Professional Documents
Culture Documents
This document provides high level steps that describe how to migrate data from Oracle Process Manufacturing Release 11.5.10 to
Release 12.1. Wherever possible, links to more detailed information have been provided.
All steps are mandatory except where SPECIFICALLY noted. All patches must be installed in the order specified – Patch
Merge functionality CANNOT be employed for these steps.
The columns in the checklist are required to be filled out when each step has been completed, including notes on errors or notable
conditions, and a note on optional steps indicating whether or not they were executed.
NOTE: This document is specifically limited to the migration of data from Oracle Process Manufacturing Release 11.5.10 to
12.1. Upgrades and/or migrations pertaining to the database, operating system, other products (e.g. Order Management, Oracle
Inventory), etc. are not covered in this document.
Page 1 of 19
1. Preparation
ALL Customers: The following steps are performed in preparation for migration planning. The information contained in the
referenced documents and note help to explain the overall OPM Migration process and recommendations for ensuring a smooth,
successful migration.
Page 2 of 19
2. Pre-Migration
If you have not already done so, you must complete the preparation steps listed above prior to continuing on to this
section.
The following steps are performed while the system is still available for use by end-users. The steps must be performed in the
order presented and before you continue with the other tasks in subsequent sections.
Comments
2.2. Map the data using the ALL Customers Apply following
patches if
Convergence Migration
migrating to 12.0
Setup user interface,
• 4563075
which is available in the
• 7582494
OPM System
Administration
Apply following
Responsibility. patches if
migrating to 12.1
• 4563075
• 6694260
• 9468260
Page 3 of 19
2. Action Applicability Applicable Action Owner Date Notes
Comments
Additonally,
apply patch
6696828 if
migrating to 12.1
Page 4 of 19
2. Action Applicability Applicable Action Owner Date Notes
Comments
Page 5 of 19
2. Action Applicability Applicable Action Owner Date Notes
Comments
Page 6 of 19
3. Blackout phase – Prior To Upgrade Patch Installation
The pre-migration steps listed above MUST be completed prior to beginning this section.
There should be no unresolved errors from the pre-migration phase. If errors exist from pre-migration, take the
necessary actions to correct them before proceeding.
The following steps are performed after end-users are no longer allowed to log into the system, but before the system is taken
offline to apply the 12.1 Upgrade. The steps must be performed in the order presented and before continuing with the other tasks
in subsequent sections.
Page 7 of 19
3. Action Applicability Applicable patch Action Owner Date Notes
3.4. Review, act upon, and Customers using Review, act upon, and
ASCP dispose of information
dispose of information in
provided in the Oracle
Oracle ASCP interface Advanced Supply Chain
Planning application
tables
interface tables:
GMP_APS_OUTPUT_ TBL
GMP_APS_OUTPUT_DTL
3.5. Review, act upon, and ALL Customers Review, act upon, and
using OPM MRP dispose of the
dispose of information in
information provided in
the OPM MRP interface the OPM interface table
MR_ACTN_TBL. This is
table
important as user will be
moving from using MRP
to ASCP Unconstrained.
Page 8 of 19
3. Action Applicability Applicable patch Action Owner Date Notes
Page 9 of 19
3. Action Applicability Applicable patch Action Owner Date Notes
3.13 Run Actual Cost Process Customers using Run the OPM Actual Cost
Actual Costing Process, OPM Cost
to calculate the cost and
Update Process, OPM
then post inventory & Subledger Update, OPM
GL Export, and General
resource transactions to
Ledger Journal Import.
OPM Subledger and Refer to the OPM
Manufacturing
export to GL. Also see
Accounting Controller
note below. User’s Guide & Oracle
General Ledger User's
Guide for further details.
Page 10 of 19
3. Action Applicability Applicable patch Action Owner Date Notes
Refer to document
Oracle Process
Manufacturing (OPM)
Migration Release 11i to
12.1 Migration Messages
and Technical Reference
for details.
Page 11 of 19
3. Action Applicability Applicable patch Action Owner Date Notes
Page 12 of 19
3. Action Applicability Applicable patch Action Owner Date Notes
3.21 Apply the latest additional ALL Customers Apply following patches
if migrating to 12.0
OPM In-Line Migration
patches in pre-install • 7513308:R12.INV.A
• 8363586:R12.INV.A
mode just before applying
• 9143261:R12.INV.A
the upgrade driver. • 9403348:R12.INV.A
• 8359386:R12.GMI.A
• 8359386:R12.GMI.B
• 9004088:R12.INV.B
• 9143261:R12.INV.
• 9403348:R12:INV.B
• 9476958:R12:INV.B
• 9560244:R12.ITM.C
• 9893621:R12:INV.B
• 10279332:R12:INV.B
• 10413599:R12:INV.B
Page 13 of 19
4. Post-Migration
Perform the following steps after the application of the 12.1 Upgrade and before bringing the system back up and allowing users
to log on. The steps must be performed in the order presented.
4.1. If adworker failed for any ALL Customers Refer to the Oracle
Process Manufacturing
OPM script, go to My
(OPM) Migration
Oracle Support to check Release 11i to 12.1
Migration Messages and
for any new patches or
Technical Reference for
workarounds that exist for details on running failed
scripts.
a failure in the in-line
phase. If none are found,
log a service request.
Page 14 of 19
4. Action Applicability Applicable patch Action Owner Date Notes
Page 15 of 19
4. Action Applicability Applicable patch Action Owner Date Notes
4.5. Run OPM Financials Data ALL Customers Apply following patch if
migrating to 12.0
Transformation
• 4690072
4.7. Apply patches required for ALL Customers Apply the following
patches if migrating to
reopening batches.
12.0
• 9090024:R12.GME.A
• 9170460:R12.GME.A
Page 16 of 19
4. Action Applicability Applicable patch Action Owner Date Notes
4.9. Migrate OPM Edit Text to ALL Customers Run the GMA: Edit Text
Migration concurrent
attachments
program to migrate the
OPM Edit Text to
attachments for the
organizations, items,
lots, grades, and reason
codes. Refer to the OPM
System Administration
User’s Guide for details
Page 17 of 19
4. Action Applicability Applicable patch Action Owner Date Notes
Page 18 of 19
Note for Actual Costing Users only:
After you upgrade to Release 12.1, the Actual Cost program in Release 12.1 will only recognize transactions under process
organizations that are recorded in Oracle Inventory. In other words, the average cost calculations after the upgrade will not
recognize the transactions created in the 11i OPM Inventory system. As a result, the average cost calculated may not be accurate
if the upgrade is performed during the middle of a costing period--and there are transactions in OPM Inventory for the same
costing period. If possible, consider upgrading to R12.1 at the beginning of a costing period. By doing so, you can ensure that the
majority of the transactions in that period are recorded in Release 12.1. Upgrading at the beginning of the costing period will
therefore result in a more accurate average cost when you run the Release 12.1 OPM Actual Cost Process.
Page 19 of 19