Professional Documents
Culture Documents
North:1435398
East:307812
Average Altitude: 1102m.a.s.l
Zone: North Gondar
Wereda: Tach Armachiho
4. Hydrology
5. Weir
Type: - Broad Crested weir
Weir Height: -2m
Crest length: - 2
Background
Location
Kirkirayana irrigation project is located mainly at chinqana kebele woymba gote, Tach Armachiho
Wereda of North Gondar Zone in the Amhara Regional state. The proposed irrigation project is to
be undertaken on Kirkirayana River and the headwork structures are specifically located at an
altitude of 1102masl and geographical coordinates of 1435393 N (UTM) & 307816 E (UTM).
Accessibility
The project site can be accessed from the Wereda town, Sanja after driving 8km on all weathered gravel
road. Sanja town is found at about 60km from the Zonal Capital City, Gondar.
There is no traditional irrigation practice that is conducted in the area. However farmers are much
initiated to use the river for the irrigation purpose
Specific Objectives
To identify, estimate and allocate, according to the water balance study, proportional irrigation
water for the given diversion to make sustainable the rain-fed crop production and make extra
production in the dry season irrigation for 40ha of land (ToR) through irrigation by constructing
diversion structures across the Kirkirayana River and diverting the river flow.
To appropriately estimate the design flood across the given cross section of the
diversion and/or the surrounding area by using various acceptable hydrological
methods and models, so that after construction of the structure any
unmanaged/overtopping, over flooding, back flooding and scouring ,etc/ will be
minimized and the structure will be safe throughout the life time.
To estimate reasonably design storm and design flood using required return period
to properly size the recommended hydraulic structures for the purpose.
to make detail design of the proposed weir with an engineering cost estimate
Methodology
The study procedure,
Specific Site identification:
o Field study assessment and measurement
o Review of the reconnaissance survey conducted
o 50,000 scale top map and GIS information
o topography survey at a scale of 1:1000
o Local farmers interview and discussion
o Use of Other secondary data ( Meteorology and that of the woreda)
Flow estimation
o Physical observation on flood mark indications and local information about high flood and
critical flow condition of the river
o Base flow estimated during the reconnaissance field visit by floating method.
o Base flow estimated during the study field visit by floating method.
o Base flow estimated using aged farmers information
Topographic survey:
o Surveying the headwork site and the Command area with sufficient radius, using Total
Station
Section І: hydrology
2. Hydrology
2.1 Hydro-metrological data availability
Climate
Hydrologists and designers are faced with lack of good or recorded hydrometric data on the target
stream/river and on local weather and climate conditions. Stream gauging stations are virtually non-existent
in remote rural areas of Ethiopia; meteorological stations are almost rare. Likewise, at the Project area
location and in the catchment area of this project, there is no meteorological station of any level. Moreover,
there are no recorded flow data for the river. Therefore, data for the hydro-meteorological analysis is taken
from the nearby station and similar areas. Therefore it is technically advisable to use the Gondar rainfall
station for the purpose.
As per the data of the station, March – April are identified as high temperature periods whereas December–
January are low temperature periods. The mean annual rainfall amount is 1101mm (1961 - 1995 data) and
most of it occurred from June to August.
Daily Heaviest Rainfall Data
In order to compute the design flood for design of the diversion structure, the daily maximum rainfall is
collected from Gondar Metrological stations with a record of 35 years. Because this station is the
nearest one as compared to other NMSA stations.
Flow measurement conducted on 18/09/2005, using floating method at the proposed weir site is
70l/s. there is no upstream and downstream users. As to the downstream case since the river joins
Sanja river after few kms, there is no lack of water for environmental maintenance purpose.
Watershed characteristics
The Watershed has marked topographic variation. All types of slopes are present. The dominant slope
class is 3-8% which covers 64.58% of the total area followed by 0-3% which is 18.16%. Sloping and
moderately steep slopping accounts 16.40 and 0.86 percent respectively. There is very steep slope.
Certain physical properties of watersheds significantly affect the characteristics of the runoff and
sediment yield and are of great interest in hydrologic analyses. The rate and volume of runoff, and
sediment yield from the watershed have much to do with shape, size, slope and other parameters of the
landscape. These suggest that there should be some important relations between basin form and
hydrologic performance. If the basin and hydrologic characteristics are to be related, the basin form must
also be represented by quantitative descriptors. These parameters are measured from maps as follows.
Catchment Area = 20.77 km2
Stream Length = 9.7 Km
CN(II) = 82
At the selected reference point, the area of Kirkirayana catchment is 20.7 km 2 and consists of a network of
tributaries.
Kirkirayana River at the headwork site is characterized by well-defined channel system and enough
flows. It looks that the gradient of the river is medium and hence there exists no more deposition.
Design flood analysis
For the design and analysis of structures to be constructed on the river, estimation of flood
magnitude is an important task. This can be done using different techniques depending on the
data available at or nearby the selected irrigation project site. For this particular case, there are no
river flow data and hence the flood estimation is done using the rainfall data and applying SCS
Curve Method. However this is not the best and only method to be used. The result can be
checked using other river hydraulic or geometry hydrodynamic reactions or checked using flood
mark method.
Based on the data of 24hr peak rainfall given in Table 2.1 the design rainfall, RF is computed by
using different distributions.
Outlier Test
Higher Limit,Y H =Ymean+ Kn∗Sy , Kn = 2.753 for 35 Years of data.
Lower Limit, Y H =Ymean−Kn∗Sy , .
Therefore, the data shows relatively good consistency to use as design input.
D-Index test
After checking the consistency of the data for higher and lower outlier, the 35 years data is obtained as
representative for the analysis using D-index. The D-Index test is believed to be the better goodness to
fitness in many literatures. Hence in this study it was used to determine the best statistical distribution to
estimate the peak rainfall. The D-index for the comparison of the fit of various distributions is
summarized as follows.
6
1
D −Index =( )∗∑ |( Xi− Xi' )|
X m i=1
Where Xi and Xi’ are the ith highest observed and computed values for the distribution respectively.
Table 1.1: Test for goodness to fit using D-index
Log Pearson Log Pearson
Normal Type III Normal Type III Gumbel EVI Gumbel
Rank XI XI -'XI' XI -'XI' XI -'XI' XI -'XI' XI -'XI' XI -'XI'
1 99 19.306 12.285 12.319 16.569 9.841 12.452
2 82 6.904 1.981 2.001 4.239 0.691 6.936
3 69.5 2.586 6.466 6.453 5.268 7.166 21.270
4 65.4 4.362 7.607 7.598 7.094 7.936 26.986
5 65.4 2.424 5.250 5.245 5.227 5.323 28.504
6 65 1.136 3.678 3.675 4.021 3.563 30.388
Sum 36.718 37.267 37.291 42.418 34.521 126.535
Sum/Mean 0.702 0.713 0.713 0.811 0.660 2.420
Point Rainfall 81.69 88.68 86.87 82.81 89.39 95.22
Design Point Rainfal = 89.387
All the candidate distributions give almost identical correlation coefficients. However, the standard errors
are significantly lower for the Gumbel’s EVI Method which is 0.66 that makes. However, since the data
of Gondar is taken for the site which is far by 60km, taking this design storm may underestimate the
flood, for this reason Gumbel’s distribution is selected to be safe. Therefore, the design point rainfall
for 50 years return period is 95.22 mm.
Peak Discharge Determination
General
The river is not gauged river. The design flood is calculated by using SCS unit hydrograph method. Thus,
it is preferred to base the flood analysis on rainfall data. In the hydrologic analysis for drainage structures,
it must be recognized that there are many variable factors that affect floods. Some of the factors that need
be recognized and considered on an individual site by site basis are; rainfall amount and storm
distribution; catchment area, shape and orientation; ground cover; type of soil; slopes of terrain and
stream(S); antecedent moisture condition; Storage potential (over bank, ponds, wetlands, reservoirs,
channel, etc.). After simulated design flood is obtained based on the actual river and watershed data, the
result is compared with the flood mark method that is checked during field assessment.
Peak flood analysis by The United States Soil Conservation Service/SCS / method
Design flood is calculated by using SCS method. This method is widely adopted and more reliable
simulation method for flood estimation. The approach considers, watershed parameters, like Area, Curve
number, and Time of concentration.
Time of concentration has been calculated by taking the stream profile of the longest streamline and
dividing it in to different elevation ranges. Kirpich formula is adopted for computation.
0.948∗❑
Tc=
❑
Base time,
T b=2.67∗T p = 2.46hr
Recession time,
T r=1.67∗T p=1.54hr.
Curve number (CN) is achieved based on SCS method by watershed characterization in terms of land
cover, treatment, hydrologic condition and soil group. From the watershed analysis curve number at
condition II = 82 since peak rainfall is found at an antecedent moisture condition III state, this value has
to be changed to antecedent moisture condition III.
Areal Rainfall
As the area of the catchment gets larger, coincidence of all hydrological incidences becomes less and less.
This can be optimized by changing the calculated point rainfall to aerial rainfall. The conversion factor is
taken from standard table and curves that relate directly with the size of watershed area and type of the
gauging station (IDD manual). The result is shown in Table 2.4 below.
( I −0.2∗S)2
Q=
( I + 0.8∗S)
S= ( 25400
CN )
−254
Time H1 H2 H3 H4 H5 H6 SUM
0.00 0.00
0.50 0.00 0.00 0.00
0.60 0.00 0.37 0.37
0.92 0.00 1.57 0.00 1.57
1.30 0.00 2.99 4.79 7.78
1.42 0.00 3.44 6.73 0.00 10.18
1.70 0.00 2.82 11.18 13.96 27.97
1.92 0.00 2.32 14.72 29.42 0.00 46.47
2.20 0.00 1.70 12.06 48.87 12.07 74.70
2.42 0.00 1.21 9.94 64.33 25.44 0.00 100.91
2.70 0.00 0.58 7.27 52.68 42.26 4.46 107.26
2.92 0.09 5.15 33.36 55.63 9.40 103.63
3.10 0.00 3.45 22.30 49.17 13.39 88.31
3.42 0.37 2.40 37.55 20.56 60.88
3.96 0.00 0.00 18.08 13.36 31.44
4.46 0.00 6.68 6.68
4.96 0.00 0.00
From the analysis, the 50 years return period design run off is 107.26m 3/s. This implies that for
this watershed the peak flood rate per km2 area of the watershed is about 5.164 m3/s/km2
The 6hr synthetic hydrograph is shown using the following graphical representation
1
H1
H2
H3
H4
H5
H6
SUM
0 2 4 6 8 10 12
Field assessment and topographic survey, the normal and maximum flood mark points has been
selected by interviewing the local aged farmers and marked in cross section of selected river
geometry. The river is a more channelized one having defined bed and banks dominantly
covered by fresh basalt settings. It is also steeply in slope proving that flood is concentrated in
the outlet in 1.12 hrs time (calculated. There is no overflowing problem.
The cross section of the river looks the following starting from the right side bank of the river (BM-
2, left side )
1106
1105
1104
1103
1102
1101
1100
0 2 4 6 8 10 12 14 16 18 20
Tail water depth of the river is equal to the flood depth and amount at the proposed weir site before
construction of the weir. It is used to crosscheck peak flood estimated by the SCS unit hydrograph
method with flood mark method and to see the flood feature after the hydraulic jump. During field visit,
the flood mark of the river at the proposed diversion site was marked based on dwellers information and
physical indicative marks. The river cross-section was surveyed.
Average river bed slope
Elevatio
Northing Easting Partial Distance Cum.Distance n
307775.49 1435370.42 0.00 0.00 1102.60 upstream
307782.92 1435378.14 10.72 10.72 1102.26
307792.07 1435379.91 9.32 20.03 1102.08
307802.85 1435389.54 14.45 34.48 1102.13
307811.87 1435398.50 12.72 47.20 1102.25 center
307822.24 1435412.92 17.77 64.97 1102.05
307831.53 1435425.16 15.36 80.33 1102.00
downstrea
307857.45 1435438.21 29.02 109.35 1101.47 m
slope 0.010
Q=V ∗A
Table 1.7: Stage discharge analysis
1104.50
1104.00
1103.50
1103.00
1102.50
1102.00
1101.50
1101.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00
Figure 1.4: Stage Discharge Rating Curve
From the above stage discharge table the computed design peak discharge is 107.26m3/s (at a depth of 2.3
m from the river bed)
However we adopted the scs value of flood i.e. 107.26m3/s because the flood mark flood is a little
exaggerated.
Therefore, the downstream high flood level before construction can be calculated as
⇒ D/S HFL = 1102.25+2.3= 1104.55 masl
.
River Geomorphology
It is a common fact that the river development tends to accommodate itself to the local geology that
develops along the structurally weak zones like faults, joints, folds, etc. The drainage system of the study
area is strongly influenced by geological structures and formations, the nature of the vegetation cover and
climate. The nature of geological formations and structures has also strong influence on the development
of the channel.
The present morphology of the Kirkirayana River channel is a function of a number of processes and
environmental conditions, including the composition of the bed and the banks. The river flows in
meandering pattern. Particularly at the diversion site, the river has gentle slope. But as we move some
meters downstream of the diversion site the river take steep slope. The river has narrower section in
upstream direction whereas to downstream side the river section becomes somewhat wider.
Right Bank
This abutment forms nearly small ridge. It is characterized by moderately to highly weathered, jointed
and fractured rock. It is covered by weathered rock with silt clay soil for few centimeter thicknesses on
the top part of this bank. This rock is not extending in the downstream direction instead it is replaced by
red silt clay soil at the river bank but in the upstream side it extends for some meters. At the proposed
weir site the height of this bank is about 1.5m with steeply slope. This rock is good for anchoring the
proposed weir structure and the recommended retaining wall along this side with it.
Left Bank
The left bank of the River geological formation is characterized by consolidated sandstone and
unconsolidated or weathered hard rock. The soil type along this bank is characterized with reddish color
and having fine to intermediate grain size. From visual examination of the pit, there is thin fine silty clay
soil having low plasticity.
The rock type found at this quarry site is basalt, which has dark gray color, fine grained texture, and high
strength. The rock unit shows closely spaced joints that disintegrated and dislodged fragments of the rock
are observed in large quantity. In addition to this intact and jointed (by widely spaced joints) outcrops of
the rock unit and subsurface extensions are found. At the site large extent exposure of the rock is
available..
Fine Aggregates
Aggregates are highly required for headwork concrete structures and the main canal masonry structures
and other structures that can be constructed in the project. The aggregates required for use in concrete
works are coarse and fine aggregates that can be found from natural deposits or artificially by crushing of
suitable rock.
The project stream itself and other nearby ones have been assessed for natural sand deposits with the help
of the local dwellers. The streams do not possess natural sand along their beds at and nearby the site
because since the stream around the command area is steep the sand cannot be deposited at the project
area. The streams are found at higher elevation part of the region that deposition of suspended sediments
of sand to clay sizes is not possible due to their nature, rather coarser sediments or rock exposures
characterize their bed.
Water
Water for construction purposes can be found from the project stream, Kirkirayana River, itself. The
stream is perennial throughout the year that there is some amount of flow along its course. During this
field time the stream base flow was more than 70 l/second.
a. Crest length
Lacey’s regime width, L=4.75∗ √ Q ,=4.75∗ √ 107.26 = 49.19 m.
Actual river section width of the over flow section of the river is = 22m take22m
b. Discharge over the weir section
Design discharge, Q = 107.26 m3/s
Q=CLHe 3 /2
2/3 2/3
Q 107 . 26
He=
CL [ ] [ =
1 .7∗22 ] =2. 02 m
He: specific energy head (over flow depth + approaching velocity head (m))
σ : Specific weight of weir body (2.35 for cyclopean concrete)
He 2 .02
T= = =1 .71 m
Top width, √σ −1 √2 .35−1
He+P 2 .28+ 2. 0
B= = =3 . 43 m
Bottom width, √σ −1 √ 2. 35−1
However this computed value of the dimensions shall be fixed after stability analysis of the structure.
After stability analysis safe we fixed Top width=1.0m, Bottom width=2.6m
U/S and D/S HFL Calculation & Determination
From the stage –discharge curve prepared in hydrology Section the high flood level after construction (i.e.
D/s HFL) corresponding to the design flood is1103.93m a.s.l.
D/s HFL = 1103.93 m amsl ------------------------------------ (a)
U/s HFL = U/s bed level + weir height + Hd ----------------- (b)
Hd is the depth of water over the weir crest. This is calculated by assuming broad crested weir formula.
3
Q=C∗L∗H e 2
Q 32
H e= (
C∗L )
= 2.02m, L is the gross crest length i.e. 13m
The velocity head, ha is computed from the approach velocity as shown below
v
a2
ha =
2g
Where g: acceleration due to gravity = 9.81m/sec 2
Va is Approach velocity determined by
Q
V a=
Lxhd
L is Weir crest length + under sluice length = 21+1 = 22m,
hd is flow depth over the weir and also,
hd =H e−h a
2 2
Q 107 . 26
ha =H e −hd =
( ) (
L∗h d
=
( 22 )∗h d )
(2 g) ( 2∗9 .81 )
By trial and error method, hd is found to be 1.39m
ha = He-hd = 2.02m-1.39m = 0.63m
Velocity head, ha = 0.63m
Afflux
⇒ Afflux = U/s HFL- D/s HFL = 1105.64m a.s.l – 1103.93m a.s.l = 1.71m.
From the flood level analysis, it is seen that the flood overtops the banks of the river upstream of the
structure. This condition is not allowed to take place as it inundates the canal head at the right side and
has negative impact on the structures. On the left side the flood may scour the bank and may change its
route in that direction. So, it is necessary to construct a structure to confine it.
Q 107.26 m 3/s
q= = =4.88 m 2¿ s
l 22 m
q2 4.882
h a= =
2∗g∗y 2 2∗g∗y 12
4.882
2.02=0
2∗g∗y 12
Fo=
∑ ( M +) =175 .12 =4 .56
∑ ( M−) 38 . 41 >1.5 Safe!
ii) Factor of safety against sliding (FS)
U∑ FV 0.75∗119. 6
Fs= Fs= =1.56 >1. 5 , safe .
∑ FH µ=0.75, 57. 62
iii) Check for tension (i.e. whether the resultant lies within the middle third)
The location of the resultant force from the toe is given by
X=
∑ M (+)−∑ M (−) =175 .12−35. 41 =1 .17 m
∑V 119. 6
The eccentricity (e) = B/2‒X, B = 2.6m
Hence, e = /1.3‒1.17/ = 0.13m
2.6
=0.43
The eccentricity (e) should be less than B/6 = 6 , Hence the obtained e = 0.13m <
0.43m.
⇒The resultant lays within the middle third no tension
Conclusion: From stability analysis, the designed weir section is safe
Under sluice
The under sluice is mainly provided here to remove silt deposition as a result of barrier structure/weir.
Hence the sill level of the under sluice is fixed to facilitate this deposited silt to increase the efficiency of
water abstracting to the main canal through the head regulator from the pocket. The sill level of this sluice
is fixed to be 1.4m above from the minimum bed level. Hence the sill level of the under sluice is
1102.25+1.4=1103.65m.a s.l.
Even if the position of the under sluice is on concave side that is on scouring side, there might be boulders
that may come into the pocket of the under sluice due to the barrier structure. Hence in addition to the
supply of water to the intake and the removal of silt, this acts to remove the boulder that comes to wards
it. Considering this, the opening size of the gate is 0.6m*0.7m
The capacity of under sluice is determined considering the following points.
The capacity should be at least five times the canal discharge to ensure proper scouring.
Capacity of passing about 10% to 20% of the maximum flood discharge at high floods.
During construction, it should be able to pass the prevailing (at least base flow) discharge of the
river.
From stated above 6 times of the base flow can be taken to fix the under sluice capacity not to exaggerate
the capacity i.e. 6*70=420 l/s. The dimensions of under sluice are determined by using broad crest
formula for maximum flood condition i.e.
• Outlet size
From the weir discharge formula the outlet size is determined as follows
Q = CLHe3/2
Where; C = Coefficient of discharge = 1.7
L = Length of water way (m)
He = head above sill level (neglecting the velocity head) = 0.50m
Q 0 . 42
L= 3/ 2
= =0. 70 m
CHe 1. 7 x 0 . 503/2
Outlet capacity for dry season irrigation = Duty x command area x correction factor (when necessary)
Retaining Walls
At the two ends of the diversion weir, walls have been provided to safeguard the structure from scour of
banks at the ends and also as a facility to the canal outlet operation and maintenance at the canal outlet
portion. The walls are basically provided to keep the highest flood flow within the weir crest section and
to safeguard areas out of the river bank.
Data available:-
3 3 3
γ m=23 KN /m , γ w =10 KN /m , γ soil =19 . KN /m
W1
Ps
W2
B2
Dimension
H FB HT B1 B2 B
3.40 0.50 1.20 1.70
Stability analysis
Table U/s retaining wall
Horizonta
vertical l force
Type of force load KN KN moment arm m moment
(-) (+)
Wt of 50.40350
back Pav 38.76 1.30 4
fill soil Pah 36.57 1.13 41.446068
weight W1 39.1 0.25 9.775
of the
body W2 46.92 1.13 53.176
sum 124.78 36.57 3.82 41.446068 113.355
Fo 2.73 >1.5 safe
∑ 71.9084
Fs 2.56 >1.5 safe M= 4
0.5762
x 8
e 0.31
e<B/6
B/6 0.34 safe
Dimension
H FB HT B1 B2 B
1.70 0.50 0.70 1.20
Stability analysis
vertical load Horizontal
Type of force KN force KN moment arm m moment
(-) (+)
Wt of
back fill Pav 11.31 0.97 10.93
soil Pah 9.14 0.57 5.18
weight of W1 19.55 0.25 4.89
the body W2 13.69 0.57 7.75
sum 44.54 9.14 2.35 5.18 23.57
Fo 4.55 >1.5 safe
∑
Fs 3.65 >1.5 safe ∑M= 18.39
x 0.41
e 0.19
B/6 0.20 e<B/6 safe
Table 1.10: D/s retaining wall analysis
Note: during construction period anchoring depths can be extended bellow the bed match greater than
the provided value until sound foundation is existed in both upstream and downstream guide walls and for
All the structures going to be constructed.