Claim and Adjustment 074 UNS 020320 CAR STR
Claim and Adjustment 074 UNS 020320 CAR STR
II Debris removal
Sediment cleaning at diversion structure 5,870.97 m3 77,500.00 455,000,175.00 4,884.87 m3 77,500.00 378,577,425.00
Sediment cleaning at main dam right side 2,609.99 m3 77,500.00 202,274,225.00 2,609.99 m3 77,500.00 202,274,225.00
Sediment cleaning at main dam left side 28,930.09 m3 77,500.00 2,242,081,975.00 28,930.09 m3 77,500.00 2,242,081,975.00
Sediment cleaning at outlet 6,580.84 m3 77,500.00 510,015,100.00 5,961.85 m3 77,500.00 462,043,375.00
Sediment cleaning at cofferdam foundation 13,599.00 m3 77,500.00 1,053,922,500.00 13,599.00 m3 77,500.00 1,053,922,500.00
Total II 4,463,293,975.00 4,338,899,500.00