.00 380,000.00 385,000.00
9 Kusen dan Pintu PVC Toilet unit 800,000.00 750,000.00 755,000.00 800,000.00
10 Genteng Keramik ex Jatiwangi bh 7,500.00 7,000.00 7,500.00
11 Genteng Keramik Glazur ex KANMURI bh 22,500.00 22,500.00 24,000.00
12 Nok Genteng Keramik EX Jatiwangi bh 42,000.00 40,000.00 42,000.00
13 Nok Genteng Keramik Ex Kanmuri bh 47,000.00 45,000.00 47,000.00
14 Kran Zink bh 485,000.00 485,000.00 490,000.00 485,000.00
15 Kran Dinding bh 240,000.00 240,000.00 245,000.00 240,000.00
16 Kitchen Zink bh 850,000.00 800,000.00 785,000.00 850,000.00
17 Floor Drain bh 110,000.00 110,000.00 112,000.00 110,000.00
18 Bak Air Fibergles bh 395,000.00 380,000.00 385,000.00 395,000.00
19 Klep Diameter 3/4" bh 112,000.00 110,000.00 114,000.00 112,000.00
20 Tangkin Air 1000 Liter bh 1,850,000.00 1,850,000.00 1,870,000.00 1,900,000.00
21 Tangki Air 500 Liter bh 845,000.00 850,000.00 835,000.00 845,000.00
22 Pelampung Otomatis bh 170,000.00 155,000.00 165,000.00 170,000.00
23 Roof Drain Metal bh 97,000.00 95,000.00 98,000.00 97,000.00
24 Mesin Jet Pump kap 250 watt ex Grounfos bh 5,600,000.00 5,650,000.00 5,700,000.00 5,600,000.00
25 Mesin Pompa Tekan kap. 150 watt ex Grounfos bh 3,450,000.00 3,500,000.00 3,550,000.00 3,450,000.00
26 Box Panel PVC isi 4 MCB ex Legran bh 210,000.00 190,000.00 195,000.00 210,000.00
27 MCB 6 A ex Legran bh 52,000.00 50,000.00 55,000.00 52,000.00
28 MCB 4 A ex Legran bh 48,000.00 45,000.00 47,000.00 48,000.00
29 Kabel telephone 4 x 0.5 mm m' 22,000.00 14,000.00 17,000.00 22,000.00
30 Oulet TV Broco bh 220,000.00 210,000.00 215,000.00 220,000.00
31 Outlet Telephone bh 230,000.00 220,000.00 225,000.00 230,000.00
32 Dowlight/PLC 13 W bh 62,000.00 65,000.00 60,000.00 62,000.00
DAFTAR HARGA SATUAN BAHAN
TAHUN 2019

NAMA TOKO
Keterangan

12 13 14
NAMA TOKO
Keterangan

12 13 14
NAMA TOKO
Keterangan

12 13 14
DAFTAR HARGA SATUAN BAHAN
TAHUN 2019

A. Harga Satuan Bahan

NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9

BATU KALI DAN BATU ALAM


1 Batu Kali/batu bulat 15-30 cm m3 305,000.00 574,200.00 305,000.00 308,000.00
2 Batu Belah 1.0-5.0 cm m3 345,000.00 594,000.00 350,000.00 345,000.00
3 Batu Pecah Besar 15/30 cm m3 205,000.00 462,000.00 205,000.00 208,000.00
4 Batu Pecah 5/7 cm m3 310,000.00 607,200.00 310,000.00 315,000.00
5 Batu Pecah 3/5 cm m3 316,000.00 462,000.00 316,000.00 318,000.00
6 Batu Pecah 3-4 cm m3 335,000.00 613,800.00 345,000.00 335,000.00
7 m3 396,000.00 620,400.00 398,000.00 396,000.00
8 Batu Pecah Mesin 1 - 2 cm m3 475,000.00 495,000.00 485,000.00 475,000.00
9 Batu Pecah 2-3 cm m3 450,000.00 620,400.00 450,000.00 460,000.00
10 Batu Pecah 1 - 2 cm m3 550,000.00 858,000.00 550,000.00 570,000.00
11 Batu Pecah 0,5 - 1 Cm m3 385,000.00 462,000.00 385,000.00 390,000.00
12 Batu Alam Andesit Bintik Bakar 40 x 40 m2 116,000.00 23,111.88 118,000.00 116,000.00
13 Batu Alam Andesit Alur m2 120,000.00 235,356.00 125,000.00 120,000.00
14 Batu Alam Live Grendia m2 119,000.00 162,360.00 210,000.00 119,000.00
15 Batu Candi m2 125,000.00 148,500.00 125,000.00 125,000.00
16 Batu Candi Hitam (Ukuran 30 x 30 x 2 Cm) Cirebon m2 112,000.00 151,800.00 115,000.00 112,000.00
17 Batu Candi Hitam (Ukuran 30 x 30 x 3 Cm) Cirebon m2 162,000.00 219,120.00 172,000.00 162,000.00
18 Batu Candi Hitam (Ukuran 30 x 30 x 5 Cm) Cirebon m2 238,000.00 316,800.00 240,000.00 238,000.00
19 Batu Candi Hitam (Ukuran 20 x 20 x 2 Cm) Cirebon m2 99,500.00 139,920.00 110,000.00 99,500.00
20 Batu Candi Hitam (Ukuran 20 x 30 x 5 Cm) Cirebon m2 218,000.00 300,696.00 218,000.00 219,000.00
21 Batu Putih Jogya / Palimanan (30 x 30 x 2 Cm) m2 107,000.00 141,240.00 110,000.00 107,000.00
22 Batu Putih Jogya / Palimanan (30 x 30 x 3 Cm) m2 148,000.00 195,360.00 151,000.00 148,000.00
23 Batu Putih Jogya / Palimanan (30 x 30 x 5 Cm) m2 214,000.00 290,400.00 218,000.00 214,000.00
24 Batu Alam Palimanan Putih Super m2 118,000.00 161,700.00 125,000.00 118,000.00
25 Batu hitam Jember 5 x 20 halus m2 89,500.00 117,150.00 90,000.00 89,500.00
26 Batu hitam Jember 20 x 40 halus m2 94,500.00 125,400.00 110,000.00 94,500.00
27 Batu hitam Jember 15 x 30 halus m2 88,500.00 115,869.60 91,000.00 88,500.00
28 Batu hitam Singaraja 15 x 30 halus m2 95,000.00 125,400.00 198,000.00 95,000.00
29 Batu hitam Singaraja 20 x 40 halus m2 90,000.00 125,400.00 98,000.00 90,000.00
30 Batu hitam karangasem/Batu Tabas (20 x 40 x 3) m2 160,000.00 792,000.00 165,000.00 160,000.00
31 Paras Silakarang Tipis (Ukuran 15 x 30 x 5 Cm) m2 318,000.00 422,400.00 320,000.00 318,000.00
32 Paras Silakarang Tebal (Ukuran 15 x 30 x 8 Cm) m2 348,500.00 462,000.00 350,000.00 348,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
33 Batu Paras Bali/Pawon (Abu - Abu Terang) m2 274,000.00 359,040.00 274,000.00 280,000.00
34 Paras Kelating / Kerobokan (Ukuran 3 x 20 x 40 Cm) bh 10,000.00 19,800.00 17,000.00 10,000.00
35 Batu pilah m2 125,000.00 132,000.00 125,000.00 127,000.00
36 Batu pilah Singaraja 30 x 30 m2 130,000.00 124,812.60 130,000.00 135,000.00
37 Batu pilah Singaraja 20 x 20 m2 117,000.00 117,189.60 117,000.00 118,000.00
38 Split Kasar m3 320,000.00 562,320.00 320,000.00 325,000.00
39 Split Halus m3 312,000.00 607,200.00 312,000.00 318,000.00
40 Koral Beton diameter 1 - 2 cm m3 412,000.00 858,000.00 412,000.00 415,000.00
41 Batu Sikat Hitam Lokal Super kampil 95,000.00 144,804.00 95,000.00 98,000.00
42 Batu Sikat Akik Merah kampil 25,000.00 36,498.00 25,000.00 27,000.00
43 Batu Sikat Putih Salju kampil 35,000.00 56,166.00 35,000.00 35,000.00
44 Koral Sikat (Lokal) sak 55,000.00 66,000.00 55,000.00 57,000.00
45 Kerikil m3 410,000.00 510,000.00 410,000.00 420,000.00
46 Kerikil Beton m3 500,000.00 780,000.00 550,000.00 500,000.00
47 Kerikil Halus m3 420,000.00 540,000.00 420,000.00 425,000.00
48 Pasir Halus m3 258,000.00 627,000.00 258,000.00 258,000.00 261,000.00
49 Pasir Pasang m3 215,000.00 541,200.00 215,000.00 218,000.00
50 Pasir Cor m3 195,000.00 501,600.00 200,000.00 195,000.00
51 Pasir Urug m3 195,000.00 462,000.00 195,000.00 198,000.00
52 Tanah Urug m3 149,000.00 243,210.00 150,000.00 149,000.00
53 Tanah Urug Pilihan 125,000.00 189,600.00 125,000.00 130,000.00
54 Tanah Lempung m3 118,000.00 112,800.00 118,000.00 120,000.00
55 Sirtu m3 248,000.00 432,960.00 248,000.00 251,000.00
56 Batu Karang Bukit m3 318,000.00 283,800.00 318,000.00 319,000.00
57 Limestone m3 185,000.00 244,860.00 185,000.00 189,000.00
58 Abu Bata 450,000.00 576,000.00 450,000.00 450,000.00
59 Batako Lubang bh 2,700.00 4,620.00 2,700.00 3,000.00
60 Batako Buntu bh 2,800.00 4,686.00 2,800.00 2,800.00 3,100.00
61 Batu Bata bh 1,200.00 3,049.20 1,200.00 1,200.00 1,500.00
62 Bata Ringan setara falcon uk. 75 x 200 x 500 mm m3 785,000.00 1,295,910.00 785,000.00 885,000.00 875,000.00
63 Bata Ringan setara falcon uk. 100 x 200 x 600 mm m3 785,000.00 1,295,910.00 785,000.00 895,000.00 898,000.00
64 Bata Ringan setara falcon uk. 125 x 200 x 600 mm m3 795,000.00 1,295,910.00 795,000.00 893,000.00 899,000.00
65 Bata Ringan setara falcon uk. 150 x 200 x 600 mm m3 950,000.00 1,317,360.00 950,000.00 952,000.00 958,000.00
66 Bata Merah Klas I bh 2,800.00 5,544.00 2,800.00 2,900.00
67 Bata Merah Klas II bh 2,900.00 4,851.00 2,900.00 2,950.00
68 Bata Merah Klas III bh 2,950.00 3,465.00 2,950.00 3,000.00
69 Bata Merah Super (Pripian) ex tulikup bh 6,500.00 8,108.76 6,500.00 7,000.00
70 Bata Pres 22x10x6cm bh 3,400.00 4,147.44 3,400.00 3,600.00
71 Bata Pres 22x10x5cm bh 4,000.00 4,356.00 4,000.00 4,500.00
72 Batu Gosok bh 11,000.00 11,484.00 35,000.00 38,000.00 39,000.00
73 Filler kg 40,000.00 52,800.00 40,000.00 45,000.00 46,000.00
74 Additive liter 18,000.00 18,000.00 45,000.00 50,000.00 50,000.00
75 Agregat m3 300,000.00 330,000.00 300,000.00 320,000.00
76 Closeter bh 100,000.00 103,686.00 100,000.00 150,000.00
77 Lis Batu Alam L=7, T=40 bh 5,500.00 35,065.80 5,500.00 7,000.00
78 Lem Batu Alam kaleng 55,000.00 73,128.00 55,000.00 55,000.00 60,000.00
79 Coating (CP.27) kaleng 73,000.00 73,128.00 89,000.00 95,000.00 96,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
SEMEN
80 PC. Tiga Roda 50 Kg sak 75,000.00 98,753.16 75,000.00 76,000.00 76,000.00
81 PC Tiga Roda 40 Kg sak 50,000.00 79,200.00 50,000.00 52,000.00 54,000.00
82 PC. Tonasa 50 Kg / Busoa 50 Kg sak 47,000.00 95,634.00 47,000.00 48,000.00 49,000.00
83 PC. Gresik 40 Kg sak 50,000.00 80,520.00 50,000.00 52,000.00 53,000.00
84 PC. Gresik 50 Kg sak 63,000.00 100,980.00 63,000.00
85 PC Rajawali 40 Kg sak 46,500.00 69,300.00 46,500.00 49,500.00 50,000.00
86 PC Holcim 40 Kg sak 45,000.00 45,000.00 48,000.00 49,000.00
87 PC Conch 40 Kg sak 43,500.00 43,500.00 46,000.00 48,000.00
88 Semen Gresik kg 1,250.00 2,046.00 50,000.00 54,000.00 55,000.00
89 Semen Tiga Roda kg 1,250.00 1,980.00 50,000.00 54,000.00 56,000.00
90 Semen Tonasa kg 1,000.00
91 Semen Bosowa kg 1,150.00 1,980.00 46,000.00 48,000.00 49,000.00
92 Semen Holcim kg 1,150.00 1,980.00 46,000.00 48,000.00 49,000.00
93 Semen Conch kg 1,150.00 46,000.00 48,000.00 49,000.00
94 Semen Warna MU 408/ Nat kg 14,000.00 36,960.00 14,000.00 16,000.00 18,000.00
95 Semen Tipe V kg 3,000.00 3,168.00
96 Semen Portland kg 2,300.00 2,337.72

Mortar Utama
97 ThinBedMAX/Perekat Bata Ringan (MU 380) @40 Kg sak 128,000.00 194,040.00 128,000.00 131,000.00 130,000.00
98 PlasterPlus/Pas. Bata & Plester (MU-301) @40 kg sak 86,200.00 130,680.00 86,200.00 87,000.00 88,000.00
99 Plester premium (MU-100)@ 40 kg sak 91,000.00 145,200.00 91,000.00 93,000.00 94,000.00
100 Finish Plesteran/ Render (MU 290)@ 40 kg sak 159,500.00 246,840.00 159,500.00 161,000.00 161,500.00
101 SkimWall/Acian Plesteran & Beton (Skimcoat) 20 kg (MU-200) sak 72,000.00 105,600.00 72,000.00 73,000.00 74,000.00
102 SkimWall/Acian Plesteran & Beton (Skimcoat) 40 kg (MU-200) sak 136,500.00 198,000.00 136,500.00 140,000.00 142,000.00
103 Acian Putih (MU-270)@25 kg sak 152,000.00 231,000.00 152,000.00 153,000.00 160,000.00
104 Perata Lantai (MU-440)@40kg sak 90,000.00 131,788.80 90,000.00 91,000.00 94,000.00
105 Perata Lantai Expose (MU 445) 40 kg sak 171,000.00 258,192.00 171,000.00 172,000.00 174,000.00
106 Self Leveling Floor /Underlayment (MU-410) @25kg sak 146,000.00 409,860.00 146,000.00 148,000.00 150,000.00
107 Primer Self Leveling Floor (MU-L410) @ 5lt Set 75,000.00 458,040.00 75,000.00 76,000.00 78,000.00
108 Floor Hardener (MU 700) 25 kg sak 140,000.00 209,880.00 140,000.00 141,000.00 142,000.00
109 Granitfix/Perekat Granite Tile & Batu Alam (MU-400) @25kg sak 117,000.00 180,840.00 117,000.00 118,000.00 119,000.00
110 Cerafix/Perekat Keramik (MU-420)@25 kg sak 82,000.00 125,136.00 82,000.00 83,000.00 84,000.00
111 Poolfix White/Perekat keramik area terendam (MU-460)@25 kg sak 385,000.00 592,812.00 385,000.00 390,000.00 391,000.00
112 Renofix/Perekat keramik diatas keramik (MU-480)@25 kg sak 231,000.00 355,212.00 231,000.00 232,000.00 233,000.00
113 Powerfix Flex/Perekat keramik serba guna (MU-485)@25 kg sak 298,000.00 454,740.00 298,000.00 298,000.00 299,000.00
114 Rapidfix Flex/Perekat keramik Fast Setting (MU-490)@25 kg sak 300,000.00 491,832.00 310,000.00 300,000.00 320,000.00
115 Colorfill/ Pengisi nat interior & eksterior (MU-408C) kg 9,200.00 16,500.00 9,200.00 9,500.00 10,000.00
116 ColorPlus/Pengisi nat interior,eksterior,area basah(MU-408P) kg 16,000.00 28,380.00 16,000.00 17,000.00 18,500.00
117 Glliter/Pengisi nat dengan efek Glliter (MU-408G)@ 2kg set 30,000.00 235,884.00 30,000.00 31,000.00 32,000.00
118 PowerPool/Pengisi nat area terendam(MU-408PP)@2kg set 87,000.00 126,852.00 87,000.00 88,000.00 89,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
119 FixGrout/Perbaikan struktur beton (MU-800)@20kg sak 79,500.00 118,800.00 79,500.00 81,500.00
120 PatchCrete/Perbaikan permukaan beton(MU-830)@40kg sak 248,000.00 378,180.00 248,000.00 249,600.00
121 SkimRep/Perbaikan permukaan acian(MU-840)@25kg sak 231,000.00 470,052.00 231,000.00 233,500.00
122 DryShield/Pelapis kedap air (MU-600)@3kg set 101,000.00 156,420.00 101,000.00 105,000.00
123 ArcyBond/Perekat Mortar & Beton akrilik (MU-L500)@900ml set 40,000.00 48,180.00 40,000.00 42,000.00

Uzin
124 Beton Instan (UZ K300) 50 kg sak 110,000.00 110,600.16 135,000.00 138,000.00
125 Plester dinding instan (UZ Plester) 50 Kg sak 80,000.00 109,148.16 80,000.00 82,000.00
126 Plester Finish tanpa Aci (UZ Render) 50 kg sak 120,000.00 139,574.16 120,000.00 121,000.00
127 Acian diatas beton (UZ SC100) 40 kg sak 101,000.00 155,713.80 101,000.00 102,000.00
128 Acian dinding instan interior (UZ SC 50) 40 kg sak 118,000.00 145,259.40 118,000.00 119,000.00
129 Acian dinding instan eksterior (UZ SC 75) 40 kg sak 120,500.00 148,170.00 120,500.00 122,000.00
130 Perekat Bata Ringan (UZ TB20) 50 kg sak 98,000.00 157,897.08 98,000.00 99,500.00

Bostik
Perekat Keramik & Batu Alam
131 Fix Crete 25kg sak 75,000.00 448,800.00 75,000.00 80,000.00
132 Fix all 20kg sak 85,000.00 207,476.28 85,000.00 86,000.00
133 Super Fix all 20kg sak 65,000.00 295,307.76 65,000.00 70,000.00
134 Super Fix all trade/white 20kg sak 265,000.00 358,513.32 265,000.00 268,000.00
135 Asaflex 45 kg (15lt +30 kgp) set 1,350,000.00 1,793,286.00 1,350,000.00 1,353,000.00
136 Mortar Fix 100kg set 151,000.00 1,985,676.00 151,000.00 153,000.00
137 Mortar Fix 50 kg set 860,000.00 1,913,340.00 860,000.00 865,000.00
138 Mortar Fix 5 kg set 90,000.00 1,131,240.00 90,000.00 93,000.00
139 Renofix 25 kg Zak 350,000.00 448,800.00 350,000.00 350,000.00
140 Grout ( Semen Nat) 20 kg sak 340,000.00 536,024.28 340,000.00 343,000.00
141 Grout ( Semen Nat) 1 kg sak 17,000.00 24,090.00 17,000.00 18,000.00
142 Liquid Grout Adictive (LGA) 20 Lt pail 951,000.00 1,291,374.48 951,000.00 961,000.00
143 Mega Lastic Acrilic Base 20Lt pail 951,000.00 1,291,374.48 951,000.00 961,000.00

Wall System
144 Skim Plas 25 Kg sak 70,000.00 156,057.00 70,000.00 75,500.00
145 Skim Crete 25 Kg sak 78,000.00 204,996.00 78,000.00 80,500.00
146 Fix. Plas 40 kg sak 65,000.00 142,560.00 65,000.00 70,000.00
147 Fix T. 40 kg sak 70,000.00 207,906.60 70,000.00 75,000.00

Waterproofing
148 Ultra Coat RC2 20 Lt pail 850,000.00 1,636,088.52 850,000.00 875,000.00
149 Boscosem Slury 33 Kg set 520,000.00 684,937.44 520,000.00 535,000.00
150 Damplix 2 20 kg set 355,000.00 2,136,761.88 355,000.00 365,000.00
151 Damplix 3 45 kg set 2,175,000.00 2,834,892.72 2,175,000.00 2,185,000.00
152 Damplix 3E 35 kg set 1,285,000.00 1,572,453.96 1,285,000.00 1,350,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
153 Boscoseal Tom (Wp membran Bakar) Uk. 1m x 10 m rol 950,000.00 1,244,451.12 950,000.00 960,000.00
154 Indo primer ( lapisan primer WP membran) 20 Lt pail 810,000.00 1,018,963.44 810,000.00 815,000.00
155 Integral Kristalisasi (Waterproofing kristal) 20 kg pail 1,625,000.00 2,186,647.32 1,625,000.00 1,725,000.00
156 Sika Top Seal Set 20 kg + cairan set 345,000.00 345,000.00 375,000.00 380,000.00

Sealent
156 No More Nail (320 GR) bh 80,600.00 106,920.00 82,000.00 81,500.00 80,600.00
157 Seal n Flex 1 (600 ML) bh 110,000.00 154,805.64 113,000.00 110,000.00 112,000.00
158 Boscosil 313 (300 ML) bh 60,000.00 80,388.00 60,000.00 65,000.00 67,000.00
159 Boscosil 616 (300 ML) bh 62,000.00 80,520.00 62,000.00 66,000.00 67,500.00
160 Fil A Gap (300 ML) bh 40,000.00 51,387.60 40,000.00 40,000.00 41,000.00
161 Boscosil Mastic (300 ML) khusus R. Pendingin bh 50,800.00 67,594.56 51,600.00 50,800.00 51,900.00
162 Bostik Z Bond 6S (300 ML) bh 145,000.00 193,011.72 145,000.00 148,000.00 149,500.00
163 Bostik Z PU Contrcuction (600 ML) bh 128,000.00 168,810.84 128,000.00 130,000.00 131,000.00
164 Quelyd Super Express (250 GR) bh 40,000.00 49,665.00 40,000.00 42,000.00 44,000.00
165 Expanda Foam (340 GR) bh 185,000.00 237,911.52 185,000.00 189,000.00 189,500.00
166 Barel Gun bh 540,000.00 725,993.40 540,000.00 545,000.00 546,000.00
167 Flash Band rol 188,000.00 228,513.12 188,000.00 190,000.00 191,000.00

BAMBU
168 Bambu Ukuran 8"- 10" panjang 4 m btg 15,000.00 21,060.00 15,000.00 16,000.00
169 Bambu Ukuran 3"-6" panjang 4 m btg 8,500.00 14,400.00 8,500.00 9,000.00
170 Gedeg kulit kelas I m2 15,000.00 53,220.00 15,000.00 20,000.00
171 Gedeg kulit kelas II m2 10,000.00 49,440.00 10,000.00 12,000.00
172 Gedeg Biasa m2 9,000.00 48,510.00 9,000.00 10,000.00

KAYU
173 Kayu jati Balok m3 9,500,000.00 45,012,000.00 9,500,000.00 10,000,000.00
174 Kayu jati papan m3 12,000,000.00 51,018,000.00 12,000,000.00 12,500,000.00
175 Kayu jati Usuk m3 7,500,000.00 21,780,000.00 7,500,000.00 8,000,000.00
176 Kayu jati Reng m3 8,750,000.00 21,417,000.00 8,750,000.00 8,800,000.00
177 Kayu merbau Balok m3 18,500,000.00 23,284,800.00 18,500,000.00 19,100,000.00
178 Kayu merbau papan m3 8,900,000.00 25,940,100.00 8,900,000.00 8,950,000.00
179 Kayu kamper balok m3 8,850,000.00 14,541,600.00 8,850,000.00 8,900,000.00
180 Kayu kamper usuk/reng m3 9,500,000.00 13,871,280.00 9,500,000.00 9,510,000.00
181 Kayu kamper papan m3 9,500,000.00 17,820,000.00 9,500,000.00 9,510,000.00
182 Kayu Profil 4/5 kamper m3 9,500,000.00 13,825,680.00 9,500,000.00 9,510,000.00
183 List Kayu m' 48,500.00 53,400.00 48,500.00 48,500.00
184 List profil 2/4 kamper m' 48,800.00 51,600.00 48,800.00 48,800.00
185 Kayu kruing balok m3 6,750,000.00 10,362,000.00 6,850,000.00 6,750,000.00
186 Kayu kruing papan m3 7,450,000.00 10,494,000.00 7,500,000.00 7,450,000.00
187 Kayu Usuk Kruing m3 7,450,000.00 10,362,000.00 7,500,000.00 7,450,000.00
188 Kayu Reng Kruing m3 7,450,000.00 10,362,000.00 7,500,000.00 7,450,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
189 Kayu Papan Meranti m3 6,715,000.00 8,976,000.00 6,715,000.00 6,750,000.00
190 Kayu Balok Meranti m3 6,816,000.00 9,009,000.00 6,816,000.00 6,850,000.00
191 Kayu Usuk Meranti m3 6,800,000.00 8,976,000.00 6,800,000.00 6,855,000.00
192 Kayu Reng Meranti m3 6,500,000.00 8,976,000.00 6,500,000.00 6,510,000.00
193 Kayu Bangkirai Papan m3 11,600,000.00 23,572,560.00 13,550,000.00 11,600,000.00
194 Kayu Bangkirai Balok m3 11,100,000.00 20,790,000.00 11,100,000.00 11,600,000.00
195 Kayu Begisting 5/7 m3 2,500,000.00 6,120,000.00 2,500,000.00 2,700,000.00
196 Kayu Seseh Balok m3 4,150,000.00 4,177,800.00 4,500,000.00 4,600,000.00
197 Kayu Dolken / Skapolding 8,000.00 27,720.00 8,000.00 9,000.00
198 Kayu Seseh Dolken D 20 Panjang 3 m btg 240,000.00 244,800.00 350,000.00 360,000.00
199 Kayu Seseh Dolken D 8-10 Panjang 4m btg 12,000.00 153,120.00 12,000.00 13,000.00
200 Kayu Usuk Albesia 5/7 Panjang 4 m btg 65,000.00 75,240.00 65,000.00 67,000.00
201 Kayu Reng mekanis Uk 2 x 3 x 400 cm m3 4,500,000.00 6,402,000.00 4,500,000.00 4,500,000.00
202 Kayu Reng mekanis Uk 3 x 5 x 400 cm m3 5,650,000.00 6,800,640.00 5,650,000.00 5,660,000.00
203 Kayu Usuk mekanis Uk 4 x 6 x 400 cm m3 5,650,000.00 7,128,000.00 5,650,000.00 5,660,000.00
204 Kayu Usuk mekanis Uk 5 x 7 x 400 cm m3 6,700,000.00 6,903,600.00 6,700,000.00 6,750,000.00
205 Kayu Balok mekanis Uk. 6 x 12 x 400 cm m3 6,700,000.00 7,458,000.00 6,700,000.00 6,750,000.00
206 Kayu Balok mekanis Uk. 6 x 15 x 400 cm m3 6,700,000.00 7,656,000.00 6,700,000.00 6,750,000.00
207 Kayu Balok mekanis Uk. 6 x 20 x 400 cm m3 6,700,000.00 8,857,200.00 6,700,000.00 6,750,000.00
208 Kayu Kelas III lokal m3 2,000,000.00 3,967,200.00 2,000,000.00 2,150,000.00
209 Kayu 7/7, Kelas III m3 3,500,000.00 3,720,000.00 3,500,000.00 3,700,000.00
210 Kayu Cempaka lokal m3 2,995,000.00 3,963,960.00 2,995,000.00 3,100,000.00
211 Kayu Bakar m3 850,000.00 976,800.00 850,000.00 870,000.00
212 Papan Bakesting m3 1,450,000.00 4,587,660.00 1,600,000.00 1,450,000.00
213 Papan Kayu Ulin m3 5,300,000.00 20,790,000.00 5,300,000.00 5,310,000.00
214 Papan Kayu, Kelas II m3 13,500,000.00 207,900.00 13,500,000.00 13,500,000.00
215 Balok Kayu Ulin m3 5,300,000.00 20,790,000.00 5,300,000.00 5,310,000.00
216 Lem Aica Aibond kg 60,000.00 83,160.00 60,000.00 65,000.00
217 Lem Kayu setara Fox ltr 16,000.00 27,720.00 16,000.00 17,000.00
218 Minyak bekisting setara Calform NX*R ltr 45,000.00 53,118.12 48,000.00 45,000.00
219 Jaro bubut bh 30,000.00 30,000.00 36,000.00
220 Kayu Perancah m3 48,000.00 48,000.00 48,500.00

Flooring/ Lantai
221 Parket Jati lokal Uk. 1,2 x 5 x 20 cm m2 255,000.00 403,920.00 255,000.00 265,000.00
222 Parket Jati lokal Uk. 1,2 x 5 x 25 cm m2 275,000.00 409,200.00 275,000.00 285,000.00
223 Parket Jati lokal Uk. 1,2 x 5 x 30 cm m2 310,000.00 415,800.00 310,000.00 315,000.00
224 Jati Eksport Uk. 1,2 x 5 x 20 cm m2 380,000.00 429,000.00 380,000.00 385,000.00
225 Jati Eksport Uk. 1,2 x 5 x 25 cm m2 395,000.00 456,720.00 395,000.00 398,000.00
226 Jati Eksport Uk. 1,2 x 5 x 30 cm m2 410,000.00 469,920.00 410,000.00 412,000.00
227 Jati Eksport Uk. 1,5 x 9 x 30 - 120 cm m2 510,000.00 637,560.00 510,000.00 515,000.00
228 Jati Eksport Uk. 1,5 x 12 x 30 - 120 cm m2 535,000.00 866,250.00 535,000.00 540,000.00
229 Parket Kayu Merbau Kelas I Uk. 1 x 5 x 20 cm m2 340,000.00 391,776.00 340,000.00 345,000.00
230 Parket Kayu Merbau Kelas I Uk. 1 x 5 x 30 cm m2 345,000.00 403,920.00 345,000.00 346,000.00
231 Parket Kayu Merbau Kelas I Uk. 1 x 9 x 30 - 120 cm m2 518,000.00 623,700.00 518,000.00 519,000.00
232 Parket Kayu Merbau Export Uk. 1 x 9 x 30 - 120 cm m2 540,000.00 679,140.00 540,000.00 545,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
233 Parket Kayu Merbau Export Uk. 1 x 9 x 60 - 120 cm m2 516,000.00 658,350.00 516,000.00
234 Decking Bangkirai Uk. 1,9 x 9 x 180 - 390 cm m2 548,000.00 654,720.00 548,000.00
235 Decking Krewing Uk. 1,9 x 9 x 180 - 400 cm m2 415,000.00 623,700.00 415,000.00
236 Decking Merbau Uk. 1,9 x 9 x 180 - 400 cm m2 445,000.00 720,720.00 445,000.00
237 Decking Ulin Sulawesi Uk. 1,9 x 9 x 200 cm m2 685,000.00 957,000.00 685,000.00

Lambersering
238 Lambersering Bangkirai Uk. 1 x 9 x 200 cm m2 469,000.00 583,440.00 469,000.00
239 Lambersering Kruing Uk. 2 x 9 x 200 cm m2 385,000.00 446,160.00 385,000.00

Lis Kayu
240 Lis plapond kayu mekanis Uk. 1 x 5 x 400 cm btg 26,000.00 30,360.00 26,000.00 26,500.00
241 Lis Plapond dobel kayu mekanis Uk. 1 x 5 x 400 cm btg 28,000.00 28,776.00 28,500.00 28,000.00
242 Lis Plapond Uk. 0,8 x 5 x 400 cm btg 21,000.00 24,420.00 21,000.00 21,000.00
243 Lis Plapond Uk.1 x 3 x 400 cm btg 19,500.00 22,440.00 19,500.00 19,600.00
244 Lis Plapond tanpa profil Uk. 1 x 5 x 400 cm btg 32,000.00 33,000.00 44,000.00 45,000.00
245 Lisplang kayu mekanis Uk. 2 x 6 x 400 cm btg 51,000.00 58,080.00 51,000.00 52,000.00
246 Lisplang kayu mekanis Uk. 2 x 7 x 400 cm btg 57,000.00 69,960.00 57,000.00 58,000.00
247 Lisplang kayu mekanis Uk. 2 x 8 x 400 cm btg 65,000.00 76,560.00 65,000.00 67,000.00
248 Lisplang kayu mekanis Uk. 2 x 10 x 400 cm btg 81,000.00 104,940.00 81,000.00 82,000.00
249 Lisplang kayu mekanis Uk. 2 x 12 x 400 cm btg 101,000.00 127,080.00 101,000.00 102,000.00
250 Lisplang kayu mekanis Uk. 2 x 15 x 400 cm btg 122,000.00 122,760.00 125,500.00 126,000.00
251 Lisplang kayu mekanis Uk. 2 x 20 x 400 cm btg 122,500.00 123,000.00 130,000.00 131,000.00
252 Lis Kaca Uk. 1,5 x 3 cm m' 16,500.00 16,896.00 16,500.00 17,000.00
253 Lis Dowel Kecil Uk. 1 x 2 cm m' 6,000.00 6,120.00 7,000.00 8,000.00
254 Lis Dowel Besar Uk. 1,3 x 3 cm m' 6,500.00 6,732.00 7,500.00 8,500.00
255 Lis Kusen m' 6,200.00 6,336.00 8,500.00 9,000.00

CONWOOD
Flooring/Deck Application
256 Conwood Deck 4" ( 102 x 3050 x 14 mm) Pcs 81,500.00 103,620.00 81,500.00 83,000.00
257 Conwood Deck 6" ( 152 x 3050 x 14 mm) Pcs 138,000.00 176,880.00 138,000.00 139,500.00
258 Conwood Deck 8" ( 203 x 3050 x 14 mm) Pcs 168,000.00 201,960.00 168,000.00 170,000.00
259 Conwood Deck 4" ( 102 x 3050 x 25 mm) Pcs 168,000.00 203,280.00 168,000.00 170,000.00
260 Conwood Deck 6" ( 152 x 3050 x 25 mm) Pcs 250,500.00 298,320.00 250,500.00 251,000.00
261 Conwood Deck 8" ( 203 x 3050 x 25 mm) Pcs 325,000.00 392,040.00 325,000.00 326,000.00
262 Conwood Deck 12"( 300 x 3050 x 25 mm) Pcs 475,000.00 591,360.00 475,000.00 480,000.00

Decorative Stair
263 Conwood Stair 8" (Vertical) (200 x 1200 x 16 mm) Pcs 91,000.00 113,652.00 91,000.00 93,000.00
264 Conwood Stair 12" (Horisontal) (300 x 1200 x 25 mm) Pcs 189,800.00 235,752.00 189,800.00 189,800.00
265 Conwood Handrail (85 x 3050 x 30 mm) Pcs 148,500.00 204,072.00 148,500.00 149,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9

Ceiling Application
266 Celling Border (50 X 3050 X 11 mm) Pcs 40,000.00 60,456.00 40,000.00 45,600.00
267 Conwood Lath 3" Cut (76 x 3050 x 11 mm) Pcs 61,000.00 72,336.00 61,000.00 63,500.00
268 Conwood Lath 4" Cut (100 x 3050 x 11 mm) Pcs 75,000.00 91,740.00 75,000.00 78,900.00
269 Conwood Lath 3"(UG)(600 x 1200 x 8 mm) Pcs 125,000.00 147,840.00 125,000.00 128,600.00
270 Conwood Lath 3"(UG)(1200 x 2400 x 8 mm) Pcs 515,000.00 620,520.00 515,000.00 518,500.00

Eave/lisplank
271 Conwood Eave 2 IN 1 (235 x 3050 x 16 mm) Pcs 178,000.00 214,500.00 178,000.00 181,000.00

Wall Application
272 Conwood Lap Siding 6" BG (152 x 3050 x 11mm) Pcs 85,000.00 88,565.40 85,000.00 90,000.00
273 Conwood Lap Siding 8" GO (200 x 3050 x 11mm) Pcs 98,000.00 115,453.80 98,000.00 98,500.00
274 Conwood Decorative Panel (600 x 1200 x 11mm) Pcs 180,000.00 214,500.00 180,000.00 181,000.00
275 Conwood Decorative Panel " V-Groove" (305 x 3050 x 14mm) Pcs 215,000.00 262,800.00 215,000.00 217,000.00

Moulding Application
276 Conwood Floor Mould 4" (Louis) (102 x 3050 x 11mm) Pcs 125,000.00 71,280.00 125,000.00 126,500.00
277 Conwood Floor Mould 4" (Louis) (102 x 3050 x 14mm) Pcs 41,000.00 80,520.00 41,000.00 43,500.00
278 Conwood Floor Mould 4" (Classic) (102 x 3050 x 11mm) Pcs 65,000.00 65,003.40 65,000.00 66,500.00
279 Conwood Floor Mould 4" (Classic) (102 x 3050 x 14mm) Pcs 60,000.00 87,780.00 60,000.00 61,000.00
38,000.00 40,100.00
Decorative Application
280 Conwood Plank 1" (100 x 3050 x 25 mm) Pcs 110,000.00 130,680.00 110,000.00 115,000.00
281 Conwood Plank 2" (50 x 3050 x 16 mm) Pcs 45,000.00 51,084.00 45,000.00 46,500.00
282 Conwood Plank 2" (50 x 3050 x 25 mm) Pcs 65,000.00 78,672.00 65,000.00 66,500.00
283 Conwood Sun Shade 3" (76 x 3050 x 14 mm) Pcs 53,000.00 64,800.00 53,000.00 54,100.00
284 Conwood Fence 4" Arrow - 1M (100x 1000 x 16 mm) Pcs 40,000.00 40,920.00 40,000.00 41,600.00
285 Conwood Fence 4" Arrow - 1,5M (100x 1500 x 16 mm) Pcs 52,000.00 64,680.00 52,000.00 53,000.00
286 Conwood Fence 4" Botany - 1M (100x 1000 x 16 mm) Pcs 38,000.00 52,272.00 38,000.00 41,000.00
287 Conwood Fence 4" Botany - 1,5M (100x 1500 x 16 mm) Pcs 53,000.00 61,560.00 53,000.00 54,000.00
288 Conwood Fence 4" Classic - 1,5M (100x 1500 x 16 mm) Pcs 55,000.00 64,548.00 55,000.00 56,000.00
289 Conwood Fence 4" Branch - 1M (100x 1000 x 16 mm) Pcs 40,000.00 48,840.00 40,000.00 41,500.00

Planks
290 Conwood Plank 8" Textured (200 x 3050 x 8 mm) Pcs 94,000.00 79,200.00 94,000.00 98,500.00
291 Conwood Plank 8" Plain (200 x 3050 x 8 mm) Pcs 91,000.00 79,200.00 91,000.00 93,000.00

BESI
292 Mour + Bout bh 2,950.00 12,600.00 2,950.00 3,100.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
293 Besi strip kg 13,000.00 20,097.00 13,000.00 15,000.00 16,000.00
294 Besi strip 30x3 mm m' 18,000.00 29,280.00 18,000.00 20,000.00 25,000.00
295 Baja Strip (0,2 x 2) cm / Plat Strip Kg 15,833.33 24,120.00 95,000.00 98,500.00 99,000.00
296 Besi Beton U24 (Polos) Kg 9,800.00 18,018.00 9,800.00 9,900.00 10,100.00
297 Besi Beton Ulir U 32 Kg 12,500.00 18,714.00 12,500.00 12,700.00 12,750.00
298 Besi Ulir 13,0x 12 sni (Ts-40) Kg 12,000.00 12,234.00 115,000.00 118,000.00 119,500.00
299 Besi Ulir 16,0x 12 sni (Ts-40) kg 11,000.00 11,829.60 170,800.00 172,000.00 173,000.00
300 Besi Ø5 (3,8 x 6,0) btg 4,950.00 9,108.00 4,950.00 5,100.00 6,000.00
301 Besi Ø6 (5,0 x 12) btg 18,200.00 24,684.00 18,200.00 18,300.00 19,000.00
302 Besi Ø6 (5,2 x 12) btg 21,000.00 27,192.00 21,850.00 21,900.00 21,000.00
303 Besi Ø6 (5,7 x 12) btg 27,400.00 30,600.00 27,400.00 28,500.00 29,000.00
304 Besi Ø8 (6,5 x 12) btg 29,100.00 40,920.00 29,100.00 30,100.00 31,000.00
305 Besi Ø8 (6,7 x 12) btg 30,400.00 43,800.00 30,400.00 32,000.00 33,000.00
306 Besi Ø8 (6,9 x 12) SNI btg 31,800.00 46,200.00 31,800.00 34,000.00 35,000.00
307 Besi Ø8 (7,1 x 12) SNI btg 36,100.00 52,560.00 36,100.00 38,000.00 39,000.00
308 Besi Ø8 (7,4 x 12) SNI btg 38,200.00 52,800.00 38,200.00 41,000.00 42,000.00
309 Besi Ø8 (7,6 x 12) SNI btg 39,100.00 55,440.00 39,100.00 42,500.00 43,000.00
310 Besi Ø8 (7,7 x 12) SNI btg 40,100.00 54,600.00 40,100.00 41,600.00 42,500.00
311 Besi Ø8 (7,8 x 12) SNI btg 42,000.00 56,760.00 42,000.00 43,500.00 44,000.00
312 Besi Ø8 SNI U 24 btg 39,600.00 63,360.00 39,600.00 40,600.00 41,000.00
313 Besi Ø10 (8,4 x 12) SNI btg 46,900.00 64,800.00 46,900.00 48,500.00 49,000.00
314 Besi Ø10 (8,6 x 12) SNI btg 50,200.00 68,760.00 50,200.00 52,300.00 53,000.00
315 Besi Ø10 (8,9 x 12) SNI btg 52,200.00 69,900.00 52,200.00 53,600.00 54,000.00
316 Besi Ø10 (9,2 x 12) SNI btg 54,750.00 71,400.00 54,750.00 55,600.00 56,000.00
317 Besi Ø10 (9,4 x 12) SNI btg 58,500.00 75,108.00 58,500.00 59,100.00 60,000.00
318 Besi Ø10 (9,6 x 12) SNI btg 61,050.00 82,080.00 61,050.00 63,000.00 64,000.00
319 Besi Ø10 (9,8 x 12) SNI btg 63,500.00 85,392.00 63,500.00 64,500.00 65,000.00
320 Besi Ø10 SNI U 24 btg 64,000.00 67,560.00 64,000.00 65,000.00 66,000.00
321 Besi Ø10 Ulir (9,5 x 12) SNI btg 58,500.00 77,880.00 58,500.00 61,500.00 62,000.00
322 Besi Ø10 Ulir (9,7 x 12) SNI btg 56,000.00 78,936.00 56,000.00 60,000.00 61,000.00
323 Besi Ø12 (11,5 x 12) SNI btg 84,500.00 108,360.00 84,500.00 85,500.00 86,000.00
324 Besi Ø13 Ulir (11,5 x 12) SNI btg 80,500.00 108,240.00 80,500.00 81,600.00 82,000.00
325 Besi Ø13 Ulir (11,7 x 12) SNI btg 93,000.00 117,600.00 93,000.00 94,500.00 95,000.00
326 Besi Ø13 Ulir (12,0 x 12) SNI btg 96,500.00 118,692.00 96,500.00 97,800.00 98,500.00
327 Besi Ø13 Ulir (12,5 x 12) SNI btg 101,000.00 127,380.00 101,000.00 111,000.00 112,000.00
328 Besi Ø13 Ulir (12,7 x 12) SNI btg 101,000.00 132,240.00 108,500.00 109,600.00 101,000.00
329 Besi Ø16 Ulir (14 x 12) SNI btg 130,000.00 149,400.00 130,000.00 131,000.00 132,000.00
330 Besi Ø16 Ulir (14,5 x 12) SNI btg 132,000.00 161,040.00 132,000.00 133,000.00 134,000.00
331 Besi Ø16 Ulir (15,0 x 12) SNI btg 140,000.00 171,600.00 140,000.00 142,500.00 142,000.00
332 Besi Ø16 Ulir (15,5 x 12) SNI btg 150,500.00 195,360.00 150,500.00 153,000.00 154,000.00
333 Besi Ø16 Ulir (15,7 x 12) SNI btg 154,800.00 201,960.00 154,800.00 156,000.00 157,000.00
334 Wiremesh M6@50m rol 2,300,500.00 3,504,600.00 2,300,500.00 2,350,600.00 2,352,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
335 Wiremesh M7 (D6,5mm) Uk. 2,1 x 5,4 m lbr 450,000.00 515,400.00 450,000.00 452,000.00 455,000.00
336 Wiremesh M8 (D7,5mm) Uk. 2,1 x 5,4 m lbr 695,000.00 788,040.00 695,000.00 698,000.00 698,000.00
337 Wermes Diameter 8 (U 50) lbr 3,011,000.00 711,334.80 3,011,000.00 3,115,000.00 3,116,000.00
338 Beugel Besi O8 kg 20,000.00 17,569.20 20,000.00 23,000.00 22,000.00
339 Beugel penguat /plaat kg 18,000.00 103,080.00 18,000.00 196,000.00 19,700.00
340 Kawat Beton RRT kg 32,000.00 35,400.00 32,000.00 33,500.00 34,000.00
341 Kawat berduri m' 120,000.00 246,360.00 215,000.00 218,000.00 219,000.00
342 Kawat Ayak / Kuasa 5 X 5 cm m2 65,000.00 69,960.00 65,000.00 68,000.00 69,000.00
343 Kawat Harmonika 3 X 3 cm m2 62,000.00 64,260.00 62,000.00 64,500.00 64,500.00
344 Kawat Nyamuk m2 48,000.00 51,000.00 48,000.00 50,100.00 51,000.00
345 Kawat Jaring m2 49,500.00 36,300.00 49,500.00 50,500.00 51,800.00
346 Kawat Bronjong kg 50,000.00 64,140.00 50,000.00 51,600.00 52,000.00
347 Besi / Baja profil kg 15,000.00 39,060.00 15,000.00 16,700.00 17,000.00
348 Besi Baja L60 X 60 X 6 / L50 x 50 x 5 kg 18,500.00 19,770.00 18,500.00 19,600.00 19,800.00
349 Baja WF (150 x 12 GG) btg 1,950,000.00 2,195,424.00 1,950,000.00 2,000,000.00 2,000,000.00
350 Baja WF (200 x 12 GG) btg 2,500,000.00 3,345,408.00 2,500,000.00 2,700,000.00 2,750,000.00
351 Besi Baja WF 200 x 100 x 4,5 x 7 kg 15,000.00 16,968.00 15,000.00 16,000.00 17,000.00
352 Besi Baja WF 200 x 100 x 5,5x8 kg 14,500.00 14,500.00 15,000.00 16,000.00
353 Besi Baja WF 250 x 125 x 5 x 7 kg 16,000.00 16,968.00 19,800.00 20,500.00 21,000.00
354 Besi Baja C 100 x 50 x 3,2 kg 14,000.00 16,698.00 14,000.00 15,000.00 16,000.00
355 Baja Ringan Type C- 75, 0.8 m' 19,800.00 25,740.00 19,800.00 20,500.00 21,000.00
356 Baja Ringan Type C- 75, 0.6 m' 14,000.00 130,800.00 14,000.00 15,000.00 16,000.00
357 Reng Baja m' 11,250.00 11,420.40 11,250.00 11,350.00 11,450.00
358 Profil Canal "C" Tipe C71.075 btg 85,000.00 446,760.00 85,000.00 97,000.00 100,000.00
359 Profil Canal "C" Tipe C81.075 btg 96,000.00 137,280.00 96,000.00 97,000.00 98,000.00
360 Profil Canal "C" Tipe C81.065 btg 90,000.00 132,240.00 90,000.00 92,000.00 95,000.00
361 Profil "Omega / reng Tipe AA btg 45,000.00 90,780.00 45,000.00 55,000.00 55,500.00
362 Profil "Omega / reng Tipe A btg 55,000.00 77,484.00 55,000.00 57,000.00 60,000.00
363 Profil "Omega / reng Tipe AB btg 65,000.00 67,322.40 65,000.00 67,000.00 68,000.00
364 Profil Aluminium Kaca 3/4 m' 18,000.00 22,044.00 18,000.00 19,000.00 18,500.00
365 Profil Aluminium L 3 cm lis Kaca m' 18,000.00 22,044.00 18,000.00 19,000.00 18,500.00
366 Profil Aluminium 4" m' 22,000.00 101,160.00 22,000.00 23,000.00 24,000.00
367 Besi Plat kg 23,000.00 36,096.72 23,000.00 28,000.00 28,000.00
368 Besi plat 3 X 6 tebal 1,2 mm btg 90,000.00 313,411.20 90,000.00 95,000.00 96,000.00
369 Besi plat 4 X 8 tebal 1,8 mm btg 22,000.00 705,962.40 22,000.00 24,000.00 25,000.00
370 Baja Plat Hitam L = 10 lbr 285,000.00 2,621,220.00 285,000.00 288,000.00 299,000.00
371 Baja Plat Hitam L = 8 lbr 510,000.00 2,103,948.00 510,000.00 515,000.00 516,000.00
372 Baut Galvanis 3/4 x 2 " bh 9,500.00 10,200.00 9,800.00 9,500.00 9,700.00
373 Baut Galvanis 3/4 x 2 1/2 " bh 10,000.00 11,311.08 10,000.00 10,500.00 10,600.00
374 Baut Galvanis 3/4 x 3 " bh 12,000.00 12,390.00 12,000.00 12,500.00 13,000.00
375 Baut Galvanis 3/4 x 3 1/2 " bh 12,000.00 13,757.04 12,000.00 13,500.00 13,000.00
376 Baut Galvanis 3/4 x 4 " bh 13,500.00 14,942.40 13,500.00 14,000.00 14,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
377 Baut Galvanis 3/4 x 4 1/2 " bh 15,000.00 16,117.20 15,000.00 15,500.00 15,200.00
378 Baut Galvanis 3/4 x 5 " bh 17,000.00 17,133.60 17,000.00 17,500.00 18,000.00
379 Baut Galvanis 3/4 x 5 1/2 " bh 9,500.00 10,860.00 9,500.00 10,000.00 10,500.00
380 Baut Galvanis 3/4 x 6 " bh 17,000.00 20,037.60 17,000.00 18,000.00 18,000.00
381 Plat Siku Panjang 30 cm bh 21,000.00 35,208.00 21,000.00 22,000.00 23,000.00
382 Plat Siku Panjang 40 cm bh 28,000.00 37,752.00 28,000.00 30,000.00 31,000.00
383 Plat Siku Panjang 50 cm bh 15,000.00 43,920.00 15,000.00 16,500.00 17,000.00
384 Plat Siku Panjang 60 cm bh 18,500.00 50,820.00 18,500.00 19,000.00 19,000.00
385 Plat Aluminium 2mm m2 30,500.00 399,540.00 30,500.00 31,000.00 32,000.00
386 Besi siku / engsel m' 38,500.00 38,500.00 40,000.00 41,000.00
387 Besi Siku L.30.30.3 mm btg 34,500.00 107,496.84 34,500.00 36,500.00 37,000.00
388 Baut UNC 5/8 x 2" bh 3,500.00 5,820.00 4,200.00 3,500.00 4,000.00
389 Baut UNC 5/8 x 2 1/2" bh 4,250.00 4,920.00 4,500.00 4,550.00 4,250.00
390 Baut UNC 5/8 x 3" bh 2,100.00 5,577.00 2,100.00 2,500.00 3,000.00
391 Baut UNC 5/8 x 3 1/2" bh 2,800.00 5,662.80 2,800.00 3,100.00 4,000.00
392 Baut UNC 5/8 x 4" bh 3,100.00 6,316.20 3,100.00 3,500.00 4,500.00
393 Baut UNC 5/8 x 4 1/2" bh 3,800.00 6,824.40 3,800.00 4,000.00 4,800.00
394 Baut UNC 5/8 x 5" bh 4,100.00 7,729.20 4,100.00 4,500.00 5,000.00
395 Baut UNC 5/8 x 5 1/2" bh 4,300.00 7,898.88 4,300.00 4,700.00 5,000.00
396 Baut UNC 5/8 x 6" bh 4,500.00 8,661.60 4,500.00 5,000.00 6,000.00
397 Baut UNC 3/4 x 2" bh 4,600.00 7,695.60 4,600.00 5,500.00 5,000.00
398 Baut UNC 3/4 x 2 1/2" bh 4,900.00 8,349.00 4,900.00 5,800.00 6,000.00
399 Baut UNC 3/4 x 3" bh 8,900.00 9,147.60 8,900.00 9,500.00 10,000.00
400 Baut UNC 3/4 x 3 1/2" bh 10,000.00 10,500.00 10,000.00 10,200.00 10,300.00
401 Baut UNC 3/4 x 4" bh 11,000.00 11,190.00 11,000.00 11,100.00 11,200.00
402 Baut UNC 3/4 x 4 1/2" bh 11,500.00 11,616.00 11,500.00 11,600.00 11,700.00
403 Baut UNC 3/4 x 5" bh 12,000.00 12,559.80 12,500.00 12,000.00 12,600.00
404 Baut UNC 3/4 x 5 1/2" bh 13,000.00 13,620.00 13,500.00 13,000.00 13,700.00
405 Baut UNC 3/4 x 6" bh 5,000.00 14,229.60 5,000.00 7,000.00 8,000.00
406 Baut CB 3/8 x 5" bh 2,500.00 2,814.00 2,500.00 2,650.00 2,700.00
407 Baut CB 3/8 x 3" bh 1,200.00 1,597.20 1,500.00 1,200.00 3,000.00
408 Baut CB 3/8 x 2" bh 1,345.00 1,346.40 1,345.00 1,350.00 1,360.00
409 Behel 7/8 bh 5,100.00 172,920.00 5,100.00 5,800.00 7,000.00
410 Baut Baja A325 16 x 50 bh 8,500.00 9,900.00 8,500.00 8,700.00 8,900.00
411 Baut Baja A325 16 x 60 bh 9,500.00 9,732.00 9,500.00 9,700.00 9,750.00
412 Baut Baja A325 16 x 70 bh 10,000.00 10,164.00 10,000.00 10,200.00 10,100.00
413 Baut Baja A325 16 x 80 bh 11,500.00 11,616.00 11,500.00 11,650.00 11,600.00
414 Baut Baja A325 16 x 90 bh 12,350.00 12,705.00 12,400.00 12,350.00 13,000.00
415 Baut Baja A325 16 x 100 bh 13,500.00 13,866.60 13,500.00 13,500.00 13,800.00
416 Baut Baja A325 16 x 110 bh 15,500.00 15,972.00 15,500.00 15,600.00 15,700.00
417 Baut Baja A325 16 x 120 bh 17,000.00 17,424.00 17,000.00 17,200.00 17,300.00
418 Baut Baja A325 16 x 130 bh 18,000.00 18,876.00 18,000.00 18,500.00 18,700.00
419 Baut Baja A325 16 x 140 bh 20,300.00 20,328.00 20,300.00 20,400.00 20,450.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
420 Baut Baja A325 16 x 150 bh 20,500.00 21,054.00 21,000.00 20,500.00 21,500.00
421 Baut Baja A325 19 x 50 bh 13,500.00 13,939.20 13,500.00 13,600.00 13,650.00
422 Baut Baja A325 19 x 60 bh 15,000.00 15,318.60 15,200.00 15,350.00 15,000.00
423 Baut Baja A325 19 x 70 bh 16,500.00 16,589.76 16,500.00 16,789.00 16,567.00
424 Baut Baja A325 19 x 80 bh 17,325.00 17,424.00 17,425.00 17,325.00 17,550.00
425 Baut Baja A325 19 x 90 bh 19,500.00 20,110.20 20,110.00 19,500.00 20,000.00
426 Baut Baja A325 19 x 100 bh 21,000.00 21,344.40 21,300.00 21,200.00 21,000.00
427 Baut Baja A325 19 x 110 bh 21,000.00 23,232.00 23,200.00 22,500.00 21,000.00
428 Baut Baja A325 19 x 120 bh 24,000.00 24,684.00 24,000.00 24,300.00 24,500.00
429 Baut Baja A325 19 x 130 bh 25,000.00 27,370.20 25,000.00 26,000.00 27,000.00
430 Baut Baja A325 19 x 140 bh 27,200.00 27,297.60 27,200.00 27,300.00 28,000.00
431 Baut Baja A325 19 x 150 bh 28,000.00 29,040.00 28,000.00 29,000.00 28,500.00
432 Baut Galvanis 3/8 x 2 " bh 2,000.00 2,007.60 2,000.00 2,000.00 2,000.00
433 Baut Galvanis 3/8 x 2 1/2 " bh 2,100.00 2,100.00 2,500.00 2,100.00 2,200.00
434 Baut Galvanis 3/8 x 3 " bh 2,250.00 2,250.60 2,250.00 2,250.00 2,300.00
435 Baut Galvanis 3/8 x 3 1/2 " bh 2,700.00 2,702.40 2,750.00 2,700.00 2,740.00
436 Baut Galvanis 3/8 x 4 " bh 2,800.00 2,911.20 2,900.00 2,800.00 2,850.00
437 Baut Galvanis 3/8 x 4 1/2 " bh 2,900.00 2,970.00 2,950.00 2,900.00 2,965.00
438 Baut Galvanis 3/8 x 5 " bh 3,000.00 3,121.80 3,100.00 3,000.00 3,200.00
439 Baut Galvanis 3/8 x 5 1/2 " bh 3,200.00 3,552.00 3,450.00 3,500.00 3,200.00
440 Baut Galvanis 3/8 x 6 " bh 3,800.00 3,870.00 3,800.00 3,850.00 4,000.00
441 Baut Galvanis 5/8 x 2 " bh 5,100.00 5,160.00 5,200.00 5,100.00 5,120.00
442 Baut Galvanis 5/8 x 2 1/2 " bh 5,740.00 5,844.96 5,840.00 5,740.00 5,840.00
443 Baut Galvanis 5/8 x 3 " bh 6,200.00 6,353.16 6,300.00 6,200.00 6,350.00
444 Baut Galvanis 5/8 x 3 1/2 " bh 7,000.00 7,114.80 7,100.00 7,000.00 7,250.00
445 Baut Galvanis 5/8 x 4 " bh 7,600.00 7,623.00 7,600.00 7,650.00 7,655.00
446 Baut Galvanis 5/8 x 4 1/2 " bh 8,200.00 8,203.80 8,200.00 8,250.00 8,450.00
447 Baut Galvanis 5/8 x 5 " bh 8,650.00 8,682.96 8,650.00 8,680.00 8,750.00
448 Baut Galvanis 5/8 x 5 1/2 " bh 9,850.00 10,041.60 9,850.00 10,100.00 12,000.00
449 Baut Galvanis 5/8 x 6 " bh 10,100.00 10,309.20 10,100.00 11,000.00 13,000.00
450 Besi Pipa Galvanis lonjor 120,500.00 1,118,040.00 120,500.00 123,000.00 124,000.00
451 besi tangga D 19, enamel cat bh 85,500.00 85,500.00 90,000.00 91,000.00
452 Handle Besi Ø 12, enamel cat bh 95,800.00 95,800.00 96,500.00 97,000.00
453 Angker diameter 12mm bh 21,000.00 21,489.60 108,500.00 110,000.00 112,000.00
454 Skruf Fixer 5 cm bh 1,000.00 1,098.00 18,500.00 19,500.00 19,600.00
455 Dynabolt bh 4,500.00 6,600.00 4,500.00 4,650.00 5,000.00
456 Rapidrant gln 98,500.00 98,500.00 99,100.00 101,000.00
457 Sealant tube 40,000.00 54,912.00 40,000.00 43,500.00 45,000.00
458 Silicon kg 43,500.00 102,148.20 43,500.00 44,600.00 45,000.00
459 Elektrode 0,6 % bh 118,500.00 190,575.00 118,500.00 119,600.00 120,000.00
460 Elektrode 2 % bh 315,000.00 353,232.00 315,000.00 318,000.00 319,000.00

BESI PAGAR
461 Pagar Setara BRC T.90 diameter 6mm m' 245,000.00 274,032.00 245,000.00 265,000.00 270,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
462 Pagar Setara BRC T.120 diameter 6mm m' 289,000.00 312,180.00 289,000.00 289,800.00 291,000.00
463 Pagar Setara BRC T.150 diameter 6mm m' 289,000.00 320,760.00 289,000.00 289,800.00 293,000.00
464 Pagar Setara BRC T.175 diameter 7mm m' 485,000.00 485,760.00 485,000.00 486,000.00 495,000.00
465 Pagar Setara BRC T.190 diameter 7mm m' 685,000.00 722,700.00 685,000.00 695,000.00 691,000.00
466 Pagar HotDip Galvanized T.90 diameter 6mm m' 234,000.00 234,300.00 235,000.00 240,000.00 241,000.00
467 Pagar HotDip Galvanized T.120 diameter 6mm m' 250,000.00 250,800.00 255,000.00 265,000.00 265,800.00
468 Pagar HotDip Galvanized T.150 diameter 7mm m' 285,000.00 320,400.00 285,000.00 295,000.00 295,000.00
469 Pagar HotDip Galvanized T.175 diameter 7mm m' 309,000.00 353,760.00 309,000.00 310,000.00 311,000.00
470 Pagar HotDip Galvanized T.190 diameter 7mm m' 248,000.00 372,504.00 345,000.00 248,000.00 249,000.00

CAT
471 Cat Marka Jalan Kg 61,000.00 61,192.80 97,775.00 98,500.00 98,000.00
472 Glas Bit Kg 38,000.00 38,115.00 70,000.00 72,000.00 73,000.00
473 Cat besi kg 57,000.00 129,733.20 57,000.00 60,000.00 61,000.00
474 Cat Menie besi Kg 40,000.00 69,492.00 40,000.00 45,000.00 45,000.00
475 Cat menie Kayu kg 30,000.00 68,607.00 30,000.00 32,000.00 33,000.00
476 Cat Dasar Tembok Setara Emco Kg 65,000.00 82,928.40 65,000.00 66,800.00 65,000.00
477 Cat Setara weldon biasa Kg 33,000.00 52,512.00 33,000.00 35,000.00 40,000.00
478 Cat Setara weldon warna Kg 35,000.00 64,500.00 35,000.00 38,500.00 38,500.00
479 Cat Setara weldon warna tua Kg 38,000.00 72,672.00 38,000.00 41,000.00 42,000.00
480 Cat Setara emco Lux Biasa kg 33,000.00 83,400.00 33,000.00 38,000.00 39,000.00
481 Cat Setara emco Lux Warna kg 35,000.00 91,836.00 35,000.00 42,000.00 43,000.00
482 Cat Setara emco Lux Warna Tua kg 40,000.00 106,722.00 40,000.00 43,500.00 44,000.00
483 Cat tembok Setara Decolith kg 38,000.00 55,680.00 38,000.00 41,000.00 41,000.00
484 Cat tembok Setara Dulux Exterior kg 145,000.00 175,929.60 145,000.00 148,000.00 149,000.00
485 Cat tembok Setara Dulux Interior kg 110,000.00 130,191.60 110,000.00 118,000.00 119,000.00
486 Cat tembok Setara Vinilex kg 26,500.00 56,064.00 26,500.00 28,500.00 29,000.00
487 Cat Galvanis kg 55,000.00 122,263.20 55,000.00 58,500.00 58,000.00
488 Cat Kayu Emco kg 65,000.00 89,016.00 65,000.00 68,000.00 69,000.00
489 Cat Baja Chromate (anti karat) Kg 57,000.00 153,060.00 57,000.00 58,500.00 59,000.00
490 Cat Kansteen Kg 82,000.00 82,440.00 115,000.00 118,000.00 118,500.00
491 Kalkarium Kg 110,500.00 110,500.00 115,000.00 116,000.00
492 Kapur sirih Kg 15,000.00 15,000.00 18,500.00 19,000.00
493 Amplas lbr 5,000.00 9,786.00 5,000.00 5,000.00 6,000.00
494 Kuas Bh 12,000.00 22,110.00 12,000.00 13,500.00 14,000.00

Cat KCA
495 Cat Natural@25 kg Pail 890,000.00 894,960.00 890,000.00 898,000.00 899,000.00
496 Cat Flakes@25 kg Pail 985,000.00 1,171,500.00 985,000.00 989,000.00 989,000.00
497 Cat Genteng @25kg Pail 288,000.00 1,079,760.00 288,000.00 310,000.00 315,000.00

Stone Coating :
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
498 Clear gloss air kg 75,000.00 105,336.00 75,000.00 75,000.00 80,000.00
499 Black gloss air kg 88,000.00 115,500.00 88,000.00 88,500.00 89,000.00
500 Clear gloss solvent kg 79,500.00 105,072.00 79,500.00 80,000.00 82,000.00
501 Black gloss solvent kg 89,000.00 112,200.00 89,000.00 89,500.00 90,000.00
502 Clear doft solvent kg 89,500.00 112,200.00 89,500.00 90,000.00 91,000.00
503 Black doft solvent kg 89,800.00 113,124.00 89,800.00 90,500.00 91,000.00
504 Dempul / Plamir ltr 45,000.00 73,180.80 45,000.00 46,500.00 50,000.00
505 Dempul / Plamir Altik ltr 42,500.00 64,491.24 42,500.00 43,500.00 44,000.00
506 Dempul Impra Kayu ltr 40,000.00 68,607.00 40,000.00 41,000.00 42,000.00
507 Kuas untuk mengecat bh 8,000.00 21,720.00 8,000.00 9,000.00 10,000.00
508 Lem Fox (Rajawali Kuning) Gln 135,000.00 221,067.00 135,000.00 145,000.00 146,000.00
509 Lem Wall Paper Kg 80,000.00 42,600.00 80,000.00 81,000.00 82,000.00
510 Mild zak 10,000.00 18,600.00 10,000.00 11,000.00 13,000.00
511 Minyak cat ltr 28,000.00 64,491.24 28,000.00 30,000.00 31,000.00
512 Melamine Lack / Imfra ltr 89,500.00 106,722.00 89,500.00 90,500.00 91,500.00
513 Okear / Veap Kg 25,000.00 124,080.00 25,000.00 26,100.00 27,100.00
514 Plamir kayu kg 28,000.00 69,000.00 28,000.00 30,100.00 31,000.00
515 Plamir tembok setara wall Putty kg 32,000.00 221,067.00 32,000.00 33,000.00 34,000.00
516 Politur ultra ltr 65,000.00 104,129.52 65,000.00 66,500.00 65,000.00
517 Politur Jadi ltr 70,000.00 105,197.40 70,000.00 71,500.00 73,000.00
518 vernis ltr 40,000.00 83,853.00 40,000.00 41,500.00 43,000.00
519 Residu / Teer Ltr 45,000.00 50,160.00 45,000.00 46,500.00 47,000.00
520 Roll Buah 28,500.00 53,361.00 28,500.00 30,100.00 31,000.00
521 Sending Seaker ltr 89,500.00 105,600.00 89,500.00 89,500.00 90,000.00
522 Soda Api Kg 11,000.00 34,080.00 11,000.00 11,500.00 12,000.00
523 Thiner A Spesial ltr 28,500.00 38,715.60 28,500.00 30,000.00 31,000.00
524 Thiner B ltr 30,000.00 38,715.60 30,000.00 31,000.00 32,000.00
525 Teack Oil ltr 65,000.00 92,238.96 65,000.00 68,000.00 70,000.00
526 Wall Paper Setara Silk House m2 775,000.00 915,360.00 775,000.00 785,000.00 795,000.00
527 Wood Filler ltr 45,000.00 84,453.60 45,000.00 48,500.00 49,000.00
528 Cat Scotlight Ltr 195,000.00 236,040.00 195,000.00 198,500.00 199,000.00
529 Mowilex Kg 78,000.00 78,000.00 81,000.00 83,000.00

KACA
530 Bingkai Nako Silver daun 47,500.00 62,640.00 47,500.00 48,000.00 49,000.00
531 Bingkai Nako Coklat daun 49,500.00 57,780.00 49,500.00 50,000.00 51,000.00
532 Glass Block bh 28,500.00 56,520.00 28,500.00 30,000.00 31,000.00
533 Kaca 2 mm bening m2 106,000.00 106,722.00 175,000.00 185,000.00 180,000.00
534 Kaca 3 mm bening m2 130,000.00 131,040.00 185,000.00 195,000.00 196,000.00
535 Kaca 5 mm bening m2 110,000.00 209,160.00 110,000.00 112,000.00 115,000.00
536 Kaca 6 mm bening m2 259,000.00 259,182.00 310,000.00 311,500.00 311,000.00
537 Kaca 8 mm bening m2 315,000.00 440,609.40 315,000.00 318,000.00 319,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
538 Kaca 10 mm bening m2 341,000.00 533,610.00 395,000.00 341,000.00 345,000.00
539 Kaca 12 mm bening m2 585,000.00 686,070.00 585,000.00 595,000.00 595,000.00
540 Kaca Cermin 3 mm m2 198,000.00 235,560.00 198,000.00 200,000.00 201,000.00
541 Kaca Cermin 5 mm m2 365,000.00 426,888.00 365,000.00 368,000.00 369,000.00
542 Kaca Es/Kapur 3 mm m2 231,000.00 274,428.00 231,000.00 321,000.00 332,000.00
543 Kaca Es/Kapur 5 mm m2 235,000.00 356,400.00 235,000.00 336,000.00 338,000.00
544 Kaca Nako Bening m2 137,000.00 137,814.00
545 Kaca Nako Rayben m2 182,500.00 182,952.00
546 Kaca ryben 3 mm m2 118,000.00 138,600.00 118,000.00 119,000.00 119,500.00
547 Kaca ryben 5 mm m2 185,000.00 213,444.00 185,000.00 195,000.00 196,000.00
548 Kaca asahi tebal 3 mm polos clear m2 101,000.00 105,600.00 101,000.00 102,000.00 102,000.00
549 Kaca asahi tebal 3 mm ryben dark grey m2 115,000.00 123,420.00 115,000.00 118,000.00 119,000.00
550 Kaca asahi tebal 3 mm cermin mirror m2 180,000.00 195,960.00 180,000.00 182,000.00 183,000.00
551 Kaca asahi tebal 3 mm es mislet m2 195,000.00 201,663.00 195,000.00 198,000.00 199,000.00
552 Kaca asahi tebal 3 mm biru dark blue m2 285,000.00 326,403.00 285,000.00 295,000.00 296,000.00
553 Kaca asahi tebal 3 mm one way m2 415,000.00 485,100.00 415,000.00 418,000.00 419,000.00
554 Kaca asahi tebal 5 mm polos clear m2 118,000.00 130,020.00 118,000.00 120,000.00 121,000.00
555 Kaca asahi tebal 5 mm ryben dark grey m2 145,000.00 157,311.00 145,000.00 150,000.00 151,000.00
556 Kaca asahi tebal 5 mm cermin mirror m2 255,000.00 510,840.00 255,000.00 258,000.00 259,000.00
557 Kaca asahi tebal 5 mm es mislet m2 263,000.00 263,340.00 265,000.00 268,000.00 269,000.00
558 Kaca asahi tebal 6 mm polos clear m2 185,000.00 200,970.00 185,000.00 186,000.00 187,000.00
559 Kaca asahi tebal 8 mm polos clear m2 365,000.00 400,554.00 365,000.00 375,000.00 376,000.00
560 Kaca asahi tebal 10 mm polos clear m2 415,000.00 485,100.00 415,000.00 418,000.00 419,000.00
561 Kaca asahi tebal 12 mm polos clear m2 430,000.00 502,425.00 430,000.00 431,000.00 432,000.00
562 Kaca tempered asahimas tebal 3mm polos clear m2 245,000.00 282,051.00 245,000.00 246,000.00 246,000.00
563 Kaca tempered asahimas tebal 3mm ryben dark grey m2 275,000.00 335,412.00 275,000.00 285,000.00 286,000.00
564 Kaca tempered asahimas tebal 3mm sanergy clear m2 310,000.00 837,144.00 310,000.00 315,000.00 319,000.00
565 Kaca tempered asahimas tebal 4mm polos clear m2 245,000.00 283,800.00 245,000.00 248,000.00 249,000.00
566 Kaca tempered asahimas tebal 4mm sanergy clear m2 798,000.00 959,112.00 798,000.00 798,000.00 799,000.00
567 Kaca tempered asahimas tebal 5mm polos clear m2 265,000.00 311,157.00 265,000.00 265,000.00 266,000.00
568 Kaca tempered asahimas tebal 5mm ryben dark grey m2 269,000.00 385,308.00 368,000.00 269,000.00 269,000.00
569 Kaca tempered asahimas tebal 5mm stopsol m2 518,000.00 604,296.00 518,000.00 518,500.00 519,000.00
570 Kaca tempered asahimas tebal 5mm warna m2 445,000.00 515,592.00 445,000.00 448,000.00 448,000.00
571 Kaca tempered asahimas tebal 5mm sanergy clear m2 950,000.00 1,125,432.00 953,000.00 950,000.00 957,000.00
572 Kaca tempered asahimas tebal 6mm polos clear m2 370,000.00 418,440.00 370,000.00 375,000.00 376,000.00
573 Kaca tempered asahimas tebal 6mm ryben dark grey m2 475,000.00 562,716.00 475,000.00 480,000.00 481,000.00
574 Kaca tempered asahimas tebal 6mm stopsol m2 575,000.00 1,143,450.00 575,000.00 578,000.00 579,000.00
575 Kaca tempered asahimas tebal 6mm warna m2 540,000.00 646,569.00 540,000.00 545,000.00 546,000.00
### 576 Kaca tempered asahimas tebal 6mm diamon m2 735,000.00 861,399.00 735,000.00 738,000.00 738,000.00
577 Kaca tempered asahimas tebal 6mm sanergy clear m2 1,235,000.00 1,392,600.00 1,235,000.00 1,238,000.00 1,239,000.00
578 Kaca tempered asahimas tebal 8mm polos clear m2 495,000.00 547,800.00 495,000.00 498,000.00 498,000.00
579 Kaca tempered asahimas tebal 8mm stopsol m2 1,345,000.00 1,568,952.00 1,345,000.00 1,365,000.00 1,365,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
580 Kaca tempered asahimas tebal 8mm warna m2 910,000.00 1,013,859.00 910,000.00 911,000.00 912,000.00
### 581 Kaca tempered asahimas tebal 8mm diamon m2 1,250,000.00 1,494,108.00 1,250,000.00 1,250,000.00 1,251,000.00
582 Kaca tempered asahimas tebal 8mm sanergy clear m2 1,610,000.00 1,905,750.00 1,610,000.00 1,610,000.00 1,615,000.00
583 Kaca tempered asahimas tebal 10mm polos clear m2 610,000.00 668,052.00 610,000.00 615,000.00 618,000.00
584 Kaca tempered asahimas tebal 10mm diamon m2 1,810,000.00 2,134,440.00 1,810,000.00 1,815,000.00 1,815,000.00
585 Kaca tempered asahimas tebal 12mm polos clear m2 685,000.00 783,090.00 685,000.00 695,000.00 695,000.00
586 Kaca tempered asahimas tebal 12mm diamon m2 2,310,000.00 2,720,025.00 2,310,000.00 2,315,000.00 2,318,000.00
587 Kaca tempered asahimas tebal 15mm polos clear m2 5,410,000.00 6,398,469.00 5,410,000.00 5,415,000.00 5,415,000.00
588 Kaca tempered asahimas tebal 15mm diamon m2 6,918,000.00 8,316,000.00 6,918,000.00 6,919,000.00 6,920,000.00
589 Kaca tempered asahimas tebal 19mm polos clear m2 6,210,000.00 7,363,818.00 6,210,000.00 6,215,000.00 6,215,000.00
590 Kaca tempered asahimas tebal 19mm diamon m2 9,500,000.00 10,130,967.00 9,500,000.00 9,600,000.00 9,600,000.00
591 Kaca tebal 3+3 mm laminet biasa m2 418,000.00 478,170.00 418,000.00 418,000.00 419,000.00
592 Kaca tebal 4+4 mm laminet biasa m2 510,000.00 584,892.00 510,000.00 515,000.00 515,000.00
593 Kaca tebal 5+5 mm laminet biasa m2 565,000.00 658,350.00 565,000.00 570,000.00 570,000.00
594 Kaca tebal 6+6 mm laminet biasa m2 700,000.00 791,736.00 700,000.00 715,000.00 715,000.00
595 Kaca tebal 8+8 mm laminet biasa m2 910,000.00 1,280,400.00 910,000.00 915,000.00 920,000.00
596 Kaca tebal 10+10 mm laminet biasa m2 1,215,000.00 1,442,826.00 1,215,000.00 1,216,000.00 1,218,000.00
597 Kaca tebal 12+12 mm laminet biasa m2 1,110,000.00 1,641,024.00 1,110,000.00 1,115,000.00 1,118,000.00
598 Kaca tebal 3+3 mm laminet tempered m2 1,410,000.00 1,326,402.00 1,410,000.00 1,415,000.00 1,417,000.00
599 Kaca tebal 4+4 mm laminet tempered m2 1,420,000.00 1,463,616.00 1,420,000.00 1,421,000.00 1,425,000.00
600 Kaca tebal 5+5 mm laminet tempered m2 1,430,000.00 1,501,038.00 1,430,000.00 1,435,000.00 1,445,000.00
601 Kaca tebal 6+6 mm laminet tempered m2 1,850,000.00 1,905,750.00 1,850,000.00 1,855,000.00 1,856,000.00
602 Kaca tebal 8+8 mm laminet tempered m2 1,950,000.00 2,314,620.00 1,950,000.00 1,960,000.00 1,960,000.00
603 Kaca tebal 10+10 mm laminet tempered m2 2,350,000.00 2,686,068.00 2,350,000.00 2,350,000.00 2,350,000.00
604 Kaca tebal 12+12 mm laminet tempered m2 2,960,000.00 2,957,724.00 2,960,000.00 2,965,000.00 2,965,000.00
605 Ongkos polin kaca tempered tebal 5mm m' 28,500.00 29,040.00 31,000.00 35,000.00 35,000.00
606 Ongkos polin kaca tempered tebal 6mm m' 30,000.00 30,360.00 35,000.00 38,000.00 39,000.00
607 Ongkos polin kaca tempered tebal 8mm m' 41,000.00 44,880.00 41,000.00 41,500.00 41,600.00
608 Ongkos polin kaca tempered tebal 10mm m' 40,000.00 40,920.00 43,000.00 43,500.00 43,000.00
609 Ongkos polin kaca tempered tebal 12mm m' 30,000.00 43,560.00 30,000.00 50,600.00 50,600.00
610 Ongkos polin kaca tempered tebal 19mm m' 65,000.00 147,840.00 65,000.00 68,000.00 69,000.00

PIPA
611 Pipa Galvanis 1" m' 70,000.00 77,131.56 70,000.00 75,000.00 850,000.00
612 Pipa Galvanis 1,5 BSA m' 91,000.00 116,424.00 98,500.00 98,000.00 91,000.00
613 Pipa Galvanis 2" m' 121,000.00 163,548.00 121,000.00 125,000.00 125,000.00
614 Pipa Galvanis 3" m' 178,500.00 250,866.00 178,500.00 180,000.00 181,000.00
615 Pipa Maspion AW 1/2 m' 7,510.00 12,458.40 30,040.00 31,000.00 35,000.00
616 Pipa Maspion AW 3/4 m' 9,160.00 17,186.40 36,640.00 37,000.00 40,000.00
617 Pipa Maspion AW 1 m' 11,530.00 20,569.20 46,120.00 46,500.00 47,000.00
618 Pipa Maspion AW 1-1/2 m' 21,250.00 36,540.00 85,000.00 85,600.00 85,000.00
619 Pipa Maspion AW 1-1/4 m' 16,325.00 31,820.40 65,300.00 65,900.00 66,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
620 Pipa Maspion AW 2 m' 31,550.00 42,000.00 126,200.00 127,000.00 130,000.00
621 Pipa Maspion AW 2-1/2 m' 41,075.00 53,340.00 164,300.00 164,500.00 165,000.00
622 Pipa Maspion AW 3 m' 60,250.00 73,080.00 241,000.00 241,000.00 241,000.00
623 Pipa Maspion AW 4 m' 85,250.00 104,730.00 341,000.00 342,000.00 343,000.00
624 Pipa Maspion AW 5 m' 134,500.00 18,436.80 538,410.00 538,500.00 538,000.00
625 Pipa Maspion AW 6 m' 178,250.00 217,680.00 713,000.00 715,000.00 716,000.00
626 Pipa Maspion AW 8 m' 276,750.00 385,788.00 1,107,000.00 1,107,500.00 1,108,000.00
627 Pipa Maspion AW 10 m' 394,500.00 544,260.00 1,578,000.00 1,578,000.00 1,579,000.00
628 Pipa Maspion AW 12 m' 563,000.00 877,224.00 2,252,000.00 2,253,000.00 2,254,000.00
629 Pipa Maspion AW 14 m' 792,000.00 1,114,122.00 3,168,000.00 3,168,000.00 3,169,000.00
630 Pipa Maspion AW 16 m' 992,500.00 1,360,767.60 3,970,000.00 3,970,000.00 3,975,000.00
631 Pipa Maspion C 3/4 m' 3,625.00 7,104.00 14,500.00 14,500.00 15,000.00
632 Pipa Maspion C 5/8 m' 2,010.00 3,657.60 8,040.00 8,500.00 9,000.00
633 Pipa Maspion C 1 m' 5,375.00 11,592.00 21,500.00 21,600.00 22,000.00
634 Pipa Maspion C 1-1/2 m' 8,000.00 16,743.60 32,000.00 32,000.00 33,000.00
635 Pipa Maspion C 1-1/4 m' 6,700.00 26,800.00 27,000.00 28,000.00
636 Pipa Maspion C 2 m' 12,700.00 17,541.60 50,800.00 51,000.00 52,000.00
637 Pipa Maspion C 2-1/2 m' 16,200.00 21,819.60 64,800.00 65,000.00 67,000.00
638 Pipa Maspion C 3 m' 18,750.00 31,353.60 75,000.00 76,000.00 77,000.00
639 Pipa Maspion C 3-1/2 m' 21,250.00 42,318.00 85,000.00 87,000.00 88,000.00
640 Pipa Maspion C 4 m' 24,200.00 64,281.60 96,800.00 97,900.00 98,000.00
641 Pipa Maspion D 1/2 m' 11,500.00 92,100.00 46,000.00 47,000.00 48,000.00
642 Pipa Maspion D 1-1/2 m' 11,725.00 111,234.00 46,900.00 47,900.00 48,000.00
643 Pipa Maspion D 1-1/4 m' 10,175.00 193,221.60 40,700.00 41,000.00 41,500.00
644 Pipa Maspion D 2 m' 15,237.50 335,535.60 60,950.00 61,000.00 61,000.00
645 Pipa Maspion D 2-1/2 m' 22,510.00 455,025.60 90,040.00 91,000.00 93,000.00
646 Pipa Maspion D 3 m' 32,750.00 47,514.00 131,000.00 132,000.00 133,000.00
647 Pipa Maspion D 4 m' 46,000.00 66,036.00 184,200.00 184,000.00 185,000.00
648 Pipa Maspion D 5 m' 75,600.00 106,914.00 302,400.00 303,000.00 304,000.00
649 Pipa Maspion D 6 m' 92,250.00 129,219.60 369,620.00 369,000.00 369,000.00
650 Pipa Maspion D 8 m' 160,000.00 226,386.00 640,000.00 640,000.00 641,000.00
651 Pipa Maspion D 10 m' 283,750.00 391,140.00 1,135,000.00 1,136,000.00 1,136,000.00
652 Pipa Maspion D 12 m' 386,500.00 532,482.00 1,546,000.00 1,548,000.00 1,549,000.00
653 Pipa Maspion D 14 m' 513,500.00 695,962.80 2,054,000.00 2,054,000.00 2,055,000.00
654 Pipa Maspion D 16 m' 657,500.00 899,224.80 2,630,000.00 2,631,000.00 2,632,000.00
655 Pipa / selang spiral sel kran m' 28,570.00 49,585.20 28,570.00 28,900.00 29,000.00
656 Pipa langgeng warna abu - abu AW 1/2 m' 7,225.00 15,648.00 28,900.00 28,900.00 29,000.00
657 Pipa langgeng warna abu - abu AW 3/4 m' 8,712.50 16,716.00 34,850.00 35,000.00 35,600.00
658 Pipa langgeng warna abu - abu AW 1 m' 10,960.00 19,838.40 43,840.00 44,000.00 45,000.00
659 Pipa langgeng warna abu - abu AW 1 1/4 m' 15,510.00 24,856.80 62,040.00 63,000.00 64,000.00
660 Pipa langgeng warna abu - abu AW 1 1/2 m' 20,187.50 32,964.00 80,750.00 81,000.00 83,000.00
661 Pipa langgeng warna abu - abu AW 2 m' 30,400.00 45,084.00 121,600.00 122,500.00 123,000.00
662 Pipa langgeng warna abu - abu AW 2 1/2 m' 38,475.00 153,900.00 154,000.00 155,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
663 Pipa langgeng warna abu - abu AW 3 m' 55,625.00 55,620.00 222,500.00 224,000.00 228,000.00
664 Pipa langgeng warna abu - abu AW 4 m' 81,227.50 75,930.00 324,910.00 325,000.00 326,000.00
665 Pipa langgeng warna abu - abu AW 5 m' 127,945.00 107,340.00 511,780.00 512,000.00 513,000.00
666 Pipa langgeng warna abu - abu AW 6 m' 169,525.00 212,520.00 678,100.00 679,000.00 679,000.00
667 Pipa langgeng warna abu - abu AW 8 m' 263,227.50 324,870.00 1,052,910.00 1,053,000.00 1,053,000.00
668 Pipa langgeng warna abu - abu AW 10 m' 375,000.00 453,900.00 1,500,360.00 1,500,000.00 1,500,000.00
669 Pipa langgeng warna abu - abu AW 12 m' 535,325.00 648,540.00 2,141,300.00 2,142,000.00 2,143,000.00
670 Pipa langgeng warna abu - abu AW 16 m' 943,625.00 1,131,660.00 3,774,500.00 3,775,000.00 3,776,000.00
671 Pipa langgeng warna abu - abu D 1 1/4 m' 9,500.00 1,165,680.00 38,870.00 39,000.00 38,000.00
672 Pipa langgeng warna abu - abu D 1 1/2 m' 11,030.00 16,140.00 44,120.00 45,000.00 46,000.00
673 Pipa langgeng warna abu - abu D 2 m' 14,495.00 19,848.00 57,980.00 58,000.00 59,000.00
674 Pipa langgeng warna abu - abu D 2 1/2 m' 21,400.00 29,100.00 85,600.00 86,000.00 86,000.00
675 Pipa langgeng warna abu - abu D 3 m' 31,130.00 40,020.00 124,520.00 125,000.00 129,000.00
676 Pipa langgeng warna abu - abu D 4 m' 43,745.00 55,500.00 174,980.00 175,000.00 176,000.00
677 Pipa langgeng warna abu - abu D 5 m' 71,750.00 89,250.00 287,520.00 287,000.00 289,000.00
678 Pipa langgeng warna abu - abu D 6 m' 63,250.00 108,540.00 351,430.00 352,000.00 253,000.00
679 Pipa langgeng warna abu - abu D 8 m' 154,750.00 190,140.00 619,070.00 619,000.00 619,000.00
680 Pipa langgeng warna abu - abu D 10 m' 269,500.00 324,600.00 1,078,040.00 1,078,000.00 1,079,000.00
681 Pipa langgeng warna abu - abu D 12 m' 367,700.00 442,110.00 1,470,800.00 1,471,000.00 1,481,000.00
682 Pipa langgeng warna abu - abu D 14 m' 482,525.00 590,520.00 1,930,100.00 1,931,000.00 1,932,000.00
683 Pipa langgeng warna abu - abu D 16 m' 625,000.00 749,928.00 2,500,550.00 2,500,000.00 2,500,000.00
684 Pipa langgeng warna abu - abu D 20 m' 1,076,890.00 1,288,125.60 4,307,560.00 4,308,000.00 4,309,000.00
685 Pipa langgeng warna abu - abu C 5/8 m' 2,020.00 1,325,029.20 8,080.00 9,500.00 10,000.00
686 Pipa langgeng warna abu - abu C 1/2 m' 3,345.00 6,720.00 13,380.00 14,500.00 14,600.00
687 Pipa langgeng warna abu - abu C 3/4 m' 3,620.00 8,418.00 14,480.00 15,000.00 15,000.00
688 Pipa langgeng warna abu - abu C 1 m' 5,045.00 10,740.00 20,180.00 21,000.00 21,000.00
689 Pipa langgeng warna abu - abu C 1 1/4 m' 6,685.00 13,038.00 26,740.00 27,500.00 30,000.00
690 Pipa langgeng warna abu - abu C 1 1/2 m' 7,997.50 12,300.00 31,990.00 32,000.00 33,000.00
691 Pipa langgeng warna abu - abu C 2 m' 12,060.00 18,408.00 48,240.00 49,500.00 49,000.00
692 Pipa langgeng warna abu - abu C 2 1/2 m' 15,365.00 23,880.00 61,460.00 62,000.00 63,000.00
693 Pipa langgeng warna abu - abu C 3 m' 18,730.00 26,265.60 74,920.00 75,000.00 75,000.00
694 Pipa langgeng warna abu - abu C 4 m' 23,870.00 32,475.60 95,480.00 96,000.00 96,000.00
695 Pipa langgeng warna abu - abu C 5 m' 32,300.00 46,068.00 129,200.00 130,000.00 130,000.00
696 Pipa winlon warna abu - abu AW 1/2 m' 6,175.00 9,906.00 24,700.00 25,000.00 25,000.00
697 Pipa winlon warna abu - abu AW 3/4 m' 7,750.00 13,020.00 31,600.00 31,600.00 31,000.00
698 Pipa winlon warna abu - abu AW 1 m' 10,250.00 17,448.00 41,040.00 41,500.00 41,000.00
699 Pipa winlon warna abu - abu AW 1 1/4 m' 14,925.00 20,326.80 59,700.00 60,000.00 62,000.00
700 Pipa winlon warna abu - abu AW 1 1/2 m' 17,700.00 26,256.00 70,800.00 71,000.00 71,000.00
701 Pipa winlon warna abu - abu AW 2 m' 25,400.00 36,860.40 101,600.00 102,000.00 103,000.00
702 Pipa winlon warna abu - abu AW 2 1/2 m' 33,150.00 44,037.60 132,600.00 133,000.00 133,000.00
703 Pipa winlon warna abu - abu AW 3 m' 46,500.00 61,467.60 186,000.00 187,000.00 189,000.00
704 Pipa winlon warna abu - abu AW 4 m' 71,875.00 89,472.00 287,500.00 288,000.00 289,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
705 Pipa winlon warna abu - abu AW 5 m' 113,625.00 139,218.00 454,500.00 455,000.00
706 Pipa winlon warna abu - abu AW 6 m' 143,550.00 175,080.00 574,200.00 575,000.00
707 Pipa winlon warna abu - abu AW 8 m' 227,950.00 275,400.00 911,800.00 912,000.00
708 Pipa winlon warna abu - abu AW 10 m' 324,250.00 394,920.00 1,297,000.00 1,297,000.00
709 Pipa winlon warna abu - abu AW 12 m' 545,250.00 651,306.00 2,181,000.00 2,181,000.00
710 Pipa winlon warna abu - abu D 1 1/4 m' 8,662.50 14,070.00 34,650.00 35,000.00
711 Pipa winlon warna abu - abu D 1 1/2 m' 9,850.00 16,272.00 39,400.00 39,500.00
712 Pipa winlon warna abu - abu D 2 m' 12,760.00 19,320.00 51,040.00 51,600.00
713 Pipa winlon warna abu - abu D 2 1/2 m' 18,225.00 26,400.00 72,900.00 73,000.00
714 Pipa winlon warna abu - abu D 3 m' 26,450.00 34,920.00 105,800.00 107,000.00
715 Pipa winlon warna abu - abu D 4 m' 37,510.00 35,022.00 150,040.00 151,000.00
716 Pipa winlon warna abu - abu D 6 m' 59,625.00 48,660.00 238,500.00 239,000.00
717 Pipa winlon warna abu - abu D 8 m' 131,037.50 159,660.00 524,150.00 525,000.00
718 Pipa winlon warna abu - abu D 10 m' 243,100.00 292,719.60 972,400.00 973,500.00
719 Pipa winlon warna abu - abu D 12 m' 330,750.00 395,220.00 1,323,000.00 1,335,000.00
720 Pipa winlon warna abu - abu C 5/8 m' 1,677.50 4,512.00 6,710.00 6,800.00
721 Pipa winlon warna abu - abu C 1/2 m' 3,025.00 5,056.80 12,100.00 14,000.00
722 Pipa winlon warna abu - abu C 3/4 m' 3,250.00 5,862.00 13,000.00 15,000.00
723 Pipa winlon warna abu - abu C 1 m' 4,625.00 8,136.00 18,500.00 19,000.00
724 Pipa winlon warna abu - abu C 1 1/4 m' 5,850.00 10,404.00 23,400.00 24,000.00
725 Pipa winlon warna abu - abu C 1 1/2 m' 7,625.00 11,853.60 30,500.00 31,000.00
726 Pipa winlon warna abu - abu C 2 m' 10,260.00 15,147.60 41,040.00 45,000.00
727 Pipa winlon warna abu - abu C 2 1/2 m' 12,900.00 18,822.00 51,600.00 60,000.00
728 Pipa winlon warna abu - abu C 3 m' 15,977.50 22,606.80 63,910.00 64,000.00
729 Pipa winlon warna abu - abu C 4 m' 22,025.00 29,332.80 88,100.00 89,000.00
730 Pipa wavin warna putih AW 1/2 m' 5,825.00 9,156.00 23,300.00 24,000.00
731 Pipa wavin warna putih AW 3/4 m' 7,925.00 11,790.00 31,700.00 31,800.00
732 Pipa wavin warna putih AW 1 m' 10,825.00 15,528.00 43,300.00 43,900.00
733 Pipa wavin warna putih AW 1 1/4 m' 16,200.00 21,777.60 64,800.00 65,000.00
734 Pipa wavin warna putih AW 1 1/2 m' 18,600.00 24,699.60 74,400.00 75,000.00
735 Pipa wavin warna putih AW 2 m' 23,825.00 30,891.60 95,300.00 101,000.00
736 Pipa wavin warna putih AW 2 1/2 m' 34,725.00 47,220.00 138,900.00 139,000.00
737 Pipa wavin warna putih AW 3 m' 48,900.00 61,110.00 195,600.00 196,000.00
738 Pipa wavin warna putih AW 4 m' 81,025.00 100,200.00 324,100.00 325,000.00
739 Pipa wavin warna putih AW 5 m' 128,400.00 156,720.00 513,600.00 519,000.00
740 Pipa wavin warna putih AW 6 m' 180,000.00 219,360.00 720,000.00 731,000.00
741 Pipa wavin warna putih AW 8 m' 302,200.00 364,950.00 1,208,800.00 1,209,000.00
742 Pipa wavin warna putih AW 10 m' 465,750.00 563,718.00 1,868,000.00 1,863,000.00
743 Pipa wavin warna putih AW 12 m' 658,750.00 799,560.00 2,635,000.00 2,645,000.00
744 Pipa wavin warna putih D 1 1/4 m' 10,175.00 14,340.00 40,700.00 40,800.00
745 Pipa wavin warna putih D 1 1/2 m' 11,500.00 15,420.00 46,000.00 47,000.00
746 Pipa wavin warna putih D 2 m' 14,750.00 20,550.00 59,000.00 60,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
747 Pipa wavin warna putih D 2 1/2 m' 19,925.00 27,300.00 79,700.00 80,000.00
748 Pipa wavin warna putih D 3 m' 26,450.00 34,455.60 105,800.00 106,000.00
749 Pipa wavin warna putih D 4 m' 41,600.00 53,994.00 166,400.00 167,000.00
750 Pipa wavin warna putih D 5 m' 64,200.00 80,178.00 256,800.00 257,000.00
751 Pipa wavin warna putih D 6 m' 84,525.00 104,190.00 338,100.00 339,000.00
752 Pipa wavin warna putih D 8 m' 148,650.00 182,070.00 594,600.00 595,000.00
753 Pipa wavin warna putih D 10 m' 244,875.00 298,410.00 979,500.00 979,800.00
754 Pipa wavin warna putih D 12 m' 343,500.00 431,280.00 1,374,000.00 1,374,000.00
755 Pipa langgeng warna putih AW 1/2 m' 5,372.50 9,381.60 21,490.00 21,490.00
756 Pipa langgeng warna putih AW 3/4 m' 7,357.50 19,264.80 29,430.00 29,431.00
757 Pipa langgeng warna putih AW 1 m' 10,057.50 14,012.40 40,230.00 40,231.00
758 Pipa langgeng warna putih AW 1 1/4 m' 15,085.00 23,277.60 60,340.00 60,400.00
759 Pipa langgeng warna putih AW 1 1/2 m' 17,325.00 25,602.00 69,300.00 69,400.00
760 Pipa langgeng warna putih AW 2 m' 22,175.00 28,376.40 88,700.00 88,900.00
761 Pipa langgeng warna putih AW 2 1/2 m' 32,350.00 148,320.00 129,400.00 129,500.00
762 Pipa langgeng warna putih AW 3 m' 43,625.00 55,747.20 174,500.00 174,600.00
763 Pipa langgeng warna putih AW 4 m' 72,250.00 88,473.60 289,000.00 289,000.00
764 Pipa langgeng warna putih AW 5 m' 119,500.00 142,659.60 478,000.00 478,000.00
765 Pipa langgeng warna putih AW 6 m' 167,750.00 199,164.00 671,000.00 672,000.00
766 Pipa langgeng warna putih AW 8 m' 281,750.00 331,806.00 1,127,000.00 1,128,000.00
767 Pipa langgeng warna putih AW 10 m' 435,750.00 511,762.80 1,743,000.00 1,845,000.00
768 Pipa langgeng warna putih AW 12 m' 614,250.00 599,080.80 2,457,000.00 2,458,000.00
769 Pipa langgeng warna putih AW 14 m' 841,000.00 982,945.20 3,364,000.00 3,364,000.00
770 Pipa langgeng warna putih AW 16 m' 1,051,500.00 1,229,052.00 4,206,000.00 4,300,000.00
771 Pipa langgeng warna putih D 1 1/4 m' 9,450.00 12,300.00 37,800.00 38,900.00
772 Pipa langgeng warna putih D 1 1/2 m' 10,725.00 15,258.00 42,900.00 43,900.00
773 Pipa langgeng warna putih D 2 m' 13,500.00 19,005.60 54,900.00 54,000.00
774 Pipa langgeng warna putih D 2 1/2 m' 18,562.50 23,936.40 74,250.00 75,000.00
775 Pipa langgeng warna putih D 3 m' 23,575.00 30,244.80 94,300.00 98,000.00
776 Pipa langgeng warna putih D 4 m' 37,075.00 428,340.00 148,300.00 149,000.00
777 Pipa langgeng warna putih D 5 m' 59,750.00 72,705.60 239,600.00 239,000.00
778 Pipa langgeng warna putih D 6 m' 78,825.00 94,846.80 315,300.00 316,000.00
779 Pipa langgeng warna putih D 8 m' 138,600.00 164,952.00 554,400.00 558,500.00
780 Pipa langgeng warna putih D 10 m' 228,250.00 269,392.80 913,000.00 915,000.00
781 Pipa langgeng warna putih D 12 m' 320,500.00 376,370.40 1,282,000.00 1,282,000.00
782 Pipa langgeng warna putih D 14 m' 536,500.00 633,900.00 2,146,000.00 2,147,000.00
783 Pipa langgeng warna putih D 16 m' 694,500.00 821,102.40 2,778,000.00 2,800,000.00
784 Pipa langgeng warna putih D 20 m' 1,099,675.00 1,297,730.40 4,398,700.00 4,400,000.00
785 Pipa langgeng warna putih C 5/8 m' 2,125.00 4,899.60 8,500.00 9,000.00
786 Pipa setara warna putih C 1/2 m' 3,450.00 7,500.00 13,800.00 13,900.00
787 Pipa langgeng warna putih C 3/4 m' 4,100.00 8,400.00 16,400.00 17,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
788 Pipa langgeng warna putih C 1 m' 5,200.00 8,190.00 20,800.00 21,000.00
789 Pipa langgeng warna putih C 1 1/4 m' 6,900.00 12,780.00 27,600.00 30,000.00
790 Pipa langgeng warna putih C 1 1/2 m' 8,520.00 13,797.60 34,080.00 40,000.00
791 Pipa langgeng warna putih C 2 m' 12,485.00 20,019.60 49,940.00 51,000.00
792 Pipa langgeng warna putih C 2 1/2 m' 15,815.00 20,908.80 63,260.00 64,000.00
793 Pipa langgeng warna putih C 3 m' 19,270.00 25,480.80 77,080.00 78,000.00
794 Pipa langgeng warna putih C 4 m' 24,830.00 31,065.60 99,320.00 101,000.00
795 Pipa winlon warna putih AW 1/2 m' 4,300.00 11,460.00 17,200.00 18,000.00
796 Pipa winlon warna putih AW 3/4 m' 5,725.00 10,473.60 22,900.00 23,000.00
797 Pipa winlon warna putih AW 1 m' 7,975.00 12,910.80 31,900.00 31,900.00
798 Pipa winlon warna putih AW 1 1/4 m' 11,100.00 21,054.00 44,400.00 45,000.00
799 Pipa winlon warna putih AW 1 1/2 m' 14,400.00 24,510.00 57,600.00 57,900.00
800 Pipa winlon warna putih AW 2 m' 19,850.00 33,978.00 79,400.00 80,000.00
801 Pipa winlon warna putih AW 2 1/2 m' 26,625.00 30,180.00 106,500.00 108,000.00
802 Pipa winlon warna putih AW 3 m' 36,725.00 58,860.00 146,900.00 148,000.00
803 Pipa winlon warna putih AW 4 m' 60,875.00 88,428.00 243,500.00 245,000.00
804 Pipa winlon warna putih AW 5 m' 90,475.00 138,393.60 361,900.00 365,000.00
805 Pipa winlon warna putih AW 6 m' 129,950.00 173,178.00 519,800.00 520,000.00
806 Pipa winlon warna putih AW 8 m' 203,800.00 273,360.00 815,200.00 819,000.00
807 Pipa winlon warna putih AW 10 m' 293,750.00 388,695.60 1,175,000.00 1,178,000.00
808 Pipa winlon warna putih D 1 1/4 m' 6,875.00 9,622.80 27,500.00 28,000.00
809 Pipa winlon warna putih D 1 1/2 m' 8,375.00 13,486.80 33,500.00 35,000.00
810 Pipa winlon warna putih D 2 m' 11,200.00 16,590.00 44,800.00 45,000.00
811 Pipa winlon warna putih D 2 1/2 m' 15,200.00 21,386.40 60,800.00 61,000.00
812 Pipa winlon warna putih D 3 m' 18,950.00 25,197.60 75,800.00 78,000.00
813 Pipa winlon warna putih D 4 m' 30,725.00 41,214.00 122,900.00 123,000.00
814 Pipa winlon warna putih D 5 m' 45,200.00 58,898.40 180,800.00 185,000.00
815 Pipa winlon warna putih D 6 m' 64,650.00 82,980.00 258,600.00 259,000.00
816 Pipa winlon warna putih D 8 m' 110,137.50 140,017.20 440,550.00 445,000.00
817 Pipa winlon warna putih D 10 m' 207,450.00 261,306.00 829,800.00 830,000.00
818 Pipa winlon warna putih C 5/8 m' 1,575.00 4,785.60 6,300.00 6,400.00
819 Pipa winlon warna putih C 1/2 m' 2,915.00 6,740.40 11,660.00 12,000.00
820 Pipa winlon warna putih C 3/4 m' 3,190.00 7,650.00 12,760.00 13,000.00
821 Pipa winlon warna putih C 1 m' 4,725.00 8,352.00 18,900.00 19,900.00
822 Pipa winlon warna putih C 1 1/4 m' 5,500.00 10,200.00 22,000.00 22,000.00
823 Pipa winlon warna putih C 1 1/2 m' 6,875.00 11,688.00 27,500.00 28,000.00
824 Pipa winlon warna putih C 2 m' 9,652.50 15,180.00 38,610.00 39,700.00
825 Pipa winlon warna putih C 2 1/2 m' 12,155.00 17,700.00 48,620.00 50,000.00
826 Pipa winlon warna putih C 3 m' 15,150.00 21,936.00 60,600.00 61,000.00
### 827 Pipa winlon warna putih C 4 m' 20,185.00 28,226.40 80,740.00 82,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
828 Pipa vilano warna putih AW 1/2 m' 4,000.00 8,640.00 16,000.00 17,500.00
829 Pipa vilano warna putih AW 3/4 m' 5,500.00 9,912.00 22,000.00 23,000.00
830 Pipa vilano warna putih AW 1 m' 7,177.50 11,940.00 28,710.00 29,800.00
831 Pipa vilano warna putih AW 1 1/4 m' 10,450.00 16,465.20 41,800.00 45,000.00
832 Pipa vilano warna putih AW 3 m' 32,650.00 43,363.20 130,600.00 132,000.00
833 Pipa vilano warna putih AW 4 m' 46,975.00 61,273.20 187,900.00 195,000.00
834 Pipa vilano warna putih AW 5 m' 78,250.00 98,842.80 313,000.00 315,000.00
835 Pipa vilano warna putih AW 6 m' 112,000.00 140,486.40 448,000.00 450,000.00
836 Pipa vilano warna putih D 1 1/4 m' 6,517.50 12,890.40 26,070.00 27,000.00
837 Pipa vilano warna putih D 1 1/2 m' 7,750.00 14,745.60 31,500.00 31,000.00
838 Pipa vilano warna putih D 2 m' 10,025.00 15,870.00 40,500.00 40,100.00
839 Pipa vilano warna putih D 2 1/2 m' 13,750.00 19,920.00 55,000.00 55,600.00
840 Pipa vilano warna putih D 3 m' 17,625.00 24,006.00 70,500.00 75,000.00
841 Pipa vilano warna putih D 4 m' 27,250.00 36,434.40 109,000.00 109,500.00
842 Pipa vilano warna putih D 5 m' 35,900.00 47,016.00 143,600.00 145,000.00
843 Pipa vilano warna putih D 6 m' 62,000.00 78,488.40 248,000.00 249,000.00
844 PVC Pipe dia. 150 mm m 25,000.00 216,015.60 25,000.00 26,000.00
845 Elbow 90̊, dia 150 mm bh 175,000.00 201,903.60 175,000.00 185,000.00
846 Elbow 45, dia 150 mm bh 185,000.00 176,010.00 185,000.00 195,000.00
847 Sochet dia. 150 bh 115,000.00 94,476.00 115,000.00 118,000.00
848 shortpipe ke HI dan pipa bh 22,000.00 383,910.00 22,000.00 25,000.00
849 saddle branch bh 420,000.00 460,020.00 450,000.00 420,000.00
850 solvent cement kg 15,000.00 62,370.00 15,000.00 16,000.00
851 PVC Pipe dia. 200 mm m 350,000.00 301,870.80 350,000.00 352,000.00
852 Sochet dia. 200 bh 315,000.00 190,575.00 315,000.00 316,000.00
853 Tee dia 200 x 150 mm bh 730,000.00 734,144.40 730,000.00 735,000.00
854 Pipa PVC ( class D ) dia 150 mm m' 90,000.00 91,440.00 90,000.00 91,000.00
855 Bend dia 150, 90 (DV) bh 40,000.00 45,738.00 45,700.00 40,000.00
856 Bend dia 150, 45 (DV) bh 45,750.00 45,738.00 45,750.00 45,800.00
857 sochet dia 150 mm (DV) bh 36,720.00 36,729.00 36,720.00 36,800.00
858 Pipa PVC ( class D ) dia 4" dia 100 mm, length = 4 m m' 48,700.00 48,752.88 48,700.00 48,750.00
859 Sochet dia. 100 mm bh 49,000.00 49,333.68 49,000.00 49,300.00
860 Bend dia 100, 90 bh 50,000.00 52,058.16 50,000.00 52,000.00
861 Bend dia 100, 45 bh 26,099.00 26,099.04 26,099.00 27,000.00
862 Tee Y 45 ; 4" x 2" bh 58,500.00 36,202.32 58,500.00 58,600.00
863 Tee Y 45 ; 4" x 3" bh 65,000.00 49,729.68 65,000.00 65,000.00
864 Tee Y 45 ; 4" x 4" bh 85,000.00 56,036.64 85,000.00 95,000.00
865 Dop PVC 4" bh 12,500.00 20,679.12 12,500.00 13,000.00
866 Reducer 150 x 100 mm bh 48,000.00 48,000.00 48,000.00 48,000.00
867 Pipa PVC ( class D ) dia 3" dia. 75mm, length 4 m m 31,100.00 31,132.20 31,100.00 32,000.00
868 Large Radius Elbow dia. 75, 90o bh 45,000.00 25,031.16 45,000.00 46,000.00
869 Bend dia 75, 45 bh 14,000.00 14,512.08 14,500.00 14,000.00
870 Sochet dia. 75 mm bh 9,000.00 9,051.24 9,100.00 9,000.00
871 Dop PVC 3" bh 10,500.00 10,991.64 10,500.00 10,600.00
872 Reducer 100 x 75 mm bh 50,000.00 51,600.00 50,000.00 51,500.00
873 Pipa PVC ( class D ) dia 2" m 30,000.00 16,080.00 30,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
874 Sochet dia. 50 mm bh 17,000.00 6,306.96 18,500.00 19,000.00 17,000.00
875 Large Radius Elbow dia. 50, 90o bh 11,000.00 11,032.56 11,300.00 11,000.00
876 Bend dia 50, 45 bh 6,500.00 6,501.00 6,500.00 6,550.00 6,551.00
877 Dop PVC 2" bh 9,000.00 9,702.00 9,000.00 10,000.00 10,000.00
878 Pipa PVC (class D), Ø 2 1/2" (63 mm) SCJ m 27,500.00 27,600.00 27,500.00 28,000.00 28,500.00
879 Socket dia 63 mm bh 8,000.00 9,000.00 8,500.00 8,000.00 8,650.00
880 Bend dia 63, 90o bh 7,200.00 7,200.00 7,200.00 7,250.00 7,400.00
881 Bend dia 63, 45o bh 5,200.00 5,280.00 5,280.00 5,200.00 5,400.00
882 Dop PVC 1 1/2" bh 4,100.00 4,200.00 4,100.00 4,300.00 4,100.00
883 Pipa PVC (class D), Ø 1 1/2" (40 mm) SCJ m 10,500.00 10,800.00 10,500.00 10,700.00 10,650.00
884 Socket dia 40 mm bh 5,200.00 5,400.00 5,200.00 5,350.00 5,400.00
885 Bend dia 40, 90o bh 2,600.00 2,640.00 2,620.00 2,670.00 2,600.00
886 Bend dia 40, 45o bh 3,100.00 3,120.00 3,100.00 3,120.00 3,400.00
887 Dop PVC 1 1/2" bh 2,100.00 2,160.00 2,120.00 2,100.00 2,150.00
888 Pipa PVC D, Ø 1 1/4" (30 mm) SCJ m 10,000.00 12,000.00 10,000.00 11,500.00 13,000.00
889 Socket dia 30 mm bh 3,500.00 3,780.00 3,700.00 3,500.00 3,800.00
890 Bend dia 30, 90o bh 1,500.00 1,800.00 1,500.00 1,700.00 1,900.00
891 Bend dia 30, 45o bh 1,610.00 1,620.00 1,610.00 1,650.00 1,621.00
892 Dop PVC 1 1/4" bh 1,040.00 1,080.00 1,085.00 1,040.00 1,100.00
893 Pipa PVC D, Ø 1" (25 mm) SCJ m 6,400.00 6,660.00 6,600.00 6,650.00 6,400.00
894 Socket dia 25 mm bh 2,200.00 2,220.00 2,200.00 2,250.00 2,350.00
895 Bend dia 25, 90o bh 1,025.00 1,020.00 1,025.00 1,200.00 1,250.00
896 Bend dia 25, 45o bh 1,000.00 1,020.00 1,035.00 1,200.00 1,000.00
897 Dop PVC 1 1/4" bh 850.00 900.00 850.00 900.00 950.00
898 Tee Y; 3" x 3" bh 21,000.00 21,000.00 21,000.00 22,000.00 23,000.00
899 Tee Y; 3" x 2" bh 26,000.00 26,400.00 26,500.00 26,000.00 27,000.00
900 Tee ; 2" x 2" bh 11,200.00 11,400.00 11,250.00 11,200.00 11,300.00
901 Sifon Crom Leher Angsa bh 350,000.00 184,143.96 350,000.00 351,000.00 351,500.00
902 Pipa PVC Ø 6" M 210,000.00 292,238.76 210,000.00 211,000.00 215,000.00
903 Pipa PVC Ø 4" M 89,000.00 136,798.20 89,000.00 90,000.00 91,000.00
904 Pipa PVC Ø 3" M 75,000.00 94,014.36 75,000.00 76,000.00 78,000.00
905 Pipa PVC Ø 2" M 50,000.00 43,797.60 50,000.00 51,000.00 53,000.00
906 Pipa GI Ø 4" M 16,000.00 557,997.00 16,000.00 17,000.00 18,000.00
907 Pipa GI Ø 3" M 18,000.00 401,940.00 18,000.00 19,000.00 19,800.00
908 Pipa GI Ø 2" M 12,000.00 255,717.00 12,000.00 13,000.00 14,000.00
909 PVC Tee R-R Ø 10" x 3" bh 90,000.00 7,185,994.20 90,000.00 91,000.00 92,000.00
910 PVC Tee R-R Ø 6" x 4" bh 87,000.00 1,704,780.00 87,000.00 88,000.00 89,000.00
911 PVC Tee R-R Ø 6" x 3" bh 66,000.00 1,801,800.00 66,000.00 67,000.00 68,000.00
912 PVC Tee R-R Ø 4" x 4" bh 63,000.00 942,480.00 63,000.00 64,000.00 65,000.00
913 PVC Tee R-R Ø 4" x 3" bh 53,000.00 824,670.00 53,000.00 54,000.00 56,000.00
914 PVC Tee R-R Ø 3" x 3" bh 48,000.00 418,294.80 48,000.00 49,000.00 50,000.00
915 PVC Tee R-R Ø 2" x 3" bh 73,000.00 436,590.00 73,000.00 74,000.00 75,000.00
916 PVC Tee R-SC Ø 4" x 2" bh 69,000.00 658,350.00 69,000.00 70,000.00 71,000.00
917 PVC Tee R-SC Ø 3" x 2" bh 51,000.00 416,640.00 51,000.00 52,000.00 53,000.00
918 PVC Tee SC-SC Ø 2" x 2" bh 415,000.00 93,990.00 415,000.00 416,000.00 418,000.00
919 CI Giboult Joint Std Jis Ø 10" bh 395,000.00 2,201,370.60 395,000.00 398,000.00 399,000.00
920 CI Giboult Joint Std SII Ø 6" bh 380,000.00 968,814.00 380,000.00 385,000.00 386,000.00
921 CI Giboult Joint Std SII Ø 4" bh 310,000.00 755,730.00 310,000.00 315,000.00 316,000.00
922 CI Giboult Joint Std SII Ø 3" bh 256,000.00 548,856.00 256,000.00 267,000.00 269,000.00
923 CI Gate Valve FL- FL Ø 4" bh 278,000.00 5,821,200.00 278,000.00 279,000.00 279,000.00
924 CI Plat Cap Ø 4" bh 186,000.00 278,933.16 186,000.00 187,000.00 188,000.00
925 PVC Tapper Core Ø 4" bh 115,000.00 839,130.00 115,000.00 116,000.00 117,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
926 PVC Tapper Core Ø 3" bh 101,000.00 637,560.00 101,000.00 101,000.00 102,000.00
927 BS Bend FL- FL Ø 4" x 45 ̊ bh 115,000.00 996,534.00 115,000.00 116,000.00 118,000.00
928 BS Bend FL- FL Ø 3" x 45 ̊ bh 110,000.00 717,948.00 110,000.00 112,000.00 113,000.00
929 BS Flenge Ø 4" bh 55,000.00 215,384.40 55,000.00 56,000.00 58,000.00
930 BS Flange Ø 3" bh 50,000.00 172,972.80 50,000.00 51,000.00 53,000.00
931 Karet Packing Ø 4" bh 99,000.00 29,106.00 99,000.00 101,000.00 102,000.00
932 Karet Packing Ø 3" bh 90,000.00 24,948.00 90,000.00 95,000.00 98,000.00
933 Bronze Gate Valve Ø 3" bh 60,000.00 1,940,400.00 60,000.00 62,000.00 63,000.00
934 Bronze Gate Valve Ø 2" bh 55,000.00 708,246.00 55,000.00 56,000.00 56,000.00
935 PVC Valve Sochet Ø 3" bh 90,000.00 90,000.00 91,000.00 93,000.00
936 PVC Valve Sochet Ø 2" bh 66,000.00 66,000.00 67,000.00 67,000.00
937 GI Cap Ø 3" bh 42,000.00 58,257.60 42,000.00 43,000.00 43,000.00
938 GI Cap Ø 2" bh 41,000.00 26,749.80 41,000.00 44,000.00 45,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
939 GI Elbow Ø 2" bh 6,000.00 50,011.20 6,000.00
940 PVC Bend R- R Ø 4" x 90 ̊ bh 38,000.00 284,647.20 38,000.00
941 PVC Bend R- R Ø 4" x 45 ̊ bh 40,000.00 182,034.60 40,000.00
942 PVC Bend R- R Ø 3" x 45 ̊ bh 25,000.00 132,315.60 25,000.00
943 PVC Bend R- R Ø 3" x 90 ̊ bh 21,000.00 138,784.80 21,000.00
944 PVC Elbow Ø 2" bh 10,000.00 51,282.00 10,000.00
945 PVC Reducer R-R Ø 4" x 3" bh 65,000.00 136,548.00 65,000.00
946 PVC Reducer R-R Ø 3" x 2" bh 60,000.00 65,742.00 60,000.00
947 Beton Path box bh 30,000.00 381,390.00 30,000.00
948 Beton KS bh 15,000.00 69,360.00 15,000.00
949 Pipa Selubung Valve M 30,000.00 98,024.52 30,000.00
950 Penutup Pipa bh 18,000.00 22,358.40 18,000.00
951 Patok UP bh 65,000.00 4,065.60 65,000.00
952 Beton Penahan Ø 10" bh 920,000.00 926,762.76 920,000.00 925,000.00
953 Beton Penahan Ø 6" bh 195,000.00 198,600.60 198,000.00 195,000.00
954 Beton Penahan Ø 4" bh 68,000.00 68,967.36 68,000.00 68,500.00
955 Beton Penahan Ø 3" bh 135,000.00 158,835.60 155,000.00 135,000.00
956 Beton Penahan Ø 2" bh 2,500.00 2,719.20 2,500.00 2,700.00
957 Baut Dynabol bh 4,000.00 56,040.00 4,000.00

BAHAN LISTRIK
958 Coaxial cable 5C - 75 ohm commscof m1 25,000.00 28,380.00 25,000.00
959 Box Panel (3 mm) (400 x 600) Bh 850,000.00 829,862.40 850,000.00
960 Figting lampu Broco Bh 15,000.00 30,492.00 15,000.00
961 Inbow dos plastik clipsal E 157 P OB bj 8,000.00 16,542.24 8,000.00
962 Kabel NYM 2 x 1.5 mm Suprime NYM m1 7,000.00 15,246.00 7,000.00
963 Kabel NYY 2 x 1.5 mm m1 8,900.00 22,107.36 8,900.00
964 Kabel NYM 2 x 2.5 mm m1 12,000.00 22,869.00 12,000.00
965 Kabel NYY 3 x 1.5 mm m1 14,000.00 27,442.80 14,000.00
966 Kabel NYM 3 x 2.5 mm m1 15,500.00 29,700.00 15,500.00
967 Kabel NYY 3 x 2.5 mm m1 19,500.00 38,643.00 19,500.00
968 Kabel NYM 4 mm m1 30,000.00 60,093.00 30,000.00
969 Kabel NYY 2 x 2,5 mm m1 17,000.00 29,729.04 17,000.00
970 Kabel Twisteed 2 x 16 mm m1 5,500.00 24,717.00 5,500.00
971 Kabel telephone m1 3,000.00 24,231.24 3,000.00
972 Klem clipsal 20 mm bj 2,500.00 15,280.32 2,500.00
973 Casing Lampu Bawah Air bh 85,000.00 88,704.00 85,000.00
974 Casing Lampu Tangga bh 90,000.00 92,169.00 90,000.00
975 Kap Lampu 14 Inchi Aluminium bh 120,000.00 124,740.00 120,000.00
976 Fitting Gantung E27 bh 10,000.00 21,422.40 10,000.00
977 Lampu Son 150 Watt Setara Philips Set 80,000.00 83,760.00 80,000.00
978 Lampu Mercury (halaman) bh 550,000.00 640,932.00 550,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
979 Lampu Mercury 125 Watt Setara Philips Set 60,000.00 70,032.00 60,000.00 60,500.00
980 Lampu Mercury 250 Watt Setara Philips Set 66,000.00 112,140.00 66,000.00 66,500.00
981 Lampu Mercury 400 Watt Setara Philips Set 150,000.00 152,640.00 150,000.00 151,000.00
982 Lampu pijar 10 Watt Setara Philips bh 9,000.00 11,110.80 9,000.00 9,500.00
983 Lampu pijar 15 Watt Setara Philips bh 10,000.00 11,820.00 10,000.00 11,000.00
984 Lampu pijar 25 Watt Setara Philips bh 12,000.00 12,480.00 12,000.00 12,000.00
985 Lampu pijar 40 Watt Setara Philips bh 15,500.00 13,495.20 15,500.00 16,000.00
986 Lampu TL 20 Watt Komplit (Ballast Philips) bh 151,000.00 160,083.00 151,000.00 153,000.00
987 Lampu TL 25 Watt Komplit (Ballast Philips) bh 185,000.00 197,280.00 185,000.00 185,600.00
988 Lampu LED (5 Watt) Setara Philips Bh 60,000.00 78,632.40 60,000.00 61,000.00
989 Lampu LED (7 Watt) Setara Philips Bh 75,000.00 114,936.00 75,000.00 76,000.00
990 Lampu LED (10) Setara Philips Bh 85,000.00 161,276.40 85,000.00 89,000.00
991 Lampu LED (13 Watt) Setara Philips Bh 94,000.00 207,141.60 94,000.00 95,000.00
992 Lampu Sorot LED (5 Watt) Setara Philips Bh 32,000.00 290,274.00 32,000.00 32,000.00
993 Lampu Sorot LED (7 Watt) Setara Philips Bh 35,000.00 334,461.60 35,000.00 38,000.00

994 Lampu Sorot LED (10 Watt) Setara Philips Bh 40,000.00 390,951.00 40,000.00 41,000.00
995 Lampu Sorot LED (13 Watt) Setara Philips Bh 48,000.00 503,838.00 48,000.00 49,000.00
996 Lampu Sorot LED (25 Watt) Setara Philips Bh 65,000.00 1,050,042.00 65,000.00 68,000.00
997 Lampu Sorot LED (100 Watt) Setara Philips (ip65) Bh 68,000.00 2,009,700.00 68,000.00 68,600.00
998 Lampu Sorot Cahaya RGB (LED) 100 watt setara Philips (ip65) Bh 40,000.00 3,327,600.00 40,000.00 41,000.00
999 Lampu Sorot Bawah Cahaya Warm White (bolam) 400 watt setara Philips Bh 110,000.00 4,436,400.00 110,000.00 111,000.00
1000 Lampu Sorot Bawah Cahaya Warm White (LED) 10 watt setara Philips (ip Bh 45,000.00 381,870.00 45,000.00 46,000.00
1001 Lampu Sorot Bawah Cahaya Warm White (LED) 30 watt setara Philips (ip Bh 65,000.00 527,400.00 65,000.00 67,000.00
1002 Lampu Esensial (5 Watt) Setara Philips Bh 39,000.00 42,928.80 39,000.00 40,000.00
1003 Lampu Esensial (8 Watt) Setara Philips Bh 41,000.00 53,361.00 41,000.00 42,000.00
1004 Lampu Esensial (11 Watt) Setara Philips Bh 50,000.00 61,344.00 50,000.00 51,000.00
1005 Lampu Esensial (14 Watt) Setara Philips Bh 56,500.00 73,780.80 56,500.00 57,000.00
1006 Lampu Esensial (18 Watt) Setara Philips Bh 59,000.00 81,404.40 59,000.00 60,500.00
1007 Scot Light m2 65,000.00 123,354.00 65,000.00 66,000.00
1008 Magnet Contactor 80 A SN - 50 Bh 19,000.00 1,698,160.20 19,000.00 19,800.00
1009 MCB 3 phase 40 A MG Bh 445,000.00 481,704.96 445,000.00 447,000.00
1010 MCB 3 phase 63 A MG Bh 345,000.00 915,384.36 345,000.00 346,000.00
1011 Panel MDP Unit 36,500,000.00 47,256,000.00 36,500,000.00 36,800,000.00
1012 Panel SDP Unit 19,000,000.00 23,760,000.00 19,000,000.00 19,500,000.00
1013 Pipa clipsal 20 mm bt 12,000.00 21,344.40 12,000.00 13,000.00
1014 Pipa flexible clipsal 20 mm m1 4,000.00 15,846.00 4,000.00 5,000.00
1015 Saklar ganda Setara Broco Bh 18,000.00 56,040.00 18,000.00 19,000.00
1016 Saklar tunggal Setara Broco Bh 15,000.00 28,042.80 15,000.00 16,500.00
1017 SL 18 Watt Komplit bh 225,000.00 114,162.00 225,000.00 228,000.00
1018 Sock clipsal 20 mm bj 2,000.00 5,054.40 2,000.00 3,000.00
1019 Steker bh 15,000.00 21,030.00 15,000.00 16,000.00
1020 Stop Kontak bh 26,000.00 53,148.00 26,000.00 27,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1021 Stop Kontak Khusus (Kedap Air) bh 35,000.00 77,070.00 35,000.00 44,000.00 40,000.00
1022 Travo max 50 watt bh 147,000.00 1,040,460.00 148,000.00 149,000.00 147,000.00
1023 Tee dos clipsal 20 mm bh 8,000.00 10,966.80 8,000.00 9,000.00 9,000.00
1024 Time Switch Bh 585,000.00 654,885.00 585,000.00 595,000.00 590,000.00
1025 T Foring Bh 11,000.00 69,900.00 12,000.00 15,000.00 11,000.00

MARMER / GRANIT
1026 Marmer (30 x 30) m2 375,000.00 429,528.00 375,000.00 380,000.00
1027 Marmer (40 x 40) m2 417,000.00 417,780.00
1028 Granit (30 x 30) Tekstur Kasar Tebal 3 cm m2 495,000.00 1,107,000.00 495,000.00 496,000.00
1029 Batu Andesit (30 x 30 x 5 cm) m2 460,000.00 535,524.00 461,000.00 460,000.00
1030 Roster Keramik (12 x 11 x 24) bh 55,000.00 65,617.20 55,000.00 58,000.00

GRANIT TILE
1031 Essenza 40 x 40 m2 395,000.00 437,398.80 395,000.00 396,000.00
1032 Essenza 60 x 60 m2 470,000.00 537,259.20 470,000.00 470,000.00
1033 Granito 40 x 40 cm m2 435,000.00 483,136.80 435,000.00 436,000.00
1034 Nero Granito 30 x 60 cm m2 385,000.00 424,318.80 385,000.00 386,000.00
1035 Nero Granito 40 x 40 cm m2 430,000.00 483,256.80 430,000.00 432,000.00
1036 Nero Granito 60 x 60 cm m2 435,000.00 482,127.36 435,000.00 436,000.00
1037 Setara Ex Cina 60 x 60 cm m2 220,000.00 506,160.00 220,000.00 221,000.00
1038 Setara Ex Cina 80 x 80 cm m2 235,000.00 377,040.00 235,000.00 236,000.00

KERAMIK
1039 Keramik Asia Tile 20 x 20 kelas I warna muda m2 68,000.00 102,399.00 68,000.00 68,000.00
1040 Keramik Setara Asia Tile 20 x 20 kelas I warna tua m2 68,000.00 106,216.80 69,000.00 68,000.00
1041 Keramik Setara Asia Tile 20 x 25 kelas I m2 70,000.00 107,586.00 71,000.00 70,000.00
1042 Keramik Setara Asia Tile 30 x 30 kelas I warna muda m2 55,000.00 100,524.00 55,000.00 56,000.00
1043 Keramik Setara Asia Tile 30 x 30 kelas I warna tua m2 62,000.00 82,183.20 62,000.00 62,000.00
1044 Keramik Setara Asia Tile 40 x 40 kelas I m2 70,000.00 103,890.00 70,000.00 71,000.00
1045 Keramik Setara Asia Tile 60 x 60 kelas I Setara Platinum m2 148,000.00 198,000.00 148,000.00 149,000.00
1046 Keramik Setara ARWANA ( warna putih) M2 58,000.00 94,260.00 58,000.00 59,000.00
1047 Keramik Setara ARWANA ( warna tua) M2 65,000.00 93,060.00 65,000.00 66,000.00
1048 Keramik Setara Diamond 10/20 cm (Warna Muda) M2 70,000.00 93,984.00 70,000.00 71,000.00
1049 Keramik Setara Diamond 20/20 cm (Kelas I Warna Muda) M2 75,000.00 88,506.00 75,000.00 78,000.00
1050 Keramik Setara Diamond 30/30 cm (Kelas I Warna Muda) M2 76,000.00 91,476.00 76,000.00 77,000.00
1051 Keramik Setara Diamond 10/20 cm (Warna tua) M2 80,000.00 118,650.00 80,000.00 81,000.00
1052 Keramik Setara Diamond 20/20 cm (Kelas I Warna Tua) M2 71,000.00 92,076.00 71,000.00 72,000.00
1053 Keramik Setara Diamond 30/30 cm (Kelas I Warna Tua) M2 70,000.00 91,476.00 70,000.00 72,000.00
1054 Keramik Setara Ikad (Keramik) Kw. I 10 x 20 cm (DK warna muda) M2 66,000.00 91,476.00 66,000.00 68,000.00
1055 Keramik Setara Ikad (Keramik) Kw. I 10 x 20 cm (DK warna tua) M2 68,000.00 117,150.00 68,000.00 69,000.00
1056 Keramik Setara Ikad (Keramik) Kw. I 20 x 20 cm (warna tua) m2 70,000.00 91,740.00 70,000.00 71,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1057 Keramik Setara Ikad (Keramik) Kw. I 20 x 20 cm (warna muda) m2 65,000.00 91,740.00 65,000.00 66,000.00
1058 Keramik Setara Ikad (Keramik) Kw. I 30 x 30 cm m2 68,000.00 96,162.00 68,000.00 70,000.00
1059 Keramik Setara Ikad (Keramik) Kw. I 40 x 40 cm m2 71,000.00 106,722.00 71,000.00 72,000.00
1060 Keramik Setara Ikad (Keramik) Kw. I 50 x 50 cm m2 75,000.00 124,806.00 75,000.00 77,000.00
1061 Keramik Setara KIA 20/20 cm warna muda m2 70,000.00 105,072.00 70,000.00 72,000.00
1062 Keramik Setara KIA 30/30 cm warna muda m2 75,000.00 109,560.00 75,000.00 76,000.00
1063 Keramik Setara KIA 20/20 cm warna tua m2 65,000.00 100,623.60 65,000.00 68,000.00
1064 Keramik Setara KIA 30/30 cm warna tua m2 68,000.00 113,520.00 68,000.00 69,000.00
1065 Keramik Setara Mulia Warna Putih m2 105,000.00 107,484.96
1066 Keramik Setara Mulia Warna Tua m2 65,000.00 69,300.00
1067 Keramik Setara Mulia 20 x 20 cm Warna Tua m2 58,000.00 71,280.00 58,000.00 60,000.00
1068 Keramik Setara Mulia 20 x 20 cm Warna Muda m2 60,000.00 71,656.20 60,000.00 62,000.00
1069 Keramik Setara Mulia 30 x 30 cm Warna Putih m2 62,000.00 68,640.00 62,000.00 63,000.00
1070 Keramik Setara Mulia 30 x 30 Warna Marbel m2 70,000.00 69,960.00 70,000.00 72,000.00
1071 Keramik Setara Mulia 30 x 30 Warna Impresso m2 75,000.00 78,936.00 75,000.00 78,000.00
1072 Keramik Setara Mulia 40 x 40 cm kelas I m2 78,000.00 87,120.00 78,000.00 78,500.00
1073 Keramik Setara ROMAN 20/20 cm m2 85,000.00 134,640.00 85,000.00 86,000.00
1074 Keramik Setara ROMAN 30/30 cm m2 88,000.00 155,760.00 88,000.00 88,000.00
1075 Tegel PC abu - abu 20/20 cm m2 95,000.00 122,100.00 95,000.00 96,500.00
1076 Tegel PC Warna 20/20 cm m2 95,000.00 122,100.00 95,000.00 96,500.00
1077 Tegel PC Warna 30/30 cm m2 95,000.00 122,100.00 95,000.00 96,500.00
1078 Tegel 30 x 30 TB PC m2 95,000.00 122,100.00 95,000.00 96,500.00
1079 Tegel 30 x 30 TB PC Kuning m2 96,000.00 122,100.00 96,000.00 96,500.00
1080 Tegel 30 x 30 Warna Merah m2 96,000.00 122,100.00 96,000.00 96,500.00
1081 Tegel Bata 20 x 20 Merah m2 96,000.00 122,100.00 96,000.00 96,500.00
1082 Tegel Bata 20 x 20 PC m2 96,000.00 122,100.00 96,000.00 96,500.00
1083 Tegel B/TB 20 x 20 Kuning m2 96,000.00 122,100.00 96,000.00 96,500.00
1084 Tegel Mozaik Porselint 30/30 cm m2 118,000.00 117,810.00 118,000.00 119,000.00
1085 Tegel Wafel 20/20 cm Warna m2 121,000.00 106,722.00 121,000.00 123,000.00
1086 Ubin PC Warna bh 90,000.00 9,702.00 90,000.00 93,000.00
1087 Ubin PC Warna 20 / 20 Cm m2 90,000.00 114,345.00 90,000.00 93,000.00
1088 Batu Lahar 30/30 bh 135,000.00 38,808.00 135,000.00 135,000.00
1089 Porselint 11/11 cm bh 90,000.00 69,300.00 90,000.00 92,000.00
1090 Porselen m2 98,000.00 98,000.00 99,000.00

ATAP
1091 Alang-alang panjang 2,4 meter lbr 28,500.00 28,800.00 28,500.00
1092 Alluminium foil M2 Double rol 356,000.00 412,920.00 356,000.00 359,000.00
1093 Akustik 60 cm x 120 cm lbr 76,000.00 83,160.00 76,000.00 77,000.00
1094 Asbes Bubungan lbr 58,000.00 68,514.00 58,000.00 59,000.00
1095 Asbes Gelombang 1,80 m x 0,80 m lbr 48,000.00 53,961.60 48,000.00 49,000.00
1096 Asbes Gelombang 1,80 m x 1,05 m lbr 52,000.00 66,600.00 52,000.00 53,000.00
1097 Asbes Gelombang 2,10 m x 1,05 m lbr 68,000.00 78,672.00 68,000.00 68,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1098 Asbes Gelombang 2,4 m x 1,05 m lbr 81,000.00 92,136.00 81,000.00
1099 Asbes Rata 2 m x 1 m x 4 mm lbr 76,000.00 88,200.00 76,000.00
1100 Bentala tanah liat Ex Pejaten bh 82,000.00 129,726.00 82,000.00
1101 Bentala Ex Kapal 83,000.00 114,780.00 83,000.00
1102 Bentala Besar polos Lubang 24 cm bh 97,000.00 116,985.00 97,000.00
1103 Bentala Besar Warna Lubang 25 cm bh 133,000.00 155,040.00 133,000.00
1104 Bentala Besar polos Lubang 90 cm bh 202,000.00 231,600.00 202,000.00
1105 Bentala Besar Warna Lubang 90 cm bh 203,000.00 233,640.00 203,000.00
1106 Bubungan Besar bh 8,500.00 27,084.00 8,500.00
1107 Bubungan Kecil bh 7,000.00 21,060.00 7,000.00
1108 Bubungan Bambe Kecil bh 12,000.00 27,280.80 12,000.00
1109 Bubungan Bulat Karang Pilang bh 29,000.00 35,250.00 29,000.00
1110 Bubungan Bulat Jati Wangi bh 21,000.00 26,184.00 21,000.00
1111 Bubungan Bulat Ngalayur isi 3,5/m bh 18,000.00 25,020.00 18,000.00
1112 Bubungan Besar Good Year bh 28,000.00 34,920.00 28,000.00
1113 Bubungan Beton Cisangkan bh 21,000.00 38,880.00 21,000.00
1114 Bubungan Gerard lbr 18,000.00 97,200.00 18,000.00
1115 Bubungan Karang Pilang isi 3,5/m bh 28,000.00 38,808.00 28,000.00
1116 Bubungan Pletong Jatiwangi bh 33,000.00 23,469.60 33,000.00
1117 Bubungan SL Utama bh 18,000.00 24,360.00 18,000.00
1118 Bubungan SL Ngalayur bh 17,500.00 17,760.00 20,000.00
1119 Bubungan Segi Tiga Karang Pilang bh 27,000.00 29,640.00 27,000.00
1120 Bubungan Utama isi 3,5/m bh 11,500.00 23,700.00 11,500.00
1121 Genteng Bambe bh 7,000.00 11,760.00 7,000.00
1122 Genteng Bambe Karang Pilang bh 8,000.00 11,760.00 8,000.00
1123 Genteng Bambe Kecil bh 6,000.00 9,840.00 6,000.00
1124 Genteng Beton Cisangkan bh 12,000.00 22,620.00 12,000.00
1125 Genteng Gemini bh 6,800.00 11,760.00 6,800.00
1126 Genteng Gerard Polos m2 350,000.00 363,720.00
1127 Genteng Good Year m2 8,500.00 9,840.00 8,500.00
1128 Genteng Kanmuri (glazur) isi 14/m2 bh 4,100.00 19,800.00 4,100.00
1129 Genteng Kodok Lokal bh 6,000.00 50,640.00 6,000.00
1130 Genteng Kodok Kamulan bh 5,100.00 7,320.00 5,100.00
1131 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bh 6,000.00 8,520.00 6,000.00
1132 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bh 7,000.00 9,180.00 7,000.00
1133 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bh 7,000.00 9,960.00 7,000.00
1134 Genteng Kodok Karang Pilang (Surabaya) bh 6,500.00 6,120.00 6,500.00
1135 Genteng Kodok Soka bh 4,000.00 7,320.00 4,000.00
1136 Genteng Lestari bh 3,900.00 66,000.00 3,900.00
1137 Genteng Metal 59,000.00 60,000.00
1138 Genteng Metal 80 x 77,6 (Polos) lbr 53,000.00 92,400.00 53,000.00
1139 Genteng Metal 80 x 77,6 (Pasir) lbr 78,000.00 87,060.00 78,000.00
1140 Genteng Morando Abadi isi 18/m2 bh 10,800.00 10,800.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1141 Genteng Morando Jatiwangi isi 18/m2 bh 6,500.00 12,942.00 6,500.00
1142 Genteng Morando Ngalayur isi 20/m2 bh 5,100.00 7,500.00 5,100.00
1143 Genteng Morando Metal bh 75,000.00 92,400.00 75,000.00
1144 Genteng Pejaten Mini bh 3,900.00 5,280.00 3,900.00
1145 Genteng Plentong bh 3,100.00 5,880.00 3,100.00
1146 Genteng plentong dicat bh 4,000.00 6,120.00 4,000.00
1147 Genteng Plentong Mantili bh 2,800.00 6,240.00 2,800.00
1148 Genteng Plentong Pejaten / Darmasaba bh 3,000.00 7,440.00 3,000.00
1149 Genteng Plentong Jatiwangi / Surabaya bh 3,500.00 9,240.00 3,500.00
1150 Genteng Portugis bh 2,800.00 13,800.00 2,800.00
1151 Genteng Pres Besar bh 3,500.00 5,640.00 3,500.00
1152 Genteng Pres Besar Cat bh 4,000.00 5,880.00 4,000.00
1153 Genteng Pres Mini bh 2,900.00 3,600.00 2,900.00
1154 Genteng Pres Mini Cat bh 3,000.00 5,880.00 3,000.00
1155 Genteng Terreal bh 15,000.00 16,200.00
1156 Genteng T. Romana bh 15,000.00 16,200.00
1157 Genteng Besar polos Lubang 35 cm bh 3,500.00 6,120.00 3,500.00
1158 Genteng Besar Warna Lubang 35 cm bh 3,800.00 6,120.00 3,800.00
1159 Fiberglas (1.80 x 0.80) M2 lbr 60,000.00 66,000.00 60,000.00
1160 Ijuk kg 4,500.00 6,120.00 4,500.00
1161 Ijuk Bersih bh 17,000.00 19,200.00
1162 Ijuk Lampung bh 15,000.00 16,440.00
1163 Ikut Celedu bh 290,000.00 290,400.00
1164 Ikut Celedu Besar Polos bh 109,000.00 125,400.00 109,000.00
1165 Ikut Celedu Besar Warna bh 120,000.00 138,600.00 120,000.00
1166 Ikut Celedu Kecil Polos bh 92,500.00 93,060.00 187,000.00
1167 Ikut Celedu Kecil Warna bh 125,000.00 125,400.00 189,000.00
1168 Kawat las kg 80,500.00 112,200.00 80,500.00
1169 Kawat Diameter 4 mm kg 35,000.00 125,400.00 35,000.00
1170 Murda / Puntal Paras bh 165,000.00 316,800.00 165,000.00
1171 Murda tanah liat Ex Pejaten bh 145,000.00 171,600.00 145,000.00
1172 Murda Kecil Polos Lubang 25 cm bh 108,000.00 122,760.00 108,000.00
1173 Murda Kecil Warna Lubang 25 cm bh 128,000.00 145,200.00 128,000.00
1174 Profil Aluminium "T" m3 255,000.00 316,800.00 255,000.00
1175 Seng BJLS 0,18 gelombang lbr 125,000.00 145,200.00 125,000.00
1176 Seng BJLS 0,22 gelombang lbr 135,000.00 151,800.00 135,000.00
1177 Seng BJLS 0,30 gelombang lbr 140,000.00 167,640.00 140,000.00
1178 Seng Zincalume Panjang 6m Tebal 0,5 mm lbr 118,000.00 132,000.00 118,000.00
1179 Seng Plat Lebar 0,90 M lbr 61,000.00 73,920.00 61,000.00
1180 Seng Plat 3" x 6" BJLS 28 lbr 87,000.00 99,000.00 87,000.00
1181 Seng Plat Aluminium lbr 65,000.00 76,560.00 65,000.00
1182 Sirap lbr 10,000.00 12,120.00 10,000.00
1183 Subeng Besar Polos lbr 15,600.00 17,160.00 15,600.00
1184 Subeng Besar Warna lbr 8,500.00 8,976.00 8,500.00
1185 Subeng Kecil Polos lbr 8,500.00 10,560.00 8,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1186 Subeng Kecil Warna bh 5,500.00 5,793.48 8,500.00

TALI
1187 Tali Ijuk kg 11,000.00 11,160.00 11,500.00
1188 Tali pengikat ikat 25,500.00 25,832.40 30,000.00
1189 Tali pengikat alang-alang ikat 34,000.00 34,320.00 35,000.00
1190 Tali Rafia Gulung 6,500.00 6,870.00 25,500.00

SANITAIR
1191 Bak mandi fibre glass 70x70x66 cm bh 370,000.00 488,400.00 370,000.00
1192 Bak mandi porselin/ keramik bh 365,000.00 509,454.00 365,000.00
1193 Bak mandi keramik 50x50 bh 209,000.00 394,482.00 209,000.00
1194 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh 218,000.00 657,720.00 218,000.00
1195 Floor Drain Plastic bh 27,000.00 27,600.00
1196 Floor Drain Stainless bh 90,000.00 92,301.00
1197 Floor drain plastik Setara Alianco bh 30,000.00 40,359.00 30,000.00
1198 Floor drain stainless Setara Wasser bh 185,000.00 257,400.00 185,000.00
1199 Dudukan Kloset dan Perlengkapannya bh 2,800,000.00 2,917,860.00
1200 Kloset duduk INA Komplit bh 1,100,000.00 2,445,564.00 1,100,000.00
1201 closet duduk INA (putih) STD bh 975,000.00 1,684,260.00 975,000.00
1202 closet duduk INA (warna) bh 995,000.00 2,100,000.00 995,000.00
1203 Kloset duduk Amerika Standar Winplus bh 1,875,000.00 3,814,800.00 1,875,000.00
1204 closet duduk TOTO (putih) STD bh 1,945,000.00 1,815,600.00 1,945,000.00
1205 closet duduk TOTO (warna) bh 2,000,000.00 2,376,660.00 2,000,000.00
1206 Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW 821JP COMPLIT bh 6,550,000.00 2,707,188.00 6,550,000.00
1207 Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP COMPLIT bh 6,700,000.00 8,955,018.60 6,700,000.00
1208 Kloset duduk " TOTO Type AVANTE CW 823 J bh 10,500,000.00 12,210,000.00 10,500,000.00
1209 Kloset duduk " TOTO Type CW 660J bh 1,850,000.00 1,151,317.20 1,850,000.00
1210 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh 1,950,000.00 2,839,716.00 1,950,000.00
1211 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh 2,250,000.00 3,630,000.00 2,250,000.00
1212Kloset duduk " TOTO Type CW 660J WARNA COMPLIT bh 2,350,000.00 1,287,706.20 2,350,000.00
1213 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh 3,100,000.00 4,695,768.00 3,100,000.00
1214 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh 3,950,000.00 6,006,396.00 3,950,000.00
1215 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh 4,500,000.00 5,431,800.00 4,500,000.00
1216 Kloset jongkok " TOTO Type CE 6 COMPLIT bh 565,000.00 667,557.00 565,000.00
1217 Kloset jongkok " TOTO Type CE 7 COMPLIT bh 575,000.00 498,138.96 575,000.00
1218 closet jongkok porselin/ keramik bh 215,000.00 473,626.56 215,000.00
1219 Kloset porselin jongkok TOTO (standar) bh 315,000.00 632,148.00 315,000.00
1220 Kloset porselin jongkok Ina (standar) bh 118,000.00 391,281.00 118,000.00
1221 Kran biasa Setara Onda bh 25,000.00 76,230.00 25,000.00
1222 Kran SunEi PI/3 JHR bh 215,000.00 126,720.00 215,000.00
1223 Kran TOTO T 205 LCSC bh 275,000.00 353,040.00 275,000.00
1224 Kran TOTO T 205 MC bh 385,000.00 514,800.00 385,000.00
1225 Kran TOTO T 23 B13 bh 395,000.00 389,400.00 395,000.00
1226 Kran TOTO T 23 B13V7NB bh 375,000.00 393,600.00 375,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1227 Kran TOTO T 26 - 13 bh 395,000.00 525,360.00 395,000.00
1228 Kran TOTO TX 109 LH bh 985,000.00 1,173,600.00 985,000.00
1229 Penyekat Urinoir " TOTO " Type A 100 " bh 1,425,000.00 2,079,330.00 1,425,000.00
1230 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh 375,000.00 737,160.00 375,000.00
1231 Soap holder " TOTO " Type S 6 N " bh 165,000.00 208,560.00 165,000.00
1232 Seal tape bh 5,000.00 8,218.80 5,000.00
1233 Urinoir TOTO (STD) bh 3,100,000.00 3,818,100.00 3,100,000.00
1234 Urinoir " TOTO U 57 M bh 1,615,000.00 4,116,720.96 1,615,000.00
1235 Urinoir " TOTO U 57 M BODI bh 495,000.00 2,079,620.40 495,000.00
1236 Urinoir INA (STD) bh 610,000.00 3,796,980.00 610,000.00
1237 Wastagel KIA Standard bh 850,000.00 548,400.00 850,000.00
1238 Wastagel KIA Warna bh 510,000.00 549,960.00 510,000.00
1239 Wastafel TOTO (putih) bh 535,000.00 96,924.00 535,000.00
1240 Wastafel TOTO (warna) bh 475,000.00 1,816,056.00 475,000.00
1241 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh 1,600,000.00 2,146,440.00 1,600,000.00
1242 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh 1,750,000.00 1,305,117.00 1,750,000.00
1243 Wastafel INA (putih) bh 250,000.00 1,265,220.00 250,000.00
1244 Wastafel INA (warna) bh 275,000.00 1,265,220.00 275,000.00

KUNCI DAN PENGGANTUNG


1245 Engsel H ( 80 x 50) Ps 35,000.00 37,620.00 35,000.00
1246 Engsel kupu-kupu Rafes 4' 304 ps 70,000.00 93,390.00 70,000.00
1247 Engsel pintu Setara ECOLING Ps 52,000.00 102,966.60 52,000.00
1248 Engsel jendela Setara ECOLING Ps 45,000.00 67,156.32 45,000.00
1249 Engsel jendela Setara CAMEL Ps 60,000.00 64,620.00 60,000.00
1250 Espagnoleth Setara Rafes 60 cm Ps 75,000.00 92,340.00 75,000.00
1251 Grendel Setara ESBELA Bh 160,000.00 208,236.60 160,000.00
1252 Grendel tanam Setara CAMEL Bh 175,000.00 317,226.00 175,000.00
1253 Kait angin biasa Setara CAMEL Bh 35,000.00 78,150.00 35,000.00
1254 Kait angin diameter 10 mm Bh 40,000.00 40,000.00
1255 Kait angin lipat Setara ESBELA Bh 70,000.00 122,605.56 70,000.00
1256 Kait angin tarik Setara ESBELA Bh 55,000.00 87,219.00 55,000.00
1257 Kunci kuda 2 x putar Bh 95,000.00 95,000.00
1258 Kunci lif 1 x putar Setara BELLEZA Bh 225,000.00 287,760.00 225,000.00
1259 Kunci lif 2 x putar Bh 135,000.00 243,414.60 135,000.00
1260 Kunci pintu TOP Setara ESBELA bh 85,000.00 497,940.00 85,000.00
1261 Kunci pintu Vanesa Setara CAMEL bh 215,000.00 588,000.00 215,000.00
1262 Kunci pintu Setara ESBELLA bh 265,000.00 429,000.00 265,000.00
1263 Kunci Pintu 2 x putar Setara SES Bh 395,000.00 641,400.00 395,000.00
1264 Kunci pintu Setara DELWIN) bh 295,000.00 300,900.00 295,000.00
1265 Kunci shang hae 2 x putar Bh 298,000.00 271,200.00 298,000.00
1266 Kunci slot / Grendel Pintu Setara DELLWYN bh 310,000.00 407,580.00 310,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1267 Kunci tanam 2 slag Setara Dexon bh 245,000.00 406,791.00 245,000.00
1268 Kunci silinder bh 95,000.00 95,000.00
1269 Door holder bh 80,000.00 80,000.00
1270 Rel pintu sorong m' 415,000.00 415,000.00
1271 Rolling door plaat M2 495,000.00 617,760.00 495,000.00
1272 Rolling Door Aluminium M2 375,000.00 928,230.00 595,000.00
1273 Besi Tangga D 19, Enamel Cat bh 53,000.00 54,000.00
1274 Handle Besi Ø 12, Enamel Cat bh 29,000.00 30,000.00

PAKU
1273 Paku Beton Kg 58,000.00 47,835.60 58,000.00
1274 Paku Usuk Kg 15,000.00 23,700.00 15,000.00
1275 Paku Reng Kg 15,000.00 20,790.00 15,000.00
1276 Paku List Kg 22,000.00 31,680.00 22,000.00
1277 Paku Seng Ulir bh 2,500.00 2,100.00 2,500.00
1278 Paku 2-4 cm kg 18,000.00 29,640.00 18,000.00
1279 Paku Pancing 60 x 230 Kg 25,000.00 409,200.00 25,000.00
1280 Paku 5-12 cm kg 18,000.00 32,280.00 18,000.00
1281 Paku 2 cm (30 kg) 3/4 inch SQ dus 450,000.00 666,738.60 450,000.00
1282 Paku 2,5 cm (30 kg) 1 inch SQ dus 455,000.00 707,520.00 455,000.00
1283 Paku 3 cm (30 kg) 1 1/4 inch SQ dus 460,000.00 711,480.00 460,000.00
1284 Paku 4 cm (30 kg) 1 1/2 inch SQ dus 475,000.00 711,480.00 475,000.00
1285 Paku 5 cm (30 kg) 2 inch SQ dus 485,000.00 711,480.00 485,000.00
1286 Paku 7,10,12 cm (3,4,5) inch SQ dus 486,000.00 640,800.00 486,000.00
1287 Paku 5 -12 cm (27kg) 2,3,4,5 inch dus 486,000.00 640,200.00 486,000.00
1288 Paku skrup 1/2" Kg 48,000.00 33,660.00 48,000.00
1289 Paku skrup 2" Kg 49,000.00 38,940.00 49,000.00
1290 Paku skrup 3.5" Kg 45,000.00 46,200.00 45,000.00
1291 Bendrat 20 kg rol 302,000.00 594,000.00 302,000.00
1292 Sekrup Kalisiboard buah 550.00 1,320.00 550.00

BETON CETAK
1293 Paving Arahan 30 x 30 tebal 6 cm (K225) m2 115,000.00 207,900.00 115,000.00 120,000.00
1294 Paving Arahan 20 x 20 tebal 6 cm (K225) m2 90,000.00 207,900.00 90,000.00 115,000.00
1295 Paving 10 x 20 cm tebal 6 cm K225 (Polos) m2 85,000.00 138,600.00 85,000.00 98,000.00
1296 Paving 10 x 20 cm tebal 6 cm K225 (Warna) m2 70,000.00 217,800.00 95,000.00 106,000.00 70,000.00
1297 Paving 20 x 20 cm tebal 6 cm K225 (Polos) m2 90,000.00 138,600.00 98,000.00 96,000.00 90,000.00
1298 Paving 20 x 20 cm tebal 6 cm K225 (Warna) m2 100,000.00 217,800.00 100,000.00 130,000.00
1299 Paving 10 x 20 cm tebal 6 cm K350 (Polos) m2 109,000.00 153,120.00 110,000.00 109,000.00
1300 Paving 10 x 20 cm tebal 6 cm K350 (Warna) m2 115,000.00 232,320.00 115,000.00 140,000.00
1301 Paving 20 x 20 cm tebal 6 cm K350 (Polos) m2 125,000.00 233,640.00 125,000.00 150,000.00
1302 Paving 20 x 20 cm tebal 6 cm K350 (Warna) m2 135,000.00 236,280.00 135,000.00 149,000.00
1303 Paving 10 x 20 cm tebal 8 cm K225 (Polos) m2 80,000.00 137,280.00 145,000.00 99,000.00 80,000.00
1304 Paving 10 x 20 cm tebal 8 cm K225 (Warna) m2 105,000.00 236,280.00 150,000.00 156,000.00 105,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1305 Paving 20 x 20 cm tebal 8 cm K225 (Polos) m2 102,000.00 137,280.00 158,000.00 102,000.00
1306 Paving 20 x 20 cm tebal 8 cm K225 (Warna) m2 120,000.00 236,280.00 160,000.00 165,500.00 120,000.00
1307 Paving 10 x 20 cm tebal 8 cm K350 (Polos) m2 119,000.00 174,240.00 120,000.00 119,000.00
1308 Paving 10 x 20 cm tebal 8 cm K350 (Warna) m2 145,000.00 251,460.00 145,000.00 185,000.00
1309 Paving 20 x 20 cm tebal 8 cm K350 (Polos) m2 135,000.00 195,360.00 135,000.00 138,000.00
1310 Paving 20 x 20 cm tebal 8 cm K350 (Warna) m2 145,000.00 251,460.00 145,000.00 178,000.00
1311 Paving 20 x 20 cm tebal 8 cm K400 (Polos) m2 146,000.00 208,560.00 185,000.00 146,000.00
1312 Paving 20 x 20 cm tebal 8 cm K400 (Warna) m2 186,000.00 262,020.00 195,000.00 186,000.00
1313 Paving Tiga Berlian tebal 6 Cm K225 (Polos) m2 85,000.00 130,020.00 85,000.00 96,000.00
1314 Paving Tiga Berlian tebal 6 cm K225 (Warna) m2 95,000.00 208,560.00 95,000.00 146,000.00
1315 Paving segi enam xexagon 6 cm K225 pc m2 96,800.00 108,000.00 96,800.00
1316 Paving segi enam xexagon 6 cm K225 merah m2 105,000.00 118,000.00 105,000.00
1317 Paving segi enam xexagon 6 cm K225 hitam m2 119,000.00 120,000.00 119,000.00
1318 Paving segi enam xexagon 6 cm K300 pc m2 110,000.00 110,000.00 126,000.00
1319 Paving segi enam xexagon 6 cm K300 merah m2 105,000.00 105,000.00 136,000.00
1320 Paving segi enam xexagon 6 cm K300 hitam m2 146,000.00 175,000.00 146,000.00
1321 Paving segi enam xexagon 6 cm K350 pc m2 156,000.00 165,000.00 156,000.00
1322 Paving segi enam xexagon 6 cm K350 merah m2 158,000.00 175,000.00 158,000.00
1323 Paving segi enam xexagon 6 cm K350 hitam m2 160,000.00 185,000.00 160,000.00
1324 Paving segi enam xexagon 6 cm K400 pc m2 178,000.00 188,000.00 178,000.00
1325 Paving segi enam xexagon 6 cm K400 merah m2 165,000.00 165,000.00 185,000.00
1326 Paving segi enam xexagon 6 cm K400 hitam m2 160,000.00 160,000.00 196,000.00
1327 Paving bujur sangkar tanpa tias 6 cm K225 pc m2 160,000.00 160,000.00 175,000.00
1328 Paving bujur sangkar tanpa tias 6 cm K225 merah m2 175,000.00 175,000.00 196,000.00
1329 Paving bujur sangkar tanpa tias 6 cm K225 hitam m2 185,000.00 185,000.00 206,000.00
1330 Paving bujur sangkar tanpa tias 8 cm K225 pc m2 205,000.00 205,000.00 211,000.00
1331 Paving bujur sangkar tanpa tias 8 cm K225 merah m2 210,000.00 210,000.00 218,000.00
1332 Paving bujur sangkar tanpa tias 8 cm K225 hitam m2 215,000.00 215,000.00 220,000.00
1333 Box Culvert Type 600x600x1200 K 350 Bh 1,800,000.00 3,893,911.20 1,800,000.00
1334 Box Culvert Type 800x800x1200 K 350 Bh 2,430,000.00 4,853,199.60 2,430,000.00
1335 Box Culvert Type 1000x1000X1200 K 350 Bh 3,540,000.00 5,981,168.16 3,540,000.00
1336 Box Culvert Type 1200x1200X1200 K 350 Bh 4,764,000.00 6,231,456.00 4,764,000.00
1337 Box Culvert Type 1500x1500x1200 K 350 Bh 7,650,000.00 13,796,640.00 7,650,000.00
1338 Box Culvert Type 2000x2000x1200 K 350 Bh 11,325,000.00 19,863,690.00 11,325,000.00
1339 Box Culvert Type 3000x2000x1200 K 350 Bh 18,540,000.00 20,346,480.00 18,540,000.00
1340 Box Culvert Type 3000x2500x1200 K 350 Bh 21,400,000.00 22,075,515.00 21,400,000.00
1341 Box Culvert Type 3000x3000x1200 K 350 Bh 23,500,000.00 23,867,613.00 25,100,000.00
1342 Saluran Berbentuk U Type 300x300x1200 K350 Bh 412,300.00 557,040.00 412,300.00
1343 Saluran Berbentuk U Type 300x400x1200 K350 Bh 435,000.00 663,300.00 435,000.00
1344 Saluran Berbentuk U Type 300x500x1200 K350 Bh 475,000.00 769,560.00 475,000.00
1345 Saluran Berbentuk U Type 400x400x1200 K350 Bh 447,000.00 771,540.00 447,000.00
1346 Saluran Berbentuk U Type 400x600x1200 K350 Bh 679,400.00 1,076,460.00 679,400.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1347 Saluran Berbentuk U Type 400x700x1200 K350 Bh 698,200.00 1,584,000.00 750,000.00 800,000.00 698,200.00
1348 Saluran Berbentuk U Type 500x500x1200 K350 Bh 565,400.00 1,584,000.00 800,000.00 850,000.00 565,400.00
1349 Saluran Berbentuk U Type 500x600x1200 K350 Bh 699,000.00 1,704,000.00 850,000.00 875,000.00 699,000.00
1350 Saluran Berbentuk U Type 500x700x1200 K350 Bh 844,000.00 1,848,000.00 895,000.00 898,000.00 844,000.00
1351 Saluran Berbentuk U Type 600x600x1200 K350 Bh 762,300.00 1,833,523.20 905,000.00 910,000.00 762,300.00
1352 Saluran Berbentuk U Type 600x700x1200 K350 Bh 879,200.00 1,519,749.00 975,000.00 985,000.00 879,200.00
1353 Saluran Berbentuk U Type 700x700x1200 K350 Bh 937,100.00 2,288,230.56 1,100,000.00 1,115,000.00 937,100.00
1354 Saluran Berbentuk U Type 600x800x1200 K350 Bh 897,300.00 1,618,320.00 1,125,000.00 1,200,000.00 897,300.00
1355 Saluran Berbentuk U Type 800x800x1200 K350 Bh 1,230,000.00 2,629,572.00 1,315,000.00 1,350,000.00 1,230,000.00
1356 Saluran Berbentuk U Type 800x1000x1200 K350 Bh 1,540,000.00 2,428,964.40 1,895,000.00 1,900,000.00 1,540,000.00
1357 Saluran Berbentuk U Type 1000x1000x1200 K350 Bh 1,930,000.00 2,550,240.00 2,250,000.00 2,300,000.00 1,930,000.00
1358 Bentala Exs Kapal (Paras) bh 25,000.00 94,248.00 25,000.00 30,000.00
1359 Bentala Exs Kapal (Terakota) bh 30,000.00 94,248.00 30,000.00 35,000.00
1360 Kanstein Segi Lima P40 bh 51,500.00 51,600.00 55,000.00
1361 Kanstein Segi Lima P50 bh 60,000.00 61,380.00 60,000.00
1362 Kanstein 40x28x15/12 cm bh 65,000.00 109,800.00 65,000.00
1363 Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225) m' 98,000.00 98,000.00
1364 Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225) bh 49,000.00
1365 Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225) m' 88,000.00 88,000.00
1366 Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225) bh 44,000.00
1367 Kansteen K.250 Bh 45,000.00 83,160.00 45,000.00 70,000.00
1368 Kansteen Pendek K.250 Bh 34,500.00 34,650.00 50,000.00 75,000.00
1369 Kansteen Jalan Masuk K.250 Bh 80,000.00 90,090.00 80,000.00
1370 Kansteen Jalan Masuk 15x40x50 K.300 Bh 85,000.00 85,000.00
1371 Kansteen Segilima P.50, T.20, L.15 K.250 Bh 49,000.00 49,550.16 90,000.00
1372 Kansteen Bulat P.50, T.30, LA.10 LB.15 K.250 Bh 83,000.00 83,160.00 95,000.00
1373 Kanstein Jumbo (P:50,L:15,T:30 cm K225) m' 62,000.00 62,370.00 100,000.00 105,000.00
1374 Kansteen Jumbo P.50, T.30, L.15 K.250 Bh 115,000.00 130,284.00 125,000.00
1375 Kansteen Jumbo 15x30x50 K.300 Bh 55,000.00 120,582.00 45,000.00
1376 Kansteen Jumbo Mini 15x20x50 K.300 Bh 45,000.00 158,004.00 155,000.00
1377 Kansteen Persegi T 15, P50, L 20 K 225 Bh 76,000.00 76,230.00 112,000.00
1378 Kasnteen Kursi K225 120,000.00 126,819.00
1379 Kansteen Kursi T 15, L 40, P 50 K 225 160,000.00 166,320.00
1380 Kansteen Kursi T 10, L 40, P 50 K 225 130,000.00 131,670.00
1381 Kansteen Jumbo 15 x 30 x 50 K.300 m' 110,000.00 92,862.00
1382 Kansteen Jumbo Mini 15 x 20 x 50 K.300 m' 90,000.00 81,081.00
1383 Kansteen Kursi (Jalan Masuk) 15 x 40 x 60 K.300 110,000.00 113,652.00
1384 Kansteen kotak (P:50,t.20,La.10,Lb.16cm) K225 m' 100,000.00 100,000.00
1385 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 ) m' 105,000.00 105,000.00
1386 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 ) m' 95,000.00 95,000.00
1387 Tutup Got (Grill) (P:45, L:24, T:9 cm) Bh 67,000.00 83,160.00 67,000.00
1388 Tutup Got (Grill) (P:30, L:24, T:9 cm) Bh 67,000.00 83,160.00 645,000.00
1389 Plat Penutup 600 x 1200 Bh 541,000.00 789,327.00 541,000.00
1390 Plat Penutup 800 x 1200 Bh 675,000.00 1,096,326.00 675,000.00
1391 Plat Penutup 1000 x 1200 Bh 890,000.00 1,297,362.00 890,000.00
1392 Frame Manhole 600x600 Bh 543,200.00 706,200.00 543,200.00
1393 Frame Manhole 800x800 Bh 675,400.00 820,512.00 675,400.00
1394 Frame Manhole 1000x1000 Bh 763,200.00 1,015,938.00 763,200.00
1395 Cover manhole 600x600 Bh 534,500.00 1,161,468.00 534,500.00
1396 Cover manhole 800x800 Bh 675,400.00 1,431,045.00 1,100,000.00 675,400.00
1397 Cover manhole 1000x1000 Bh 763,200.00 1,663,200.00 763,200.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1398 Grass Block 36 X 54 cm tebal 9 cm K 225 m2 105,000.00 136,620.00 105,000.00 110,000.00
1399 Grass Block lobang 5, 30 X 30 cm tebal 7 cm K 225 m2 85,000.00 113,520.00 90,000.00 85,000.00
1400 Beton Cetak Greas Blok K.250 bh 20,500.00 20,790.00 78,000.00 75,000.00
1401 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 ) bh 47,500.00
1402 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 ) bh 52,500.00

PLAFOND & TIRPLEK


1401 Acustik 30/30 lbr 167,500.00 196,680.00 167,500.00 168,000.00
1402 Celling teak (0,62 x 2,40) m2 lbr 235,000.00 274,560.00 235,000.00 238,000.00
1403 Eternit lbr 30,000.00 34,320.00 30,000.00 32,000.00
1404 Playwood 3 mm Lbr 75,000.00 75,826.08 198,000.00 199,000.00
1405 Playwood 4 mm Setara Meranti Lbr 180,000.00 180,840.00 225,000.00 235,000.00
1406 Plywood 5 mm lbr 189,000.00 232,320.00 189,000.00 190,000.00
1407 Playwood 9 mm Setara Meranti lbr 210,000.00 258,720.00 210,000.00 215,000.00
1408 Playwood aluminium lbr 155,000.00 192,720.00 155,000.00 158,000.00
1409 Gypsum Board (120x240x9) lbr 68,000.00 1,155,000.00 68,000.00 70,000.00
1410 Kalsiboard (4,5 x 1220 x 2420) mm lbr 78,500.00 156,728.88 78,500.00 80,000.00
1411 Tea Block 18 mm 300,000.00 327,360.00
1412 Hard board MDF lbr 305,000.00 196,673.40 310,000.00 305,000.00
1413 Multiplek 6 mm lbr 195,800.00 246,840.00 195,800.00 196,000.00
1414 Multiplek 9mm lbr 243,000.00 311,520.00 243,000.00 244,000.00
1415 Multiplek 12 mm lbr 280,000.00 280,000.00 295,000.00
1416 Triplek tebal 3mm (2,7mm) kayu sengon lbr 48,500.00 78,600.00 48,500.00 49,000.00
1417 Triplek tebal 3mm (2,7mm) kayu semi meranti lbr 57,800.00 89,760.00 57,800.00 58,000.00
1418 Triplek tebal 4mm (3,6mm) kayu sengon lbr 60,000.00 76,890.00 60,500.00 60,000.00
1419 Triplek tebal 4mm (3,6mm) kayu semi meranti lbr 71,000.00 90,420.00 71,500.00 71,000.00
1420 Triplek tebal 6mm (5,2mm) kayu sengon I lbr 71,000.00 99,000.00 71,500.00 71,000.00
1421 Triplek tebal 6mm (5,2mm) kayu sengon II lbr 64,400.00 91,740.00 64,400.00 65,000.00
1422 Triplek tebal 6mm (5,2mm) kayu semi meranti lbr 87,800.00 107,679.00 87,800.00 88,000.00
1423 Triplek tebal 6mm (5,2mm) kayu semi meranti II lbr 79,000.00 103,620.00 80,800.00 79,000.00
1424 Triplek tebal 8,0mm kayu sengon I lbr 101,750.00 141,966.00 101,750.00 102,000.00
1425 Triplek tebal 8,0mm kayu sengon II lbr 97,400.00 126,390.00 97,400.00 98,000.00
1426 Triplek tebal 8,0mm kayu semi meranti lbr 122,500.00 157,080.00 122,500.00 123,000.00
1427 Triplek tebal 9,0mm kayu semi meranti II lbr 112,500.00 261,360.00 112,500.00 113,000.00
1428 Triplek tebal 12 mm kayu sengon I lbr 148,500.00 192,720.00 148,500.00 148,500.00
1429 Triplek tebal 12 mm kayu semi meranti lbr 210,800.00 236,280.00 210,800.00 211,000.00
1430 Triplek tebal 15 mm kayu semi meranti lbr 250,000.00 292,380.00 250,000.00 255,000.00
1431 Triplek tebal 18 mm kayu semi meranti lbr 211,000.00 324,192.00 211,500.00 211,000.00
1432 Teakwood 122 x 244 x 2,7 mm lbr 89,100.00 121,506.00 89,100.00 89,100.00
1433 Melamine Putih/Biru 2,7 lbr 102,900.00 125,400.00 102,900.00 103,000.00
1434 Triplek aluminium jruk asli lbr 120,500.00 151,800.00 120,500.00 122,000.00
1435 Triplek aluminium jruk standar lbr 98,500.00 134,640.00 98,500.00 99,000.00
1436 Block board 18 mm sengon lbr 200,200.00 250,668.00 200,200.00 205,000.00
1437 Block board 18 mm meranti super lbr 232,000.00 288,360.00 232,000.00 232,000.00
1438 Teak block 18mm lbr 257,900.00 305,520.00 257,900.00 258,000.00
1439 Rangka Aluminium m1 38,500.00 38,760.00 38,500.00 40,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1440 Rangka Metal Furing (2 x 4 cm) panjang 4 m btg 55,200.00 67,800.00 55,200.00 56,000.00
1441 Rangka Metal Furing (4 x 4 cm) panjang 4 m btg 57,000.00 83,160.00 67,850.00 57,000.00
1442 Teak wood (1,20x2,40x 0,4) lbr 88,900.00 118,020.00 89,000.00 88,900.00
1443 Teak wood (0,90x2,00 x 0,4) lbr 145,800.00 198,000.00 145,800.00 146,000.00
1444 Jabar Wood 4 mm lbr 146,500.00 146,916.00 175,000.00 178,000.00

BUIS BETON
1445 Buis beton Diameter 25 x 75 bh 89,600.00 105,072.00 89,600.00 90,000.00
1446 Buis beton Diameter 30 x 75 bh 113,900.00 130,812.00 113,900.00 115,000.00
1447 Buis beton Diameter 50 x 75 bh 201,000.00 245,520.00 201,000.00 205,000.00
1448 Buis Beton diameter 80 cm bh 156,500.00 156,710.40 225,000.00 250,000.00
1449 Buis Beton diameter 25 cm bh 85,000.00 76,461.00 85,000.00 90,000.00
1450 Buis Beton diameter 50 cm bh 95,000.00 69,762.00 95,000.00 100,000.00
1451 Buis Beton diameter 100 cm bh 250,000.00

BETON READY MIX


1452 Beton Ready Mix K-175 TM Kap 7 m3 m3 850,000.00 1,379,400.00 850,000.00 880,000.00
1453 Beton Ready Mix K-225 TM Kap 7 m3 m3 905,000.00 1,800,480.00 905,000.00 946,000.00
1454 Beton Ready Mix K-250 TM Kap 7 m3 m3 930,000.00 1,947,000.00 930,000.00 979,000.00
1455 Beton Ready Mix K-275 TM Kap 7 m3 m3 945,000.00 1,999,800.00 945,000.00 1,012,000.00
1456 Beton Ready Mix K-300 TM Kap 7 m3 m3 965,000.00 2,047,320.00 965,000.00 1,045,000.00
1457 Beton Ready Mix K-350 TM Kap 7 m3 m3 1,025,000.00 2,151,600.00 1,025,000.00 1,111,000.00
1458 Sewa Concrete pump/M3 ls 35,000.00 46,200.00 35,000.00 35,000.00
1459 Formite/penjaga jarak bekisting/spacer bh 3,000.00 3,900.00 3,000.00 32,000.00

TALANG
1460 Talang Karet L = 0.50 m' 20,000.00 137,214.00 20,000.00 21,600.00 22,000.00
1461 Talang Karet L = 0.90 m' 29,000.00 175,329.00 29,000.00 30,500.00 31,000.00
1462 Pipa Talang PVC Setara Maspion 6" Setengah Lingkaran m' 110,000.00 130,680.00 110,000.00 112,700.00 115,000.00
1463 Pipa Talang PVC Setara Maspion 6" Kotak m' 200,000.00 153,120.00 200,000.00 201,500.00 205,000.00

ASPAL, BBM DAN PELUMAS


1464 Aspal Penetrasi 60/70 Kg 15,600.00 16,632.00
1465 Aspal Curah Kg 15,500.00 16,632.00
1466 Aspal RC Kg 12,000.00 13,860.00
1467 Aspal Emulsi ltr 18,000.00 19,681.20
1468 Aspal Emulsi CRS 1 ltr 13,000.00 14,275.80
1469 Aspal Emulsi CRS 1 Modif 14,500.00 15,107.40
1470 Aspal Emulsi CRS 2 ltr 15,500.00 16,147.56
1471 Aspal Emulsi CSS 1 h Modif ltr 13,000.00 14,414.40
1472 Aspal Emulsi CSS 1 h ltr 12,500.00 13,375.56
1473 Aspal Emulsi CSS 1 / PCE ltr 14,000.00 14,137.20
1474 Minyak Aspal ( fluck oil ) Ltr 8,500.00 9,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1475 Minyak Tanah Ltr 17,200.00 18,503.76
1476 Minyak Tanah Industri Ltr 14,500.00 15,840.00
1477 Solar Ltr 9,150.00 10,567.92
1478 Solar Industri Ltr 9,662.50 10,395.00
1479 Premium Ltr 10,000.00 11,484.00
1480 Premium (industri) Ltr 8,700.00 9,240.00
1481 Pelumas ( olie ) Ltr 35,000.00 39,293.76
1482 Kayu Api M3 425,000.00 533,610.00
1483 Gas elpiji Kg 470,000.00 528,000.00
1484 Minyak Begesting ( B 115 ) Ltr 40,000.00 42,504.00
1485 Aspal Cold Mix (Readymix) Kg 2,500.00 3,360.00

ALAT PEMADAM KEBAKARAN


1486 Instalasi pipa induk BS 3" Sch M' 254,000.00 282,051.00
1487 Intalasi pipa distribusi BS 2" Sch M' 187,000.00 190,575.00
1488 Seamesi conection Bh 2,600,000.00 2,744,280.00
1489 Box hidran dengan kelengkapannya Bh 3,700,000.00 3,811,500.00
1490 Selang pemadam 30 m Bh 4,500,000.00 4,878,720.00
1491 Pemadam api ringan 6 kg Bh 1,533,000.00 1,677,720.00

TANAMAN
1492 Pohon Lianglio / Salix Babylonica pohon 750,000.00 720,720.00 750,000.00
1493 Palem Ekor Tupai / Wodyetia Bifurcata pohon 75,000.00 2,148,300.00 350,000.00
1494 Pohon Hias pohon 56,000.00 57,600.00
1495 Pohon Jepun / Plumeria Rubra pohon 400,000.00 2,079,000.00
1496 Pohon Pudak / Pandanus Tectorius pohon 250,000.00 2,772,000.00 1,500,000.00
1497 Pohon Ketapag Kencana / Terminalia Molineti pohon 150,000.00 2,217,600.00 750,000.00
1498 Pohon Sente Batang Hitam / Alokasia 'black' pohon 60,000.00 97,020.00 75,000.00
1499 Pohon Dadap Merah / Erythrina Crista Galli pohon 300,000.00 1,940,400.00 750,000.00
1500 Pohon Jepun Pagoda / Plumeria 'pagoda' pohon 350,000.00 2,217,600.00 350,000.00
1501 Pohon Tabebuya / Chrysotricha sp pohon 500,000.00 1,801,800.00 500,000.00
1502 Rumput (Sekelas rumput mutiara) m2 21,000.00 21,600.00
1503 Semak Jempiring / Gardenia Jasminioides polybag 5,000.00 11,781.00 5,000.00
1504 Semak Spathyphilum / Spathyphylum sp polybag 7,500.00 12,474.00 15,000.00
1505 Semak Reulia Besar / Reulia Malacosperma Giant polybag 250,000.00 5,544.00 350,000.00
1506 Semak Anturium Bunga / Anthurium Andreanum polybag 10,000.00 55,440.00 45,000.00
1507 Semak Hemigrapis / Hemigrapis sp polybag 2,500.00 6,930.00 3,000.00
1508 Semak Puring / Codeaium variegatum polybag 5,000.00 12,474.00 5,000.00
1509 Semak Pakis Bulu / Nephrolepis biserrata polybag 7,500.00 18,018.00 7,500.00
1510 Tanaman rumput mutiara/jepang m2 25,000.00 33,000.00
1511 Tanaman perdu m2 33,000.00 33,600.00
1512 Lili Bangkok / Hymenocalis litoralis polybag 3,500.00 12,474.00 10,000.00
1513 Jempiring / Gardenia jasminioides polybag 10,000.00 9,702.00 15,000.00
1514 Kaki Laba-laba / Oxmosilum Liniare Yellow polybag 22,000.00 22,176.00 -
1515 Semak Bawang-bawangan / Ornithogalum umbrellatum polybag 3,000.00 6,514.20 3,500.00
1516 Semak Kebang Kertas Daun Kecil / Bogenvile small leave polybag 17,500.00 22,176.00 17,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1517 Semak Lily Paris / Hymenocallis Speciosa polybag 2,500.00 5,544.00 3,000.00
1518 Semak Daun Philodendron / Philodendron sp polybag 7,000.00 18,018.00 17,500.00
1519 Semak Bunga Yolanda / Yolanda white flower polybag 8,500.00 13,860.00 17,500.00
1520 Semak Karembusa Putih / Tebermontana carembusa 'white' polybag 7,000.00 20,790.00 10,000.00
1521 Semak Simbang Darah / Excoecaria Cochinechinensis polybag 7,000.00 11,088.00 10,000.00
1522 Semak Bromelia / Bromelia sp polybag 50,000.00 207,900.00 75,000.00
1523 Pupuk Kandang m3 15,000.00 224,532.00 15,000.00

LAIN - LAIN
1524 Air Bersih Ltr 100.00 252.00 100.00
1525 Bak Cuci Aluminium 2 Lubang Bh 495,000.00 640,200.00 495,000.00
1526 Belanja Foto Copy Lembar 420.00 420.00 500.00 420.00
1527 Cangkul Bh 98,000.00 129,360.00 98,000.00
1528 Cangkul Gigi Bh 165,000.00 221,067.00 165,000.00
1529 Ember Bh 13,000.00 36,590.40 13,000.00
1530 Ember Hitam Bh 17,000.00 18,000.00 17,000.00 17,500.00
1531 Gerinding bh 575,000.00 748,440.00 575,000.00
1532 Helm Proyek Bh 45,000.00 111,295.80 45,000.00
1533 Hammer 3 kg Bh 110,000.00 145,200.00 110,000.00
1534 Instalasi Tata Suara Titik 475,000.00 543,840.00 475,000.00
1535 Isi Bay Fresh Ruangan Buah 60,000.00 60,000.00 65,000.00 60,000.00
1536 Isi Staples No 30. Pack 70,000.00 72,600.00 72,000.00 70,000.00
1537 Isi Sabun Hand Soap Buah 21,400.00 21,600.00 21,400.00 21,500.00
1538 Isi Kapur Barus Kg 50,000.00 52,800.00 50,000.00 51,000.00
1539 Kapi Bh 18,000.00 25,680.00 18,000.00
1540 Keni 2" Bh 7,000.00 22,107.36 7,000.00
1541 Keranjang Sampah Bh 45,000.00 151,800.00 45,000.00
1542 Keset Bh 95,000.00 98,400.00 95,000.00 97,000.00
1543 Lap Kanebo Bh 80,000.00 90,000.00 80,000.00 85,000.00
1544 Lap Pel / Alat Pengepelan Buah 230,000.00 234,000.00 235,000.00 230,000.00
1545 Linggis bh 75,000.00 126,000.00 75,000.00
1546 Masker Bh 15,000.00 76,560.00 15,000.00
1547 Ompreng Besar (bak Adonan) Bh 375,000.00 706,200.00 375,000.00
1548 Panyong Bh 115,000.00 129,960.00 115,000.00
1549 Pembersih Ban Ltr 45,000.00 49,200.00 45,000.00
1550 Pembersih Lantai Galon 65,000.00 68,400.00 65,000.00
1551 Pembersih Lantai Toilet Buah 20,000.00 21,000.00 20,000.00
1552 Pembersih Kaca Galon 60,000.00 64,800.00 60,000.00
1553 Pembersih Toilet Galon 45,000.00 50,400.00 45,000.00
1554 Pengelasan cm 25,000.00 25,080.00 25,000.00
1555 Pengharum Mobil Cair Ltr 40,000.00 42,000.00 40,000.00
1556 Pengharum Ruangan Buah 33,500.00 33,600.00 33,500.00
1557 Sabun Buah 13,000.00 13,200.00 13,000.00
1558 Sabit Bh 45,000.00 93,000.00 45,000.00
1559 Sapu lidi Ikat 10,000.00 10,500.00 10,000.00
1560 Sapu Ijuk Bh 30,000.00 34,800.00 30,000.00
1561 Sapu Bulu Ayam Super Bh 60,000.00 72,000.00 60,000.00
1562 Shampo Mobil Bh 40,000.00 43,200.00 40,000.00
1563 Sepatu Karet Ltr 145,000.00 184,503.00 145,000.00
1564 Sikat baja Bh 28,000.00 46,042.92 28,000.00
1565 Sikat Ban 17,400.00 17,400.00
1566 Skop Bh 78,000.00 113,400.00 78,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1567 Tempat Sampah Tutup Buah 270,000.00 270,000.00
1568 Tissue Gulung Buah 54,000.00 54,000.00
1569 Tissue Kotak Pack 18,000.00 18,000.00
1570 Water mur Bh 48,000.00 85,800.00 48,000.00
1571 Pipa Tremi dan Casing pelindung Ls 145,000.00 178,200.00 145,000.00
1572 Pelumas (Oli) Ltr 47,280.00 47,280.00
1573 Ramset m' 10,000.00 19,800.00 10,000.00
1574 Pembuangan lumpur eks. Bor m3 132,000.00 132,000.00
1575 Mobilisasi dan demobilisasi alat bor auger ZKL28 unit 174,240,000.00 174,240,000.00
1576 Mobilisasi dan demobilisasi alat bor auger ZKL28 Unit 178,200,000.00 178,200,000.00
1577 Service Crane kapasitas 50 ton bln 15,000,000.00 174,900,000.00 15,000,000.00
1578 Excavator PC200 bln 123,420,000.00 123,420,000.00
1579 Pengadaan rail beam untuk pemancangan ls 22,440,000.00 22,440,000.00
1580 Pemotongan kepala tiang pancang turap m' 125,400.00 125,400.00
1581 Galian tanah untuk capping beam m3 138,600.00 138,600.00
1582 Pembuangan tanah galian m3 125,400.00 125,400.00
1583 Pekerjaan Cetakan/Tutup Kepala Kolom bh 330,000.00 330,000.00
1584 Pek. Pembuatan papan nama proyek ls 1,320,000.00 1,320,000.00
DAFTAR HARGA SATUAN BAHAN
TAHUN 2019

Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10

(Mengacu ke ASHP Bina Marga )


(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
Keterangan

10
(Mengacu ke ASHP Bina Marga )
10,670.00 (Mengacu ke ASHP Bina Marga )
9,800.00
10,000.00
7,000.00
8,500.00
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )

75,000.00 230,000.00

400,000.00
250,000.00
150,000.00
60,000.00
300,000.00
500,000.00
500,000.00

10,000.00 5,000.00
8,000.00 7,500.00
250,000.00
50,000.00 10,000.00
2,500.00
35,000.00 5,000.00

10,000.00 3,500.00
10,000.00

3,500.00 3,000.00
20,000.00 20,000.00
Keterangan

10
2,500.00
7,000.00
8,500.00
7,000.00 7,000.00
8,000.00 7,000.00
50,000.00
15,000.00
Keterangan

10
DAFTAR HARGA BAHAN TAMBAHAN
PADA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KOTA DENPASAR TAHUN 2020

HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp)

1 2 3 4

BIDANG UMUM
1 Jaring Sungar m2 170,000.00
2 Tali Seling m' 9,500.00
3 Tali m' 5,600.00
4 Sekop Datar bh 165,000.00
5 Selang Air m' 8,000.00
6 Terpal m2 9,500.00

BIDANG BINA MARGA


1 Uditch 1000 x 1000 x 1200 K 350 unit 1,950,000.00
2 Uditch 1200 x 1200 x 1200 K 350 unit 2,950,000.00
3 Plat Penutup 400 x 1200 K 350 unit 450,000.00
4 Plat Penutup 1200 x 1200 x 1200 K 350 unit 1,250,000.00
5 Frame Manhole 1200 x 1200 unit 450,000.00
6 Cover Manhole 1200 x 1200 unit 650,000.00
7 Abu Batu m3 ###

BAHAN K3
A Alat Pelindung Diri
1 Topi Pelindung (safety Helmet) bh 55,000.00
2 Pelindung Mata (Goggles, Spectacles) bh 95,000.00
3 Tameng Mata (face Shield) bh 215,000.00
4 Masker Selam (Breathing Apparatus) bh 350,000.00
5 Pelindung Telinga (Ear Plug, Ear Muff) bh 250,000.00
6 Pelindung Pernafasan dan Mulut (Masker) bh 45,000.00
7 Sarung Tangan (Safety Gloves) bh 40,000.00
8 Penunjang Seluruh Tubuh (Full Body Harness) bh 130,000.00
9 Jaket Pelampung (Life Vest) bh 150,000.00
10 Celemek (Apron/Coverralls) bh 90,000.00
11 Pelindung Jatuh (Fall Arrester) bh 990,000.00

B Rambu-Rambu K3 bh 150,000.00
1 Rambu Petunjuk bh 150,000.00
2 Rambu Larangan bh 150,000.00
3 Rambu Peringatan bh 150,000.00
4 Rambu Kewajiban bh 150,000.00
5 Rambu Informasi bh 150,000.00
6 Rambu Pekerjaan Sementara bh 150,000.00
7 Tongkat Pengatur Lalu Lintas (Warning Light Stck) bh 60,000.00
8 Kerucut Lalu Lintas (Traffic Cone) bh 125,000.00
9 Lampu Putar (Rotary Lamp) bh 97,000.00
10 Lampu Selang Lalu Lintas bh
HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp)

1 2 3 4

C Pengendaliang Resiko K3
1 Alat Pemadam Api Ringan (APAR) bh 550,000.00
2 Sirine bh 450,000.00
3 Bendera K3 bh
4 Lampu Darurat (Emergency Lamp) bh 170,000.00

BAHAN TAMBAHAN
1 List Gypsum Profil 5 cm m' 11,500.00
2 Bubungan Genteng glazur bh 44,651.10
3 Tempat Sabun bh 149,800.00
4 Kusen Aluminum m' 110,000.00
5 Rangka Jendela Aluminium m' 115,500.00
6 Rangka Pintu Aliminium m' 121,000.00
7 Door Stoper bh 210,000.00
8 Door Closer bh 380,000.00
9 Kusen dan Pintu PVC Toilet unit 800,000.00
10 Genteng Keramik ex Jatiwangi bh 7,500.00
11 Genteng Keramik Glazur ex KANMURI bh 22,500.00
12 Nok Genteng Keramik EX Jatiwangi bh 42,000.00
13 Nok Genteng Keramik Ex Kanmuri bh 47,000.00
14 Kran Zink bh 485,000.00
15 Kran Dinding bh 240,000.00
16 Kitchen Zink bh 850,000.00
17 Floor Drain bh 110,000.00
18 Bak Air Fibergles bh 395,000.00
19 Klep Diameter 3/4" bh 112,000.00
20 Tangkin Air 1000 Liter bh 1,850,000.00
21 Tangki Air 500 Liter bh 845,000.00
22 Pelampung Otomatis bh 170,000.00
23 Roof Drain Metal bh 97,000.00
24 Mesin Jet Pump kap 250 watt ex Grounfos bh 5,600,000.00
25 Mesin Pompa Tekan kap. 150 watt ex Grounfos bh 3,450,000.00
26 Box Panel PVC isi 4 MCB ex Legran bh 210,000.00
27 MCB 6 A ex Legran bh 52,000.00
28 MCB 4 A ex Legran bh 48,000.00
29 Kabel telephone 4 x 0.5 mm m' 22,000.00
30 Oulet TV Broco bh 220,000.00
31 Outlet Telephone bh 230,000.00
32 Dowlight/PLC 13 W bh 62,000.00
-
DAFTAR HARGA SATUAN UPAH

HARGA
NO NAMA SATUAN
Rp

1 Pekerja Hari
2 Tukang Gali Hari ###
3 Tukang batu/tembok Hari ###
4 Tukang Kayu Hari ###
5 Tukang besi/besi beton Hari ###
6 Tukang Cat/pelitur Hari ###
7 Tukang pipa Hari ###
8 Tukang pipa/operator pompa Hari ###
9 Tukang Style Bali Hari ###
10 Tukang Listrik Hari ###
11 Tukang Las Hari ###
12 Tukang aluminium Hari ###
13 Kepala Tukang Hari ###
14 Kepala Tukang Style Bali Hari ###
15 Mandor Style Bali Hari
16 Mandor Hari

UPAH KERJA LAINNYA :


17 1 Titik Instalasi Stop Kontak, Lampu Exhaust Fan dan Celling Pan titik ###
18 1 Tititk Instalasi AC titik ###
19 1 Titik Instalasi Telephone titik ###
20 1 Titik Instalasi MATV titik ###
DAFTAR HARGA BAHAN
PADA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KOTA DENPASAR

HARGA
NO NAMA BAHAN SAT
(RP)

BATU KALI DAN BATU ALAM


1 Batu Kali/batu bulat 15-30 cm m3
2 Batu Belah 1.0-5.0 cm m3
3 Batu Pecah Besar 15/30 cm m3
4 Batu Pecah 5/7 cm m3
5 Batu Pecah 3/5 cm m3
6 Batu Pecah 3-4 cm m3
7 Batu Pecah 2/3 cm m3
8 Batu Pecah Mesin 1 - 2 cm m3
9 Batu Pecah 2-3 cm m3
10 Batu Pecah 1 - 2 cm m3
11 Batu Pecah 0,5 - 1 Cm m3
13 Batu Alam Andesit Alur m2
14 Batu Alam Live Grendia m2
15 Batu Candi m2
16 Batu Candi Hitam (Ukuran 30 x 30 x 2 Cm) Cirebon m2
17 Batu Candi Hitam (Ukuran 30 x 30 x 3 Cm) Cirebon m2
18 Batu Candi Hitam (Ukuran 30 x 30 x 5 Cm) Cirebon m2
19 Batu Candi Hitam (Ukuran 20 x 20 x 2 Cm) Cirebon m2
20 Batu Candi Hitam (Ukuran 20 x 30 x 5 Cm) Cirebon m2
21 Batu Putih Jogya / Palimanan (30 x 30 x 2 Cm) m2
22 Batu Putih Jogya / Palimanan (30 x 30 x 3 Cm) m2
23 Batu Putih Jogya / Palimanan (30 x 30 x 5 Cm) m2
24 Batu Alam Palimanan Putih Super m2
25 Batu hitam Jember 5 x 20 halus m2
26 Batu hitam Jember 20 x 40 halus m2
27 Batu hitam Jember 15 x 30 halus m2
28 Batu hitam Singaraja 15 x 30 halus m2
29 Batu hitam Singaraja 20 x 40 halus m2
30 Batu hitam karangasem/Batu Tabas (20 x 40 x 3) m2
31 Paras Silakarang Tipis (Ukuran 15 x 30 x 5 Cm) m2
32 Paras Silakarang Tebal (Ukuran 15 x 30 x 8 Cm) m2
33 Batu Paras Bali/Pawon (Abu - Abu Terang) m2
34 Paras Kelating / Kerobokan (Ukuran 3 x 20 x 40 Cm) bh
35 Batu pilah m2
36 Batu pilah Singaraja 30 x 30 m2
37 Batu pilah Singaraja 20 x 20 m2
38 Split Kasar m3
39 Split Halus m3
40 Koral Beton diameter 1 - 2 cm m3
41 Batu Sikat Hitam Lokal Super kampil
42 Batu Sikat Akik Merah kampil
43 Batu Sikat Putih Salju kampil
44 Koral Sikat (Lokal) sak
45 Kerikil m3
46 Kerikil Beton m3
47 Kerikil Halus m3
48 Pasir Halus m3
49 Pasir Pasang m3
50 Pasir Beton m3
51 Pasir Urug m3
52 Tanah Urug m3
53 Tanah Urug Pilihan m4
54 Tanah Lempung m3
55 Sirtu m3
56 Batu Karang Bukit m3
57 Limestone m3
HARGA
NO NAMA BAHAN SAT
(RP)

58 Abu Bata
59 Batako Lubang bh
60 Batako Buntu bh
61 Batu Bata bh
62 Bata Merah Klas I bh
63 Bata Merah Klas II bh
64 Bata Merah Klas III bh
65 Bata Merah Super (Pripian) ex tulikup bh
66 Bata Pres 22x10x6cm bh
67 Bata Pres 22x10x5cm bh
68 Batu Gosok bh
69 Filler kg
70 Additive liter
71 Agregat m3
72 Closeter bh
73 Lis Batu Alam L=7, T=40 bh
74 Lem Batu Alam kaleng
75 Coating (CP.27) kaleng

SEMEN
76 PC. Tiga Roda 50 Kg sak
77 PC Tiga Roda 40 Kg sak
78 PC. Tonasa 50 Kg / Busoa 50 Kg sak
79 PC. Gresik 40 Kg sak
80 PC. Gresik 50 Kg sak
81 PC Rajawali 40 Kg sak
82 PC Holcim 40 Kg sak
83 PC Conch 40 Kg sak
84 Semen Gresik kg
85 Semen Tiga Roda kg
86 Semen Tonasa kg
87 Semen Bosowa kg
88 Semen Holcim kg
89 Semen Conch kg
90 Semen Warna MU 408/ Nat kg
91 Semen Tipe V kg
92 Semen Portland kg

Waterproofing
93 Ultra Coat RC2 20 Lt pail
94 Boscosem Slury 33 Kg set
95 Damplix 2 20 kg set
96 Damplix 3 45 kg set
97 Damplix 3E 35 kg set
98 Boscoseal Tom (Wp membran Bakar) Uk. 1m x 10 m rol
99 Indo primer ( lapisan primer WP membran) 20 Lt pail
100 Integral Kristalisasi (Waterproofing kristal) 20 kg pail
101 Sika Top Seal Set 20 kg + cairan set

BAMBU
102 Bambu Ukuran 8"- 10" panjang 4 m btg
103 Bambu Ukuran 3"-6" panjang 4 m btg
104 Gedeg kulit kelas I m2
105 Gedeg kulit kelas II m2
106 Gedeg Biasa m2

KAYU
107 Kayu jati Balok Ex Bojonegoro m3
108 Kayu jati papan ex Bojonegoro m3
109 Kayu jati Usuk m3
HARGA
NO NAMA BAHAN SAT
(RP)

110 Kayu jati Reng m3


111 Kayu merbau Balok m3
112 Kayu merbau papan m3
113 Kayu kamper balok m3
114 Kayu kamper usuk/reng m3
115 Kayu kamper papan m3
116 Kayu Profil 4/5 kamper m'
117 List Kayu m'
118 List profil 2/4 kamper m'
119 Kayu kruing balok m3
120 Kayu kruing papan m3
121 Kayu Usuk Kruing m3
122 Kayu Reng Kruing m3
123 Kayu Papan Meranti m3
124 Kayu Balok Meranti m3
125 Kayu Usuk Meranti m3
126 Kayu Reng Meranti m3
127 Kayu Bangkirai Papan m3
128 Kayu Bangkirai Balok m3
129 Kayu Begisting 5/7 m3
130 Kayu Seseh Balok m3
131 Kayu Dolken / Skapolding m3
132 Kayu Seseh Dolken D 20 Panjang 3 m btg
133 Kayu Seseh Dolken D 8-10 Panjang 4m btg
134 Kayu Usuk Albesia 5/7 Panjang 4 m btg
135 Kayu Reng mekanis Uk 2 x 3 x 400 cm m3
136 Kayu Reng mekanis Uk 3 x 5 x 400 cm m3
137 Kayu Usuk mekanis Uk 4 x 6 x 400 cm m3
138 Kayu Usuk mekanis Uk 5 x 7 x 400 cm m3
139 Kayu Balok mekanis Uk. 6 x 12 x 400 cm m3
140 Kayu Balok mekanis Uk. 6 x 15 x 400 cm m3
141 Kayu Balok mekanis Uk. 6 x 20 x 400 cm m3
142 Kayu Kelas III lokal m3
143 Kayu 7/7, Kelas III m3
144 Kayu Cempaka lokal m3
145 Kayu Bakar m3
146 Papan Bakesting m3
147 Papan Kayu Ulin m3
148 Papan Kayu, Kelas II m3
149 Balok Kayu Ulin m3
150 Lem Aica Aibond kg
151 Lem Kayu setara Fox ltr
152 Minyak bekisting setara Calform NX*R ltr
153 Jaro bubut bh
154 Kayu Perancah m3

BESI
155 Mour + Bout bh
156 Besi strip kg
157 Besi strip 30x3 mm m'
158 Baja Strip (0,2 x 2) cm / Plat Strip Kg
159 Besi Beton U24 (Polos) Kg
160 Besi Beton Ulir U 32 Kg
161 Besi Ulir 13,0x 12 sni (Ts-40) Kg
162 Besi Ulir 16,0x 12 sni (Ts-40) kg
163 Besi Ø5 (3,8 x 6,0) btg
164 Besi Ø6 (5,0 x 12) btg
165 Besi Ø6 (5,2 x 12) btg
166 Besi Ø6 (5,7 x 12) btg
167 Besi Ø8 (6,5 x 12) btg
HARGA
NO NAMA BAHAN SAT
(RP)

168 Besi Ø8 (6,7 x 12) btg


169 Besi Ø8 (6,9 x 12) SNI btg
170 Besi Ø8 (7,1 x 12) SNI btg
171 Besi Ø8 (7,4 x 12) SNI btg
172 Besi Ø8 (7,6 x 12) SNI btg
173 Besi Ø8 (7,7 x 12) SNI btg
174 Besi Ø8 (7,8 x 12) SNI btg
175 Besi Ø8 SNI U 24 btg
176 Besi Ø10 (8,4 x 12) SNI btg
177 Besi Ø10 (8,6 x 12) SNI btg
178 Besi Ø10 (8,9 x 12) SNI btg
179 Besi Ø10 (9,2 x 12) SNI btg
180 Besi Ø10 (9,4 x 12) SNI btg
181 Besi Ø10 (9,6 x 12) SNI btg
182 Besi Ø10 (9,8 x 12) SNI btg
183 Besi Ø10 SNI U 24 btg
184 Besi Ø10 Ulir (9,5 x 12) SNI btg
185 Besi Ø10 Ulir (9,7 x 12) SNI btg
186 Besi Ø12 (11,5 x 12) SNI btg
187 Besi Ø13 Ulir (11,5 x 12) SNI btg
188 Besi Ø13 Ulir (11,7 x 12) SNI btg
189 Besi Ø13 Ulir (12,0 x 12) SNI btg
190 Besi Ø13 Ulir (12,5 x 12) SNI btg
191 Besi Ø13 Ulir (12,7 x 12) SNI btg
192 Besi Ø16 Ulir (14 x 12) SNI btg
193 Besi Ø16 Ulir (14,5 x 12) SNI btg
194 Besi Ø16 Ulir (15,0 x 12) SNI btg
195 Besi Ø16 Ulir (15,5 x 12) SNI btg
196 Besi Ø16 Ulir (15,7 x 12) SNI btg
197 Wiremesh M6@50m rol
198 Wiremesh M7 (D6,5mm) Uk. 2,1 x 5,4 m lbr
199 Wiremesh M8 (D7,5mm) Uk. 2,1 x 5,4 m lbr
200 Wermes Diameter 8 (U 50) lbr
201 Beugel Besi O8 kg
202 Beugel penguat /plaat kg
203 Kawat Beton RRT kg
204 Kawat berduri kg
205 Kawat Ayak / Kuasa 5 X 5 cm m2
206 Kawat Harmonika 3 X 3 cm m2
207 Kawat Nyamuk m2
208 Kawat Jaring m2
209 Kawat Bronjong kg
210 Besi / Baja profil kg
211 Besi Baja L60 X 60 X 6 / L50 x 50 x 5 kg
212 Baja WF (150 x 12 GG) btg
213 Baja WF (200 x 12 GG) btg
214 Besi Baja WF 200 x 100 x 4,5 x 7 kg
215 Besi Baja WF 200 x 100 x 5,5x8 kg
216 Besi Baja WF 250 x 125 x 5 x 7 kg
217 Besi Baja C 100 x 50 x 3,2 kg
218 Baja Ringan Type C- 75, 0.8 m'
219 Baja Ringan Type C- 75, 0.6 m'
220 Reng Baja m'
221 Profil Canal "C" Tipe C71.075 btg
222 Profil Canal "C" Tipe C81.075 btg
223 Profil Canal "C" Tipe C81.065 btg
224 Profil "Omega / reng Tipe AA btg
225 Profil "Omega / reng Tipe A btg
226 Profil "Omega / reng Tipe AB btg
227 Profil Aluminium Kaca 3/4 m'
228 Profil Aluminium L 3 cm lis Kaca m'
HARGA
NO NAMA BAHAN SAT
(RP)

229 Profil Aluminium 4" m'


230 Besi Plat kg
231 Besi plat 3 X 6 tebal 1,2 mm btg
232 Besi plat 4 X 8 tebal 1,8 mm btg
233 Baja Plat Hitam L = 10 lbr
234 Baja Plat Hitam L = 8 lbr
235 Baut Galvanis 3/4 x 2 " bh
236 Baut Galvanis 3/4 x 2 1/2 " bh
237 Baut Galvanis 3/4 x 3 " bh
238 Baut Galvanis 3/4 x 3 1/2 " bh
239 Baut Galvanis 3/4 x 4 " bh
240 Baut Galvanis 3/4 x 4 1/2 " bh
241 Baut Galvanis 3/4 x 5 " bh
242 Baut Galvanis 3/4 x 5 1/2 " bh
243 Baut Galvanis 3/4 x 6 " bh
244 Plat Siku Panjang 30 cm bh
245 Plat Siku Panjang 40 cm bh
246 Plat Siku Panjang 50 cm bh
247 Plat Siku Panjang 60 cm bh
248 Plat Aluminium 2mm m2
249 Besi siku / engsel m'
250 Besi Siku L.30.30.3 mm btg
251 Angker diameter 12mm bh
252 Skruf Fixer 5 cm bh
253 Dynabolt bh
254 Rapidrant gln
255 Sealant tube
256 Silicon kg
257 Elektrode 0,6 % bh
258 Elektrode 2 % bh
259 Sealant tube
260 Kusen aluminium YKK m'

CAT
261 Cat Marka Jalan Kg
262 Glas Bit Kg
263 Cat besi kg
264 Cat Menie besi Kg
265 Cat menie Kayu kg
266 Cat Dasar Tembok Setara Emco Kg
267 Cat Setara weldon biasa Kg
268 Cat Setara weldon warna Kg
269 Cat Setara weldon warna tua Kg
270 Cat Setara emco Lux Biasa kg
271 Cat Setara emco Lux Warna kg
272 Cat Setara emco Lux Warna Tua kg
273 Cat tembok Setara Decolith kg
274 Cat tembok Setara Dulux Exterior kg
275 Cat tembok Setara Dulux Interior kg
276 Cat tembok Setara Vinilex kg
277 Cat Galvanis kg
278 Cat Kayu Emco kg
279 Cat Baja Chromate (anti karat) Kg
280 Cat Kansteen Kg
281 Kalkarium Kg
282 Kapur sirih Kg
283 Amplas lbr
284 Kuas Bh

Stone Coating
285 Clear gloss air kg
HARGA
NO NAMA BAHAN SAT
(RP)

286 Black gloss air kg


287 Clear gloss solvent kg
288 Black gloss solvent kg
289 Clear doft solvent kg
290 Black doft solvent kg
291 Dempul / Plamir ltr
292 Dempul / Plamir Altik ltr
293 Dempul Impra Kayu ltr
294 Kuas untuk mengecat bh
295 Lem Fox (Rajawali Kuning) Gln
296 Lem Wall Paper Kg
297 Mild zak
298 Minyak cat ltr
299 Melamine Lack / Imfra ltr
300 Okear / Veap Kg
301 Plamir kayu kg
302 Plamir tembok setara wall Putty kg
303 Politur ultra ltr
304 Politur Jadi ltr
305 vernis ltr
306 Residu / Teer Ltr
307 Roll Buah
308 Sending Seaker ltr
309 Soda Api Kg
310 Thiner A Spesial ltr
311 Thiner B ltr
312 Teack Oil ltr
313 Wall Paper Setara Silk House m2
314 Wood Filler ltr
315 Cat Scotlight Ltr
316 Mowilex Kg

KACA
317 Bingkai Nako Silver daun
318 Bingkai Nako Coklat daun
319 Glass Block bh
320 Kaca 2 mm bening m2
321 Kaca 3 mm bening m2
322 Kaca 5 mm bening m2
323 Kaca 6 mm bening m2
324 Kaca 8 mm bening m2
325 Kaca 10 mm bening m2
326 Kaca 12 mm bening m2
327 Kaca Cermin 3 mm m2
328 Kaca Cermin 5 mm m2
329 Kaca Es/Kapur 3 mm m2
330 Kaca Es/Kapur 5 mm m2

PIPA
331 Pipa Galvanis 1" m'
332 Pipa Galvanis 1,5 BSA m'
333 Pipa Galvanis 2" m'
334 Pipa Galvanis 3" m'
335 Pipa Maspion AW 1/2 m'
336 Pipa Maspion AW 3/4 m'
337 Pipa Maspion AW 1 m'
338 Pipa Maspion AW 1-1/2 m'
339 Pipa Maspion AW 1-1/4 m'
340 Pipa Maspion AW 2 m'
341 Pipa Maspion AW 2-1/2 m'
342 Pipa Maspion AW 3 m'
HARGA
NO NAMA BAHAN SAT
(RP)

343 Pipa Maspion AW 4 m'


344 Pipa Maspion AW 5 m'
345 Pipa Maspion AW 6 m'
346 Pipa Maspion AW 8 m'
347 Pipa Maspion AW 10 m'
348 Pipa Maspion AW 12 m'
349 Pipa Maspion AW 14 m'
350 Pipa Maspion AW 16 m'
351 Pipa Maspion C 3/4 m'
352 Pipa Maspion C 5/8 m'
353 Pipa Maspion C 1 m'
354 Pipa Maspion C 1-1/2 m'
355 Pipa Maspion C 1-1/4 m'
356 Pipa Maspion C 2 m'
357 Pipa Maspion C 2-1/2 m'
358 Pipa Maspion C 3 m'
359 Pipa Maspion C 3-1/2 m'
360 Pipa Maspion C 4 m'
361 Pipa Maspion D 1/2 m'
362 Pipa Maspion D 1-1/2 m'
363 Pipa Maspion D 1-1/4 m'
364 Pipa Maspion D 2 m'
365 Pipa Maspion D 2-1/2 m'
366 Pipa Maspion D 3 m'
367 Pipa Maspion D 4 m'
368 Pipa Maspion D 5 m'
369 Pipa Maspion D 6 m'
370 Pipa Maspion D 8 m'
371 Pipa Maspion D 10 m'
372 Pipa Maspion D 12 m'
373 Pipa Maspion D 14 m'
374 Pipa Maspion D 16 m'
375 Pipa / selang spiral sel kran m'
376 Pipa wavin warna putih AW 1/2 m'
377 Pipa wavin warna putih AW 3/4 m'
378 Pipa wavin warna putih AW 1 m'
379 Pipa wavin warna putih AW 1 1/4 m'
380 Pipa wavin warna putih AW 1 1/2 m'
381 Pipa wavin warna putih AW 2 m'
382 Pipa wavin warna putih AW 2 1/2 m'
383 Pipa wavin warna putih AW 3 m'
384 Pipa wavin warna putih AW 4 m'
385 Pipa wavin warna putih AW 5 m'
386 Pipa wavin warna putih AW 6 m'
387 Pipa wavin warna putih AW 8 m'
388 Pipa wavin warna putih AW 10 m'
389 Pipa wavin warna putih AW 12 m'
390 Pipa wavin warna putih D 1 1/4 m'
391 Pipa wavin warna putih D 1 1/2 m'
392 Pipa wavin warna putih D 2 m'
393 Pipa wavin warna putih D 2 1/2 m'
394 Pipa wavin warna putih D 3 m'
395 Pipa wavin warna putih D 4 m'
396 Pipa wavin warna putih D 5 m'
397 Pipa wavin warna putih D 6 m'
398 Pipa wavin warna putih D 8 m'
399 Pipa wavin warna putih D 10 m'
400 Pipa wavin warna putih D 12 m'

BAHAN LISTRIK
401 Coaxial cable 5C - 75 ohm commscof m
HARGA
NO NAMA BAHAN SAT
(RP)

402 Box Panel (3 mm) (400 x 600) Bh


403 Figting lampu Broco Bh
404 Inbow dos plastik clipsal E 157 P OB bj
405 Kabel NYM 2 x 1.5 mm Suprime NYM m
406 Kabel NYY 2 x 1.5 mm m
407 Kabel NYM 2 x 2.5 mm m
408 Kabel NYY 3 x 1.5 mm m
409 Kabel NYM 3 x 2.5 mm m
410 Kabel NYY 3 x 2.5 mm m
411 Kabel NYM 4 mm m
412 Kabel NYY 2 x 2,5 mm m
413 Kabel Twisteed 2 x 16 mm m
414 Kabel telephone m
415 Klem clipsal 20 mm bj
416 Casing Lampu Bawah Air bh
417 Casing Lampu Tangga bh
418 Kap Lampu 14 Inchi Aluminium bh
419 Fitting Gantung E27 bh
420 Magnet Contactor 80 A SN - 50 bh
421 MCB 3 phase 40 A MG bh
422 MCB 3 phase 63 A MG bh
423 Panel MDP Unit
424 Panel SDP Unit
425 Pipa clipsal 20 mm bt
426 Pipa flexible clipsal 20 mm m1
427 Saklar ganda clipsal bh
428 Saklar tunggal Setara clipsal bh
429 Sock clipsal 20 mm bj
430 Steker bh
431 Stop Kontak bh
432 Stop Kontak Khusus (Kedap Air) bh
433 Travo max 50 watt bh
434 Tee dos clipsal 20 mm bh
435 Time Switch bh
436 T Foring bh

KERAMIK
437 Keramik Asia Tile 20 x 20 kelas I warna muda m2
438 Keramik Setara Asia Tile 20 x 20 kelas I warna tua m2
439 Keramik Setara Asia Tile 20 x 25 kelas I m2
440 Keramik Setara Asia Tile 30 x 30 kelas I warna muda m2
441 Keramik Setara Asia Tile 30 x 30 kelas I warna tua m2
442 Keramik Setara Asia Tile 40 x 40 kelas I m2
443 Keramik Setara Asia Tile 60 x 60 kelas I Setara Platinum m2

ATAP
444 Alang-alang panjang 2,4 meter lbr
445 Alluminium foil M2 Double rol
446 Akustik 60 cm x 120 cm lbr
447 Asbes Bubungan lbr
448 Asbes Gelombang 1,80 m x 0,80 m lbr
449 Asbes Gelombang 1,80 m x 1,05 m lbr
450 Asbes Gelombang 2,10 m x 1,05 m lbr
451 Asbes Gelombang 2,4 m x 1,05 m lbr
452 Asbes Rata 2 m x 1 m x 4 mm lbr
453 Bentala tanah liat Ex Pejaten bh
454 Bentala Ex Kapal bh
455 Bentala Besar polos Lubang 24 cm bh
456 Bentala Besar Warna Lubang 25 cm bh
457 Bentala Besar polos Lubang 90 cm bh
458 Bentala Besar Warna Lubang 90 cm bh
HARGA
NO NAMA BAHAN SAT
(RP)

459 Bubungan Besar bh


460 Bubungan Kecil bh
461 Bubungan Bambe Kecil bh
462 Bubungan Bulat Karang Pilang bh
463 Bubungan Bulat Jati Wangi bh
464 Bubungan Bulat Ngalayur isi 3,5/m bh
465 Bubungan Besar Good Year bh
466 Bubungan Beton Cisangkan bh
467 Bubungan Gerard lbr
468 Bubungan Karang Pilang isi 3,5/m bh
469 Bubungan Pletong Jatiwangi bh
470 Bubungan SL Utama bh
471 Bubungan SL Ngalayur bh
472 Bubungan Segi Tiga Karang Pilang bh
473 Bubungan Utama isi 3,5/m bh
474 Genteng Bambe bh
475 Genteng Bambe Karang Pilang bh
476 Genteng Bambe Kecil bh
477 Genteng Beton Cisangkan bh
478 Genteng Gemini bh
479 Genteng Gerard Polos m2
480 Genteng Good Year m2
481 Genteng Kanmuri (glazur) isi 14/m2 bh
482 Genteng Kodok Lokal bh
483 Genteng Kodok Kamulan bh
484 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bh
485 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bh
486 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bh
487 Genteng Kodok Karang Pilang (Surabaya) bh
488 Genteng Kodok Soka bh
489 Genteng Lestari bh
490 Genteng Metal m2
491 Genteng Metal 80 x 77,6 (Polos) lbr
492 Genteng Metal 80 x 77,6 (Pasir) lbr
493 Genteng Morando Abadi isi 18/m2 bh
494 Genteng Morando Jatiwangi isi 18/m2 bh
495 Genteng Morando Ngalayur isi 20/m2 bh
496 Genteng Morando Metal bh
497 Genteng Pejaten Mini bh
498 Genteng Plentong bh
499 Genteng plentong dicat bh
500 Genteng Plentong Mantili bh
501 Genteng Plentong Pejaten / Darmasaba bh
502 Genteng Plentong Jatiwangi / Surabaya bh
503 Genteng Portugis bh
504 Genteng Pres Besar bh
505 Genteng Pres Besar Cat bh
506 Genteng Pres Mini bh
507 Genteng Pres Mini Cat bh
508 Genteng Terreal bh
509 Genteng T. Romana bh
510 Genteng Besar polos Lubang 35 cm bh
511 Genteng Besar Warna Lubang 35 cm bh
512 Fiberglas (1.80 x 0.80) M2 lbr
513 Ijuk kg
514 Ijuk Bersih bh
515 Ijuk Lampung bh
516 Ikut Celedu bh
517 Ikut Celedu Besar Polos bh
518 Ikut Celedu Besar Warna bh
519 Ikut Celedu Kecil Polos bh
HARGA
NO NAMA BAHAN SAT
(RP)

520 Ikut Celedu Kecil Warna bh


521 Kawat las kg
522 Kawat Diameter 4 mm kg
523 Murda / Puntal Paras bh
524 Murda tanah liat Ex Pejaten bh
525 Murda Kecil Polos Lubang 25 cm bh
526 Murda Kecil Warna Lubang 25 cm bh
527 Profil Aluminium "T" m3
528 Seng BJLS 0,18 gelombang lbr
529 Seng BJLS 0,22 gelombang lbr
530 Seng BJLS 0,30 gelombang lbr
531 Seng Zincalume Panjang 6m Tebal 0,5 mm lbr
532 Seng Plat Lebar 0,90 M lbr
533 Seng Plat 3" x 6" BJLS 28 lbr
534 Seng Plat Aluminium lbr
535 Sirap lbr
536 Subeng Besar Polos lbr
537 Subeng Besar Warna lbr
538 Subeng Kecil Polos lbr
539 Subeng Kecil Warna bh

TALI
540 Tali Ijuk kg
541 Tali pengikat ikat
542 Tali pengikat alang-alang ikat
543 Tali Rafia Gulung

KUNCI DAN PENGGANTUNG


544 Engsel H ( 80 x 50) Ps
545 Engsel kupu-kupu Rafes 4' 304 ps
546 Engsel pintu Setara ECOLING Ps
547 Engsel jendela Setara ECOLING Ps
548 Engsel jendela Setara CAMEL Ps
549 Espagnoleth Setara Rafes 60 cm Ps
550 Grendel Setara ESBELA bh
551 Grendel tanam Setara CAMEL bh
552 Kait angin biasa Setara CAMEL bh
553 Kait angin diameter 10 mm bh
554 Kait angin lipat Setara ESBELA bh
555 Kait angin tarik Setara ESBELA bh
556 Kunci kuda 2 x putar bh
557 Kunci lif 1 x putar Setara BELLEZA bh
558 Kunci lif 2 x putar bh
559 Kunci pintu TOP Setara ESBELA bh
560 Kunci pintu Vanesa Setara CAMEL bh
561 Kunci pintu Setara ESBELLA bh
562 Kunci Pintu 2 x putar Setara SES bh
563 Kunci pintu Setara DELWIN) bh
564 Kunci shang hae 2 x putar bh
565 Kunci slot / Grendel Pintu Setara DELLWYN bh
566 Kunci tanam 2 slag Setara Dexon bh
567 Kunci silinder bh
568 Door holder bh

PAKU
569 Paku Beton kg
570 Paku Usuk kg
571 Paku Reng kg
572 Paku List kg
573 Paku Seng Ulir bh
574 Paku 2-4 cm kg
HARGA
NO NAMA BAHAN SAT
(RP)

575 Paku Pancing 60 x 230 kg


576 Paku 5-12 cm kg
577 Paku 2 cm (30 kg) 3/4 inch SQ dus
578 Paku 2,5 cm (30 kg) 1 inch SQ dus
579 Paku 3 cm (30 kg) 1 1/4 inch SQ dus
580 Paku 4 cm (30 kg) 1 1/2 inch SQ dus
581 Paku 5 cm (30 kg) 2 inch SQ dus
582 Paku 7,10,12 cm (3,4,5) inch SQ dus
583 Paku 5 -12 cm (27kg) 2,3,4,5 inch dus
584 Paku skrup 1/2" kg
585 Paku skrup 2" kg
586 Paku skrup 3.5" kg
587 Bendrat 20 kg rol
588 Sekrup Kalisiboard buah

BETON CETAK
589 Paving 20 x 20 cm tebal 6 cm K225 (Polos) m2
590 Paving 20 x 20 cm tebal 8 cm K225 (Polos) m2
HARGA
NO NAMA BAHAN SAT
(RP)

PLAFOND & TIRPLEK


591 Acustik 30/30 lbr
592 Celling teak (0,62 x 2,40) m2 lbr
593 Eternit lbr
594 Playwood 3 mm lbr
595 Playwood 4 mm Setara Meranti lbr
596 Plywood 5 mm lbr
597 Playwood 9 mm Setara Meranti lbr
598 Playwood aluminium lbr
599 Gypsum Board (120x240x9) lbr
600 Kalsiboard (4,5 x 1220 x 2420) mm lbr
601 Tea Block 18 mm lbr
602 Hard board MDF lbr
603 Multiplek 6 mm lbr
604 Multiplek 9mm lbr
605 Multiplek 12 mm lbr
606 Triplek tebal 3mm (2,7mm) kayu sengon lbr
607 Triplek tebal 3mm (2,7mm) kayu semi meranti lbr
608 Triplek tebal 4mm (3,6mm) kayu sengon lbr
609 Triplek tebal 4mm (3,6mm) kayu semi meranti lbr
610 Triplek tebal 6mm (5,2mm) kayu sengon I lbr
611 Triplek tebal 6mm (5,2mm) kayu sengon II lbr
612 Triplek tebal 6mm (5,2mm) kayu semi meranti lbr
613 Triplek tebal 6mm (5,2mm) kayu semi meranti II lbr
614 Triplek tebal 8,0mm kayu sengon I lbr
615 Triplek tebal 8,0mm kayu sengon II lbr
616 Triplek tebal 8,0mm kayu semi meranti lbr
617 Triplek tebal 9,0mm kayu semi meranti II lbr
618 Triplek tebal 12 mm kayu sengon I lbr
619 Triplek tebal 12 mm kayu semi meranti lbr
620 Triplek tebal 15 mm kayu semi meranti lbr
621 Triplek tebal 18 mm kayu semi meranti lbr
622 Teakwood 122 x 244 x 2,7 mm lbr
623 Melamine Putih/Biru 2,7 lbr
624 Triplek aluminium jruk asli lbr
625 Triplek aluminium jruk standar lbr
626 Block board 18 mm sengon lbr
627 Block board 18 mm meranti super lbr
628 Teak block 18mm lbr
629 Rangka Aluminium m
630 Rangka Metal Furing (2 x 4 cm) panjang 4 m btg
631 Rangka Metal Furing (4 x 4 cm) panjang 4 m btg
632 Teak wood (1,20x2,40x 0,4) lbr
633 Teak wood (0,90x2,00 x 0,4) lbr
634 Jabar Wood 4 mm lbr

LAIN - LAIN
635 Air Bersih ltr
DAFTAR ANALISA PEKERJAAN TAMBAHAN

1 1 M2 PEMBUATAN STEGGER DENGAN SCAFHOLDING 120 x 180 h 190 (Sewa)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0170
Tukang Kayu OH 0.0020
Kepala Tukang OH 0.2500
Mandor OH 0.0130
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Balok Seseh btg 0.0350
Paku 10 kg 0.2000
Main Frame Bh 2.0000
End Frame Bh 2.0000
Cros brace Bh 4.0000
Join Pen Bh 4.0000
U Head Bh 4.0000
Jack Base Bh 4.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M2 PASANGAN BATA GOSOK 2 MUKA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000
JUMLAH TENAGA KERJA
B. BAHAN
Bata Gosok bh 110.0000
Semen 50 Kg kg 8.4000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
3 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000
JUMLAH TENAGA KERJA
B. BAHAN
Paras Kerobokan bh 13.7500
Semen 50 Kg kg 8.4000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

4 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K225


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500
Pekerja OH 0.5000
Mandor OH 0.0250
JUMLAH TENAGA KERJA
B. BAHAN
1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K225 m2 1.0500

JUMLAH HARGA BAHAN


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

5 1 M3 URUGAN TANAH
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Mandor OH 0.0100
JUMLAH TENAGA KERJA
B. BAHAN
Tanah Urug m3 1.200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
6 1 M2 PASANGAN BATU ANDESIT
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 1.000
Kepala tukang OH 0.250
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Batu andesit M² 1.100
Semen Kg 11.750
Pasir pasang M³ 0.035
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

7 1 M3 URUGAN TANAH
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Mandor OH 0.010
JUMLAH TENAGA KERJA
B. BAHAN
Tanah urug M3 1.200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 1 M2 PASANGAN SUNDBLAST
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.020
Tukang Kayu OH 0.200
Kepala tukang OH 0.020
Mandor OH 0.003
JUMLAH TENAGA KERJA
B. BAHAN
Sundblast M2 1.100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

9 1 M2 PASANGAN KUDA - KUDA BAJA RINGAN PROFIL C75


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Ongkos pasang Ls 1.000
JUMLAH TENAGA KERJA
B. BAHAN
Rangka C 75075 @ 6 m galvalume Btg 0.715
Reng (butten Ω 30) tebal 0.45 @ 6 m Btg 0.618
Reng pengikat kuda-kuda @ 6 m Btg 0.067
Baut kuda-kuda SDS 6-19 Bh 35.000
Baut reng SDS 6-16 Bh 20.000
Baut listplank Ø 6-70 Bh 0.947
Paku beton 5 cm Bh 0.947
Dinabold Ø 10-65 Bh 0.947
Material dan alat bantu M² 1.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

10 1 M2 PASANGAN GENTENG KODOK GOODYEAR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.150
Tukang kayu OH 0.075
Kepala Tukang OH 0.008
Mandor OH 0.008
JUMLAH TENAGA KERJA
B. BAHAN
Genteng kodok goodyear Bh 21.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
11 1 M' PASANGAN BUBUNGAN GENTENG KODOK GOODYEAR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.400
Tukang kayu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.002
JUMLAH TENAGA KERJA
B. BAHAN
Genteng bubung buah 4.000
Semen portland Kg 8.000
Pasir pasang m³ 0.032
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

12 1 M' PASANGAN TATAB KAYU KAMPER 2,5 X 7 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.10
Tukang kayu OH 0.20
Kepala Tukang OH 0.02
Mandor OH 0.01
JUMLAH TENAGA KERJA
B. BAHAN
Kayu kamper papan M3 0.002
Paku biasa ½”-1” Kg 0.050
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
13 1 M' PASANGAN LISTPLANK KAYU KAMPER 2,5 X 9 CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.10
Tukang kayu OH 0.20
Kepala Tukang OH 0.02
Mandor OH 0.01
JUMLAH TENAGA KERJA
B. BAHAN
Kayu kamper papan M3 0.003
Paku biasa ½”-1” Kg 0.050
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

14 1 M' PASANGAN LISTPLANK KAYU KAMPER 2,5 X 15 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.10
Tukang kayu OH 0.20
Kepala Tukang OH 0.02
Mandor OH 0.01
JUMLAH TENAGA KERJA
B. BAHAN
Kayu kamper papan M3 0.005
Paku biasa ½”-1” Kg 0.050
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
15 1 BH PASANGAN SAKLAR TUNGGAL
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Saklar tunggal bh 1.000
Mangkok listrik bh 1.000
Isolasi bh 0.250
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

16 1 BH PASANGAN SAKLAR GANDA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Saklar ganda bh 1.000
Mangkok listrik bh 1.000
Isolasi bh 0.250
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
17 1 BH PASANGAN STOP KONTAK
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Stop kontak bh 1.000
Mangkok listrik bh 1.000
Isolasi bh 0.250
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

18 1 M2 PASANGAN KERAMIK DINDING 20 X 25 ASIA TILE


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600
Tukang batu OH 0.350
Kepala Tukang OH 0.035
Mandor OH 0.030
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 20 x 25 cm Bh 20.000
Semen portland (Gersik) Kg 10.400
Pasir pasang M3 0.045
Semen warna Kg 1.620
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
19 1 BH GRENDEL JENDELA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH
JUMLAH TENAGA KERJA
B. BAHAN
Grendel jendela bh 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

20 1 BH ENGSEL KOBOI
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH
JUMLAH TENAGA KERJA
B. BAHAN
Engsel koboi bh 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

21 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II LAPIS ALUMINIUM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000
Tukang kayu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.0500
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0400
Lapis aluminium jeruk lbr 0.366
Lem Kayu Kg 0.5000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

22 1 UNIT PINTU KACA BENING 12 MM FLOORHINGE + ACCESORIS (60 X 210 CM)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.0000
Tukang Besi OH 0.7000
Kepala Tukang OH 0.1000
Mandor OH 0.1000
JUMLAH TENAGA KERJA
B. BAHAN
Kaca bening 12 mm M2 1.512
Floor Hinge Bh 1.000
Patch Fitting Bh 1.000
PT 24 Bh 1.000
Handle Pintu Bh 1.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

23 1 M2 PARTISI GYPSUM 9 MM RANGKA METAL STUD


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang Kayu OH 0.050
Kepala Tukang OH 0.005
Mandor OH 0.005
JUMLAH TENAGA KERJA
B. BAHAN
Metal stud M' 3.500
Gypsum Board (120x240x9) Lb 0.750
Assesoris (perkuatan, las dll) Ls 35% x rangka
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
24 1 M2 PASANG LANTAI KERAMIK ANTI SLIP 40 X 40 CM ASIA TILE
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250
Tukang Batu OH 0.125
Kepala Tukang OH 0.013
Mandor OH 0.013
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 40 x 40 cm bh 6.63
Semen kg 9.80
Pasir Pasang m3 0.045
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

25 1 BH PASANGAN STOP KONTAK AC


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Stop kontak AC bh 1.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
26 1 BH PASANGAN OUTLET DATA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Outlet data bh 1.000
Mangkok listrik bh 1.000
Isolasi bh 0.250
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

27 1 BH PASANGAN OUTLET TELEPHONE


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Outlet telephone bh 1.000
Mangkok listrik bh 1.000
Isolasi bh 0.250
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
28 1 BH PASANGAN LAMPU DOWNLIGHT 7,5 WATT LED
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Lampu downlight 7,5 watt LED bh 1.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

29 1 BH PASANGAN LAMPU DOWNLIGHT OUTBOW 11 WATT LED


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Lampu downlight outbow 11 watt LED bh 1.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

30 1 BH PASANGAN LAMPU DOWNLIGHT OUTBOW 18 WATT LED


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Lampu downlight outbow 18 watt LED bh 1.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

31 1 M2 PASANGAN KERAMIK 60 X 60 PLATINUM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.700
Tukang batu OH 0.350
Kepala Tukang OH 0.035
Mandor OH 0.035
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 60 x 60 cm m2 1.050
Semen portland Kg 9.800
Pasir pasang m³ 0.045
Semen warna Kg 1.500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

32 1 M2 PEMBONGKARAN ATAP GENTENG


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Mandor OH 0.0142
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

33 1 M2 PEMBONGKARAN USUK DAN RENG


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000
Mandor OH 0.0100
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

34 1 BH PEMBONGKARAN KUSEN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7500
Mandor OH 0.0708
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

35 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU BANGKIRAI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 6.0000
Tukang kayu OH 18.0000
Kepala Tukang OH 1.8000
Mandor OH 0.3000
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Bangkirai m3 1.2000
Paku 10 Cm Kg 1.2500
Lem Kayu Kg 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
36 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU BANGKIRAI
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000
Tukang kayu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.0500
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Bangkirai m3 0.0400
Lem Kayu Kg 0.5000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

37 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU BANGKIRAI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8000
Tukang kayu OH 2.4000
Kepala Tukang OH 0.2400
Mandor OH 0.0400
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0240
Lem Kayu Kg 0.3000
Kaca 5 mm m2 1.0500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
38 1 M' PEMASANGAN KUSEN PINTU ALLUMINIUM YKK
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.043
Tukang khusus aluminium OH 0.043
Kepala tukang OH 0.004
Mandor OH 0.002
JUMLAH TENAGA KERJA
B. BAHAN
Profil alluminium m 1.100
Skrup fixer buah 2.000
Sealant Tube 0.060
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

39 PEMASANGAN 1 M2 KUDA - KUDA BAJA RINGAN PROFIL UK-60 AXIS TRUSS RUMAH DINAS
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Ongkos pasang Ls 1.000
JUMLAH TENAGA KERJA
B. BAHAN
Rangka UK 60055 @ 6 m galvalume Btg 0.715
Reng purlin tebal 0,4 mm @ 6 m Btg 0.618
Reng pengikat kuda-kuda @ 6 m Btg 0.067
Baut kuda-kuda SDS 6-19 Bh 35.000
Baut reng SDS 6-16 Bh 20.000
Baut listplank Ø 6-70 Bh 0.947
Paku beton 5 cm Bh 0.947
Dinabold Ø 10-65 Bh 0.947
Material dan alat bantu M² 1.000
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
40 PEMASANGAN 1 M2 KUDA - KUDA BAJA RINGAN PROFIL UK-60 AXIS TRUSS GARASE
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Ongkos pasang Ls 1.000
JUMLAH TENAGA KERJA
B. BAHAN
Rangka UK 60055 @ 6 m galvalume Btg 0.400
Reng purlin tebal 0,4 mm @ 6 m Btg 0.618
Reng pengikat kuda-kuda @ 6 m Btg 0.067
Baut kuda-kuda SDS 6-19 Bh 35.000
Baut reng SDS 6-16 Bh 20.000
Baut listplank Ø 6-70 Bh 0.947
Paku beton 5 cm Bh 0.947
Dinabold Ø 10-65 Bh 0.947
Material dan alat bantu M² 1.000
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

41 PEMASANGAN 1 M2 DINDING KERAMIK UKURAN 25 CM X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.900
Tukang batu OH 0.450
Kepala Tukang OH 0.045
Mandor OH 0.045
JUMLAH TENAGA KERJA
B. BAHAN
keramik 25 x 40 cm M2 10.500
Semen portland Kg 9.300
Pasir pasang m³ 0.020
Semen warna Kg 1.940
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
42 PEMASANGAN 1 M2 KERAMIK 30 X 30 CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250
Tukang batu OH 0.125
Kepala Tukang OH 0.013
Mandor OH 0.013
JUMLAH TENAGA KERJA
B. BAHAN
keramik 30 x 30 M2 11.000
Semen portland Kg 10.000
Pasir pasang m³ 0.045
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

43 1 BH PASANGAN LAMPU LED PANEL 12 WATT ( WHITE ) PHILIPS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Lampu LED Panel 12 Watt ( White ) philips bh 1.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
44 1 BH PASANGAN LAMPU LED PANEL 6 WATT ( WHITE ) PHILIPS
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Lampu LED Panel 6 Watt ( White ) philips bh 1.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

45 1 BH PASANGAN LAMPU LED PANEL 6 WATT (WARM WHITE) PHILIPS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang listrik OH 0.100
Kepala Tukang OH 0.050
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Lampu LED Panel 6 Watt (Warm White) philips bh 1.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
46 1 M2 PASANGAN BATU PALIMANAN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 1.000
Kepala tukang OH 0.250
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
Batu palimanan M² 1.100
Semen Kg 11.750
Pasir pasang M³ 0.035
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

47 1 M2 PASANGAN GRANIT POLISH 60 X 60 CM DURAFLOOR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.700
Tukang batu OH 0.350
Kepala Tukang OH 0.035
Mandor OH 0.035
JUMLAH TENAGA KERJA
B. BAHAN
Granit 60 x 60 cm durafloor m2 1.050
Semen portland Kg 9.800
Pasir pasang m³ 0.045
Semen warna Kg 1.500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
48 1 M2 PASANG LANTAI GRANIT UNPOLISH 40 X 40 CM DURAFLOOR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250
Tukang Batu OH 0.125
Kepala Tukang OH 0.013
Mandor OH 0.013
JUMLAH TENAGA KERJA
B. BAHAN
Granit unpolish 40 x 40 cm durafloor m2 1.05
Semen kg 9.80
Pasir Pasang m3 0.045
Semen warna kg 1.300
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

49 1 M2 PASANG DINDING GRANIT KM/WC 30 X 60 CM DURAFLOOR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.900
Tukang Batu OH 0.350
Kepala Tukang OH 0.035
Mandor OH 0.035
JUMLAH TENAGA KERJA
B. BAHAN
Granit polish 30 x 60 cm m2 1.050
Semen portland kg 9.300
Pasir pasang m3 0.018
Semen warna kg 1.500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
50 1 M2 PASANG PLINT GRANIT 10 X 60 CM DURAFLOOR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.090
Tukang Batu OH 0.090
Kepala Tukang OH 0.009
Mandor OH 0.005
JUMLAH TENAGA KERJA
B. BAHAN
Granit polish 60 x 60 cm m2 0.125
Semen portland kg 1.140
Pasir pasang m3 0.003
Semen warna kg 0.100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
REKAPITULASI DAFTAR HARGA SATUAN PEKERJAAN TAMBAHAN

NO URAIAN PEKERJAAN HARGA

1 1 M2 PEMBUATAN STEGGER DENGAN SCAFHOLDING 120 x 180 h 190 (Sewa) Rp


2 1 M2 PASANGAN BATA GOSOK 2 MUKA Rp
3 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA Rp
4 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K225 Rp.
5 1 M3 URUGAN TANAH Rp
6 1 M2 PASANGAN BATU ANDESIT Rp
7 1 M3 URUGAN TANAH Rp
8 1 M2 PASANGAN SUNDBLAST Rp
9 1 M2 PASANGAN KUDA - KUDA BAJA RINGAN PROFIL C75 Rp
10 1 M2 PASANGAN GENTENG KODOK GOODYEAR Rp
11 1 M' PASANGAN BUBUNGAN GENTENG KODOK GOODYEAR Rp
12 1 M' PASANGAN TATAB KAYU KAMPER 2,5 X 7 CM Rp
13 1 M' PASANGAN LISTPLANK KAYU KAMPER 2,5 X 9 CM Rp
14 1 M' PASANGAN LISTPLANK KAYU KAMPER 2,5 X 15 CM Rp
15 1 BH PASANGAN SAKLAR TUNGGAL Rp
16 1 BH PASANGAN SAKLAR GANDA Rp
17 1 BH PASANGAN STOP KONTAK Rp
18 1 M2 PASANGAN KERAMIK DINDING 20 X 25 ASIA TILE Rp
19 1 BH GRENDEL JENDELA Rp
20 1 BH ENGSEL KOBOI Rp
21 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II LAPIS ALUMINIUM Rp
22 1 UNIT PINTU KACA BENING 12 MM FLOORHINGE + ACCESORIS (60 X 210 CM) Rp
23 1 M2 PARTISI GYPSUM 9 MM RANGKA METAL STUD Rp
24 1 M2 PASANG LANTAI KERAMIK ANTI SLIP 40 X 40 CM ASIA TILE Rp
25 1 BH PASANGAN STOP KONTAK AC Rp
26 1 BH PASANGAN OUTLET DATA Rp
27 1 BH PASANGAN OUTLET TELEPHONE Rp
28 1 BH PASANGAN LAMPU DOWNLIGHT 7,5 WATT LED Rp
29 1 BH PASANGAN LAMPU DOWNLIGHT OUTBOW 11 WATT LED Rp
30 1 BH PASANGAN LAMPU DOWNLIGHT OUTBOW 18 WATT LED Rp
31 1 M2 PASANGAN KERAMIK 60 X 60 PLATINUM Rp
32 1 M2 PEMBONGKARAN ATAP GENTENG Rp
33 1 M2 PEMBONGKARAN USUK DAN RENG Rp
34 1 BH PEMBONGKARAN KUSEN Rp
35 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU BANGKIRAI Rp
36 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU BANGKIRAI Rp
37 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU BANGKIRAI Rp
38 1 M' PEMASANGAN KUSEN PINTU ALLUMINIUM YKK Rp
39 PEMASANGAN 1 M2 KUDA - KUDA BAJA RINGAN PROFIL UK-60 AXIS TRUSS RUMAH DINAS Rp
40 PEMASANGAN 1 M2 KUDA - KUDA BAJA RINGAN PROFIL UK-60 AXIS TRUSS GARASE Rp
41 PEMASANGAN 1 M2 DINDING KERAMIK UKURAN 25 CM X 40 CM Rp
42 PEMASANGAN 1 M2 KERAMIK 30 X 30 CM Rp
43 1 BH PASANGAN LAMPU LED PANEL 12 WATT ( WHITE ) PHILIPS Rp
44 1 BH PASANGAN LAMPU LED PANEL 6 WATT ( WHITE ) PHILIPS Rp
45 1 BH PASANGAN LAMPU LED PANEL 6 WATT (WARM WHITE) PHILIPS Rp
46 1 M2 PASANGAN BATU PALIMANAN Rp
47 1 M2 PASANGAN GRANIT POLISH 60 X 60 CM DURAFLOOR Rp
48 1 M2 PASANG LANTAI GRANIT UNPOLISH 40 X 40 CM DURAFLOOR Rp
49 1 M2 PASANG DINDING GRANIT KM/WC 30 X 60 CM DURAFLOOR Rp
50 1 M2 PASANG PLINT GRANIT 10 X 60 CM DURAFLOOR Rp
DAFTAR ANALISA PEKERJAAN

I HARGA SATUAN PEKERJAAN PERSIAPAN (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PAGAR SEMENTARA DARI KAYU TINGGI 2 METER
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0200
JUMLAH TENAGA KERJA
B. BAHAN
Dolken kayu Ø 8-10/400 cm Batang 1.250
Semen portland (Gersik) Kg 5.000
Pasir beton m3 0.005
Koral beton m3 0.009
Kayu 5/7 m3 0.072
paku biasa 2"-5" Kg 0.060
Residu Liter 0.400
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M2 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.200
Tukang Kayu OH 0.400
Kepala Tukang OH 0.020
Mandor OH 0.020
JUMLAH TENAGA KERJA
B. BAHAN
Dolken kayu Ø 8-10/400 cm Batang 1.250
Semen portland (Gersik) kg 2.50
Seng gelombang Lbr 1.20
Pasir Beton m3 0.005
Koral beton m3 0.009
Kayu 5/7 m3 0.072
Paku biasa 2" - 5" kg 0.060
Meni Besi Liter 0.45
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
3 1 M2 PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 METER
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.200
Tukang kayu OH 0.300
Kepala tukang OH 0.020
Mandor OH 0.020
JUMLAH TENAGA KERJA
B. BAHAN
Dolken kayu Ø 8 -10/ 400 cm Batang 1.00
Semen portland (Gersik) Kg 2.000
Kawat duri M' 25.000
Pasir beton m3 0.005
Koral beton m3 0.009
Paku biasa 2" - 5" Kg 0.060

JUMLAH HARGA BAHAN


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

4 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.10
Tukang kayu OH 0.10
Kepala tukang OH 0.01
Mandor OH 0.005
JUMLAH TENAGA KERJA
B. BAHAN
Kayu balok 5/7 m3 0.012
Paku 2" - 3" Kg 0.02
Kayu Papan 3/20 m3 0.007
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
5 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.00
Tukang kayu OH 2.00
Tukang batu OH 1.00
Kepala tukang OH 0.30
Mandor OH 0.05
JUMLAH TENAGA KERJA
B. BAHAN
Dolken Kayu Ø 8 - 10/400 cm Batang 1.250
Kayu m3 0.180
Paku Biasa kg 0.850
Besi Strip kg 1.100
Semen portland (Gersik) kg 35.000
Pasir Pasang m3 0.150
Pasir Beton m3 0.100
Koral Beton m3 0.150
Bata Merah bh 30.000
Seng Plat lbr 0.250
Jendela Nako bh 0.200
Kaca Polos m2 0.080
Kunci Tanam bh 0.150
Plywood 4 mm lbr 0.060
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.00
Tukang Kayu OH 2.00
Kepala Tukang OH 0.20
Mandor OH 0.05
JUMLAH TENAGA KERJA
B. BAHAN
Dolken kayu diameter 8-10/400 cm btg 1.70
Kayu Meranti m3 0.210
Paku Biasa 2" - 5" kg 0.300
Semen portland (Gersik) kg 10.50
Pasir Beton m3 0.03
Koral Beton m3 0.05
Seng gelombang BJLS 30 lbr 1.50
Seng Pelat Lbr 0.250
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
7 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.00
Tukang kayu OH 1.50
Kepala tukang OH 0.15
Mandor OH 0.05
JUMLAH TENAGA KERJA
B. BAHAN
Dolken kayu Ø 8-10/400 cm Batang 3.00
Kayu m3 0.276
Paku Biasa Kg 0.700
Seng gelombang Kg 1.500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.10
Mandor OH 0.05
JUMLAH TENAGA KERJA
B. BAHAN

JUMLAH HARGA BAHAN


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
9 1 M2 PEMBUATAN BEDENG BURUH
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.00
Tukang Kayu OH 1.00
Kepala tukang OH 0.20
Mandor OH 0.05
JUMLAH TENAGA KERJA
B. BAHAN
Dolken kayu Ø 8-10/400 cm Batang 1.25
Kayu m3 0.186
Paku Biasa kg 0.300
Semen portland (Gersik) kg 18.00
Pasir Beton m3 0.03
Koral Beton m3 0.05
Seng gelombang lbr 1.50
Plywood 4 mm lbr 1.350
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

10 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X25) CM


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Tukang Kayu OH 0.30
Kepala tukang OH 0.03
JUMLAH TENAGA KERJA
B. BAHAN
Kayu papan kelas III m3 0.036
Kayu balok 5/7 kelas III m3 0.014
Paku Biasa kg 0.08
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
11 1 M2 PEMBUATAN STEGGER DARI BAMBU
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.00
Tukang kayu OH 2.00
Kepala Tukang OH 0.20
Mandor OH 0.05
JUMLAH TENAGA KERJA
B. BAHAN
Bambu diameter 6-8/600 cm btg 1.25
Tali ijuk m3 0.186
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

12 1 M2 PEMBUATAN JALAN SEMENTARA


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.000
Mandor OH 0.005
JUMLAH TENAGA KERJA
B. BAHAN
Batu Kali m3 0.150
Batu Pecah 5 - 7 m3 0.090
Pasir Pasang m3 0.010
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

13 1 M3 BONGKARAN BETON BERTULANG


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 13.334
Mandor OH 0.666
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
14 1 M3 BONGKARAN DINDING TEMBOK BATA
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 6.667
Mandor OH 0.333
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

15 1 M2 PEMASANGAN PAGAR KAWAT JARING GALVANIS PANJANG 240 CM


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.042
Tukang Besi OH 0.004
Kepala Tukang OH 0.002
Mandor OH 0.042
JUMLAH TENAGA KERJA
B. BAHAN
Kawat Jaring ' Lbr 0.1434

JUMLAH HARGA BAHAN


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

16 BONGKAR 1 M3 BETON SECARA KONVENSIONAL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 3.600
Mandor OH 0.360
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
II HARGA SATUAN PEKERJAAN TANAH (PERMEN PUPR 28/PRT/M/2016)
1 1 M3 GALIAN TANAH BIASA DALAM 1 METER
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.750
Mandor OH 0.025
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M3 GALIAN TANAH BIASA DALAM 2 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.900
Mandor OH 0.045
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 1 M3 GALIAN TANAH BIASA DALAM 3 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.050
Mandor OH 0.067
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
4 1 M3 GALIAN TANAH KERAS DALAM 1METER
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.000
Mandor OH 0.032
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

5 1 M3 GALIAN TANAH CADAS DALAM 1 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Mandor OH 0.060
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATANP
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.200
Mandor OH 0.045
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.050
Mandor OH 0.005
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 1 M3 PEMBUANGAN TANAH SEJAUH 30 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.330
Mandor OH 0.010
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

9 1 M3 PENGURUGAN KEMBALI GALIAN TANAH


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.500
Mandor OH 0.050
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

10 1 M3 PEMADATAN TANAH ( Per 20 Cm )


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.500
Mandor OH 0.050
JUMLAH TENAGA KERJA
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
11 1 M3 URUGAN PASIR
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Mandor OH 0.010
JUMLAH TENAGA KERJA
B. BAHAN
Pasur Urug m3 1.200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

12 1 M2 PEMASANGAN LAPISAN IJUK TEBAL 10 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.150
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Ijuk m3 6.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2500
Mandor OH 0.0250
JUMLAH TENAGA KERJA
B. BAHAN
Sirtu m3 1.200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
15 1 M3 TIMBUNAN PASIR SEBAGAI BAHAN PENGISI
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000
Mandor OH 0.0400
JUMLAH TENAGA KERJA
B. BAHAN
Pasir Pasang M3 1.2000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

III HARGA SATUAN PEKERJAAN PONDASI (PERMEN PUPR 28/PRT/M/2016)


1 1 M3 BATU BELAH CAMP. 1 SP : 3 PP
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 0.750
Kepala Tukang OH 0.075
Mandor OH 0.075
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 1.200
Semen portland (Gersik) Kg 202.000
Pasir Pasang m3 0.485
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M3 BATU BELAH CAMP. 1 SP : 4 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 0.750
Kepala Tukang OH 0.075
Mandor OH 0.075
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 1.200
Semen portland (Gersik) Kg 163.000
Pasir Pasang m3 0.520
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
3 1 M3 BATU BELAH CAMP. 1 SP : 5 PP
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 0.750
Kepala Tukang OH 0.075
Mandor OH 0.075
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 1.200
Semen portland (Gersik) kg 136.000
Pasir Pasang m3 0.544
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

4 1 M3 BATU BELAH CAMP. 1 SP : 6 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 0.750
Kepala Tukang OH 0.075
Mandor OH 0.075
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 1.200
Semen portland (Gersik) kg 117.000
Pasir Pasang m3 0.561
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

5 1 M3 BATU BELAH CAMP. 1 SP : 8 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 0.750
Kepala Tukang OH 0.075
Mandor OH 0.075
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 1.200
Semen portland (Gersik) kg 91.000
Pasir Pasang m3 0.584
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1SP : 1KP : 2PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 0.750
Kepala Tukang OH 0.075
Mandor OH 0.075
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 1.200
Kapur kg 0.170
Semen portland (Gersik) m3 0.170
Pasir Pasang m3 0.340
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

7 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1SP : 3KP : 10PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 0.750
Kepala Tukang OH 0.075
Mandor OH 0.075
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 1.200
Semen portland (Gersik) kg 61.000
Kapur m3 0.147
Pasir Pasang m3 0.492
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
8 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1/4 SP : 1KP : 4PP
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500
Tukang Batu OH 0.750
Kepala Tukang OH 0.075
Mandor OH 0.075
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 1.200
Semen portland (Gersik) kg 41.000
Kapur m3 0.131
Pasir Pasang m3 0.523
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

9 1 M3 PASANGAN PONDASI SIKLOP, 60% BETON CAMPURAN 1 SP : 2 PB : 3 KR DAN 40% BATU BELAH
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 3.400
Tukang Batu OH 0.850
Kepala Tukang OH 0.085
Mandor OH 0.170
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 0.480
Semen portland (Gersik) kg 194.000
Pasir Beton m3 0.312
Koral Beton m3 0.468
Besi Beton kg 126.000
Kawat Beton kg 1.800
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
10 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.400
Tukang Batu OH 0.800
Kepala Tukang OH 0.080
Mandor OH 0.119
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 0.4500
Semen portland (Gersik) kg 194.0000
Pasir Beton m3 0.3120
Koral Beton m3 0.4680
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

11 1 M3 PASANGAN BATU KOSONG


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.780
Tukang Batu OH 0.390
Kepala Tukang OH 0.039
Mandor OH 0.039
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah m3 1.200
Pasir Urug m3 0.432
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

IV PEKERJAAN DINDING (PERMEN PUPR 28/PRT/M/2016))


1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000
Semen kg 18.950
Pasir Pasang m3 0.038
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000
Semen kg 14.370
Pasir Pasang m3 0.040
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 4 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000
Semen kg 11.500
Pasir Pasang m3 0.043
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

4 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000
Semen kg 9.680
Pasir Pasang m3 0.045
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

5 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000
Semen kg 8.320
Pasir Pasang m3 0.049
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 8 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000
Semen kg 6.500
Pasir Pasang m3 0.050
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

7 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SP : 3 KP : 10 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000
Semen Portland (Gersik) kg 4.500
Kapur Padam m3 0.015
Pasir Pasang m3 0.050
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SP : 3 KP : 10 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000
Semen Portland (Gersik) kg 4.500
Kapur Padam m3 0.015
Pasir Pasang m3 0.050
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SM : 1 KP : 2 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000
Semen Merah kg 0.014
Kapur Padam m3 0.014
Pasir Pasang m3 0.028
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

10 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 2 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.030
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000
Semen Portland (Gersik) kg 44.5
Pasir Pasang m3 0.08
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

11 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 3 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.030
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000
Semen Portland (Gersik) kg 32.950
Pasir Pasang m3 0.091
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

12 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 4 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.030
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000
Semen Portland (Gersik) kg 26.550
Pasir Pasang m3 0.093
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

13 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 5 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.030
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000
Semen Portland (Gersik) kg 22.200
Pasir Pasang m3 0.102
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
14 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 6 PP
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.030
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000
Semen Portland (Gersik) kg 18.500
Pasir Pasang m3 0.122
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

15 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 3 KP : 10 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.030
JUMLAH TENAGA KERJA
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000
Semen Portland (Gersik) kg 10.080
Kapur padam m3 0.0275
Pasir Pasang m3 0.0925
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

16 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 20), campuran spesi 1 pc : 3 ps


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
HB-20 bh 12.5000
Semen Portland (Gersik) Kg 30.320
Pasir Pasang m3 0.7280
Besi Beton 8 mm kg 0.2800
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

17 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 20), campuran spesi 1 psp : 4 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
HB-20 bh 12.5000
Semen Portland (Gersik) Kg 24.260
Pasir Pasang m3 0.7720
Besi Beton 8 mm kg 0.2800
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

18 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 15), campuran spesi 1 psp : 3 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
HB-15 bh 22.7400
Semen Portland (Gersik) Kg 22.740
Pasir Pasang m3 0.550
Besi Beton 8 mm kg 0.2800
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

19 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 15), campuran spesi 1 psp : 4 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
HB-15 bh 12.5000
Semen Portland (Gersik) Kg 7.500
Pasir Pasang m3 0.027
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

20 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran spesi 1 psp : 3 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
HB-15 bh 12.5000
Semen Portland (Gersik) Kg 15.160
Pasir Pasang m3 0.364
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

21 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran spesi 1 psp : 4 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
HB-15 bh 12.5000
Semen Portland (Gersik) Kg 15.160
Pasir Pasang m3 0.364
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

22 1 M2 PASANGAN DINDING Bata Berongga Ekspose (12 x 11 x 24) CM camp 1 Pc : 3 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Bata berongga bh 30.000
Semen Portland (Gersik) kg 11.000
Pasir Pasang m3 0.035
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
V PEKERJAAN PLESTERAN (PERMEN PUPR 28/PRT/M/2016)
1 1 M2 PLESTERAN CAMP. 1 PC : 1 PP TEBAL 15 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 15.504
Pasir Pasang m3 0.016
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 10.224
Pasir Pasang m3 0.020
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 7.776
Pasir Pasang m3 0.023
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 6.240
Pasir Pasang m3 0.024
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 5.184
Pasir Pasang m3 0.026
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 4.416
Pasir Pasang m3 0.027
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
7 1 M2 PLESTERAN CAMP. 1 PC : 7 PS TEBAL 15 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 3.936
Pasir Pasang m3 0.028
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 3.456
Pasir Pasang m3 0.029
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

9 1 M2 PLESTERAN CAMP. 1 PC : 2PP TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.400
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.022
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) Kg 13.632
Pasir Pasang m3 0.027
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
10 1 M2 PLESTERAN CAMP. 1 PC : 3PS TEBAL 20 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.260
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.013
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 10.368
Pasir Pasang m3 0.031
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

11 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0130
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 10.3680
Pasir Pasang m3 0.0310
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

12 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.400
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.022
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 8.320
Pasir Pasang m3 0.032
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
13 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0220
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 6.9120
Pasir Pasang m3 0.0350
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

14 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0220
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 5.8880
Pasir Pasang m3 0.0360
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

15 1 M2 PLESTERAN CAMP. 1 PC : 1 KP : 2 PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0220
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 5.8880
Pasir Pasang m3 0.0360
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
16 1 M2 PLESTERAN BERAPEN 1 PS : 5PP TEBAL 15 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.150
Tukang Batu OH 0.075
Kepala Tukang OH 0.008
Mandor OH 0.008
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 5.184
Pasir Pasang m3 0.026
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

17 1 M' PLESTERAN SKONING 1 PC : 3 PS, TEBAL 10 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.080
Tukang Batu OH 0.400
Kepala Tukang OH 0.040
Mandor OH 0.004
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 0.500
Pasir Pasang m3 0.013
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

18 1 M2 PLESTERAN GRANIT 1 SP : 2 GRANIT TEBAL 1 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.450
Tukang Batu OH 0.225
Kepala Tukang OH 0.023
Mandor OH 0.023
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) Kg 10.000
Batu Granit Kg 15.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
19 1 M2 PLESTERAN TRASO 1 SP : 2 TRASO TEBAL 1 CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.450
Tukang Batu OH 0.225
Kepala Tukang OH 0.023
Mandor OH 0.023
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) Kg 10.000
Batu Granit Kg 15.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

20 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 4.320
Pasir Pasang m3 0.006
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

21 1 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.150
Tukang Batu OH 0.075
Kepala Tukang OH 0.008
Mandor OH 0.008
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 3.108
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
22 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.070
Tukang Batu OH 0.035
Kepala Tukang OH 0.004
Mandor OH 0.004
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 1.600
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

23 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300
Tukang Batu OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 6.340
Pasir Pasang m3 0.012
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

24 1 M2 PEKERJAAN ACIAN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.200
Tukang Batu OH 0.100
Kepala Tukang OH 0.01
Mandor OH 0.01
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 3.25
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
VI PEKERJAAN KAYU (PERMEN PUPR 28/PRT/M/2016)
1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 7.0000
Tukang kayu OH 21.0000
Kepala Tukang OH 2.1000
Mandor OH 0.3500
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Jati m3 1.1000
Paku 10 Cm Kg 1.2500
Lem Kayu Kg 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS III
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 6.0000
Tukang kayu OH 18.0000
Kepala Tukang OH 1.8000
Mandor OH 0.3000
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kruing m3 1.2000
Paku 10 Cm Kg 1.2500
Lem Kayu Kg 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3500
Tukang kayu OH 1.0500
Kepala Tukang OH 0.1050
Mandor OH 0.0180
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0400
Paku 5-7 Cm Kg 0.0500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3500
Tukang kayu OH 1.0500
Kepala Tukang OH 0.1050
Mandor OH 0.0180
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kruing m3 0.0400
Paku 5-7 Cm Kg 0.0500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000
Tukang kayu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.0500
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0400
Lem Kayu Kg 0.5000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8000
Tukang kayu OH 2.4000
Kepala Tukang OH 0.2400
Mandor OH 0.0400
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0240
Lem Kayu Kg 0.3000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS II
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000
Tukang kayu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.0500
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0640
Lem Kayu Kg 0.5000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA TERTUTUP, KAYU KELAS II (Lebar Sampai 90 Cm)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7000
Tukang kayu OH 2.1000
Kepala Tukang OH 0.2100
Mandor OH 0.0350
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0250
Paku 1-2,5 Cm Kg 0.0300
Lem Kayu Kg 0.5000
Plywood 4 mm Lbr 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

9 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8000
Tukang kayu OH 2.4000
Kepala Tukang OH 0.2400
Mandor OH 0.0400
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0256
Paku 1-2,5 Cm Kg 0.0300
Lem Kayu Kg 0.5000
Plywood 4 mm Lbr 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS II
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6700
Tukang kayu OH 2.0000
Kepala Tukang OH 0.2000
Mandor OH 0.3350
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0600
Paku 1-2,5 Cm Kg 0.1500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8000
Tukang kayu OH 2.4000
Kepala Tukang OH 0.2400
Mandor OH 0.0400
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Jati m3 0.0250
Paku 1-2,5 Cm Kg 0.0300
Lem Kayu Kg 0.3000
Teakwood 4 mm uk 90x220 cm Lbr 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

12 MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8500
Tukang kayu OH 2.5500
Kepala Tukang OH 0.2550
Mandor OH 0.0430
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0250
Paku 1-2,5 Cm Kg 0.0300
Lem Kayu Kg 0.8000
Teakwood 4 mm uk 90x220 cm Lbr 1.0000
Formika Lbr 0.5000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

13 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS II Bentang 6 M'


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 4.0000
Tukang kayu OH 12.0000
Kepala Tukang OH 1.2000
Mandor OH 0.2000
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kamper m3 1.1000
Besi Strip Tebal 5 cm Kg 15.0000
Paku 12 Cm Kg 5.6000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 6.7000
Tukang kayu OH 20.1000
Kepala Tukang OH 2.0100
Mandor OH 0.3350
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Jati m3 1.2000
Besi Strip Tebal 5 cm Kg 15.0000
Paku 12 Cm Kg 5.6000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.4000
Tukang kayu OH 7.2000
Kepala Tukang OH 0.7200
Mandor OH 0.1200
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Jati m3 1.1000
Besi Strip Tebal 5 cm Kg 15.0000
Paku 12 Cm Kg 3.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000
Tukang kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Kaso-Kaso ( 5 x 7 ) Cm m3 0.0140
Reng ( 2 x 3 ) Cm m3 0.0036
Paku 5 Cm dan 10 Cm Kg 0.2500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000
Tukang kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Kaso-Kaso ( 5 x 7 ) Cm m3 0.0140
Reng ( 2 x 3 ) Cm Kg 0.0072
Paku 5 Cm dan 10 Cm Kg 0.2500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

18 MEMASANG 1 M2 USUK EXPOSE KAYU KLS I KAMPER


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000
Tukang kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Usuk ( 5 x 7 ) Cm m3 0.0105
Paku 5 Cm dan 10 Cm Kg 0.2500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
19 MEMASANG 1 M2 RENG KAYU KLS I KAMPER
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000
Tukang kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Reng ( 2 x 3 ) Cm m3 0.0036
Paku 5 Cm dan 10 Cm Kg 0.2500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

20 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1200
Tukang kayu OH 0.1200
Kepala Tukang OH 0.0120
Mandor OH 0.0060
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kamper m3 0.1650
Paku 5 Cm dan 10 Cm Kg 0.2000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

21 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Tukang kayu OH 0.3000
Kepala Tukang OH 0.0300
Mandor OH 0.0750
JUMLAH TENAGA KERJA
B. BAHAN
Kaso-Kaso ( 5 x 7 ) Cm m3 0.0154
Paku 7 Cm dan 10 Cm Kg 0.2000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
22 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000
Tukang kayu OH 0.3000
Kepala Tukang OH 0.0300
Mandor OH 0.0100
JUMLAH TENAGA KERJA
B. BAHAN
Kaso-Kaso ( 5 x 7 ) Cm m3 0.0163
Paku 7 Cm dan 10 Cm Kg 0.2500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

23 MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000
Tukang kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0108
Paku 7 Cm dan 10 Cm Kg 0.1000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

24 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000
Tukang kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0110
Paku 7 Cm dan 10 Cm Kg 0.0500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
25 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Tukang kayu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0080
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kamper m3 0.0280
Paku 5 Cm dan 7 Cm Kg 0.1500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

26 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Tukang kayu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0080
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kamper m3 0.0280
Paku 5 Cm dan 7 Cm Kg 0.1500
Teakwood 4 mm uk 90x220 cm Lbr 0.8600
Lem Kayu Kg 0.5600
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

27 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000
Tukang kayu OH 0.6000
Kepala Tukang OH 0.0600
Mandor OH 0.0100
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kamper m3 0.0280
Paku 5 Cm dan 7 Cm Kg 0.1500
Plywood tebal 4 mm uk 120 x 240 cm Lbr 0.8600
Lem Kayu Kg 0.5600
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
28 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA HOLO
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Tukang kayu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0080
JUMLAH TENAGA KERJA
B. BAHAN
Rangka Holo Btg 1.5000
Paku 5 Cm dan 7 Cm Kg 0.1500
Teakwood 4 mm uk 90x220 cm Lbr 0.8600
Lem Kayu Kg 0.5600
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

29 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA HOLO


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000
Tukang kayu OH 0.6000
Kepala Tukang OH 0.0600
Mandor OH 0.0100
JUMLAH TENAGA KERJA
B. BAHAN
Rangka Holo Btg 1.5000
Paku 5 Cm dan 7 Cm Kg 0.1500
Plywood tebal 4 mm uk 120 x 240 cm Lbr 0.8600
Lem Kayu Kg 0.5600
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

30 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6000
Tukang kayu OH 1.8000
Kepala Tukang OH 0.1800
Mandor OH 0.0300
JUMLAH TENAGA KERJA
B. BAHAN
Papan Kayu Kamper m3 0.0070
Paku 5 Cm dan 10 Cm Kg 0.1000
Paku Skrup 10 cm Kg 0.1500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

31 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0250
Tukang kayu OH 0.0750
Kepala Tukang OH 0.0080
Mandor OH 0.0010
JUMLAH TENAGA KERJA
B. BAHAN
Plywood tebal 4 mm uk 120 x 240 cm Lbr 0.4000
Paku 1 Cm dan 2.5 Cm Kg 0.0500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

VII PEKERJAAN BETON ( PERMEN PUPR 28/PRT/M/2016))


1 MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c = 0,87
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650
Tukang Batu OH 0.275
Kepala Tukang OH 0.028
Mandor OH 0.083
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 247.000
Pasir Beton kg 869
Koral Beton kg 999
Air Liter 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 MEMBUAT 1 M³ BETON MUTU f'C= 9,8 Mpa (K125), Slump (12 ± 2)cm, w/c = 0,78
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650
Tukang Batu OH 0.275
Kepala Tukang OH 0.028
Mandor OH 0.083
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 276.000
Pasir Beton kg 828
Koral Beton kg 1,012
Air lt 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0830
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 299.0000
Pasir Beton kg 799
Koral Beton kg 1,017
Air lt 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

4 MEMBUAT 1 M³ LANTAI KERJA BETON MUTU F'C = 7,4 MPA SLUMP (3-6)CM, W/C =0.87
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.200
Tukang Batu OH 0.200
Kepala Tukang OH 0.020
Mandor OH 0.060
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 230.0000
Pasir Beton kg 893
Koral Beton kg 1,027
Air lt 200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
5 MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c = 0,66
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650
Tukang Batu OH 0.275
Kepala Tukang OH 0.028
Mandor OH 0.083
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 326.0000
Pasir Beton kg 760
Koral Beton kg 1,029
Air liter 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 MEMBUAT 1 M³ BETON MUTU f'C= 16,9 Mpa (K200), Slump (12 ± 2)cm, w/c = 0,61
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650
Tukang Batu OH 0.275
Kepala Tukang OH 0.028
Mandor OH 0.083
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 352.0000
Pasir Beton kg 731
Koral Beton kg 1,031
Air liter 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

7 MEMBUAT 1 M³ BETON MUTU f'C= 19,3 Mpa (K225), Slump (12 ± 2)cm, w/c = 0,58
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650
Tukang Batu OH 0.275
Kepala Tukang OH 0.028
Mandor OH 0.083
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 371.000
Pasir Beton kg 698
Koral Beton kg 1,047
Air lietr 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650
Tukang Batu OH 0.275
Kepala Tukang OH 0.028
Mandor OH 0.083
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 384.000
Pasir Beton kg 692
Koral Beton kg 1,039
Air liter 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

9 MEMBUAT 1 M³ BETON MUTU f'C= 24,0 Mpa (K275), Slump (12 ± 2)cm, w/c =0,53
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650
Tukang Batu OH 0.275
Kepala Tukang OH 0.028
Mandor OH 0.083
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 406.000
Pasir Beton kg 684
Koral Beton kg 1,026
Air Liter 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

10 MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650
Tukang Batu OH 0.275
Kepala Tukang OH 0.028
Mandor OH 0.083
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 413.000
Pasir Beton kg 681
Koral Beton kg 1,021
Air liter 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

11 MEMBUAT 1 M³ BETON MUTU f'C= 28,8 Mpa (K325), Slump (12 ± 2)cm, w/c =0,49
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.100
Tukang Batu OH 0.350
Kepala Tukang OH 0.035
Mandor OH 0.105
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 439.0000
Pasir Beton kg 670
Koral Beton kg 1,006
Air lt 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

12 MEMBUAT 1 M³ BETON MUTU f'C= 31,2 Mpa (K350), Slump (12 ± 2)cm, w/c =0,48
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.100
Tukang Batu OH 0.350
Kepala Tukang OH 0.035
Mandor OH 0.105
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland (Gersik) kg 448.0000
Pasir Beton kg 667
Koral Beton kg 1,000
Air liter 215
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

13 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.070
Tukang Besi OH 0.070
Kepala Tukang OH 0.007
Mandor OH 0.004
JUMLAH TENAGA KERJA
B. BAHAN
Besi Beton (Polos/ Ulir) kg 10.500
Kawat Beton kg 0.150
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
Harga Satuan Pekerjaan untuk 1 Kg

14 PEMBESIAN 10 KG kabel prategang (prestressed) polos/strands


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.050
Tukang Besi OH 0.050
Kepala Tukang OH 0.005
Mandor OH 0.003
JUMLAH TENAGA KERJA
B. BAHAN
Besi Beton (Polos/ Ulir) kg 10.500
Kawat Beton kg 0.100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
Harga Satuan Pekerjaan untuk 1 Kg

15 PEMBESIAN 10 KG DENGAN BESI POLOS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0700
Tukang Besi OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Besi Beton (Polos/ Ulir) kg 10.5000
Kawat Beton m3 0.1500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
Harga Satuan Pekerjaan untuk 1 Kg

16 Pemasangan 10 Kg jaring kawat baja (wiremesh)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.025
Tukang Besi OH 0.025
Kepala Tukang OH 0.025
Mandor OH 0.001
JUMLAH TENAGA KERJA
B. BAHAN
Jaring kawat baja dilas kg 10.200
Kawat Beton kg 0.0500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
17 1 M2 PASANG BEKISTING UNTUK PONDASI
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.520
Tukang Kayu OH 0.260
Kepala Tukang OH 0.026
Mandor OH 0.026
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III m3 0.040
Paku Biasa 5 - 10 cm kg 0.300
Minyak Bekisting ltr 0.100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

18 1 M2 PASANG BEKISTING UNTUK SLOOF


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.5200
Tukang Kayu OH 0.2600
Kepala Tukang OH 0.0260
Mandor OH 0.0260
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III m3 0.045
Paku Biasa 5cm - 10cm kg 0.300
Minyak Bekisting ltr 0.100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

19 1 M2 PASANG BEKISTING UNTUK KOLOM


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.660
Tukang Kayu OH 0.330
Kepala Tukang OH 0.033
Mandor OH 0.033
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III m3 0.040
Paku Biasa 5cm - 12cm kg 0.400
Minyak Bekisting ltr 0.200
Balok kayu kelas II m3 0.015
Plywood tebal 9 mm lbr 0.350
Dolken Kayu 8 - 10 cm /4 m Batang 2.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

20 1 M2 PASANG BEKISTING UNTUK BALOK


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.660
Tukang Kayu OH 0.330
Kepala Tukang OH 0.033
Mandor OH 0.033
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III m3 0.040
Paku Biasa 5 cm - 12 cm kg 0.400
Minyak Bekisting ltr 0.200
Balok kayu kelas II m3 0.018
Plywood tebal 9 mm lbr 0.350
Dolken Kayu Ø (8 - 10)cm /4 m btg 2.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

21 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.660
Tukang Kayu OH 0.330
Kepala Tukang OH 0.033
Mandor OH 0.033
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III m3 0.040
Paku Biasa 5cm - 12cm kg 0.400
Minyak Bekisting ltr 0.200
Balok kayu kelas II m3 0.015
Plywood tebal 9 mm lbr 0.350
Dolken Kayu Ø( 8 - 10) cm /4 m btg 6.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
22 1 M2 PASANG BEKISTING UNTUK DINDING
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6600
Tukang Kayu OH 0.3300
Kepala Tukang OH 0.0330
Mandor OH 0.0330
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III m3 0.030
Paku Biasa 5cm - 12 cm kg 0.400
Minyak Bekisting ltr 0.200
Balok kayu kelas II m3 0.020
Plywood tebal 9 mm lbr 0.350
Dolken Kayu Ø ( 8 - 10)cm/4 m btg 3.000
Formite/penjaga jarak bekisting/spacer Bh 4.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

23 1 M2 PASANG BEKISTING UNTUK TANGGA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6600
Tukang Kayu OH 0.3300
Kepala Tukang OH 0.0330
Mandor OH 0.0330
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III m3 0.030
Paku Biasa 5cm - 12 cm kg 0.400
Minyak Bekisting ltr 0.150
Balok kayu kelas II m3 0.015
Plywood tebal 9 mm lbr 0.350
Dolken Kayu Ø (8 - 10)cm /4 m btg 2.000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
24 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.150
Tukang Kayu OH 0.050
Kepala Tukang OH 0.005
Mandor OH 0.008
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III (papan) m3 0.0264
Paku Biasa 5 cm - 12 cm kg 0.600
Dolken Kayu Ø (8 - 10) cm /4 m btg 0.500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

25 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.180
Tukang Batu OH 0.020
Tukang Kayu OH 0.020
Tukang Besi OH 0.020
Kepala Tukang OH 0.006
Mandor OH 0.009
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III m3 0.002
Paku Biasa 5cm - 12cm kg 0.010
Minyak bekisting Liter
Besi Beton polos kg 3.000
Kawat Beton kg 0.450
Semen Portland ( Gersik) kg 4.000
Pasir Beton m3 0.006
Koral Beton m3 0.009
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
26 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.297
Tukang Batu OH 0.033
Tukang Kayu OH 0.033
Tukang Besi OH 0.033
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III m3 0.003
Paku Biasa 5 cm - 12 cm kg 0.020
Minyak bekisting Liter
Besi Beton Polos kg 3.600
Kawat Beton kg 0.050
Semen kg 5.500
Pasir Beton m3 0.009
Koral Beton m3 0.015
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

27 1 M2 BEKISTING DINDING BETON BIASA DENGAN MULTIFLEX 12 mm *2 kali pakai*


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2400
Tukang Kayu OH 0.1200
Kepala Tukang OH 0.0120
Mandor OH 0.0240
JUMLAH TENAGA KERJA
B. BAHAN
Multiflex 12 mm Lbr 0.2030
Kaso 5/7 cm M3 0.0090
Paku 5 cm dan 7 cm Kg 0.2400
Minyak Bekisting L 0.2000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
28 1 M2 BEKISTING PONDASI DAN SLOOF BETON BIASA MENGGUNAKAN PAPAN 3/20 CM *2 kali pakai*
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0300
JUMLAH TENAGA KERJA
B. BAHAN
Papan 3/20 cm Kayu Kelas II Lbr 0.0220
Kaso 5/7 cm M3 0.0160
Paku 5 cm dan 7 cm Kg 0.2400
Minyak Bekisting L 0.2000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

29 1 M2 PERANCAH/PENYOKONG BEKISTING DINDING BETON MENGGUNAKAN KAYU 5/7 ,Tinggi Maks 2,5 m *2 kali pakai*
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3600
Tukang Kayu OH 0.1800
Kepala Tukang OH 0.0180
Mandor OH 0.0360
JUMLAH TENAGA KERJA
B. BAHAN
Kaso 5/7 cm M3 0.0170
Paku 5 cm dan 7 cm Kg 0.2400
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

1 M2 PERANCAH/PENYOKONG BEKISTING PONDASI DAN SLOOF BETON MENGGUNAKAN KAYU 5/7 ,Tinggi Maks 2,0 m *2 kali
30
pakai*
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0200
JUMLAH TENAGA KERJA
B. BAHAN
Kaso 5/7 cm M3 0.0190
Paku 5 cm dan 7 cm Kg 0.2500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
VIII HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM (PERMEN PUPR 28/PRT/M/2016)
1 1 KG PEMASANGAN BESI PROFIL
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.060
Tukang las konstruksi OH 0.060
Kepala tukang OH 0.006
Mandor OH 0.003
JUMLAH TENAGA KERJA
B. BAHAN
Besi Profil Kg 1.150

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 KG PEMASANGAN RANGKA KUDA-KUDA BAJA IWF


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.060
Tukang las konstruksi OH 0.060
Kepala tukang OH 0.006
Mandor OH 0.003
JUMLAH TENAGA KERJA
B. BAHAN
Besi baja IWF Kg 1.150

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 100 KG PENGERJAAN PEKERJAAN PERAKITAN


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.060
Tukang las konstruksi OH 0.060
Kepala tukang OH 0.006
Mandor OH 0.003
JUMLAH TENAGA KERJA
B. BAHAN
Besi baja IWF Kg 1.150

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

4 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1 X40.40.2MM, MODUL 60 X 120 CM, UNTUK PLAFON
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.350
Tukang besi OH 0.350
Kepala Tukang OH 0.035
Mandor OH 0.018
JUMLAH TENAGA KERJA
B. BAHAN
Rangka metal hollow 40.40.2 mm m 4.000
Assesoris (perkuatan, las dll) Ls 100% x rangka

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

IX PEKERJAAN PENUTUP ATAP (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Tukang Kayu OH 0.0750
Kepala Tukang OH 0.0080
Mandor OH 0.0080
JUMLAH TENAGA KERJA
B. BAHAN
Genteng Plentong bh 25.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Tukang Kayu OH 0.0750
Kepala Tukang OH 0.0080
Mandor OH 0.0080
JUMLAH TENAGA KERJA
B. BAHAN
Genteng Plentong dicat bh 25.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0020
JUMLAH TENAGA KERJA
B. BAHAN
Bubungan Plentong bh 5.0000
Semen kg 10.8000
Pasir Pasang m3 0.0320
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1400
Tukang Kayu OH 0.0670
Kepala Tukang OH 0.0070
Mandor OH 0.0070
JUMLAH TENAGA KERJA
B. BAHAN
Asbes Gelombang 1.8 mx0.92mx5mm lbr 0.6600
Paku Pancing 60 x 230 kg 2.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0840
Tukang Kayu OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Bubungan Stel Gelombang lbr 2.4000
Paku Skrup 3,5" kg 4.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
6 1 M2 PASANGAN LAPISAN ALUMINIUM FOIL
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0330
Tukang Kayu OH 0.0330
Kepala Tukang OH 0.0030
Mandor OH 0.0020
JUMLAH TENAGA KERJA
B. BAHAN
Aluminium Foil m2 1.1000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

7 1 M1 PASANG NOK SENG GELOMBANG


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Tukang Kayu OH 0.0700
Kepala Tukang OH 0.0080
Mandor OH 0.0060
JUMLAH TENAGA KERJA
B. BAHAN
Seng Plat 3" x 6" BJLS 28 lbr 0.3000
Paku biasa 1/2" - 1" kg 0.0400
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 1 BH PEKERJAAN PASANGAN IKUT CELEDU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0500
Mandor OH 0.0250
JUMLAH TENAGA KERJA
B. BAHAN
Ikut celedu bh 1.0000
Semen kg 0.0130
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
9 1 BH PEKERJAAN PASANGAN MURDHA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0500
Mandor OH 0.0250
JUMLAH TENAGA KERJA
B. BAHAN
Murda bh 1.0000
Semen kg 0.0130
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

X PEKERJAAN PLAFOND / LANGIT - LANGIT (PERMEM PUPR 28/PRT/M/2016))


1 MEMASANG 1 M2 LANGIT-LANGIT ASBES SEMEN, TEBAL 4 MM, 5 MM DAN 6 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0300
Tukang Kayu OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Asbes Semen lbr 1.1000
Paku biasa 1/2" - 1" kg 0.0100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/3 MM, 4MM, 6MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
TRIIPLEKS lbr 0.3750
Paku biasa 1/2" - 1" kg 0.0300
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8000
Tukang Kayu OH 0.8000
Kepala Tukang OH 0.0800
Mandor OH 0.0400
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Papan Kamper m3 0.0150
Paku biasa 1/2" - 1" kg 0.0100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 1 M2 PLAFOND GYPSUM, RANGKA KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Kayu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
Gypsum Board (120x240x9) Lbr 0.3640
Kayu Kruing Usuk M3 0.0230
Paku Kalsiboard Kg 0.2600
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

9 1 M2 PLAFOND GYPSUM, RANGKA HOLO


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100
Tukang Kayu OH 0.050
Kepala Tukang OH 0.005
Mandor OH 0.005
JUMLAH TENAGA KERJA
B. BAHAN
Gypsum Board (120x240x9) Lbr 0.3640
Hollow Galvalume 4x4 m' 2.4000
Hollow Galvalume 2x4 m' 3.3000
Paku Kalsiboard Kg 0.1100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
10 1 M2 PLAFOND KALSIBOARD, RANGKA KAYU
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Kayu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
Kalsiboard (4,5 x 1220 x 2420) mm Lbr 0.3640
Kayu Kruing Usuk M3 0.0230
Paku Kalsiboard Kg 0.2600
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

11 1 M2 PLAFOND KALSIBOARD, RANGKA HOLO


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000
Tukang Kayu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
Kalsiboard (4,5 x 1220 x 2420) mm Lbr 0.3640
- M3 1.0000
Paku Kalsiboard Kg 0.1100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

XI PEKERJAAN SANITASI ( PERMEN PUPR 28/PRT/M/2016) )


1 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 "
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0540
Tukang Pipa OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0270
JUMLAH TENAGA KERJA
B. BAHAN
Pipa Galvanis m' 1.2000
Perlengkapan 35% x harga pipa
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
2 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3"
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1080
Tukang Pipa OH 0.1800
Kepala Tukang OH 0.0180
Mandor OH 0.0054
JUMLAH TENAGA KERJA
B. BAHAN
Pipa Galvanis m' 1.2000
Perlengkapan 35% x harga pipa
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5"


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0360
Tukang Pipa OH 0.0600
Kepala Tukang OH 0.0060
Mandor OH 0.0018
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC m' 1.2000
Perlengkapan 35% x harga pipa
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

4 MEMASANG 1 M1 PIPA PVC TYPE AW f 2"


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0540
Tukang Pipa OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0030
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC m' 1.2000
Perlengkapan 35% x harga pipa
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
5 MEMASANG 1 M1 PIPA PVC TYPE AW f 3"
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0810
Tukang Pipa OH 0.1350
Kepala Tukang OH 0.0135
Mandor OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC m' 1.2000
Perlengkapan 35% x harga pipa
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 MEMASANG 1 M1 PIPA PVC TYPE AW f 4"


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0810
Tukang Pipa OH 0.1350
Kepala Tukang OH 0.0135
Mandor OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC m' 1.2000
Perlengkapan 35% x harga pipa
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

XII PEKERJAAN BESI DAN ALUMINIUM (PERMEN PUPR 28/PRT/M/2016)


1 1 KG MEMASANG RANGKA BAJA IWF
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0060
Tukang besi OH 0.0600
Kepala Tukang OH 0.0060
Mandor OH 0.0003
JUMLAH TENAGA KERJA
B. BAHAN
Besi Baja WF kg 1.1500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
XII PEKERJAAN KUNCI DAN KACA PERMEN PUPR 28/PRT/M/2016)
1 1 BH PASANG KUNCI TANAM BIASA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.5000
Kepala Tukang OH 0.0500
Mandor OH
JUMLAH TENAGA KERJA
B. BAHAN
Kunci Tanam Biasa bh 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 BH PASANG ENGSEL PINTU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH
JUMLAH TENAGA KERJA
B. BAHAN
Engsel Pintu bh 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 1 BH PASANG ENGSEL JENDELA KUPU-KUPU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH
JUMLAH TENAGA KERJA
B. BAHAN
Engsel Jendela bh 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
4 1 BH PASANG KAIT ANGIN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1000
Kepala Tukang OH 0.0010
Mandor OH
JUMLAH TENAGA KERJA
B. BAHAN
Kait Angin ps 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

5 1 BH PASANG GRENDEL TANAM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.2500
Kepala Tukang OH 0.0250
Mandor OH
JUMLAH TENAGA KERJA
B. BAHAN
Grendel tanam bh 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 1 M2 PASANG KACA, TEBAL5 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1600
Tukang Besi OH 0.1600
Kepala Tukang OH 0.1600
Mandor OH 0.0080
JUMLAH TENAGA KERJA
B. BAHAN
Kaca bh 1.1000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
XIII PEKERJAAN PENUTUP LANTAI DAN DINDING (PERMEN PUPR 28/PRT/M/2016)
1 1 M2 PASANG LANTAI KERAMIK 40 X 40 CM ASIA TILE
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250
Tukang Batu OH 0.125
Kepala Tukang OH 0.013
Mandor OH 0.013
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 40 x 40 cm bh 6.63
Semen kg 9.80
Pasir Pasang m3 0.045
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 20 x 20 bh 26.5000
Semen kg 10.4000
Pasir Pasang m3 0.0450
Semen warna/semen grouting kg 1.6200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 1 M' PASANG PLINT KERAMIK UKURAN 10 CM X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09
Tukang Batu OH 0.09
Kepala Tukang OH 0.009
Mandor OH 0.005
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 40 x 40 cm bh 2.65
Semen Portland kg 1.14
Semen Warna kg 0.10
Pasir Pasang m3 0.003
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

XIV PEKERJAAN PENGECATAN (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0200
Tukang cat OH 0.0630
Kepala Tukang OH 0.0063
Mandor OH 0.0025
JUMLAH TENAGA KERJA
B. BAHAN
Plamir kg 0.1000
Cat dasar kg 0.1000
Cat Penutup 2x kg 0.2600
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN KUAS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0600
Tukang cat OH 0.0500
Kepala Tukang OH 0.0050
Mandor OH 0.0030
JUMLAH TENAGA KERJA
B. BAHAN
Cat Tembok Vinilex kg 0.2400
Kuas Bh 0.0150
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN ROLL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0400
Tukang cat OH 0.0300
Kepala Tukang OH 0.0030
Mandor OH 0.0020
JUMLAH TENAGA KERJA
B. BAHAN
Cat Tembok Vinilex kg 0.4700
Roll Bh 0.0100
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
4 1 M2 WATERPROOFING
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0150
Tukang cat OH 0.1600
Kepala Tukang OH 0.0140
Mandor OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Waterprofing dumplix 3 kg 0.4500
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

5 1 M2 PEKERJAAN PASANG WALL PAPER DENGAN PEREKAT SILK HOUSE


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0100
Tukang cat OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Wall Paper m2 1.1000
Perekat Kg 0.2000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

6 1 M2 PEKERJAAN MELAPIS MENI KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0750
Mandor OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Meni kg 0.1700
Minyak Cat ltr 0.1000
Kuas bh 0.0150
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
7 1 M2 PEKERJAAN MENDEMPUL ATAU MEMPLAMIR DAN MENGGOSOK KAYU
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang cat OH 0.1100
Kepala Tukang OH 0.0110
JUMLAH TENAGA KERJA
B. BAHAN
Dempul kayu kg 0.1500
Plamir Kayu Kg 0.0080
Minyak Cat Ltr 0.1000
Amplas Lbr 1.0000
Kuas Bh 0.0150
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

8 1 M2 PEKERJAAN PENGECATAN DASAR 1 LAPIS PADA KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang cat OH 0.0750
Kepala Tukang OH 0.0080
JUMLAH TENAGA KERJA
B. BAHAN
Cat Dasar Kg 0.1700
Minyak Cat Ltr 0.1000
Amplas Lbr 1.0000
Kuas Bh 0.0150
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

9 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Tukang cat OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0080
JUMLAH TENAGA KERJA
B. BAHAN
Cat Tembok Vinilex kg 0.3000
Minyak Cat Ltr 0.2000
Kuas Bh 0.0200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
10 1 M2 PEKERJAAN MELAPIS MENI PADA PERMUKAAN BAJA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0750
Mandor OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Meni kg 0.1000
Minyak Cat Kg 0.1000
Amplas Bh 0.5000
Kuas Bh 0.0150
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

11 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA SECARA MANUAL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500
Tukang cat OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0080
JUMLAH TENAGA KERJA
B. BAHAN
Cat Warna Zingkronasi Kg 0.2000
Minyak Cat Kg 0.1000
Kuas Bh 0.0200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

12 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA/KAYU DENGAN SEMPROT


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0200
Tukang cat OH 0.1500
Kepala Tukang OH 0.0010
Mandor OH 0.0010
JUMLAH TENAGA KERJA
B. BAHAN
Cat Warna Zingkronasi Kg 0.4000
Minyak Cat Kg 0.1000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
13 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN TEAK OIL
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang cat OH 0.1000
Kepala Tukang OH 0.0100
JUMLAH TENAGA KERJA
B. BAHAN
Teak Oil Ltr 0.3000
Amplas Lbr 0.5000
Kuas Bh 0.0150
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

14 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN POLITUR 2 LAPIS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2500
Tukang cat OH 0.2500
Kepala Tukang OH 0.0250
Mandor OH 0.0130
JUMLAH TENAGA KERJA
B. BAHAN
Wood Filler Kg 0.1000
Politur Jadi Ltr 0.2000
Amplas Lbr 1.0000
Kuas Bh 0.0200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

15 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN VERNIS 2 LAPIS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang cat OH 0.1000
Kepala Tukang OH 0.0100
JUMLAH TENAGA KERJA
B. BAHAN
Vernis Ltr 0.3000
Amplas Lbr 0.5000
Kuas Bh 0.0200
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
XVII PEKERJAAN ELEKTRIKAL (PERMEN PUPR 28/PRT/2016)
1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Biaya Pasang ttk 1.0000
JUMLAH TENAGA KERJA
B. BAHAN
Kabel NYM 3 x 2.5 mm ex. Supreme m1 8.0000
Pipa Clipsal 20 mm hitam bt 3.0000
Tee dos clipsal 20 mm hitam bh 2.0000
Klem clipsal 20 mm hitam bj 15.0000
Sock clipsal 20 mm hitam bj 3.0000
Inbow dos plastik clipsal E 157 P bj 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

2 1 TITIK INSTALASI AC
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Biaya Pasang ttk 1.0000
JUMLAH TENAGA KERJA
B. BAHAN
Kabel NYM 3 x 2.5 mm ex. Supreme m1 10.0000
Pipa Clipsal 20 mm hitam bt 3.0000
Tee dos clipsal 20 mm hitam bh 1.0000
Klem clipsal 20 mm hitam bj 15.0000
Sock clipsal 20 mm hitam bj 4.0000
Inbow dos plastik clipsal E 157 P bj 1.0000
Pipa flexible clipsal 20 mm hitam m1 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)

3 1 TITIK INSTALASI TELEPHONE


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Biaya Pasang ttk 1.0000
JUMLAH TENAGA KERJA
B. BAHAN
Kabel Telephone m1 25.0000
Pipa Clipsal 20 mm hitam bt 8.0000
Tee dos clipsal 20 mm hitam bh 1.0000
Klem clipsal 20 mm hitam bj 25.0000
Sock clipsal 20 mm hitam bj 5.0000
Inbow dos plastik clipsal E 157 P bj 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
4 1 TITIK INSTALASI MATV
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Biaya Pasang ttk 1.0000
JUMLAH TENAGA KERJA
B. BAHAN
Coaxial cable 5C-75 ohm commscof m1 20.0000
Pipa Clipsal 20 mm hitam bt 6.0000
Tee dos clipsal 20 mm hitam bh 2.0000
Klem clipsal 20 mm hitam bj 20.0000
Sock clipsal 20 mm hitam bj 6.0000
Inbow dos plastik clipsal E 157 P bj 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C)
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E)
REKAPITULASI DAFTAR HARGA SATUAN PEKERJAAN

NO URAIAN PEKERJAAN HARGA

I HARGA SATUAN PEKERJAAN PERSIAPAN (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PAGAR SEMENTARA DARI KAYU TINGGI 2 METER Rp.
2 1 M2 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER Rp.
3 1 M2 PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 METER Rp.
4 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK Rp.
5 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN Rp.
6 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT Rp.
7 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU Rp.
8 1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN Rp.
9 1 M2 PEMBUATAN BEDENG BURUH Rp.
10 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X25) CM Rp.
11 1 M2 PEMBUATAN STEGGER DARI BAMBU Rp.
12 1 M2 PEMBUATAN JALAN SEMENTARA Rp.
13 1 M3 BONGKARAN BETON BERTULANG Rp.
14 1 M3 BONGKARAN DINDING TEMBOK BATA Rp.
15 1 M2 PEMASANGAN PAGAR KAWAT JARING GALVANIS PANJANG 240 CM Rp.
16 BONGKAR 1 M3 BETON SECARA KONVENSIONAL Rp.

II HARGA SATUAN PEKERJAAN TANAH (PERMEN PUPR 28/PRT/M/2016)


1 1 M3 GALIAN TANAH BIASA DALAM 1 METER Rp.
2 1 M3 GALIAN TANAH BIASA DALAM 2 METER Rp.
3 1 M3 GALIAN TANAH BIASA DALAM 3 METER Rp.
4 1 M3 GALIAN TANAH KERAS DALAM 1METER Rp.
5 1 M3 GALIAN TANAH CADAS DALAM 1 METER Rp.
6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER Rp.
7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER Rp.
8 1 M3 PEMBUANGAN TANAH SEJAUH 30 METER Rp.
9 1 M3 PENGURUGAN KEMBALI GALIAN TANAH Rp.
10 1 M3 PEMADATAN TANAH ( Per 20 Cm ) Rp.
11 1 M3 URUGAN PASIR Rp.
12 1 M2 PEMASANGAN LAPISAN IJUK TEBAL 10 CM Rp.
13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan Rp.
14 1 M3 TIMBUNAN PASIR SEBAGAI BAHAN PENGISI Rp.

III HARGA SATUAN PEKERJAAN PONDASI (PERMEN PUPR 28/PRT/M/2016)


1 1 M3 BATU BELAH CAMP. 1 SP : 3 PP Rp.
2 1 M3 BATU BELAH CAMP. 1 SP : 4 PP Rp.
3 1 M3 BATU BELAH CAMP. 1 SP : 5 PP Rp.
4 1 M3 BATU BELAH CAMP. 1 SP : 6 PP Rp.
5 1 M3 BATU BELAH CAMP. 1 SP : 8 PP Rp.
6 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1SP : 1KP : 2PP Rp.
7 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1SP : 3KP : 10PP Rp.
8 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1/4 SP : 1KP : 4PP Rp.
9 1 M3 PASANGAN PONDASI SIKLOP, 60% BETON CAMPURAN 1 SP : 2 PB : 3 KR DAN 40% BATU BELAH Rp.
10 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M Rp.
11 1 M3 PASANGAN BATU KOSONG Rp.

IV PEKERJAAN DINDING (PERMEN PUPR 28/PRT/M/2016))


1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS Rp.
2 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS Rp.
3 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 4 PS Rp.
4 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS Rp.
5 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS Rp.
6 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 8 PS Rp.
7 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SP : 3 KP : 10 PP Rp.
8 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SP : 3 KP : 10 PP Rp.
9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SM : 1 KP : 2 PP Rp.
10 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 2 PP Rp.
11 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 3 PP Rp.
12 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 4 PP Rp.
13 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 5 PP Rp.
14 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 6 PP Rp.
NO URAIAN PEKERJAAN HARGA

15 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 3 KP : 10 PP Rp.


16 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 20), campuran spesi 1 pc : 3 ps Rp.
17 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 20), campuran spesi 1 psp : 4 pp Rp.
18 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 15), campuran spesi 1 psp : 3 pp Rp.
19 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 15), campuran spesi 1 psp : 4 pp Rp.
20 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran spesi 1 psp : 3 pp Rp.
21 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran spesi 1 psp : 4 pp Rp.
22 1 M2 PASANGAN DINDING Bata Berongga Ekspose (12 x 11 x 24) CM camp 1 Pc : 3 PP Rp.

V PEKERJAAN PLESTERAN (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PLESTERAN CAMP. 1 PC : 1 PP TEBAL 15 MM Rp.
2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM Rp.
3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM Rp.
4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM Rp.
5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM Rp.
6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM Rp.
7 1 M2 PLESTERAN CAMP. 1 PC : 7 PS TEBAL 15 MM Rp.
8 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM Rp.
9 1 M2 PLESTERAN CAMP. 1 PC : 2PP TEBAL 20 MM Rp.
10 1 M2 PLESTERAN CAMP. 1 PC : 3PS TEBAL 20 MM Rp.
11 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM Rp.
12 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM Rp.
13 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM Rp.
14 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM Rp.
15 1 M2 PLESTERAN CAMP. 1 PC : 1 KP : 2 PS TEBAL 20 MM Rp.
16 1 M2 PLESTERAN BERAPEN 1 PS : 5PP TEBAL 15 MM Rp.
17 1 M' PLESTERAN SKONING 1 PC : 3 PS, TEBAL 10 MM Rp.
18 1 M2 PLESTERAN GRANIT 1 SP : 2 GRANIT TEBAL 1 CM Rp.
19 1 M2 PLESTERAN TRASO 1 SP : 2 TRASO TEBAL 1 CM Rp.
20 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS Rp.
21 1 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH Rp.
22 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE Rp.
23 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS Rp.
24 1 M2 PEKERJAAN ACIAN Rp.

VI PEKERJAAN KAYU (PERMEN PUPR 28/PRT/M/2016)


1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I Rp.
2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS III Rp.
3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II Rp.
4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III Rp.
5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II Rp.
6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS II Rp.
7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS II Rp.
8 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA TERTUTUP, KAYU KELAS II (Lebar Sampai 90 Cm) Rp.
9 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS II Rp.
10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS II Rp.
11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I Rp.
12 MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE, KAYU KELAS II Rp.
13 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS II Bentang 6 M' Rp.
14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I Rp.
15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II Rp.
16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II Rp.
17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II Rp.
18 MEMASANG 1 M2 USUK EXPOSE KAYU KLS I KAMPER Rp.
19 MEMASANG 1 M2 RENG KAYU KLS I KAMPER Rp.
20 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II Rp.
21 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II Rp.
22 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II Rp.
23 MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS II Rp.
24 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS II Rp.
25 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II Rp.
26 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KELAS II Rp.
27 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KELAS II Rp.
28 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA HOLO Rp.
NO URAIAN PEKERJAAN HARGA

29 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA HOLO Rp.


30 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I Rp.
31 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM Rp.
NO URAIAN PEKERJAAN HARGA

VII PEKERJAAN BETON ( PERMEN PUPR 28/PRT/M/2016))


1 MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c = 0,87 Rp.
2 MEMBUAT 1 M³ BETON MUTU f'C= 9,8 Mpa (K125), Slump (12 ± 2)cm, w/c = 0,78 Rp.
3 MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72 Rp.
4 MEMBUAT 1 M³ LANTAI KERJA BETON MUTU F'C = 7,4 MPA SLUMP (3-6)CM, W/C =0.87 Rp.
5 MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c = 0,66 Rp.
6 MEMBUAT 1 M³ BETON MUTU f'C= 16,9 Mpa (K200), Slump (12 ± 2)cm, w/c = 0,61 Rp.
7 MEMBUAT 1 M³ BETON MUTU f'C= 19,3 Mpa (K225), Slump (12 ± 2)cm, w/c = 0,58 Rp.
8 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56 Rp.
9 MEMBUAT 1 M³ BETON MUTU f'C= 24,0 Mpa (K275), Slump (12 ± 2)cm, w/c =0,53 Rp.
10 MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52 Rp.
11 MEMBUAT 1 M³ BETON MUTU f'C= 28,8 Mpa (K325), Slump (12 ± 2)cm, w/c =0,49 Rp.
12 MEMBUAT 1 M³ BETON MUTU f'C= 31,2 Mpa (K350), Slump (12 ± 2)cm, w/c =0,48 Rp.
13 PEMBESIAN 1 KG DENGAN BESI POLOS ATAU BESI ULIR Rp.
14 PEMBESIAN 1 KG kabel prategang (prestressed) polos/strands Rp.
15 PEMBESIAN 1 KG DENGAN BESI POLOS Rp.
16 Pemasangan 10 Kg jaring kawat baja (wiremesh) Rp.
17 1 M2 PASANG BEKISTING UNTUK PONDASI Rp.
18 1 M2 PASANG BEKISTING UNTUK SLOOF Rp.
19 1 M2 PASANG BEKISTING UNTUK KOLOM Rp.
20 1 M2 PASANG BEKISTING UNTUK BALOK Rp.
21 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI Rp.
22 1 M2 PASANG BEKISTING UNTUK DINDING Rp.
23 1 M2 PASANG BEKISTING UNTUK TANGGA Rp.
24 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON Rp.
25 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM) Rp.
26 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM) Rp.
27 1 M2 BEKISTING DINDING BETON BIASA DENGAN MULTIFLEX 12 mm *2 kali pakai* Rp.
28 1 M2 BEKISTING PONDASI DAN SLOOF BETON BIASA MENGGUNAKAN PAPAN 3/20 CM *2 kali pakai* Rp.
29 1 M2 PERANCAH/PENYOKONG BEKISTING DINDING BETON MENGGUNAKAN KAYU 5/7 ,Tinggi Maks 2,5 m *2 kaliRp.
30 1 M2 PERANCAH/PENYOKONG BEKISTING PONDASI DAN SLOOF BETON MENGGUNAKAN KAYU 5/7 ,Tinggi Maks
Rp.2,

VIII HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM (PERMEN PUPR 28/PRT/M/2016)
1 1 KG PEMASANGAN BESI PROFIL Rp.
2 1 KG PEMASANGAN RANGKA KUDA-KUDA BAJA IWF Rp.
3 100 KG PENGERJAAN PEKERJAAN PERAKITAN Rp.
4 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1 X40.40.2MM, MODUL 60 X 120 CM, UNTUK PLAFON Rp.

IX PEKERJAAN PENUTUP ATAP (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG Rp.
2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT Rp.
3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG Rp.
4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM Rp.
5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M Rp.
6 1 M2 PASANGAN LAPISAN ALUMINIUM FOIL Rp.
7 1 M1 PASANG NOK SENG GELOMBANG Rp.
8 1 BH PEKERJAAN PASANGAN IKUT CELEDU Rp.
9 1 BH PEKERJAAN PASANGAN MURDHA Rp.

X PEKERJAAN PLAFOND / LANGIT - LANGIT (PERMEM PUPR 28/PRT/M/2016))


1 MEMASANG 1 M2 LANGIT-LANGIT ASBES SEMEN, TEBAL 4 MM, 5 MM DAN 6 MM Rp.
2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/3 MM, 4MM, 6MM Rp.
3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING Rp.
4 1 M2 PLAFOND GYPSUM, RANGKA KAYU Rp.
5 1 M2 PLAFOND GYPSUM, RANGKA HOLO Rp.
6 1 M2 PLAFOND KALSIBOARD, RANGKA KAYU Rp.
7 1 M2 PLAFOND KALSIBOARD, RANGKA HOLO Rp.

XI PEKERJAAN SANITASI ( PERMEN PUPR 28/PRT/M/2016) )


1 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 " Rp.
2 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3" Rp.
3 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5" Rp.
4 MEMASANG 1 M1 PIPA PVC TYPE AW f 2" Rp.
5 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" Rp.
NO URAIAN PEKERJAAN HARGA

6 MEMASANG 1 M1 PIPA PVC TYPE AW f 4" Rp.


NO URAIAN PEKERJAAN HARGA

XII PEKERJAAN BESI DAN ALUMINIUM (PERMEN PUPR 28/PRT/M/2016)


1 1 KG MEMASANG RANGKA BAJA IWF Rp.

XIII PEKERJAAN KUNCI DAN KACA PERMEN PUPR 28/PRT/M/2016)


1 1 BH PASANG KUNCI TANAM BIASA Rp.
2 1 BH PASANG ENGSEL PINTU Rp.
3 1 BH PASANG ENGSEL JENDELA KUPU-KUPU Rp.
4 1 BH PASANG KAIT ANGIN Rp.
5 1 BH PASANG GRENDEL TANAM Rp.
6 1 M2 PASANG KACA, TEBAL5 MM Rp.

XIV PEKERJAAN PENUTUP LANTAI DAN DINDING (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PASANG LANTAI KERAMIK 40 X 40 CM ASIA TILE Rp.
2 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM Rp.
3 1 M' PASANG PLINT KERAMIK UKURAN 10 CM X 40 CM Rp.

XV PEKERJAAN PENGECATAN (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) Rp.
2 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN KUAS Rp.
3 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN ROLL Rp.
4 1 M2 WATERPROOFING Rp.
5 1 M2 PEKERJAAN PASANG WALL PAPER DENGAN PEREKAT SILK HOUSE Rp.
6 1 M2 PEKERJAAN MELAPIS MENI KAYU Rp.
7 1 M2 PEKERJAAN MENDEMPUL ATAU MEMPLAMIR DAN MENGGOSOK KAYU Rp.
8 1 M2 PEKERJAAN PENGECATAN DASAR 1 LAPIS PADA KAYU Rp.
9 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA KAYU Rp.
10 1 M2 PEKERJAAN MELAPIS MENI PADA PERMUKAAN BAJA Rp.
11 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA SECARA MANUAL Rp.
12 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA/KAYU DENGAN SEMPROT Rp.
13 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN TEAK OIL Rp.
14 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN POLITUR 2 LAPIS Rp.
15 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN VERNIS 2 LAPIS Rp.

XIV PEKERJAAN ELEKTRIKAL (PERMEN PUPR 28/PRT/2016)


1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN Rp.
2 1 TITIK INSTALASI AC Rp.
3 1 TITIK INSTALASI TELEPHONE Rp.
4 1 TITIK INSTALASI MATV Rp.
REKAPITULASI
BILL OF QUANTITY (BOQ)

SATUAN KERJA : KANWIL KEMENTERIAN HUKUM DAN HAM DENPASAR


PEKERJAAN : REHAB 3 UNIT RUMAH DINAS TYPE C
LOKASI : KOTA DENPASAR

NO. URAIAN PEKERJAAN JUMLAH HARGA


( Rp. )

PERLENGKAPAN SMKK (SISTEM MANAJEMEN KESELAMATAN


A.
KONTRUKSI)

B. RUMAH DINAS BAGIAN TIMUR

C. RUMAH DINAS BAGIAN TENGAH

D. RUMAH DINAS BAGIAN BARAT

REAL COST
PPN 10 %
TOTAL COST
DIBULATKAN
TERBILANG :
……………………………………..

……………...,………… 2020
Kontraktor
PT/CV………….

…………………….
Jabtatan
BILL OF QUANTITY (BOQ)

UNIT KERJA : KANWIL KEMENTERIAN HUKUM DAN HAM DENPASAR


PEKERJAAN : REHAB 3 UNIT RUMAH DINAS TYPE C
LOKASI : KOTA DENPASAR

No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga


(Rp) (Rp)

A. PERLENGKAPAN SMKK (SISTEM MANAJEMEN KESELAMATAN KONTRUKSI)


I. Sosialisasi dan Promosi K3
1 Spanduk K3 Bh 1.00

II. Rambu - Rambu K3


1 Rambu - Rambu Bh 1.00

III. Fasilitas Sarana Kesehatan


1 Kotak P3K Set 1.00

IV. Kelengkapan Pekerja


1 Helm proyek Bh 25.00
2 Rompi proyek Bh 25.00
3 Masker Bh 25.00
4 Sepatu proyek Pasang 25.00
5 Sarung tangan proyek Pasang 25.00

TOTAL PEKERJAAN SMKK


B. RUMAH DINAS BAGIAN TIMUR
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap genteng dan bubungan M2 138.53
2 Pek. Pembongkaran usuk dan reng M2 138.53
3 Pek. Pembongkaran kuda - kuda M3 2.35
4 Pek. Pembongkaran listplank M2 17.76
5 Pek. Pembongkaran plafond M2 119.97
6 Pek. Pembongkaran keramik M2 7.50
7 Pek. Pembongkaran kusen Bh 15.00
8 Pek. Pembongkaran tembok M3 1.53
9 Pek. Pembersihan dan langsiran sisa bongkaran Rit 5.00

II. PEKERJAAN TANAH DAN PASIR


1 Pek. Galian tanah pondasi menerus M3 0.42
2 Pek. Urugan Tanah Peninggian + pemadatan M3 7.28
3 Pek. Urugan Pasir Bawah Lantai M3 10.39

III. PEKERJAAN PASANGAN DAN PLESTERAN


1 Pek. Pas. Batu bata 1 : 5 M2 76.81
2 Pek. Pas. Batako 1 : 5 M2 5.52
3 Pek. Plesteran 1 : 5 M2 156.69
4 Pek. Acian M2 156.69
5 Pek. Pas. Loster batu palimanan ukir Bh 15.00
6 Pek. Pas. Loster beton Bh 2.00
7 Pek. Pas. Batu palimanan M2 5.16
8 Pek. Pas. Batu andesit M2 3.12

IV. PEKERJAAN BETON


1 Pek. Cor beton rabat Lantai 1 : 3 : 5 M3 6.23
2 Pek. Sloop praktis M' 13.15
3 Pek. Kolom praktis M' 44.60
4 Pek. Ring praktis M' 55.00

V. PEKERJAAN KAYU DAN ALUMINIUM


1 Pek. Pas. Kusen kayu bengkirai 5 x 11 cm M3 0.39
2 Pek. Pas. Kusen aluminium YKK 4 x 10 cm M' 5.08
3 Pek. Pas. Daun pintu panil kayu bengkirai M2 8.65
4 Pek. Pas. Daun jendela kaca kayu bengkirai M2 13.07
5 Pek. Pas. Pintu aluminium listplank + assesoris (70 x 210 cm) Unit 1.00
No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga
(Rp) (Rp)
VI. PEKERJAAN ATAP
1 Pek. Pas. Kuda - kuda baja ringan profil UK-60 axis truss rumah dinas M2 119.97
2 Pek. Pas. Atap genteng kodok goodyear M2 150.33
3 Pek. Pas. Bubungan genteng kodok goodyear M' 30.00
4 Pek. Pas. Kuda - kuda baja ringan profil UK-60 axis truss garase M2 15.03
5 Pek. Pas. Atap garase alderon M2 15.03
6 Pek. Pas. Listplank fibersemen 1,6 x 24 cm shera eave pro M' 44.40
7 Pek. Pas. Listplank fibersemen 0,8 x 20 cm shera plank teak M' 11.39
8 Pek. Pas. Ikut celedu paras Bh 4.00
9 Pek. Pas. Murdha paras Bh 2.00

VII. PEKERJAAN PLAFOND


1 Pek. Pas. Plafond gypsum 9 mm + rangka hollow M2 111.25
2 Pek. Pas. List gypsum 1/5 M' 176.54

VIII. PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pek. Pas. Lantai granit polish 60 x 60 cm durafloor M2 79.12
2 Pek. Pas. Lantai granit unpolish garase 40 x 40 cm durafloor M2 31.31
3 Pek. Pas. Lantai granit unpolish KM/WC 40 x 40 cm durafloor M2 3.15
4 Pek. Pas. Granit dinding KM/WC 30 x 60 cm durafloor M2 19.90
5 Pek. Pas. Granit meja dapur 60 x 60 cm durafloor M2 1.47
6 Pek. Pas. Granit dinding meja dapur 60 x 60 cm durafloor M2 3.78
7 Pek. Pas. Plint granit 10 x 60 cm durafloor M' 72.99

IX. PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 Pek. Pas. Engsel pintu solid Bh 15.00
2 Pek. Pas. Engsel jendela solid Bh 26.00
3 Pek. Pas. Grendel jendela solid Bh 13.00
4 Pek. Pas. Kait angin solid Bh 26.00
5 Pek. Pas. Kunci pintu 2 slaag solid Bh 5.00

X. PEKERJAAN PENGECATAN
1 Pek. Pengecatan tembok vinilex M2 447.31
2 Pek. Pengecatan plafond vinilex M2 111.25
3 Pek. Polituran M2 45.06
4 Pek. Pengecatan kayu M2 11.48

XI. PEKERJAAN INSTALASI LISTRIK


1 Pek. Penyambungan listrik baru 1300 Watt Ls 1.00
2 Pek. Pas. Instalasi titik lampu penerangan Titik 9.00
3 Pek. Pas. Instalasi stop kontak Titik 8.00
4 Pek. Pas. Stop kontak Bh 8.00
5 Pek. Pas. Saklar tunggal Bh 6.00
6 Pek. Pas. Saklar ganda Bh 2.00
7 Pek. Pas. Lampu LED Panel 12 Watt ( White ) philips Bh 3.00
8 Pek. Pas. Lampu LED Panel 6 Watt ( White ) philips Bh 4.00
9 Pek. Pas. Lampu LED Panel 6 Watt (Warm White) philips Bh 2.00
10 Pek. Pas. MCB Unit 1.00

XII. PEKERJAAN PLUMBING DAN SANITAIR


1 Pek. Pas. Kloset duduk setara Toto CW 421 J Bh 1.00
2 Pek. Pas. Kran tembok setara Toto T23B13V7NB Bh 1.00
3 Pek. Pas. Tempat sabun setara TotoTX2BV1B Bh 1.00
4 Pek. Pas. Tempat tisu setara Toto TX 720 ACRB Bh 1.00
5 Pek. Pas. Floor drain setara Toto TX 1 BN Bh 1.00
6 Pek. Pas. Shower spray setara Toto TX403SMCRB Bh 1.00
7 Pek. Pas. Rain Shower setara Wasser Brass ESC-C330 Bh 1.00
8 Pek. Pas. Sink dapur setara Modena Bh 1.00
9 Pek. Pas. Kran sink setara Toto TX606KES Bh 1.00
10 Pek. Pipa Air Bersih Ø 3/4" M' 35.00
11 Pek. Pipa Air Lantai Ø 3" M' 18.00
12 Pek. Pipa Air Kotor Ø 4" M' 10.00
13 Pek. Pas. Pompa booster shimizu Unit 1.00
14 Pek. Penyambungan PDAM Ls 1.00
15 Pek. Pas. Biotop septictank BSV - 4 kapasitas 500 lietr Unit 1.00
16 Pek. Peresapan Unit 1.00
No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga
(Rp) (Rp)

TOTAL PEKERJAAN RUMAH DINAS BAGIAN TIMUR


BILL OF QUANTITY (BOQ)

UNIT KERJA : KANWIL KEMENTERIAN HUKUM DAN HAM DENPASAR


PEKERJAAN : REHAB 3 UNIT RUMAH DINAS TYPE C
LOKASI : KOTA DENPASAR

No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga


(Rp) (Rp)

C. RUMAH DINAS BAGIAN TENGAH


I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap genteng dan bubungan M2 138.53
2 Pek. Pembongkaran usuk dan reng M2 138.53
3 Pek. Pembongkaran kuda - kuda M3 2.35
4 Pek. Pembongkaran listplank M2 17.76
5 Pek. Pembongkaran rangka + atap pada bagian emper M2 32.06
6 Pek. Pembongkaran plafond M2 119.97
7 Pek. Pembongkaran keramik M2 17.52
8 Pek. Pembongkaran kusen Bh 16.00
9 Pek. Pembongkaran tembok M3 1.53
10 Pek. Pembersihan dan langsiran sisa bongkaran Rit 5.00

II. PEKERJAAN TANAH DAN PASIR


1 Pek. Galian tanah pondasi menerus M3 0.42
2 Pek. Urugan Tanah Peninggian + pemadatan M3 7.28
3 Pek. Urugan Pasir Bawah Lantai M3 10.39

III. PEKERJAAN PASANGAN DAN PLESTERAN


1 Pek. Pas. Batu bata 1 : 5 M2 73.74
2 Pek. Pas. Batako 1 : 5 M2 5.52
3 Pek. Plesteran 1 : 5 M2 150.56
4 Pek. Acian M2 150.56
5 Pek. Pas. Loster batu palimanan ukir Bh 15.00
6 Pek. Pas. Loster beton Bh 2.00
7 Pek. Pas. Batu palimanan M2 5.16
8 Pek. Pas. Batu andesit M2 3.12

IV. PEKERJAAN BETON


1 Pek. Cor beton rabat Lantai 1 : 3 : 5 M3 6.23
2 Pek. Sloop praktis M' 13.15
3 Pek. Kolom praktis M' 30.60
4 Pek. Ring praktis M' 55.00

V. PEKERJAAN KAYU DAN ALUMINIUM


1 Pek. Pas. Kusen kayu bengkirai 5 x 11 cm M3 0.39
2 Pek. Pas. Kusen aluminium YKK 4 x 10 cm M' 5.08
3 Pek. Pas. Daun pintu panil kayu bengkirai M2 8.65
4 Pek. Pas. Daun jendela kaca kayu bengkirai M2 13.07
5 Pek. Pas. Daun pintu aluminium partisi listplank Unit 1.00

VI. PEKERJAAN ATAP


1 Pek. Pas. Kuda - kuda baja ringan profil UK-60 axis truss rumah dinas M2 119.97
2 Pek. Pas. Atap genteng kodok goodyear M2 150.33
3 Pek. Pas. Bubungan genteng kodok goodyear M' 30.00
4 Pek. Pas. Kuda - kuda baja ringan profil UK-60 axis truss garase M2 15.03
5 Pek. Pas. Atap garase alderon M2 15.03
6 Pek. Pas. Listplank fibersemen 1,6 x 20 cm M' 44.40
7 Pek. Pas. Listplank fibersemen 1,6 x 15 cm M' 11.39
8 Pek. Pas. Ikut celedu paras Bh 4.00
9 Pek. Pas. Murdha paras Bh 2.00

VII. PEKERJAAN PLAFOND


1 Pek. Pas. Plafond gypsum 9 mm + rangka hollow M2 111.25
2 Pek. Pas. List gypsum 1/5 M' 176.54

VIII. PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pek. Pas. Lantai granit polish 60 x 60 cm durafloor M2 79.12
No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga
(Rp) (Rp)
2 Pek. Pas. Lantai granit unpolish garase 40 x 40 cm durafloor M2 31.31
3 Pek. Pas. Lantai granit unpolish KM/WC 40 x 40 cm durafloor M2 3.15
4 Pek. Pas. Granit dinding KM/WC 30 x 60 cm durafloor M2 19.90
5 Pek. Pas. Granit meja dapur 60 x 60 cm durafloor M2 1.47
6 Pek. Pas. Granit dinding meja dapur 60 x 60 cm durafloor M2 3.78
7 Pek. Pas. Plint granit 10 x 60 cm durafloor M' 72.99

IX. PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 Pek. Pas. Engsel pintu solid Bh 15.00
2 Pek. Pas. Engsel jendela solid Bh 26.00
3 Pek. Pas. Grendel jendela solid Bh 13.00
4 Pek. Pas. Kait angin solid Bh 26.00
5 Pek. Pas. Kunci pintu 2 slaag solid Bh 5.00

X. PEKERJAAN PENGECATAN
1 Pek. Pengecatan tembok vinilex M2 447.31
2 Pek. Pengecatan plafond vinilex M2 111.25
3 Pek. Polituran M2 45.06
4 Pek. Pengecatan kayu M2 11.48

XI. PEKERJAAN INSTALASI LISTRIK


1 Pek. Pas. Instalasi titik lampu penerangan Titik 9.00
2 Pek. Pas. Instalasi stop kontak Titik 8.00
3 Pek. Pas. Stop kontak Bh 8.00
4 Pek. Pas. Saklar tunggal Bh 6.00
5 Pek. Pas. Saklar ganda Bh 2.00
6 Pek. Pas. Lampu LED Panel 12 Watt ( White ) philips Bh 3.00
7 Pek. Pas. Lampu LED Panel 6 Watt ( White ) philips Bh 4.00
8 Pek. Pas. Lampu LED Panel 6 Watt (Warm White) philips Bh 2.00
9 Pek. Pas. MCB Unit 1.00

XII. PEKERJAAN PLUMBING DAN SANITAIR


1 Pek. Pas. Kloset duduk setara Toto CW 421 J Bh 1.00
2 Pek. Pas. Kran tembok setara Toto T23B13V7NB Bh 1.00
3 Pek. Pas. Tempat sabun setara TotoTX2BV1B Bh 1.00
4 Pek. Pas. Tempat tisu setara Toto TX 720 ACRB Bh 1.00
5 Pek. Pas. Floor drain setara Toto TX 1 BN Bh 1.00
6 Pek. Pas. Shower spray setara Toto TX403SMCRB Bh 1.00
7 Pek. Pas. Rain Shower setara Wasser Brass ESC-C330 Bh 1.00
8 Pek. Pas. Sink dapur setara Modena Bh 1.00
9 Pek. Pas. Kran sink setara Toto TX606KES Bh 1.00
10 Pek. Pipa Air Bersih Ø 3/4" M' 35.00
11 Pek. Pipa Air Lantai Ø 3" M' 18.00
12 Pek. Pipa Air Kotor Ø 4" M' 10.00
13 Pek. Pas. Pompa booster shimizu Unit 1.00
14 Pek. Pas. Biotop septictank BSV - 4 kapasitas 500 lietr Unit 1.00
15 Pek. Peresapan Unit 1.00

TOTAL PEKERJAAN RUMAH DINAS BAGIAN TENGAH


BILL OF QUANTITY (BOQ)

UNIT KERJA : KANWIL KEMENTERIAN HUKUM DAN HAM DENPASAR


PEKERJAAN : REHAB 3 UNIT RUMAH DINAS TYPE C
LOKASI : KOTA DENPASAR

No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga


(Rp) (Rp)

D. RUMAH DINAS BAGIAN BARAT


I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap genteng dan bubungan M2 138.53
2 Pek. Pembongkaran usuk dan reng M2 138.53
3 Pek. Pembongkaran kuda - kuda M3 2.35
4 Pek. Pembongkaran listplank M2 17.76
5 Pek. Pembongkaran rangka + atap pada bagian emper M2 39.37
6 Pek. Pembongkaran plafond M2 119.97
7 Pek. Pembongkaran keramik M2 7.50
8 Pek. Pembongkaran kusen Bh 15.00
9 Pek. Pembongkaran tembok M3 2.07
10 Pek. Pembersihan dan langsiran sisa bongkaran Rit 6.00

II. PEKERJAAN TANAH DAN PASIR


1 Pek. Galian tanah pondasi menerus M3 0.42
2 Pek. Urugan Tanah Peninggian + pemadatan M3 2.57
3 Pek. Urugan Pasir Bawah Lantai M3 10.39

III. PEKERJAAN PASANGAN DAN PLESTERAN


1 Pek. Pas. Batu bata 1 : 5 M2 73.74
2 Pek. Pas. Batako 1 : 5 M2 5.52
3 Pek. Plesteran 1 : 5 M2 150.56
4 Pek. Acian M2 150.56
5 Pek. Pas. Loster batu palimanan ukir Bh 15.00
6 Pek. Pas. Loster beton Bh 2.00
7 Pek. Pas. Batu palimanan M2 5.16
8 Pek. Pas. Batu andesit M2 3.12

IV. PEKERJAAN BETON


1 Pek. Cor beton rabat Lantai 1 : 3 : 5 M3 6.23
2 Pek. Sloop praktis M' 13.15
3 Pek. Kolom praktis M' 30.60
4 Pek. Ring praktis M' 55.00

V. PEKERJAAN KAYU DAN ALUMINIUM


1 Pek. Pas. Kusen kayu bengkirai 5 x 11 cm M3 0.39
2 Pek. Pas. Kusen aluminium YKK 4 x 10 cm M' 5.08
3 Pek. Pas. Daun pintu panil kayu bengkirai M2 8.65
4 Pek. Pas. Daun jendela kaca kayu bengkirai M2 13.07
5 Pek. Pas. Daun pintu aluminium partisi listplank Unit 1.00

VI. PEKERJAAN ATAP


1 Pek. Pas. Kuda - kuda baja ringan profil UK-60 axis truss rumah dinas M2 119.97
2 Pek. Pas. Atap genteng kodok goodyear M2 150.33
3 Pek. Pas. Bubungan genteng kodok goodyear M' 30.00
4 Pek. Pas. Kuda - kuda baja ringan profil UK-60 axis truss garase M2 15.03
5 Pek. Pas. Atap garase alderon M2 15.03
6 Pek. Pas. Listplank fibersemen 1,6 x 20 cm M' 44.40
7 Pek. Pas. Listplank fibersemen 1,6 x 15 cm M' 11.39
8 Pek. Pas. Ikut celedu paras Bh 4.00
9 Pek. Pas. Murdha paras Bh 2.00

VII. PEKERJAAN PLAFOND


1 Pek. Pas. Plafond gypsum 9 mm + rangka hollow M2 111.25
2 Pek. Pas. List gypsum 1/5 M' 176.54

VIII. PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pek. Pas. Lantai granit polish 60 x 60 cm durafloor M2 79.12
No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga
(Rp) (Rp)
2 Pek. Pas. Lantai granit unpolish garase 40 x 40 cm durafloor M2 31.31
3 Pek. Pas. Lantai granit unpolish KM/WC 40 x 40 cm durafloor M2 3.15
4 Pek. Pas. Granit dinding KM/WC 30 x 60 cm durafloor M2 19.90
5 Pek. Pas. Granit meja dapur 60 x 60 cm durafloor M2 1.47
6 Pek. Pas. Granit dinding meja dapur 60 x 60 cm durafloor M2 3.78
7 Pek. Pas. Plint granit 10 x 60 cm durafloor M' 72.99

IX. PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 Pek. Pas. Engsel pintu solid Bh 15.00
2 Pek. Pas. Engsel jendela solid Bh 26.00
3 Pek. Pas. Grendel jendela solid Bh 13.00
4 Pek. Pas. Kait angin solid Bh 26.00
5 Pek. Pas. Kunci pintu 2 slaag solid Bh 5.00

X. PEKERJAAN PENGECATAN
1 Pek. Pengecatan tembok vinilex M2 447.31
2 Pek. Pengecatan plafond vinilex M2 111.25
3 Pek. Polituran M2 45.06
4 Pek. Pengecatan kayu M2 11.48

XI. PEKERJAAN INSTALASI LISTRIK


1 Pek. Pas. Instalasi titik lampu penerangan Titik 9.00
2 Pek. Pas. Instalasi stop kontak Titik 8.00
3 Pek. Pas. Stop kontak Bh 8.00
4 Pek. Pas. Saklar tunggal Bh 6.00
5 Pek. Pas. Saklar ganda Bh 2.00
6 Pek. Pas. Lampu LED Panel 12 Watt ( White ) philips Bh 3.00
7 Pek. Pas. Lampu LED Panel 6 Watt ( White ) philips Bh 4.00
8 Pek. Pas. Lampu LED Panel 6 Watt (Warm White) philips Bh 2.00
9 Pek. Pas. MCB Unit 1.00

XII. PEKERJAAN PLUMBING DAN SANITAIR


1 Pek. Pas. Kloset duduk setara Toto CW 421 J Bh 1.00
2 Pek. Pas. Kran tembok setara Toto T23B13V7NB Bh 1.00
3 Pek. Pas. Tempat sabun setara TotoTX2BV1B Bh 1.00
4 Pek. Pas. Tempat tisu setara Toto TX 720 ACRB Bh 1.00
5 Pek. Pas. Floor drain setara Toto TX 1 BN Bh 1.00
6 Pek. Pas. Shower spray setara Toto TX403SMCRB Bh 1.00
7 Pek. Pas. Rain Shower setara Wasser Brass ESC-C330 Bh 1.00
8 Pek. Pas. Sink dapur setara Modena Bh 1.00
9 Pek. Pas. Kran sink setara Toto TX606KES Bh 1.00
10 Pek. Pipa Air Bersih Ø 3/4" M' 35.00
11 Pek. Pipa Air Lantai Ø 3" M' 18.00
12 Pek. Pipa Air Kotor Ø 4" M' 10.00
13 Pek. Pas. Pompa booster shimizu Unit 1.00
14 Pek. Pas. Biotop septictank BSV - 4 kapasitas 500 lietr Unit 1.00
15 Pek. Peresapan Unit 1.00

TOTAL PEKERJAAN RUMAH DINAS BAGIAN BARAT


RENCANA ANGGARAN BIAYA (RAB)

UNIT KERJA : KANWIL KEMENTERIAN HUKUM DAN HAM DENPASAR


PEKERJAAN : - REHAB 3 UNIT RUMAH DINAS TYPE C
- #REF!
- #REF!
LOKASI : KOTA DENPASAR

No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga


(Rp) (Rp)

B. ###
I. PERLENGKAPAN SMKK (SISTEM MANAJEMEN KESELAMATAN KONTRUKSI)
1 Perlengkapan SMKK Ls 1.00 #REF! #REF!
Sub. Total I #REF!
II. PEKERJAAN PERSIAPAN
1 Pek. Pembongakran bale bengong lama Ls #REF! 4,500,000.00 #REF!
2 Pek. Pembongkaran tembok M3 #REF! - #REF!
3 Pek. Pengukuran dan Pas. Bouwplank M' #REF! - #REF!
4 Pek. Pembersihan sisa hasil bongkaran Rit #REF! 550,000.00 #REF!
Sub. Total II #REF!
III. PEKERJAAN TANAH DAN PASIR
1 Pek. Galian tanah pondasi menerus M3 #REF! - #REF!
2 Pek. Urugan tanah kembali M3 #REF! 65,002.88 #REF!
3 Pek. Urugan Tanah Peninggian + pemadatan M3 #REF! - #REF!
4 Pek. Urugan pasir Bawah Pondasi M3 #REF! - #REF!
5 Pek. Urugan Pasir Bawah Lantai M3 #REF! - #REF!
Sub. Total III #REF!
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pas. Batu kosong M3 #REF! - #REF!
2 Pek. Pas. Batu kali 1 : 5 M3 #REF! - #REF!
3 Pek. Pas. Batako 1 : 5 M2 #REF! - #REF!
4 Pek. Plesteran 1 : 5 M2 #REF! - #REF!
5 Pek. Acian M2 #REF! - #REF!
Sub. Total IV #REF!
V. PEKERJAAN BETON
1 Pek. Cor beton rabat Lantai 1 : 3 : 5 M3 #REF! - #REF!
2 Pek. Sloop praktis M' #REF! - #REF!
3 Pek. Kolom praktis M' #REF! - #REF!
4 Pek. Ring praktis M' #REF! - #REF!
5 Pek. Cor beton plat talang
- Cor beton K. 250 M3 0.756 - -
- Pembesian Kg 75.567 - -
- Begisting plat M2 9.400 - -
Sub. Total V #REF!
VI. PEKERJAAN ALUMINIUM DAN KACA
1 Pek. Pas. Kusen kayu kamper 5 x 11 cm M3 #REF! - #REF!
2 Pek. Pas. Daun pintu kaca 12 mm 60 x 210 cm Unit #REF! - #REF!
3 Pek. Pas. Daun pintu panil kayu kamper M2 #REF! - #REF!
4 Pek. Pas. Daun jendela kaca kayu kamper M2 #REF! - #REF!
Sub. Total VI #REF!
VII. PEKERJAAN ATAP
1 Pek. Pas. Kuda - kuda baja ringan profil C75 surya truss M2 54.870 - -
2 Pek. Pas. Atap genteng kodok goodyear M2 68.759 - -
3 Pek. Pas. Bubungan genteng kodok goodyear M' 20.200 - -
4 Pek. Pas. Listplank fibersemen 0.8 x 20 cm M' 30.100 20,000.00 602,000.00
5 Pek. Pas. Ikut celedu paras Bh #REF! - #REF!
6 Pek. Pas. Murdha paras Bh #REF! - #REF!
Sub. Total VII #REF!
VIII. PEKERJAAN PLAFOND DAN PARTISI
1 Pek. Pas. Plafond gypsum 9 mm + rangka hollow M2 - - -
2 Pek. Pas. Partisi gypsum 9 mm + rangka metal stud M2 - - -
3 Pek. Pas. List gypsum 7/7 M' - 25,000.00 -
4 Pek. Pas. Plint fibersemen 0.8 x 10 cm M' - 20,000.00 -
Sub. Total VIII -
IX. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pek. Pas. Lantai keramik 40 x 40 cm asia tile M2 - - -
No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga
(Rp) (Rp)
2 Pek. Pas. Lantai keramik anti slip 40 x 40 cm asia tile M2 - - -
3 Pek. Pas. Plint keramik 10 x 40 cm asi tile M' - - -
Sub. Total IX -
X. PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pek. Pas. Engsel pintu Bh 3.000 - -
2 Pek. Pas. Engsel jendela Bh 20.000 - -
3 Pek. Pas. Grendel jendela Bh 10.000 - -
4 Pek. Pas. Kait angin Bh 20.000 - -
5 Pek. Pas. Kunci pintu 2 slaag Bh 1.000 - -
Sub. Total X -
XI. PEKERJAAN PENGECATAN
1 Pek. Pengecatan tembok vinilex M2 - - -
2 Pek. Pengecatan plafond vinilex M2 - - -
3 Pek. Pengecatan kayu M2 #REF! - #REF!
4 Pek. Polituran M2 #REF! - #REF!
5 Pek. Waterproofing M2 #REF! - #REF!
Sub. Total XI #REF!
XII. PEKERJAAN INSTALASI LISTRIK
1 Pek.Pas. Instalasi titik lampu penerangan Titik #REF! - #REF!
2 Pek. Pas. Instalasi stop kontak Titik #REF! - #REF!
3 Pek. Pas. Instalasi data Titik #REF! 379,000.00 #REF!
4 Pek. Pas. Instalasi telephone Titik #REF! - #REF!
5 Pek. Pas. Instalasi AC Titik #REF! - #REF!
6 Pek. Pas. Stop kontak Bh #REF! - #REF!
7 Pek. Pas. Stop kontak AC Bh #REF! - #REF!
8 Pek. Pas. Saklar tunggal Bh #REF! - #REF!
9 Pek. Pas. Saklar ganda Bh #REF! - #REF!
10 Pek. Pas. Outlet data Bh #REF! - #REF!
11 Pek. Pas. Outlet telephone Bh #REF! - #REF!
12 Pek. Pas. Lampu downlight 59263 Eridani 7,5 watt philip LED Bh #REF! - #REF!
13 Pek. Pas. Lampu downlight outbow DN027C 11 watt philip LED Bh #REF! - #REF!
14 Pek. Pas. Box MCB Unit #REF! 450,000.00 #REF!
Sub. Total XII #REF!

TOTAL PEKERJAAN PEMBANGUNAN RUANG PELAYANAN #REF!

You might also like