To,
M/s. Ravindra Kumar Jain
Chhatarpur (M.P.)
Dear Sir,
Pursuant to your furnishing the requisite Performance Security as stipulated in ITB
Clause 30 and signing of the Contract for the construction of MP-06-705 and routine
maintenance for five years after completion of construction, you are hereby instructed to
proceed with the execution of the said works in accordance with the contract documents.
Contract amount Including GST of Rupees 1091.37 Lakh (Rs. Ten Crore Ninety One
Lakh Thirty Seven Thousand)
Sanction Rate : 26.26% below SSR 05-11'2019
Performance Security :27 .28 Lakh
Time allowed for completion of work L8 months including rainy season.
(F.J. Khan
General Manager
N{fi .r!.ural Road Development Authority
PrU,Chhatarpur(M.P.)
,T
Endt. \ ll3 tstctPrutzo2o Chhatarpur, Dated,
Ab)rfu
Copy forwarded to;
1. Shri A.K. Agrawal, Assistant Manager, PIU Chhatarpur
2. Ku. Pratibha Mishra, S/E PIU, Chhatarpur
for necessary action. The detail DPR Contract agreement etc. may please be collected
from this office & work may be got commenced accordingly.
( F.J. Khan
General Manager
M.P. Rural Road Development Authority
q)ilr, chhatarPur(M.P.)
Information related to work order for package No. Mp06-70s
District- Chhatarpur
(NIT I{o. 900 (PMGSY-[I, Batch-I) dt 04-07-2020)
Agreement No. & Date 08 I GMI 2020 -2 1 /PMG S y-III/Mp 06 -7 0 5 D ate 2 1 I 09 t ziim
General Manager
M.P. Rural Road Development Authority
V4 PIU,Chhatarpur(M.p.)