Professional Documents
Culture Documents
TW19.077 TWF Presentation 24jul19
TW19.077 TWF Presentation 24jul19
BS5975:2019
Overview of Procedures
e &
O n
First Published 1982
i on onEditioned
ec t Second
o a t 1996
S Tw pd
Third Edition 2008
ly o n e u
On ecti s aFourth r Amended 2011
Edition 2019
S re
e du
c
Pro
£340.20
{ £378 full price } 248 pages
2
BS 5975:2019 - Presentation Topics
Introduction & Foreword by Frank
Clause 7 Clients
Clause 8 Designers
Clause 9 Contractors (PC & Managing)
Clause 10 Suppliers/manufacturers
FOREWORD
INTRODUCTION
and
Principal Changes
5
Foreword & Principal Changes
• intended to be used by all organisations but
lacked detail other than for PC
• updated in accordance with CDM Regulations 2015
• As Bragg intended PC’s TWC retains overall
control for all TW on site
• terms and definitions updated
• description of temporary works added
• includes recommendations on partial factors for
TW designers
• safety issue in Section 3 has been advised
6
Foreword & Principal Changes
• Partial revision in 2011 and following items
reviewed and confirmed
– BS 12812 exists in parallel for limit state design
of Falsework
– Design Classes A, B1 & B2 ‐ no advice on Class A
so BS 5975 Section 3 applies
• Little construction work undertaken by PC ‐
need to reflect this and
• CDM states ALL contractors should plan,
manage and monitor their own works and
liaise with others i.e. CO‐ORDINATE
7
Introduction
Additional background
•BS 5975 still based on Bragg (1974) but need
to remember West Gate Bridge (Yarra Bridge)
‐ see ICE Publication TEMPORARY WORKS
Principles of Design and Construction Second
Edition (December 2018)
– Causes of collapse included: client not selecting a
suitably experienced contractor and;
designer not responding to contractor queries on
temporary conditions of the permanent works
8
Written QUESTIONS
• Q1 New BS5975 is 3 x size of previous version; Why?
• A Revision to suit CDM, additional pages for Overview
(TWf requested a Lite version), needed Procedures for
Clients, Designers and Contractors other than PC as
they were not implementing procedures.
• Q1 SMEs struggle with current version and will find this
too complex linked to
• Q4 Why organisation focussed approach?
• A We tried both organisation and function but found
organisation worked best. Also it is back to back with
CDM Regulations. SMEs can find the relevant pages
more easily as they are together under contractors
(other than PC ) and work for SMEs under contract
to the client or the PC.
9
Peter
CLAUSE 5 OVERVIEW & TRAINING
&
CLAUSE 6 PROCEDURAL CONTROL
10
QUESTION TIME
Which of the following is mandatory?
G. Hoarding?
H. Mobile towers?
I. Access scaffold?
J. Crane outrigger foundations?
K. Excavation to repair a 150 dia water main?
L. Barge carrying crane, piling hammer,
generator & sheet piles etc.?
2 of 5
13
BS 5975 “Temporary Works”
“Temporary Works” is not defined.
3 of 5
14
Clause 5.1.1.1 continued
Temporary works includes but is not limited to:-
4 of 5
15
Karnuk Temple, Luxor
Built by Rameses III about 1170 BC
Temporary
works of
earth ramps
REMEMBER
Source: BS 5975:1982 to date !
18
5.2 Training
5.2.1 All those managing TW should have,
as a minimum, an understanding of :-
• the procedures outlined in Section 2 of BS5975
• understand and be able to operate the company
temporary works procedure
Client Managing
Responsible for:
Contractor Subcontractor
Designers comply
Co-operate
Subcontractor
Co-ordinate
Pass Information
22
CDM Coordination between Designers
Principal Permanent
Works
Designer Designer
C
L Responsible for:
I Designers comply TW
Co-operation Supplier
E Co-ordination Designer
N Information
T
Principal Temporary
Contractor Works
Designer
23
The single
CLIENT
contractor on
small project contract
Contractor
Appointed
Temporary
Works
Supervisor
Temp Wks
Temp Wks
Project or Site
Figure 2 a)
24
Several
CLIENT
contractors
client appoints contract
PC
Principal Contractor (PC)
appointed
Temporary
Works Temporary
Supervisor Works
Supervisor
Temp Wks
Temp Wks
Temp Wks
Part of Site or
Main Project or Site another
Figure 2(b) Site
25
Contractor
has several CLIENT
small sites contract
contract
Sub contractor does Principal Contractor’s
NOT have ability to Temporary Works Co-ordinator
manage the TW
Sub- Contractor
appointed
Temporary
Works
Supervisor Temp Wks
27
PC on a large CLIENT
and/or complex site contract
Temporary
Works
Supervisor Temporary
Works
Temp Wks Supervisor
Temp Wks
Temp Wks
Temp Wks
Well defined area X
Well defined area Y
of Project or Site A
Figure 2(e) of Project or Site A
28
BS 5975:2019 Managing Contractors
29
PC appoints
a managing CLIENT
sub contractor
contract
contract
Principal Contractor’s
Temporary Works Co-ordinator
Temp Wks
Figure 3(a)
30
Client appoints
a contractor CLIENT
for work which contract
includes TW
Principal Contractor (PC)
contract
appointed
Principal Contractor’s
Temporary Works Co-ordinator
Client’s Contractor
appointed
Temp Wks
Figure 3(b)
31
QUESTION TIME
32
Implementation Risk Classification of TW
BS5975 Table 1 classes of Implementation Risk for
temporary works with level of risk, permits required
and gives suggested control measures:-
Very low risk, low risk,
medium risk or high risk
**
Identical temporary works N F
may U S E same design
need
O T C O O R Y **
DO N location
but in a different
K C A T E
have G different
** risk!
** C HE C
Classifications
E SI G N seen in company procedures
often * * are
** D WI T H
N R I SK *
** Minor , NNormal
T A T I O and Special *
P E M E
L A, Class T I O N Class C
or
** I M Class
S IF I C A B and
or A S
CL 3, Type 2 and Type 1
Type
**
Note: BS EN 12812 (falsework) uses Class A, B1 & B2
1 of 3
33
PAS 8811 Temporary works – Major infrastructure
client procedures
Code of practice
Published by BSI with
Temporary Works Forum
Introduces:
Type Classification N, S, P
Questions on
37
BS 5975:2019 - Presentation Topics
38
Clause 6 re‐cap
Definition of which organisations should have
a procedure has changed :‐
•6.1.1.1 When a project has, or might be
anticipated to have, the requirement for any
temporary works, the organizations listed in
6.1.1.2 should have and implement a procedure
which outlines how that organization is to
discharge its duties in relation to temporary
works.
•This then identifies clients, designers, contractors (all
including the PC) and manufacturers/suppliers
39
Clients & Designers
• 5.1.1.1 Temporary works can be described as providing an
"engineered solution" that is used to support or protect either an
existing structure or the permanent works during construction, or to
support an item of plant or equipment, or the vertical sides or side‐
slopes of an excavation during construction operations on site or to
provide access. It is used to control stability, strength, deflection,
fatigue, geotechnical effects & hydraulic effects within defined limits.
• Discussion ‐ taking previous discussion on
what temporary works are:
• Which projects would not have any
temporary works?
40
7.0 Clients
• Check that any contractors and any designers
they appoint have the necessary experience in
relation to the temporary works which may be
expected in their contract.
• Cl 7.1.3 client advises directly appointed
contractors that PC to approve their procedure
and has full responsibility for TW on project
through the PC’s DI.
• This is repeated & cross referenced in both
the PC’s and Contractor’s responsibilities.
1 of 3
41
7.0 Clients
Client should :
•ensure PC is co‐ordinating ALL TW on the project
and working in accordance with its procedure.
How this is done depends on the client and project.
•identify assets which may be affected by TW
•identify schemes which require formal approval
•identify hold points
•provide information to allow the PD or PC to
design, construct and remove temporary works
2 of 3
42
7.0 Clients
• Cl 7.1.4 & 5 if client is PD and / or PC
then the client must have procedures
outlined for PD and procedures outlined
for the PC too.
3 of 3
43
8.0 Designers
• References to TWC mean both PC’s TWC
and managing contractor’s TWC
• Although new procedure it is based on
CDM Regulations except the Designers
(including PD) are required to liaise with
TWC. Could be direct with TWD and TWC
copied in if agreed.
• Should respond promptly to queries from
TWC ‐ again a problem with no response
as experienced at Yarra Bridge collapse!
1 of 2
44
8.0 Designers
• Lead Designer (TW) ‐ solution to problem on
NR Bridge GE 19
– Various parts of bridge launch designed by
different organisations
• Signs off the TWD when various parties
design different parts of a TW Scheme
– Reviews all designs and signs off an overall
design certificate.
– May have a Lead Design Checker who signs
off an overall design check certificate.
2 of 2
45
9.0 Contractors
• As for all DI’s, the contractor’s DI should be a member, or
directly responsible to a member of, the main or
supervisory board. See clause 6.1.2.1
• The duties on the PC (was Main Contractor) have remained
the same in relation to its own works BUT additional duties
have been added in relation to the work of other contractors
• The duties on other contractors are as the basic duties on
the PC in relation to managing their temporary works.
i.e. write a procedure, appoint a competent TWC and
co‐ordinate their temporary works
(including with other contractors)
1 of 11
46
9.0 Contractors
• This is where we had difficulties with some not
understanding that subcontractors could manage their own
TW. It has been an option since 2008.
It is NOT done through the subcontractor’s TWS !
• 9.1.8 Where contractors are appointed by the client and/or
PC, the PC's DI should ensure that contractors’ temporary
works procedures are satisfactory. The contractor should
supply evidence of how the procedure has been
implemented on previous contracts and which type of
temporary works the contractor has been responsible for.
• NOTE Attention is drawn to the CDM Regulations 2015
and the HSE Guidance Notes L153 on the Regulations].
• (ALL Contractors to plan, manage & monitor their own works.)
2 of 11
47
9.0 Contractors
Discussion ‐ Which Contractors does this mean?
• ALL ?
• Client appointed ?
• Specialists ‐ RC Frame, Marine, Demolition ?
• Not general sub‐contractors ?
• Cannot generalise ‐ PC’s DI must assess
3 of 11
48
9.0 Contractors
• 9.2.2 includes a requirement that the
PC’s DI should check that contractors
appointed by the PC, the client or a third
party have a satisfactory procedure.
• This clause builds on the clause under
clients which requires them to inform the
contractors that the PC’s DI will check
their temporary works procedures.
4 of 11
49
9.0 Contractors
• PC’s DI in relation to other contractors
– When contractor’s procedure should be provided
– How the procedures should be checked
– What if procedure is inadequate?
– How PC’s TWC should interact with the
contractor’s TWC
– How & when PC’s TWC should verify the design
briefs from the contractor
– How & when PC’s TWC should check the
design certification
5 of 11
50
9.0 Contractors
• Confirm that the contractor’s procedure
is satisfactory ( or otherwise !)
i.e. The contractor is deemed to have the
knowledge, skills, experience and
organizational capability to manage its
own temporary works.
6 of 11
51
9.0 Contractors
• Contractors duty after appointment
• The PC’s DI should be provided with a
copy of the assessment of the competence
of the contractor’s PROPOSED TWC and
confirm acceptance (or otherwise) through
the PC’s TWC.
7 of 11
52
9.0 Contractors
PC’s responsibility for Temporary Works –
(clause introduced following comment from Hinckley Point)
9.3.2.5. Where a particularly technically or logistically complex
project can be split into more than one well‐defined area,
then a PC’s TWC may be appointed for each area. Each
individual PC’s TWC should be responsible for all the temporary
works in the area allocated, irrespective of which organization
carries out the temporary works in the area. Only one PC’s
TWC should be responsible for a specific area. One of these
individuals should be appointed as lead PC's TWC to manage
the interfaces between the areas.
NOTE: On a contract such as a motorway or railway the project could be
split into sections, having a PC’s TWC for each section, provided that the
interface is clearly established. It is extremely rare that a building
project would justify more than one PC’s TWC. 8 of 11
53
9.0 Contractors
9.3.3 covers appointment of TWCs NOT
appointed by the PC
•Role has the same responsibilities as basic
PC’s TWC but note that the PC’s TWC has
additional duties to ensure the contractor’s
TWC is working in a well‐defined area and
doing as the contractor’s procedure requires.
More on this from Peter later
9 of 11
54
9.0 Contractors
Appointment of TWS
•This applies to both PC & other contractors
•The TWS is NOT a sub‐contractor’s TWC
by another name.
•The TWS role NEVER included a requirement
to co‐ordinate temporary works.
•The TWS role is to inspect temporary works
during their (stages of) construction / erection
and only sign a permit to load/unload IF
they are deemed competent to do so.
10 of 11
55
9.0 Contractors
• 9.5.2.1 The client contractor’s roles and
responsibilities are the same as those for the
contractor appointed by the PC and should be in
accordance with 9.5.1.1 to 9.5.1.7.
• 9.5.2.3 The PC’s DI has a responsibility to ensure
the client contractor’s procedures are satisfactory
(see 9.2.4)
• These two clauses indicate that the PC has
responsibility for ALL temporary works on the
project and that the client contractor SHOULD
submit their TW procedure for approval.
11 of 11
56
10.0 Suppliers/Manufacturers
Written by Chief Engineer of a major supplier
10.3 The supplier's procedure should cover:
– a) equipment conforms to the published
technical data;
– b) original design of components, verification and
production of technical information for
individual and assemblies of proprietary items;
continues
1 of 3
57
10.0 Suppliers/Manufacturers
– c) ensuring manufactured and repaired items
conform to original design requirements for
initial and all subsequent production through
application of robust quality control;
• I have experience of a supplier changing fabrication details
but NOT checking how the design was affected!
– d) material handling and transportation;
– e) maintenance and repair of items that are hired
or offered for second‐hand sale; and
– f) equipment substitutions when the original
component is not available.
continues
2 of 3
58
10.0 Suppliers/Manufacturers
–If they carry out design or erection
(construction) of works then they should have
procedures as outlined in clause 8 and
clause 9 respectively.
Suppliers / Manufactures should provide :
• Technical information (data sheets)
• Design data
• Information for safe use of the equipment
• Standard solutions (as appropriate.)
3 of 3
59
Audience QUESTIONS
Questions on
60
Peter
• Clause 11 TWC
• Clause 12 TWS
• Clause 13 Design of Temporary Works
61
Duties of the
Temporary Works
Co-ordinator (TWC)
1975 First recommendation for constructor to
appoint a properly qualified TWC.
1 of 7
continues 63
Existing PC’s Managing
TWC activity TWC TWC
6 of 7
continues 68
NEW WE SURVIVED ! PC’s Managing
TWC duties TWC TWC
11) ensure TWDs and checkers competent
and verified by organisation’s DI
12) ensure PC TWC rectification instructions
carried out and to PC TWC satisfaction
PC’s duties to Other Contractors
13) receive contractor’s DI’s assessment of
capability of TWC & TWS(s)
14) provide relevant TW information
15) define interfaces between PC & others
16) receive briefs; confirm no adverse effect
17) receive relevant TW info, designs, certs..
18) inspect contractor’s TW as necessary
7 of 7
69
QUESTION TIME
A. Can a TWC carry out design
and/or design checking?
70
QUESTION TIME
A. Can a TWC carry out design
Yes
and/or design checking?
71
QUESTION TIME
A. Can a TWC carry out design
Yes
and/or design checking?
72
QUESTION TIME
A. Can a TWC carry out design
Yes
and/or design checking?
73
PAS 8812
Temporary works –
Application of
European Standards
in design - Guide
Published by BSI with
Temporary Works Forum
January 2016
£ 123
64 pages
Source: BSI publications
74
Clause 13.3.9 Partial Safety Factor
75
QUESTION TIME
A. Should you design stable structures ?
and
1 of 4
76
Construction (Design and Management) Regs 2015
Reg. 19 - Stability of Structures
2 of 4 77
Foreseeable Loading !!
3 of 4 78
BS 5975:2019 Design Guidance
13.3.10 For each temporary works design, the designer
should take into account:-
(a) the structural strength and stiffness of the
individual members and their connections to
transmit the applied forces safely including any
p-delta or feedback effects;
(b) the lateral stability of both individual members
and the structure as a whole;
( c) the resistance to overturning or rotational
failure;
(d) positional stability; and
(e) the effects on the permanent works and its
surroundings.
4 of 4 79
BS 5975:2019 Design Check Categories - Table 2
Complex or by another
3 innovative design organisation
80
BS 5975 The Future ?
BS 5975 – 1 : 20xx
Code of practice -
Part
One
Procedural control of
BS 5975:2019 Temporary Works
BS 5975 – 2 : 20xx
Code of practice - Falsework
Part 2-1 General
Two 2-2 Loadings / Actions
2-3 Analysis
2-4 Limit state design
2-5 Permissible stress design
81
Temporary Works
Principles of Design
and Construction
34 Chapters
e nt
ge m e s
Second nEdition
a ua t
M a d
Published 2 December
g ra 2018 !
t e r f or rk s
p o
C ha ding ry w
& r e a or a
f e ty ory m p
S a l s t e
1 pu to £145
t e r c o m e w
a p n
Ch ld be yone
o u a n
sh an d 528 Pages
Source - ICE Publishing
82
The End Final Questions ?
83